district heat project august 2012
TRANSCRIPT
-
7/31/2019 District Heat Project August 2012
1/23
DISTRICT HEAT PROJECT
August 22, 2012
-
7/31/2019 District Heat Project August 2012
2/23
Key Points
Project is within budget
Ongoing operation is viable Citys risks are addressed
Project goals are met
-
7/31/2019 District Heat Project August 2012
3/23
Recommended Action
Authorize City Manager to proceed with project Notify the State and DOE of this decision Continue signing up customers
Issue bids in September for receipt in October Review bids in November, consider project adjustments.
Award contract.
Consider options for use of available funds, possibleadditional assistance for connections.
Begin construction in spring of 2013 Provide Thermal Energy to Customers on 10/1/13
-
7/31/2019 District Heat Project August 2012
4/23
Presentation
Overall Project Description and Funding Summary Project Costs
Customer Commitments City/School heating costs Financing Package Citys Risk System Management, City Goals and Master Plan,
Assumptions and Projections, City Votes
Recommended Action
-
7/31/2019 District Heat Project August 2012
5/23
Project Goals
Reduce emissions
Replace oil with regional fuel source
Stabilize heating costs for city/school
Economic development opportunity for downtown
Citys project costs within current expenses
-
7/31/2019 District Heat Project August 2012
6/23
Project Summary
State Central Heating Plant 40.2 MMBTU capacity
City Distribution System 9.71 MMBTU (24%) of stateplant, ability to purchase up to 16.3 MMBTU
Both Public and Private Customers
Primarily Wood Chips for winter fuel (Oct April)
Summer Hot Water through system boilers
-
7/31/2019 District Heat Project August 2012
7/23
-
7/31/2019 District Heat Project August 2012
8/23
Overall Funding Summary
Federal Department of Energy $8.00 million State of Vermont Capital Funds $7.00 million State of Vermont In Kind $1.20 million City of Montpelier 2011 Bond $2.00 million CEDF Grant $1.00 million CEDF Loan, 1%, deferred payment $0.75 million Forest Service Grant (new) $0.248 million Village Green Grant (new) $0.10 million TOTAL $20.298 million
-
7/31/2019 District Heat Project August 2012
9/23
Funding Allocation
State Funds for heat plant $8.200 million DOE Grant to state for heat plant $3.249 million DOE Grant to state for city capacity $2.558 million
City/CEDF funds to state for capacity $1.077 million DOE Grant to city for dist. system $2.193 million City/CEDF funds for dist. system $2.673 million Other grant funds for dist. system $0.348 million Total for Central Heating Plant $15.047 million Total for Distribution System $5.214 million
-
7/31/2019 District Heat Project August 2012
10/23
Overall City Funding Status
TOTAL Distribution System $ $5,214,419
Spent/Committed to date $899,651
Available Balance for Project $4,314,768
Revised Project Cost Estimate $3,732,351
Project Balance $582,417 (17.71%) Contingencies (included in estimate) $393,739 (11.97%) Combined cushion $976,156 (29.68%) May only need $1.45 M Bond instead of $2.0 M
-
7/31/2019 District Heat Project August 2012
11/23
Annual System Budget (2014)
2011 Bond Payment @ $2.0 M $169,191 (highest)Bond @ $1.45 M = $122,663
Contract with State $68,032 2009 Bond Payment $20,376 (highest) Operations $10,228 CEDF Loan Interest $7,500 Total Must Pay Obligations $275,327 (w/ $2 M Bond)
$228,799 (w/$1.45 M Bond)
Cash Reserve (5% of rev.) $12,992 Operating/Admin 10 customers $46,026 ($65,348 max) TOTAL $334,345
With $1.45 M Bond $287,817
-
7/31/2019 District Heat Project August 2012
12/23
Customer Commitments using 2014
Capacity Rates City Complex (City Hall, Fire, Police) $46,009 Union Elementary School $77,350 Vermont Mutual $151,830 prorated $30,366 GSA $40,656 County (Court House, Sheriff) $14,738 Everett (52, 46 & 27 State St) $26,934 Nedde (City Center) $26,257
NECI/Nick (118 Main St) $12,949Jacobs (22 Elm/Jailhouse Common) $8,165 Beard (15 E. State St) $6,776 TOTAL $290,200
-
7/31/2019 District Heat Project August 2012
13/23
Customer Base
10 Customers involve 15 Connections
Initial System design = 34 Connections
Commitments for 44% of connections
Additional connections create additional financial stability.
-
7/31/2019 District Heat Project August 2012
14/23
10 Cust. $3.73 M Project. $1.45 M Bond
($100,000)
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
District Heat
Annual Operating BudgetProjection
Annual Revenues
Annual Expenses
Annual Budget BalanceTotal Cash on Hand
-
7/31/2019 District Heat Project August 2012
15/23
City/School Fuel at $2.99/gallon
City & UES use 60,600 gallons per year of oil
Combined DH capacity fee = $123,359
Combined DH energy fee = $58,063
Total Combined DH cost = $181,422
$181,422/60,600 gallons = $2.99 per gallon
-
7/31/2019 District Heat Project August 2012
16/23
Comparison to Oil
$3,515,833
$4,384,564
$5,555,435
$3,034,069
$481,764
$1,350,495
$2,521,366
$120,695$298,248 $447,936
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
City/School Oil@ 3% increase
City/School Oil@ 5.25%
increase
City/School Oil@ 8% increase
City/School DH,2.5% wood
increase
NPV COSTS & SAVINGS
of Oil and District Heat for City/School
20 Year NPV Cost - Oil & DH
20 Yr NPV savings with DH
10 year NPV savings with DH
-
7/31/2019 District Heat Project August 2012
17/23
Financing for Customer Connections
Partnership with VT Economic Dev. Authority (VEDA)
Village Green grant pays 10% of cost
VEDA finances remaining 90% at 4% over 5-7 years
Effective rate = 0% for 5 years, 1% for 7 years
City will include repayment on DH bill
-
7/31/2019 District Heat Project August 2012
18/23
-
7/31/2019 District Heat Project August 2012
19/23
Citys Risks for Proceeding
Project Costs running over
Under budget, sufficient contingency, current bid climate,project sectioning options
Stuck with Annual Operating Cost
Full $2.0 M Bond. Minimal Customers GSA, County,VM, Everett.
-
7/31/2019 District Heat Project August 2012
20/23
Bad Case Scenario
Must Pay Obligations $275,327 City/School Energy Fees $58,063 TOTAL MUST PAY $333,390 Income (4 customers) $112,694 Net For City to Pay $220,696
Less City/School Capacity $123,359 Less City/School Energy $58,063 TOTAL City paying $181,422Net Added DH Costs for City $39,274
-
7/31/2019 District Heat Project August 2012
21/23
City Risk Comparison
City/School Oil prices
$3.00/gallon for 60,600 gallons = $181,422
$3.31/gallon for 60,600 gallons = $200,586
$3.50/gallon for 60,600 gallons = $212,100
2009 Bond payment = $20,376
City Costs with no DH = $201,798 to $232,476Net Cost under Bad DH = $220,696
-
7/31/2019 District Heat Project August 2012
22/23
Other Considerations
Operating costs and responsibilities are manageable Consistent with City Council 2012 Goals Consistent with Citys 2010 Master Plan Citys analysis reasonable as to method and assumptions
and the substance of the agreements to be reasonable inlight of normal energy purchase and sale agreements
Public votes on this project: 2003 Bond $250,000 1,273-875 59% 2009 Re-use of the 03 bond 1,024-745 57% 2010 Charter amendments 2,826-755 78% 2011 Bond $2,000,000 963-609 61%
-
7/31/2019 District Heat Project August 2012
23/23
Recommended Council Action
Authorize City Manager to proceed with project Notify the State and DOE of this decision Continue signing up customers Issue bids in September for receipt in October Review bids in November, consider project adjustments.
Award contract.
Consider options for use of available funds, possibleadditional assistance for connections.
Begin construction in spring of 2013 Provide Thermal Energy to Customers on 10/1/13