document of the world bankdocuments.worldbank.org/curated/en/... · document of the world bank...
TRANSCRIPT
Document of
The World Bank
Report No: NCO00003051
NOTE ON CANCELLED OPERATION REPORT
(IDA-48390; IDA-H6340)
ON A CREDIT
IN THE AMOUNT OF SDR1.6 MILLION
(US$2.5 MILLION EQUIVALENT)
AND ON A GRANT
IN THE AMOUNT OF SDR1.6 MILLION
(US$2.5 MILLION EQUIVALENT)
TO THE
KINGDOM OF CAMBODIA
FOR AN
AGRIBUSINESS ACCESS TO FINANCE PROJECT
December 22, 2014
Agriculture Global Practice
Southeast Asia Country Management Unit
East Asia and Pacific Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CAMBODIA – GOVERNMENT FISCAL YEAR
January 1 – December 31
CURRENCY EQUIVALENTS
(Exchange Rate Effective as of December 15, 2014)
Currency Unit = Cambodia Riel (KHR)
KHR 1.00 = US$ 0.00025
US$ 1.00 = SDR0.68
ABBREVIATIONS AND ACRONYMS
ANZ Australia and New Zealand Banking Group Limited
CEO Chief Executive Officer
ESOM Environmental and Social Operations Manual
FI Financial Intermediary
FSAP Financial Sector Assessment Program
GDP Gross Domestic Product
IDA International Development Association
IFC International Finance Corporation
ISR Implementation Status and Results Report
M&E Monitoring and Evaluation
MFI Micro Finance institutions
NCO Note on Cancelled Operation
PAD Project Appraisal Document
PDO Project Development Objective
PFI Participating Financial Intermediary
PO Portfolio Officer
RGC Royal Government of Cambodia
RM Relationship Manager
RSA Risk Sharing Agreement
RSF Risk Sharing Facility
SDR Special Drawing Rights
SEMS Social and Environmental Management System
SME Small and Medium Enterprise
TA Technical Assistance
TTL Task Team Leader
WBG World Bank Group
Vice President:
Country Director:
Country Manager:
Global Practice Senior Director:
Global Practice Director:
Practice Manager:
Project Team Leader:
NCO Team Leader :
Mr. Axel van Trotsenburg, EAPVP
Mr. Ulrich Zachau, EACTF
Mr. Alassane Sow, EACSF
Mr. Juergen Voegele, GFADR
Ms. Ethel Sennhauser, GFADR
Mr. Nathan M. Belete, GFADR
Mr. Paavo Eliste, GFADR
Mr. Paavo Eliste, GFADR
KINGDOM OF CAMBODIA
Agribusiness Access to Finance Project
CONTENTS
Data Sheet:
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Ratings of Program Performance in ISRs
Section 1. Context, Project Development Objectives, and Design ................................. 1
Section 2: Key Factors Affecting Implementation and Outcomes. ................................ 3 Section 3. Project Implementation and Reasons for Cancellation .................................. 5
Section 4. Assessment of World Bank Group and Borrower Performance .................... 8 Section 5. Lessons Learned ........................................................................................... 10
Annex 1. Bank Lending and Implementation Support/Supervision Processes ............. 12 Annex 2. List of Supporting Documents ...................................................................... 14
MAP No. IBRD 33381R…………………………………………………….………...15
A. Basic Information
Country: Cambodia Project Name:
Cambodia Agribusiness
Access to Finance
Project
Project ID: P121809 L/C/TF Number(s): IDA-48390,IDA-H6340
NCO Date: 12/21/2014
Lending Instrument: Financial Intermediary
Loan (FIL) Borrower:
ROYAL
GOVERNMENT OF
CAMBODIA
Original Total
Commitment: XDR 3.20M Disbursed Amount: XDR 0.13M
Revised Amount: XDR 0.13M
Environmental Category: Financial Intermediary
Implementing Agencies: International Finance Corporation (IFC)
Co-financiers and Other External Partners: N/A
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 05/19/2010 Effectiveness: 05/12/2011 05/05/2011
Appraisal: 09/29/2010 Closing: 12/31/2018 06/26/2014
Approval: 12/16/2010
C. Ratings Summary
Performance Rating by NCO
Outcomes: Not Applicable
Risk to Development Outcome: Not Applicable
Bank Performance: Moderately Satisfactory
IFC Performance Moderately Satisfactory
PFI Performance Moderately Unsatisfactory
Borrower Performance: Moderately Satisfactory
D. Sector and Theme Codes
Original
Sector Code (as % of total Bank financing)
Agro-industry, marketing, and trade 50
Microfinance 25
SME Finance 25
Theme Code (as % of total Bank financing)
Micro, Small and Medium Enterprise support 50
Rural markets 50
E. Bank Staff
Positions At NCO At Approval
Vice President: Axel van Trotsenburg James W. Adams
Country Director: Ulrich Zachau Annette Dixon
Sector/Practice Manager: Nathan Belete Jeeva A. Perumalpillai-Essex
Project Team Leader: Paavo Eliste Paavo Eliste
NCO Team Leader: Paavo Eliste
F. Ratings of Project Performance in ISRs
No. Date ISR
Archived DO IP
Actual
Disbursements 1
(USD millions)
1 08/09/2011 Satisfactory Satisfactory 3.00
2 09/04/2012 Moderately
Unsatisfactory
Moderately
Unsatisfactory 3.00
3 03/20/2013 Unsatisfactory Unsatisfactory 3.00
4 10/22/2013 Unsatisfactory Unsatisfactory 3.22
1 These figures are before IFC refunded IDA. Actual net disbursements amounted to
XDR 0.13 million.
1
Section 1. Context, Project Development Objectives, and Design
1. Context. Cambodia’s economy experienced significant growth throughout the
2000s and showed resilience against external shocks during the 2008/09 economic and
financial crisis when overall GDP contracted. The agriculture sector emerged in the late
2000s as one of the key drivers of the country’s economic growth, driven primarily by the
crop sector where paddy production made up about one-fourth of the sector’s value-added.
Paddy production reached 7.3 million tons in 2009, up from 4.2 million tons in 2001, with
estimated domestic surplus of around 3 million tons. It was estimated that about 2 million
tons of paddy moved to Vietnam and Thailand through informal border trade in 2009,
where it was milled and exported to international markets. Formally processed (milled)
rice exports from Cambodia reached about 12,613 tons in 2009, up from about 2,000 tons
in 2004.
2. The sector’s performance contributed to the growth of agribusiness enterprises as
more raw materials became available for trading and value-added processing. However,
the value-addition of agriculture remained limited compared to that of neighboring
countries. This was because Cambodia’s agribusiness sector, where most of the value
addition occurred, remained largely traditional in nature. Limited access to finance was
one of the main constraints to the development of a modern, internationally competitive
agro-processing industry, which could utilize the agricultural potential of the country.
3. In 2010, the Royal Government of Cambodia (RGC) prepared a policy on the
promotion of paddy production and rice exports, with the objective of reaching a goal of 1
million tons of milled rice formally exported by 2015. A key policy action called for the
establishment of a credit guarantee scheme to encourage commercial bank lending to the
rice sector. Subsequently, RGC requested IDA and IFC support in 2010 to establish such a
financial instrument.
4. Rationale of the Operation. The rationale for the joint IDA/IFC involvement
through a credit guarantee scheme was two-fold. First, the Cambodian economy was
dominated by small and medium enterprises (SMEs) and micro businesses, numbering
about 55,000 in 2007. Agriculture and agribusiness SMEs made up about one-third of all
these SMEs. They were significant contributors to rural employment and local economic
growth. However, most of these firms were largely informal with limited access to
finance, limiting their future growth potential. Second, despite Cambodia’s banking
system having excess liquidity in 2009 and 2010 lending to the agribusiness sector was
limited given the perception that it was riskier and/or less profitable than other sectors.
Due to this perceived risk, banks were charging high lending rates, attaining margins of up
to 6percent on their agribusiness portfolio. Consequently, the economic development
potential of this segment of the economy remained largely untapped. There was thus a
strong justification for creating a financial instrument allowing the banks to hedge against
loan losses emanating from this sector to unlock part of this excess liquidity by lending to
agribusinesses, which otherwise would have continued to face difficulties in accessing
loans from banks.
2
5. PDO and Key Performance Indicators. The project development objective
(PDO) was “to increase the sustainable flow of credit to agribusinesses sector.” The
PDO Outcome Indicators were: increased number and value of loans disbursed to
agribusiness SMEs by participating financial institutions (PFIs) on market-based terms.
The PDO and results framework were not changed during implementation.
6. Target groups. The primary project target groups were agribusiness enterprises in
Cambodia where activities ranged from trading, storing, processing, packaging, exporting
and providing related logistical support. The majority of these enterprises participated in
rice value chains (as processors/millers, traders, distributors, input dealers, etc.). The
secondary project target groups were the eligible Participating Financial Intermediaries
(PFI) that would provide credit. The facility was to help them build agribusiness portfolios
and a broader client base and to improve their understanding of the risks involved in
lending to the sector.
7. Project Components. The project had one component, the Risk Sharing Facility
(RSF), which was to provide a partial credit guarantee to cover 50percent of losses of a
portfolio of new agribusiness loans by PFIs. It comprised an US$5 million first loss
coverage provided by the RGC through IDA financing, and a second loss of US$20
million of IFC financing. It was expected that US$5 million IDA financing would
leverage up to US$50 million of commercial bank lending to the agribusiness sector. The
RSF structure would have reimbursed the PFIs for a fixed percentage (50percent) of
incurred loan losses. The PFIs had a three-year ramp-up period during which agribusiness
loans could be brought under the coverage of the guarantee facility. The project was a
pilot under Phase II of IDA/IFC Pilot Program for Risk Sharing Facilities (RSF). The
design of the RSF followed thus the general structure of the previous pilots. The project
was designed as a stand-alone RSF, which was embedded in a wider IFC Advisory
Services (AS) programs in Cambodia. The project component was not changed during
implementation.
8. The facility was open to all eligible FIs that met the project selection criteria. The
RGC, IDA and IFC closely consulted on the selection of PFIs. During project preparation,
IFC worked with a number of FIs in Cambodia for whom it has carried out preliminary
checks and who were expected to meet basic eligibility criteria for the project. Some of
these banks had expressed initial interest to participate in the RSF, out of which one bank
(ANZ Royal) completed IFC’s investment review. This bank was the first to identify a
viable pipeline of loan applications for transactions that could be approved following
IFC’s Board approval and signing of the Risk Sharing Agreement with IFC. In parallel,
IFC sought interest from additional FIs to participate in the facility. It was envisaged that
the RGC, IDA and IFC would carry out a comprehensive performance review of the PFIs’
loan portfolio and utilization of the facility 18 months after project effectiveness.
3
Section 2: Key Factors Affecting Implementation and Outcomes.
Project Preparation, Design and Quality at Entry.
9. Soundness of Background Analysis. While no specific analytical study was
carried out to inform the preparation of this RSF, the available sectoral analytical evidence
at the time of the project preparation provided sufficient information to guide the project
design. For example, an IFC survey of SMEs from 2009 showed that about 90 percent of
agribusiness SMEs in Cambodia had identified lack of access to finance as their major
constraint for growth, compared to only two-thirds of manufacturing and service sector
SMEs2. The study showed that agribusiness firms needed both large amounts of working
capital to purchase raw materials during harvest times, and term capital to upgrade or
expand their processing equipment. For example, while agribusiness SMEs made up
about one-third of all SMEs in Cambodia, their financing needs were about half of the
total financing demand of all SMEs. Another survey of 124 agribusinesses in Cambodia
in 2009/10, (less than 1percent of all agribusiness SMEs in Cambodia), showed that their
demand for bank finance was about US$26 million, or about US$215,000 per enterprise,
of which about two-thirds was needed for long-term loans3.
10. Assessment of Project Design. The choice of RSF was considered an appropriate
financial instrument during project preparation, given the liquidity of Cambodia’s
financial sector in 2009 and 2010 and the availability of funds for lending was not
considered a constraint. At that time, some 36percent of banking assets were in the form
of cash and quasi-cash assets, which earned little return. Most banks were also adequately
capitalized, with regulatory capital levels at around 28 percent of total assets in 2008;
therefore, there was sufficient capital available within the financial sector to fund
investments in agriculture, agro-industry and SMEs in general. Yet, commercial bank
lending to agriculture was only about US$130 million in 2008, representing about 5
percent of all lending, while the lending to the agribusiness sector, which was classified as
manufacturing, was about US$80-110 million or about 3-4percent of total lending. The
reason for such limited lending, despite of liquidity situation in the banking sector, was
perceived low profitability of agribusiness enterprises, lack of information about potential
borrowers, and resulting high risk perception about the sector. The purpose of the RSF
was to unlock commercial bank lending to agribusinesses by providing them the credit
protection needed to cover their potential losses (if occurred) and, therefore, to mitigate
the perceived high risk of agribusiness lending.
11. Environmental and Social Safeguards. The project was classified as Category
FI. The project triggered OP/BP 4.01 on Environmental Assessment, OP/BP 4.10 on
Indigenous Peoples and OP/BP 4.12 on Involuntary Resettlement. It was anticipated that
the majority of transactions covered by the RSF would have environmental or social risks
2 IFC. Understanding the SME Sector in Cambodia and Their Need for Financial Services and Products.
2010 3 JICA. The Preparatory Survey on the SMR Two-Step Loan Project in Kingdom of Cambodia. March, 2010
4
that would be readily identified and addressed by the application of IFC Performance
Standards and World Bank Group Environmental Health and Safety Guidelines. As a
condition of joining the RSF, each new PFI would be required to prepare a Social and
Environmental Management System (SEMS) to guide them in identifying, assessing and
managing environmental and social risks associated with loan applications. The
formulation of SEMS would need to be acceptable to IFC and IDA based on the
framework presented in the Environmental and Social Operations Manual (ESOM). The
IFC would work with the PFI to determine if any new PFI’s SEMS would meet criteria in
the ESOM. The draft ESOM was disclosed to the Infoshop and in the Cambodian Public
Information Center on September 3, 2010. The final ESOM was disclosed at both
locations on November 1, 2010.
12. Implementation Arrangements. According to the design, the RGC was the
recipient of the IDA credit/grant funds while IFC was the implementing agency on behalf
of RGC. IDA funds to cover RGC’s ‘first loss’ portion of funds were transferred, on
behalf of the RGC, to a Trust Fund account which was administered by IFC. IFC, in its
capacity as facility agent, was responsible for all operational aspects of the management
of the Trust Fund and RSF, and acted as a liaison between PFIs and the RGC during
project design and implementation. Its operational responsibilities included identification
of qualified PFIs and carrying out their due diligence; signing a risk-sharing facility
agreement with selected PFIs; assessment of project performance and compliance with
applicable fiduciary policies; verification of loan losses and payment of eligible losses;
and monitoring and evaluation (M&E) of the results. Given the confidentiality of the
business relationship between IFC and PFIs, IFC was solely responsible for its
interactions with PFIs and provided IDA/RGC necessary information for M&E purposes.
13. Assessment of Risks. The overall risk rating at entry was “moderate” which seem
to be inadequate in retrospect. The main challenge during the preparation was to find
enough qualified PFIs that would be willing to participate in the RSF. This issue was
identified also as the main risk for the project and was rated “moderate”. IFC had been
working with a number of financial institutions in Cambodia for whom it had carried out
due diligence and who were expected to meet basic eligibility criteria for the project. The
RGC and IDA expressed its concern over going ahead with only one PFI, and IFC agreed
to make best efforts to bring at least one or two additional FIs under the guarantee facility
during the 18 month period following project effectiveness.
14. Another key risk which was identified during preparation was possible low
utilization of the RSF by banks. This is related to possible lack of understanding of the
technical details by the PFIs. The team addressed this risk through building enough
flexibility into the legal agreements which would have allowed changes in loan eligibility
criteria, structure of the RSF and product design, if necessary, to ensure that the facility
would meet the needs of agribusinesses and banks, and to stimulate the demand for the
facility.
5
15. An additional risk, not identified during the preparation, was changing market
conditions that would have made the RSF financially unviable due to declining lending
margins in the sector.
16. Monitoring and Evaluation (M&E). The project established an M&E system
and results framework. The M&E was responsibility of the IFC, as the facility agent,
while the PFI was responsible for providing agreed data on its loan portfolio and bank
performance. IFC portfolio officer was responsible for the interactions with the PFI and
provide IDA and RGC necessary information for M&E purposes. The yearly joint
supervision missions conducted comprehensive assessments of the monitoring indicators
and an evaluation of project’s performance both in terms of portfolio performance of
guarantee scheme and development impact. The IFC compiled and shared with the IDA
and RGC three quarterly project progress reports which tracked project performance
indicators. The quarterly reports provided the summary discussion of the project progress
and provided data on the performance of the portfolio of agribusiness loans under the
facility. This data was used to review development impact of the agribusiness utilization
of loans and their safeguard compliance through in-depth interviews which took place
during joint IDA, IDC, RCG supervision missions. However, these loans were later
removed from RSF coverage by the PFI.
Section 3. Project Implementation and Reasons for Cancellation
17. Context. In early 2011 the RGC, IDA and IFC signed the Risk Sharing
Framework of the project. IFC also signed a Risk Sharing Agreement (RSA) with the
ANZ Royal - the first PFI to participate in the program. The ANZ was expected to reach a
total portfolio of underlying agribusiness loans of US$30 million, with the risk being
shared 50:50 between ANZ and IFC, with IDA and the RGC providing a first loss to IFC
amounting to up to US$3 million. At the time of project preparation, ANZ had already
identified a pipeline of agribusiness loans which it intended to cover under RSF. The
remaining IDA funding of US$2 million was earmarked for other banks as they became
eligible to participate in the project.
18. Slow Start-up and First Amendment of RSA. The project experienced a slower
than expected start during its first year. In order to speed up booking the loans under the
facility and tailor the facility to the PFI lending program to better suit the financing needs
of its borrowers, RGC, IDA and IFC agreed to amend the RSA with ANZ on December 9,
2011. The following changes were introduced: (i) while the PAD and legal documents
were clear about inclusion of short term working capital and longer term investment loans
under the facility, the ANZ requested further clarification in the current language on the
inclusion of short term working capital credit lines in the eligibility criteria for the RSF;
(ii) clarification that all loan amounts will be calculated on the basis of disbursed amounts
rather than committed amounts; (iii) clarification of the extension of the ramp-up period
from two to three years to ensure full use of the RSF (PAD stated ramp-up of three years);
and (iv) modifications made in the Single Borrower Exposure limits which would allow
6
the ANZ to better meet the demand for agribusiness SMEs, especially in the rice milling
sector. The amended RSA was signed between IFC and ANZ on January 19, 2012.
19. The amendment, however, did not increase significantly the loans booked under
the facility. The cumulative value of loans disbursed by ANZ under the facility during its
first year of implementation was only US$5.3 million or 35 percent of its first year
lending target of US$15 million. This caused the project to be downgraded to “Moderately
Unsatisfactory”. The reasons for slow loan disbursements cited by ANZ included: (i)
difficulties to evaluate credit worthiness of potential borrowers due to the informality of a
large share of the agribusiness sector in Cambodia (i.e. lack of credible financial
statements, etc.); and (ii) increasing competition from other banks for potential
agribusiness clients. However, it should be noted that loans which were made by ANZ
with the support of RSF were used to upgrade rice milling equipment, which increased
mills’ processing capacities to meet increasing export demand, and for working capital.
As such the project did contribute to supporting the implementation of RGC’s rice policy.
20. Second Amendment to Legal Agreements. In September 2012 the IDA, IFC and
RGC agreed on the second amendment to legal agreements, which resulted in the
following changes:
(i) Reallocating SDR 195,000 out of SDR 640,000 for Category 3 - First Loss
Coverage for the third PFI - to refinance the Project Preparation Advance for the
Community Based Agricultural Productivity Project (P117642); and
(ii) Adding Category 5 in the disbursement table for the repayment of the project
Preparation Advance for the Community Based Agricultural Productivity Project
in the amount of SDR 195,000.
21. Suspension of the RSF. Delays in implementing the RSF continued in the second
year, and in late-2012 the RSF was suspended. One of the challenges was that there was a
lack of clarity over the interpretation of the eligibility criteria for agribusiness loans.
According to the RSA signed between IFC and the ANZ, all loans that met the eligibility
criteria were to be included in the Facility, as the coverage was to be provided on a
portfolio basis, to avoid the case where ANZ would include only very risky or delinquent
loans. However, during project implementation ANZ wanted to change this condition in
order to have discretion on which loan would be included in the Facility. As a result ANZ
did not include the entire agribusiness loan portfolio under the guarantee coverage. After
several rounds of discussion, it was agreed that all SMEs loans could potentially be
included, but no clear guidelines were developed concerning larger corporate
agribusinesses. In addition, discussions took place on guarantee pricing which ANZ now
felt was no longer commercially viable given the significant increase in liquidity in the
Cambodian banking sector and the renewed willingness of banks to lend to the
agricultural sector. This development led IDA to downgrade the project rating to
Unsatisfactory.
7
22. Addition of potential new PFIs. IFC continued to search for additional PFIs to
participate in the facility. However, given the lack of interest from the eligible commercial
banks, it was agreed to focus the facility on Micro Finance Institutions (MFIs). The joint
IDA/IFC team met with one MFI to explore its interest in joining the facility, but the joint
team concluded that this bank needed more time to improve its capacity and develop
agribusiness lending systems before it could implement RSF. Discussions with other
potential MFIs also did not yield positive results. Several potential MFIs were facing
liquidity shortfalls in 2012, which was not the case during project preparation. Others had
opaque ownership structures which prevented IFC from working with them.
23. Termination. During the joint IDA/IFC meeting with ANZ on December 6, 2012,
the latter made proposals for the continuation with the RSF. It was agreed in principle to
define the cut-off for SMEs at the maximum annual turnover level of US$15 million (as
per IFC standard definition of upper ceiling for SMEs). This approach was approved by
IFC management in February 2013 and the IFC team started to work on a historical
adjustment of the loans, which was needed before discussing other possible changes in the
legal agreements enabling ANZ to start booking new loans under the facility.
24. However, ANZ subsequently advised that it had concluded the RSF as structured
was no longer economically viable and expressed its wish to terminate it. This decision
based on the following reasons: (i) overall commercial bank lending to agribusinesses had
sharply increased between 2011 and 2013, with some local banks aggressively targeting
this segment; and (ii) such increased competition had resulted in a decrease in lending
rates, and decreased margins, which made the RSF no longer commercially viable. Data
gathered by the IFC team indicated that lending margins had dropped from 5 to 6 percent
as of January 2009 to approximately 4 percent in mid-2011, and further to approximately
2 percent in early 2013 compared to about 2.5 percent of RSF fees. For these reasons, all
exogenous to the project, while the RSF did meet the needs of the ANZ at the beginning
of the project in 2010, it had lost its relevance by 2013 as it had become financially
unviable due to rapid changes in the Cambodian financial sector.
25. In October 2013, the IDA-IFC team submitted a proposal to RGC to terminate the
RSF and re-allocate the US$5 million IDA funds to the provision of non-lending services
to Cambodian agribusinesses, in order to make them more attractive for financial
institutions, following the existing implementation arrangements. RGC expressed a lack
of interest in pursuing this option and on December 26, 2013, it requested that the Bank
cancel the project.
26. The project did not materialize as expected due to the rapidly changing market
conditions which were beyond its control. The team responded to these dynamics by
restructuring the project, but it was not enough to maintain the financial viability of the
facility. However, the agribusiness sector has seen significant expansion of credit and
declining interest rates since 2010 driven by general improvement of financial sector and
enabling environment. Both Bank and IFC have been supporting broader financial sector
reforms through FSAP and various advisory services. For example, IFC contributed to the
establishment of Cambodia Credit Agency which allowed the banks to better assess the
8
credit worthiness of the potential borrowers. In this regard, the original goal of the
program to increase PFI financing to agribusinesses was indeed achieved, although it was
not attributed to the project which did not materialize. The data provided by ANZ showed
that the value of loans it made to agribusinesses exceeded the planned landing targets
under the RSF. The table below shows that the value of ANZ lending to agribusinesses
(excluding plantation and other primary production activities) increased from $25.5
million in 2010 (baseline year) to $69 million in 2013. The incremental increase of $43.5
million is in line with the projected incremental value of $40 million agribusiness lending
over the same time period from the PAD. This data illustrates that ANZ was able to reach
its agribusiness sector lending targets without the support of the RSF coverage due to the
changes in the market conditions, which explains the reason to terminate the facility.
Table: Projected PAD loan volumes and actual PFI loan volumes (2010-2013)
2010
(Baseline) 2011 2012 2013
Projected value of loans (USD)
disbursed to agribusiness SMEs from
PAD
- 15,000,000 15,000,000 10,000,000
Actual ANZ value of loans (USD)
distributed to agribusiness SMEs 25,487,583 37,186,760 55,519,786 69,007,819
Incremental ANZ actual value of
agribusiness loans
11,699,177 18,333,026 13,488,033 Source: ANZ and Project Appraisal Document
27. Furthermore, the overall commercial bank lending to agriculture increased from
US$400 million in 2010 to US$920 million in 2012. In terms of outcomes, the rice milling
sector, which was the main beneficiary of this credit expansion, has seen its exports
increase from 105,260 tons in 2010 to 378,856 tons in 2013.
Section 4. Assessment of World Bank Group and Borrower Performance
Bank Group Performance: Moderately Satisfactory.
28. Quality at Entry Performance: Moderately Satisfactory. The project was
prepared and processed efficiently in seven months by a joint IDA-IFC team. Identified in
May 2010, the project went to the Board on December 16, 2010, and became effective on
May 5, 2011. The project was designed in close coordination with the Ministry of
Economy and Finance. Its design was in line with the country’s priorities and strategies as
expressed in RGC’s policy on the promotion of paddy production and rice exports. The
technical design of the project was sound and based on (i) experiences and lessons from
three pilot Risk Sharing Facilities in the Africa Region (Mali, Ghana and Madagascar);
(ii) recommendations made by an IDA-IFC Task Force Report in its review of the use of
IDA funds for Risk Sharing Facilities and Partial Credit Guarantee projects; and (iii)
sectoral analytical work carried out by IFC and donors. The PDO was highly relevant
during the project preparation given the significant liquidity in the credit markets and lack
of willingness of the banks to lend to agribusinesses. The Results Framework was
9
developed based on extensive discussions between IFC and IDA teams in participation
with the PFIs. All indicators were appropriate to measure the intended outcomes and
outputs, as well as easily monitorable from the data to be provided by the PFIs. The IFC’s
assessment of the PFIs’ commitment and the risks was sound and based on its widely
accepted financial modelling results.
29. The project design was relatively simple in that it included only one component –
i.e., RSF. It did not have a stand-alone TA component as in other RSF pilots and relied
instead on existing IFC Advisory Services. This approach facilitated speedy preparation of
the project, as per IFC’s request at the time, and met the needs of the first PFI.
30. Three WBG parties were involved in project preparation and implementation –
IDA, IFC advisory team and IFC investment team. The IDA-IFC team spent substantial
amount of time to discuss the details of the RSF and its utilization with the PFI. The PFI
was closely involved in the design of the facility. The IDA-IFC team included qualified
financial sector, banking and agriculture/agribusiness specialists, some of whom had prior
experience with the design and implementation of similar RSFs in Africa Region. RGC
strongly supported the project and provided a counterpart team that engaged closely with
the WBG team throughout project preparation and negotiations. Both project task team
leaders (TTLs) were based in the East Asia Region – the Bank TTL in Phnom Penh and
the IFC operational TTL in Hanoi. The core IFC investment team was based in Ho Chi
Minh City, which enabled frequent visits to Cambodia, with a residual technical team
members based in Washington, DC.
31. Quality of Supervision: Moderately Satisfactory. There were three semi-annual
joint IDA-IFC supervision missions, which included briefings to the RGC. In addition,
there were numerous visits by the IFC investment team from Ho Chi Minh City and
Washington to discuss project implementation issues directly with the PFI. The IFC
produced quarterly progress reports on a timely basis and these were shared with IDA and
RGC. The IFC team kept the IDA team informed on implementation issues.
32. When the project faced implementation issues in 2012 as detailed in Section 2
above, several meetings were organized both between the IDA/IFC and the PFI in order to
find feasible solutions. Discussions also took place between IFC's and the PFI's regional
management teams in order to understand the strategic issues that the project may have
been facing. A detailed supervision mission was conducted by the IFC and IDA in the fall
of 2012 and various scenarios were analyzed and put forward in order to assess options to
potentially modify the scope of the project and restructure the facility. Such scenarios
were discussed at length with the PFI. Regular meetings and discussions continued in
2013 until termination of the facility, as detailed in Section 2 above.
Borrower Performance: Moderately Satisfactory.
33. Royal Government of Cambodia Performance. The Government strongly
supported the project and engaged actively in project preparation. It appointed a project
preparation team, which met with the IDA-IFC team on a regular basis to discuss
10
preparation progress. The RGC team also engaged closely during the supervision
missions and reviewed the performance reports. Rating: Satisfactory.
34. Implementing Agency Performance. The project was implemented by the IFC
investment team, which included a Relationship Manager (RM), based in Ho Chi Minh
City, and a Portfolio Officer (PO), based in Phnom Penh. The proximity of the RM and
PO enabled regular contacts with the PFI, including on-site visits. The team also received
strong support from the Portfolio Manager as well as from the RM for the ANZ Group
based in Hong Kong, SAR, China. During project preparation, the IFC team conducted
thorough discussions with the PFI to explain the technical and legal aspects of the project
and functioning of the facility. Quarterly reports from the PFI were received on time and
summary reports were provided to IDA and RGC. The IFC actively coordinated the
restructuring of the RSA between the PFI, IDA, and the RGC to reach agreement and to
proceed swiftly with the restructuring. Specifically, the IFC team actively engaged in
discussion with the PFI, both at operational and management levels, in order to reach a
solution. Actions taken also included a detailed World Bank portfolio review in
Cambodia, which took place in November 2012, as well as internal discussions with
management. The restructured RSA was processed in bout 3 months between October
2012 and January 2013, which is quite rapid given that all changes had to be agreed and
approved by IFC, IDA, PFI and RGC. However, the IFC was not able to bring additional
PFIs under the facility due to the changes in the credit market conditions which affected
the financial viability of the facility. Rating: Moderately Satisfactory.
35. PFI Performance. Implementation of the loan portfolio under the RSF was the
responsibility of the PFI (ANZ). Following a change in the PFI’s country management,
which assessed that the RSF was not financially viable due to declining lending margins
in the sector, the PFI no longer actively used the RSF. The PFI was nevertheless able to
increase its lending volumes to agribusiness sector without the RSF, contributing thus to
the overall growth of agribusiness sector as envisioned under the project. Rating:
Moderately Unsatisfactory.
Section 5. Lessons Learned
36. If RSFs are to become more streamlined lending products for the WBG, there are a
number of steps to increase design efficiency as discussed below:
(a) Ensure that PFIs commit to the technical structure and eligibility criteria of
the RSF. The RSA with ANZ was signed four months after Board approval. However,
by the time the first quarterly report was due, ANZ had already flagged issues, such as
inclusion of working capital loans in the facility and calculation of fees based on the
utilization of these working capital loans. While it was clear from the IDA/IFC side
that working capital loans were included under the facility, ANZ claimed that it did
not fully understand this. As for the fees, as they were calculated on the outstanding
portfolio amount at the end of each quarter, ANZ asked to revise the RSA to clarify
the inclusion of short term loans, and calculate the fees on the actual utilization over
11
the quarter. This led to a lengthy renegotiation process, and an eventual amendment
after a six-month consultation process internally within IFC, ANZ, IDA, and the RGC.
(b) Ensure the commitment of the PFI to the target market, and its ability to
serve the agreed target market. The PFI senior management commitment to the
development of the target market (e.g. SME or agribusiness) and to a clear vision for
market positioning is critical and all senior managers should be on board. For
multinational PFIs, it is also critical that regional management be supportive of the
initiative taken by the subsidiary.
(c) There is no evidence that going ahead with one PFI will create interest from
others to follow. It should be preferable, if not obligatory, to start a RSF with at least
two banks. In cases where the PFIs are local banks, they would usually require
technical assistance to build lending capacity among SMEs. This would require a
stand-alone TA component - as was done in the Africa Region RSF pilots (see point f
below).
(d) IFC guarantee pricing should be more flexible towards changing market
conditions and risk perceptions of the banks in fast growing countries such as
Cambodia. Commercial banks are highly sensitive to levels of facility fees given the
declining lending margins in highly competitive environments where some banks are
learning rapidly about risks and are willing to lend to riskier segments while others
may resort to more lax lending standards. While the commercial principles of the IFC
business model are generally justified, there may be exceptions where such principles
may not be fully warranted (and the “subsidy” provided by IDA financing is not
enough to reduce facility cost), given the significant public goods nature of the stated
objectives. The RSF may be such a case.
(e) The ramp-up period of the facility should allow sufficient time for the PFI to
develop its procedures and build up its portfolio. Some PFIs might need to develop
new credit processes for the target market. For example, to target SMEs, PFIs might in
general need at least 1.5 years for market strategy development, credit processing
development, loan platform development, product development, staff training, and
marketing. Thus the ramp-up period for the RSF with different PFIs would need to
vary depending on the readiness of the PFIs for SME lending (benchmarks to measure
readiness could include SME market analysis, SME market segmentation, SME
strategy, product development, credit process for SME lending, staff training, IT
system, loan platform, delivery channels, etc.). It is expected that the RSF portfolio
build-up will be slower in the first two years and then grow from the third year.
(f) Targeted TA to potential SME borrowers is critical to the success of a RSF. It
is better to outsource such TA to SMEs to experienced consulting services. The TA
has to be properly designed and implemented by experts that are selected by IFC/IDA
on a competitive basis.
12
Annex 1. Bank Lending and Implementation Support/Supervision Processes
(a) WBG Task Team members
Names Title Unit Responsibility/
Specialty
Lending
Paavo Eliste, Lead Rural Development Specialist GFADR Task Team Leader
Koichi Hiramoto Senior Investment Officer IFC co-TTL
Luc Lecuit
Harvey Van Veldhuizen
Satoshi Ishihara
Julia Brickell
Nathalie Louat
John Law
Richard Caines
Alexis Diamond
Martin Habel
Operations Advisor
Lead Environmental Specialist
Senior Social Development Resident
Representative
Structured Finance Specialist
Banking Specialist
Principal Environmental Specialist
Evaluation Officer
Senior Financial Officer
SARDE
OPCQC
GSURR
IFC
IFC
IFC
IFC
IFC
IFC
Operations quality
Env safeguards
Social safeguards
Advisor
Structuring
Banking Specialist
Safeguards
M&E
Portfolio analysis
Cheena Trikha
Jung Mee Kim
Etienne de Belloy
Investment Officer
Investment Officer
Investment Analyst
IFC
IFC
IFC
Investment Officer
Investment Officer
Investment Analyst
Roch Levesque
Mark Walker
Glenn Jessee
Senior Counsel
Chief Counsel
Principal Counsel
LEGES
LEGES
IFC
Legal
Legal
Legal
Ahmet Soylemezouglu Financial Sector
Specialist/Consultant
GFADR Financial sector/
banking specialist
Chris Fabling
Seida Heng
Thao Le Nguyen
Ahsan Ali
Ngozi Blessing Malife
Senior Financial Management
Specialist
Financial management Specialist
Senior Finance Officer
Lead Procurement Specialist
Program Assistant
GGODR
GFMDR
CTRFC
GGODR
GENDR
Financial
management
Project FM
Disbursements
Procurement
Team Assistance
Narya Ou
Vachraras Pasuksuwan
Tho Nhu Hoang
Program Assistant
Program Assistant
Team Assistant
EACSF
EACTF
IFC
Team assistance
Team assistance
Team assistance
Supervision
Paavo Eliste Lead Rural Development Specialist GFADR Task Team Leader
Koichi Hiramoto Senior Investment Officer IFC co-TTL
Charles Schneider
Richard Caines
Alexis Diamond
Martin Habel
Bas Rozemuller
Resident Representative
Principal Environmental Specialist
Evaluation Officer
Senior Financial Officer
Advisory Services Officer
IFC
IFC
IFC
IFC
IFC
Advisor
Safeguards
M&E
Portfolio analysis
Advisory Officer
Etienne de Belloy Investment Analyst IFC Investment officer
Roch Levesque
Glenn Jessee
Senior Counsel
Principal Counsel
LEGES
IFC
Legal
Legal
Chris Fabling
Senior Financial Management
Specialist
GGODR
Financial
management
13
Seida Heng
Ngozi Blessing Malife
Financial management Specialist
Program Assistant
GFMDR
GENDR
Project FM
Team Assistance
Narya Ou
Vachraras Pasuksuwan
Tho Nhu Hoang
Program Assistant
Program Assistant
Team Assistant
EACSF
EACTF
IFC
Team assistance
Team assistance
Team assistance
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including
travel and consultant costs)
Lending
FY10 0.00 30.33
FY11 11.46 103.41
Total: 11.46 133.74
Supervision/NCO
FY12 5.85 28.28
FY13 6.25 31.50
FY14 8.69 47.53
FY15 as of December 15, 2014 0.75 4.11
Total: 21.54 111.42
14
Annex 2. List of Supporting Documents
1. World Bank. Cambodia Agribusiness Access to Finance Project: Restructuring
Paper for refinance the Project Preparation Advance (PPA No. Q7090-KH) for the
proposed Community-Based Agricultural Productivity Project (CBAPP, P117642).
2. Risk Sharing Agreement between ANZ Royal Bank Cambodia, and IFC,
Investment Number 28471, April 1, 2011
3. World Bank. Cambodia Agribusiness Access to Finance Project, Aide Memoire of
First Implementation Support Mission, May 8-30, 2012.
4. Cambodia Agribusiness Access to Finance Project, Risk Sharing Framework
Agreement, between the Kingdom of Cambodia, IFC and IDA, February 11, 2011.
5. World Bank. Cambodia Agribusiness Access to Finance Project, Financing
Agreement (Grant No.H-634 and Credit No 4839), between the Kingdom of
Cambodia and IDA, February 11, 2011.
6. World Bank. Cambodia Agribusiness Access to Finance Project, Project Appraisal
Document, December 16, 2010