document of the world bankdocuments.worldbank.org/curated/en/...fyp five-year plan gef global...

82
Document of The World Bank Report No: ICR00003806 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-78490) ON A LOAN IN THE AMOUNT OF US$50 MILLION TO THE PEOPLE’S REPUBLIC OF CHINA FOR A NINGBO NEW COUNTRYSIDE DEVELOPMENT PROJECT October 20, 2016 Social, Urban, Rural and Resilience Global Practice China and Mongolia Country Management Unit East Asia and Pacific Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 25-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

Document of

The World Bank

Report No: ICR00003806

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IBRD-78490)

ON A

LOAN

IN THE AMOUNT OF US$50 MILLION

TO THE

PEOPLE’S REPUBLIC OF CHINA

FOR A

NINGBO NEW COUNTRYSIDE DEVELOPMENT PROJECT

October 20, 2016

Social, Urban, Rural and Resilience Global Practice

China and Mongolia Country Management Unit

East Asia and Pacific Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

CURRENCY EQUIVALENTS

Appraisal Completion

Effective January 25, 2010 Effective December 1, 2015

RMB1.00 = US$ 0.146 RMB1.00=US$0.154

US$ 1.00 = RMB6.8 US$1.00=RMB6.5

FISCAL YEAR

January 1 – December 31

ABBREVIATIONS AND ACRONYMS

AM Aide Memoire

BCR Benefit Cost Ratio

BOD2 Biochemical Oxygen Demand

CAST Cyclic Activated Sludge Technology

CEA Consolidated Environment Assessment

CODCR Chemical Oxygen Demand

CPH Community Participation Handbook

CPS Country Partnership Strategy

CPC Communist Party of China

DI Design Institute

DRC Development & Reform Commission

EA Environmental Assessment

EIA Environmental Impact Assessment

EIRR Economic Internal Rate of Return

EMP Environmental Management Plan

EMF Environmental Management Framework

EPB Environmental Protection Bureau

ESMAP Energy Sector Management Assistance Programme

FCIC Fenghua City Investment Company

FM Financial Management

FYP Five-Year Plan

GEF Global Environment Facility

HH Households

IBRD International Bank for Reconstruction and Development

ICR Implementation and Completion Report

IFRs Interim Financial Reports

IOI Intermediate Outcome Indicators

KPIs Key Performance Indicators

M&E Monitoring and Evaluation

MEP M&E Program

Page 3: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

MOF Ministry of Finance

MTR Mid-Term Review

Mu Chinese unit of land area (1mu = 666m2 or 0.0666 hectare)

NCD New Countryside Development

NCB National Competitive Bidding

NH3N Ammoniacal Nitrogen

NMG Ningbo Municipal Government

NMPMO Ningbo Municipal Project Management Office

NMFB Ningbo Municipal Finance Bureau

NNCD Ningbo New Countryside Development

NPV Net Present Value

NRCR National Research Center for Resettlement

NRWTPMO Ningbo Rural Wastewater Treatment Project Management Office

O&M Operations & Maintenance

OP Operations Policy

PAD Project Appraisal Document

PCN Project Concept Note

PDO Project Development Objective

PIU Project Implementing Unit

PLG Project Leading Group

PMO Project Management Office

QAG Quality Assurance Group

QEA Quality at Entry

QSA Quality of Supervision

RAO Rural Affairs Office

RAP Resettlement Action Plan

RMB Renminbi = Yuan (Chinese currency)

RPF Resettlement Policy Framework

SBR Sequencing Batch Reactor

SS Suspended Solids

TA Technical Assistance

TP Total Phosphorus

TTL Task Team Leader

WWTP Wastewater Treatment Plant

Senior Global Practice Director: Ede Jorge Ijjasz-Vasquez

Country Director: Bert Hofman

Practice Manager: Abhas K. Jha

Project Team Leader: Ximing Zhang

ICR Team Leader: Ximing Zhang

Page 4: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

PEOPLE’S REPUBLIC OF CHINA

Ningbo New Countryside Development

CONTENTS

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

1. Project Context, Development Objectives and Design ............................................... 1

2. Key Factors Affecting Implementation and Outcomes .............................................. 5

3. Assessment of Outcomes .......................................................................................... 14

4. Assessment of Risk to Development Outcome ......................................................... 22

5. Assessment of Bank and Borrower Performance ..................................................... 23

6. Lessons Learned ....................................................................................................... 27

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 28

Annex 1. Project Costs and Financing .......................................................................... 29

Annex 2. Outputs by Component ................................................................................. 30

Annex 3. Economic and Financial Analysis ................................................................. 47

Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 56

Annex 5. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 57

Annex 6. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 64

Annex 7. Social Safeguards .......................................................................................... 67

Annex 8. List of Supporting Documents ...................................................................... 68

Annex 9. Map…………………………………………………………………………69

Page 5: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

A. Basic Information

Country: China Project Name:

Ningbo New

Countryside

Development Project

Project ID: P106956 L/C/TF Number(s): IBRD-78490

ICR Date: 07/15/2016 ICR Type: Core ICR

Lending Instrument: SIL Borrower: PEOPLES REPUBLIC

OF CHINA

Original Total

Commitment: USD 50.00M Disbursed Amount: USD 50.00M

Revised Amount: USD 50.00M

Environmental Category: B

Implementing Agencies:

Ningbo Municipality Development and Reform Committee

Cofinanciers and Other External Partners: NA

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 12/18/2008 Effectiveness: 07/16/2010 NA

Appraisal: 08/17/2009 Restructuring(s): NA NA

Approval: 02/25/2010 Mid-term Review: NA NA

Closing: 03/31/2016 03/31/2016

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Satisfactory

Risk to Development Outcome: Moderate

Bank Performance: Satisfactory

Borrower Performance: Satisfactory

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Satisfactory Government: Satisfactory

Quality of Supervision: Satisfactory Implementing

Agency/Agencies: Satisfactory

Overall Bank

Performance: Satisfactory

Overall Borrower

Performance: Satisfactory

Page 6: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem

Project at any time

(Yes/No):

No Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): Yes

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status: Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

General water, sanitation and flood protection sector 56 56

Public administration- Water, sanitation and flood

protection 1 1

Rural and Inter-Urban Roads 41 41

Sub-National Government 2 2

Theme Code (as % of total Bank financing)

City-wide Infrastructure and Service Delivery 52 52

Municipal governance and institution building 1 1

Other public sector governance 1 1

Rural services and infrastructure 40 40

Water resource management 6 6

E. Bank Staff

Positions At ICR At Approval

Vice President: Victoria Kwakwa James W. Adams

Country Director: Bert Hofman Hsiao-Yun Elaine Sun

Practice

Manager/Manager: Abhas K. Jha Ede Jorge Ijjasz-Vasquez

Project Team Leader: Ximing Zhang Shenhua Wang

ICR Team Leader: Ximing Zhang -

ICR Primary Author: Sarah Xinyuan Lin -

Page 7: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document) The project development objective is to improve rural wastewater management in selected

villages and enhance infrastructure and township management in a small town, in support

of the New Countryside Development (NCD) Program in Ningbo Municipality.

Revised Project Development Objectives (as approved by original approving authority)

NA

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Number of households with appropriate rural wastewater management services

in project area (Number, Custom)

Value

quantitative or

Qualitative)

0.00 41000.00 NA 45500.00

Date achieved 12/31/2009 03/31/2016 NA 03/31/2016

Comments

(incl. %

achievement)

Achieved. At loan closing, the number of households with project-funded rural

wastewater management services had exceeded the target figure by

approximately 11%.

Indicator 2 : Fenghua # Chunhu traffic using new access road (car equivalent) (Number,

Custom)

Value

quantitative or

Qualitative)

0.00 13000.00 NA 13,933.00

Date achieved 12/31/2009 03/31/2016 NA 03/31/2016

Comments

(incl. %

achievement)

Achieved. The Chunhu-Fenghua access road (Jinhai Road) opened to traffic six

months ahead of schedule on February 7, 2013. The target of 13,000 car

equivalent units was exceeded by approximately 7%.

Indicator 3 : Chunhu population served from a reliable and higher-quality water supply

(Number, Custom)

Value

quantitative or

Qualitative)

0.00 76000.00 NA 76500.00

Date achieved 12/31/2009 03/31/2016 NA 03/31/2016

Comments

(incl. %

achievement)

Achieved. Water meeting national quality standards is now available 24 hours

daily to about 76,500 people, slightly over the target value.

Indicator 4 : Wastewater treatment rate in Chunhu Town (Percentage, Custom)

Value

quantitative or 0.00 70.00 NA 84.00

Page 8: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

Qualitative)

Date achieved 12/31/2009 03/31/2016 NA 03/31/2016

Comments

(incl. %

achievement)

Achieved. The wastewater treatment rate in Chunhu Town exceeded the target

amount, with 84% of wastewater treated compared to the 70% target.

Indicator 5 : Adoption of energy efficiency guidelines by NMG (Text, Custom)

Value

quantitative or

Qualitative)

0.00 Completed NA Completed

Date achieved 12/31/2009 03/31/2016 NA 01/13/2015

Comments

(incl. %

achievement)

Achieved. Energy efficiency and construction guidelines for rural housing

projects were developed and implemented in Silian and Xixie Villages in

Chunhu. The Chunhu Middle School had an assessment plan and guidelines

drawn up for developing a green campus, and has implemented

recommendations that were feasible within budget constraints.

Indicator 6 : Proposal for Ningbo Countryside Development Plan for upcoming 12th Five

Year Plan (2011-2015) and Chunhu Town planning completed (Text, Custom)

Value

quantitative or

Qualitative)

0.00 Completed NA Completed

Date achieved 12/31/2009 03/31/2016 NA 09/26/2015

Comments

(incl. %

achievement)

Achieved. Through a series of workshops and trainings, consultants worked with

staff from the Chunhu Town government, Fenghua DRC, Fenghua Planning

Bureau and Fenghua planning institutions to assess current plans and formulate

the NCD strategy for the 12th Five-Year Plan, as well as the Chunhu Town

Master Plan

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Number of villages with completed project-financed wastewater treatment

infrastructure (Number, Custom)

Value

(quantitative

or Qualitative)

0.00 150.00 NA 144.00

Date achieved 12/31/2009 03/31/2016 NA 03/31/2016

Comments

(incl. %

achievement)

Partially achieved. The actual achievement is 96% of the target, but the number

of HH with improved wastewater was exceeded, as shown in PDO Indicator 1

above.

Indicator 2 : Implementation progress of the access road (%) (Percentage, Custom)

Value

(quantitative

or Qualitative)

0.00 100.00 NA 100.00

Date achieved 12/31/2009 03/31/2016 NA 01/25/2013

Page 9: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

Comments

(incl. %

achievement)

Construction began on March 31, 2011 and was completed half a year earlier on

January 25, 2013. The road was opened to traffic on February 7, 2013.

Indicator 3 : Length of Water Main built (km) (Kilometers, Custom)

Value

(quantitative

or Qualitative)

0.00 15.00 NA 15.00

Date achieved 12/31/2009 03/31/2016 NA 03/16/2015

Comments

(incl. %

achievement)

Construction of water supply mains began on July 20, 2012 and was completed

on March 16, 2015.

Indicator 4 : Length of newly built and rehabilitated water distribution network (km)

(Kilometers, Custom)

Value

(quantitative

or Qualitative)

0.00 13.00 NA 14.50

Date achieved 12/31/2009 03/31/2016 NA 03/25/2016

Comments

(incl. %

achievement)

Construction and rehabilitation of the water distribution network began on

October 13, 2014 and was completed on March 25, 2016.

Indicator 5 : Length of sewage main built (Kilometers, Custom)

Value

(quantitative

or Qualitative)

0.00 10.00 NA 10.00

Date achieved 12/31/2009 03/31/2016 NA 12/31/2015

Comments

(incl. %

achievement)

Construction of the Chunhu Town Sewage Network began on April 15, 2011 and

was completed on August 28, 2013.

Indicator 6 : Completion of the wastewater treatment plant (Percentage, Custom)

Value

(quantitative

or Qualitative)

0.00 100.00 NA 100.00

Date achieved 12/31/2009 03/31/2016 NA 11/30/2011

Comments

(incl. %

achievement)

Construction of the Chunhu WWTP, with a treatment capacity of 10,000 m3/day,

began on November 8, 2010 and was completed ahead of schedule on November

30, 2011.

Indicator 7 : People provided with access to "improved sanitation facilities" under the proj.

(Number, Core)

Value

(quantitative

or Qualitative)

0.00 164000.00 NA 166000.00

Date achieved 12/31/2009 03/31/2016 NA 03/31/2016

Comments

(incl. %

achievement)

Achieved, with 2000 more people provided access than targeted.

Indicator 8 : People provided with access to "improved sanitation facilities" - urban (Number,

Core Breakdown)

Value 0.00 0.00 NA 0.00

Page 10: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

(quantitative

or Qualitative)

Date achieved 12/31/2009 03/31/2016 NA 12/31/2015

Comments

(incl. %

achievement)

NA

Indicator 9 : People provided with access to "improved sanitation facilities" - rural (Number,

Core Breakdown)

Value

(quantitative

or Qualitative)

0.00 164000.00 NA 166000.00

Date achieved 12/31/2009 03/31/2016 NA 03/31/2016

Comments

(incl. %

achievement)

Achieved.

Indicator 10 : Direct project beneficiaries (Number, Core)

Value

(quantitative

or Qualitative)

0.00 292000.00 295000.00

Date achieved 12/31/2009 03/31/2016 12/31/2015

Comments

(incl. %

achievement)

Achieved.

Indicator 11 : Female beneficiaries (Percentage, Core Supplement)

Value

(quantitative

or Qualitative)

0.00 50.00 50.00

Date achieved 12/31/2009 03/31/2016 12/31/2015

Comments

(incl. %

achievement)

Achieved.

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 03/03/2011 Satisfactory Satisfactory 1.50

2 04/10/2012 Moderately Satisfactory Moderately Satisfactory 15.53

3 03/17/2013 Moderately

Unsatisfactory

Moderately

Unsatisfactory 28.73

4 10/26/2013 Moderately Satisfactory Moderately Satisfactory 30.73

5 04/12/2014 Moderately Satisfactory Moderately Satisfactory 36.13

6 07/12/2014 Moderately Satisfactory Moderately Satisfactory 36.81

7 12/06/2014 Satisfactory Moderately Satisfactory 39.17

8 06/21/2015 Satisfactory Satisfactory 44.05

9 12/01/2015 Satisfactory Satisfactory 47.82

Page 11: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

H. Restructuring (if any)

Not Applicable

I. Disbursement Profile

Page 12: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

Country and Sector Background

1. At appraisal in 2009, approximately 55% of China’s total population lived in rural

areas. Despite significant economic development following economic reforms introduced

in 1978, the countryside continued to lag behind urban areas. Rural areas were

characterized by underdeveloped basic infrastructure and generally poor standards of living,

and the rural population earned less than one-third the income of their urban counterparts.

Some 50% of administrative villages had no access to tap water, and 60% of the rural

population had no access to sanitary toilets. The institutional and regulatory framework

for rural infrastructure was also lacking. These factors strained the rural environment,

particularly the lack of wastewater treatment that adversely affected the quality of drinking

water sources and the population’s health.

2. To tackle the growing urban-rural disparity, China’s New Countryside

Development (NCD) program was developed in 2003, based on the principle that

industrialized, developed urban areas should be responsible for committing resources to

the development of the countryside. The NCD program targeted several aspects of growth,

including balancing the social and economic development of cities and the countryside,

promoting modern agriculture, promoting sustainable increases in rural incomes and

improving the basic infrastructure in villages and raising the standards of living. The

program also emphasized town development as a strategy for creating local engines of

growth and overall rural development. A well-planned, well-developed town was seen as

being able to demonstrate a model of efficient, ecologically friendly, sustainable growth.

3. China’s 11th Five Year Plan (2006 to 2010) further established the NCD program

as one of the country’s key development strategies, and both central and local governments

subsequently emphasized countryside development as a priority area. When the Ningbo

New Countryside Development Project (NNCDP) was conceptualized in 2008, the central

government was allocating over US$44 billion of its annual budget to support new

countryside development activities. However, despite the considerable emphasis placed on

it, the program was still in its infancy and lacked well-defined implementation principles

and experience.

4. The NNCDP was designed to fit into the overall NCD plan. Ningbo Municipality,

a major city in the southeastern coastal zone, recognized the importance of implementing

the NCD program in order to support more sustainable development in its hinterlands. As

a key commercial center with extensive international trade links, Ningbo had experienced

rapid economic growth, but its rural areas lagged behind. Agricultural output accounted

for only 5.7% of GDP, and rural residents had only 45% of the average annual disposable

income of urban dwellers.

Page 13: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

2

5. The Ningbo Municipal Government (NMG) identified three key aspects of the

NCD that required focus. Firstly, as rural areas were characterized by a lack of wastewater

collection and treatment, as well as poor sanitation, the potential adverse impact on rural

and urban water sources necessitated an effective system of rural wastewater management.

Protection of drinking water sources was a high priority for the Municipality. Secondly,

small towns had inadequate basic infrastructure and lacked financial resources and

management capacity to improve it. Thirdly, local institutional capacity to implement the

NCD program was weak. These three areas subsequently became the main focus of

NNCDP.

Rationale for Bank assistance

6. The Bank had worked successfully with NMG on several projects, including ones

focused on water and environmental issues, such as the Ningbo Water and Environment

Management Project (Ln. 4770). NNCDP provided the Bank with an opportunity to

partner with Ningbo again to work on a new urban/rural integration initiative that would

assist the Municipality to reduce disparities in growth and living standards between its

urban and rural areas. The Bank could draw on its international experience in effective

rural wastewater projects, basic urban infrastructure and small town management to

support implementation of the national NCD program, not only in Ningbo but potentially

in other similar parts of China.

Higher level objectives to which the project contributes

7. With its focus on balancing urban-rural development, improving rural

infrastructure and improving institutional capacity to support sustainable development, the

NNCDP was consistent with the “Reducing Poverty, Inequality and Social Exclusion”

pillar of the Bank’s 2006-2010 Country Partnership Strategy (CPS) for China. The project

was also consistent with China’s 11th Five-Year Plan (2006-2010), particularly the high

priority placed by the central government on reducing urban-rural disparities in growth and

development.

1.2 Original Project Development Objectives (PDO) and Key Indicators (KPI)

8. The original PDO, as stated in the Project Appraisal Document (PAD), was “to

improve rural wastewater management in selected villages and enhance infrastructure and

township management in a small town, in support of the NCD Program in Ningbo

Municipality.” The PDO in the Loan Agreement had slight differences in phrasing – “to

support Ningbo Municipality in the implementation of its New Countryside Development

Program by improving rural wastewater management in selected villages and enhancing

infrastructure and township management in small towns.”

9. KPI were as follows:

(a) The number of households with appropriate rural wastewater management

services in operation;

(b) Fenghua-Chunhu traffic using new access road;

Page 14: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

3

(c) The Chunhu population served from a reliable and higher-quality water supply;

(d) The wastewater treatment rate in Chunhu Town;

(e) NMG adoption of energy efficiency guidelines for rural housing construction;

and

(f) Proposal for NCD plan for upcoming 12th Five Year Plan (2011-2015) and

Chunhu Town planning completed.

1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and

reasons/justification (N.A.)

1.4 Main Beneficiaries

10. The project benefited several groups. First, 45,500 households in 144 villages

would benefit from the provision of wastewater management services in rural Ningbo.

Second, residents of Chunhu Town (76,500 at project completion) would benefit from the

new Chunhu Access Road, which would provide a faster, more direct connection to

Fenghua City as compared to two existing bypass roads. Around Fenghua city, the towns

of Chunhu, Song’ao and Qiucun, as well as the Hongsheng Haitang Development Zone,

with a total 2015 population of 121,300 would benefit from the Fenghua Coastal Water

Supply, Phase 1. Finally, Chunhu Town residents would additionally benefit from new

wastewater management services.

11. Other beneficiaries included officials and villagers who received capacity-building

and implementation support for both the rural wastewater management component and the

development of infrastructure in Chunhu Town. These included staff of the Project

Management Office (PMO) and Project Implementation Units (PIUs), including the

Fenghua City Investment Company (FCIC), the designated PIU for all infrastructure

components except rural wastewater facilities. Village-level training was also undertaken

to raise awareness of the rural wastewater infrastructure component and equip villagers

with decision-making abilities as part of the participatory approach. Selected villagers also

underwent training to carry out routine maintenance upon completion of the infrastructure.

Additionally, under the Technical Assistance (TA) component, beneficiaries included

government officials and local Design Institutes (DIs) who received training and capacity-

building as part of the e-government, energy efficiency and master planning sub-

components.

1.5 Original Components

12. Component 1. Rural Wastewater Management (US$47.96 million, IBRD

US$19.42 million): About 150 rural villages in six counties, cities, districts in Ningbo

Municipality, would receive appropriate, sustainable wastewater treatment technologies.

Villages would be targeted and prioritized based on their location near water surface

protection areas, their ability and willingness to pay for wastewater services, and their

overall poverty levels. A program-based participatory approach would be used to identify

and select villages where at least 80% of the villagers would agree to the project’s

principles, particularly concerning operation and maintenance (O&M) of the systems once

installed.

Page 15: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

4

13. Component 2. Chunhu Town Infrastructure Development (US$78.49 million,

IBRD US$28.67 million):

(a) Chunhu access road, for construction of a four lane, Class I road between

Chunhu Town and Fenghua City with a length of 6.2km, including a tunnel of

3.26km, to meet the needs for improved connectivity under the NCD program;

(b) Fenghua coastal water supply, including (i) construction of a 15.8km long

transmission pipeline from the Qiujiushan Water Supply Works to Chunhu

Town and Hongsheng Haitang; and (ii) renovation and expansion of the Chunhu

Town water distribution network, comprising 12.9km of distribution pipelines;

(c) Chunhu Town wastewater management, including (i) a wastewater collection

network 19km in length; and (ii) a wastewater treatment plant (WWTP) with a

capacity of 10,000m3 per day.

14. Component 3. Capacity Building and Implementation Support (US$1.96 million,

IBRD US$1.96 million):

(a) Capacity building and implementation support for rural wastewater

management, including: (i) technical assistance (TA) for project management

and implementation support to PMOs in the Ningbo Municipality Rural Affairs

Office (RAO) and each project County/District; (ii) village-level education and

awareness raising; (iii) training and study tours (domestic and foreign); and (iv)

miscellaneous equipment.

(b) Chunhu Township management enhancement, capacity building and energy-

efficiency demonstration, including TA for: (i) business promotion activities –

business promotion strategy, web page and brochure development, skills

training and marketing; (ii) town governance enhancement, including e-

government system, improvement of government reporting and information in

disclosure procedures, support for activities promoting public awareness and

participation in planning and decision-making, and enhancement of official

performance evaluation; and (iii) promotion of energy-efficient township,

supported by ESMAP (US$250,000), consisting of the development of energy

efficient building designs and renovation guidelines, a demonstration rural

collective housing project, as well as development of sustainable energy action

guidance and pilots.

(c) Support for preparation of the 12th Five-Year Plan on NCD in Fenghua City,

including (i) specialist support to Fenghua DRC to study and draft the 12th Five-

Year Plan (2011-2015) for NCD of Fenghua City, to prioritize various

institutional strengthening and investment activities, and to guide Fenghua

City’s NCD in 2011-2015; (ii) Chunhu Town NCD Strategy and Township

Master Plan; (iii) village level NCD planning – spatial and sectoral development

plans and detailed design of two selected villages in Chunhu Town.

1.6 Revised Components

15. There were no formal revisions made to the components over the project period.

1.7 Other significant changes

Page 16: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

5

16. No significant changes were made over the project period.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

Soundness of Background Analysis

17. The Bank’s background analysis demonstrated an adequate understanding of the

rural development challenges that Ningbo faced, specifically the need for basic rural

infrastructure in order to sustainably develop rural areas and, in the case of rural wastewater

treatment, to protect drinking water sources. Sound consideration of key government

strategies, as well as NMG’s commitment to the NCD program, benefited project

preparation and design. The ongoing relationship with the Bank in implementing projects

in similar sectors, such as the Zhejiang Urban Environment Project (Ln 4724-CHA) and

the Ningbo Water and Environment Project, ensured that the Bank was familiar with the

local context and could continue to build on its strong relationship with NMG.

18. Chunhu town was selected based on the town government’s own development of,

and commitment to, a detailed NCD plan. Given the proximity of Chunhu to the

Hongsheng Haitang Development Zone, it was also anticipated that the growth of the

economic zone would in future increase demand for Chunhu as a place to live, therefore

necessitating adequate infrastructure development, including wastewater treatment, a

reliable water supply and road connectivity to the nearby city of Fenghua and its regional

railway station. There thus appeared to be a strong rationale for selecting Chunhu as a

demonstration NCD site.

19. The Bank’s experience and lessons learned from rural infrastructure projects in

China and other countries influenced design in three ways. Firstly, previous experience

demonstrated that beneficiary participation during planning and implementation was

essential to ensuring sustainability of community-level infrastructure. Secondly, rural

wastewater management systems had to be designed specifically to suit the rural context,

i.e. to function successfully at lower cost, while being suitable for both individual homes

and communities as a whole, at times over a wide geographical area. Thirdly, infrastructure

designs need to be based on realistic demand projections to avoid over-design, wasting

resources and burdening users with higher-than-necessary charges and tariffs.

Assessment of Project Design

20. The design of NNCDP was generally sound. The PDO had three parts, with

reasonably clear linkages between the project components and the results framework. (See

Sections 2.3 and 3.1 below.) The results framework was straight-forward, with well-

established roles and responsibilities for collecting data for reporting, but with weaknesses

in monitoring the outcomes of the TAs linked to enhancing small town management.

Page 17: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

6

21. The project duration and budget were appropriate to carry out the participatory

aspects, infrastructure works and TA. The institutional structure for implementation

involved entities at several levels, from the Project Leading Group (PLG) chaired by NMG,

to the main PMO, sub-PMOs and various PIUs. This multi-tiered structure was necessary

given the various components involved, as well as the dispersed nature of villages in the

rural wastewater component.

22. The rural wastewater component was somewhat complex given its wide

geographical coverage (spanning across five districts/counties with a total area of 6,202 sq.

km) and the adoption of a community participation approach, which was novel in this

sector in China. A comprehensive Framework for Implementation of the Rural Wastewater

Management Component was developed to guide implementation. The use of a

programmatic approach, with works divided into batches, was wise as it allowed

implementation guidelines to be refined incrementally based on lessons learned.

23. Villages were categorized and prioritized as follows: (a) those within water surface

protection areas, often in remote, undeveloped and mountainous areas; (b) relatively

wealthy villages outside of water protection areas, often on plains, close to population

centers, with better ability and willingness to pay for wastewater services; and (c) relatively

poor villages outside of water protection areas. This categorization of villages also

facilitated the setting of wastewater tariffs upon completion of the rural wastewater

infrastructure, with government support calibrated according to the socio-economic

conditions of the different villages.

24. The Chunhu Town infrastructure component focused on developing basic

infrastructure in road transportation, water supply and wastewater. Investments in these

three sub-components were clearly linked to the second objective of “enhancing

infrastructure in small towns”. The access road between Chunhu Town and Fenghua City

was proposed to improve connectivity between the two, based on a steadily increasing

average daily traffic volume in preceding years, and in anticipation of further growth in

Chunhu Town. For the Fenghua coastal water supply works, the demand for water in the

long-term could not be assessed with certainty, so the investment supported only a first

phase; however, the transmission mains were designed such that they could be extended as

demand warranted in the future.

25. The project included two financial covenants, one each for the Fenghua coastal

water supply and Chunhu wastewater treatment sub-components, stipulating that tariffs for

water and wastewater treatment should be established in order to achieve O&M cost

coverage/ full cost recovery within specific timeframes. Given the difficulties of

implementing such tariffs in China, and the effectiveness of such covenants in other Bank

projects, their inclusion as part of project design warranted deeper consideration.

26. The capacity building and implementation support component consisted of

three separate sub-components. First, capacity-building for the rural wastewater

component was integral to its implementation by building management capacity and

helping the PIUs with the participatory aspect of the component. The second sub-

Page 18: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

7

component consisted of a mix of small individual activities, which were broadly aimed at

improving Chunhu township management. Finally, the third sub-component provided

training and support for the development of an NCD strategy and master planning for

Chunhu Town, which helped build local capacity, and facilitated continued implementation

of NCD principles.

27. The lack of KPIs and IOIs to measure the extent to which township management

had been improved was an issue with project design. The sub-components on business

promotion and introduction of an e-government system, for example, were not monitored

in the RF, making their contribution to the overall PDO difficult to discern. Rather than

having several small sub-components that were not all monitored, NNCDP could have

focused on a more selective number of targeted township management initiatives, with

clear intended outcomes and an appropriate accompanying RF. Additionally, the

component was designed specifically for enhancement of management in Chunhu town,

with no indication of how the activities or results could enhancement management of other

“small towns”, as worded in the PDO.

Adequacy of Government Commitment

28. Commitment by NMG for NNCDP was high, with the project being in line with

the NMG’s own commitment to improving rural standards of living and narrowing the

rural-urban gap. Support from the NMG was also evidenced in the provision of financing,

which included full subsidies for rural households to provide indoor connections to the

rural wastewater treatment infrastructure, as well as to cover O&M costs of various

infrastructure components.

Assessment of Risks

29. The project was given an overall risk rating of “Modest”, and most risks were

correctly identified and had mitigation measures put in place. In the rural wastewater

component, the extensive involvement of local communities in the selection and design of

wastewater infrastructure helped to ensure that the systems implemented were appropriate

for each context. The provision of full financial subsidies by municipal and country

governments was important in mitigating against low household connection rates, which

are often a barrier to effective wastewater treatment implementation in rural China.

30. However, several risks were either not identified or not adequately mitigated

against. In the rural wastewater component, the lack of experience in implementing a

community participation approach as well as lack of capacity in various aspects of technical

design, project and financial management among PIUs, was under-estimated, resulting in

significant initial delays. The lack of interest among local design institutes (DI), as well as

the poor quality of schemes submitted by DIs, were also unforeseen risks that led to delays.

31. In the Chunhu Town infrastructure component, the decision to build only the first

phase of the Fenghua coastal water supply but design the infrastructure for future expansion

mitigated against uncertainty over future population growth. One area that may not have

Page 19: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

8

been foreseeable was that of the economic slowdown in China, which impacted the pace

of development in Hongsheng Haitang, the economic zone close to Chunhu Town. With

less development in that economic zone, wastewater output is not reaching projections, so

the project’s WWTP is currently functioning below capacity.

32. In terms of the capacity-building and implementation support component, the risk

of not delivering on the various small sub-components was not considered. In the ESMAP-

supported energy efficiency sub-component, for instance, several recommendations on

were eventually not adopted because of high costs, e.g. the use of solar lighting in school

buildings. Cost was likely a deterring factor in having the energy efficiency guidelines

more widely adopted, and could have been better mitigated against had the risk been

identified upfront.

33. Overall, quality at entry is rated satisfactory. Although design of the capacity-

building and implementation support component could have been improved with a more

focused set of sub-components and closer monitoring of outcomes, thorough preparation

work was carried out for the rural wastewater and Chunhu Town infrastructure components,

particularly for the former given the novelty of the community participation approach.

Some risks could have been better identified, but as whole the major risks were adequately

mitigated against.

2.2 Implementation

34. NNCDP was completed on schedule and slightly over budget. Infrastructure-related

targets were met and in some cases exceeded, but implementation progress among the

different components was uneven, as discussed in this section.

35. The rural wastewater component was implemented in five batches using the

programmatic approach discussed above and in Annex 2. However, the component

encountered significant delays early on, and half way through implementation, the

component had only achieved 25% of its PAD targets. This led to the project being

downgraded to “Moderately Unsatisfactory” in the March 2013 Implementation Status

Report (ISR). The main causes for these delays are detailed below.

36. Lack of Experience with Community Participation Approach. A lack of experience

with the community participation approach, not only from implementing agencies but also

among communities involved, resulted in slow village selection and slow implementation

of works, particularly in the first two batches of villages. The NRWTPMO and county

PIUs stepped up efforts to inform and involve villages in the selection process using

brochures and cartoons to disseminate information on the project’s benefits and the

requirements for selection. To tighten the implementation process, additional village

selection criteria and additional conditions for the commencement of works were added to

the Rural Wastewater Management Framework, emphasizing aspects such as the need to

have DIs work with villagers during the design stage.

37. Low Capacity of Implementing Agencies. Initial delays also resulted from low

management capacity and frequent staff changes in the PMOs and PIUs. The Bank

Page 20: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

9

intensified training to improve the capacity of PMO and PIUs, covering areas such as

contract management, monitoring and evaluation, procurement management, financial

management, and participatory management. The NRWTPMO organized domestic study

tours for PMO and PIU staff to Beijing, Tianjin, Weihai and Yunnan to understand best

practices in rural wastewater construction.

38. Lack of Experience among DIs and Frequent Design Changes. The project called

for the PIUs to employ experienced DIs to prepare detailed plans and bidding documents.

However, the local DIs showed little interest in bidding due to the small size of the works

and the rural site locations. In addition, numerous design changes were required during

implementation because the inexperienced PIUs carried out poor quality preparatory field

work and surveys, which provided erroneous levels and alignments.

39. Chunhu Town infrastructure and township enhancement component. These

works progressed steadily with all three sub-components completed on schedule. For the

Chunhu Town Wastewater Management sub-component, one issue that arose was a lag

between the completion of the WWTP and the accompanying collection network, resulting

in the WWTP resting idle for over a year. This suggests the need for better timing and

coordination in the construction of linked assets, as discussed further in Section 5.2.

40. The three sub-components of the capacity-building and implementation support

component progressed at different rates. In particular, the ESMAP-supported sub-

component on energy efficiency guidelines encountered delays. Firstly, the PIU faced

challenges in identifying appropriate DIs due to the relatively small contract values and a

lack of qualified firms. Secondly, while the rural housing project in Dongxie Village had

been identified at appraisal as the demonstration site for energy efficient guidelines and

improvements, the site had to be changed during implementation to Silian Village, as

villagers were no longer willing to participate in the pilot. A lack of related KPI and IOIs

for the various TAs meant that they were not closely monitored during implementation,

and, with the exception of the energy efficiency component, results were not disseminated

to other small towns.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

41. Design. The project’s M&E design was straightforward, and took advantage of

existing reporting systems to streamline data collection. The principal tool for M&E was

the results framework, which included six KPIs – one to measure the number of households

with appropriate rural wastewater services in operation, three to measure the outcomes of

the three sub-components of the Chunhu Town infrastructure development component, and

two related to improving town management. The number of KPIs was reasonable

considering the breadth of the NNCDP components.

42. There were also six intermediate outcome indicators (IOI): one to track the

increasing number of villages with wastewater treatment, and five for Chunhu Town

infrastructure development. While the IOI for the Chunhu-Fenghua access road was

improved road accessibility, the IOI measured only physical progress of road construction,

instead of access improvement. More suitable IOIs might have been an access indicator

Page 21: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

10

such as increase in the number of villages within a certain distance from a main road, or

one such as reduced time between Chunhu and Fenghua. Likewise, for the outcome of

improved reliability and quality of drinking water, the related IOIs measured only physical

progress of the related assets, instead of actual progress in water reliability or quality.

43. One strength of the project’s M&E design was that it included a specific monitoring

and evaluation program (MEP) for the rural wastewater component, designed to evaluate

nine different areas of performance after the first batch of villages had been implemented.

Key objectives of the MEP were to recommend modifications to the design and approach

as required, and identify key factors that would ensure the program’s replicability and

sustainability. The need to have DIs work in closer consultation with villagers during the

design stage, for example, was one such MEP finding. The Rural Wastewater component

also included a monitoring program for treated water quality, which was made available in

semi-annual progress reports. The results of the monitoring show that water quality has

improved, though results were not included in the project’s RF, as this was not the main

focus of the PDO.

44. However, a weakness of the M&E design was that it contained no IOIs pertaining

to improving the management of small towns, making the contribution of the various

individual sub-components to the overall objective difficult to quantify. Some IOIs might

have quantified, for instance, improved energy efficiency in pilot sites, governance

efficiency gains due to the e-government system, or milestones in planning outputs to

reflect improving township management. This is discussed further in Section 3.2.

45. Implementation and utilization. Data for results monitoring was collected by

various implementing agencies, and was incorporated into semi-annual progress reports as

well as the borrower’s ICR report. The NMPMO was responsible for coordinating and

presenting the required data from multiple PIUs, and it performed this task effectively. No

major issues with this aspect of M&E were encountered over the course of the project.

46. The M&E system was generally effective for monitoring implementation progress

of the rural wastewater infrastructure components, having identified shortcomings in the

first batch of works and made recommendations to improve various procedures in the

subsequent batches. For example, the MEP identified that irregular, inconsistent

monitoring of the performance of the wastewater infrastructure was being carried out by

contractors, and that a lack of training for local villagers had also resulted in inadequate

monitoring by the community. To address this, a set of O&M management rules –

Operation and Maintenance Management Rules for Rural Wastewater Treatment

Facilities for World Bank Project in Ningbo Municipality – were issued by NMG, in

consultation with the World Bank, in February 2013. These formed the basis for a more

consistent approach to O&M.

47. In terms of the Chunhu Town infrastructure component, one area of weakness was

that M&E did not pick up on the mismatch in construction timing between the WWTP and

its accompanying collection network, which led to the WWTP sitting idle for over one year.

The individual IOIs measuring the progress of the WWTP and collection network

Page 22: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

11

construction could have been more closely linked to one another, as opposed to being

considered separately. As discussed above and in Section 2.1, the lack of related KPI and

IOI in the RF meant that the smaller TA sub-components under the implementation support

and capacity-building component (e-government system and business promotion strategy)

were not monitored.

2.4 Safeguard and Fiduciary Compliance

Safeguards Compliance

48. The NNCDP was rightly classified as a Category B project because the components

were not large in size or scope, and were not situated in areas likely to be negatively

impacted by construction or eventual operation of the planned infrastructure. In addition,

all environmental issues associated with the construction of the project components could

be well-managed with adequate planning, monitoring and adoption of proper engineering

and construction standards. Three safeguards policies were triggered: OP 4.01:

Environmental Assessment (EA), OP 4.37: Safety of Dams and OP/BP 4.12: Involuntary

Resettlement.

49. Environmental Safeguards. An Environmental Impact Assessment (EIA) was

carried out for each project component, and an associated Environmental Management

Plan (EMP) was also developed as part of the EIA report. A Consolidated Environment

Assessment (CEA) report was also compiled. As only the first batch of villages in the rural

wastewater component could be prepared during appraisal, an Environmental Management

Framework (EMF) was prepared to guide implementing agencies on safeguards-related

matters for the four remaining batches. The EIA report in Chinese was disclosed on May

22 and May 26, 2009 through different websites, while the English language CEA was

disclosed through the Bank’s InfoShop on July 20, 2009.

50. The NMPMO was responsible for monitoring compliance with and reporting on

environmental safeguards through the project’s semi-annual project reports, and was

critical in providing guidance to implementing agencies on safeguards-related matters.

Overall, the project complied with the Bank’s Environmental safeguards satisfactorily, and

the environmental impacts were well anticipated during project preparation. Proposed

mitigation measures were implemented by contractors and PIUs satisfactorily, with no

complaints received from affected parties. The Ningbo Water Conservation Bureau carried

out the necessary strengthening and renovation works required for the Hengshan Reservoir

dam in accordance with the Bank’s requirements under OP 4.37..

51. Social Safeguards. Efforts were made to minimize resettlement impacts during

project planning and design. A Resettlement Action Plan (RAP) was prepared for the

Chunhu town infrastructure development component (in both English and Chinese), while

a Resettlement Policy Framework (RPF) was prepared for the rural wastewater component.

As a linkage issue was identified in the Fenghua coastal water supply component, a

retroactive resettlement review was prepared as an annex to the RAP. All resettlement

preparations complied satisfactorily with OP 4.12, as well as the relevant domestic laws

and regulations. The RAP in Chinese was disclosed through local media on July 21, 2009

Page 23: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

12

and was made available at the NMPMO, PIUs, public libraries and on websites. The RAP

in English was disclosed in the InfoShop on July 21, 2009.

52. All necessary resettlement-related activities required in the RAP and RPF were

carried out as required with issues resolved in a timely manner. Regular internal monitoring

by the PMO, as well as feedback from three external reviews over a two-year period, helped

to ensure that any issues were proactively addressed. Implementing agencies kept the

communities informed on progress throughout the land acquisition and resettlement

process. A transparent grievance redress system was established, and no complaints were

received over the course of the project. A Resettlement Post-Evaluation report was carried

out by an external monitor at completion. The report found that all requirements in terms

of the Bank’s social safeguards policy had been satisfactorily met.

53. Adverse impacts of land acquisition and demolition of houses on the incomes and

livelihoods of project affected persons (PAP) were mitigated against, and all property

losses were adequately compensated. The resettlement of PAPs proceeded smoothly, and

improvements in their living conditions were noted (See Annex 7). Comparing the annual

income and expenditure of affected households in 2009 and 2015, a survey conducted by

external monitors found that per capita net income had risen significantly, from

approximately CNY 40,000 to CNY 58,600. Some 44% of PAPs were very satisfied with

current living conditions, 50% were somewhat satisfied, and just under 6% were neither

satisfied nor dissatisfied. All PAPs agreed that their lawful rights and interests had not been

infringed on.

54. Land acquisition and resettlement for all three subcomponents were conducted in

accordance with project construction schedules. In terms of land acquisition, actual figures

for permanent acquisition and demolition of houses were higher than planned. (See Annex

7, Table 7.1). A total of 325mu of land were acquired, or a 24% increase over the planned

amount, and housing demolition doubled due to unforeseen requirements for the Chunhu-

Fenghua Access Road. Land originally thought to only require temporary occupation had

to be acquired, as it was unusable on its own when adjacent parcels had been acquired.

Resettlement and acquisition of the additional land were carried out satisfactorily in

accordance with the RAP.

Fiduciary Compliance

55. Financial Management. Overall, Financial Management (FM) was satisfactory.

The Ningbo Municipal Finance Bureau (NMFB) and NMPMO both had extensive

experience in FM prior to NNCDP, which enabled them to provide training and build the

capacity of the less experienced PIUs. A well-prepared FM manual proved effective in

this regard. Interim Financial Reports (IFRs) and audit reports were submitted in

accordance with the Loan Agreement, and all audits were carried out by independent

auditors, were produced on time and received unqualified (clean) opinions. The project

was given a FM risk rating of “moderate” at appraisal, and the mitigating measures

implemented (i.e. training for all project finance staff, most of whom were new to Bank-

financed projects) were effective.

Page 24: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

13

56. Procurement and Contract Management. Procurement was done satisfactorily in

accordance with Bank procedures. In the rural wastewater component, procurement

suffered delays early on largely due to the PIUs’ unfamiliarity with Bank policies and

procedures. As difficulties were encountered in identifying appropriate DIs and

accommodating numerous changes between preparatory and detailed design stages, the

Bank showed flexibility in allowing, for instance, reducing the contract scales and

combining survey and detailed design into one contract. Procurement and contract

management were generally satisfactorily managed.

2.5 Post-completion Operation/Next Phase

Rural Wastewater Management Component

57. Before hand-over of the rural wastewater infrastructure to individual Village

Committees, O&M was to be managed by contractors for an 18-month period following

completion of works. At closing, 96 out of 144 villages remained in the 18-month handover

period. Of the 48 villages with O&M handed over, 10 villages had O&M managed by the

local town government, while 38 had engaged third-party providers. Each village has

members who have undergone training to carry out simple, regular maintenance.

58. Site visits to Fenghua and Ninghai counties were carried out to observe O&M

procedures put in place by external companies. While the monitoring platforms had their

merits, including the use of technology to remotely monitor physical conditions, the

systems were not standardized, with variations on how data was collected and assessed.

Based on observations of these O&M systems, the PMO noted that the technical capacity

of firms with regard to rural wastewater infrastructure, varies considerably. Closer

monitoring and coordination among PIUs and the PMO are necessary to ensure consistency

in monitoring and measurement of results, and in the systems’ overall sustainability. To

this end, the PMO prepared a set of guidelines – Zhejiang Rural Wastewater Treatment

Facilities Operation and Maintenance Management Assessment Methods – in March 2016.

These should tighten the process of appointing external companies, by more clearly

specifying the standards and requirements for O&M systems at the bidding stage.

59. O&M funding policies, as well as longer-term infrastructure replacement policies,

were determined at the county level, with cost subsidies determined in line with the socio-

economic status of villages, as designed. In Fenghua and Ninghai Counties, where

approximately half of the villages were categorized as relatively poor, 100% of O&M costs

and infrastructure replacement costs will be covered by county governments. In Yuyao

County, with around 3% of villages considered relatively poor and more than half of

villages relatively wealthy, the county will cover O&M costs, but villages are fully

responsible for electricity and equipment upgrading. A wastewater treatment tariff of

between 0.45 – 0.8 CNY/m3 of water or RMB 2.67 – 4.75/month has been introduced in 55

of the 144 villages, the majority of which fall in the relatively wealthy category.

Wastewater tariffs are collected every two months by the county government. The amount

charged is reasonable considering that the average amount households were willing to pay

when surveyed at appraisal was RMB 3.98/month.

Page 25: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

14

Chunhu Town Infrastructure Development Component

60. Fenghua City assumed responsibility for O&M of the assets on behalf of FCIC, and

has outsourced this to different external companies. The City is also responsible for

providing budget appropriations to meet O&M requirements and payments to the

management companies, which it has expressed commitment to continuing.

61. Chunhu-Fenghua Access Road. Following completion of check-and-acceptance

procedures, the road was handed over to the Tunnel Management Office and Road

Construction Management Office (part of the Fenghua Road Management Division under

the Fenghua Transport Bureau) in January 2013, and was assessed as being in good

condition at acceptance. The road belongs to the national Class I Highway Network and

follows the standard O&M procedures, as laid out by the National Highway Management

Department. The project relies entirely on government support for funding O&M.

62. Fenghua Coastal Water Supply. The water supply system was handed over to the

Fenghua Xinyuan Water Company in phases upon completion of separate components

between September 2014 and March 2016. The Fenghua Xinyuan Water Company is

responsible for O&M of the infrastructure, as well as collecting a water tariff. A charge of

RMB 2.05/m3 of water was introduced in 2015 and will increase by 25% every three years,

beginning in 2018. Based on the company’s financial projections, this water tariff will be

sufficient to cover O&M costs by end-2016, and full cost-recovery will be achieved by

end-2022, in line with the project’s financial covenant for this component. Other costs are

being met by subsidies Fenghua City. (Details are presented in Annex 3, Table 3.4).

63. Chunhu Town Wastewater Treatment. The Chunhu town WWTP was handed over

to a company called the Chunhu WWTP upon completion in November 2011, while the

sewage network was handed over in August 2013. The company is responsible for

operating and maintaining the infrastructure, as well as collecting a wastewater tariff,

which is not currently being levied. The company intends to levy a tariff of 0.4 CNY/m3 of

wastewater together with a water tariff starting in 2017. It is projected that the tariff itself

will only be able to cover the cost of O&M from 2022 onwards, meaning that the project’s

financial covenant requiring wastewater user charges to cover O&M expenses by end-2016

will not be met. Similar to the coast water supply component, other costs are being met by

subsidies from Fenghua City (Details are presented in Annex 3, Table 3.5).

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

Relevance of Objectives: High

64. The PDO remained highly relevant to priorities of both the national and municipal

governments. Rural issues have remained a national priority since the NCD strategy was

first put forward in the Communist Party of China’s 2006 No. 1 Central Document; the

annual report is typically taken as an indicator of the strategic priorities for the year. In

Page 26: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

15

China’s 13th Five-Year Plan (2016-2020), emphasis is placed on well-managed urban

growth, balancing growth with ecological and environmental concerns, the provision of

quality infrastructure in rural areas and the narrowing of the urban-rural divide. The

objectives of the NNCDP remain well-aligned to these national priorities. NMG’s own

commitment to the NCD strategy remains strong, as evidenced by the estimated RMB 7

billion spent by end-2016 to complete wastewater treatment infrastructure in

approximately 1,469 villages, benefitting 720,000 households.

65. The project also remains relevant to the World Bank’s FY 2013 – 2016 China CPSP,

particularly the pillars of “Supporting greener growth” and “Promoting more inclusive

development”. NNCDP’s program-based approach and emphasis on community

involvement as a success factor for rural infrastructure remain highly relevant given the

continued focus on inclusive development and bridging the urban-rural gap. Protecting

local water sources through the implementation of proper wastewater management systems,

as well as TA on developing energy efficiency guidelines and sustainable town planning,

are also aligned with the green growth focus.

Relevance of Design and Implementation: Substantial

66. As a whole, NNCDP components were relevant and clearly linked to achieving the

PDO, and were well-designed to enable Ningbo to implement its NCD strategy. A

combination of infrastructure investments and TA targeted the development of improved

rural wastewater management systems, as well as the development of Chunhu as a

demonstration prototype for small towns. However, the inclusion of a number of other

small TA sub-components was overly ambitious.

67. Rural Wastewater Component. Given NMG’s strategic goal of protecting both rural

and urban local water sources, the construction of rural wastewater treatment infrastructure

to prevent toxic wastewater from seeping into municipal water bodies was critical to

protecting water quality. Targeting and prioritizing villages in water protection zones

ensured that this goal would be achieved more quickly and efficiently than selecting

villages at random. In all, 54 out of 144 villages, or 35% in total, were within water

protection zones. By adopting a community participation approach, the project addressed

the need for appropriate, context-specific infrastructure solutions for each village and

ensured the sustainability of the schemes. Thus the links between the PDO, outputs and

outcomes were strong.

68. Chunhu Town Infrastructure Development Component and Township Management.

The three infrastructure sub-components were clearly linked to the PDO of enhancing

small town infrastructure, with infrastructure works on roads, water and wastewater. One

minor issue is that the KPI for roads measured cars using the new access road, whereas the

NCD model sought to enhance connectivity. Reduced time travel between Chunhu and

Fenghua might have been more appropriate. For the capacity-building and implementation

support component, while capacity-building to support implementation of the rural

wastewater component was essential, the anticipated results of the numerous other small

TAs were not well-articulated, and the results framework did not capture their impact.

Page 27: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

16

Given the broad nature of the NCD program, a small number of TA components could still

have been designed to enhance township management in line with NCD principles, rather

than including several. This is further discussed in Section 3.2. Nevertheless, for the vast

majority of the project, the design was substantially relevant.

3.2 Achievement of Project Development Objectives

Rating: Substantial

69. The core of the PDO in both the PAD and Loan Agreement consisted of two

elements: (a) to improve rural wastewater management in selected villages and (b) to

enhance infrastructure and township management in support of the NCD Program in small

towns. Part (b) is further broken down into two sub-sections in the discussion below. Based

on this, the PDO rating is determined on a weightage of 50% for (a), and 25% each for

(b)(i) and (b)(ii) below.

(a) Improving Rural Wastewater Management: High

70. At appraisal, households in Ningbo’s rural areas had no wastewater infrastructure

or services. The NNCDP successfully implemented appropriate rural wastewater

technology in 144 villages, and the total number of households served by the new

infrastructure was 45,500, exceeding the target of 41,000 households under KPI #1. The

connection rate of households to the new systems was high, at 85%. In response to various

context-specific factors, including local topographic conditions, cost and ease of O&M,

different types of treatment options were implemented in the project villages. The majority

of villages (over 90%) adopted a piped sewer system with different treatment options,

while a number opted for shared septic tanks, the two main options offered. In addition,

the physical infrastructure was complemented by TA under Component 3a to improve local

technical and management capacity, providing training to implementing agencies in areas

that were otherwise unfamiliar, such as the community participation approach, project

management, financial management and O&M. In the interest of space, further details on

how the project worked are presented in Annex 2.

71. Prior to implementation, wastewater from village industries and households was

often discharged into open drains before leaking into the ground, adversely affecting

drinking water sources such as reservoirs. PAD-stage design criteria for rural wastewater

treatment outlined control parameters to be met in order to reduce levels of pollutants.

However, given that this was not a pollution reduction project, pollutant discharge testing

results were not captured by the results framework. Regular environmental monitoring

reports conducted by external environmental monitoring firms have nonetheless shown that

the pollution reduction rate has been significant (See Annex 2, Table 2.3 for further details).

In Jiangbei County, for example, the average pollution reduction rate across five main

pollutant measures – chemical oxygen demand (CODCR), suspended solids (SS), total

phosphorus (TP), ammoniacal nitrogen (NH3N) and biochemical oxygen demand (BOD)

– was between 90 to 99%. Finally, the standards for rural wastewater treatment devised

under NNCDP have been adopted, not only in Ningbo Municipality, but across all of

Page 28: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

17

Zhejiang Province, which is a major unanticipated outcome and a demonstration of the

effectiveness of these standards.

(b) (i)Enhancing Infrastructure: Substantial

72. Chunhu Access Road. The project constructed a four-lane, Class I road connecting

Chunhu town to Fenghua City, shortening the travel distance by 10km, and reducing

traveling time from 40 to 15 minutes. In line with NMG’s NCD objectives, the road has

met the growing demand for faster connectivity between Chunhu town and Fenghua City,

which had otherwise been served by bypass roads that on more circuitous routes. At closing,

new Jinhai Road had exceeded the target for KPI #2 by approximately 7%, serving 13,933

car equivalent units per day, compared to the target of 13,000.

73. Fenghua Coastal Water Supply. Chunhu town had previously relied on local natural

reservoirs for its drinking water supply, but these had proven an unreliable source as

capacity was low, supply was inconsistent and water quality was diminished by pollution.

The project built a new 15.8km-long transmission pipeline from the town to the Qiujiushan

WTP, and replaced and expanded 12.9km of the Chunhu Town water distribution network.

The supply network now provides water 24 hours a day, seven days a week, benefiting a

total of 76,500 residents in 25,500 households, slightly exceeding the 76,000 residents

targeted under KPI #3. Water quality also meets National Standards for Drinking Water

Quality GB 5749-2006. By providing a consistent supply of water that meets national

drinking water standards, this component has enhanced essential basic infrastructure in

Chunhu Town. The transmission pipelines were also built to allow for future connections

in a second phase of the coastal water supply network, to serve other small towns and

villages in the area. This second phase, serving the towns of Qiucun and Song’ao, is under

construction and is expected to be completed by end-2017.

74. Chunhu Wastewater Management. Chunhu Town had no wastewater collection or

treatment facilities at appraisal. Demand for wastewater treatment was projected to grow,

both from the town’s population as well as the development of the Hongsheng Haitang

development zone, with wastewater generation expected to reach 10,000 m3/day by 2015

and 25,000 m3/day by 2025. To treat the additional wastewater generated, the project

financed a 19km-long wastewater collection network and a WWTP with a daily capacity

of 10,000m3. KPI #4 set a target of having 70% of wastewater treated in Chunhu. This

target was exceeded, with 84% of Chunhu wastewater being treated at closing. Water

discharged from the WWTP also meets Municipal Wastewater Treatment Plant Discharge

Standards (GB 18918 2002).

75. While the KPI was achieved, the WWTP is currently functioning at about 60% of

design capacity, or 6,000 m3/day. The reason for this is the slowdown in China’s economy,

which resulted in a slower-than-anticipated pace of growth in Hongsheng Haitang, the new

development zone close to Chunhu Town. The lower volume of industrial wastewater has

reduced the quantity of influent while at the same time increasing the quality of influent,

resulting in lower pollution reduction quantities. This issue is, however, out of the project’s

Page 29: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

18

span of control, and the component has still contributed to the overall objective of

improving basic infrastructure in the town.

(b) (ii) Enhancing Township Management: Moderate

76. While there was strong support for the NCD program by NMG when the project

was developed, NMG also recognized its lack of experience in small town development.

The project therefore provided TA support for institutional development in line with NCD

principles, including energy efficiency, strategic and spatial planning and improved

government administration. As raised in Sections 2.1 and 2.3, an issue with the design of

this component was the lack of suitable KPI and IOI to sufficiently monitor progress and

achievements. KPI #5 and KPI #6 measured only whether specific activities (adoption of

energy efficiency guidelines and completion of NCD plans for Chunhu town) were

completed. While these were met, and the activities specified under the remaining TA sub-

components were also completed, largely as they had been designed, it is difficult to

ascertain the degree of enhancement of township management in absence of a robust RF.

It should also be noted that the PDO in the LA made reference to improving management

in “small towns”, indicating that a demonstration effect was likely intended. However,

there were no deliberate efforts made to ensure that this would take place. (Detailed

information is presented in Annex 2).

77. Based on information obtained at the ICR stage, the different TA components

appear to have had varying levels of effectiveness in enhancing township management.

Firstly, under business promotion, activities were intended to enable the Chunhu Town

government to promote the town as a desirable location for commercial activity and other

complementary services close to the Hongsheng Haitang area. Deliverables included a

website to promote investment in Chunhu Town and organizing seminars and business

fairs to market investment opportunities and sound out investor demand. The town

government has committed to ensuring business promotion remains a priority, and have

attributed the successful relocation of four manufacturing businesses to Chunhu Town.

Secondly, under e-governance enhancement, an online platform for information sharing

among government agencies was created. However, no details were available in terms of

how widely this is used, or how it has improved government efficiency.

78. The third TA on energy efficiency, supported by ESMAP, faced some limitations

in its effectiveness as a result of cost constraints. Guidelines for rural housing sites and a

school site were developed (KPI #5 was met), but could not be implemented fully because

of cost – suggested efficiency measures such as the installation of solar panels, and the

renovation of buildings using more energy efficient materials, were not implemented. At

the same time, the guidelines were utilized in rural housing projects in two villages beyond

the demonstration sites, indicating a small degree of dissemination. Finally, for the TA on

preparing strategic and master plans, feedback has indicated that the way in which the TA

was conducted – the process of developing plans was iterative, and involved several rounds

of consultations and discussions between consultants, government officials and local DIs

– helped to build capacity among local institutions. The proposals required for plans under

KPI#6 were also completed.

Page 30: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

19

3.3 Efficiency

Rating: Substantial

79. An economic analysis was conducted covering the rural wastewater component

and the Chunhu Town infrastructure component (i.e. the Fenghua-Chunhu access road,

Fenghua Coastal Water Supply and Chunhu Wastewater Treatment sub-components).

Together, these accounted for 99% of total project costs. The project was expected to

generate a variety of economic benefits to Ningbo Municipality, including improved public

health and quality of life in villages and Chunhu Town, improved quality of waterbodies

and soil in the project area, as well as saved travel time and cost and increased productivity.

80. Given the challenges of quantifying the economic benefits related to water quality

improvement, and in determining the causal link between the benefits realized and the

improvements made, a cost-effectiveness approach for evaluating the rural wastewater

component, as well as the Fenghua coastal water supply and Chunhu Town wastewater

treatment investments was adopted, which allowed effective, low-cost solutions for each

component to be selected. The table below compares appraisal and completion indicators

for components assessed using the cost effectiveness approach.

Table 3.3.1: Comparison of Indicators at Appraisal and Completion

Component/ Sub-Component PAD ICR

1. Rural Wastewater Component

No. of beneficiary villages 150 144

Beneficiary households (Target/ Actual) 41,000 45,500

Investment (Million RMB) 327.4 394.8

Beneficiary households per RMB 10,000

investment

1.3 1.2

2. Chunhu Town Infrastructure Development

(i) Fenghua Coastal Water Supply

Water supply capacity (tons per day, 2015) 26,000 26,000

Beneficiary population (Target/ Actual) 76,000 76,500

Investment (Million RMB) 107.4 131

Beneficiary population per RMB 10,000

investment

7.1 5.8

(ii) Chunhu Town Wastewater Management

Water treatment capacity (tons per day, 2015) 10,000 10,000

Wastewater Treatment Rate (Target/ Actual) 70% 84%

Investment (Million RMB) 55.5 59.6

81. Actual project investment costs exceeded estimates across all components by a total

of 17%, as shown in Annex 1, largely due to exchange rate fluctuations, as well as increased

costs associated with resettlement and land acquisition, particularly for the Chunhu-

Fenghua access road. The Fenghua Coastal Water Supply component also saw an increase

in costs associated with water conveyance tunnels, as these were found to require a deeper

Page 31: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

20

depth than anticipated for operational safety reasons. The comparison above shows that the

project achieved levels of efficiency that were fairly close to, or in some cases better, than

what had been estimated at appraisal.

82. Comparisons were also made with other projects as appropriate. For the rural

wastewater component, NNCDP costs were compared with those of NMG’s own, more

widespread project to provide rural wastewater services to more than 720,000 households

elsewhere in the Municipality. NNCDP provided rural wastewater infrastructure at an

average cost of 8,000CNY/household, while NMG’s own project did so at a significantly

higher cost of between 10,000 – 15,000CNY/ household. The Chunhu Town WWTP, with

a capacity of 10,000m3/day, was constructed at a total cost of 27.04 million CNY. In

comparison, a WWTP with half the capacity (5,000m3/day) constructed as part of the

Zhejiang Qiantang River Basin Small Town Environment Project was constructed at a cost

of 24.53 million CNY, a difference of less than 10%. Both plants were designed to meet

the same national Class 1B treatment standards. As construction methods and local

topographical conditions were unique to the NNCDP, a suitable comparison was not made

for the Fenghua Coastal Water Supply system.

83. A cost-benefit analysis was conducted for the Fenghua-Chunhu access road.

Sensitivity analysis (assuming a 20% increase in capital costs and 20% decrease in

economic benefits) showed that the access road investment will provide an EIRR of 12.1%

or 10.2%, with and without the increase in land value respectively. Despite the EIRR being

lower at completion than at appraisal, it still exceeds the 10% generally accepted by both

the Bank and the Government. Full details are presented in Annex 3.

84. In terms of administrative efficiency, the project was prepared in 14 months from

concept review to approval by the Board, at a cost of US$380,000. A comparison with

other NCD, rural wastewater and small town development projects revealed that the NNCD

project took the average length of time for project preparation (14 months), but was

prepared at a cost that was approximately 14% higher than average, possibly because of

the extensive preparation involved in the community participation approach. At the

implementation stage, all components progressed smoothly with the exception of the rural

wastewater management component, which encountered early delays but which was

completed before the original closing date. No extension was necessary.

85. A financial analysis for the Fenghua coastal water supply and Chunhu wastewater

treatment components was also conducted, as detailed in Annex 3. Revised financial

projections for the water supply network show performance to be slightly better at project

closure than at the appraisal stage, with the debt service coverage ratio in 2021 at 1.31 as

compared to 0.97 (See Annex 3, Table 3.4 for details). This is in spite of a more cautious

water demand projection from Hongsheng Haitang and the Zhejiang Shipyard, both of

which have been affected by economic slowdowns. The Fenghua City government has

implemented a Three-Year Action Plan to build a water distribution network covering 51

villages around Chunhu Town by 2018, thereby increasing the demand for water from the

completed water supply network.

Page 32: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

21

86. Financial performance for the Chunhu wastewater treatment component was better

at appraisal than at project close. Projections indicate that O&M costs will only be fully

covered by tariffs in 2022, seven years later than foreseen at appraisal. The debt service

coverage ratio will exceed 1 in 2025, a year later than calculated at appraisal stage. While

the financial performance covenant for Chunhu Town to be able to cover O&M expenses

with wastewater tariff charges by end-2016 will not be met, the township is committed to

covering all subsidies as needed until such time that O&M cost recovery can be achieved

(See Annex 3, Table 3.5 for details).

3.4 Justification of Overall Outcome Rating

Rating: Satisfactory

87. The project’s overall outcome is satisfactory. The PDO remained highly relevant

to both the government’s strategies and to the Bank’s CPS in terms of inclusive, sustainable

development and narrowing the urban-rural divide. The design relevance was substantial,

and efficacy is high for reaching the rural wastewater management PDO, and substantial

for the small town infrastructure enhancement PDO. Efficiency was assessed as also being

substantial. In addition, as raised in Section 3.5(c), the project helped to establish province-

wide standards for rural wastewater discharge, which did not exist when the project was

implemented. However, the PDO on enhancing the management of small towns was only

modestly achieved, with a lack of KPI and IOIs to adequately track progress and

achievement of objectives.

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

88. Community participation played an integral role in the rural wastewater component.

Through a comprehensive framework for community participation, the project ensured that

only villages with at least 80% of buy-in from residents were included, and that the rural

wastewater works were tailored made for each village’s particular circumstances. The

provision of financial incentives for households to connect to the wastewater treatment

infrastructure was important in ensuring that households connected, as a common issue in

the provision of wastewater treatment facilities in rural China is that household connection

rates tend to be low. Overall, an 85% connection rate was achieved.

(b) Institutional Change/Strengthening

89. While the NMFB and NMPMO had already accumulated significant project

implementation experience from working on other Bank-funded projects, many sub-PMO

and PIU staff were new to Bank operations. The combination of the capacity building

support offered under Component 3(a) and the extensive training carried out by the Bank,

covering procurement, FM, safeguards and operationalizing community participation for

village selection, as well as technical aspects including rural wastewater management

techniques, helped to build capacity among the PIU personnel at county and district

governments. Similarly, the capacity of the DIs was strengthened through thorough

Page 33: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

22

reviews by the Bank, which also helped to address the issue of poor capacity in the project’s

early stages. Together, these efforts to improve capacity-building were essential in enabling

the project to overcome initial implementation delays, and equipped staff with the

necessary skills to manage the project and similar projects in future.

90. In terms of the TA activities implemented, the involvement of various government

planning departments and officials in the activity for development of Fenghua’s 12th Five-

Year Plan and Chunhu Town’s Master Plan contributed to capacity-building among

participants. The TA was carried out through a series of workshops, training sessions and

site visits and was implemented by an international planning consultancy. Exposure to

international best practices in urban planning, as well as the iterative nature of the plan-

formulation process, were important elements in strengthening capacity in the local

planning departments and DIs.

(c) Other Unintended Outcomes and Impacts (positive or negative)

91. The standards for rural wastewater treatment devised for NNCDP have been

adopted across Zhejiang Province. Prior to the project, no technical standards existed for

rural wastewater discharge in China. Standards for city and town wastewater treatment

were unsuitable in the rural context. The standards for the rural wastewater component

were approved for use by the Ningbo Environmental Protection Bureau (EPB) during

project preparation, forming the foundation for design work. These standards were later

accepted by the Zhejiang Provincial EPB, resulting in the issuance of a province-level

standard for rural wastewater treatment – DB33/973-2015, Water Pollutants Discharge

Standards for Rural Sewage Treatment Facilities. Standards were released on June 29,

2015 and became effective on July 1, 2015.

92. In addition to the establishment of province-level wastewater treatment standards,

NMG estimates it will have invested about RMB 7 billion by end-2016 to complete

wastewater treatment infrastructure in approximately 1,469 villages, benefitting 720,000

households. This widespread expansion of rural wastewater infrastructure was enabled in

part by the project’s managerial and technical capacity-building.

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

93. No beneficiary surveys of stakeholder workshops were conducted.

4. Assessment of Risk to Development Outcome

94. The overall risk rating is moderate based on the risks described below.

95. Risk that village wastewater treatment systems will not be properly maintained,

resulting in environmental degradation. Rating: Moderate. While the design of the rural

wastewater component included important mitigation measures to better ensure

sustainability, O&M remains a concern. Capacity of Village Committees and third-party

providers in this regard is limited. The borrower’s ICR has noted, for example, cases in

which broken sewer connections, unprotected treatment terminals and malfunctioning

Page 34: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

23

electrical equipment have hampered the effectiveness of the treatment facilities. As

discussed in Section 2.5, O&M procedures will require close supervision to ensure the

guidelines established by NMPMO are followed. Regular inspections by Village

Committees, in close cooperation with PIUs, are needed to prevent wastewater treatment

infrastructure from being compromised.

96. Risk of damage to infrastructure due to natural hazards. Rating: Moderate.

Zhejiang Province experiences the heaviest economic losses from tropical cyclones in all

of China, with six of the top ten costliest tropical cyclones during the period 1983-2006

affecting the province1. Given the location of the project (see Map), there is a moderate

risk of damage to the completed infrastructure as a result of typhoons and flooding. To

mitigate against unexpected costs of damage repair, O&M budgeting factored in the

damage repair costs due to by natural hazards. Still, project design could have been

strengthened by factoring in the need for resilience of infrastructure to natural hazards.

97. Risk of continued slow pace of economic growth, impacting demand for water and

wastewater treatment and resultant low operating capacity of related infrastructure.

Rating: Moderate. The economic slowdown in China has resulted in lower-than-

anticipated growth in the Hongsheng Haitang economic zone, which has in turn impacted

the daily volume of wastewater being treated by the Chunhu WWTP. Given the current

economic climate and projections for slower, but more sustainable, economic growth in

China, the operating efficacy of the completed infrastructure could continue to be impacted.

98. Risk to sustainability of O&M financing for Chunhu Town wastewater treatment

component. Rating: Low. The sustainability of O&M for the Chunhu Town wastewater

sub-component is contingent in part on the water tariff levied on residents. Challenges in

levying tariffs for wastewater treatment are not unusual in China, where wastewater

treatment is often viewed as the responsibility of the government. The sustainability of

O&M in the interim will be dependent on government subsidies; that said, the government

is committed to providing support for wastewater treatment in Chunhu, and NMG’s current

financial status appears to allow this to continue. As such, the risk to development outcome

is considered low.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Rating: Satisfactory

1 Zhai Panmao, Wang Cuicui and Li Wei, 2007. “A Survey of the Research on Changes in Extreme Precipiation

Events”. Advances in Climate Change Research 3(3): 144-148. Zhai Panmao, Xuebin Zhang, Hui Wan and Xiaohua

Pan. 2005. “Trends in Total Precipitation and Frequency of Daily Precipitation Extremes over China.” Journal of Climate 18: 1096-1108.

Page 35: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

24

99. The NNCDP was conceived and designed to be highly relevant to both the national

NCD strategy as well as the Bank’s strategic engagement with China. The task team at

preparation comprised members with appropriate specializations given the focus of the

project, such as water resources, transport, urban development, social development and

financial analysis. Alternatives for implementation were duly considered during the

preparation stage, and institutional arrangements were appropriate given the decentralized

nature of the project area. Major risks were identified and adequately mitigated against.

100. The rural wastewater component in particular introduced a novel community

participation approach to the sector in China. The component also prioritized water source

areas and poorer villages in its selection of sites, in line with the strategic imperatives of

the NCD program. At the same time, acknowledging that the participatory approach was

unfamiliar to communities and implementing agencies, and that implementation of the

component in geographically scattered villages would be challenging, preparation was

thorough, drawing on lessons from similar rural infrastructure projects both in China and

internationally. A comprehensive Framework for Implementation of the Rural Wastewater

Component established clear policies and procedures for implementing the rural

wastewater component. The inclusion of an MEP was also significant in ensuring that the

program-based approach was effective. However, an area that could have been

strengthened during project preparation was the assessment of the client’s institutional

capacity, where weak capacity of the PIUs and the DIs slowed implementation.

101. In terms of the Chunhu Town infrastructure component, Chunhu was selected based

on careful consideration of the town government’s commitment to implementing the

national NCD strategy, as well as its anticipated future growth and potential to serve as a

demonstration site for NCD principles. The decision to finance only Phase 1 of the Fenghua

Coastal Water Supply network proved to be prudent as expansion of the Zhejiang Shipyard

has been considerably slowed in light of the general slowing of the shipbuilding industry.

102. As described in Sections 2.1 and 2.3, the capacity-building and implementation

support component was not as well-designed as the rest of the components, although their

inclusion was in line with broader NCD principles. As a whole, the TAs were fairly

ambitious in scope, targeting several different aspects of township management

enhancement, but without enough suitable KPI or any IOIs to measure progress and

achievement. The component also did not touch on how to operationalize the

demonstration effect of enhanced township management in other small towns.

(b) Quality of Supervision

Rating: Satisfactory

103. Overall, the quality of Bank supervision was satisfactory. The Bank helped the

borrower overcome initial delays in the rural wastewater component with close monitoring,

supervision and provision of training. In light of the slow overall implementation progress

observed in early 2013, the team exercised candor in downgrading the project to

“Moderately Unsatisfactory” status. At the same time, Bank management topped up the

supervision budget with an additional US$20,000 to conduct extensive training on project

Page 36: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

25

management, procurement, FM, social and environmental safeguards and contract

management, which were acknowledged by the borrower as having built capacity among

implementing agencies. The task team was also able to build on the already strong working

relationship with NMG, ensuring close communication and supervision throughout the

implementation process.

104. A total of twelve full supervision missions (excluding the ICR mission) were

conducted, and the supervision task teams largely comprised members with an adequate

skill mix given the scope of the project. Site visits to monitor the status and operation of

completed project-funded infrastructure were carried out as part of each mission.

Supervision of the safeguards and fiduciary aspects of the project was effective. The

change in task team leader in 2012 also did not impact implementation progress. The team

was proactive in addressing issues that arose, and gave clear, effective guidance to

overcome delays and issues faced. In the Chunhu wastewater treatment system, for

example, the WWTP was completed on schedule in April 2012, but lay idle or functioned

at a low daily capacity because the necessary secondary and tertiary networks were not

built. By stressing the importance of a time-bound action plan for construction of these

networks and closely supervising implementation progress, the team worked closely with

the borrower to increase the utilization of the WWTP.

105. The task team generally placed more emphasis on the various infrastructure

components of the project during supervision as compared to the TA sub-components,

especially given the delays encountered in the rural wastewater components. As the TA

component also lacked IOIs, closer monitoring of the capacity building and

implementation support component was also somewhat limited by the RF design. A mid-

term review was not required for the project and one was thus not carried out, though it

may have been useful in terms of identifying shortcomings in the TA components.

(c) Justification of Rating for Overall Bank Performance

Rating: Satisfactory

106. On the basis of the above assessments, the Bank’s performance is rated Satisfactory.

It should also be highlighted that the borrower widely acknowledged the Bank’s support

during the implementation phase, noting that the task team’s close supervision,

responsiveness and practical advice enabled PMOs and PIUs to enhance their capacity to

implement the project.

5.2 Borrower Performance

(a) Government Performance

Rating: Satisfactory

107. This rating considers the performance of the Ningbo Municipal Government

(NMG). NMG remained a committed partner in the NNCD project, working closely with

both the Bank and implementing agencies to ensure successful preparation and

Page 37: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

26

implementation. The project triggered three safeguard policies, which NMG had the

experience and capacity to address. Counterpart funds were sufficient and allocated in a

timely manner, and no major issues with requesting funds or processing reimbursements

were encountered. One particular area in which the NMG was actively involved was in the

promotion of O&M guidelines for the rural wastewater component. The O&M

management rules issued in March 2013 were the first of their kind for NMG, and helped

to provide a set of standards for all villages to follow, which was necessary given the large

number of villages involves as well as challenges faced with high staffing turnover and

poor capacity among PIUs.

108. In addition, NMG provided considerable financial subsidies for the various project

components, fully covering the costs of indoor household connections and some O&M in

the rural wastewater component, as well as contributing to O&M for the Chunhu-Fenghua

access road and the Chunhu Town wastewater treatment components. The high connection

rate of 85% for the rural wastewater treatment component is attributable to the full coverage

of connection costs in each county, of which NMG made partial contributions.

(b) Implementing Agency or Agencies’ Performance

Rating: Satisfactory

109. The project was implemented by several implementing agencies, including an

overall municipal PMO, PMOs at the city and county levels, as well as PIUs in each

participating country/ district. The rating in this section considers the performance of the

key implementing agencies.

110. Ningbo Municipal Project Management Office (NMPMO). NMPMO was able to

build on its prior experience of working on other Bank-funded projects to provide support

and guidance to sub-PMOs and PIUs. NMPMO’s role as overall coordinator was

significantly strengthened when a new Deputy Director was hired to oversee the project in

2012, in response to the initial delays encountered in implementation and the need for

greater coordination and training among other implementing agencies. Overall, NMPMO

played a critical role in institutional coordination, organizing trainings and monthly

progress meetings among the various implementing agencies.

111. Ningbo Rural Wastewater Treatment Project Management Office (NRWTPMO).

Low capacity among PMO staff resulted in initial delays, as staff were not familiar with

project management and Bank procedures. This was eventually addressed through

extensive training organized by the task team and the NMPMO, including domestic study

tours to understand best practices. The NRWTPMO played a central role in obtaining

approval from the Ningbo EPB for the project’s proposed standard for rural wastewater

discharge, which went on to form the basis of a new province-wide standard. In addition,

NRWTPMO was instrumental in ensuring that the community participation approach was

better-understood and implemented by PIUs following initial delays.

112. Fenghua City Investment Company, Ltd (FCIC). FCIC was the PIU for all

infrastructure and TA under the Chunhu Town development component. The PIU

Page 38: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

27

performed satisfactorily as the implementing agency for this component, ensuring that

implementation was completed according to schedule, and that required M&E reporting

was carried out in a timely manner. In terms of the TA components, FCIC was pro-active

in addressing delays in implementation, such as the lack of interest from local DIs in

bidding for advertised projects and the need to identify an alternative demonstration site

for the energy efficiency component.

113. However, an area that could have been more closely managed by FCIC was the

coordination of Bank-funded infrastructure with other connecting infrastructure. The

Chunhu WWTP, for example, was completed on schedule, but was unused for a period of

one year as the secondary and tertiary collection networks were not planned for completion

at the same time. One area that could have been strengthened was in sharing knowledge or

best practices of the various township enhancement measures with other small towns, in

line with the objective of the component. However, this may be more of an issue to do with

the original project design, which did not require such steps to be taken.

(c) Justification of Rating for Overall Borrower Performance

Rating: Satisfactory

114. Based on the assessment of performance by both the Government and

implementing agencies, the overall borrower performance is rated Satisfactory.

6. Lessons Learned

115. A participatory approach is an effective and efficient way to solve otherwise

complex issues in construction and O&M of rural wastewater facilities, but requires

sufficient time for familiarization and capacity-building in new environments. A challenge

in implementing rural wastewater facilities is the scattered, varying nature of the locations

involved, with each requiring a degree of adaptation of the infrastructure and O&M to suit

the local context. NNCDP involved villagers in all stages of the process, from village

selection to design and O&M, and took into account villagers’ priorities and concerns

through well-designed and participatory procedures. The amount of time required, however,

to get the first batch of villages implemented was under-estimated in terms of the need for

awareness raising among communities as well as the training of staff in implementing

agencies in the community participation approach. Project complexity and implementation

capacity need to be properly matched during project design.

116. The provision of financial subsidies, in combination with awareness-raising of

wastewater treatment services among communities, is necessary to achieve a high rate of

individual household connections to rural wastewater treatment infrastructure. NMG

provided full subsidies to households to cover the costs of indoor connections. This, along

with the awareness raising on the need for and benefits of rural wastewater infrastructure,

were key elements in enabling the project to achieve a high rate of indoor household

connections (85%).

Page 39: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

28

117. Implementing wastewater tariffs remains a challenge to self-sufficiency in covering

O&M costs, and the role of financial covenants in ensuring tariff implementation appears

limited. The treatment of wastewater has traditionally been viewed as the responsibility of

the government in China, leading to challenges in levying charges for wastewater treatment

services. One of the financial covenants for the NNCDP required O&M costs of the

Chunhu Town Wastewater Management investment to be fully covered by wastewater

tariffs by 2016, but based on projections at project close, this would only be achieved in

2022, assuming the tariff is increased at a steady rate every three years. O&M expenditures

still require government subsidies, and this may continue for longer than planned given the

general sentiment towards paying for wastewater treatment. That said, NMG remains

committed to covering the shortfall in meeting O&M costs. This raises the question of

whether more realistic assumptions and requirements for covering O&M costs should be

used in such projects, given the limited effectiveness of financial covenants and the

willingness and ability of some governments to contribute to covering O&M costs. A

combination of tariffs, transfers and taxes, for example, can also be considered as means

to cover O&M costs.

118. TA components to enhance township management should be designed in a targeted

manner, with well-established links to the overall project objective and appropriate

indicators to demonstrate effectiveness. NNCDP included several TA sub-components,

which were all aimed at broadly improving township management. Without clear desired

results, the contribution of the various sub-components to the overall PDO is hard to

discern. The KPI for the TA component captured the completion of discrete tasks (e.g. the

completion of a revised NCD plan, and the completion of energy efficiency guidelines),

but did not measure the extent to which these activities improved township management,

whether in Chunhu Town or in other surrounding areas. A more measured approach with

fewer sub-components, together with appropriately designed output and outcome

indicators, would have been more effective.

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners

(a) Borrower/implementing agencies

119. A summary of the Borrower’s ICR is presented in Annex 5. Overall, the Borrower

has found the NNCD project to be successfully completed, and highlighted the guidance

and support from the World Bank task team as having contributed significantly to the

project’s success.

(b) Cofinanciers

Not applicable.

(c) Other partners and stakeholders

Not applicable.

Page 40: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

29

Annex 1. Project Costs and Financing

(a) Project Cost by Component (in USD Million equivalent)

Components

Appraisal

Estimate (USD

millions)

Actual/Latest

Estimate (USD

millions)

Percentage of

Appraisal

Component1: Rural Wastewater

Management 47.96 60.80 127%

Component2: Chunhu Town

Infrastructure Development 78.49 103.36 132%

(a) Chunhu Access Road 55.45 74.00 133%

(b) Fenghua Coastal Water Supply: (i)

Transmission Pipeline (US $12.60m); (ii)

Chunhu Town Distribution Network

Renovation and Expansion (US $3.13m)

15.73 20.18 128%

(c) Chunhu Wastewater Management 7.31 9.18 126%

Component3: Capacity Building and

Implementation Support 1.96 1.53 78%

(a) Rural wastewater management

component capacity building and

implementation support

0.71 0.53 75%

(b) Chunhu Town capacity building and

energy efficiency demonstration 0.60 0.41 68%

(c) 12th 5-Year Plan preparation support to

Fenghua Development Reform

Commission

0.35 0.35 100%

(d) Project Management and Business

Development Support for FCIC 0.30 0.24 80%

Total Baseline Cost 128.41 165.69 129%

Physical Contingencies 11.74 0.00 0%

Price Contingencies 2.04 0.00 0%

Total Project Costs 142.19 165.69 117%

Interest During Construction 14.77 4.51 31%

Front-end fee 0.13 0.13 100%

Total Financing Required 157.09 170.33 108%

(b) Financing

Source of Funds

Appraisal

Estimate

(USD millions)

Actual/Latest

Estimate

(USD millions)

Percentage of

Appraisal

Borrower 107.09 120.33 112%

International Bank for Reconstruction and

Development 50.00 50.00 100%

Total 157.09 170.33 108%

Page 41: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

30

Annex 2. Outputs by Component Project Outputs Plan at Appraisal Actual Completed

Component 1: Rural Wastewater Management

Service district 6 1. The rural wastewater management component was implemented in 144

villages across 5 districts, serving a total of 45,500 households and benefitting

approximately 141,000 rural residents. Using a program-based approach, the

component was implemented in five separate batches, with each batch adopting a

community participation methodology to select villages and appropriate treatment

technologies for each context. Municipal and county governments covered the cost

of indoor sewage connections as a means of encouraging participation in the rural

wastewater management scheme, which helped to achieve an average indoor

connection ratio of 85%. Table 2.1: Beneficiary Villages, Households and Population

Batch No. of participating

villages

No. of beneficiary HH No. of beneficiaries

1 14 3,048 9,448

2 28 7,135 22,118

3 29 9,748 30,219

4 23 8,695 26,955

5 50 16,875 52,260

Total 144 45,500 141,000

2. The project worked in the following manner, according to the Framework for

Implementation. Rural villages were identified in three broad categories: (i) those

within water surface protection areas, often in remote, undeveloped and mountainous

areas; (ii) relatively wealthy villages outside of water protection areas, often on

plains, close to population centers, with better ability and willingness to pay for

wastewater services; and (iii) relatively poor villages outside of water protection

areas. Those in water surface protection areas were generally given priority for

participation in the program, as was the case in the first batch of villages, where 13

out of 14 villages were in such areas. In total, villages in surface protection areas

Service villages About 150

Service households 41,000

Page 42: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

31

Project Outputs Plan at Appraisal Actual Completed

accounted for over one-third of all villages in the project at completion. The project

also provided TA to assist the PIUs to educate and raise villager awareness of the

importance of wastewater treatment, including consideration of technology choices,

benefits and responsibilities of asset ownership, O&M, revenue mobilization, and

hygiene education. As an incentive to connect, the project offered grants, financed

through counterpart funds, to make up for the cost of connecting to the sewer system.

A participatory approach to confirm villages for participation was adopted to ensure

that the villages were committed and suitable for inclusion in the scheme.

Table 2.2: Villages by Category

Category No. of Villages Proportion

1. Within water surface

protection areas

50 34.7%

2. Relatively wealthy

villages close to

population centers

51 35.4%

3. Relatively poor villages

outside of water

protection areas

43 29.9%

Total 144 100%

3. When villages signaled their agreement to participate in the project, the PIUs

undertook village topographical and soil investigations, prepared feasibility studies,

preliminary designs, cost estimates and financing plans, procurement plans, and the

necessary safeguard documents, and then recommended the most suitable technology

option to the villages. To build capacity, the project provided TA to support these

tasks under Component 3(a)(i), as well as office equipment. Two basic technology

options were offered: a piped sewer system or a septic tank system. The most

appropriate option was based on affordability, O&M sustainability, and the ability to

meet discharge requirements agreed on with the Environmental Protection Bureau

(EPB). Financing of the program was split between the NMG, the county

governments and the Village Committees. NMG provided a capital cost subsidy of

Page 43: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

32

Project Outputs Plan at Appraisal Actual Completed

50% from the Loan proceeds, and the county governments provided the balance from

their own revenues, including contributions from villages. Contributions from

villages were in the form of land – a total of 205 mu of land was donated for the 242

treatment terminals in 144 villages.

4. In response to various factors, including local topographic conditions, cost

and ease of O&M, different types of treatment termination options were implemented

in the project villages. The majority of villages (over 90%) adopted a piped sewer

system but utilized different treatment processes, at times in different combinations.

A total of 1,217km of pipework was laid as part of this component. Pipes were

generally UPVC wall pipes and HDPE double-wall corrugated pipes varying sizes

(DN150, DN200 AND DN300), depending on requirements set out in technical

specifications. A trickling filter system was adopted in 31% of villages, while 29%

had a combination of anaerobic treatment tanks and constructed wetlands. 23% of

villages used prefabricated advanced oxidation (AO) treatment facilities, while 9%

had wastewater collected and channeled to treatment plants. Close to 5% utilized

biological rotating contractors and the remaining 1% used sequencing batch reactor

(SBR) technology. The exact combination of technologies used was heavily

dependent on the local context. In villages that did not opt for a piped sewer system,

142 septic tanks on a two family-sharing basis and 223 community septic tanks were

also built. Tanks were built of high-quality, fiberglass-reinforced plastic.

5. The design criteria for rural water treatment outlined control parameters to

be met by the rural wastewater management systems in order to reduce levels of

pollutants discharged into bodies of water in rural Ningbo, which was important given

the municipality’s focus on protecting local water sources. While project design had

stipulated that two boreholes be drilled in each village to allow villagers to monitor

their scheme’s efficiency and assess potential contamination of surface water, this

was not implemented due to various challenges on the ground, including resistance

from villagers and unsuitable terrain. Instead, monitoring was carried out at effluent

discharge points. Although the pollutant discharge level testing results were not

captured by the results framework, regular environmental monitoring reports

Page 44: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

33

Project Outputs Plan at Appraisal Actual Completed

conducted by external environmental monitoring firms have shown that the pollution

reduction rate has been significant. In Jiangbei County, for example, the average

pollution reduction rate across five main pollutant types was between 90 to 99%.

Monitoring is carried out once every three months, and results are monitored by the

NRWPMO, NMPMO and Ningbo EPB. Table 2.3 contains further information.

Table 2.3: Pollutant Reduction Rates (December 2015)

County CODcr

(mg/l)

SS

(mg/l)

TP

(mg/l)

NH3-N

(mg/l)

BOD

(mg/l)

Xiangshan

Influent 181.8 41.2 7.1 25.5 54.8

Effluent 43.9 14.0 0.6 10.7 13.9

Pollutant

reduction

rate

76% 66% 91% 58% 75%

Jiangbei

Influent 522.3 333.3 9.1 82.4 250.4

Effluent 30.0 12.3 0.1 6.4 2.8

Pollutant

reduction

rate

94% 96% 99% 92% 99%

Fenghua

Influent 45.0 19.2 2.0 14.3 -

Effluent 22.5 9.4 1.4 7.7 -

Pollutant

reduction

rate

50% 51% 32% 46% -

Yuyao

Influent 273.9 75.7 11.8 52.8 108.2

Effluent 47.7 20.7 1.0 10.3 13.5

Pollutant

reduction

rate

83% 73% 91% 80% 88%

Ninghai Influent 196.0 87.7 1.7 16.0 76.9

Effluent 78.3 23.3 0.3 5.7 21.6

Page 45: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

34

Project Outputs Plan at Appraisal Actual Completed

Pollutant

reduction

rate

60% 72% 81% 64% 72%

Component 2: Chunhu Town Infrastructure Development

a) Chunhu Access Road

Construction contents

road specification

Build an access road between

Fenghua City and Chunhu

Town. This road has a total

width of 24.5m with four lanes

and a length of 6.2km

including a tunnel of 3.26km.

It is designed for an average

vehicle speed of 80km/h.

1. The Chunhu-Fenghua access road – named Jinhai Road – was implemented

as planned. It is a 6.2km-long, four-lane road, 24.5m in width, with a 3.26km-long

tunnel section, beginning at the end point of the planned Chunhu west Ring Road and

ending at the access road to Fenghua Railway Station. Construction began on 31

March, 2011 and was completed half a year earlier than planned on 25 January, 2013.

The road was opened to traffic on 7 February, 2013.

2. With the construction of the road, the distance from Chunhu Town to the

center of Fenghua City has been shortened from 24km to 14.2km, fulfilling the

intention of constructing a quicker access road as an alternative to the two bypass

roads (Chunhu-Abide Road and Chunhu-Lichen Road) that existed at the time of

appraisal. Travel time was shortened from 40 minutes to 15 minutes, and the daily

car equivalent volume of traffic as at project close was 13,933, which exceeded the

target of 13,000 by around 7%. Jinhai Road has helped to facilitate access to the

Hongsheng Haitang economic development area, a coastal development zone which

is planned as the largest industrial area in Fenghua. Residents of Chunhu and other

neighboring villages and towns such as Qiu Village and Song’ao Town, are able to

enjoy easier access to Fenghua, from which highway access also allows quick access

to Ningbo city.

3. The road was designed and constructed as a Class I standard road according

to specifications in Road Engineering Technical Standards (JTC B01-2003). In terms

of construction materials, the road was made of base layers of cement stabilized

crushed stone, and topped with layers of asphalt. The road belongs to the national

Class I Highway Network and follows the standard O&M procedures, as laid out by

the National Highway Management Department.

Road connection

function

The road section will connect

the northwestern part of the

corridor with the roads that

will eventually lead to the

Ningbo, Taizhou, and

Wenzhou railway stations. The

proposed road section will also

provide further access to

downtown Fenghua City. The

road will improve access from

Fenghua City to Chunhu

Township and shortens the

total travel distance by 10km.

Car equivalent The car equivalent in 2016 is

expected to achieve 13000.

Page 46: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

35

Project Outputs Plan at Appraisal Actual Completed

b) Fenghua Coastal Water Supply

Pipeline laying Build water supply

transmission mains from

Fenghua City to Chunhu

Town, including renovation

and expansion of the Chunhu

Town water distribution

network.

1. 15km of water supply transmission mains from the Qiujiushan Water Supply

Works

in Fenghua City to Chunhu Town were built, together with a booster pump station

and a 13km-long water distribution network. As at project close, a population of

76,500 in Chunhu (around 25,500 households) benefitted from the new water supply,

slightly exceeding the target of 76,000. As intended at project design, the mains were

constructed to allow future expansion of the water supply service to the towns of

Qiucun and Song’ao, as well as the Zhejiang Shipyard, as and when population

growth necessitated the extension (construction of the second phase, not financed by

the project, began in May 2015 and is expected to be completed by end-2017).

2. Construction of water supply mains began on 20 July, 2012 and was

completed on 16 March, 2015. Construction and rehabilitation of the water

distribution network began on 13 October, 2014 and was completed on 25 March,

2016. The completed booster pump station has a capacity of 20,000m3. Water quality

is in line with the National Standards for Drinking Water Quality (GB 5749-2006),

and water supply is available 24 hours a day, 7 days a week.

3. The pipes consisted of nodular cast iron pipes, steel pipes and HDPE pipes of

varying diameters. All pipe material used are in accordance with the relevant national

standards - GB/T13295-2003 for nodular cast iron pipes, GB/T13633-2000 for PE

pipes and GB/T13793-1992 for steel pipes. All construction processes were in

accordance with the GB50268-2008 standard for water and wastewater pipe

construction engineering and acceptance.

Pipeline scale

population

Build 15km new water main

and 13km water distribution

network, it is expected that

76000 Chunhu population

served from a reliable and

high-quality water supply by

the end of 2015.

c) Chunhu Wastewater Management

Page 47: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

36

Project Outputs Plan at Appraisal Actual Completed

Pipeline construction Build a 19km Chunhu

wastewater collection main

and branch pipeline

1. The completed wastewater infrastructure achieved a wastewater treatment

rate of 84% at project close. 10km of the 19km-long network was financed by the

World Bank loan, while the remaining 9km was funded by domestic counterpart

funds. Construction of the sewage pipe network began on 15 April, 2011 and was

completed on 28 August, 2013.

2. Construction of the WWTP began on 8 November, 2010 and was completed

on 30 November, 2011. However, as secondary and tertiary collection networks had

not been constructed at the time that the WWTP was completed, the plant lay idle for

over a year. The WWTP was built with a capacity of 10,000 m³/day, but was treating

a volume of 6,000 m³/day at project close due to the lower-than-anticipated capacity

from the Hongsheng Haitang new development zone. Table 2.4 below shows the

annual and daily treatment volume of water, which has steadily increased over the

last four years.

Table 2.4: Annual/ Daily Wastewater Treatment Volume

Year Annual treated WW volume(m3) Daily treatment volume (m3)

2013 1,319,543 3615

2014 1,982,245 5430

2015 2,134,420 5848

2016 11,459,912 5983

3. Water discharge standards must meet Class B-1 requirements of Municipal

Wastewater Treatment Plant Discharge Standards (GB18918-2002). Based on

monitoring data obtained at end-August 2016, the national standards for effluent

quality had been met. Table 2.5 shows pollution reduction rates as at end-August

2016.

Table 2.5: Pollution Reduction Rate COD NH3-N TP

Inflow (mg/L) 86.8 8.65 0.65

Wastewater treatment

plant capacity and

wastewater treatment

rate

Build a wastewater treatment

plant with a capacity of 10,000

m³/d in order to help Chunhu

achieve a wastewater

treatment rate of 70% in 2015.

Page 48: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

37

Project Outputs Plan at Appraisal Actual Completed

Outflow (mg/L) 27.5 2.43 0.43

Reduction (%) 68.3 71.9 33.8

Component 3: Capacity Building and Implementation Support

a) Capacity Building

and Implementation

Support for Rural

Wastewater

Management

Project management and

capacity building for rural

wastewater management,

including (i) consulting

services for project

management and

implementation support to

PMOs in the Ningbo

Municipality Rural Affairs

Office (RAO) and each project

County/District, comprising

design review, bid document

review and project supervision

and reporting; (ii) village-level

education and awareness

raising to help empower

villages with decision-making

abilities, consider options

including participation in the

program, technology choice,

1. Attachment 1 below contains detailed information on the training sessions

organized as part of this sub-component. Intended to complement the rural

wastewater infrastructure component, training sessions focused on various areas,

including financial management, project management, procurement etc., as well as

on the community participation approach.

2. A key takeaway from the rural wastewater MEP was that dissemination of

information among villagers needed to be improved, in order to secure the support

and participation of more villagers. To encourage more villages to be involved in the

NNCD projects, the NRWTPMO organized training sessions by sub-PMO staff to

villagers in different counties. The sessions were designed to share information on

the significance of rural wastewater treatment projects, in a bid to have villagers

understand the benefits of participating in the NNCD project. Brochures and posters

were produced and disseminated, complementing the information shared in more

traditional village meetings. Capacity-building for the second to fifth batches of the

rural wastewater component involved 726 attendees. 54000 brochures and 430

posters were produced and shared.

3. Two domestic study trips were arranged in July 2012 and October 2012 to

Beijing/Tianjin/Weihai and Hainan to learn applied treatment technologies and

Page 49: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

38

Project Outputs Plan at Appraisal Actual Completed

benefits and responsibilities of

asset ownership, routine

operation and maintenance

functions; (iii) training and

study tours (domestic and

foreign); and (iv)

miscellaneous equipment

comprising hardware, office

equipment, vehicle, digital

camera etc.

advanced methods in rural wastewater treatment project. Staff from sub-PMOs in

Xiangshan, Ninghai, Yuyao and Fenhua participated in these site visits. They went to

some villages and communicate with local staffs in meetings. They exchanged ideas

in project design and issues in project implementation, such as discharge standards,

designs on treatment terminals, pipeline network distributions and community

participation. In June, 2015, 20 staff from sub-PMOs in Xiangshan, Ninghai, Yuyao

and Fenhua also went to Dali, Yunnan Province for site visits and discussions with

local staff on the construction of rural wastewater facilities.

b) Chunhu Township

Management

Enhancement, Capacity

Building, and Energy

Efficiency

Demonstration

Chunhu Town capacity

building and energy efficiency

demonstration, including (i)

business promotion activities –

business promotion strategy,

web page and brochure

development, skills training

and marketing activities; (ii)

town governance

enhancement, including e-

government system installed

and updated, improvement of

government reporting and

information in disclosure

procedure, support for

activities promoting public

awareness and participation in

planning and decision-making,

and enhancement of official

performance evaluation; and

(iii) promotion of energy-

efficient township, supported

1. Consulting services for business promotion activities and the development

of an e-government system were carried out between May 2013 and June 2014.

2. Given the proximity of Chunhu Town to the Hongsheng Haitang Economic

Zone, it was envisaged that Chunhu could attract investors looking to establish

supporting industries or services. The intention of the business promotion activities

was to provide capacity-building in business/ investment promotion among Chunhu

township management. As part of the business promotion sub-component, four

small-scale investment seminars and training sessions were organized, as follows:

(a) May 2013: Seminar on Chunhu Government Capacity Enhancement and

Business Promotion activities with NMPMO, Chunhu Government,

Yangzhou University and Tongji Planning Institute. The seminar had more

than 20 participants exchanging their experiences in promoting business

activities.

(b) November 2013: A 2-day training session by Hong Kong SAR, China-

based businessman to share international perspectives on business

development.

(c) November 2013: Study trip to Shanghai, focusing specifically on the

fishery industry (e.g. low-carbon aquatic feeding systems).

(d) June 2014: Seminar conducted by Taiwan Fishery Feeding Association on

the application of grouper feeding technologies.

Page 50: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

39

Project Outputs Plan at Appraisal Actual Completed

by ESMAP, consisting of the

development of energy

efficient building designs and

renovation guidelines, a

demonstration rural collective

housing project, as well as

development of sustainable

energy action guidance and

pilots.

There were no KPI or IOIs to measure the achievements under this TA activity.

However, it is reported to have contributed to a more systematic mode of business

promotion and investment attraction by Chunhu township, and has been credited

with attracting four new manufacturing businesses to set up operations in the town.

3. In terms of the e-government system, consultants designed and implemented

an online information sharing platform for agencies to share information, documents

and administrative services. The intention behind this system was to allow for quicker

sharing of information and subsequent follow-up on items requiring attention, e.g.

the need for municipal infrastructure such as roads or reservoirs to be maintained or

fixed. The system was designed both for use on PCs and on mobile phones, and was

used by senior Chunhu Town government officials as well as staff in several

departments, including the Industry and Trade office, Agriculture and Fisheries

Department and the Urban Construction Office, and over 100 village cadres.

However, without KPI or IOIs, the outcomes of this initiative are not clear, and its

contribution to improving township management cannot be quantified. There is also

no evidence that such a system has been implemented in other small towns.

4. The energy-efficiency township component was supported by ESMAP, and

was intended to improve the capacity of Chunhu Town to pursue energy efficiency

buildings. Consulting services began in June 2012, and were completed in January

2015. Delays were caused initially due to the lack of interest among local DIs, as well

as the need to identify an alternative demonstration site after the original village

identified, Dongxie Village, decided to no longer participate in the scheme.

Deliverables for this sub-component were as follows:

(a) Research reports on status of energy efficiency of rural housing in Silian

Village;

(b) Guidelines for rural housing energy efficiency design and retrofitting of

existing buildings (including sample construction drawings) in Xixie

Village;

(c) Guidelines on energy efficiency buildings and construction guidelines for

solar water heating systems;

Page 51: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

40

Project Outputs Plan at Appraisal Actual Completed

(d) Assessment and action plan for “green renovation” at Chunhu Middle

School; and

(e) Chunhu Town sustainable energy action plan.

5. Guidelines for rural housing energy efficiency were implemented in Silian

Village with the construction of two residential buildings, each with three storeys

above-ground, one basement and two homes of about 100m2 on each floor. However,

due to budgetary constraints, not all measures could be adopted, particularly the

installation of solar panels. Even without solar panels, the completed homes were still

significantly more expensive than those normally built by villagers, averaging 2,000

– 3,000CNY/m2. The homes were reported to all have been sold, but no land was

subsequently made available for other similar developments given the high cost.

While not adopted beyond the two demonstration buildings in Silian Village, the

villages of Hongxi and Jiaotongsi were reported to have adopted the guidelines in the

construction of new residential buildings, constructing 102 and 48 homes

respectively. However, no follow-up studies were conducted to measure the energy

efficiency of the completed homes as compared to more traditional homes.

6. Similarly, while the Chunhu Middle School implemented certain

recommendations to develop the campus as a green development, such as introducing

energy-saving and water-saving campaigns, adopting other measures such as the

renovation of buildings with more efficient building materials was not possible due

to prohibitive costs. Nonetheless, the energy efficiency guidelines resulted in the

following modifications being made to the existing school site:

a) Containment Structure Reform – addition of thermal insulation materials and

replacement of windows

b) Replacement of indoor lights with energy-saving lights

c) Replacement of water taps with water-saving taps, and replacement of iron

pipes with UPVC pipes

d) Add water permeable bricks and grass-planting ground to enhance rainwater

permeability

e) Improve campus environment

Page 52: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

41

Project Outputs Plan at Appraisal Actual Completed

i. Increase green areas on campus by about 910 m2, from 4,736.3m to

5,646.3m2.The greening ratio increased from 14.3% to 17.1%.

ii. Replace regular dustbins with recyclable/ non-recyclable bins.

c) Support for

preparation of the 12th

Five-Year-Plan on

NCD in Fenghua City

Support for preparation of the

12th Five Year-Plan on NCD in

Fenghua City, including (i) the

12th Five-Year Plan on NCD in

Fenghua City – specialist

support to Fenghua DRC to

study and draft the 12th Five-

Year Plan (2011-2015) for

NCD of Fenghua City, to

prioritize various institutional

strengthening and investment

activities, and to guide

Fenghua City’s NCD in 2011-

2015; (ii) Chunhu Town NCD

Strategy and Township Master

Plan – update of Chunhu

Township NCD strategy and

completion of the township

master plan; (iii) village level

NCD planning – spatial and

sectoral development plans

and detailed design of two

selected villages in Chunhu

Town.

1. Working with the governments of both Fenghua City and Chunhu Town, the

activity was designed to strengthen Fenghua’s integrated planning management as

well as Chunhu Town’s institutional capacity in strategic and master planning. In

terms of project KPIs, KPI #5 was directly related to this sub-component.

Consultancy services began on 8 January, 2013 and were concluded on 26 September,

2014.

2. The consultants worked with Chunhu Town government officials, Fenghua

DRC, Fenghua Planning Bureau and Fenghua planning institutions to deliver the

following:

(a) An inception report, covering the deliverables and schedules for the entire

consultancy;

(b) Fenghua City 12th Five-Year Plan (2011 – 2015) for NCD;

(c) Suggestions for improvement of the Chunhu Town Master Plan, as well as

the Chunhu Town Regulatory Control Plan;

(d) Village Construction Plans for two demonstration towns

(e) Capacity-building for Fenghua planning institutes in urban planning

concepts, and national and international best practices, as well as design

concepts and technical skills for village construction plans.

3. An iterative, participatory approach was adopted to deliver the components

above. Three workshops, four training sessions and two site visits were conducted by

the consultants and government participants, in order to build an understanding of

site conditions as well as to have more in-depth discussions regarding the plans and

Page 53: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

42

Project Outputs Plan at Appraisal Actual Completed

priorities of Fenghua and Chunhu. The village construction plans were implemented

in Tangtouzhou and Zhujiadian villages. Based on the recommendations of the NCD

plan for Fenghua, Fenghua City has also begun to focus on smart city development

and eco-tourism villages as priorities for future growth.

Page 54: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

43

Attachment 1 to Annex 2: Training Sessions Conducted Under Component 3a)

No. Training

Course Duration Organizer Trainer Trainees

Core Content and Skills

Developed Activities

Cost

(RMB)

A: Domestic Training

1 Project

construction

management,

Project

Management of

Bank financed

projects, Rural

wastewater

treatment

techniques.

2009.7.7-

11(1st )

2009.8.10-

14(2nd)

NRWTPMO

/Munical

Constructio

n

Committee

Ningbo

University/P

MO/

Hydrochina

Huadong

Engineering

Corporation:

Yan

Yonghong,

Yang

Xiaoming,

Wei Jun

Responsible person

of the first-batch 16

villages /

Townership Leader

/ Responsible

person of Sub-PMO

and business header

Laws, policies and regulations

related with new countryside

development; intergration

construction for urban and rural

areas; engineering construction

management and procedures, land

acquisition and house demolition;

introduction to ningbo rural

wastewater treatment planning;

management procedures for WB

projects, rural wastewater collection

and treatment technologies.

Disseminate 3000 brochures and 30

posters.

Lectures

and group

discussion

50000

2 Procurement 2009.7.29 PMO LIU Xujun NNCD staffs/

Tendering

Agency/Sub-PMO

Procurement procedures,

introduction to procurement plan

Lectures

and group

discussion

5000

Page 55: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

44

3 Procurement

and Payment

2010.3.4-5 NRWTPMO

/ Ningbo

Financial

Bureau

Li Dejian,

Yang

Jintian,

Yang

Xiaoming

Responsible person

of four counties,

business header,

accounter and

responsible person

of county financial

bureau

Introduction to WB project process,

financial management, and discuss

on household connection

technologies.

Lectures

and group

discussion

54800

4 Second-batch

village

selection

2010.10.8-

11.6

Sub-PMOs NRWTPMO Responsible person

of 60 candidate

villages/ for the

second batch/part of

village

representatives

introduction on the significance of

rural wastewater treatment,

technologies, and key issues during

project implementation.Disseminate

8000 brochures and 120 posters

Lectures

and group

discussion

28700

5 Third-batch

village

selection

2011.7.6-

27

Sub-PMOs NRWTPMO Responsible person

of 40 candidate

villages for the third

batch/ part of

village

representatives

introduction on the significance of

rural wastewater treatment,

technologies, and key issues during

project implementation.Disseminate

10000 brochures and 80 posters

Lectures

and group

discussion

16100

6 Contract

Management,

Construction

Supervision

Management

2011.11.21 ESD ESD: Zhao

Qihong

Responsible person

of the 4 Sub-PMO,

business header /3

design institutes/3

construction

supervisor

Explanations on standard contract

template, project construction

engineering supervision, project

working process and procedures

Lectures

and group

discussion

5000

7 Project

Management,

Attest Audit,

Project O&M

2012.1.5-6 NRWTPMO

/ Ningbo

Financial

Bureau

NRWTPMO

/ Ningbo

Financial

Bureau

Responsible person

of four counties,

business header,

accounter and

responsible person

of county financial

bureau

Trainings on project management,

auditing, discussion on O&M

mechanism

Lectures

and group

discussion

50000

Page 56: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

45

8 Fourth-batch

village

selection

2012.8.10-

9.19

Sub-PMOs Sub-PMOs Responsible person

of 39 candidate

villages for the

fourth batch/ part of

village

representatives

introduction on the significance of

rural wastewater treatment,

technologies, and key issues during

project implementation.Disseminate

9000 brochures and 80 posters

Lectures

and group

discussion

15000

9 Project

Management

2012.10.23 Easen Easen:Han

Xiaowei, Li

Wenhua,

Wang Zikai,

Cheng Yijun

Responsible persons

for all components;

Designer;

Construction

Supervisors,

Contractor; Staffs

on Procurement,

Payment, and File

Management

Trainings on procurement

management, financial management,

construction management and

environment management

Lectures

and group

discussion

13700

10 Procurement

management,

capacity

building,

implementation

management,

environmental

management,

resettlement

management

2013.4.22-

24

WB WB Expert:

Wang Yuan,

Yan

Guangmin,

Yuan Jinmu,

Xie Qingtao

Government

bureaus in the

municipal level,

FCIC and

NWRTPMO, four

sub-PMOs, 2

consultant firms,

construction

supervisor

Trainings on procurement

management, capabilities

management, implementation

procedures management,

environment management

Lectures

and group

discussion

50600

11 Fifth-batch

village

selection

2013.7-8 Sub-PMOs NRWTPMO Responsible person

of 33 candidate

villages for the fifth

batch/ part of

village

representatives

introduction on the significance of

rural wastewater treatment,

technologies, and key issues during

project implementation.Disseminate

14000 brochures and 70 posters

Lectures

and group

discussion

15000

Page 57: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

46

12 Project contract

management

2014.4.17 PMO WB Expert:

Hu Shunong

Government bureau

in the municipal

level, FCIC and

NWRTPMO, four

sub-PMOs, 3

consultant firms,

construction

supervisor

introduction on contract, contract

management

Lectures

and group

discussion

2200

13 Fifth-batch

supplementary

village

selection

2014.5 Sub-PMOs NRWTPMO Responsible person

of 24 candidate

villages for the fifth

batch/ part of

village

representatives

introduction on the significance of

rural wastewater treatment,

technologies, and key issues during

project implementation.Disseminate

10000 brochures and 50 posters

Lectures

and group

discussion

10000

14 Fifth-batch

village site

training

(Fenghua)

2015.1.12-

13

Sub-PMOs NRWTPMO Responsible person

of Fenghua Ninghai

and Jiangbei Sub-

PMO and business

header, 33 village

representatives and

villager supervisor,

township

responsible person

and business person,

contractor and

construction

supervisor

How to handle policy issues, and

how to coordinate all stakeholders.

Key treatment technologies in rural

wastewater treatment, key issues in

construction, quality testing in

treatment terminals and piplelines

Lectures

and group

discussion

51000

Page 58: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

47

15 Fifth-batch

village site

training

(Yuyao)

2015.2.3 Sub-PMOs NRWTPMO Responsible person

of Fenghua Yuyao

Sub-PMO and

business header,17

village

representatives and

villager supervisor,

township

responsible person

and business person,

contractor and

construction

supervisor

Project organization and

implementation procedures, key

issues in site construction

Lectures

and group

discussion

23600

16 Fifth-batch

village staff

training

(Yuyao)

2015.6.18 Sub-PMOs NRWTPMO Villager manager

from 17 villages and

related staffs and

liason man

project construction requirement and

key points in project construction

Lectures

and group

discussion

8500

17 O&M training 2015.9.1 NRWTPMO NRWTPMO Director of Village

Committee from 91

villages in

operation, main

responsible person

from sub-PMOs

Introduction on O&M and

experience, disseminate 100 O&M

brochures

Lectures

and group

discussion

36400

B: Domestic Study Tour

1 Rural

Wastewater

construction

site study tour

(Beijing,

Tianjin,

Weihai)

2012.7.16-

21

NRWTPMO Sub-PMOs in

Xiangshan, Ninghai,

Yuyao and Fenhua

and related staffs

Learn successful experiences from

other areas on rural wastewater and

advanced technologies

Site

investigati

on and

group

meeting

and

discussion

136684

Page 59: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

48

2 Rural

Wastewater

construction

site study tour

(Hainan)

2012.10.25

-30

NRWTPMO Sub-PMOs in

Xiangshan, Ninghai,

Yuyao, Fenghua

and Jiangbei and

construction

supervision

Learn successful experiences from

other areas on rural wastewater and

advanced technologies

Site

investigati

on and

group

meeting

and

discussion

62800

3 Rural

Wastewater

construction

site study tour

(Yunnan)

2015.6.30

-7.3

NRWTPMO Sub-PMOs in

Xiangshan, Ninghai,

Yuyao, Fenghua

and Jiangbei and

construction

supervision

Explore WB project management

experience and effective ways in

rural wastewater facilities operation

Site

investigati

on and

group

meeting

and

discussion

68071

Page 60: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

49

Annex 3. Economic and Financial Analysis

Economic Analysis

Economic Benefits and Costs, General Assumptions and Valuation Methods

1. When assessed during project appraisal, the Ningbo New Countryside

Development (NNCD) project was expected to generate a variety of economic benefits to

Ningbo Municipality, particularly to the rural population in project areas. These benefits

included improvement of quality of soil and waterbodies, increases in productivity and

livelihood, increases in land and property values, improvements to health and living

standards, reduced cost of water treatment in poorer communities, improved long-term

security of drinking water sources, improved access to better public services and energy

savings and pollution reduction. The project would also bring about longer term benefits

in small town development and rural wastewater management in Ningbo and similar

regions through its small town development demonstration pilots, as well as energy

efficiency improvements.

2. While it was acknowledged at appraisal that the improvement of water supply

services and wastewater treatment services had significant long-term environmental and

health benefits, it was also difficult to quantify the causal link between the two.

Environmental and health benefits observed would ultimately be attributable to various

efforts, and not solely to the project. A cost effectiveness analysis was thus adopted for the

following components: (i) Rural Wastewater Management; (ii) Fenghua Coastal Water

Supply; (iii) Chunhu Town Wastewater Management. A cost-benefit analysis was used to

examine the economic feasibility of the Fenghua-Chunhu access road component.

3. The main economic costs for each component were identified as capital investments,

including associated resettlement and environmental mitigation costs of the investments

identified in the safeguards analysis, as well as O&M. It was assumed that market prices

for most elements would not vary much from their economic value, therefore market prices

were applied directly without conversion in most cases. Economic benefits and costs were

valued at the price levels of the base year 2008, net of inflation, duties and taxes. The

project duration would be 20 years, and different construction periods were used depending

on components. A discount rate of 8% was applied; this was the rate generally accepted by

the Chinese government for most of its projects.

Cost-Effectiveness Analysis

Rural Wastewater Component

4. The objective of this component was to improve wastewater management and the

environment by building wastewater collection and treatment systems in about 150 villages

in six counties/ districts of Ningbo Municipality. A cost-effectiveness analysis was

conducted in order to select the least-cost option, considering that the full benefits and costs

of implementing this component would be difficult to quantify or monetize. A design

Page 61: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

50

framework and guidelines for low-cost design were adopted for the first batch of villages,

and a program-based approach was adopted for the remaining batches of villages. The total

estimated investment for this component was US$47.96 million.

5. A survey was also carried out to gauge the willingness and ability of local residents

to pay for rural wastewater treatment. Results showed that 94% of the 401 respondents

were willing to participate in daily O&M of the project, and 70% were willing to pay a fee

for the wastewater treatment service. The average amount that rural households were

willing to pay for wastewater treatment was RMB 3.98/month. Based on the analysis of

projects in the first batch of villages, the annual O&M cost ranged from RMB 6.97/person

to RMB 38.5/person. Even at the higher end of the spectrum, the annual O&M cost

accounted to only about 0.34% of the average net income of rural residents of Ningbo

Municipality. NMG was committed to providing adequate income support to low-income

households under the government’s social protection program, in order to protect against

the project negatively affecting these households’ income levels

Fenghua Coastal Water Supply Component

6. The purpose of this component was to help overcome seasonal water shortages,

which were a constraint to local economic development in Chunhu town and nearby coastal

areas in southeastern Fenghua. Based on the projected water demand of the project area,

the component was projected to increase the area’s water supply capacity to 26,000m3 /

day by 2015, and 60,000 m3 / day by 2025. Two alternatives were considered in the cost-

effectiveness approach. The first was to convey water from the Fenghua City network to

three coastal towns and neighboring areas through the construction of pipelines and a

pumping station, and the second was to divert water from the Baixi Water Diversion Canal

through the construction of a water plant and pipelines to distribute water to the three

coastal towns and neighboring areas. The first option was found to be more cost-effective,

and was subsequently the option implemented in this component. The estimated total

investment for this component was US$15.73 million.

7. A willingness-to-pay survey was conducted for this component. It was found that

the average price that the survey respondents were willing to pay for water supply was

RMB 8.73/household per month. To achieve financial viability with an acceptable financial

internal rate of return of above 6%, it was noted at appraisal that a tariff of RMB 1.6/m3

for domestic water use was recommended. Given the average annual income of local

residents of over RMB 10,000 at appraisal, increasing the tariff from RMB 0.80/m3 (the

prevailing tariff at the time) to RMB 1.6/m3 was considered affordable for the majority of

local residents. Assuming an average consumption level of 100 liters/ day, the total annual

expense of a rural household on water usage would account for less than 1% of income.

Chunhu Wastewater Treatment Component

8. The Chunhu Wastewater Treatment component was intended to provide

wastewater collection and treatment services in Chunhu Town through the construction of

a WWTP and sewage networks for both domestic and industrial sources in the town. Based

Page 62: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

51

on the projected water demands and wastewater discharge in the project area, the

wastewater collection and treatment component was designed with a treatment capacity of

10,000m3/ day by 2015, 20,000m3/ day by 2025 and 40,000m3/ day by 2030. Two

alternatives in terms of wastewater treatment processes were considered in the cost-

effectiveness approach: the first was cyclic activated sludge technology and the second was

A/A/oxidation ditch. Option 2 was found to be more cost effective, and was applied to the

Chunhu Wastewater Treatment component. The estimated total investment at appraisal

was US$8.17 million.

9. An analysis of wastewater treatment affordability was carried out, based on

payment of O&M costs only, i.e., excluding capital costs for construction of the wastewater

treatment plant and pipelines. The analysis showed that O&M costs for wastewater

treatment would amount to RMB 0.69/m3. It was assumed that the charge levied on

domestic users would be low, given the cost distribution between industrial and domestic

uses and the commitment of the local government to rural development. With a tariff set

based on the O&M cost of RMB 0.69/m3, the total expense of a local household on

wastewater treatment would account for only about 0.02% of income.

Cost-Effectiveness at Completion

10. A simple comparison of indicators at appraisal and at completion was carried out

to assess efficiency, as shown in the table below. Across the board, investment costs were

higher than estimated at appraisal, largely because of exchange rate fluctuations. The

number of beneficiaries per RMB 10,000 of investment for the first two components was

lower on completion that at appraisal. For the rural wastewater component this was an

insignificant difference of 0.1 per RMB 10,000 in investment, but for the Fenghua Coastal

Water Supply the difference was 1.3 per RMB 10,000.

Table 3.1: Comparison of Indicators at Appraisal and Completion

Component/ Sub-Component PAD ICR

Rural Wastewater Component

No. of beneficiary villages 150 144

Beneficiary households (Target/ Actual) 41,000 45,500

Investment (Million RMB) 327.4 394.8

Beneficiary households per RMB 10,000

investment

1.3 1.2

Chunhu Town Infrastructure Development

Fenghua Coastal Water Supply

Water supply capacity (tons per day, 2015) 26,000 26,000

Beneficiary population (Target/ Actual) 76,000 76,500

Investment (Million RMB) 107.4 131

Beneficiary population per RMB 10,000

investment

7.1 5.8

Chunhu Town Wastewater Management

Water treatment capacity (tons per day, 2015) 10,000 6,000

Page 63: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

52

Wastewater Treatment Rate (Target/ Actual) 70% 84%

Investment (Million RMB) 55.5 59.6

11. Comparisons were also made with other projects as appropriate. For the rural

wastewater component, NNCDP costs were compared with those of NMG’s own, more

widespread project to provide rural wastewater services to more than 720,000 households

elsewhere in the Municipality. NNCDP provided rural wastewater infrastructure at an

average cost of 8,000CNY/household, while NMG’s own project did so at a significantly

higher cost of between 10,000 – 15,000CNY/ household. The Chunhu Town WWTP, with

a capacity of 10,000m3/day, was constructed at a total cost of 27.04 million CNY. In

comparison, a WWTP with half the capacity (5,000m3/day) constructed as part of the

Zhejiang Qiantang River Basin Small Town Environment Project was constructed at a cost

of 24.53 million CNY, a difference of less than 10%. Both plants were designed to meet

the same national Class 1B treatment standards. As construction methods and local

topographical conditions were unique to the NNCDP, a suitable comparison was not made

for the Fenghua Coastal Water Supply system.

Cost Benefit Analysis

Fenghua-Chunhu Access Road

12. The objective of this component was to improve road accessibility between

Fenghua City Center and Chunhu Town. The road would provide fast access between the

two areas by shortening the existing travel distance by approximately 10km, meeting the

demand for fast transportation in Chunhu Town by providing a quicker alternative

compared to the existing bypass roads. Benefits such as saved time and transport costs,

reduced traffic jams, less frequent traffic accidents and increased value of land close to the

road were included and calculated. Other benefits such as increased productivity, better

accessibility to public services in Fenghua, and reduced air pollution emissions, were not

included due to difficulties in quantifying such benefits.

13. Land value increase was factored into the analysis as it was believed that the

completion of the access road would increase the value of the undeveloped land along the

new road. The aggregated results of the analysis showed that the economic internal rate of

return (EIRR) of the road was 16.96%, and net present value (NPV) was RMB 450.89

million, including land value increase. Excluding land value increase, EIRR was 14.18%,

and NPV was RMB 331.04 million. The Benefit Cost Ratio (BCR) was 2.4 and 3.3

respectively.

14. Economic analysis carried out at the ICR stage showed that the EIRR is 16.7% and

NPV RMB 443 million including increased land value, and 13.7%/ RMB 319 million with

increase land value excluded. The BCR was 2.3 and 3.2 respectively, which is marginally

lower than the case presented at appraisal. Sensitivity analysis (assuming a 20% increase

in capital costs and 20% decrease in economic benefits) further showed that the access road

investment will provide an EIRR of 12.1% or 10.2%, with and without the increase in land

Page 64: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

53

value respectively. Despite the EIRR being lower at completion than at appraisal, it is still

significantly better than the 10% generally accepted by both the Bank and the Government.

Table 3.2: Sensitivity Analysis of Chunhu-Fenghua Access Road

Base Case

EIRR

20% increase in

capital

investment

20% decrease

in main

benefits

Combined

Case

Increased land

value included

16.7% 14.3% 14.0% 12.1%

Increased land

value excluded

13.7% 12.1% 11.9% 10.2%

The lower EIRR, NPV and BCR figures compared to the figures at appraisal can be

attributed to higher-than-planned actual investment, which, in turn is attributable to

exchange rate fluctuations and higher resettlement-related costs). The actual traffic flow

along the completed road was, however, found to be higher than the estimated figures

adopted during appraisal.

Financial Analysis

15. A project-level financial analysis was carried out at appraisal and at project

completion to ascertain the financial viability of the project during the implementation and

operation period.

Project Level Analysis

Rural Wastewater Component

16. The rural wastewater component was planned to be implemented on a cost sharing

basis, with Ningbo Municipality providing a capital grant of USD 40 million, including

USD 20 million of loan proceeds, and County and District Governments as well as Village

Committees contributing the remaining capital requirements. Communities were expected

to contribute some capital costs and all O&M costs. Upon completion of the rural

wastewater facilities, assets would be transferred to Village Communities, who would be

responsible for O&M. At appraisal, it was assessed that because appropriate technological

solutions would be adopted in this component – based on a community participation

approach – maintenance requirements and costs would be considered affordable to all

villages. In addition, maintenance tasks would be fairly straightforward and could be

carried out by trained village operators.

17. At project close, the majority of villages (96 out of 144) remained within the 18-

month handover period, meaning O&M had not yet been handed over to local Village

Committees or third-party management companies. Of the 48 villages with O&M handed

over, 10 villages had O&M managed by the local town government, while 38 had engaged

third-party providers. In line with the project’s focus on community participation as an

Page 65: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

54

essential element in ensuring project sustainability, each village has villagers who have

undergone training to be able to carry out simple, regular maintenance.

18. O&M funding policies were determined at the county level, with cost subsidies

determined in line with the socio-economic status of villages, as designed. In Fenghua and

Ninghai Counties, where approximately half of the villages were categorized as relatively

poor, 100% of O&M costs were covered by county governments. In Xiangshan, with 25%

of villages considered relatively poor, the county government funded O&M costs fully, but

villages were responsible for 30% of electricity charges and the cost of upgrading

equipment. In Yuyao, with around 3% of villages considered relatively poor and more than

half of villages relatively wealthy, the county covered O&M costs while villages were fully

responsible for electricity and equipment upgrading. A wastewater treatment tariff of

between 0.45 – 0.8 CNY/m3 has been introduced in 55 of the 144 villages, the majority of

which fall in the relatively wealthy category. The tariffs and subsidies in combination are

sufficient to cover the O&M costs.

Chunhu-Fenghua Access Road

19. The Chunhu-Fenghua access road was not designed as a toll road, so its

maintenance is carried out with city government support. Fenghua City is responsible for

providing annual budget appropriations to meet the O&M requirements, and make

payments to the management contractor that has assumed O&M responsibilities. In

addition, the City is also providing budgetary support for road resurfacing at least once

every eight to ten years.

Fenghua Coastal Water Supply

20. Similar to the Chunhu-Fenghua Access Road, Fenghua City has outsourced O&M

functions for this component to an external company, in this case, the Fenghua Xinyuan

Water Company. The company is responsible for operating and maintaining the pipes,

pumping stations and other assets under this component, as well as for collecting water

tariffs, which would be used to buy raw water and pay O&M fees. O&M fees included

salaries and welfare payments of staff and workers, power for pumping stations, chemicals

for further water treatment, maintenance and management fees.

21. At appraisal, the average water tariff in Chunhu Town was RMB 0.80/m3. To meet

the requirements of cost recovery as laid out in the Bank’s financial covenant for the project,

Fenghua City agreed to increase the average water tariff in Chunhu Town to RMB 2.00/m3

in 2013 (when transmission mains and distribution networks were planned for completion

and operation), with a further increase to RMB 2.50/m3 in 2018, when the second phase of

the overall coastal water supply network to serving Qiucun Town and Song’ao Town was

planned to be in place. The water tariff would increase 10% every three years thereafter,

and would be applied in Qiucun Town, Song’ao Town and Zhejiang Shipyard. Based on

these assumptions, the financial projections showed that O&M cost coverage would be

achieved in 2013, and that the debt service coverage ratio would be 1.10 in 2022.

Page 66: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

55

22. Table 3. 3 below reflects the population and water demand projections utilized by

the Fenghua Xinyuan Water Company. In comparison to the appraisal stage, demand

projections for the Hongsheng Haitang Development Zone have been lowered, reflecting

a more cautious outlook on the development of the economic zone. Similarly, the Zhejiang

Shipyard is also projected to have far lower demand for water compared to the current

scenario. Once a key enterprise in Ningbo, the shipyard has been affected by the global

slowdown in the shipping industry, and water demand is expected to fall in the medium

term. While the demand for water from industrial sources is lower than projected at the

appraisal stage, the Fenghua City government has introduced a Three-Year Action Plan,

which aims to build a water distribution network covering 51 villages around Chunhu

Town by 2018, thereby increasing the demand for water from the Fenghua Coastal Water

Supply. By the end of 2016, 27 villages will be covered by the distribution network.

Table 3.3: Population and Water Demand Projections

Town or

Development Zone

Population Water Demand(m3/day)

2006 2015 2025 2006 2015 2025

Chunhu Town 28,000 65,000 90,200 7,000 17,000 27,000

Hongsheng Haitang

Development Zone - 3,000 20,000 - 1,000 11,000

Qiucun Town 10,000 29,000 80,000 1,500 6,700 18,000

Song’ao Town 15,000 12,800 10,498 3,000 3,500 3,200

Zhejiang Shipyard - - - 5,000 12,000 2,500

Total 53,000 109,800 200,698 16,500 40,200 59,200

23. According to the new water tariff policy in place, a charge of RMB 2.05/m3 was

introduced in 2015, and will increase by 25% every three years beginning in 2018. This

was slightly higher than the tariff of RMB 2.00/m3 planned at project appraisal. The revised

financial projections for the Fenghua Coastal Water Supply are shown in the table below.

Financial performance is assessed to be slightly better at project closure than at the

appraisal stage, with the debt service coverage ratio in 2021 higher than calculated (1.31

as compared to 0.97).

Table 3.4: Financial Projections for Fenghua Coastal Water Supply (Unit: RMB 1,000)

Component/ Year 2016 2017 2018 2019 2020 2021

Water sold (1,000m3) 5,664 5,960 10,298 10,825 11,379 11,962

Water tariff (RMB/m3) 2.05 2.05 2.56 2.56 2.56 3.20

Increase in rate of tariff - - 25% - - 25%

Tariff collection rate 90% 90% 90% 90% 90% 90%

Revenue 10,450 10,996 23,750 24,966 26,244 34,484

Water purchase cost 4,867 5,275 9,569 10,361 11,217 12,760

O&M costs 3,140 3,284 5,485 5,749 6,028 6,452

VAT 612 644 1,393 1,464 1,539 1,861

Page 67: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

56

Interest 4,746 4,305 3,864 3,423 2,981 2,540

Principal Repayment 7,721 7,721 7,721 7,721 7,721 7,721

Depreciation 4,795 8,026 8,026 8,026 8,026 8,026

Financial Indicators

O&M cost coverage 1.21 1.19 1.44 1.42 1.40 1.64

Debt service coverage

ratio

0.15 0.15 0.63 0.66 0.70 1.31

Chunhu Wastewater Management

24. The management and operation of the assets created under the Chunhu Wastewater

Management component would be handed over to Fenghua City. Following completion of

construction and quality verification, Fenghua City outsourced O&M functions to a

competent company - in this case, the Chunhu WWTP Company. The cost of O&M is

being funded by wastewater tariffs and subsidies from Fenghua City, as the initial

wastewater tariff was acknowledged to be insufficient to cover the cost of O&M (which

included salaries and welfare payments of staff and workers, power, chemicals for

treatment, maintenance and management).

25. At appraisal, there was no wastewater tariff collected in Chunhu Town, as was the

case throughout rural China. Fenghua City agreed to begin levying wastewater treatment

tariffs using a “one bill, two tariffs” system, collecting wastewater charges together with

water supply charges. Fenghua City intended to begin charging a wastewater tariff that

covered only half of O&M costs in the first year (RMB 0.31/m3 in 2013), before increasing

the tariff to RMB 0.69/m3 to fully meet the O&M costs within three years. The tariff would

then increase 10% every three years. The financial projections for this component at

appraisal indicated that the cumulative income of the wastewater tariff over the project

lifespan would cover the full cost of operating the Chunhu Wastewater assets. O&M costs

would be fully covered in 2015, and the debt service coverage ratio would be 1.22 in 2024.

26. Revised financial projections for this component are found in the table below. The

current wastewater tariff is RMB 0.40/m3, RMB 0.29/m3 lower than what had been

proposed during appraisal. The projections indicate that O&M costs will only be fully

covered by tariffs in 2022, seven years later than foreseen at appraisal. The debt service

coverage ratio will exceed 1 in 2025, a year later than calculated at appraisal stage. While

the financial performance covenant for Chunhu Town to be able to cover O&M expenses

with wastewater tariff charges by end-2016 will not be met, the township is committed to

covering all subsidies as needed until such time that O&M cost recovery can be achieved.

Table 3.5: Financial Projections for Chunhu Wastewater Management (Unit: RMB 1,000)

Component/

Year

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Water

treated (per

1,000m3)

5,664 5,960 6,272 6,600 6,945 7,308 7,690 8,093 8,516 9,430

Page 68: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

57

Wastewater

tariff

(RMB/m3)

0.40 0.40 0.40 0.52 0.52 0.52 0.68 0.68 0.68 0.68

Increase in

rate of tariff

- - - 30% - - 30% - - 30%

Tariff

collection

rate

90% 90% 90% 90% 90% 90% 90% 90% 90% 90%

Revenue 2,039 2,146 2,258 3,089 3,250 3,420 4,679 4,924 5,181 7,459

O&M costs 3,454 3,557 3,664 3,774 3,887 4,004 4,124 4,248 4,375 4,506

Interest 1,738 1,565 1,391 1,217 1,044 870 761 718 674 631

Principal

Repayment

3,040 3,040 3,040 3,040 3,040 3,040 870 870 870 870

Depreciation 2,190 2,190 2,190 2,190 2,190 2,190 2,190 2,190 2,190 2,190 Financial Indicators

O&M cost

coverage

0.59 0.60 0.62 0.82 0.84 0.85 1.13 1.16 1.18 1.66

Debt service

coverage

ratio

-0.30 -0.31 -0.32 -0.16 -0.16 -0.15 0.25 0.31 0.37 1.35

Page 69: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

58

Annex 4. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Project Preparation

Greg J. Browder Lead Water Resource Management Specialist GWADR

Shenhua Wang Sr Urban Specialist GSURR

Zhentu Liu Senior Procurement Specialist GGODR

Yi Dong Senior Financial Management Specialist GGODR

A. D. C. Godavitarne Consultant GSURR

Chaogang Wang Senior Social Development Specialist GSURR

Chongwu Sun Senior Environmental Specialist GENDR

Fang Zhang Financial Management Specialist GGODR

Guangming Yan Senior Urban Development Specialist GSURR

Hongwei Zhao Program Assistant EACCF

Jun Zeng Senior Social Development Specialist GSURR

Ximing Zhang Senior Water Resources Specialist GWADR

Xuemei Guo Country Program Assistant EACPQ

Yuan Wang Procurement Specialist GGODR

Project Supervision/ICR

Ximing Zhang Senior Water Resources Specialist GWADR

Yuan Wang Procurement Specialist GGODR

Fang Zhang Financial Management Specialist GGODR

Chaogang Wang Senior Social Development Specialist GSURR

Chongwu Sun Senior Environmental Specialist GENDR

Sarah Xinyuan Lin Operations Analyst/ ICR Author GSURR

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY2008 8.46 60.30

FY2009 26.53 227.77

FY2010 10.70 100.82

Total: 45.69 388.88

Supervision/ICR

FY2010 1.00 5.14

FY2011 12.75 58.04

FY2012 13.07 77.91

FY2013 13.42 63.39

FY2014 10.18 45.85

FY2015 11.00 44.16

FY2016 13.00 51.28

FY2017 3.65 6.75

Total: 78.87 352.52

Page 70: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

59

Annex 5. Summary of Borrower's ICR and/or Comments on Draft ICR

Section 1: Project Context, Objectives and Design

Original Project Development Objective and Project Components

27. The original PDO was to “Improve rural wastewater management in selected

villages and enhance infrastructure and township management in a small town, in support

of the New Countryside Development (NCD) Program in Ningbo Municipality”.

28. The project includes the three components as follows:

Component 1: Rural Wastewater Management: Implementation of rural wastewater

management in about 150 selected villages in six Counties/ Cities/ Districts in Ningbo

Municipality using appropriate and sustainable technology and a program-based approach

in participation with village communities.

Component 2: Chunhu Town Infrastructure Development: Chunhu-Fenghua Access Road:

Construction of a four-lane Class I road connecting Fenghua City with Chunhu Town;

Fenghua Coast Water Supply: Construction of transmission mains from Fenghua City to

Chunhu Town; including renovation and expansion of the Chunhu Town water distribution

network; Chunhu Town Wastewater Management: Construction of trunk and collection

sewers and a wastewater treatment plant to serve Chunhu Town.

Component 3: Capacity Building and Implementation Support: Capacity Building and

Implementation Support for Rural Wastewater Management; Chunhu Town Capacity

Building and Energy-Efficiency Demonstration Support for preparation of the 12th Five-

Year Plan on NCD in Fenghua City; capacity Building and Implementation Support to

FCIC.

Section 2: Key Factors Affecting Implementation and Outcomes

Project Preparation, Design and Identification Quality

29. The Project Objective is the summary of all Components’ objectives:

Rural Wastewater Management: Its objective is to support Ningbo Government as

it improves rural sanitation and protects surface drinking water resources of Ningbo

Municipality. These goals could be accomplished by providing wastewater

collection and treatment facilities in rural communities, and by using technologies

that are appropriate, low-cost and easily maintainable by rural artisans.

Chunhu Town Infrastructure Development: Its objective is to improve the road

accessibility between Fenghua City Center and Chunhu Town, helping Chunhu

Town to overcome the seasonal water shortage; and, to provide wastewater

collection and treatment service in Chunhu Town by building a wastewater

Page 71: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

60

treatment plant and sewage networks for both domestic and industrial sources in

Chunhu Town.

Capacity Building and Implementation Support: Its target is to provide capacity-

building and implementation support for Rural Wastewater Management

Component implementation and FCIC; promote Chunhu Town capacity building

and energy-efficiency demonstration; and support for preparation of the 12th Five-

Year-Plan on NCD in Fenghua City.

30. Thus by realization of the design targets and the contents of three components, the

total target of the NNCD can be reached, that is to improve rural wastewater management

in selected villages and enhance infrastructure and township management in a small town,

in support of the New Countryside Development (NCD) Program in Ningbo Municipality.

31. Project Institutional and Implementation Support. A three-level project institution

was established in this project, with a Project Leading Group, chaired by the Vice Mayor

of the Municipality, providing policy direction and guidance for project implementation.

The Ningbo Municipal Project Management Office (NMPMO) has been designated by the

municipal-level PLG as the primary office for the preparation and implementation of the

proposed project. A sub-PMO, the Ningbo Rural Water Treatment Project Management

Office (NRWTPMO), was established to guide the implementation of the Rural

Wastewater Management component. NRWTPMO coordinated preparation of the first

batch of villages. County-level rural wastewater treatment PIUs are responsible for the

implementation of the Rural Wastewater Management component. A comprehensive TA

package (including facilitators) are provided to train the village communities and the

village operators. The FCIC is the PIU for the Chunhu Town Infrastructure Development

component and is responsible for the design and construction of the infrastructure, and the

servicing of debt using asset management fees that will be paid by Fenghua City.

32. All PIUs and sub-PMOs are well established with the requirements of Bank-

financed projects. PIUs and sub-PMOs had their own clear responsibilities and effective

institutions. Complete communication channels were made among all levels of PIUs and

sub-PMOs with government agencies, like monthly meetings were regularly held, to ensure

the contracts implementation. During the construction period, each party plays its own role

to finish the project target.

33. Foresight of the Bank’s Decision. The Rural Wastewater Management component

under NNCD is the first rural wastewater management project in China, which was

approved and started its construction in 2010. It is totally corresponded with the

background of the domestic largely promoted new countryside construction and the “Five

Water Works” Projects, thus it has the function of foresight and guidelines.

34. Flexibility in Procurement. Most of the contracts in the two components of NNCD

were NCB contracts, and most of them were in the Rural Wastewater Component. In the

early stage of the construction, according to the usual practices and experiences from Bank

financed projects, proper scale of one single contract was required, but the work amount of

each village was limited except for a large village, thus requires several village combined

Page 72: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

61

in one NCB contract (in most cases there should be 4 more villages). This caused some

troubles in bidding document preparation, as the issuing of bidding document required all

villages to be read for construction. Thus the beginning implementation of the Rural

Wastewater Management component was slow. When looking back, it is a main factor for

slow progress. As the construction moved forward, the PIUs became aware that it was not

necessary to maintain a proper scale of a NCB contract, flexibility was needed to accelerate

implementation. For villages ready for construction, they should be gathered to form a

contract and go into bidding procedure. This helped to quicken the procurement process.

35. Community Participation. A community participation mechanism was established

in this project. During the project preparation, community participation guidelines were

prepared to define the community participation measures in periods of project preparation,

implementation and operation.

36. First standardization of rural wastewater discharge. Before the implementation of

the NNCD, there was no technical standard and discharge standard for rural wastewater in

China. Existing technical measurements recommended are too high for rural wastewater

discharge, and the project would not conform to requirements for economic efficiency if

subject to these standards. Based on this, the NRWTPMO applied for approval from the

Ningbo EPB for an additional standard for rural wastewater discharge in May 2009. With

sound preparation of information submitted to the EPB for consideration, the Rural

Wastewater Discharge Standard was officially issued by Ningbo EPB and formed the

foundation of design works. This standard was also accepted by Zhejiang Provincial EPB,

and based on it, a provincial level standard DB33/973-2015 “Water Pollutants Discharge

Standards for Rural Sewage Treatment Facilities” was prepared and issued on July 1, 2015.

Bank’s Safeguard Policy

37. Environment Management. Environmental Assessment was triggered and the

project was classified as Category B. A comprehensive EIA was conducted during project

preparation stage, analyzing and evaluating the negative environmental impact from the

project and benefits after completion. An Environmental Management Plan (EMP) was

prepared to mitigate against the negative impacts identified. In general, the EMP was

comprehensive and detailed, providing practical monitoring standards and an effective and

reasonable communication and reporting mechanism.

38. Involuntary Resettlement and Land Acquisition. Efforts have been made to

minimize resettlement impacts during project planning and design. However, some

resettlement impact cannot be avoided. Final results were: land acquisition of 270.67mu,

5.61mu more than planned; demolition areas totaled 7647.62m2, which was 4.168.62 m2

more than the planned 3,479 m2. Sophisticated and effective fund management systems in

PIUs were in place for appropriation and payment of resettlement funds. The disbursement

procedure was transparent, clear and effective. Resettlement funds were paid to affected

persons in time. During construction, no appeals were received on the grievance redress

system.

Page 73: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

62

39. Safety of Dams. Safety of Dams was triggered because the Hengshan Reservoir is

the main water source for Qiujiushan Water Works, which provided water for the proposed

Fenghua Coastal Water Supply component. The Ningbo Water Conservation Bureau

implemented the required strengthening and renovation works.

Main Reasons of Success and Failure during Project Implementation

40. Long design duration and frequent variations. The isolated location of villages and

large coverage areas, and designers’ lack of experience in rural wastewater treatment,

resulted in a long 4-month period for the design work of each batch. Insufficient survey

work also resulted in frequent design variations during construction. As designers also did

not communicate sufficiently with villagers, villagers were not satisfied with the initial

design work, leading to even more design variations. Faced with these challenges, changes

were made. These included the combination of survey/ measurement and design work, and

the requirement that villagers’ opinions be sought in the preliminary design stage.

NRWTPMO strengthened the supervision and management of design institutes.

41. Lack of standards and regulations for the project design. There were no standards

for rural wastewater discharge. NRWTPMO successfully sought approval from the Ningbo

EPB to establish a new set of standards for rural wastewater discharge.

42. Trouble in village selection, lack of participation and support from villagers.

Insufficient dissemination of information and awareness of the project benefits led to a low

participation rate in early stages of village selection. The dissemination of information in

brochures and in cartoon form helped to raise awareness of the project and its benefits,

which helped to increase the participation of villages.

43. Slow procurement process in the early stage. Procurement for one contract often

lasted 3 months in the early stage of project implementation. Ningbo PMO strengthened

the review process of bidding documents and design papers, and provided training to PIUs.

Revisions to the procurement plan were also made, with the contract scale for villages in

batches 4 and 5 not required to be as large as in earlier batches.

Other Significant Measures Taken

44. Significant Support from WB and Borrower. To strengthen the capacity of PIUs,

leaders from Ningbo PMO proactively took measures to enhance supervision. World Bank

also provided strong support in project management, procurement, financial management,

technical and contract management through intensive training seminars. These improved

the capacity of Ningbo PMO, NRWTPMO and all PIUs.

45. Enhance regulation and institutional development. Recommended by the World

Bank, the Ningbo PMO, NRWTPMO and all PIUs came up with consolidated regulations

to form the basis of project management. These included “Contract Variation Rules for

Rural Wastewater Treatment Facilities for World Bank Project in Ningbo Municipality”,

“Final Acceptance Test Rules for Rural Wastewater Treatment Facilities for World Bank

Page 74: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

63

Project in Ningbo Municipality” and “Operation and Maintenance Management Rules for

Rural Wastewater Treatment Facilities for World Bank Project in Ningbo Municipality”.

Section 3: Project Results Assessment

46. The project design and implementation are fully in compliance with the PDO.

Although the project experienced slow implementation in early stages, the results achieved

were in line with the PDO. The results indicators are evaluated as follows, and the overall

project assessment result is considered Satisfactory.

KPI 0.1: Number of households with appropriate wastewater management

service in project area; the target value is 41,000, actual figure achieved was

45,000, which is 10.96% higher.

KPI 0.2: Fenghua-Chunhu traffic using new access road (car equivalent);

The target value is 13,000 in 2016; at project close the car equivalent will

be 13,933, which exceeds the target by 7.18%.

KPI 0.3: Chunhu population served from a reliable and higher-quality water

supply; the target value is 76,000; the actual value achieved is 76,500.

KPI 0.4: Wastewater treatment rate in Chunhu Town; the rate achieved was

84% compared to the target of 70%.

KPI 0.5: Adoption of energy efficiency guidelines by NMG; completed.

KPI 0.6: Proposal for NCD plan for upcoming 12th Five Year Plan (2011-

2015) for Chunhu Town; completed.

47. The actual project investments (US$170.33m) exceeded the planned investment

(US$157.09m) by 8.4%. The main reason for this was the change in the USD exchange

rate, from 6.827 during project appraisal to 6.4927 during project implementation, an

increase of approximately 5%.

48. Economic Analysis. The economic benefits by component are described below:

Rural Wastewater Component: Benefits mainly include i) improvements to

the health and quality of life of local populations; ii) improvements to the

water system and quality of soil; iii) decreased water treatment costs in

lower reach communities; (iv) protection of water environment and

improved long-term security of drinking water sources in Ningbo.

Chunhu Access Road Component: Economic analysis shows that the ERR

is 11.25% excluding the increase in value of land.

Chunhu Wastewater Treatment Component: At present the treatment

capacity of the Chunhu WWTP is 6,000 cubic meters per day.

Fenghua Coastal Water Supply Component: although the economic benefits

of water supply and wastewater management components cannot be directly

calculated, it has a significant impact on improving the health of the general

population, improving quality of life and production efficiency.

Page 75: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

64

49. Financial Analysis. In the initial stages, all sub-components will rely on

government support from general budgets for capital and operational costs. Given FCIC’s

experience in project management and operations experience, together with the training

provided to strengthen the capacity of FCIC in business planning, asset management and

risk analysis, it is taken as guaranteed that it can achieve the objective of cost recovery. It

is expected that both Ningbo and Fenghua governments can manage the counterpart

financing and loan repayment amounts required.

Overall Assessment of Project Achievements

50. All three components of the NNCD have been achieved. The project has also

provided training to a batch of project implementation personnel who will be able to

provide good management and guidance for other infrastructure projects in future. The

environment of villages in the rural wastewater component have been greatly improved. In

addition, by the end of 2016, it is estimated that Ningbo City will invest CNY 7 billion in

completing decentralized wastewater treatment projects for about 1,469 villages,

benefitting 720,000 households.

Section 4: Assessment of Risk to Development Outcome

51. For the Rural Wastewater Management component, the risk rating is considered

low. The sustainable development of O&M is guaranteed with the commitments in policy,

administration, technology and funding. The involvement of villagers to participate in

O&M works will ensure project sustainability. The project also applied affordable, low-

maintenance wastewater treatment technologies and adopted solutions suited to each

context.

52. The risk rating is negligible for the Chunhu Town Infrastructure Component.

Fenghua and Ningbo governments have ensured that there is sufficient funding to support

O&M of the different sub-components, aside from the tariffs that have been introduced.

Section 5: Assessment of Bank and Borrower Performance

Bank Performance

53. In the project preparation and implementation stages, World Bank provided great

support and guidance. Leaders in NMG, PMO, sub-PMOs and PIUs feel that the

performance of the Bank has been highly satisfactory. The adoption of a program-based

approach, the promotion of a new discharge standard for rural wastewater treatment,

flexible procurement, strong technical support and enhanced guidance and monitoring to

solve issues were specific areas that the Bank performed well.

Borrower Performance

54. To ensure project preparation and implementation quality, NMG, PMOs, sub-

PMOs and PIUs all made strong contributions. All departments cooperated proactively

Page 76: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

65

with the World Bank and provided the necessary resources to ensure project success. The

NMPMO in particular played a significant role in institutional coordination, organizing

trainings and monthly meetings to monitor project progress and pro-actively identify

problems. They were the main communication bridge between the World Bank and other

implementing agencies.

55. Strong government support was also provided in terms of land acquisition, house

demolition and resettlement. NRWTPMO and PIUs in different counties were the first

implementation agencies in China to carry out a rural wastewater treatment project. The

agencies put in significant effort to develop their capabilities in implementing such a

project.

Section 6: Experience and Lessons

Lessons

56. Keep team stable. During the 7-year period from project preparation to project close,

the team has witnessed one variation of WB Task Team Leader, three changes in PMO

Project Manager and frequent staff variations at the PIU level, which has led to difficulties

in project implementation. Although the progress has caught up and obtained “Twin

Satisfactory” ratings, due to extensive training provided by the WB and significant effort

put in by the PMO and all PIUs, the stability of the team should be emphasized as an

important factor in ensuring that technical competencies are retained, and that the project

can proceed smoothly.

57. Enhance knowledge of World Bank processes. A lack of familiarity with certain

WB processes led to initial project delays. Ensuring that the implementing agencies have

capabilities in terms of procurement processes is essential. Training in such areas should

be provided before the bidding process begins, so that both bidding firms and implementing

agencies are familiar with Bank processes.

58. Enhance O&M management. Apart from maintaining infrastructure, O&M should

also focus on the following aspects. Firstly, ensure the surrounding environment is also

well-maintained. Secondly, the inflow quantity needs to be monitored such that the

intended treatment capacity is not exceeded. Health education should also be carried out to

raise awareness among villagers in aspects such as environmental and water pollution.

Effort should also be made to monitor the management of O&M by external companies

and village committees.

Page 77: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

66

Annex 6. Comments of Cofinanciers and Other Partners/ Stakeholders

Not applicable.

Page 78: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

67

Annex 7. Social Safeguards

1. Social Safeguards. Efforts were made to minimize resettlement impacts during

project planning and design. A Resettlement Action Plan (RAP) was prepared for the

Chunhu town infrastructure development component (in both English and Chinese), while

a Resettlement Policy Framework (RPF) was prepared for the rural wastewater component.

As a linkage issue was identified in the Fenghua coastal water supply component, a

retroactive resettlement review was also prepared as an annex to the RAP. All resettlement

preparations were made in compliance with OP 4.12: Involuntary Resettlement, as well as

the relevant domestic laws and regulations. The RAP in Chinese was disclosed through

local media on July 21, 2009 and was made available at the NMPMO, PIUs, public libraries

and on websites. The RAP in English was disclosed through InfoShop on July 21, 2009.

2. Resettlement Post-Evaluation Report. A Resettlement Post-Evaluation Report was

prepared by external monitors – the National Research Center for Resettlement (NRCR) –

after the project had closed. The report was based on both desk work and fieldwork, and

included focus group discussions with affected households, a follow-up survey with 20

sample households as well as interviews with key agencies involved in the implementation

and monitoring of resettlement processes. The report found that all requirements in terms

of the Bank’s social safeguards policy as well as the RAP had been well met. Adverse

impacts of land acquisition and demolitions of houses on affected persons’ incomes and

livelihoods had been mitigated against, and all property losses were adequately

compensated. The resettlement of affected persons had proceeded smoothly, and

improvements in their living conditions were noted.

3. Institutional Arrangements. The Fenghua City Investment Company Ltd. (FCIC),

as the PIU for the Chunhu Town Infrastructure Development component, was primarily

responsible for the implementation of the RAP, including supervision, management and

coordination of resettlement activities. FCIC established two separate offices to oversee

different aspects of resettlement – the Fenghua Tongyi Land Acquisition office

implemented land acquisition activities, while the Fenghua House Demolition office

implemented those relating to demolition of houses. The Fenghua PMO, working closely

with the FCIC, was responsible for monitoring overall progress, preparing M&E reports

and reporting results to the overall project implementing agency – the Ningbo Municipal

Project Management Office – as well as the Bank task team. Resettlement training

activities were also carried out to improve the capacity of local staff in the resettlement

agencies. The NRCR had also been appointed by FCIC to conduct regular reviews of

progress on resettlement, and provided a total of three external monitoring reports between

August 2010 and August 2012.

4. Land Acquisition and Resettlement Results. Land acquisition and resettlement

activities for all three subcomponents were conducted in a timely manner, in accordance

with the actual project construction schedule. In terms of land acquisition numbers, actual

figures for permanent acquisition and demolition of houses were higher than planned, as

shown in Table 8.1 below. A total of 325mu of land was acquired, as compared to the 262

mu planned. Demolition of houses was double the planned amount, totaling 7,647m2 as

Page 79: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

68

compared to 3,479 m2. The differences in these figures are attributed to additional land

acquisition and demolition of houses in the Chunhu Access Road component. Land

originally thought to only require temporary land occupation had to be acquired, as it was

unusable on its own when adjacent land had also undergone acquisition. As resettlement

and acquisition of the additional land was carried out in accordance with policies in the

RAP, it was considered acceptable and reasonable. The actual amount of land occupied

temporarily was 35.15mu, which was 119.39mu less than the 154.54mu planned.

Table 7.1: Comparison of Planned and Actual Resettlement Impact

Component Permanent Land

Acquisition (mu)

Demolition of

Houses (m2)

Temporary Land

Occupation (mu)

Planned Actual Planned Actual Planned Actual

1. Fenghua-Chunhu

Access Road

208.3 260.9 3,027 7,647.6 0 8

2. Fenghua Coastal

Water Supply

6.8 13.97 - - 111.5 8.8

3. Chunhu Town

Wastewater

Management

49.96 50.7 452 0 42.9 18.3

Total 265.06 325.63 3,479 7,647.6 154.5 35.1

5. Given the increases in land acquisition and demolition of houses, the associated

costs have correspondingly increased, totaling CNY 99.35million, a 34% increase over the

planned cost of CNY74.03 million. As the largest increase in land acquisition and

demolition of houses was attributed to the Chunhu-Fenghua Access Road component, costs

for this component also saw the largest increase, from CNY 60.81million to CNY

84.01million, a difference of 40%. The Fenghua coastal water supply acquisition and

housing demolition costs saw an increase of just over CNY 3 million.

Table 7.2: Comparison of Planned and Actual Resettlement Costs

Component Permanent Land

Acquisition (CNY million)

Planned Actual

1. Fenghua-Chunhu

Access Road

60.81 84.01

2. Fenghua Coastal

Water Supply

5.21 8.34

3. Chunhu Town

Wastewater

Management

8.01 6.99

Total 74.03 99.35

6. Impacts. No adverse impacts on persons affected by the project were found. A

transparent grievance redress channel was established during the planning and

Page 80: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

69

implementation of each of the three subcomponents, and these were publicized to affected

persons using local channels such as newspapers and through focus group discussions. No

appeals were received through the grievance redress systems. In addition, a sample survey

of 20 affected households conducted as part of the post-evaluation report also found that

44% were very satisfied with present living conditions, and 50% were somewhat satisfied.

None of the households surveyed felt that their lawful rights and interests had been

infringed on. Some 72% of those surveyed indicated that they had been made aware of

acquisition through meetings or publicity materials distributed by Village Committees,

indicating that there had been effective disclosure of information.

Table 7.3: Comparison of Planned and Actual PAPs

Component PAPs (Households) PAPs (Individuals)

Planned Actual Planned Actual

1. Fenghua-Chunhu

Access Road

70 114 201 355

2. Fenghua Coastal

Water Supply

10 11 29 32

3. Chunhu Town

Wastewater

Management

15 20 57 63

Total 95 145 287 450

7. Key Lessons. The post-evaluation report also noted key lessons to be drawn from

the NNCD project, as follows:

a) A sound organizational structure is essential for successful implementation

of resettlement activities, with clearly-defined responsibilities to ensure that

all the necessary actions are carried out in line with the RAP.

b) Resettlement policies and activities should be communicated clearly and

extensively to affected communities.

c) Frequent internal supervision and external M&E are critical in ensuring that

any issues encountered are addressed in a timely manner.

d) A clear and accessible grievance redress channel should be established to

facilitate communication with affected persons.

Page 81: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

70

Annex 8. List of Supporting Documents

1) Project Concept Note

2) Project Appraisal Document (Report No. 48663-CN)

3) Loan Agreement and Project Agreement

4) Aide Memoires

5) Implementation Status Reports

6) Environmental and Social Safeguards Documents (Environmental Impact

Assessment, Social Assessment Report, Resettlement Policy Framework and

Resettlement Action Plan)

7) Resettlement Post-Evaluation Report

8) Community Participation Post-Evaluation Report

9) Ningbo Municipal Government Operation & Maintenance Rules for Rural

Wastewater Treatment

10) Borrower’s ICR and Annexes

Page 82: Document of The World Bankdocuments.worldbank.org/curated/en/...FYP Five-Year Plan GEF Global Environment Facility HH Households ... NRWTPMO Ningbo Rural Wastewater Treatment Project

71

Annex 9. Map