Program Review Suggested Preparation Timeline Activity Timeline for Completion Program Review Committee liaison meets with 6-12 months prior to deadline department/functional area/unit director/ leadership team Identify internal department/functional 6-12 months prior to deadline area/unit review team Program Review Committee liaison meets with 6-12 months prior to deadline department/functional area/unit review team Set review team meeting times 6-12 months prior to deadline Write self-study 6-12 months prior to deadline Identify internal/external reviewers for site visit 2-3 months prior to deadline Conduct site visit 3 months prior to deadline Site visit report submitted to department/ 1 month after site visit functional area/unit Submit action plan By review deadline

Upload: others

Post on 14-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Division of Student Life | University of Oregon - … · Web viewSite visit report submitted to department/1 month after site visit functional area/unit Submit action plan By review

Program ReviewSuggested Preparation Timeline

Activity Timeline for CompletionProgram Review Committee liaison meets with 6-12 months prior to deadlinedepartment/functional area/unit director/leadership team

Identify internal department/functional 6-12 months prior to deadlinearea/unit review team

Program Review Committee liaison meets with 6-12 months prior to deadlinedepartment/functional area/unit review team

Set review team meeting times 6-12 months prior to deadline Write self-study 6-12 months prior to deadline

Identify internal/external reviewers for site visit 2-3 months prior to deadline

Conduct site visit 3 months prior to deadline

Site visit report submitted to department/ 1 month after site visitfunctional area/unit

Submit action plan By review deadline

Present executive summary to SLLT First available SLLT meeting after conclusion of program review

Disseminate results In consultation with VPSL and Strategic Communications and Marketing