donald bruce ppt

Upload: aymen-chekir

Post on 06-Mar-2016

25 views

Category:

Documents


0 download

DESCRIPTION

Deep Soil Mixing

TRANSCRIPT

  • The Deep Mixing Methods Background andHistory of Usage in the U.S.

    Dr. D.A. Bruce

  • Original Classification of Deep Mixing Methods(FHWA 2000)

    Nature of MaterialPlaced

    Mixing/BlendingPrinciple

    Mixing/Blending Location

    U.S. Examplese.g.,

    SSM, SCC, Mectool

    Hayward Baker

    e.g.,DSM, Trevimix

    Schnabel

    e.g.,GeoJet

    e.g.,Lime-Cement

    Columns

    DM Methods

    Fluid Grouts Dry Materials

    Rotary Rotary and Jet Grout

    Shaft Mix End Mix End Mix

    Rotary

    End Mix

  • Conditions Favoring DMM

    Ground is neither very stiff or very dense Ground has no boulders/obstructions Treatment < 120-foot depth Unrestricted overhead clearance Good and constant binder source Large spoil volumes can be tolerated Vibrations are to be avoided Treated soil volumes are large Performance Specifications applicable Treated ground parameters well defined

  • Example of Wet Rotary Shaft System

  • Example of Wet Rotary End System

  • Example of Dry Rotary End System

  • Example of Wet Jet End System

  • Low vibration, moderate noise. Applicable in most soil conditions. In appropriate conditions, good homogeneity and

    continuity can be achieved.

    Conventional (Rotary Vertical Axis) DMM

    Particular Advantages

    Productivities can be high 2,000/3,000 sf/shift. Unit prices are low -

    moderate. Several good, experienced

    contractors in the U.S.

  • Large, heavy equipment. Practical depth 110 feet (vertical). Method sensitive to very dense or stiff soil, organics,

    boulders. Mobilization/demobilization costs high.

    Conventional DMM

    Potential Drawbacks

  • Updated Classification (Bruce, 2010)

  • 3. Category 2 Cut-Offs (Mix in Place)

    DMM (Deep Mixing Methods)

    RotaryVertical

    Axis

    JetAssisted Vertical Axis (Turbojet)

    Trench Cutting and Mixing

    (TRD)

    HorizontalAxis Cuttingand Mixing

    WetEndMix

    WetShaftMix

    DryEndMix

    Conventional

    LowPressure(CSM)

    High Pressure(CT Jet)

  • Conceived in 1993 in Japan. First used in U.S. in 2005. 170 ft. depth capability, 18-34 inches

    wide. Continuous wall created by lateral

    motion of vertical chain saw, installed in a predrilled hole.

    TRD (Trench Re-Mixing and Cutting Deep Wall) Method

  • Blue print

  • Blades vary according to soil condition

    A)Standard bladeB)Rounding blade for hard clayC)Long-nosed blade for boulder

    A B

    C

  • Continuous, homogeneous, joint-free wall in all soil and many rock conditions. Productivities can be extremely high (instantaneous

    production > 400 sft/hour).

    TRD

    Particular Advantages

    High degree of real time QA/QC. Adjustability of cutting teeth. Can operate in low headroom

    (20 ft). Very quite, modest size support

    equipment, clean operation.

  • Sharp alignment changes. Especially hard/massive/abrasive rock. Trapping of post in soilcrete or refusal on

    boulders/rock. Only one (excellent) contractor!

    TRD

    Potential Drawbacks

  • Joint Bauer Maschinen/Bachy Soletanche development in 2003 Combines expertise in hydromill and deep mixing. Rapidly increasing in popularity worldwide (over 30

    units in service). Similar system developed by Trevi (CT Jet). Maximum depth 180 feet, 20-47 inches wide.

    CSM (Cutter Soil Mix) Method

  • The CSM machine is fitted with aset of instruments that convey tothe operator, in real time, all theinformation that is needed tomonitor and control quality of thework.

    CSM Quality Control Systems

    BAUER B-Tronic system

    External pressure sensor

    Instruments that read:

    Verticality on X and Y axes

    Torque on cutting wheels

    Wheel speeds

  • Continuity assured by very strict verticality control. Very homogeneous product. Applicable in all soil

    conditions (peat should be removed). Adjustable teeth.

    CSM

    Particular Advantages

    A j CSM can be mounted on non-specialized carriers. Productivity can be very high. Can accommodate sharp alignment changes. Quiet and vibration free.

  • As for all DMM variants, rock, boulders and organics are challenges.

    Needs considerable headroom. Cost base (as for all DMM variants).

    CSM

    Potential Drawbacks

  • Overview of Deep Mix Methods

  • Historical Background U.S.A.1986 SMW Seiko arrive in U.S.Late 1980s Jackson Lake Dam, WY (Seiko/GeoCon)Late 1980s Start of Environmental Applications (GeoCon)Early 1990s Start of Levee (Cutoffs) and Dam (Seismic)

    Remediations1992-1994 First major Earth Retaining Structure (Boston, MA)1995 Visit by U.S. engineers to Japan1996 First Lime-Cement Column project

    (New York)1997-1998 Largest wet DMM project to that time (Boston,

    MA)1997-2000 FHWA State of Practice Studies2001-2005 National Deep Mixing Research Program

    (States Funded)

  • Historical Background U.S.A. (continued)2000-2003 Desk, Bench and Field Tests, New Orleans2003 International Conference in New Orleans2005 Katrina and Rita2006 Task Force Guardian2006-2007 Deep Mixing at Tuttle Creek Dam, KS2007-Present National Deep Mixing Project Revised2008-Present Cutoff Walls at Lake Okeechobee2010-2011 LPV 1112012 International Conference in New Orleans

  • PHASE 1: DESK, BENCH AND FIELD TESTS 2000-2003 - Inner Harbor Navigation Channel (IHNC)

    PHASE 2: TASK FORCE GUARDIAN (2006) AND LATER WORKS TO 2010

    PHASE 3: LPV 111 (2010-2011)

    Brief History of Deep Mixing in New Orleans

  • Phase 1 Original Field Test

  • Extraction of Column

  • Loading of Test Area

  • Katrina and Rita, 2005

  • Mission Statement (paraphrased):

    To restore the flood protection to pre-Katrina levels by 1 June 2006.

    Approximately 169 miles of levees and floodwalls repair work.

    Task Force Guardian (2006)

  • Independent Technical Review

  • Phase 2 Work (Task Force Guardian 2010)

  • Orleans Avenue Interim Closure Structure

    17th Street Canal Interim Closure Structure

    Homeplace Levee Enlargement

    IHNC Deep Mixed Cutoff Wall

    Four TFG Projects (2006)

  • 17th Street and Orleans Avenue Canal Closure Structures

  • Orleans Avenue

    Flood SideProtected Side

  • Phase 2: Wet Mixing at Orleans Avenue

  • Phase 2: Dry Mixing at 17th Street Canal and Homeplace Levee

  • Phase 2: Dry Mixing at 17th Street Canal

  • Phase 2: Homeplace Levee Enlargement Plaquemines Parish

  • P24 Column LayoutPlan View

  • Homeplace Levee Enlargement (P24) (2006)

  • Inner Harbor Navigation CanalSeepage Cutoff Walls

  • During hurricane Katrina a substantial percentage of New Orleans East Levee System failed, including LPV111.

    The Hurricane Protection Office of the US Army Corps of Engineers attributed the failure of the system to overtopping, erosion, and subsequent breaching of levees along the GIWW.

    Phase 3: LPV 111

  • LPV 111 - Project Overview

    In order to address the technical and logistical demands of the project, the deep mixing method was designed as the most suitable technology utilizing Early Contractor Involvement.

  • In order to prevent settlement of the additional overburden and resist potential lateral forces originated by storm surges, the ground improvement was designed to cover 30% of the new levee footprint to create rows of parallel buttresses, approximately 15 feet apart, perpendicular to the levee axis. In between adjacent buttresses, an individual element was installed to avoid differential settlement.

    Large diameter single and double deep mixed columns were incorporated in the design.

    The larger columns allowed the reduction of the total number of elements to be installed with obvious advantages for the highly demanding schedule.

    Design

  • Design

  • Technology

    Over 60% of the ground improvement was accomplished with the Trevi Turbo Mix technology, single and double axis.

    The TTM method is a recent development of the deep mixing technology. It combines the injection of cement slurry at high velocity into the ground with mechanical mixing of the rotating blades.

    The additional energy provided by the grout jets greatly improves the quality of the mixing of the soil with the grout and reduces the time required for the installation of the soil-mix columns.

  • Pre-Construction

    The contract required that pre-construction activities be performed during the design phase to determine the most appropriate construction parameters and technical solutions:

    Soil Investigation (2 phases) Desk Study Bench Scale mixing program (4 phases) Field Validation Test program (5+ phases)

    Due to schedule constraints, only the first stages of the pre-construction activities were accomplished before the beginning of the actual production. The remaining stages were performed as work areas became available .

  • Production

    PRODUCTION START DATE 1/14/2010PRODUCTION COMPLETION DATE 3/18/2011

    TOTAL CALENDAR DAYS N 439.00 TOTAL MONTHS N 14.43

    TOTAL SHIFTS WORKED (as of 3/18/2011) N 3,309 TOTAL MANHOURS (as of 3/18/2011) N 502,817

    TOTAL DMM ELEMENT INSTALLED N 18,028 TOTAL VOLUME TREATED CY 1,681,579

    TOTAL CEMENT USED SHTON 457,693 TOTAL TRUCK-LOADS (approx.) N 17,500

    TOTAL WATER USED GAL 136,832,094TOTAL CORING N 506

    TOTAL UCS TESTS N 5,082 OVERALL AVERAGE UCS (required = 100 psi) PSI 292

    TOTAL FAILING UCS TESTS (

  • Construction

    2x12 hrs/shifts, 5.5 days/week 6 dual auger + 2 single auger

    rigs 8 active batch plants producing F\KURIJURXW

    approximately 460,000 tons of cement used o 17,500 trucks

    3 coring rigs over 500,000 man-hours in 14

    months of production

    LPV111 CHALLENGES:schedule logistics design soil characteristics size of the job

  • Phase 3: LPV 111

  • Dr. D.A. BruceDFI Deep Mixing SeminarApril 7-8, 2011

  • Conference Papers on LPV 111(New Orleans, February 2012)

    Overview of Deep Mixing at Levee LPV 111, New Orleans, LA (Cali et al. (2012)

    Deep Mixing Design for Raising Levee Section, LPV 111, New Orleans, LA (Cooling et al. 2012)

    Construction Operations and Quality Control of Deep Mixing at Levee LPV 111 in New Orleans (Schmutzler et al. 2012)

    Bench-Scale testing and Quality Control/Quality Assurance Testing for Deep Mixing at Levee LPV 111 (Bertero et al. 2012)

    Use of Deep Mixing Return Material for Levee Construction at LPV 111 (Druss et al. 2012).

  • Enjoy the Seminar!