document of the world bankdocuments.worldbank.org/curated/en/... · cps country partnership...

58
Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00004243 IMPLEMENTATION COMPLETION AND RESULTS REPORT IBRD 7705‐CN ON A LOAN IN THE AMOUNT OF US$80 MILLION TO THE PEOPLE’S REPUBLIC OF CHINA FOR A SHANXI COAL BED METHANE DEVELOPMENT AND UTILIZATION ( P100968 ) JUNE 18, 2018 Energy and Extractives Global Practice East Asia And Pacific Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 19-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

Document of 

The World Bank 

FOR OFFICIAL USE ONLY  

 Report No: ICR00004243 

  

 

IMPLEMENTATION COMPLETION AND RESULTS REPORT 

IBRD 7705‐CN 

ON A 

LOAN  

IN THE AMOUNT OF US$80 MILLION 

TO THE 

 PEOPLE’S REPUBLIC OF CHINA  

FOR A 

SHANXI COAL BED METHANE DEVELOPMENT AND UTILIZATION ( P100968 )  

 JUNE 18, 2018  

 

 

 

 

 

 

Energy and Extractives Global Practice 

East Asia And Pacific Region 

   

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

CURRENCY EQUIVALENTS  

(Exchange Rate Effective June 30, 2017)  

Currency Unit =   Chinese Yuan (CNY) 

CNY 1 =  US$0.15 (At closing) 

US$1 =  CNY 6.78 (At closing) 

 FISCAL YEAR 

July 1 ‐ June 30   

ABBREVIATIONS AND ACRONYMS  

CBM  Coal Bed Methane 

CMM  Coal Mine Methane 

CPS  Country Partnership Strategy 

DSCR  Debt Service Coverage Ratio 

EIRR  Economic Internal Rate of Return 

EMP  Environmental Management Plan 

EPC  Engineering, Procurement, and Construction 

FIRR  Financial Internal Rate of Return 

FM  Financial Management 

GHG  Greenhouse Gas 

GOC  Government of China 

ICR  Implementation Completion and Results Report 

LNG  Liquefied Natural Gas 

MRC  Mixed Refrigeration Cycle 

M&E  Monitoring and Evaluation 

O&M  Operations and Maintenance 

PAD  Project Appraisal Document 

PDO  Project Development Objective 

PMC  Project Management Consultant 

RAP  Resettlement Action Plan 

SCBMC  Shanxi Coal Bed Methane Company Limited 

SOE  State‐owned Enterprise 

SPC  Special Purpose Company 

TA  Technical Assistance 

TTL  Task Team Leader        

Page 3: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

       

Regional Vice President: Victoria Kwakwa 

Country Director: Bert Hofman 

Senior Global Practice Director: Riccardo Puliti 

Practice Manager: Jie Tang 

Task Team Leader(s): Ximing Peng 

ICR Main Contributor: Takayuki Doi  

Page 4: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

TABLE OF CONTENTS 

DATA SHEET ............................................................................................................................1 

I.  PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ........................................................ 5 

A. CONTEXT AT APPRAISAL ........................................................................................................... 5 

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION ................................................................. 8 

II.  OUTCOME ...................................................................................................................... 11 

A. RELEVANCE OF PDOs .............................................................................................................. 11 

B. ACHIEVEMENT OF PDOs (EFFICACY) ........................................................................................ 11 

C. EFFICIENCY ............................................................................................................................. 14 

D. JUSTIFICATION OF OVERALL OUTCOME RATING ..................................................................... 16 

E. OTHER OUTCOMES AND IMPACTS .......................................................................................... 16 

III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 18 

A. KEY FACTORS DURING PREPARATION..................................................................................... 18 

B. KEY FACTORS DURING IMPLEMENTATION .............................................................................. 19 

IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 20 

A. QUALITY OF MONITORING AND EVALUATION (M&E) ............................................................. 20 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ..................................................... 21 

C. BANK PERFORMANCE ............................................................................................................. 22 

D. RISK TO DEVELOPMENT OUTCOME ........................................................................................ 23 

V.  LESSONS AND RECOMMENDATIONS .............................................................................. 24 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ............................................................ 26 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 31 

ANNEX 3. PROJECT COST BY COMPONENT............................................................................. 33 

ANNEX 4. PROJECT DIAGRAM ................................................................................................ 34 

ANNEX 5. CBM PRODUCTION ................................................................................................ 36 

ANNEX 6. EFFICIENCY ANALYSIS ............................................................................................ 37 

ANNEX 7. BORROWER, CO‐FINANCIER, AND OTHER PARTNER/STAKEHOLDER COMMENTS .. 41 

ANNEX 8. SUPPORTING DOCUMENTS .................................................................................... 44 

ANNEX 9. ENVIRONMENTAL SAFEGUARDS ............................................................................ 45 

ANNEX 10. SOCIAL SAFEGUARDS AND RESETLEMENT ............................................................ 46 

ANNEX 11. TECHNICAL DEVELOPMENT (L‐TYPE HORIZONTAL WELL TECHNOLOGY) ............... 48 

MAP (CHN43541) ................................................................................................................... 54 

   

Page 5: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 1 of 54

         

DATA SHEET 

  

BASIC INFORMATION  Product Information 

Project ID  Project Name 

P100968  Shanxi Coal Bed Methane Development and Utilization 

Country  Financing Instrument 

China  Investment Project Financing 

Original EA Category  Revised EA Category 

Full Assessment (A)  Full Assessment (A) 

Organizations 

Borrower  Implementing Agency 

People's Republic of China  Shanxi Coal Bed Methane Company Ltd. (SCBMC) 

Project Development Objective (PDO)  Original PDO 

The development objective of the project is to increase the production and utilization of CBM/CMM to replace coal as a fuel for thermal use and to reduce GHGs and local air pollutants associated with coal combustion. The project development objective will be achieved by (a) enhancing the subsectorâ s policy framework and ins tu onal capacity, and (b) supporting the exploration, production and liquefaction of CBM to increase market access.  Revised PDO 

The revised PDO of the project is to increase production of coal bed methane to reduce GHGs associated with coal combustion in theproject area.   

Page 6: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 2 of 54

FINANCING 

 

  Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) 

World Bank Financing        IBRD‐77050 

80,000,000  80,000,000  80,000,000 

Total    80,000,000  80,000,000  80,000,000 

Non‐World Bank Financing       

Borrower  47,300,000  51,000,000  51,000,000 

Local Sources of Borrowing Country 

77,000,000  92,640,000  84,600,000 

Total  124,300,000  143,640,000  135,600,000 

Total Project Cost  204,300,000  223,640,000  215,600,000  

  KEY DATES 

   

Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 

19‐May‐2009  18‐Sep‐2009  26‐Nov‐2012  31‐Dec‐2014  30‐Jun‐2017 

   RESTRUCTURING AND/OR ADDITIONAL FINANCING 

 

 

Date(s)  Amount Disbursed (US$M)  Key Revisions 

18‐Nov‐2013  22.48  Change in Loan Closing Date(s) Change in Implementation Schedule 

19‐Feb‐2016  46.27  Change in Project Development Objectives Change in Results Framework Change in Components and Cost Change in Loan Closing Date(s) Reallocation between Disbursement Categories Change in Implementation Schedule 

  

KEY RATINGS  

 

Outcome  Bank Performance  M&E Quality 

Satisfactory  Satisfactory  Substantial 

 

Page 7: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 3 of 54

RATINGS OF PROJECT PERFORMANCE IN ISRs  

 

No.  Date ISR Archived  DO Rating  IP Rating Actual 

Disbursements (US$M) 

01  28‐Apr‐2010  Satisfactory  Satisfactory  .20 

02  27‐Jun‐2011 Moderately 

Unsatisfactory Moderately Unsatisfactory  .20 

03  08‐Apr‐2012 Moderately 

Unsatisfactory Unsatisfactory  8.20 

04  12‐Nov‐2012 Moderately 

Unsatisfactory Moderately Unsatisfactory  8.20 

05  20‐Dec‐2012  Moderately Satisfactory  Moderately Satisfactory  8.20 

06  24‐Jun‐2013  Moderately Satisfactory  Moderately Satisfactory  21.30 

07  18‐Dec‐2013  Moderately Satisfactory  Moderately Satisfactory  22.68 

08  24‐May‐2014 Moderately 

Unsatisfactory Moderately Unsatisfactory  22.87 

09  24‐Jun‐2014 Moderately 

Unsatisfactory Moderately Unsatisfactory  23.20 

10  10‐Dec‐2014  Moderately Satisfactory  Moderately Satisfactory  29.35 

11  29‐Jun‐2015  Moderately Satisfactory  Moderately Satisfactory  31.43 

12  14‐Dec‐2015  Moderately Satisfactory  Moderately Satisfactory  40.96 

13  28‐Jun‐2016  Moderately Satisfactory  Moderately Satisfactory  62.07 

14  20‐Dec‐2016  Moderately Satisfactory  Moderately Satisfactory  62.07 

15  22‐Jun‐2017  Moderately Satisfactory  Moderately Satisfactory  80.00 

 

SECTORS AND THEMES  

 Sectors 

Major Sector/Sector  (%) 

 

Energy and Extractives   100 

Non‐Renewable Energy Generation  99 

Public Administration ‐ Energy and Extractives  1 

  

Page 8: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 4 of 54

Themes   

Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  Environment and Natural Resource Management  100  

Climate change  70  

Mitigation  70    

Environmental Health and Pollution Management  30  

Air quality management  10   

Water Pollution  10   

Soil Pollution  10  

    

ADM STAFF  

Role  At Approval  At ICR 

Regional Vice President:  James W. Adams  Victoria Kwakwa 

Country Director:  David R. Dollar  Bert Hofman 

Senior Global Practice Director:  John A. Roome  Riccardo Puliti 

Practice Manager:  Ede Jorge Ijjasz‐Vasquez  Jie Tang 

Task Team Leader(s):  Jianping Zhao  Ximing Peng 

ICR Contributing Author:    Takayuki Doi 

         

Page 9: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 5 of 54

I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES 

A. CONTEXT AT APPRAISAL 

Context 

1. Energy  demand.  Energy  consumption  in  China  increased  from  990  million  tons  of  coal equivalent  in 1990  to 2,460 million  tons of  coal  equivalent  in 2006,  reflecting  the  rapid  growth of  its economy. The average growth rate of 5.8 percent per year was more than triple the rest of the world.  

2. Coal  consumption.  China’s  rising  energy  demand  was  met  largely  by  domestic  coal,  which accounted for 69.4 percent of primary energy consumption in 2006. Coal consumption increased from 1.06 billion tons in 1990 to 2.39 billion tons in 2006. Even with an aggressive fuel diversification policy, coal was expected to remain the dominant energy source for the foreseeable future. About 80 percent of urban households also relied on coal. By comparison, in the Organization for Economic Cooperation and Development  countries,  nearly  100 percent  of  the  households  and heat  boilers  relied on natural gas.  

3. Air pollution. The rapid increase in energy consumption, and their primary reliance on coal, had contributed to China’s severe air pollution. In particular, the combustion of bituminous coal was causing serious  atmospheric  pollution  from  airborne  particulates  and  emissions  of  sulfur  dioxide  (SO2)  and carbon dioxide  (CO2).  In  addition,  the production of  coal was estimated  to  result  in  the  release of 18 billion m3 (270 million tons CO2 equivalent) of methane into the atmosphere in 2006, about 43 percent of the global methane release associated with coal mining. This level was expected to rise to more than 50 percent, by 2020, if no significant action would be taken.  

4. Shanxi.  Shanxi  was  the  sixth  largest  energy  consuming  province  in  China.  Its  energy consumption was  overwhelmingly  dominated  by  coal,  which  accounted  for  94.7  percent  of  the  total energy demand in 2006, compared with the national average of 69.4 percent. The combustion of coal resulted in serious air pollution problems. Shanxi was the largest coal producing province in China, with coal  production  of  691.9  million  tons  in  2006,  nearly  one‐third  of  the  nation’s  total  production.  An estimated 6 billion m3 of coal mine methane (CMM) was released from coal mining operations in 2006, of which only 500 million m3 was captured and used. Shanxi was estimated to have the largest coal bed methane (CBM) resource amounting to about 10 trillion m3.  

5. Government  policy.  The  Chinese  authorities  were  fully  aware  of  the  need  to  address environmental  problems  and  to  formulate  policies  focused  on  environmentally  sustainable  economic development. Efforts were being made to promote efficient use of energy and cleaner energy resources. The Government was also taking assertive action to diversify energy sources,  including an accelerated nuclear power program, an ambitious gas penetration target, and significant hydropower and renewable energy development. The medium‐ to long‐term energy plan called for increasing gas consumption from the  current  3  percent  to  6  percent  and  10  percent  of  the  total  energy  demand  by  2010  and  2020 respectively. China was deficient in natural gas resources, so the development of CBM was considered an  integral  part  of  the  gas  expansion  program.  The  Government  established  a  dedicated  CBM/CMM development and utilization plan.  

Page 10: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 6 of 54

6. Province policy. At the Shanxi provincial level, the Government was committed to improving its environmental  performance  through  increased  energy  efficiency  and  diversification  of  its  energy sources. A core element of Shanxi’s energy plan for the Eleventh Five‐Year Plan was to actively promote the  development  and  utilization  of  CBM  and  CMM  resources.  A  dedicated  CBM/CMM  plan  was developed and had been under implementation since early 2000s. 

Original Theory of Change (Results Chain) 

7. The  original  theory  of  change  reflected  the  Country  Partnership  Strategy  (CPS)1   for  China approved by the Board in May 2006 (CPS 2006–2010). One of the five key pillars of CPS 2006–20102 was to ‘Manage resource scarcity and environmental challenges’ to address key constraints to China’s future growth, especially  through development of  indigenous  clean energy and mitigation of  air  pollution.  If successful,  the  project  was  expected  to  directly  contribute  to  this  key  pillar  of  CPS  2006–2010  by supporting the development of a clean fuel to replace the more polluting coal. Specifically, the project was expected to increase clean energy supply by harnessing the otherwise underused indigenous energy resources.  It would  facilitate sustainable development by enhancing  the security of  the energy supply and mitigating the negative environmental impact of energy production and consumption. 

8. The proposed activities were designed to produce practical outputs, including gas and liquefied natural  gas  (LNG)  production,  capacity  building,  financial  sustainability,  and  new  policy  making.  The outputs were expected to promote CBM/CMM production and utilization at the Shanxi provincial level and contribute to one of CPS pillars ‘Manage resource scarcity and environmental challenges’ in the long run (see figure 1). 

9. As part  of  its  overall  efforts  to  promote  clean  energy  development  in  China,  the World Bank supported the Central Government to develop a comprehensive set of institutional and policy initiatives necessary  to  establish  and  promote  the  CBM/CMM  industry.  This  had  led  to  the  implementation  of many  important policy  incentives aimed at creating an environment conducive to the development of the  CBM/CMM  sector.  The World  Bank’s  direct  support  to  Shanxi  included  the  first  large‐scale  CMM capture  and  utilization  project  designed  to  reduce  greenhouse  gas  (GHG)  emissions.  Through  sector work, the World Bank also supported the provincial government to assess the development potential of CBM and CMM, evaluate the investment needs, and design an action plan to ensure timely and optimal implementation.  

10. The involvement of the World Bank in this lending operation was expected to provide a platform for it to continue policy dialogue with the Shanxi Government for several years. It was also expected to increase  the  prospects  for  the  implementation  of  the  institutional  and  policy  recommendations.  The technical  assistance  (TA)  component of  the project was designed  to  assist  Shanxi  in  the  creation and implementation of an integrated development plan and policy framework. The investment component directly addressed the strategic issues of promoting gas market development, while also enhancing the 

1 CPS dated May 23, 2006, Report No: 35435 2 CPS 2006–2010  includes  five key pillars  (a)  Integrating China  into  the world economy;  (b)  reducing poverty,  inequality, and social exclusion; (c) managing resource scarcity and environmental challenges; (d) financing sustained and efficient growth; and (d) improving public and market institutions. 

Page 11: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 7 of 54

technical capacity of the sector. The capacity‐building elements of both components were envisaged to bridge the existing shortfalls in knowledge and skills and support the government advisers and planners, mine  designers,  technical  staff,  and  mine  management  in  their  efforts  to  build  a  commercially sustainable  CBM/CMM  industry  in  Shanxi.  The  World  Bank’s  involvement  was  expected  to  bring knowledge  and  experience  in  market  development,  economic  analysis  of  CBM  projects,  and  best technologies in methane extraction through vertical wells and in converting CBM to LNG. 

Figure 1. Original Theory of Change 

 

Original Project Development Objectives (PDOs) 

11. The  objective  of  the  project  in  the  original  loan  agreement was  ‘to  assist  Shanxi  Province  in increasing the production and utilization of CBM/CMM to replace coal as a fuel for thermal use and to reduce GHGs and  local air pollutants associated with coal  combustion’. The development objective of the  project  in  the  original  Project  Appraisal  Document  (PAD)  was  ‘to  increase  the  production  and utilization  of  CBM/CMM  to  replace  coal  as  a  fuel  for  thermal  use  and  to  reduce  GHGs  and  local  air pollutants associated with coal combustion’, slightly different but almost identical in essence. The PDO was expected to be achieved by (a) supporting the exploration, production, and liquefaction of CBM to increase supply and market access and (b) enhancing the subsector’s policy framework and institutional capacity. 

Activities Outputs PDOs/Outcomes Long-term Outcomes

Exploration and development of CBM production wells

Construction of gas collection pipelines and CBM gathering to collect the CBM from each well and transport it to the LNG plant

Construction of a LNG plant

Program to assist the project entity in developing its capacity to construct and operate the facilities efficiently and safely, and to expand business activities in the area of CBM/CMM development to achieve long-term financial sustainability

Program to assist the key stakeholders in Shanxi Province to enhance their institutional and technical capacities for policy making and implementation to scale up the CBM/CMM industry in Shanxi

Manage resource scarcity and environmental challenges

<PDOs>

Assist Shanxi Province in increasing the production and utilization of CBM/CMM to replace coal as a fuel for thermal use

Reduce GHGs and local air pollutants associated with coal combustion

<Outcomes>

• Produce and capture 2,000 million m3 of CBM/CMM in Shanxi annually

• Utilize 1,500 million m3 of CBM/CMM in Shanxi annually

Produce 250 million m3 of CBM annually

Produce 200,000 tons of LNG annually

Train 300 of staff-week for both SECBMIH and Shanxi province

Complete the studies

Formulate and implement new policy incentives and rules

Enhance SECBMH’s financial sustainability

Page 12: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 8 of 54

Key Expected Outcomes and Outcome Indicators 

12. The key performance indicators of the achievement of PDOs were planned to be measured by the increased volume of CBM/CMM produced and used, compared to the baseline in Shanxi Province. The main intermediate outcomes for the proposed project were (a) the quantity of CBM produced and LNG  sold  directly  from  the  project’s  investment  and  (b)  new  subsector  policies,  rules,  and  standards developed  and  implemented,  and  the  development  of  new methodologies  to  assess  the  CBM/CMM resources and evaluate utilization options. 

Components 

13. The project consisted of two components.  

14. Investment  Component  (US$202.6  million).  The  investment  component  included  (a)  the exploration and development of CBM production wells, (b) the construction of gas collection pipelines and  a  CBM  gathering  station,  and  (c)  the  construction  of  an  LNG  plant  consisting  of  four  modular, transportable  liquefaction  plants with  individual  production  capacities  of  50,000  tons  per  year  for  an ultimate processing capacity of 200,000 tons per year. The project diagram is illustrated in annex 4. 

15. TA  Component  (US$1.7  million).  The  TA  component  included  two  subcomponents:  (a)  a program  to  assist  the  project  entity  in  developing  its  capacity  to  construct  and  operate  the  facilities efficiently and safely and to expand business activities in the area of CBM/CMM development to achieve long‐term  financial  sustainability  and  (b)  a  program  to  assist  the  key  stakeholders  to  enhance  their institutional and technical capacities for policy making and implementation to scale up the CBM/CMM industry in Shanxi. 

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION   

The First Restructuring 

16. The project was restructured twice, once in in 20133 and again in 2016.4 The first restructuring in 2013  was  level  2  and  the  changes  included  (a)  modification  of  the  project  description  in  the  legal agreements due to changes in the technical design5 of the LNG plant and location6 of drilling wells and (b)  extension  of  the  project  closing  date  by  1.5  years,  from  December  31,  2014,  to  June  30,  2016. Neither the PDO, indicators, nor components were changed in 2013.  

 

3 Restructuring paper dated November 18, 2013, Report No: RES11768. 4 Restructuring paper dated February 19, 2016, Report No: RES 22208. 5 The  technical  design  of  the  LNG  plant  was  revised  to  adopt  the  latest  and  higher  efficiency  technology  called  mixed refrigeration cycle  (MRC). Although MRC had been used  in United States and Europe,  it had  less application  in China at  that time. Through detailed reports and technical reviews, it was confirmed that MRC can be technically and economically justified. 6 The upstream drilling site was relocated from Zhengzhuang Block to Libi Block for larger amount of production based on a new feasibility study. No new safeguard policies were triggered and the environmental assessment category remained unchanged.  

Page 13: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 9 of 54

The Second Restructuring 

17. The second restructuring, in 2016, was level 1 and the changes are summarized in the following paragraphs. 

Revised PDOs and Outcome Targets 

18. The  PDO  was  revised  in  the  second  restructuring  in  2016.  The  revised  PDO  in  the  legal agreement  and  the  second  restructuring  paper  was  ‘to  increase  production  of  coal  bed methane  to reduce GHGs associated with coal combustion in the project area’. The provincial level outcome, which was  included  in the original PDO, was excluded from the main targets. With the second restructuring, the  project  started  focusing  on  the  CBM  development  in  the  project  area,  considering  the  changing needs of the CBM industry and the responsibility of the implementation agency. In addition, the phrase “to replace coal as a fuel for thermal use” was deleted from the PDO. The rationale of this restructuring is described in paragraph 22. 

Revised PDO Indicators 

19. In  line  with  the  changes  of  PDO,  the  indicators  were  also  revised.  Both  ‘volume  of  CBM produced annually’  and  ‘volume of  LNG produced annually’ were  included  as PDO‐level  indicators.  In addition,  ‘avoided  GHGs  emissions  annually’  was  also  added  as  one  of  the  PDO‐level  indicators.  The original PDO‐level  indicators  (‘Total amount of CBM/CMM produced and captured  in  Shanxi annually’ and ‘Total amount of CBM/CMM utilized in Shanxi annually’) were removed because (i) the focus of the project  shifted  to  the  specific  area  rather  than  the provincial  level,  and  (ii)  the produced  LNG can be exported and utilized outside of the Shanxi province. (See table 1.) 

Table 1. The Original and Revised PDO Indicators 

Original PDO Indicators  Revised PDO Indicators 

Total amount of CBM/CMM produced and captured in Shanxi annually (million m3) 

Volume of CBM produced annually (million m3) 

Volume of LNG produced annually (metric ton) Total amount of CBM/CMM utilized in Shanxi annually (million m3)  Avoided GHGs emission annually (metric ton) 

Revised Components 

20. While  the  core  structure  of  the  project  components  remained,  technical  designs  for  the investment component (CBM and LNG development) were adjusted to incorporate the latest technology development of both gas drilling and liquefaction and the geologic conditions in the new location of the upstream gas drilling area. The activities in the TA component were also adjusted to be in line with the revised PDO and focus more on capacity building in the implementation agency. 

Other Changes 

21. Second Extension of Closing Date. The closing date of the project was further extended by one year, from June 30, 2016, to June 30, 2017. The primary purpose of the second extension was to allow the  implementing  agency  to  select  the  most  appropriate  technology  based  on  observation  of  the 

Page 14: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 10 of 54

performance of testing wells. A new advanced horizontal drilling technology was becoming mainstream in  the global  gas  industry.  To achieve higher production of CBM by  the  innovative  technology,  it was necessary  to  complete  the  test of  the upstream gas drilling and acquire additional geographical data. The detail of the technology development is presented in annex 11. 

Rationale for Changes and Their Implication on the Original Theory of Change 

22. During  an  implementation  support  mission  by  the  World  Bank,  an  attribution  issue  was identified  between  the  original  PDO  and  the  implementation  arrangement.  According  to  the  original project  design,  the  project  included  (a)  investment  in  a  specific  gas  drilling  component  and  a  gas liquefaction plant and (b) TA for capacity building for CBM/CMM development  in Shanxi Province as a whole. In addition, the PDO‐level indicators referred to increasing gas production in of the entire Shanxi Province, whereas the investment activities were more discreet. Furthermore, the project implementing company (Shanxi Energy Coal Bed Methane Investment Holding Limited, later renamed Shanxi Coal Bed Methane Company Limited [SCBMC]) was to be responsible for both the investment component and the TA component. At appraisal,  it was expected for the SCBMC, which  is a special purpose company and operates a specific project,  to motivate the relevant provincial agencies and  institutions to  implement the provincial‐level TA components such as policy studies and the development of data and information systems. These TA components were designed  to encourage  the private sector’s participation  in CBM development in Shanxi province. CBM development and gas liquefaction were previously nonexistent in Shanxi, and the private sector had little interest when the project was appraised. However, investments from private  companies were organically  initiated when  the government opened  the market  for both the public and private sectors. The provincial‐level TA, which was originally planned, became no longer necessary.  Therefore,  it  was  rational  that  the  project  focused  on  the  investment  component  and capacity building for the SCBMC. In addition, the phrase “to replace coal as a fuel for thermal use” was deleted from the original PDO, because it turned out that CBM and LNG from the project could be used for various purposes such as power generation, city gas and car  fuels. The PDO, outcome targets and indicators were revised to align to the workable project activities. All changes were still in line with the CPS  approved  in  October  2012  (CPS  2013–2016)7.  One  of  three main  strategic  themes  of  CPS  2013–20168 was ‘Supporting greener growth’. The revised theory of change properly reflected the CPS 2013–2016 and was expected to have a positive  impact on this CPS’s main theme (see figure 2).  In fact, the government strengthened the policy to accelerate the use of gas for heating purposes instead of coal in order to address the issues around air pollution. Although the project shifted to focus on the SCBMC’s activities, as a result, the project promoted advance clean energy supply in China and Shanxi Province by demonstrating advanced well drilling technology and the integration of production and liquefaction by a Chinese company.  

7 CPS dated October 11, 2012, Report No. 67566‐CN 8 CPS  2013–2016  includes  three  main  strategic  themes  (a)  Supporting  greener  growth;  (b)  Promoting  more  inclusive development; and (c) Advancing mutually beneficial relations with the world. 

Page 15: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 11 of 54

Figure 2. Revised Theory of Change 

 

II. OUTCOME 

A. RELEVANCE OF PDOs 

Assessment of Relevance of PDOs and Rating Rating: High 

23. Throughout the project  (from appraisal to completion), the PDO remained highly relevant and fully  aligned with  the World  Bank’s  CPS  2006–2010  at  appraisal  and  CPS  2013–2016  at  the  first  and second restructurings).  In particular, the project directly supported one of the key pillars  in CPS 2006–2010—'Managing resource scarcity and environmental challenges’ and one of main strategic themes in CPS 2013–2016 —'Supporting greener growth’. In addition, the project achievements supported two of the six core messages in the 2013 strategic China 20309 that highlighted the importance to ‘accelerate the pace of innovation and create an open innovations system’ and ‘seize the opportunity to go green’.  

24. Given the PDOs’ consistency with the CPS and the related World Bank’s strategy, the rating for Relevance is High. 

B. ACHIEVEMENT OF PDOs (EFFICACY) 

Assessment of Achievement of Each Objective/Outcome 

25. Because the PDO and the indicators were formally revised in the level 1 restructuring in 2016, the  original  and  revised  PDOs  are  separately  evaluated  as  follows.  The  original  PDO  had  two  parts 

9 The  2013  strategic  China  2030  identified  six  core  messages  (a)  Implement  structural  reforms,  (b)  accelerate  the  pace  of innovation and create an open innovation system, (c) seize the opportunity to go green, (d) expand opportunities and promote social security for all, (e) strengthen the fiscal system, and (f) seek mutually beneficial relations with the world.  

Activities Outputs PDOs/Outcomes Long-term Outcomes

Exploration and development of CBM production wells

Construction of gas collection pipelines and CBM gathering to collect the CBM from each well and transport it to the LNG plant

Construction of a LNG plant

Program to assist the project entity in developing its capacity to construct and operate the facilities efficiently and safely in the area of CBM development to achieve long-term financial sustainability

Support greener growth

<PDOs>

Increase production of coal bed methane to reduce GHGs associated with coal combustion in the project area.

<Outcomes>

• Produce 100 million m3 of CBM in the project area annually when all wells are put into commercial operation

• Produce 160,000 metric tons of LNG in the project area annually

• Avoid 520,000 metric tons of GHGs Emission from the project area annually

Develop 126 CBM wells

Train 800 of staff-week for SCBMC

Enhance SECBMH’s financial sustainability

Transport CBM to the LNG plant

Convert CBM to LNG for sale on the market

Page 16: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 12 of 54

referred  to  as  (PDO1‐a)—'to  assist  Shanxi  Province  in  increasing  the  production  and  utilization  of CBM/CMM  to  replace  coal  as  a  fuel  for  thermal  use’  and  (PDO1‐b)—'to  reduce  GHGs  and  local  air pollutants associated with coal combustion’. The revised PDO had one part  referred to as  (PDO2)—to increase production of CBM to reduce GHGs associated with coal combustion in the project area.  

Assessment of Achievement of the original PDO (PDO1‐a and PDO1‐b) Rating: Substantial 

26. According to the project design in the original PAD, the TA included provincial‐level activities to organize policy studies and develop CBM/CMM data and the information inventory system. As described in  paragraph  22,  these  parts  of  the  TA  became  no  longer  necessary  and  were  not  carried  out.  The project  focused  on  the  specific  investment  component  and  capacity  building  only  for  the  SCBMC. Although  the  activities  in  the  SCBMC  partly  contributed  to  the  provincial‐level  CBM/CMM developments, the intended contribution was not fully made. Therefore, PDO1‐a is rated Modest (3). As for  PDO1‐b,  on  the  other  hand,  at  the  time  of  the  level  1  restructuring,  the  PDO  indicators  had significantly exceeded the end target (see table 2). Although there was no indicator to directly measure the  reduction of GHGs  and  local  air  pollutants,  the produced CBM  reduced  the  consumption of  coal. GHGs reduction is almost proportional to the amount of CBM/CMM produced, captured, and used (see paragraph 30 and annex 6 for detail). Thus, PDO1‐b was substantially achieved in Shanxi Province and the wider area. Considering this high achievement ratio to the end target, the rating for PDO1‐b is High (5).  Averaging  the  ratings  for  PDO1‐a  (3)  and  PDO1‐b  (5),  the  overall  rating  for  the  original  PDO  is Substantial (4).  

Table 2. Achievement of the Original PDO Indicators Before the Level 1 Restructuring 

  Baseline  End Target Actual 

(at the Second Restructuring) 

Achievement 

Date December 31, 2008 (million) 

June 30, 2016 (billion) 

December 09, 2015 (billion) 

December 09, 2015 (%) 

Total amount of CBM/CMM produced and captured in Shanxi annually (m3) 

300  2  8.1  405 

Total amount of CBM/CMM used in Shanxi annually (m3) 

200  1.5  4.5  300 

 

Assessment of Achievement of the Revised PDO (PDO2) Rating: Substantial 

27. At the second restructuring in 2016, the PDO was revised to ‘to increase production of CBM to reduce GHGs associated with coal combustion in the project area’ and the indicators were also revised accordingly. Because the original PDO indicators had achieved more than what was originally intended, the end targets of the revised PDO indicators were set at an ambitious level. As shown in table 3, each indicator did not reach the set target at closing in 2017. 

Page 17: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 13 of 54

Table 3. Achievement of the Revised PDO Indicators After the Level 1 Restructuring 

  Baseline  End Target Actual (2016) 

Actual (2017) 

Forecast (2018) 

Forecast (2019) 

Date December 01, 

2009 December 31, 

2017 December 

2016 December 

2017 December 

2018 December 

2019 

Volume of CBM produced annually (m3)a 

0   60 million (2017)   90 million (2018) 100 million (2019) 

9.2 million 20 million (33%) 

80 million (89%) 

145 million (145%) 

Volume of LNG produced annually (Metric ton) 

0  160,000 41,532 (26%) 

119,000 (74%) 

120,000 (75%) 

160,000 (100%) 

Avoided GHGs emission annually (Metric ton) 

By the original conversion factorb 520,000 

134,980 (26%) 

386,750 (74%) 

390,000 (75%) 

585,000 (100%) 

By the revised conversion factorc 243,200 

63,130 (26%) 

180,880 (74%) 

182,400 (75%) 

243,200 (100%) 

Note:  a. The  planned  targets  of  CBM  production  are  60,  90,  and  100  million  m3  in  2017,  2018,  and  2019 

respectively and will reach full production by 2019. b. 3.25 tons CO2 per ton of LNG. At appraisal, due to lack of track records, it was tentatively assumed that all 

the LNG produced would be used for power generation and GHGs from coal‐fired plants would directly reduce. 

c. 1.52  tons  CO2  per  ton  of  LNG.  At  closing,  statistical  data  became  available.  Therefore,  the  conversion factor is recalculated based on the actual usage portfolio. Details are described in annex 6. 

28. Volume  of  CBM  production. However,  the  volume  of  CBM production was  still  increasing  at closing. The production volume was expected to keep increasing because it generally takes about nine months for CBM production to become stabilized and reach its peak after the completion of drilling. In order to carefully evaluate how likely the operation is to achieve its objectives, the submission date of the Implementation Completion and Results Report (ICR) was extended by six months so that the future CBM production can be more accurately estimated by confirming evidence and actual production trend. In  fact,  the  total volume of CBM has been  increasing and  is  forecasted to reach  its peak  in 2019. The achievement rate in 2019 is expected to reach 145 percent of the planned target. The CBM production data  (both past and future), which was reviewed and verified by the World Bank team,  is provided  in annex 5. The implementation agency intends to make continuous efforts for further achievements. 

29. Volume of LNG production. As for the outputs from the constructed LNG plants, the available facility  capacity  had  already  reached  200,000  ton  (100  percent  of  the  planned  capacity)  at  project closing. The LNG plant was supposed to use both the company’s own CBM and purchase gas from Petro China (see annex 4). However, due to the government policy change to accelerate the usage of gas for heating, instead of coal, the district heating sector and residential users were allowed to use natural gas on a priority basis, and the SCBMC could not procure enough gas for LNG production. It was beyond the company’s  control.  On  the  other  hand,  considering  that  the  volume  of  CBM  production  under  the project is increasing in 2018 and 2019 and that more gas pipelines will be built to improve the gas supply situation, it is expected that the volume of LNG production will reach the planned target in 2019. 

Page 18: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 14 of 54

30. Avoided GHG emission. Pursuant  to  the second restructuring paper, avoided GHG emission  is calculated based on the LNG production, which replaces the consumption of carbon‐intensive fuel such as  coal  and  gasoline  (see  annex  6  for  details).  Because  the  volume  of  avoided  GHG  emission  is proportional to the LNG production and sales, the achievement rate of this third indicator is same as the second indicator (LNG production) and will reach 100 percent of the planned target in 2019. As for GHG counting, various methodologies and conversion factors could be considered. Table 3 shows two simple but  clear  cases,  including  (a)  figures based on  the original  conversion  factor  and  (b)  figures based on another conversion factor based on the actual LNG off‐takers’ portfolio provided by the SCBMC. 

31. Best  use  of  available  technology.  From  another  aspect,  the  evaluation  takes  into  account whether the project used the best available technology and produced CBM as much as the geographical conditions would allow with reasonable cost. To employ the  latest technologies and maximize the gas production,  a  cautious  approach  toward  changes  of  technical  schemes  was  taken—a  first  batch  of testing  wells,  including  both  vertical  and  horizontal  wells  was  developed  to  compare  the  cost effectiveness of different  technologies  in  the  region. Based on  the observation of  the performance of these  testing wells,  the  SCBMC decided  on  the  final  technical  schemes  for  the  remaining wells.  As  a result, the test data and technical development indicated the possibility of the combination of vertical and  horizontal  wells.  The  choice  between  horizontal  and  vertical  wells  at  each  location  would significantly affect CBM volume and the cost‐effectiveness of the upstream gas drilling. Although it took the  SCBMC more  than  a  year  to  compare  the  production  and  cost  of  both  technologies  in  each well location,  the  optimal  technologies  were  selected  with  the  consent  of  the  World  Bank.  The  L‐type horizontal  well  technology  was  applied  mainly  in  the  project  and  became  a  good  showcase  in  the country. The project played a catalytic role and made a great contribution not only to this project, but also  to  the  following projects.  Peer  companies  such as Petro China  and Blue  Flame have  successively used the L‐type horizontal well technology for CBM developments  in similar geological structures. The detail of technology development is presented in annex 11. 

32. Although the achievement rate, at closing, was less than the planned target, considering (a) the high achievement expectation in the near future and (b) utmost efforts that were made to maximize the outcome, the efficacy rating of the revised PDO is Substantial. 

Justification of Overall Efficacy Rating  PDO1 Rating: Substantial (PDO1‐a: Modest and PDO1‐b: High), and PDO2 Rating: Substantial 

33. A split rating is applied due to the second restructuring, in which the PDO was revised. Although the achievement rates of the original PDO indicators were significantly high, the efficacy rating for the original PDO (PDO1‐a and PDO1‐b)  is rated Substantial because the originally  intended contribution to the outcome at the provincial level was partially but not fully made. Although the revised PDO indicators did  not  reach  the  set  target  at  closing  in  2017,  the  efficacy  rating  for  the  revised  PDO  (PDO2)  is Substantial because  significant  increase  in CBM production after  the  closing date was  confirmed,  and intended outcomes are predicted to be achieved in the near future.  

C. EFFICIENCY 

Assessment of Efficiency and Rating Rating: Substantial 

Page 19: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 15 of 54

34. Economic  analysis. At  appraisal,  the project was  found  to be economically  sound based on a baseline economic internal rate of return (EIRR) of 25 percent before including environmental impacts, which would  increase  the  EIRR.  This  result was  robust  to  sensitivity  analysis  of  gas  production  rates, drilling costs, and gas prices within reasonable values. A separate analysis at completion, using the same cost benefit  analysis method but  the economic value  is  calculated at market prices of  the LNG at  ICR (shadow price was  calculated at  appraisal),  shows  the EIRR  to be 15 percent without  considering  the avoided  carbon  emission  benefits,  or  18  percent when  carbon  benefits  are  taken  into  consideration. While  this  is  lower  than what was estimated at appraisal  (see  table 4) due  to  the  longer construction period  (actual  eight  years  versus planned  three  years  in  the PAD),  higher  investment  cost,  and  lower LNG prices  in  the  first  several operation years  (as discussed  in paragraph 55),  the EIRR  is nonetheless substantial, higher  than  the World Bank’s benchmark of 12 percent. Further details of  the changes  in assumptions and methodology, and an updated EIRR estimate with CO2 impacts, are provided in annex 6. 

Table 4. EIRR (excluding environmental benefits) at Appraisal and Closing 

EIRR at Appraisal  EIRR at Closing 

25%  15% 

35. Financial analysis. At completion, the financial internal rate of return (FIRR) is calculated to be 12 percent. This is based on (A) the actual loan conditions, (B) the actual cost and revenue from 2013 to 2017,  and  (C)  reasonable  predictions  for  2018  and  future  years.  The  FIRR  estimated  at  completion  is slightly  higher  than  the  original  estimation  at  appraisal  of  9  percent  (see  table  5).  This  positive improvement  is mainly attributable to the higher volume of CBM production and government subsidy for CBM production. The data used to produce these figures can be found in annexes 5, 6, and 7. 

Table 5. FIRR at Appraisal and Closing 

FIRR at Appraisal  FIRR at Closing 

9%  12% 

36. Sensitivity  analysis.  Several  sensitivity  analyses  were  carried  out  to  determine  the  financial viability of the project under various scenarios. The results indicate that changes in key parameters such as  (a)  operation  expense,  (b)  CBM  production,  and  (c)  LNG  market  price,  would  indeed  affect performance.  In  particular,  the  LNG market  price  is  one  of  the most  sensitive  variables  because  the profit  margin  of  the  company  highly  depends  on  it.  Nevertheless,  the  project’s  financial  strength  is expected to remain robust as shown in table 6.  

Table 6. Sensitivity Analyses 

Pessimistic Scenario  FIRR at Closing (%) 

20% increase in operation expenses  11 

20% reduction in CBM production  10 

20% reduction in LNG market price  7 

37. Aspects  of  design  and  implementation.  The  closing  date  of  the  project was  extended  twice. However, it was not simply due to the delay in implementation. The implementing agency requested for the extension to prioritize the project outcome rather than to complete the project within the original 

Page 20: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 16 of 54

timeframe. There were significant improvements in well drilling technologies during the project period. To maximize the production of gas, it was necessary to obtain the actual operation data of existing wells. Based on  the data analysis,  the  technologies and  locations of horizontal wells and vertical wells were properly  redesigned. As  a  result,  the  implementing  agency  achieved  greater  outcomes.  Average CBM production  volume  from  a  single  well  in  the  project  is  significantly  higher  than  other  projects  in neighboring  area.  According  to  the  assessment  by  a  third  party  (China  University  of  Mining  and Technology), the average daily CBM production from a single horizontal well under the project could be 12,000  m3,  much  higher  than  the  daily  production  of  single  horizontal  wells  operated  by  other companies in the neighboring areas in the same region, recorded as 2,000–6,000 m3 per day (see annex 11). 

38. Although there was a slight cost increase (see annex 6 for details) and the EIRR is lower than the estimation  at  appraisal,  given  the  sound  absolute  level  of  the  EIRR  and  FIRR  achieved  and  the operational  efficiency  being  well‐above  industry  standards,  the  rating  for  project  efficiency  is Substantial. 

D. JUSTIFICATION OF OVERALL OUTCOME RATING 

39. Although  a  split  rating  is  applied,  both  outcome  ratings  before  and  after  restructuring  are Satisfactory based on the ICR guideline. Therefore, the overall outcome rating is ‘Satisfactory’ as shown in table 8. 

Table 8. Overall Outcome Rating 

  Before Restructuring  After Restructuring 

Relevance of objective  High 

Efficacy (PDO)  Substantial  Substantial 

   PDO 1‐a  Modest PDO2  Substantial 

 PDO 1‐b  High 

Efficiency  Substantial 

Outcome ratings  Satisfactory  Satisfactory 

Overall Outcome Rating  Satisfactory 

 

E. OTHER OUTCOMES AND IMPACTS 

Gender 

40. The  project  was  not  gender  tagged  and,  therefore,  did  not  specifically  focus  on  gender. However,  the  project  indirectly  provides  several  positive  impacts  on  the  gender  aspect  as  well.  For cleaning and  landscaping in the project area, 50  local villagers,  including 28 women (56 percent) were employed. In addition, from a long‐term perspective, supporting greener growth and managing resource scarcity will  result  in better quality of air and sufficient energy supply at the household  level. This will improve  the  quality  of  life  for  cooking,  cleaning,  exercising  outside,  and  laundry.  Those who  benefit most from such improvements are housewives. 

Page 21: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 17 of 54

 

Institutional Strengthening 

41. The project strengthened the institutional capacity of the implementing company (SCBMC). The number of staff‐weeks of training for the SCBMC reached 2,150 and it is more than double the original end  target  (800  staff‐weeks).  In  the  training,  the  capabilities  in  project  management,  corporate management, construction, gas liquefaction, and safety were strengthened. In addition to the training, the experience gained from the project will be useful for future work, including new site development and operations and maintenance (O&M). Furthermore, the project accommodated a tailored simulation system  in  2016.  The  system  can  provide  practical  training  programs  for  the  LNG  plant  operators  to understand how  to control  the LNG plant under both normal and emergency  situations. Through  this realistic  training,  the  SCBMC  can  effectively  enhance  and  maintain  operators’  capability  and  avoid severe accidents. Because this is a unique and advantageous system in Shanxi Province, it has been used for not only the SCBMC’s employees, but also for other companies’ operators. This training service has yielded  an  additional  income  (CNY  400,000  as  of  March  2018),  which  can  be  used  for  the  system maintenance and future upgrade. Photos of the simulation system are shown in annex 12. 

Mobilizing Private Sector Financing 

42. The  project  implementing  agency  was  a  Special  Purpose  Company  (SPC)  created  to  prepare, finance, construct, and operate the project facilities. The World Bank loan was made to the Government of China (GOC) according to the IBRD’s standard terms and conditions. The GOC loaned the proceeds to the Shanxi provincial Government, who then forwarded the proceeds to the SPC on the same terms and conditions. The project was funded by the World Bank, the government subsidy, public domestic banks, and state‐owned entities. Therefore, no private sector financing was directly injected in to the project. However,  the  successful  production  of  the  project  catalyzed  and  mobilized  private  sector  financing. Successful  production  and  the  technology  used  in  the  project  became  a  good  showcase,  drove  the following projects, and attracted further private investments of CNY 580 million in the neighboring area. (See annex 4). 

Poverty Reduction and Shared Prosperity 

43. The project brought considerable social benefits to the village, created more than 400 new job opportunities,  and,  therefore,  contributed  to  directly  reducing  local  poverty.  For  example,  the construction of wells and gas collection facilities generated CNY 27 million (US$4 million) worth jobs for local  villagers, which  included  civil works, water  transport,  and  temporary  employment.  According  to the  social  survey,  most  villagers  had  experienced  a  significant  increase  of  income  during  project construction by working for the company, leasing houses to construction workers, and selling vegetables and farm products to the contractors. In 2016, the average per capita income in the village had reached CNY 13,000, which was 172 percent higher  than  in 2008  (CNY 4,780 per capita). Furthermore,  from a long‐term  perspective,  the  LNG  produced  in  the  project  has  been  supporting  the  affordability  and sufficiency of energy supply on a regional  level. The scarcity of energy could be a critical  issue for the country that encountered rapid economy growth. The stable energy supply from the project exerted a positive impact on the prosperity of the country. 

Page 22: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 18 of 54

 

Other Unintended Outcomes and Impacts 

44. Road upgrade. The  road  infrastructure  in  the project area before  the project was poor and  it was  inconvenient  for  local  villagers  to move  in  the area especially when  it  rained or  snowed.  For  the project construction purpose, more than 100 km of local roads were redeveloped. The upgraded roads are  now  being  used  by  local  villagers  and  are  highly  appreciated.  This  improved  the  efficiency  of villagers' economic activities and the quality of life in the area where the project was executed. Photos of local roads are shown in annex 12. 

III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME 

A. KEY FACTORS DURING PREPARATION  

Project Design 

45. Analytical  studies  were  conducted  by  the  World  Bank  to  underpin  the  project  design.  The aspects  that  were  properly  designed  included  lending  instrument,  project  components,  and environmental  and  social  management.  On  the  other  hand,  ‘institutional  and  implementation arrangements’ planned during the preparation stage diverged from what was originally expected, and the level 1 restructuring was required. The detail is described in the following subsection.  

Institutional and Implementation Arrangements 

46. The  project  implementing  company  (SCBMC)  was  to  be  responsible  for  both  the  investment component and the TA component. However, the original PDO and indicators included the improvement of CBM/CMM development  in Shanxi Province as a whole. As described earlier,  it was not realistic for the  SCBMC  to motivate  the  relevant provincial  agencies and  institutions  to  implement  the provincial‐level activities  such as policy  studies and  the development of data and  information  systems. To  solve this issue, the PDO and indicators were revised in the second restructuring. As a result, the SCBMC was able to focus on the workable project activities. 

Technical Aspects 

47. The vertical well technology selected during preparation was proven and demonstrated by other completed  and  ongoing  CBM  projects  in  the  world.  It  was  considered  to  match  the  geological  and methane  reservoir  conditions  at  the  project  site.  The  overall  well  and  surface  facility  design  was standard  for  this  type of operation at  that  time. However,  the  advancement of  technology and more actual sampling data obtained during the early stage of development provided opportunities to analyze and compare alternative methodologies. In the end, the project adopted horizontal wells in 33 locations, which  were  not  originally  planned.  Having  said  that,  it  is  natural  that  the  underground  well  drilling projects  hold  a  certain  degree  of  uncertainty.  The  project  successfully  and  flexibly  adapted  recent technology during the implementation. 

Page 23: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 19 of 54

48. In  the  LNG  plant,  the  liquefaction  technology  selected  during  the  project  preparation  was Expansion Refrigeration Cycle and four skid‐mounted trains to be built with the capacity of 50,000 tons for each train (a total of 200,000 tons annually). This technology was mature and was a widely accepted conventional technology that was used in many small LNG production plants. The first train in the LNG plant was built  following  this  design.  The evolving  LNG market  development  exerted pressure on  the SCBMC to consider more efficient technology, so a comparison of different technologies was conducted again.  It  concluded  that  the  remaining  three  trains  (total 150,000  tons annually) would be merged as one  train and  the Mixed Refrigerant Cycle  technology would be used. This change of  technical design enables the SCBMC to produce better quality LNG with less electricity consumption.  

B. KEY FACTORS DURING IMPLEMENTATION  

(i) Factors subject to implementing entities control 

Human Resources and Organizational Capacity 

49. The number of staff‐weeks of training for the SCBMC reached 2,150, which is 269 percent of the target (800 staff‐weeks). The SCBMC repeatedly organized the necessary trainings for all levels of staffs, including  relevant  technical personnel, middle‐level  leaders, and management.  It effectively  improved the  company's  technical  and  organizational  capabilities  to  ensure  successful  implementation  of  the project. 

Basic Logistics 

50. The SCBMC has effectively used the existing pipeline facilities owned by Petro China to transmit the  CBM produced  in wells  to  the  LNG  plant.  Even  during  step‐by‐step  construction  of  gas‐gathering stations,  the  least‐cost method  of  gas  transportation was  realized  by  using  temporary  connection  of wellheads under  the agreement with Petro China. The LNG was  transported  to Shanxi, Hebei, Henan, and eastern China through low‐temperature tanker trucks. The efficient logistics were well‐structured. 

Social and Environmental 

51. Through  continued  learning  and  efforts by  the  SCBMC,  the environmental  issues, which were identified during  implementation, were addressed or remedied and did not have a residual  impact on the environment. As for the social safeguards, the project involved a certain amount of permanent land acquisition  and  temporary  land  occupation.  The  resettlement  actions  were  handled  very  well  in compliance  with  the  national  law,  local  regulations,  and  World  Bank  requirements.  The  details  are presented in annexes 9 and 10. 

Safety 

52. Throughout  the  project,  the  SCBMC  maintained  a  ‘safety  first’  policy  and  took  effective measures, including the establishment of a safety management system, three‐level security inspection, and  risk  assessment.  Every  year,  the  investigation  of  potential  safety  hazards was  carried  out.  Safety learning  and  training opportunities,  including emergency drills, were organized more  than 50  times  a year  to  enhance  the  safety  awareness  of  all  staff  and  effectively  improve  the  ability  to  deal  with 

Page 24: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 20 of 54

incidents.  Through  a  series  of  effective  safety  measures,  work‐related  accidents  did  not  occur.  An independent safety panel was established, comprising technical experts from the industry, to guide the SCBMC  in  improving  its  safety  management.  The  simulation  system  established  under  the  TA component has also empowered the operation staff to practice safety measures. 

(ii) Factors subject to the World Bank control 

Adequacy of Supervision 

53. Supervision  was  efficient  and  adequate.  Although  the  task  team  leader  (TTL)  was  changed before the  launch of the project,  the transition and the task handover were conducted smoothly. The project launch mission was initiated in November 2009 followed by periodic supervision missions. At the end  of  every  mission,  a  wrap‐up  presentation  was  shown  to  the  stakeholders  to  clearly  share  the mission result. 

Adequacy of Reporting 

54. The  reporting  by  the World  Bank  through Aide Memoires,  implementation  status  and  results reports, and wrap‐up presentations was of high quality, detailed, and candid. The supervision missions included necessary experts in areas including technical, fiduciary, safeguards, and safety. These experts monitored  the  project  and  guided  the  borrower whenever  necessary.  Such  actions  taken  by  experts were properly summarized in the annexes of Aide Memoires. 

(iii) Factors outside the control of implementing entities 

LNG Market Price Decline 

55. At the time of project appraisal, the price of LNG was generally negotiated between producers (mainly  Australian  suppliers)  and  consumers  (Chinese  power  generation  companies  etc.)  with  the intervention  of  the  governments,  and  the  amount  of  LNG was  limited  in  China. With  the  reform and development of the gas market in China, the LNG price is now set by the market. The LNG is traded as a commodity and  its price  is  affected by market  conditions. Due  to  the decline of  the domestic energy demand  coupled with  the  sharp  fall  in  international  oil  prices,  the  LNG prices  in  the market declined compared to the assumption at the appraisal stage. The price fluctuated between CNY 5,000 and CNY 7,000 per  ton before 2013 and then started a continuous decline  from 2014.  In 2016,  the  transaction price dropped to CNY 2,500 per ton. In 2017, prices slightly rebounded and the average price reached around CNY 3,600 per ton. However, it is still considerably low compared to the trend in 2010–2013. The LNG price decline affected the LNG production and the project FIRR negatively.  

IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME 

 

A. QUALITY OF MONITORING AND EVALUATION (M&E) Rating: Substantial 

 

Page 25: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 21 of 54

M&E Design 

56. The set of the original PDO result indicators and intermediate indicators had several weaknesses to monitor and evaluate  the project. These weaknesses  include  the  following:  (a) GHG reduction was one of key aspects of the original PDO, but there were no indicators to quantify GHG reduction, (b) the original  PDO  included  the  provincial‐level  improvement,  but  it  was  hard  to  evaluate  how  much  the project contributed to such provincial improvement with the original indicators, and (c) the debt service coverage ratio (DSCR) was included in the intermediate indicators to monitor financial strength in each year during  implementation, but  it was not enough to ensure  long‐term financial sustainability. These issues  were  addressed  with  the  second  restructuring.  The  revised  PDO  and  the  indicators  were appropriate and sufficient to measure the project’s progress.  

M&E Implementation 

57. The restructured Results Framework properly guided the client and the World Bank to monitor and  evaluate  the  project  progress  toward  the  achievement  of  the  PDO.  The  implementation  agency regularly collected, consolidated, and analyzed data in line with the M&E design. The methodology and report were of high quality and acceptable.  In addition, when necessary, an external monitoring team was effectively recruited for surveys. 

M&E Utilization 

58. The  implementation  agency  and  the World Bank  regularly  used  the  indicators  to manage  the project progress toward the PDO. At the end of every mission, a wrap‐up meeting was held to conduct consultations  for  improvement  based  on  the  data  derived  from M&E  activities.  The  results  of  these consultations  were  summarized  in  Aide Memoires  and  shared  with  wider  concerned  parties  so  that appropriate next actions could be taken on time. 

Justification of Overall Rating of Quality of M&E 

59. The overall  rating of  quality of M&E  is  Substantial. M&E  implementation and utilization were conducted  properly.  Although  there  were  some  weaknesses  in  the  original  M&E  design,  corrective action was taken to address them. By the closing date, the data being collected informed the project’s achievements reliably. 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE  Environmental Safeguards 

60. The overall rating of environmental safeguards is Moderately Satisfactory. The project involved extractive  activity  in  a  mountain  area  and  the  construction  of  the  LNG  plant,  thus  the  soil  erosion, vegetation clearance, and safety issues of primary concern were identified. Given its nature and scale, it was  appropriately  classified  as  Category  A,  with  the  Environmental  Assessment  (OP/BP  4.01)  being triggered. The safeguard rating at the beginning of the implementation was relatively low. For example, the  vegetation  restoration  was  not  immediately  conducted.  However,  the  final  safeguard  rating achieved was Satisfactory  through  continued  learning and effort  by  the SCBMC  (photos of  vegetation 

Page 26: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 22 of 54

restoration in the drilling area of 53,000 m2 are provided in annex 12). The compliance issues, identified during  implementation,  were  addressed  or  remedied  and  did  not  have  a  residual  impact  on  the environment, implementation progress, or project objectives. The details are presented in annex 9. 

Social Safeguards 

61. The overall rating of social safeguards is Satisfactory. The project  involved a certain amount of permanent  land  acquisition  and  temporary  land  occupation.  Involuntary  Resettlement  (OP  4.12) was appropriately triggered. To address this issue, a Resettlement Action Plan (RAP) was prepared and social safeguard activities were well‐handled in compliance with the national law, local regulations, and World Bank  requirements. Through  the  course of  the project  implementation,  the external monitoring  team conducted  regular  surveys.  Based  on  the  survey  of  affected  households  and  interviews  with  key stakeholders, compensations and the process under the RAP were satisfactory enough for the affected people. The details are presented in annex 10. 

Financial Management 

62. The  overall  project  financial  management  (FM)  performance  is  assessed  as  Satisfactory. Appropriate  FM  arrangements  were  in  place  to  ensure  proper  use  of  the  World  Bank  loan  and accounting  of  the  project  funds.  Given  that  the  project  was  implemented  by  a  wholly  state‐owned enterprise  (SOE),  the project’s FM benefited from the SOE’s sound corporate governance and  internal controls.  The  project  audits  were  carried  out  by  independent  auditors  and  the  audit  reports  were submitted  to  the  World  Bank  on  time  in  compliance  with  the  loan  covenant.  Although  some  audit reports  raised  certain  insignificant  finance‐related  problems,  these  problems  were  addressed  by  the borrower  during  implementation  with  the  supervision  of  the  auditors  and  the World  Bank.  Most  of unaudited interim financial reports were provided to the World Bank on time.  

Procurement Management 

63. The procurement performance rating has been satisfactory throughout  the  implementation of the project. The World Bank procurement policies and procedures were followed properly and no major procurement issues were found. The project concluded a total of 144 contracts, of which 57 contracts were funded by the World Bank loan. The largest procurement package was a US$47 million package for the second phase of the LNG plant. To ensure the successful procurement and implementation of this large‐scale plant design and supply contract, the client employed the professional services of a project management  consultant  (PMC)  to  provide  technical  and  project  management  support  for  the  single responsibility  engineering,  procurement,  and  construction  (EPC)  contract  that  was  effectively  and successfully  implemented.  For  disbursement  rate,  there  was  delay  in  the  early  stage  of  the  project. However,  it  was  not  caused  by  the  procurement  issues,  but  the  client  simply  took  a  longer  time  to determine the optimal process technology for the facilities. 

C. BANK PERFORMANCE 

Quality at Entry Rating: Moderately Satisfactory 

Page 27: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 23 of 54

64. The PDO was highly relevant to both the national agenda and the World Bank’s CPS. The World Bank team worked closely with the client to identify specific needs and design the appropriate project components.  The World Bank mobilized a  large  team with necessary  specializations,  including  energy development, gas production, safeguard, resettlement, procurement, and finance. Lessons learned from global experiences were  incorporated  in the project design. One drawback was that  the authorities  in Shanxi Province were not  involved as one of  implementation agencies or  focal points. This  resulted  in restructuring during the implementation. 

Quality of Supervision Rating: Satisfactory 

65. The World Bank team employed regular supervision to review the progress and identify issues on  time. Aide Memoires,  implementation  status and  results  reports,  and wrap‐up presentations were produced  and  always  focused  on  the  key  issues  to  achieve  the  desired  development  outcomes.  The identified  problems  were  properly  reported  to  the World  Bank  management  and  necessary  actions, including  two  restructurings,  were  taken.  The  supervision  task  team  comprised  members  with appropriate  skills,  including  safety,  which  is  very  important  in  a  project  of  this  scale,  to  address  any problems with  the  client.  The  TTL’s  presence  in  China  enabled  a  richer  and more  frequent  dialogue. Support  and  guidance  from  the  World  Bank  team  were  appropriate  and  sufficient.  In  addition  to fiduciary  support, many  technical  recommendations were  offered  to  ensure  efficient  implementation and high‐quality trainings. These efforts reflected in high CBM production, efficient LNG plant operation, and an effective training simulator. The dedication of the World Bank team to the project contributed to better outcomes and higher achievement of the objectives. 

Justification of Overall Rating of Bank Performance Rating: Satisfactory 

66. Although there was a shortcoming in Quality at Entry, it was addressed during implementation without  causing  any  substantial  problems.  The  stakeholders  are  satisfied  with  the  World  Bank’s performance (see annex 7). Given the satisfactory supervision and outcomes,  the overall  rating of  the World Bank performance is Satisfactory. 

D. RISK TO DEVELOPMENT OUTCOME 

Risk of poor O&M: Low 

67. The management and staff of the implementation company were well‐trained in the project and have never  caused any  serious problems and accidents  in  the operation.  This  reliable performance  is based on not only the individual skill sets but also on well‐organized institutional strength. The training simulator has also contributed to maintain the practical O&M skills in the company. The risk related to the future O&M is considered Low. 

Risk of unsustainable fiscal management: Low 

68. The implementation company anticipates stable annual sales of CNY 600 million and profits of CNY 100 million after 2019. Because financial sustainability is one of the indicators, the DSCR, return‐on‐

Page 28: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 24 of 54

assets,  and  current  ratio  have  been  properly  monitored.  The  financial  analysis  confirmed  that  the financial status has been kept stable and is expected to be even better (see annex 6). The financial risk of the company is considered Low. 

Risk of further decline of LNG market price: Modest 

69. The  current  LNG market  price  is  less  than  the  expectation  at  appraisal  stage.  This  downward trend was observed not only  in China but also  in other countries. However, the price cannot be lower than the marginal cost of LNG production. Most of experts,  including the International Energy Agency, predict the gas price will increase in the long run. Having said that, the price can still go down to some extent in the short run and can negatively affect the company’s cash flow. As shown in paragraph 36, 20 percent reduction in the LNG price will lower the FIRR (from 12 percent to 7 percent). Considering the potential impact, the risk related to the LNG price is considered Modest. 

Risk of natural disasters and climate change: Low 

70. The project  sites are  in a  low‐risk earthquake  zone. Now,  the area  is not exposed  to extreme climate disasters such as  typhoons, droughts, and  flooding. Although  future climate change may raise the disaster risk triggered by heavy rain or wind gust, the constructed infrastructure was designed to be resilient enough against natural disasters (for example, 70 m/s wind and 100‐year probability rainfall). A good drainage facility is also well‐developed. The critical properties are insured against severe damages. Therefore, the disaster related risk is considered Low. 

V. LESSONS AND RECOMMENDATIONS 

Lessons Learned from Challenging Experience 

71. Alignment  of  project  objectives  with  the  implementation  agencies  needs  to  be  carefully designed. At appraisal, it was expected for the sole implementation agency to implement the provincial‐level TA components. During  implementation of  the project,  it  turned out to be challenging. Although the issue was addressed in the restructuring, this might have been noticed at the appraisal stage if each entity’s role and responsibility were further discussed and scrutinized. 

72. It could be more cost effective to (a) bundle small separated works and procurements into a consolidated  EPC  contract  with  a  single  responsibility  and  (b)  outsource  a  part  of  construction management tasks. The project concluded a total of 144 contracts. The company encountered a lot of challenges,  especially  in  the  first  phase  of  the  LNG  plant  construction,  in  which  many  separated contracts were concluded. A management cost for the coordination and adjustment among contractors was required. Each small procurement package was  less attractive  for potential bidders.  It  resulted  in construction delay and additional cost. In the second phase of the LNG plant procurement, the PMC and EPC approach was applied.  Then,  the  implementation agency was able  to avoid delay  in  construction and  cost  escalation.  The  second  phase  of  the  LNG  plant  was  efficiently  and  cost‐effectively implemented.  

 

Page 29: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization (P100968)

Page 25 of 54

 

Recommendations Based on Successful Experience 

73. It is vital to prepare for the deployment of new technologies even during implementation. The project paid attention to new technologies that would work better than the original plan. During project implementation, the technical design was adjusted and the L‐type horizontal well technology was used effectively.  Although  this  change  required  the  extension  of  the  closing  date,  it  was  reasonable  to prioritize  the  project  outcome  (maximizing  CBM  production  in  this  case)  rather  than  sticking  to  the original schedule.  

74. Initial  Investment  in capacity building can ensure the project’s sustainability and reduce the life cycle cost. The project established the company’s sustainable training system, including the training simulator. There was a long discussion before the company made the decision to invest in the training simulator because none of the peer companies in the region owned such facilities. After the cost‐and‐benefit analysis, the installation was decided. As a result, the training simulator has greatly contributed to enhancing and maintaining the operators’ skills. Compared to the potential damage caused by lack of capacity,  the  training  cost  is  nearly  negligible  (0.6  percent  on  the  total  cost  in  this  project).  The  LNG plant was designed to last more than 25 years. The operators’ skills must be passed on to the succeeding generations. Tangible training facilities support a safe and efficient operation during the whole asset life.  

 . 

Page 30: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 26 of 54

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS 

     A. RESULTS INDICATORS  A.1 PDO Indicators   

    

 Objective/Outcome: Produce 100 million m3 of CBM in the project area annually when all wells are put into commercial operation 

 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Volume of CBM Produced Annually 

Cubic Meter(m3) 

0.00  0.00  60000000.00  20000000.00 

  20‐Apr‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): The indicator didn't reach the target at the completion. Actual achievement rate in 2017 was 33% of the target. However, the volume of CBM production was still increasing at closing. The production volume was expected to keep increasing because it generally takes about nine months for CBM production to become stabilized and reach its peak after the completion of drilling. It is predicted to surpass the target in the near future and keep improving to reach 145% of the target (See Paragraph 27‐31 and Annex 5). 

     

 Objective/Outcome: Produce 160,000 metric tons of LNG in the project area annually 

 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Volume of LNG Produced  Metric ton  0.00  0.00  160000.00  119000.00 

Page 31: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 27 of 54

 

Annually    20‐Apr‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): The indicator didn't reach the target at the completion. Actual achievement rate in 2017 was 74% of the target due to the government policy change (See Paragraph 29). However, it is predicted to reach 100% of the target in 2019 (See Paragraph 27‐31 and Annex 6). 

     

 Objective/Outcome: Avoid 520,000 metric tons of GHGs Emission from the project area annually 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Avoided GHGs Emission Annually 

Metric ton  0.00  0.00  520000.00  386750.00 

  01‐Dec‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): The indicator didn't reach the target at the completion. Actual achievement rate in 2017 was 74% of the target due to the government policy change (See Paragraph 29). However, it is predicted to reach 100% of the target in 2019 (See Paragraph 27‐31 and Annex 6). 

  

 A.2 Intermediate Results Indicators      

 Component: Exploration and development of CBM production wells 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Numbers of wells drilled in total 

Number  0.00  0.00  126.00  126.00 

  20‐Apr‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): The target was fully met. 93 vertical wells and 33 horizontal wells were constructed. 

   

Page 32: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 28 of 54

   

 Component: Program to assist the project entity in developing its capacity (i) to construct and operate the facilities efficiently and safely, and (ii) to achieve long‐term financial sustainability 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

The number of staff‐week trained for SCBMC 

Number  0.00  0.00  800.00  2150.00 

  20‐Apr‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): The indicator substantially exceeded the end target. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

SCBMC's Financial Sustainability ‐ DSC Ratio 

Number  0.00  1.40  1.40  1.00 

  20‐Apr‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): The indicator didn't reach the target at the completion due to the reduction in LNG sales. However, it is estimated to continue improving and exceed the target in 2020 (See Annex 6). 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

SCBMC's Financial Sustainability ‐ Rate of Return on equity 

Percentage  0.00  9.00  9.00  11.59 

  20‐Apr‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): The indicator exceeded the end target at completion. 

Page 33: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 29 of 54

    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

SCBMC's Financial Sustainability ‐ Ratio of current assets to current liabilities 

Number  0.00  1.10  1.10  0.70 

  20‐Apr‐2009  31‐Dec‐2014  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets): The indicator didn't reach the target at the completion due to the reduction in LNG sales. However, it is estimated to continue improving and exceed the target in 2020 (See Annex 6). 

              

Page 34: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 30 of 54

B. KEY OUTPUTS BY COMPONENT  

Objective/Outcome 1 

 Outcome Indicators 1. Volume of CBM Produced Annually 2. Volume of LNG Produced Annually 3. Avoided GHGs Emission Annually 

Intermediate Results Indicators 

1. Numbers of wells drilled in total 2. The number of staff‐week trained for SCBMC 3. SCBMC's Financial Sustainability ‐ DSC Ratio 4. SCBMC's Financial Sustainability ‐ Rate of Return on equity 5. SCBMC's Financial Sustainability ‐ Ratio of current assets to current liabilities 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 1) 

(Component 1: Investment) 1. 126 CBM wells (93 vertical wells and 33 horizontal wells) were constructed. 2. Gas collection pipelines and the CBM gathering station were constructed. 3. The (first phase and second phase) LNG plants were constructed.  (Component 2: TA) 4. The number of staff‐weeks of training for SCBMC reached 2,150. 5. SCBMC’s financial sustainability was improved. 

 

  

Page 35: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 31 of 54

 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION 

 

A. TASK TEAM MEMBERS 

Name  Role 

Preparation 

Jianping Zhao  Task Team Leader 

James Monday  Senior Enviromental Engineer 

Xiaowei Guo  Senior Procurement Specialist 

Feng Ji  Operations Officer 

Chaogang Wang  Senior Social Scientist 

Haixia Li  Financial Management Specialist 

Peter Meier  Economic Analysis Consultant 

Alan Carter  LNG Consultant 

Edwin Moritz  Gas Production Consultant 

Ivy Cheng  Financial Analysis Consultant 

Franz Gerner  Peer Reviewer 

Wolfhart Pohl  Peer Reviewer 

Youxuan Zhu  Resettlement Consultant 

Norma Leon  Office Manager 

Cristina Hernandez  Program Assistant 

Chunxiang Zhang  Program Assistant 

Supervision/ICR 

Ximing Peng  Task Team Leader 

Yunlong Liu  Procurement Specialist 

Haixia Li  Financial Management Specialist 

Fowzia Hassan  Team Member 

Tianxiu Kang  Team Member 

Chaogang Wang  Social Safeguards Specialist 

Zhuo Yu  Team Member 

Fang Zhang  Team Member 

James Orehmie Monday  Social Safeguards Specialist 

Feng Ji  Social Safeguards Specialist 

Lijun Zhang  Team Member 

Wenqiang Gong  Safety Consultant 

Hua Du  Energy Consultant 

Shanshan Ye  Team Member 

Na Han  Team Member 

Youxuan Zhu  Social Safeguards Specialist 

Yongli Wang  Enviramental Safeguards Specialist 

Vilija Kostelnickiene  ICR Contributor 

Alan David Lee  ICR Contributor 

Li Peng  ICR Contributor 

Takayuki Doi  ICR Main Contributor 

Page 36: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 32 of 54

    

B. STAFF TIME AND COST 

Stage of Project Cycle Staff Time and Cost 

No. of staff weeks  US$ (including travel and consultant costs) 

Preparation 

FY06  2.000  22,689.18 

FY07  9.725  72,192.67 

FY08  24.070  198,792.38 

FY09  9.717  68,563.70 

Total  45.51  362,237.93  Supervision/ICR 

FY09  0  1,539.86 

FY10  6.050  64,804.17 

FY11  7.650  66,208.18 

FY12  5.650  101,497.75 

FY13  5.350  93,755.34 

FY14  3.300  49,934.54 

FY15  6.800  80,390.27 

FY16  7.618  78,765.38 

FY17  11.405  73,272.86 

FY18  6.026  41,627.90 

Total  59.85  651,796.25     

  

   

Page 37: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 33 of 54

ANNEX 3. PROJECT COST BY COMPONENT 

 

Components Amount at Approval 

(US$, millions) Actual at Project Closing 

(US$, millions) Percentage of Approval 

(US$, millions) 

Investment Component (CBM and LNG Development) 

202.6  214.4  105.8 

TA Component (Institutional Strengthening and Capacity Building) 

1.7  1.2  70.6 

Total  204.3  215.6  105.5 

  

   

Page 38: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 34 of 54

ANNEX 4. Project Diagram 

Facilities 

1. The  facilities  constructed  in  the project  include  (a)  CBM production wells,  (b)  a  gas‐gathering plant and collection pipelines, and (c) LNG plants. Gas from the individual wells is transported through collection pipelines to gas‐gathering systems. The gas is transported through main gas pipelines to the processing  plant,  followed  by  liquefaction  in  the  LNG  plants.  The  electric  power  for  the  facilities  is supplied  through  a  35‐kV  transformer  station  in  the  Zhengzhuang  Block.  This  provides  reliable  and relatively low‐cost supply for the field operations. 

Figure 4.1. Facilities constructed in the project 

 

 

   

Page 39: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 35 of 54

Funding Structure 

2. The  project  implementing  agency  (SCBMC)  is  a  special  purpose  company  (SPC)  created  to prepare,  finance, construct, and operate the project  facilities. Shareholders are SOEs. The World Bank loan was made to the Government of China (GOC) following the IBRD’s standard terms and conditions. The GOC loaned the proceeds to the Shanxi provincial government, who then forwarded the proceeds to  the  SPC on  the  same  terms and  conditions. Domestic  financial  institutions  also  loaned  to  the  SPC. Therefore, no private sector financing was directly injected to the project 

Figure 4.2. Funding Structure 

 

Private sector participation 

3. Due to the uncertainty of underground conditions,  it was challenging for  the private sector to make a decision toward CBM development. As they said, the project might catalyze the private sector’s participation. In fact, as shown in table 4.1, private sector financing was mobilized in neighboring CBM developments after 2013 when the project started its CBM production. 

Table 4.1. New Projects in the Neighboring Area after 2013 

Project Name  Year  Investment (CNY, millions)  Public/Private 

Shun Tianda  2014  180  Private 

Huagang  2016  950  Public 

Hao Kun  2016  400  Public‐Private Partnership 

 

Government policy to promote gas utilization 

4. Development  of  gas  has  been  included  in  the  government’s  energy  plan.  Shanxi  provincial government  also  launched  a  provincial  gasification  program  in  2013  to  promote  the  production  and utilization of gas  in Shanxi province.  In 2017, urgent action to promote clean heating was required by the central government in order to address the serious air pollution issues in northern China. The coal‐to‐gas  (replacing  coal  with  gas  for  space  heating)  program  was  a  key  part  of  this  initiative,  and  it included  Beijing,  Tianjin,  Hebei  provinces  and  their  adjacent  regions  including  Shanxi.  Government subsidy was provided for the program. LNG produced under the project has been distributed mainly to be used for city gas, industrial gas consumers and gas filling stations for vehicles. 

 

Page 40: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 36 of 54

ANNEX 5. CBM Production 

1. Increasing  CBM production. The project  closed  in  June 2017.  Since  then,  the volume of CBM production has actually been increasing. It generally takes at least several months for each CBM well to stabilize and reach its peak after the completion of drilling. Most of the wells were constructed in 2017 and will stabilize by the end of 2018. The total CBM production is expected to keep increasing and reach its peak in 2019. Figure 5.1 shows the actual volume of monthly CBM production after the closing date. 

Figure 5.1. Monthly CBM Production (Actual) 

                                              Source: Borrower’s ICR Report.  

2. Long‐term forecast. Based on the track record from 2013 to 2018, it is estimated that (i) ramp rate to the peak at each well is around 85% per year, (ii) peak sustained period is around seven years for vertical wells and around five years for horizontal wells, and (iii) decline rate after peak is around 15% per  year.  Figure  5.2  shows  a  cumulative  curve  of  CBM  production  from  all  126  wells.  The  CBM production volume is forecasted to surpass its end target (60 million m3 per year)  in 2018. It will keep increasing  to  145  million  m3  per  year  in  2019.  Once  each  well  reaches  its  peak  production,  it  can maintain the same level of production for several years. Then the volume will start gradually decreasing. The economic lifetime of the wells is around 15 years, but the SCBMC can construct additional wells in the area if necessary. This can increase the project’s internal rate of return further. 

Figure 5.2. Yearly CBM Production (Actual and Forecast) 

                                Source: Borrower’s ICR Report. 

Page 41: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 37 of 54

ANNEX 6. EFFICIENCY ANALYSIS 

1. Economic  analysis  at  appraisal.  A  cost‐benefit  analysis  was  conducted.  The  economic  costs include yearly  capital  investments and operation expenses,  excluding  tax, duty,  and  financial  charges. The economic benefits include the incremental LNG sales and associated environmental benefits.  

2. At appraisal, the project as a whole (including CBM and LNG production) was estimated to have a baseline EIRR of 25 percent, excluding environmental benefits and 42 percent, including environment benefits  (reduction  of  particulates,  SO2,  CO2,  and methane  emissions).  Key  assumptions  included  the following. The economic benefit of gas production, and of gas input to produce LNG, was valued at the economic  price  for  pipeline  gas.  This  price was  estimated  in  terms  of  opportunity  cost  based  on  the border price of LNG, with a baseline value of CNY 1.17 per m3, constant for all years (lower and higher values  were  tested  in  the  sensitivity  analysis).  This  economic  price  was  higher  than  the  prevailing financial  gas price  in 2009, CNY 0.88 per m3  (excluding  tax), which was  regulated by  the GOC at  that time. The economic benefit of LNG production had a baseline value of CNY 0.75 per m3, calculated as the distributor’s willingness to pay for LNG from the plant (CNY 1.92 per m3) less the value of input gas (CNY 1.17 per m3), also constant for all years.10 The economic value of CO2 equivalent emissions was assumed to be fixed at US$15 per ton. At appraisal, it was conservatively assumed that LNG would be used mainly for power generation. The sensitivity analysis  found  that CBM production would become uneconomic (that  is,  its  EIRR  excluding  environmental  benefits would  fall  below 10  percent)  if  the  amount  of  gas produced was 64 percent of the expected best case, while LNG production would become uneconomic if it added less than CNY 0.44 per m3 in value to gas input. 

3. Financial analysis at appraisal. The project entity was newly established and therefore did not have a record of financial performance. Most of inputs were based on tentative assumptions. The main financial benefit from the project was revenue from LNG sales. The planned production level of the LNG plant  was  200,000  tons  per  year  (fully  operational).  The  financial  costs  are  (a)  capital  cost  of construction, including applicable taxes and duties and (b) O&M costs, including input materials, power, maintenance, depreciation, wages, and administrative expenses. The  largest expenditure  item  is CBM purchase which is needed to keep the LNG plant operating at capacity. 

4. Project costs. The total investment of the project from the beginning to the closing was US$216 million, which is 6 percent higher than the originally estimated cost of US$204 million at appraisal. The slight  cost  increase  was  mainly  due  to  the  first  phase  of  the  LNG  plant  construction,  where  many separate procurements were concluded and a lot of adjustments and management costs were required. Based  on  the  lessons  learned,  this  aspect  was  improved  in  the  second  phase  of  the  LNG  plant construction, for which the PMC and EPC approaches were applied. Because the total cost increase was not significant, the impact on economic and financial sustainability is limited. In fact, additional finance from  the  World  Bank  was  not  required  because  the  implementing  agency  was  able  to  cover  the incremental cost. 

10 The PAD text (page 62) says the difference was assumed to be CNY 1 per m3, but PAD table 9.3 shows a difference of CNY 0.75 per m3.  

Page 42: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 38 of 54

Changes in Assumptions and Methodology for the ICR  

5. Because  the  GOC  deregulated  gas  prices  in  2013,  at  the  time  of  completion,  gas  prices  are negotiated based on net‐back market price and the LNG price is determined by the market. For the ICR, the actual price of gas (excluding tax), negotiated between the SCBMC and its suppler (Petro China), is taken as CNY 1.74 per m3  in 2018,  increasing 3 percent each year  to CNY 1.96  in 2022,  and  constant thereafter. The actual sales price of LNG from the plant  (excluding tax)  is taken as CNY 4,566  in 2013, decreasing  yearly  to  the  lowest  at  CNY  2,531  in  2016  and  recovering  to  CNY  3,299  in  2017.  It  is anticipated that the LNG price could increase in the coming years with the recovery of global economy and growth of natural gas demand in China. The LNG price was assumed at CNY 3,800 per ton in 2018, increasing yearly to CNY 4,200 in 2019, CNY 4,500 in 2020, CNY 4,700 in 2021, and CNY 5,000 in 2022.  

6. Overall, the EIRR, excluding environment benefits is 15 percent. The lower EIRR than anticipated at  appraisal  can  be  attributed  to  the  longer  construction  period  (2011  to  2018)  than  anticipated  at appraisal  (2009  to  2011),  higher  investment  cost,  and  lower  LNG  price  in  the  first  several  operation years. This, in turn, is due to the lower‐than‐expected rate of the CBM and LNG production to date, for reasons  explained  earlier  in  the  ICR.  Nonetheless,  the  EIRR  remains  higher  than  the  World  Bank’s benchmark of 12 percent.  

7. The EIRR is higher when environment benefits are included, along similar lines to the analysis at appraisal.  For  the  purposes  of  the  ICR,  quantification  of  environmental  benefits  focuses  on  CO2 reductions associated with the use of LNG to displace other, more carbon‐heavy fossil fuels. Specifically, the EIRR,  including CO2 benefits  is  found  to  increase  to 18 percent using an updated methodology.  It would be higher still if local pollutants and methane were also included. The methodology to calculate the avoided CO2 emissions is revised in accordance with the actual track record and recent guidance on carbon  pricing.  In  contrast  to  the  appraisal  assumption  of  LNG  use  for  power  generation,  it  has  in practice  been  used  mainly  for  industrial  use,  city  gas,  and  car  fuels.  To  estimate  the  avoided  GHG emission more accurately,  the replacement of LNG  in  these sectors was analyzed based on the actual information  collected  by  the  company.  For  industrial  use,  LNG  is  mainly  used  in  gas‐fired  boilers  to replace coal‐fired boilers. For city gas use, LNG is assumed to also mainly replace coal. For the car fuel use, LNG  is assumed to replace gasoline, which  is more carbon‐intensive than LNG. The proportion of different  uses  of  LNG  has  been  analyzed  according  to  the  actual  sale  information  in  2016  and  2017 provided  by  the  company.  For  different  uses,  the  replaced  coal  and  gasoline  consumption  and  the avoided CO2 emissions are calculated. The social value of carbon suggested in the Guidance Note Social Value of Carbon in Project Appraisal September 2014 is adopted in the analysis. Key inputs and results at appraisal and completion are summarized in table 6.1. 

Table 6.1. Key Input Values and Results for Economic Analyses at Appraisal and At Completion 

Row  Parameter  Unit  Appraisal  Completion 

  Assumptions       

1.   Exchange rate  CNY/US$  6.83  6.30 

2.   Electricity tariff (excluding tax)  CNY/kWh  0.398; 0.45  0.511 

3.   Economic value of gas   CNY/m3  1.17  1.30 to 1.76 

4.   Economic value of LNG  CNY/m3  1.92  1.65 to 3.27 

5.   Added value of LNG compared to value of gas (for a given year) 

CNY/m3  0.75  0.36 to 1.50 

Page 43: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 39 of 54

Row  Parameter  Unit  Appraisal  Completion 

6.   Average CO2 emissions reduced per unit of LNG consumed11 

tCO2/ton of LNG 

3.25  1.52 

7.   Economic value of CO2 emissions avoided12  US$/tCO2  15  21 to 56 

8.   Effective operating lifetime  years  18  19 for CBM 25 for LNG 

  Implementation data       

9.   Total project investment  US$, million  204  216 

10.   Gas production peak volume  106 m3/year  213  145 

11.   Gas production peak year  year  2012  2019 to 2020 

12.   LNG production peak volume  106 m3/year  323  180 

13.   LNG production peak year  year  2012 onward  2020 onward 

  Economic and Financial Analysis Results       

14.   FIRR (including tax)  %/year  9  12 

15.   EIRR excluding environmental benefits    25  17 

16.   EIRR including benefits of reduced particulates, SO2, CO2 and CH4 

%/year  42  N/A 

17.   EIRR including benefits of reduced CO2    N/A  19 

8. Sensitivity  analysis. Whereas  it  is  impossible  to  precisely  predict  the  future  LNG  prices,  the volatility  is  considered  and  tested  in  sensitivity  studies.  Even with  a  20 percent  reduction  in  the  LNG price, the FIRR is estimated to be 7 percent. 

9. Economic value of the project. Major economic value added by the project is LNG produced as the energy source as shown in figure 6.2. The LNG plant, with an annual production capacity of 200,000 tons, was built in the project and is already functional. Although the CBM production from the project is anticipated to start decreasing gradually around 2024, the LNG plant’s functionality will last for at least 25 years. Further, the implementation agency plans to develop new wells  in the area to keep its CBM production (with additional investment) and maintain at least 160,000 tons of LNG production volume. Other  assumptions,  including  operating  costs  and  environmental  benefits  are  estimated  under  the reasonable prediction linked to the LNG production. 

11 At appraisal, LNG was presumed to replace power generation with an emissions factor of 899 g CO2 per kWh. At completion, LNG is estimated to replace use of other fossil fuels for industry (75 percent), city gas (15 percent), and vehicles (10 percent). 12 World Bank 2015 guidelines recommend US$30 per ton in 2015 rising to US$65 per ton in 2040 as a base case social cost of CO2. 

Page 44: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 40 of 54

Figure 6.1. Economic value of the project 

                    Source: Authors. 

10. Financial  sustainability.  Table  6.2  shows  two  important  financial  indicators  for  5  years  from now.  In addition  to  the World Bank  loan,  the  company has borrowed a  certain amount of  fund  from several  domestic  financial  institutions  (details  are  provided  in  annex  7).  The  repayment  and  interest could be a severe burden and a future risk to financial sustainability. However, as the LNG production is operating normally, the financial situation of the company is expected to continue improving. 

Table 6.2. Financial sustainability indicators (Forecast) 

  2019  2020  2021  2022  2023 

Current ratio  0.64  1.12  1.74  2.91  4.08 

DSCR  1.30  1.79  1.74  5.65  5.62 

  

   

Page 45: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 41 of 54

ANNEX 7. BORROWER, CO‐FINANCIER, AND OTHER PARTNER/STAKEHOLDER COMMENTS 

1. The following is the summary of the stakeholders’ comments. 

Project Implementation Agency (SCBMC) 

2. The World Bank’s services were very satisfactory. During the implementation of the project, the following were observed: 

Timely response. Regarding the issues raised, the World Bank experts gave timely answers and worked with  excellent  cooperation.  As  for  the  payment  procedure,  the World  Bank completed the payment within three working days.  

Lending  terms  and  conditions.  The  lending  condition  was  reasonable,  according  to  the financial agreement signed by our company with the Ministry of Finance of Shanxi Province on March 28, 2011. Compared to other financial institutions, including domestic banks, the World  Bank  loan  allowed  a  longer  repayment  period,  lower  interest  rates,  and  a  longer grace  period.  The  repayment  was  designed  to  increase  when  the  production  capacity becomes fully online, thus being in line with the actual needs of the company.  

Technical  support.  Since  the  start  of  the  project,  the World  Bank  had  provided  several trainings  on  procurement,  finance,  and  project  management.  With  these  trainings,  the company  management  personnel  were  greatly  informed.  The  advanced  management experience  and  lessons  learned  from  the  World  Bank’s  other  projects  were  greatly beneficial. The World Bank also provided strong technical support for the construction of the  company's  liquefaction  plant  and  upstream  gas  drilling.  The  United  States  experts reviewed the technical specifications and design of the liquefaction plant and the upstream development technology. The in‐depth discussions played a significant role  in the project decision making. 

Support from the World Bank team. The team provided valuable advice and ensured the smooth progress of the project. The team was patient and careful in their supervision and cared about all aspects of the project. The TTL actively helped the communication between the  Ministry  of  Finance,  the  National  Development  and  Reform  Commission,  and  the project  company.  The  TTL  coordinated  the  smooth  implementation  and  made  great contributions  to  the  project.  The  safety  expert  visited  the  site  and  established  the sophisticated  simulation  system.  The  environmental  safeguard  expert  demonstrated outstanding  professional  skills  in  solving  specific  issues.  The  social  safeguard  specialist cared  about  the  people's  livelihood.  He  thoroughly  understood  the  situation  of  land acquisition  and  conducted  meticulous  investigation  to  quickly  resolve  issues.  The procurement specialist had a high  level of professionalism and was very responsible. The FM specialist was patient and provided detailed explanations every time.  

Page 46: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 42 of 54

3. After  years  of  joint  efforts,  the  project  was  completed  in  strict  accordance  with  the requirements of the World Bank and was remarkably successful in construction, quality, and technology, while also producing satisfactory results. 

The Largest Shareholder (Shanxi Energy Industries Group Co., Ltd.) 

4. The project is evaluated as highly successful. 

5. Demonstration of clean energy development. There was a significant technical development in the project. It became a good showcase for the CBM industry.  

6. Government  support.  The  Shanxi  Province  has  been  known  for  its  great  CBM  potential. However, due to the uncertainty of geological conditions, it was not easy for a company to promote the upstream well development. The Government considers CBM as one of the strategic industries in Shanxi Province and has provided the company a great deal of administrative support, which ensured smooth implementation. 

7. The World Bank  assistance.  The  company  is  satisfied with  the World Bank’s assistance. From the  beginning  to  the  end,  the  World  Bank  team  showed  professionalism  and  dedication.  In  every implementation support mission,  the company had productive discussions and  learned a  lot  from the World  Bank’s  knowledge  and  experience.  The  mission  helped  the  company  properly  keep  track  of milestones as well. 

8. Social benefit. The project created new job opportunities for the local community. In addition, the  road  prepared  for  the  construction  was  used  by  villagers  and  has  been  highly  appreciated.  The World  Bank’s  safeguard  specialists  accurately  captured  the  local  needs  and  kept  providing  practical instructions. 

9. Lessons  learned. The procurement was challenging  for  the company  in  the early  stage of  the project.  The  company  encountered  a  lot  of  difficulties  especially  in  the  first  phase  of  the  LNG  plant procurement,  in  which  many  separate  contracts  were  concluded.  It  resulted  in  some  delay  and additional costs. Upon the World Bank’s advice, the company applied the PMC and EPC approach for the second  phase  of  the  LNG plant.  It worked  successfully.  The  company  recommends  the  PMC  and  EPC approach for projects of similar scale and nature. 

10. Future  projects.  The  company  is  satisfied  with  the  project’s  result  and  the  World  Bank’s performance.  The  company  will  continue  exploring  the  opportunities  for  further  green  energy developments.  If  an  occasion  arises,  continuous  cooperation  with  the  World  Bank  will  be  highly appreciated.  

Shanxi Provincial Government Agency (Finance Bureau)  

11. The  collaboration  among  the  World  Bank,  the  company,  and  the  Government  is  highly appreciated, especially in the following aspects: 

Decision‐making process. When the project was appraised, it was not easy to evaluate the risk in the CBM project. Due diligence conducted by the World Bank’s experts provided a 

Page 47: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 43 of 54

good  guidance  for  the  Government  as  well.  This  experience  accelerated  clean  energy development in Shanxi Province. 

Changes  in  technical  design.  During  the  implementation  of  the  project,  the well  drilling technology  was  significantly  developed.  The  World  Bank  continuously  provided  TA  and supported  the  company  to  use  the  best  available  technology.  The  World  Bank’s involvement helped the other lenders’ internal approval processes. 

Lenders’  coordination.  In  the  early  phase  of  the  project,  equity  injection  from  the shareholding companies was delayed. The World Bank and other lenders collaborated on the  issues  that  resulted  from  the  abovementioned  delay  with  continued  efforts. Consequently, it was possible to maintain a sound debt‐and‐equity balance, including the Government subsidy. The details are shown in table 7.1. 

Table 7.1. Equity and Debt Balance (CNY, millions) 

Fund Composition  Entity  Amount 

Equity 

Shanxi Energy Industry Group Co., Ltd.  173.4 

Shanmei Investment Group Co., Ltd.  102.0 

Shanxi Gas Industry Group Co., Ltd.  64.6 

The World Bank  IBRD  517.9 

Domestic Lending 

Industrial and Commercial Bank of China Hi‐tech Development Zone Branch 

76.5 

43.2 

102.0 

173.4 

93.1 

China Clean Energy Development Fund Management Center  60.0 

Shanxi SME Venture Capital Fund (Limited Partnership)  20.0 

Shanxi Energy Industry Group Co., Ltd.  30.0 

Government subsidies (including fiscal discounts and CBM drainage subsidies) 

19.4 

Total    1,475.5 

  

   

Page 48: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 44 of 54

ANNEX 8. SUPPORTING DOCUMENTS 

 1. Country Partnership Strategy FY2006–2010 

 2. Country Partnership Strategy FY2013–2016 

 3. China 2030 Building a Modern, Harmonious, and Creative Society (2013) 

 4. Project Appraisal Document 

 5. Loan Agreement 

 6. Resettlement Action Plan 

 7. Environmental Assessment 

 8. Aide Memoires 

 9. Implementation Status and Results Reports 

 10. Borrower’s ICR Report 

 11. CBM Development Technology Report (China University of Mining) 

 12. China boosts CBM output in 2017 (AsiaElec, Asia Power Monitor, February 2018) 

 13. Europe needs China’s help to clear the LNG market (Goldman Sachs Commodities Research, May 2017) 

14. China’s dash for gas runs into supply constraints (Goldman Sachs Commodities Research, December 

2017) 

   

Page 49: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 45 of 54

ANNEX 9. ENVIRONMENTAL SAFEGUARDS

1. The project  involved extractive activity  in  a mountain  area  and  construction of  an  LNG plant, thus the soil erosion, vegetation clearance, and safety issue of primary concern were identified. Given its nature  and  scale,  it  was  appropriately  classified  as  Category  A,  with  the  Environmental  Assessment (OP/BP 4.01) being triggered.  

2. An Environmental Impact Assessment and an Environmental Management Plan (EMP), including a  Safety  Management  Plan  were  prepared  during  project  preparation.  They  addressed  the environmental impacts that may arise from the construction and operation of well drilling and the LNG plant. A comprehensive analysis of alternatives was conducted  for the site  location for the LNG plant, compression  station  and  pipeline  route,  and  for  the  technology  for  wastewater  treatment.  So,  the environmental  impacts  of  primary  concern were minimized  or  adequately mitigated.  In  addition,  the mitigation measures were well‐incorporated into the project design and EMP.  

3. During implementation, the implementation agency assigned a dedicated environmental officer and  engaged  an  external  environmental  monitoring  consultant  to  carry  out  the  required monitoring programs.  The  environmental  monitoring  reports  were  regularly  submitted  to  the  World  Bank  for review. Overall, the project EMP implementation is Moderately Satisfactory in that (a) the spoil was not adequately managed at the beginning; (b) the vegetation restoration was not immediately conducted at the beginning; (c) the remedy was conducted with enhancement in training and supervision on‐site by the enterprise;  (d)  there were no residual  impacts; and  (e)  the project environmental monitoring was conducted properly and well documented. 

4. In  addition,  as  a  remedy,  the  enterprise  changed  its  environmental  consultant  and  allocated more  resources  to  improve  its  environmental  management.  The  most  crucial  factor  that  drove  the implementation  of  its  EMP  in  the  right  direction  was  the  awareness  improvement  of  the  enterprise management.  The  training  for  the  enterprise  leaders,  and  particularly  the  good  result  of  the  on‐site environmental facilities that improved the project’s profile, largely accelerated the learning curve of the enterprise management.  

5. The internal system for safety management was established with proper institutional structure and  adequate  budget  support,  which  will  ensure  the  sustainable  management  of  the  safety  issue  in operation  stage.  This  system  is  comprehensive  and  comprises  a  safety  assessment,  leadership responsibility,  an  emergency  preparedness  plan,  specific  operation  procedures,  a  training  plan,  and regular  examination.  In  addition,  the  strong  safety  awareness  of  the  management  promoted  the progress of standardization in the safety operation. The enterprise passed and obtained the certificate of Class  III  for  safety  standardization  in 2015 and pledged  to meet  the  requirement  for Class  II  safety standardization in one or two years. 

   

Page 50: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 46 of 54

ANNEX 10. SOCIAL SAFEGUARDS AND RESETLEMENT 

 1. The project includes two physical components. One is the LNG plant component and the other is the  gas  exploration  and  collection  component.  Both  involve  certain  amounts  of  permanent  land acquisition and temporary land occupation. To address such impacts, a RAP was prepared during project preparation, which was approved by the World Bank.  

2. The land acquisition was implemented first for the LNG plant site, which involved acquisition of 112 mu (74,667 m2) of land area from Dongshan and Jinfeng villages. The adopted compensations were either the same or higher than that in the RAP. The 13 households who lost their 12.8 mu (8,533 m2) of contracted  land were  provided with  land  compensation,  green  crop  compensation,  and  allocation  of replacement of farmland. For the other acquired rural land, except for compensation of green crop and attachments, all  compensations were kept  in  the village as a village development  fund. The  fund was used to develop new farmland, improve village infrastructure, provide support to vulnerable groups, and set up social security insurance for the elderly. 

3. Along  with  permanent  land  acquisition,  additional  land  areas  were  acquired  temporarily  for construction  of  related  facilities,  such  as  transmission  lines,  gas  pipelines,  access  roads,  and  flood control  facilities,  which  amounted  to  132  mu  (88,000  m2)  of  land  area  and  CNY  0.75  million  of compensations. All the compensations were delivered to the affected households.  

4. In addition  to  the compensations  received  for  the  land acquisition,  the LNG plant project also brought  considerable  social  benefits  to  the  village.  According  to  the  social  survey, most  villagers  had experienced a significant increase of income during the project construction, which was contributed by working for the company, providing labors on construction sites, leasing houses to construction workers, and selling vegetables and farm products to the contractors. By the end of 2016, the average per capita income  in  the village had  reached CNY 13,000 per  capita, which was 172 percent higher  than  that  in 2008 when the land acquisition took place (CNY 4,780 per capita).  

5. For the gas exploration and collection component, the gas exploration area was changed during project implementation. As a result, a supplement RAP for the gas exploration component was prepared in 2012 and submitted to the World Bank in 2013. According to the supplement RAP, only gas storage stations  would  involve  permanent  acquisition  of  17  mu  (11,333  m2)  of  unused  land  area.  For construction of other  facilities,  they would  involve  temporary  land occupation of 1700 mu  (1,133,333 m2)  land  area.  About  90  percent  of  the  affected  land  areas  are  woodlands,  with  10  percent  being farmlands or other rural lands. Most of the affected land areas are in three villages and two state‐owned forest  farms.  In  terms  of  compensation  policies,  for  both  permanent  land  acquisition  and  temporary land occupation, the proposed compensations were either the same or higher than that in the previous RAP.  

6. In  the  beginning,  the  implementation  of  the  component  moved  slowly.  To  facilitate  the implementation,  20  experimental  gas  wells  were  developed.  The  first  group  of  wells  temporarily occupied  106  mu  (70,667  m2)  of  land  area  from  two  villages.  All  compensations  were  paid  to  the affected villages. Following the experiments, a total of 126 gas wells were developed by the end of 2017, including 33 horizontal gas wells and 93 vertical gas wells. The  land acquisitions  for all gas wells were 

Page 51: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 47 of 54

completed in 2016.  

7. According  to  the  statistics  by  the  company,  a  total  of  896 mu  (597,333 m2)  of  land  area was acquired, including 621 mu (414,000 m2) of land area temporarily leased by the company, and 275 mu (183,333  m2)  of  woodland  being  permanently  acquired.  In  addition,  about  28  mu  (18,667  m2)  of concrete surface rural road have also been occupied. For all these land occupation and land acquisition, following the provision in the RAP, compensations have all been paid to the affected parties.  

8. Only  the  land  area  of  one  gas  storage  site  (14  mu  or  9,333  m2)  has  not  yet  been  formally acquired. This  is because the originally acquired site was  located under the transmission  line, which  is considered as inappropriate for gas storage construction. As a result, an alternative site was provided by the  local government. Because  the  site  is  located  in  the area without a  land utilization plan,  the  land acquisition had to wait for the completion of land use readjustment by Qinshui County. According to the company,  such  a  readjustment was  finally  completed  at  the  end  of  2017.  As  of March  2018,  a  land acquisition application is being prepared by the county land resources bureau, which will be submitted to  the provincial  land  resources department  for  approval. At  the  same  time, under agreement of  the local government, civil work construction for gas storage stations is being carried out with a temporary land  occupation  arrangement.  The  affected  village will  be  provided with  full  compensation  once  the approval of land acquisition is obtained. It is hoped that the formal land acquisition procedure could be completed in 2018 to create conditions conducive to begin operation of the gas storage site.  

9. Through  the  course  of  project  implementation,  the  external monitoring  team  has  conducted regular  monitoring  activities  for  the  project  and  produced  a  total  of  eight  resettlement  monitoring reports.  Based  on  a  sample  survey  of  the  affected  households  and  interviews with  key  stakeholders, these  monitoring  reports  provided  a  comprehensive  review  of  land  acquisition  performance  for  the project.  According  to  these  reports,  the  affected  people  were  consulted  for  various  land  acquisition impacts,  all  compensations  following  the RAP were paid  to  the  affected people,  and  the process  and outcome of resettlement were found to be satisfactory for the affected people. 

  

   

Page 52: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 48 of 54

ANNEX 11. TECHNICAL DEVELOPMENT (L‐type Horizontal Well Technology) 

1. Technical  development. The  L‐type horizontal well  technology played a  significant  role  in  the project.  Considering  the  depth  of  the  coal  seam  in  the  Qinshui  Basin  (>800  m),  vertical  wells  were considered the most appropriate for the project site at the appraisal stage. Horizontal wells had shown good production only in areas of shallow depth. On the other hand, the horizontal well technology is still new and has been under rapid development. This includes four generations: the first generation (multi‐branch  horizontal  wells),  the  second  generation  (double‐maintenance  or  main‐supported  horizontal wells),  the  third generation  (U‐shaped segmented horizontal wells), and the  fourth generation  (L‐type segmented fracturing horizontal wells). The capability of the CBM production has been improving step by step. 

2. Improvement  in the L‐type horizontal well. The fourth generation (L‐type) horizontal well has achieved  significantly  good  and  stable  gas  production  compared  to  previous  generations.  The  third generation (U‐type) horizontal wells needed to be connected to a vertical well at the far end of the main wellbore of  the horizontal well  for  gas  drainage. Due  to  the  complexity  of  the  configuration,  a  lot  of inspection  and  maintenance  works  are  required.  The  L‐type  horizontal  wells  have  simpler configurations, require less O&M costs, and can offer higher production. 

Figure 11.1. The Third Generation (U‐type) Horizontal Well 

 

                                                 Source: China University of Mining and Technology. 

Page 53: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 49 of 54

Figure 11.2. The Fourth Generation (L‐type) Horizontal Well 

 

                                                  Source: China University of Mining and Technology. 

3. Output Efficiency. The project is located at the Zhengzhuang‐Libi Cooperation Block in the mid‐deep part of Qinshui Basin. The target  layer has a thickness of 5.3–6.1 m at a depth of around 800 m with a methane content of 11–24 m3 per ton. This layer has typical characteristics of high buried depth, high  reservoir  pressure,  high  ground  stress,  and  low permeability.  The  Zhengzhuang‐Libi  Cooperation Block covers an area of 50 km2, accounting for 6 percent of the Zhengzhuang Block with an area of 834 km2.  At  present,  the  methane  output  per  vertical  well  is  up  to  950 m3  per  day  and  the  output  per horizontal  well  is  up  to  12,000  m3  per  day,  both  of  which  are  significantly  higher  than  those  of neighboring blocks with similar geological conditions. The difference can be seen in table 11.1.  

Table 11.1. Comparative Statistics of Methane Output of Neighboring Blocks 

No.  Name of Block  Developer  Type of well Output from Single Well (m³/d) 

Difference a 

(%) 

1  Zhengzhuang‐Libi Cooperation Block (The project) 

SCBMC (project implementation agency) 

Vertical  950  100 

2  Horizontal  12,000  100 

West of Zhengzhuang Block 

Huabei Oilfield 

Vertical  450   48 

Horizontal 

1,868  16 

5  1,856  16 

6  2,673  22 

7 South of Mabi Block  Asian American Gas, Inc 

Vertical  527  56 

8  Horizontal  4,219–5,563  35–46 

9 West of Shizhuangnan Block 

China United Coalbed Methane Corporation, Ltd 

Vertical  460  48 

Source: Liu Shenggui, Associate Professor, China University of Mining and Technology. Note: a. Take the output of single well of Shanxi Coal Bed Methane as reference to describe the output differences 

with neighboring blocks. 

Page 54: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 50 of 54

4. Awards. The  implementation agency (SCBMC) explored the adaptability of horizontal wells for the project.  The analytical  studies  indicated  that  the use of  the  L‐type horizontal wells was  the most economical  for  several  locations.  The  SCBMC decided  to use  the  L‐type horizontal well  technology  to develop CBM in the depth of 800 m to 1,000 m. After the project, peer companies  (Petro China, Blue Flame,  and  so  on)  have  also  successively  used  the  L‐type  horizontal  well  technology.  Due  to  these achievements,  the  SCBMC  obtained  the  national  high‐tech  enterprise  certification.  In  addition,  the company was awarded the title of Taiyuan Municipal Technical Center.    

Page 55: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 51 of 54

ANNEX 12. PHOTOS OF PROJECT SITES 

Well Drilling (under implementation) 

 

 

Vertical Well (after completion) Horizontal Well (after completion) 

 

Zhengzhuang‐Libi Cooperation Block (Upstream gas drilling area) 

 

Page 56: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 52 of 54

Road Constructed for the Project 

 

Gas‐gathering Station 

 

Vegetation Restoration in the Well Drilling Sites 

 

Power Distribution for Well Facilities       Antenna for Remote Well Monitoring 

 

Page 57: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 53 of 54

LNG Plant            LNG Tanks 

 

SCBMC Office                                                                  LNG Plant Surveillance Monitors 

 

Training Simulator 

 

Fitness Facilities for LNG Plant Operators 

 

Page 58: Document of The World Bankdocuments.worldbank.org/curated/en/... · CPS Country Partnership Strategy ... No. Date ISR Archived DO Rating IP Rating ... The Government was also taking

The World Bank Shanxi Coal Bed Methane Development and Utilization ( P100968 )

Page 54 of 54

MAP (CHN43541)