Page 1: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 CONSTRUCTION PROGRAM

***Dates in the 2015 Program are subject to change without notice

DISTRICT 3

JOHN R. KASICH, OHIO GOVERNOR | JERRY WRAY, ODOT DIRECTOR | ALLEN C. BIEHL, DISTRICT DEPUTY DIRECTOR

SERVING ASHLAND, CRAWFORD, ERIE, HURON, LORAIN, MEDINA, RICHLAND AND WAYNE COUNTIES

Page 2: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

ASHLAND COUNTY 1

Ashland County Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

81932 ASD-89-10.32 Bridge Deck

Replacement

At its bridge over Interstate 71

7/24/14

2/23/15

7/31/15

$1,690,547

Ruhlin

Construction

150-day detour

92897 ASD-96-6.26 Signal

Improvements

At various intersections, including

Holbrook Road, Lee Ave; and US 250

in the City of Ashland

10/2/14

12/3/14

5/22/15

$295,718.90

Perram Electric

Maintained at all times

88811 ASD-511-14.07 Resurface

Resurfacing from SR 60 to the Lorain

County line, including its

overlap with SR 302

3/5/15

5/1/15

9/30/15

$2,288.925.18

Kokosing

Maintained with flaggers or

temporary signal, except for

45-day detour for bridge

work

88739 ASD-42-7.75 Bridge

Replacement

Interchange improvement & bridge

replacement on US 42 at US 250/SR96 4/9/15

5/26/15

11/13/15

$8,100,000

Unknown

90-day detour

86699 ASD-604-0.00 Chip Seal On State Route 604 in Ashland and

Wayne Counties 6/18/15

8/1/15

11/1/15

$1,500,000

Unknown

Maintained with flaggers

93118 RIC-39-24.93 Resurface From SR 603 in Richland County to

the Holmes County line

6/18/15

8/1/15

11/30/15

$3,370,000

Unknown

Maintained with flaggers and

temporary signalized lane

closures for bridge work

Page 3: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

ASHLAND COUNTY 2

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 4: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

CRAWFORD COUNTY 3

Crawford County Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

93108 CRA-98-19.3 Resurface From Dickson Road to State Route 61 in

Richland County 11/13/14

6/1/15

9/30/15

$1,946,696.61

Shelly & Sands

Maintained with flaggers

97539 CRA-TR-50-6.10 Bridge

Replacement Scott Road over Nogle ditch 1/15/15

4/1/15

8/31/15

$427,340.00

R & I

Construction

45-day detour

94383 CRA-98-0.00 Resurface Marion County line to State Route 4; and

on SR 4 from SR 98 to Charles Street 7/2/15

8/1/15

10/31/15

$2,500,000

Unknown

Maintained with flaggers

Page 5: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

CRAWFORD COUNTY 4

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 6: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

ERIE COUNTY 5

Erie County Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

79851 ERI-2-0.14 Preventative

Maintenance From the Edison Bridge to US Route 6 6/26/14

7/28/14

6/30/15

$3,592,664

Strawser

One lane maintained in

each direction

77440 ERI-2-30.41 Preventative

Maintenance

From just west of the Lorain County

line to east of Baumhart Road;

includes US 20 in Lorain County from

Middle Avenue to State Route 57

8/21/14

4/1/15

6/30/15

$2,654,065

Burton Scot

One lane maintained in

each direction

84556 ERI-250-1.14 Intersection

Improvement US 250 and Perkins Ave 11/26/14

4/1/15

10/15/15

$3,074,920.43

SET, Inc.

Maintained at all times

94898 ERI-250-9.78 Culvert

Replacement Just south of Strecker Road 11/13/14

4/13/15

7/17/15

$191,387.25

Underground

Utilities

Shoulder closures as

necessary

88764 ERI-6-11.25 Resurface

Between the City of Sandusky and

City of Huron, and on SR 547 in the

village of Monroeville

11/26/14

4/1/15

6/30/15

$993,853.65

Erie Blacktop

Maintained with flaggers

88407 ERI-250-0.00 Corridor

Improvement From US Route 6 to Bogart Road 3/5/15

5/4/15

9/15/16

$14,228,715.75

Miller Brothers

Maintained at all times

86697 ERI-6-19.25 Preventative

Maintenance

The City of Huron and the City of

Vermilion, and in Lorain County on

SR 82 from SR 57 to the Cuyahoga

County line

6/18/15

8/1/15

11/1/15

$1,500,000

Unknown

Maintained with flaggers

Page 7: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

ERIE COUNTY 6

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 8: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

HURON COUNTY 7

Huron County Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

89367 HUR-13-6.90 Slide Repair Just south of Rundel Street 1/9/14

2/215

7/1/15

$473,531.00

BBR Drilling

90-day detour

86692 D03 SMOOTH

FY2015

Preventive

Maintenance

On SR 60 from the City of Vermilion

to the village of New London 6/26/14

9/2/14

6/30/15

$2,301,352

Erie Blacktop

Maintained with flaggers

97548 HUR-TR-48-0.55 Bridge

Replacement

Lovers Lane

1/15/15

4/1/15

8/31/15

$623,800.00

Mosser

Construction

60-day detour

91657 HUR-224-6.16 Rehabilitation From just east of SR 99 to the eastern

corporation limit of Willard 3/26/15

5/1/15

12/15/15

$1,328,000

Unknown

Maintained at all times;

truck traffic will be

detoured

90362 HUR-61-15.93 Culvert

Rehabilitations

On SR 61, one-quarter mile south of

Johnson Road and on SR 162, one-

half-mile east of Lyon Road

4/9/15

6/1/15

8/15/15

$250,000

Unknown

Maintained with flaggers

SR-61: Signalized lane

closure for bridge work

and CR-128 will be

closed for 14 days

SR-162: 24-day detour

Page 9: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

HURON COUNTY 8

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 10: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

LORAIN COUNTY 9

Lorain County Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

23104 LOR-58-7.36 Railroad Grade

Separation

0.14 mile north of State Route 18 in

the Village of Wellington 1/17/13

4/1/13

10/15/15

$12,324,028.86

Beaver Exc.

35-day detour near

project completion

25732 LOR-2-10.46 Bridge Deck

Replacement

At bridges over the railroad and

Murray Ridge Road

1/23/14

3/3/14

10/31/16

$10,124,197.97

JD Williamson

I-90: Two lanes in each

direction at all times

82645 LOR-57-19.42 Major

Rehabilitation

Between the I-90 interchange with

SR 57 and Ohio Turnpike 4/10/14

5/1/14

7/15/16

$20,538,253.95

Karvo Paving

SR 57: Two lanes of

traffic in each direction.

Midway Mall Blvd &

Griswold Rd: One lane in

each direction

83793 LOR-254-0.01 Intersection

Improvement

State Route 254 & West River Road in

the City of Elyria 6/26/14

2/12/15

8/15/15

$3,720,359

Karvo Paving

90-day detour

88825 LOR-18-12.29 Bridge Repair Between Indian Hollow Road and

Foster Road 10/2/14

4/1/15

5/30/15

$607,000

Ohio Bridge

45-day detour

81078 LOR-90-

OVERLAYS

Bridge

Maintenance

At I-90 bridges over SR 57, US 20 and

the CSX railroad tracks 10/16/14

4/15/15

8/31/15

$256,643.60

Karvo Paving

One lane maintained at all

times in both directions at

night/PETERS

81933 LOR-90-17.53 Bridge Deck

Replacement French Creek Road over I-90 10/30/14

4/6/15

10/2/15

$1,759,893.80

Mosser

Construction

180-day detour

96999 LOR-20-22.19 Demolition

Various structures in North Ridgeville 10/30/14

12/8/14

6/5/15

$969,747.00

All Aspects

Contracting, Inc

Maintained at all times

Page 11: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

LORAIN COUNTY 10

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 12: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

LORAIN COUNTY 11

Lorain County Projects (continued)

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

82262 LOR-90-SYSSIGN

FY2015

Sign

Replacements Various locations on SR 10 & US 20 11/26/14

2/1/15

1/30/16

$134,438.50

MP Dory

Maintained at all times

88767 LOR-511-13.41 Resurface From US Route 20 to the

City of Oberlin 11/26/14

6/15/15

8/31/15

$982,928.84

Kokosing

One lane of traffic

maintained at all times

with flaggers

80123 LOR-162-5.77 Bridge

Replacement

Nearly one-half-mile west of SR 58

3/26/15

6/1/15

8/15/15

$330,000

Unknown

30-day detour

86272 LOR-58-23.79 Resurfacing Urban Paving on SR 58 in Amherst 3/26/15

6/1/15

10/31/15

$710,000

Unknown

One lane maintained in each

direction; paving at night

94900 LOR-10-1.13 Culvert

Construction

at three locations along SR 10 and one

culvert on US 20 4/23/15

06/01/15

12/31/15

$400,000

Unknown

One lane maintained in

each direction at all times

97551 LOR-TR-15 & TR-

129 and MED-CR-44

Bridge

Replacement

Parsons Road over Black River; Snell Road

and State Road in Medina County 5/7/15

6/15/15

9/15/15

$2,200,000

Unknown 60 days each structure

91303 LOR-252-2.30 Slide Repair 0.36 miles south of SR 82 6/4/15

8/3/15

10/30/15

$550,000

Unknown

90-day detour

92009 LOR-611-3.44 Bridge Repair Henderson Drive bridge over Black River in

City of Lorain 6/4/15

8/1/15

5/2/16

$5,300,000

Unknown

One lane in each direction

at all times

93709 LOR CULVERTS

FY2015

Culvert

Replacements

On US 20 just west of Baird Road; on SR

252 north of River Glen Drive; and on

SR 303 just east of West Road

6/4/15

8/3/15

11/1/15

$400,000

Unknown

21-day detour for each

culvert replacement

92836 LOR-82-8.99 Intersection

Improvement At intersection with Boone Road 9/24/15

4/4/16

9/2/16

$1,500,000

Unknown

Boone Rd: 60-day detour

on each approach; SR 82:

Maintained

Page 13: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

LORAIN COUNTY 12

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 14: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

MEDINA COUNTY 13

Medina County Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

79760 MED-18-15.15 Preventative

Maintenance

From just east of Nettleton Road to

Windfall Road 6/24/14

8/8/14

6/26/15

$704,278.11

Karvo Paving

Mostly night work

86731 MED-94-18.74 Resurface

From SR 303 to the Cuyahoga County

line; on SR 303 from the Lorain

County line to City of Brunswick

10/16/14

6/15/15

9/30/15

$2,250,576.81

Karvo Paving

Maintained at all times

with flaggers

92691 MED-57-17.67 Roundabout

Construction

State Route 57, Speith Road, and State

Route 252 intersection 10/30/14

6/15/15

8/31/15

$1,645,870.05

Karvo Paving

60-day detour

93116 MED-301-0.00 Resurface From the Wayne County line to the

Village of Spencer 11/13/14

5/1/15

8/31/15

$1,787,357.45

Chagrin Valley

Maintained at all times

with flaggers

93113 MED-57-3.24 Resurface

On SR 57 from the City of Wadsworth

to the City of Medina & on SR 94

from SR 18 to SR 3

11/26/14

5/1/15

10/15/15

$2,481,506.16

Karvo Paving

Maintained at all times

with flaggers

96567 MED-94-14.61 Signals Signal installation at SR 94 and I-271

South interchange 12/11/14

2/2/15

9/30/15

$88,248.43

Greenwich

Electric

Maintained at all times

97549 MED-TR-33-3.23

MED-CR-4-7.19

Bridge

Replacement

TR 33, over Mallet Creek, and on

West Smith Road over Black River 1/29/15

4/1/15

9/1/15

$861,173.50

Reitschlin

TR-33: 90-day detour

CR-4: 45-day detour

86756 MED-3-9.53 Signals New traffic signal on SR 3 at

Highpoint/Lexington Ridge Drive 4/9/15

6/1/15

10/16/15

$150,000

Unknown

Maintained at all times

86893 MED-42-18.98 Intersection

Improvement At Fenn Road 4/9/15

6/1/15

10/16/15

$3,700,000

Unknown

One lane in each direction

on US 42 and Fenn Rd

Page 15: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

MEDINA COUNTY 14

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2013

New Construction in 2014

Sale in 2014; Construction in 2015

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 16: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

MEDINA COUNTY 15

Medina County Projects (continued)

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

88773 MED-94-1.16 Resurface Urban paving in Wadsworth

4/9/15

6/1/15

12/31/15

$890,000

Unknown

Maintained with flaggers;

Night paving work

92883 MED-303-6.00 Resurface Urban Paving in Brunswick 4/9/15

7/1/15

10/31/15

$1,500,000

Unknown

Maintained with flaggers;

All work at night

97541

MED-CR-29-

4.69 & MED-CR-

46-3.41

Bridge

Replacement Congress Road and Seville Road 4/20/15

5/25/15

9/1/15

$1,000,000

Unknown

90-day detour at both

structures

81338 MED-94-3.8 Rehabilitation Reconstruct and improve the SR 94

and I-76 interchange corridor 5/21/15

7/2/15

8/31/17

$9,100,000

Unknown

Maintained with flaggers

96227 MED-71-24.02 Intersection

Improvement

Improve the I-71 south exit to SR 303

with widening and extending 5/21/15

8/31/15

10/16/15

$3,300,000

Unknown

Slip ramp closed during

construction; SR 303:

Maintained at all times

77038 MED-271-0.00 Preventive

Maintenance From I-71 to Summit County line 6/18/15

8/1/15

9/30/15

$1,700,000

Unknown

One lane maintained in

each direction at all times

Page 17: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

MEDINA COUNTY 16

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 18: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

RICHLAND COUNTY 17

Richland County Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

88808 RIC-95-0.00 Resurface

On SR 95 from the Knox County line

to the Village of Perrysville and on SR

603 from SR 95 to SR 39

7/10/14

8/8/14

7/31/15

$3,010,466.61

Shelly & Sands

Maintained with flaggers at

all times

88827 RIC-42-12.34 Bridge Repair

Between Smith Avenue and 8th

Avenue in the City of Mansfield 10/16/14

6/15/15

8/28/15

$294,252.80

Page Excavating

28-day detour

82261 RIC-30- FY14 Sign

Replacement

From just west of the SR 309 overpass

to the Ashland County line 4/10/14

5/21/14

5/18/15

$156,240.00

Lake Erie Const.

One lane maintained at all

times in each direction

97112 CR-303-1.02 &

CR-303-3.68

Bridge

Replacements Pleasant Valley Road 6/5/14

3/16/15

5/31/15

$2,251,602.00

Complete General

CR-303-1.02: 45-day detour

CR-303-3.68: 60-day detour

97540 RIC-TR-383

CR-31

Bridge

Replacement

On Hay Road and on Bellville Johnson

Road 1/29/15

4/1/15

8/31/15

$1,237,840

Complete General

CR-31: 75-day detour

TR-383: 45-day detour

93710 RIC-CULVERTS

2015

Culvert

Rehabilitation At various locations on US 30 and I-71 2/10/15

5/1/15

8/31/15

$149,716.00

Stanley Miller*

Maintained at all times

82263 RIC-30-

SYSSIGN

Sign

Replacement On US 30 and SR 309 3/20/15

5/1/15

4/1/16

$240,000

Unknown

Maintained at all times

88728 RIC-13-14.41 Resurface Urban Paving in Mansfield on SR 13,

SR 39, SR 430, US 42 and SR 545 5/18/15

5/1/15

8/1/15

$4,190,000

Unknown

Signalized lane closure for

bridge work; Truck traffic

may be detoured

79792 RIC-71-0.0 Preventive

Maintenance

From the Morrow County line to just

south of the SR 39 interchange

6/18/15

8/1/15

10/1/15

$3,900,000

Unknown

One lane maintained in each

direction at night with two

lanes maintained during day

*Apparent low bidder

Page 19: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

RICHLAND COUNTY 18

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 20: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

RICHLAND COUNTY 19

Richland County Projects (continued)

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

86839 RIC-39-1.87 Resurface Urban Paving in Shelby on SR 39,

SR 61 and SR 96 6/18/15

8/1/15

10/1/15

$1,800,000

Unknown

Maintained at all times

93118 RIC-39-24.93 Resurface From SR 603 to the Ashland/Holmes

County line 6/18/15

8/1/15

11/30/15

$3,370,000

Unknown

Maintained with flaggers

or signalized lane

closures for bridge work

93096 RIC-30-9.13 Reactive

Maintenance

From just west of SR 309 to the

Mansfield corporation limit

6/18/15

8/1/15

12/1/15

$500,000

Unknown

One lane maintained in

each direction

93122 RIC-314-0.00 Resurface

From Morrow County line to SR 61,

including within the City of Ontario

9/24/15

4/1/16

12/31/16

$2,300,000

Unknown

Maintained with flaggers

Page 21: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

RICHLAND COUNTY 20

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 22: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

WAYNE COUNTY 21

Wayne County Projects

PID

Number

Route &

Section Work Type Location

Sale Date Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

83203 WAY-585-2.75 Section

Improvement

Between Geyers Chapel Road and

Thompson Road

6/5/14

8/4/14

9/30/15

$3,480,723.10

Mark Schaffer

SR 585: 150-day detour

Geyers Chapel Rd: Intermittent Detours

83453 WAY-BH-

FY2015

Bridge

Repairs

On seven bridge decks along US 30;

SR 94, SR 585; SR 172 and

SR 302

12/11/14

5/1/15

9/30/15

$1,535,000.00

APBN Inc.

14-day detour of SR 302 to US 30 West

ramp as well as various signalized single

lane closures at other structures

94902 WAY-250-7.10 Culvert

Construction

Just east of Old Lincolnway and just

south of Secrest Road

1/15/15

3/2/15

8/31/15

$109,226.79

Stanley Miller

Maintained at all times

90936 WAY Safe Routes

to School Village of Creston

1/15/15

4/1/15

6/30/15

$307,116.45

Stanley Miller

Maintained at all times

86728 WAY-94-14.16 Resurface

From Fox Lake Road to the City of

Wadsworth, and on SR 585 from

SR 94 to Summit County line

2/26/15

5/1/15

10/31/15

$3,000,000

Unknown

Signalized lane closure for bridge work

with two short closures of CR 70; One

lane maintained with flaggers

86840 WAY-57-10.82 Resurface Urban paving in Rittman 3/19/15

5/1/15

8/1/15

$1,100,000

Unknown

Signalized lane closure for bridge work;

One lane maintained with flaggers

87745 WAY-30-9.18 Preventative

Maintenance in the City of Wooster

3/5/15

5/26/15

9/10/15

$794,217.00

Strawser Const.

One lane maintained at all times in each

direction; possible night time ramp closures

91300 WAY-3-1.40 Slide Repair 0.25 south of Newkirk Road

4/23/15

5/15/15

8/31/15

$500,000

Unknown

90-day detour

84605 WAY-302-4.86

WAY-302-6.22

Culvert

Replacements

At two locations between Silver

Road and Smyser Road

6/4/15

8/1/15

11/1/15

$750,000

Unknown

45-day detour

Page 23: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

WAYNE COUNTY 22

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 24: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

WAYNE COUNTY 23

Wayne County Projects (continued)

PID

Number

Route &

Section Work Type Location

Sale Date Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

98736 WAY-30-3.96 Culvert

Replacement 0.75 mile east of Firestone Road 6/4/15

7/15/15

8/15/15

$100,000

Unknown

Single lane or shoulder closures as

needed

77476 WAY-30-11.79 Surface

Treatment

From the SR 3 interchange to just

east of Kansas Road 7/2/15

8/13/15

10/30/15

$3,500,000

Unknown

One lane maintained in each direction

90882 WAY-604-0.01 Bridge Repair

At the Ashland/Wayne County line 8/13/15

4/1/16

5/31/16

$580,000

Unknown

90-day detour

87710 WAY-21-0.00 Reactive

Maintenance

From the Stark County line to the

Summit County line 10/22/15

5/1/16

9/30/16

$1,600,000

Unknown

One lane maintained in each direction

Page 25: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

WAYNE COUNTY 24

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 26: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

DISTRICT WIDE PROJECTS 25

District Wide Projects

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

96718 D03 MOW

FY2014-15

Mowing Various routes and sections

throughout District Three

12/12/13

5/15/14

11/15/15

$659,834.00

Tom Mayle & Sons

Maintained at all times

89419 D03-LOOP-

FY2013

Loop

Maintenance

Various routes and sections

throughout District Three

1/17/13

6/6/13

5/31/15

$99,410.00

Perram Electric Maintained at all times

96719 D03 MOW

FY2014-15

Mowing Various routes and sections

throughout District Three

1/9/14

5/12/14

11/15/15

$324,000.00

Brypan LLC Maintained at all times

95217 D03 PR

FY2013

Pruning,

Tree/Bush

Removal

Various routes and sections

throughout District Three

3/28/13

6/27/13

5/31/15

$116,530.00

VanCuren

Maintained at all times

89429 D03 RPM

FY2014

Raised

Pavement

Markers

Various routes and sections

throughout District Three

3/27/14

6/17/14

4/30/15

$164,455

A & A Safety

Maintained at all times

96720 D03 MOW

FY2014-15

Mowing Various routes and sections

throughout District Three

3/27/14

5/12/14

11/15/15

$354,364.00

Brypan LLC

Maintained at all times

86693 D03 CHIP

FY2015

Chip Seal On State Route 303 from the Huron

County Line to village of LaGrange

7/24/14

5/1/15

6/30/15

$558,464.00

Erie Blacktop

Maintained with flaggers

84581 D03 BH

FY2015

Bridge Repair Several structures on SR 2 in Erie

County; Coen Road & Barnes Road

were repaired in 2014

8/21/14

10/6/14

8/31/15

$637,660.09

Bridge Overlay

Risden Road: 30-day detour

89444 D03 PR

FY2015

Pruning,

Tree/Bush

Removal

Various routes and sections

throughout District Three

8/21/14

10/29/14

9/30/15

$656,225

Van Curen

Maintained at all times

89443 D03 GR

FY2015

Guardrail

Repair

Various routes and sections

throughout District Three

10/2/14

1/30/15

1/13/16

$584,755

Lake Erie Const.

Maintained at all times

Page 27: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

DISTRICT WIDE PROJECTS 26

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 28: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

DISTRICT WIDE PROJECTS 27

District Wide projects (continued)

PID

Number

Route &

Section Work Type Location

Sale Date

Est. Start

&

Est. End

Est. Cost

&

Contactor

Maintenance of Traffic

93864

D03 Mohican

Campground

Resurfacing State Park campgrounds and Culvert

Replacements in the State Forest

11/26/14

4/15/15

5/22/15

$731,355.40

Karvo Paving

Maintained at all times

89445

D03 LG

FY2015

Lighting

Maintenance

Various routes and sections

throughout District Three

12/11/14

2/15/15

8/31/15

$105,609.80

Greenwich Elec

Maintained at all times

84587

D03 DECK

OVERLAYS

FY2015

Bridge

Maintenance

Various bridges along State Route 2

in Erie and Lorain Counties

2/26/15

1/15/15

10/31/15

$525,000.00

B&G

Construction

30-day detour of Main Street in

Amherst; one lane maintained in each

direction on the other structures

89446

D03 LOOP

FY2015

Loop Detector

Repair

Various routes and sections

throughout District Three

2/26/15

6/1/15

5/31/17

$189,312.75

Perram Electric

Maintained at all times

89447

D03 RPM

FY2015

Raised

Pavement

Markers

Various routes and sections

throughout District Three

3/26/15

6/1/15

9/1/15

$347,000

Unknown

Maintained at all times

89448

D03 PM

FY2015

Pavement

Marking

Various routes and sections

throughout District Three

6/4/15

7/1/15

10/1/15

$2,445,000

Unknown

Maintained at all times

86697

D03 MICRO

FY2016

Preventive

Maintenance

Preventive Maintenance - Surface

Treatment

6/18/15

8/1/15

11/1/15

$2,449,000

Unknown

Maintained at all times

86698

D03 SMOOTH

FY2016

Preventive

Maintenance

Preventive Maintenance - Surface

Treatment

6/18/15

8/1/15

10/1/15

$1,656,000

Unknown

Maintained with flaggers

97357

D03 PR

FY2016

Pruning,

Tree/Bush

Removal

Various routes and sections

throughout District Three

7/2/15

8/1/15

8/1/16

$200,000

Unknown

Maintained at all times

Page 29: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

2015 DISTRICT 3 CONSTRUCTION PROGRAM

DISTRICT WIDE PROJECTS 28

Resurfacing

Reactive/Preventive Maintenance

Bridge/Culvert

Continued Construction from 2014

New Construction in 2015

Page 30: DISTRICT 3 - Ohio Department of Transportation D-3 Construction Program.pdfStrawser One lane maintained in each direction 77440 ERI-2-30.41 Preventative Maintenance From just west

To provide easy conveyance of people

and goods from place to place, we will:

Take care of what we have;

Make our system work better;

Improve safety;

Enhance capacity

A long-term, reliable, professional and

highly productive organization

O U R M I S S I O N

O U R V I S I O N

For more information, Allen C. Biehl, P.E., District Deputy Director at (419) 207-7002,

Robert L. Weaver, P.E., P.S., District Construction Administrator at (419) 207-7158, or

Christine Myers, Public Information Officer at (419) 207-7182.

Like us on Facebook: www.facebook.com/OhioDepartmentofTransportationDistrict3

Follow us on Twitter: www.twitter.com/ODOT_NorthCenOH

Statewide Traffic Information: www.Ohgo.com

For general information, call (800) 276-4188 or visit District 3’s Web site at: www.transportation.ohio.gov/dist3