Your New Data Center
data stations + solutions
![Page 2: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/2.jpg)
So, you finally decided to come out of the closet…
![Page 3: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/3.jpg)
and get into a data center
![Page 4: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/4.jpg)
If I told you how to SAVE
…would you be interested?
MONEY TIME ENERGY
36%-78%less on
your monthly
lease
get your data
center in weeksnot years
reduce electricity consumed
by
43%
![Page 5: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/5.jpg)
1. MONEY savings
too smallretail / collocation
few racks
$300kW / month
too bigwholesale
10,000 sq.ft raised floor
$125kW / month
till now, you’ve had two choices
![Page 6: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/6.jpg)
DockIT is just right
kW / month
mini-wholesale
![Page 7: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/7.jpg)
DockIT is cost effective
• Traditional data center: 60% of the capital cost goes into:
generators, chillers and batteries
• DockIT infrastructure cost is17% with smaller containers
flywheel UPS + generatorelectrically powered chiller
![Page 8: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/8.jpg)
2. TIME savingsYou purchase or lease:Data Center Container from
H-P VerariIBM SunDell RackableAPC AST
DockIT (or you) purchase or lease:
Back-Up Power Container: Active Power, or Others
Chiller Container from:Active Power, TAS or Others
![Page 9: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/9.jpg)
DockIT saves time
• Vendors take 6 weeks to build, commission and ship containers.
• DockIT pre-builds data stationbuilding. Everything is ready for arrival of containers.
• Could take you 18-24 months to design and build your own building.
![Page 10: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/10.jpg)
DockIT Data Station20 mini-wholesale data centers
electricity pre-wiredplenty of Internet providersroof over data center containerconcrete pad for support containersoffices
![Page 11: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/11.jpg)
150 to 650 kW per container7 internet service providersconcrete tilt-slab buildingoverhead utility corridorsperimeter security
DockIT Data Station
Offices + Operations
Data CenterUPS + Generator
Chiller
designed & pre-built for containers
![Page 12: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/12.jpg)
DockIT reduces risk•No real estate•No building design•No permitting•No construction•No delays•Plug and Play
![Page 13: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/13.jpg)
3. ENERGY savings
big data centers:approx. 1.8 to 2.2
DockIT data centers:
1.25 or less
Power Usage Effectiveness (PUE) = total facility power
divided byIT equipment power
![Page 14: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/14.jpg)
DockIT saves electricity
• Typical data centers work at 30% of the rated capacity--very inefficient
• DockIT generators and chillers are modular, match the load and run 75% of capacity--very efficient.
• Buy or lease just the capacity you need--no more waste.
![Page 15: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/15.jpg)
FINAL THOUGHT
Your not going to buy just one data center.
![Page 16: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/16.jpg)
Conventional Wisdom
“Put all of your eggs in one basket and then watch that basket.”
Andrew Carnegie
![Page 17: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/17.jpg)
Current Wisdom
“Put copies of your eggs in many little baskets”
DockIT Network
Northern Virginia
New York Chicago
Silicon Valley
Los Angeles
Dallas
![Page 18: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/18.jpg)
Data Center Biodiversity• Not everything needs to be Tier III
10%-15% high density + redundancy10%-15% medium density + redundancy70%-80% low density + little redundancy
• Mix and match Tier levels within a DockIT data station or between DockIT sites.
• DockIT has robust monitoringsystems and software.
• Dock IT is vendor neutral.
![Page 19: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/19.jpg)
Contacts
Eliza I. Wojtaszek, CEOElectrical [email protected] 930-7733
Frank J. Piatkowski, COOArchitect & Developerfpiatkowski @yahoo.com202 330-9725
![Page 20: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/20.jpg)
DockIT is ready now
• Gainesville,Virginia
• Ready for occupancy:6 containers
• Construction started: 20 containers
![Page 21: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/21.jpg)
One more thing…
For server huggers, instead of containers,For server huggers, instead of containers,we can put regular racks in our data station.we can put regular racks in our data station.
![Page 22: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/22.jpg)
Back-Up Slides
![Page 23: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/23.jpg)
DockIT location
eGainesville
Virginia
![Page 24: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/24.jpg)
Mini-wholesale data centerData Center Container• 1 to 20 racks• up to 1,200 blade servers• 175 to 625 kW= 4,000 sq.ft. of raised floor Generator + UPS• Match data center load• Tier I to Tier IVChiller Container• 120 tons of cooling--average• 67 degree water--closed loop
with data center container
![Page 25: Dock It Customer Intro 14 Aug 09](https://reader034.vdocuments.site/reader034/viewer/2022051323/5495fc2eac7959482e8b4f1f/html5/thumbnails/25.jpg)
Checklist for your data center• Power: 130-825 kW• Connectivity: 5 Internet providers• Building:
concrete walls: 7 ¼” thickoutdoor pad: 1,800 sq.ft. 50% coveredindoors: 900 sq.ft. offices air conditioned
• Security: perimeter access and alarms, each box has additional alarm system
• Fire Protection: sprinkled buildingeach box also has fire suppression system
• Permits: boxes are non-occupied equipment generator emissions