district heat project august 2012

Upload: keithmontpvt

Post on 05-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 District Heat Project August 2012

    1/23

    DISTRICT HEAT PROJECT

    August 22, 2012

  • 7/31/2019 District Heat Project August 2012

    2/23

    Key Points

    Project is within budget

    Ongoing operation is viable Citys risks are addressed

    Project goals are met

  • 7/31/2019 District Heat Project August 2012

    3/23

    Recommended Action

    Authorize City Manager to proceed with project Notify the State and DOE of this decision Continue signing up customers

    Issue bids in September for receipt in October Review bids in November, consider project adjustments.

    Award contract.

    Consider options for use of available funds, possibleadditional assistance for connections.

    Begin construction in spring of 2013 Provide Thermal Energy to Customers on 10/1/13

  • 7/31/2019 District Heat Project August 2012

    4/23

    Presentation

    Overall Project Description and Funding Summary Project Costs

    Customer Commitments City/School heating costs Financing Package Citys Risk System Management, City Goals and Master Plan,

    Assumptions and Projections, City Votes

    Recommended Action

  • 7/31/2019 District Heat Project August 2012

    5/23

    Project Goals

    Reduce emissions

    Replace oil with regional fuel source

    Stabilize heating costs for city/school

    Economic development opportunity for downtown

    Citys project costs within current expenses

  • 7/31/2019 District Heat Project August 2012

    6/23

    Project Summary

    State Central Heating Plant 40.2 MMBTU capacity

    City Distribution System 9.71 MMBTU (24%) of stateplant, ability to purchase up to 16.3 MMBTU

    Both Public and Private Customers

    Primarily Wood Chips for winter fuel (Oct April)

    Summer Hot Water through system boilers

  • 7/31/2019 District Heat Project August 2012

    7/23

  • 7/31/2019 District Heat Project August 2012

    8/23

    Overall Funding Summary

    Federal Department of Energy $8.00 million State of Vermont Capital Funds $7.00 million State of Vermont In Kind $1.20 million City of Montpelier 2011 Bond $2.00 million CEDF Grant $1.00 million CEDF Loan, 1%, deferred payment $0.75 million Forest Service Grant (new) $0.248 million Village Green Grant (new) $0.10 million TOTAL $20.298 million

  • 7/31/2019 District Heat Project August 2012

    9/23

    Funding Allocation

    State Funds for heat plant $8.200 million DOE Grant to state for heat plant $3.249 million DOE Grant to state for city capacity $2.558 million

    City/CEDF funds to state for capacity $1.077 million DOE Grant to city for dist. system $2.193 million City/CEDF funds for dist. system $2.673 million Other grant funds for dist. system $0.348 million Total for Central Heating Plant $15.047 million Total for Distribution System $5.214 million

  • 7/31/2019 District Heat Project August 2012

    10/23

    Overall City Funding Status

    TOTAL Distribution System $ $5,214,419

    Spent/Committed to date $899,651

    Available Balance for Project $4,314,768

    Revised Project Cost Estimate $3,732,351

    Project Balance $582,417 (17.71%) Contingencies (included in estimate) $393,739 (11.97%) Combined cushion $976,156 (29.68%) May only need $1.45 M Bond instead of $2.0 M

  • 7/31/2019 District Heat Project August 2012

    11/23

    Annual System Budget (2014)

    2011 Bond Payment @ $2.0 M $169,191 (highest)Bond @ $1.45 M = $122,663

    Contract with State $68,032 2009 Bond Payment $20,376 (highest) Operations $10,228 CEDF Loan Interest $7,500 Total Must Pay Obligations $275,327 (w/ $2 M Bond)

    $228,799 (w/$1.45 M Bond)

    Cash Reserve (5% of rev.) $12,992 Operating/Admin 10 customers $46,026 ($65,348 max) TOTAL $334,345

    With $1.45 M Bond $287,817

  • 7/31/2019 District Heat Project August 2012

    12/23

    Customer Commitments using 2014

    Capacity Rates City Complex (City Hall, Fire, Police) $46,009 Union Elementary School $77,350 Vermont Mutual $151,830 prorated $30,366 GSA $40,656 County (Court House, Sheriff) $14,738 Everett (52, 46 & 27 State St) $26,934 Nedde (City Center) $26,257

    NECI/Nick (118 Main St) $12,949Jacobs (22 Elm/Jailhouse Common) $8,165 Beard (15 E. State St) $6,776 TOTAL $290,200

  • 7/31/2019 District Heat Project August 2012

    13/23

    Customer Base

    10 Customers involve 15 Connections

    Initial System design = 34 Connections

    Commitments for 44% of connections

    Additional connections create additional financial stability.

  • 7/31/2019 District Heat Project August 2012

    14/23

    10 Cust. $3.73 M Project. $1.45 M Bond

    ($100,000)

    $0

    $100,000

    $200,000

    $300,000

    $400,000

    $500,000

    $600,000

    $700,000

    $800,000

    $900,000

    2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

    District Heat

    Annual Operating BudgetProjection

    Annual Revenues

    Annual Expenses

    Annual Budget BalanceTotal Cash on Hand

  • 7/31/2019 District Heat Project August 2012

    15/23

    City/School Fuel at $2.99/gallon

    City & UES use 60,600 gallons per year of oil

    Combined DH capacity fee = $123,359

    Combined DH energy fee = $58,063

    Total Combined DH cost = $181,422

    $181,422/60,600 gallons = $2.99 per gallon

  • 7/31/2019 District Heat Project August 2012

    16/23

    Comparison to Oil

    $3,515,833

    $4,384,564

    $5,555,435

    $3,034,069

    $481,764

    $1,350,495

    $2,521,366

    $120,695$298,248 $447,936

    $0

    $1,000,000

    $2,000,000

    $3,000,000

    $4,000,000

    $5,000,000

    $6,000,000

    City/School Oil@ 3% increase

    City/School Oil@ 5.25%

    increase

    City/School Oil@ 8% increase

    City/School DH,2.5% wood

    increase

    NPV COSTS & SAVINGS

    of Oil and District Heat for City/School

    20 Year NPV Cost - Oil & DH

    20 Yr NPV savings with DH

    10 year NPV savings with DH

  • 7/31/2019 District Heat Project August 2012

    17/23

    Financing for Customer Connections

    Partnership with VT Economic Dev. Authority (VEDA)

    Village Green grant pays 10% of cost

    VEDA finances remaining 90% at 4% over 5-7 years

    Effective rate = 0% for 5 years, 1% for 7 years

    City will include repayment on DH bill

  • 7/31/2019 District Heat Project August 2012

    18/23

  • 7/31/2019 District Heat Project August 2012

    19/23

    Citys Risks for Proceeding

    Project Costs running over

    Under budget, sufficient contingency, current bid climate,project sectioning options

    Stuck with Annual Operating Cost

    Full $2.0 M Bond. Minimal Customers GSA, County,VM, Everett.

  • 7/31/2019 District Heat Project August 2012

    20/23

    Bad Case Scenario

    Must Pay Obligations $275,327 City/School Energy Fees $58,063 TOTAL MUST PAY $333,390 Income (4 customers) $112,694 Net For City to Pay $220,696

    Less City/School Capacity $123,359 Less City/School Energy $58,063 TOTAL City paying $181,422Net Added DH Costs for City $39,274

  • 7/31/2019 District Heat Project August 2012

    21/23

    City Risk Comparison

    City/School Oil prices

    $3.00/gallon for 60,600 gallons = $181,422

    $3.31/gallon for 60,600 gallons = $200,586

    $3.50/gallon for 60,600 gallons = $212,100

    2009 Bond payment = $20,376

    City Costs with no DH = $201,798 to $232,476Net Cost under Bad DH = $220,696

  • 7/31/2019 District Heat Project August 2012

    22/23

    Other Considerations

    Operating costs and responsibilities are manageable Consistent with City Council 2012 Goals Consistent with Citys 2010 Master Plan Citys analysis reasonable as to method and assumptions

    and the substance of the agreements to be reasonable inlight of normal energy purchase and sale agreements

    Public votes on this project: 2003 Bond $250,000 1,273-875 59% 2009 Re-use of the 03 bond 1,024-745 57% 2010 Charter amendments 2,826-755 78% 2011 Bond $2,000,000 963-609 61%

  • 7/31/2019 District Heat Project August 2012

    23/23

    Recommended Council Action

    Authorize City Manager to proceed with project Notify the State and DOE of this decision Continue signing up customers Issue bids in September for receipt in October Review bids in November, consider project adjustments.

    Award contract.

    Consider options for use of available funds, possibleadditional assistance for connections.

    Begin construction in spring of 2013 Provide Thermal Energy to Customers on 10/1/13