discharge alternatives report · 2020-03-20 · staff engineer frainklenzi o project director, vice...
TRANSCRIPT
"^
^ A R C A D I S Infrastructure, environment, buildings Imagine the result
DISCHARGE ALTERNATIVES REPORT
Public Well TCE Site (DE-1361) Millsboro, Delaware
January 14, 2011
AR000439
^ A R C A D I S
Chase McLaughlin Staff Engineer
inKLenzo Frai Project Director, Vice President
£o&.
^ U Darren Scillieri Project Manager
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
Proparod lor
United Stales Environmental Protection Agency
Region lit
PropaiQd by.
ARCADIS U.S., Inc.
10 Friends Lane
Suite 200
Newtown
Pennsykania 18940
Tel 267.685.1800
Fax 267.685.1801
On behalf of
tulerck and Co., Inc. (Merck) and
Mallinckrodt Veterinary, Inc (Mallinckrodt)
Qui Re(.:
NP000686.0001.00005
Dato:
January 14, 2011
This docurriBnt is intended only for the use
of the individual or entity for which it was
prepared and may contain informafion that
is privileged, conlidenlial and exempt from
disclosure under applicable law. Any
dissemination, distribution or copying of
this document is strictly prohibited.
AR000440
(^ARCADIS Table of Contents
1. introduction
1.1 Purpose and Objectives
1.2 Report Organization
2. Site Setting
2.1 Site Physical Setting
2.2 Site Geology
2.3 Site Hydrogeology
3. Public Wells 1 and 2: System Description and Operations
3.1 Public Wells 1 and 2 System Configuration
3.2 PW-1 and PW-2 Influent/Effluent Water Quality
4. Regulatory Obligations and Permitting Requirements
5. Discharge Alternatives Evaluation
5.1 Identification of Discharge Alternatives
5.2 Alternative 1 - Groundwater Reinjection
5.3 Alternative 2 - Spray Irrigation
5.4 Alternative 3 - Surface Water Discharge to Millsboro Pond
5.5 Comparative Evaluation of Alternatives
Conclusions
References
1
1
2
3
3
3
4
5
5
6
7
7
8
11
12
13
15
15
Tables
Table 1
Table 2
Table 3
PW-1 2010 Monthly Operational Data
PW-2 2010 Monthly Operational Data
2010 Trichloroethene Analytical Results
AR000441
_ Table of Contents (SI ARCADIS
Table 4 Anion Analytical Results
Table 5 Altemative Discharge Saeening Summary
Figures
Figure 1 Existing Monitoring Well Locations
AR000442
^ A R C A D I S
Discharge Alternatives Report
Public Well TCE Site (DE-1361), IVIillsboro, Delaware
1. Introduction
1.1 Purpose and Objectives
This Discharge Altemative Report (DAR) has been prepared by ARCADIS U.S., Inc. (ARCADIS)
on behalf of Merck and Co., Inc. (Merck) and Mallinckrodt Veterinary, Inc (Mallinckrodt), to
evaluate altemative discharge options for groundwater treated for trichloroethene (TCE) from
Millsboro Public Wells 1 and 2 (PW-1 and PW-2). This document responds to the United States
Environmental Protection Agency (EPA) November 26, 2010, Amendment Number 1 to the
Administrative Settlement and Order on Consent dated May 11, 2010 (Amendment No. 1).
Amendment No. 1 requires submittal of a report assessing certain alternatives available for
treated groundwater discharge from PW-1 and PW-2 other than use as part of the Town of
Millsboro's water supply. The goal of this DAR is to recommend an appropriate alternative for
the treated effluent discharge from PW-1 and PW-2 for implementation as soon as practicable.
PW-1 and PW-2 are groundwater extraction wells that presently provide hydraulic control of
TCE-impacted groundwater in the Columbia aquifer. Amendment No. 1 requires that the
evaluation of the discharge options address the following: (i) the expeditious disconnection of
Public Wells 1 and 2 from the Town of Millsboro water supply; (ii) the continuation of
pumping of such wells at their maximum capacity or in such lesser amount sufficient to
maintain hydraulic control of TCE in the subsurface groundwater; and (ill) the discharge or
disposal of water produced by such pumps in a manner that will not cause further harm to the
environment or negate the beneficial effects of the continued pumping of such wells.
Cun^ently water pumped from PW-1 and PW-2 is treated through dedicated granular activated
carbon (GAC) systems located proximal to each vjeW. To date, the treated effluent from PW-1
and PW-2 has discharged to the town water supply; however, the installation and start-up of a
new Manokin Aquifer pumping well (PW-5) and a new water treatment plant has reduced the
operational uptime of PW-1 and PW-2. This supplemental supply has resulted in a reduced
output from PW-1 and PW-2 since August 2010 (the average flow rate is approximately 30 to 50
gpm, See Tables 1 and 2). The results of the hydrogeologic study and the numerical flow
simulations presented during the August 3, 2010 meeting at the Town of Millsboro indicate that a
significant reduction in pumping of the Columbia Aquifer risks a loss of the lateral and vertical
migration control established under the past pumping conditions. Therefore, it is imperative that
an altemative discharge option be implemented as soon as practicable to allow sustained higher
withdravral of water from PW-1 and PW-2 to minimize the potential for migration of the TCE
plume both laterally and vertically.
AR000443
^ A R C A D I S
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
The following list represents altemative discharge options for PW-1 and PW-2 to be considered
as specified in the Amendment No.1:
• Discharge of said water to Millsboro Pond or Indian River Bay;
• Reinjection of said water into a local aquifer; and
• A spray irrigation and/or rapid infiltration system.
Accordingly, the following discharge alternatives were evaluated:
• Reinjection into the Columbia Aquifer in the WB Atkins Memorial Park; use of an existing
18-inch benefiaal reuse water line, and altemative constnjction of a 6-inch line to deliver
water to the new injection wells were each considered,
• Spray irrigation via beneficial reuse water line to be completed in the future as part of
existing Town of Millsboro construction plans, and
• Surface water discharge to Millsboro Pond via a new 6-inch high density polyethylene
(HDPE) pipeline from the PW-1 and PW-2 systems to the pond.
The primary objective of the DAR is to recommend the altemative that will allow for the most
rapid implementation to resume proper operation of PW-1 and PW-2 and provide containment of
the TCE plume.
1.2 Report Organization
The report is organized as follows:
• Section 2 presents background information concerning the site physical and
hydrogeologic setting;
• Section 3 describes the PW-1 and PW-2 system characteristics;
• Section 4 describes the regulatory obligations and permitting requirements;
• Section 5 reviews the discharge altematives, and evaluates the feasibility of each
altemative;
AR000444
m ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
• Section 6 provides the DAR's conclusions; and
• Section 7 provides a list of references
2. Site Setting
2.1 Site Physical Setting
The Town of Millsboro well field is situated approximately 1,500 ft dowmgradient from the
Millsboro TCE site. See Figure 1. On-going environmental investigations indicate that affected
groundwater has migrated laterally in the shallow portion of the groundwater system (less than
60 feet deep) resulting in a narrow TCE plume. In the vicinity of the Millsboro well field, the
impacted groundwater has been drawm deeper and resulted in impacts above the TCE maximum
contaminant level (MCL) in two of Millsboro's water supply production wells ( PW-1 and PW-2).
Three additional production wells (PW-3, PW-4, and PW-5) have been installed deeper in the
system. Based on the available data, the deeper wells have not indicated site-related impacts
above the TCE MCL to date.
2.2 Site Geology
Based on site-specific boring logs and regional information, the subsurface geology is principally
composed of the following hydrostratigraphic units:
• Omar Formation and Beaverdam Formation of Columbia Group (from ground surface to approximately 95 feet deep) (DGS, 1984, 1990)
• The Bethany Formation (from approximately 95 to 180 feet deep) is composed of muddy silt beds overiying sands and sandy mud deposits wrfiich act as a semi-confining unit for the lower aquifers (DGS, 2004)
• The Pokomoke, Ocean City and Manokin Aquifer system (from approximately 180 to 260 feet deep); and
• The St. Marys formation (a gradational transition to underiying clay and sand units w/hich compose the bottom of the Manokin aquifer).
The Town of Millsboro well field is located on the Atlantic Coastal Plain and is underiain by the
Columbia Formation (Pleistocene in age). The Columbia Formation is described by the
Delaware Geological Survey (DGS) as yellow to reddish-brown, fine to coarse feldspathic quartz
sand with varying amounts of gravel. Scattered beds of tan to reddish-gray clayey silt are
common. In places, the upper 5 to 25 feet consists of grayish- to reddish-browm silt to very fine
sand overlying medium to coarse sand. Near the base, clasts of cobble to small boulder size
AR000445
I ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
have been found in a gravel bed ranging from a few inches to three feet thick. The Columbia
Fomiation fills a topographically irregular surface, can be up to 100 feet thick, and is interpreted
to be a body of fluvial glacial outwash sediment. Geologic findings from previous investigations
conducted at the Site are consistent with the DGS's description of the Columbia Fonmation.
The Columbia Formation is underiain by the Bethany Formation. Based on the production well
drilling logs from Millsboro, the Bethany Fonnation has been characterized as "gray clay wth
sand near its top" and "silt to gray silty-sand wnth increasing clay content" near its bottom. Given
the proximity of the well field to the Atlantic shore, significant variability in sand and day content
is expected both laterally and vertically, as the sediments transition ft'om high- to low-energy with
the historical sea level rise and fall. Qualitatively, the site's depositional setting and observed
lithology are consistent with a leaky aquifer, or low-yield aquifer, instead of a competent aquitard.
The Manokin Formation underiies the Bethany at approximately 180 feet below grade. The
Manokin Formation is characterized as fine to medium and coarse gray sand.
2.3 Site Hydrogeology
Ground surface elevations (i.e., topography) at the Site range from approximately 20 ft to 25 ft
above Mean Sea Level (MSL). Groundwater monitoring results from 2009 indicate that
groundwater elevations at the Site range from approximately 5 ft to approximately 15 ft MSL.
Horizontal groundwater flow mimics the local topography and generally flows north-east towards
the Indian River and Millsboro Pond. Regional gradients are approximately 1.05 X 10E-4 ft/ft and
6.31 X 10E-4 ft/ft in the unconfined and confined aquifers, respectively (DGS, 1984). Average
yeariy precipitation and evapotranspiration at the Site are approximately 40 inches and 25
inches, respectively (ESC, 1990).
Millsboro Pond and the Indian Bay Inlet are the closest surface water bodies and are located
approximately 1,200 ft downgradient of the Towm of Millsboro well field. The Indian Bay Inlet
exhibits tidal fluctuafions wrfiereas the section to the west that is dammed (Millsboro Pond) does
not exhibit tidal fluctuations.
Migration of the plume ft^om the Millsboro TCE site is influenced by the nature and stnjcture of
the sediments comprising the aquifer systems beneath the town and pumping in the Millsboro
well field.
Regional water production and local testing results indicate that the Columbia and Pokomoke,
Ocean City, and Manokin (Manokin) Aquifers are capable of producing significant water yields.
However, serious doubt exists regarding the Bethany Formation as a competent aquitard, and its
ability to prevent downward migration of impacted water from the Columbia, particulariy vrfien
AR000446
^ A R C A D I S
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
Millsboro's deep wells are all operating. The available data suggests that the nature of the
Bethany fonnation leads to its classificafion as a leaky aquitard (DGS, 2004) and in some areas
along the mid-Atlantic coast is transmissive enough to be exploited for water supply.
Regional data indicate that recharge of the Columbia and Manokin Aquifer systems is primarily
through infiltration of rainwater, and most of the recharge to the Manokin aquifer probably occurs
in the outcrop area. This result implies that a significant portion of water removed via pumping in
the deeper Manokin fomnation would be replaced by water derived from geologic formafions
above it.
3. Public Wells 1 and 2: System Description and Operations
3.1 Public Wells 1 and 2 System Configuration
Public Wells 1 and 2 each have independent treatment systems utilizing liquid phase granular
activated cart)on (LPGAC) to remove TCE. Each well has a 20 horsepower (HP) submersible
pump that pumps groundwater from the Columbia Aquifer through three parallel pairs of LPGAC
vessels operating in series. The three lead vessels in each pair provide primary treatment for
TCE; the lag vessels in each of the three pairs act as a polishing step to adsorb TCE that may
escape from the primary unit. The midpoint concentration is monitored to determine the need for
change outs.
The piping network between each wellhead and the vessels consist of 3-inch steel that
transitions to schedule 80 polyvinyl chloride (sch. 80 PVC) piping prior to a flanged connection to
a 3-inch flow meter. Following the flow meter, the PVC line manifolds to 3 lines with a ball valve
for each lead vessel. Each ball valve in the manifold is fitted wth a male cam-lock connection so
system piping can be transitioned for lead/lag operation follown'ng a LPGAC change out. The
effluent piping of each vessel has a ball valve and cam-lock connection for lead/lag piping
variations. The lag vessel piping manifolds to the system effluent that distributes either directly to
the tovm supply or to storage tanks depending on the demand.
In June of 2010, mechanical upgrades were conducted to install air relief valves to the top of
each vessel to prevent air entrainment w/hich can lead to channeling and eariy breakthrough.
Future system upgrades will be conducted followflng the altemative discharge design to
inconporate alarnis that wnll notify personnel of system shutdowns. These upgrades wnll help to
minimize downtime and target maximum uptime to maintain plume capture.
AR000447
l i l ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
3.2 PW-1 and PW-2 Influent/Effluent Water Quality
Table 3 provides a summary of weekly PW-1 and PW-2 system influent, midpoint, and effluent
discharge water quality sample results, for the period from January 2010 to December 2010.
TCE concentrations have fluctuated for PW-1 and PW-2 with the decreased pumping rates. PW-
1 has had a maximum concentration of 820 pg/L (ppb) and PW-2 concentrations have dropped
to less than 10 ppb since well output was reduced in August 2010.
Midpoint and effluent concentrations are monitored to schedule change outs. Typically a change
out is scheduled if midpoint TCE concentrations are between 2-3 ppb or above 5 ppb. If
concentrations are noted in the effluent from the second unit, the systems are immediately
shutdown and change out is immediately scheduled.
Samples were collected from PW-1 in October and from PW-1 and PW-2 in December 2010 to
analyze nitrate and other anion levels. Nitrate concentrations ranged from 6.0 to 7-0 mg/L. These
results are consistent wflth nitrate concentrations observed in samples collected by the Tovm of
Millsboro. Analytical results for nitrate, bicarbonate, cart)onate, chloride, and sulfate are
presented in Table 4.
4. Regulatory Obligations and Permitting Requirements
The three discharge altemative opfions of the treated effluent groundwater, the associated
pemiitting requirements, estimated time to receive permit approval, and the relevant pemiitting
authority are presented below:
Discharge Option
1. Reinjection to the Columbia aquifer in the WB Atkins Memorial Pari<
Permit Required
Underground Injection Control Pennit
Estimated Time to Pennit Approval
60 - 90 days (includes public notice and comment period)
AR000448
^ ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
2. Spray imgation
via beneficial reuse'
water line to be
. completed in the
future as part of
existing Town of
Millsboro
construction plans.
3. Surface water
discharge to
Millsboro Pond
Land Application
Permit
NPDES permit
105-135 days
(includes 60 - 90 day
review of the Design
Report, 30 day review
of the plans and
specifications, and a
15-day public notice
and comment period)
60 - 90 days
(includes public
notice and
comment period)
5. Discharge Alternatives Evaluation
5.1 Identification of Discharge Alternatives
This section identifies and describes the potential discharge alternatives for PW-1 and PW-2
water that are currently under consideration. Each altemative will require that backflow
preventers be placed on both the PW-1 and PW-2 discharges before manifolding together into
one 6-inch HDPE line that mns north to Church Street for the future altemative connection. The
existing piping from each system WAII remain in case the Tow/n water supply needs to be
supplemented by either treatment system. These wells would need to be identified for this
application on the subsequent water allocations pennit. The ability to discharge to the Town
water supply will be coordinated wnth Millsboro and designed into the system.
This DAR evaluated the followflng three altematives:
1. Reinjection into one or more wells in the WB Atkins Memorial Park;
2. Spray irrigation/beneficial reuse; and
3. Surface water discharge to Millsboro Pond by installation of a 6-inch high density
polyethylene (HDPE) pipeline from the pumping systems to the pond.
AR000449
51) ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
A detailed analysis of each of the alternatives is provided in the following sections. Detailed
analysis performed for the altematives consist of an assessment against each of the following
evaluation criteria:
1. Overall protection of human health and the environment;
2. effectiveness;
3. implementability;
4. state/community concerns; and
5. cost-effectiveness.
This DAR does not fully evaluate system design. Design and final costing will be conducted
following selection and regulatory approval of a discharge altemative.
5.2 Alternative 1 - Groundwater Reinjection
This altemative focuses on pumping groundwater from the Columbia aquifer, treating for TCE,
and then injecting via injection wells located in WB Atkins Memorial Park back into the Columbia
aquifer. Treated water is transported to the injection wells via the existing 18-inch beneficial
reuse line that runs west down Church Street before fuming north on Sussex Street and then
tuming west into the park. A valved connection would be tapped into the existing beneficial
reuse line piping and 6-inch HDPE weuld run from the connection to the new injection wells. The
well design w/ill depend on the volume that can be discharged based on the subsurface
characteristics at the Site. Presence of high permeability media and high aquifer recharge are
necessary for using this discharge option. The injection can be conducted under gravity or
pressurized through horizontal or vertical wells. Beyond the benefit of disposal of the treated
water, there are two primary advantages to recharging the aquifer :(1) beneficial reuse
of treated groundwater through aquifer recharge, and (2) preventing acute deterioration of
the groundwater yield of the aquifer.
OverafJ Protect/on of Human Health and the En wronment -This altemative provides a level
of protection similar to that of the cun-ent system operation. PW-1 and PW-2 treatment systems
wflll provide hydraulic control which is still the primary objective, wflth the only difference being on-
site injection instead of potable water use of treated groundwater. Detailed hydraulic modeling
suggests that re-injection can be accomplished wflthout compromising the ability of PW-1 and
PW-2 to maintain hydraulic control. (See the Executive Summary of Hydrogeologic Investigation
AR000450
1 ^ ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361) Millsboro, Delaware
of the Downward Migration Potential of Dissolved Solutes Present in the Columbia Aquifer to
Reach the Manokin Aquifer [ARCADIS, October 2010]). Addifional detailed modeling will be
required to determine the appropriate design and location of the reinjection wells. In addifion,
there is no deleterious impact on the aquifer water quality in the area of recharge since water of
similar quality, from the Columbia formation neartsy (treated for TCE), is being recharged.
This alternative w/ill not affect protection of human health and the environment. Treated water
from the systems discharge is anticipated to have similar nitrate concentrations to the
groundwater in the reinjection zones.
Effectiveness — In general, the Columbia aquifer is very penneable and the results of
preliminary hydraulic modeling suggests infiltrafion via reinjection wnll be effective. Aquifer •
recharge testing would be required to determine the location for effective recharge of
groundwater.
Implementability—An Underground Injection Control (UIC) permit may be required for
implementation of this option. The required equipment and services for constructing and
operating injection wells are available. The potential to use the existing beneficial reuse line
makes this option the fastest possible to install. The injection wells and short distance of piping
can be installed wflthin a matter of 3 to 6 months.
Implementafion will require tapping into the existing infrastructure for the beneficial reuse line.
New piping wnll be installed from the beneficial reuse line to the injection wells and the wells will
be protected by vaults surrounded by bollards. Engineering design work, materials procurement,
equipment and electrical components installation, as well as system construction and testing will
also be required.
If the current discharge line is not available for use in the reinjection system, implementation of
this altemative WAII require new piping to be installed ft^om the current system locations to the
proposed injection wells. Construction would include wori< within local side streets (Church and
Sussex Streets) to extend the piping to WB Atkins Memorial Pari<. The installation of the
conveyance piping through Church Street and Sussex Street may require building and road
closure permits.
Sctiedule/Estimated Timeline—Since most of the infrastructure is already installed this
altemative would be the most time efficient selecfion. Construction activities for well installation
and piping connecfions are anticipated to take 3-6 months if the beneficial reuse line is used.
AR000451
^ A R C A D I S
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
If a new discharge line is required, construction activities to permit and install new piping
between the wells and the treatment systems wnll increase the timeline for implementation.
Construction activities for well installation and installation of new piping are anticipated to take 9-
12 months.
State/Community Concerns - The reintroduction of treated groundwater back into the
Columbia Aquifer should not be a concern because TCE will have been removed.
The treated Columbia fonnation water will be reinjected back into the Columbia aquifer
in a slightly different location in essentially the same condition it was removed - except
for the treatment of TCE.
Cost— The capital costs associated wflth implementing this option are expected to be moderate
to high based on the number of injection wells required. O&M costs associated wnth the
maintenance of the discharge line are expected to be moderate to high depending on the degree
• of scaling and fouling encountered wnthin the discharge piping and injection wells. If fouling is
excessive a backup reinjection well may be required to accommodate maintenance of the
primary wells.
The estimated costs are provided in the Alternative Discharge Saeening Summary table
attached as Table 5. These costs include capital costs associated wflth construction of
reinjection systems and yeariy costs for routine treatment system O&M including groundwater
monitoring costs. Anticipated O&M activities associated with the reinjection system include daily
operation of the extraction, treatment and reinjection systems, equipment repairs and
preventative maintenance activities, operational and compliance monitoring activities, purchase
and installation of supplies, property maintenance, waste management, and well redevelopment
activities.
Estimated capital costs for construction of inft-astructure piping and reinjection wells are
approximately $450,000, including contingencies. Conceptual constnjction costs include the
installation of backflow preventers, vaults, conveyance piping, controls, plus the installation of an
estimated two 90-foot-deep injection wells and associated piping.
If the current discharge line is not available to facilitate delivery of the treated groundwater to the
injection well locations the addition of new HDPE piping and valves between the treatment
systems and the wells WAH be required. Constnjction vAW likely require permits and road closures.
Estimated capital costs for construction of the new discharge piping are approximately $150,000.
10
AR000452
1 ^ ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361) Millsboro, Delaware
5.3 Alternative2-Spray Irrigation
This altemative would utilize the existing beneflcial reuse wateriine that currently njns from the
treatment system area to WB Atkins Memorial Park; however, it is not anticipated that the line WAII
be completely installed and ready for at least two to three more years. When complete the
beneficial reuse pipeline will run approximately 2 to 3 miles northwest to a storage tank that will
distribute water for irrigation.
Overall Protection of Human Health and the Environment- If operated year-round, this
altemative could provide a level of protection similar to that of the current system operation. PW-
i and PW-2 treatment systems wnll provide hydraulic control w/hich is still the primary objective.
This alternative will not affect protection of human health and the environment.
Effectiveness— Spray irrigation would be an alternative use of treated groundwater from PW-1
and PW-2. However, this option vj\\\ not provide the year round discharge and disposal of the
effluerit from PW-1 and PW-2 required to maintain plume control.
Implementability — The Towm of Millsboro is cun^ently pursuing installation of a beneficial reuse
line for the purpose of spray imgation. Beneficial reuse for spray irrigation w/ill not be a possibility
for potentially 2 to 3 more years wtiile infrastructure is installed to carry the pipeline to the final
end use location. Even when the pipeline is installed and water is sent to the imgation tanks for
reuse, this option will require another end use of the treated water from PW-1 and PW-2 during
times of decreased demand for irrigation water. At present, end uses sufficient to consume all
effluent from PW-1 and PW-2 have not been idenfified. Penmitting is also difficult and is likely
to.push back the construction of the pipeline.
Schedule/Estimated Timeline— Per conversations with Town officials construction activities for
additional beneficial reuse piping WAII not be completed for an estimated 2-3 years.
State/Community Concerns - Discharge of treated groundwater via spray imgation for
beneficial reuse should not be a concem. Delaware has a long history of promoting beneficial
reuse of reclaimed water. Some fields in Delaware have been receiving reclaimed water since
the 1970's Wflth no adverse effects to the fields, crop yields or the water table beneath the field.
As of 2002, there are 23 facilities permitted in Delaware to apply reclaimed water onto 2200
acres of land. Most of the land used for beneficial reuse is agricultural, but reclaimed water is
also used to irrigate tvro golf courses and several tracts of wooded land.
Cost—The capital costs associated wnth implementing this option are low. Existing/future lines
would be utilized to convey treated system water.
11
AR000453
^ A R C A D I S
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
5.4 Alternative 3 - Surface Water Discharge to Millsboro Pond
Local surface water bodies may be available to accept discharge ft"om a groundwater treatment
system. Millsboro Pond is located approximately 1,200 fl north of the Millsboro water plant.
Smaller tributaries and stonm drains are closer and discharge to the Millsboro Pond. A discharge
line and an outfall can be constnjcted from the treatment system to existing drainage toward
neart)y surface water bodies.
Overall Protection of Human Health and the Environment - This altemative provides a level
of protection similar to that of the past system operation. PW-1 and PW-2 treatment systems vAW
provide hydraulic control which is still the primary objective.
Nutrient loadings have been idenfified as a significant contribution to the degradation of
Delaware's surface waters. DNREC enforces regulations governing the pollution control strategy
for the Indian River and Bay, Rehoboth Bay and Little Assawoman Bay Watersheds. The
Pollution Control Strategy is designed to reduce the amounts of nitrogen and phosphoms
entering the Inland Bays and their tributaries to levels required to meet water quality standards.
The strategy includes provisions to establish buffers to filter and remove pollutants before they
flow into the Inland Bays and their tributaries
This altemative w/ill not affect protection of human health and the environment. However,
treatment for nitrates will likely be required before discharging to surface water.
Effectiveness groundwater.
-Surface water discharge is an effective disposal method for treated
Implementability — A discharge permit and monitoring will be required. An environmental
assessment of the impact on the discharge may be required. Nitrate treatment will more than
likely be required. Infrastmcture piping and constmction logistics through existing town roads are
very invasive. There are no clear paths to Millsboro Pond that don't require going through private
property or busy streets.
The cun-ent nitrate concentrations measured in October and December 2010 in PW-1 and PW-2
were between 6 to 7 mg/L; these levels are attributable to background. See Table 4. Nitrate
treatment WAII require ion exchange for direct surface water discharge to Millsboro Pond. The
system effluent streams would be combined prior to ion exchange treatment. Two
vessels would be operated in series to remove anions from the combined streams.
The treated effluent will then discharge to conveyance piping to the Millsboro Pond.
Nitrate treatment w t̂h ion exchange wn'th cun-ent site concentrations of 6-7 mg/L will require
12
AR000454
J ^ ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
frequent resin change outs or regeneration that will cause system dovmtime and generation of
residual waste from the change-out or regeneration process.
Ion exchange technology is effective for removing nitrate; however, the capital and O&M costs
associated with ion exchange technology are extremely high. The frequency of resin change
outs (or regeneration) makes ion exchange an extraordinary logistic burden because vendor-
provided resin usage rates suggest a change out (or regeneration) frequency of every 1 to 2
weeks.
Schedule/Estimated Timeline— Constmction activities to permit and install the new piping
between the surface water discharge and the treatment systems is considered to be complex as
the piping w/ill probably have to be routed up main roads through the Tovm of Millsboro. Design
and constnjction activities for surface water outfall and installation of new piping and nitrate
treatment system are anticipated to take 1-2 years. Furthermore, O&M associated wflth frequent
resin change outs activities would lead to system dovmtime.
State/Community Concerns - Discharge of treated groundwater via surface discharge should
not be a concem as the effluent discharged meets drinking water quality standards.
Cost— Capital costs will be very high based on the distance and the impact to private property
and/or road closures. Capital costs are anticipated around $600,000 to run conveyance
piping to Millsboro Pond and install an outfall structure. Nitrate treatment requirements add
$1,100,000 to the capital costs and $600,000 for the annual O&M costs, an order of magnitude
higher than other options. Accordingly, implementation of any discharge option involving
treatment of nitrates is time and cost prohibitive.
5.5 Comparative Evaluation of Alternatives
This section compares the altematives, utilizing the criteria evaluated in the above sections. The
inifial evaluafion includes a comparison of the altematives against the threshold criteria. The
threshold criteria represent the minimum requirements for each alternative in order to be eligible
for selection. The primary balandng criteria (protection of human health and the environment,
effectiveness, implementability. State and community concems, and cost-effectiveness) allow.for
the direct comparison of altematives against each other.
Overall Protection of Human Health and the Environment
All discharge altematives would allow for the system to operate and maintain containment of the
groundwater plume preventing the potential of constituent transport. With system downtime
13
AR000455
^ ARCADIS
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
being the most critical component of this evaluation, Altemative 1 will be the fastest opfion to
implement.
Effectiveness
Altemafive 1 (Reinjecfion using the exisfing beneficial reuse line) is considered an effecfive
discharge altemative. Reinjection of the groundwater wnll allow the systems to run and maintain
hydraulic control of the groundwater plume. Altemative 2 (Spray Imgation) is not a satisfactory
alternative because it WAII only provide a complete discharge altemafive during periods of high
imgation demand. Alternative 3 is not a satisfactory altemative because of excessive time and
cost constraints along with the uncertainty associated vflth the placement of the discharge line
through private properties.
Implementabilitv
Altemafive 1 is easily implementable and has the best potenfial for an expedited implementation.
Injection wells WAII be installed in WB Atkins Memorial Park and piping connections could be
tapped into the existing beneficial reuse line. While Altematives 2 and 3 are implementable, it
\N\\\ simply require a longer fimeline to acquire road closure permits and install the piping.
Permitting risks for each of these altematives are the same.
State/Community Concems
Although none of the altematives are likely to cause public concern. Alternative 1 does not
involve discharge to a surface water body, and WAII most likely meet wflth public acceptance.
Cost-Effectiveness
Capital and O&M costs would be associated with all three discharge altematives. Based on
preliminary cost estimates developed for this report (Table 5), Altemative 2 would involve low
upfront capital costs however, it will not be an implementable solution for 2-3 years. Capital costs
associated wnth Altemative 3, the surface water discharge option, would be very high based on
the distance and the impact to private property and/or road closures. In addition, this discharge
option would include an extraordinarily high O&M cost associated with nitrate treatment - making
this option cost prohibitive. Altemative 1 would be the least expensive opfion for the fastest
installation, requiring approximately $450,000 of capital, wnth estimated annual OM&M costs of
about $25,000.
14
AR000456
^ A R C A D I S
Discharge Alternatives Report
Public Well TCE Site (DE-1361), Millsboro, Delaware
6. Conclusions
This DAR has evaluated three possible altematives:
• Reinjecfion into two wells in the WB Atkins Memorial Pari< utilizing either the exisfing 18-
inch beneficial reuse wateriine or a new 6-inch HDPE pipeline.
• Spray irrigation/beneficial reuse.
• Surface Water Discharge
Altemafive 1, reinjection into wells in the WB Atkins Memorial Park ufilizing exisfing 18-inch
beneficial reuse wateriine, has been detemiined to be the most rapidly implementable of the
altematives. With system dovmtime being the most critical component of this evaluation.
Alternative 1 will be the fastest option to implement. Altematives 2 and 3 would require a longer
design and construction/installation timeline for conveyance piping networks.
Spray Irrigation (Altemative 2) is not considered a viable discharge option due to time-frame
required for full implementation and its inability to assure year round disposal. Surface water
discharge (Altemative 3) is not considered due to low implementability, high costs, extended
timeframes, and the requirement of nitrate treatment.
Regardless of the altemative implemented, the PW-1 and PW-2 systems will be retrofitted wnth a
backfiow preventer so flow can be directed to the town water supply or to the discharge
altemative so the Town wnll not lose PW-1 and PW-2 capacity for emergency situations.
7. References
ARCADIS US, INC., 2010. Evaluation of Potential Risks Associated with Expanded Pumping in
IVIanokin Aquifer, Millsboro, Delaware.
Delaware Geological Survey (DGS), 1984. Hydrology of the Manokin, Ocean City, and
Pocomoke Aquifers of Southeastern Delaware, Report of Investigation No.38
Delaware Geological Sun/ey (DGS), 1990. Ages of Bethany, Beaydam, and Omar Formations of
Southern Delaware, Report of Investigation No.47
15
AR000457
Discharge Alternatives Report
( ^ ARCADIS
Millsboro, Delaware
Delaware Geological Survey (DGS), 2004. The Cat Hill Formation and Bethany Fonnation of-
Delaware, Report of Invesfigation No.67
EPA, 2010. Amendment Number 1 to Administrative Settlement and Order on Consent for
Removal Action Response. November 2010
16
AR000458
ARCADIS
Table 1 PW-1 2010 Monthly Operational Data Millsboro, Delaware
PW-1
Date
Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10
Flow Differential
(gal)
5,050,400 4,318,500 4,778,100 5,529,000 6,774,100 7,803,500 8,041,800 4,297,501 1,455,901 2,345,700 1,236,600 717,900
Time Differential
(days)
31 28 31 30 31 30 31 31 30 31 30 31
Time Differential
(min)
44,640 40,320 44,640 43,200 44,640 43,200 44,640 44,640 43,200 44,640 43,200 44,640
Up Time (gal/200)
(min)
25,252 21,593 23,891 27,645 33,871 39,018 40,209 21,488 7,280
11,729 6,183 3,590
Up Time
(days)
17.5 15.0 16.6 19.2 23.5 27.1 27.9 14.9 5.1 8.1 4.3 2.5
Up Time
%
57% 54% 54% 64% 76% 90% 90% 48% 17% 26% 14% 8%
Average Flow (gpm)
113 107 107 128 152 181 180 96 34 53 29 16
Notes: gal: gallons gpm: gallons per minute PW-1 has an approximate fiowrate of 200 gpm
Page 1 of 1
AR000459
ARCADIS
Table 2 PW-2 2010 Monthly Operational Data Millsboro, Delaware
PW-2
Date
Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10
Flow Differential
(gal)
5,258,300 4,506,500 4,983,800 4,836,857 6,767,215 7,854,500 6,887,800 4,423,801 4,726,001 2,155,500 2,028,100 1,166,202
Time Differential
(days)
31 28 31 30 31 30 31 31 30 31 30 31
Time Differential
(min)
44,640 40,320 44,640 43,200 44,640 43,200 44,640 44,640 43,200 44,640 43,200 44,640
Up Time (AG/200)
(min)
26,292 22,533 24,919 24,184 33,836 39,273 34,439 22,119 23,630 10,778 10,141 5,831
Up Time
(days)
18.3 15.6 17.3 16.8 23.5 27.3 23.9 15.4 16.4 7.5 7.0 4.0
Up Time
%
59% 56% 56% 56% 76% 91% 77% 50% 55% 24% 23% 13%
Average Flow (gpm)
118 112 112 112 152 182 154 99
109 48 47 26
Notes: gal: gallons gpm: gallons per minute PW-2 has an approximate fiowrate of 200 gpm
Page 1 of 1
AR000460
Table 3 2010 Trichloroettiene Analytical Results Millsboro, Delaware
1/4/2010 1/11/2010 1/18/2010 1/25/2010 2/1/2010 2/9/2010 2/15/2010 2/22/2010 3/1/2010 3/8/2010 3/15/2010 3/22/2010 3/29/2010 4/7/2010 4/12/2010 4/19/2010 4/26/2010 5/3/2010 5/10/2010 5/17/2010 5/24/2010 6/1/2010 6/7/2010 6/14/2010 6/21/2010 6/28/2010 7/6/2010 7/13/2010 7/19/2010 7/26/2010 8/2/2010 8/9/2010 8/16/2010 8/23/2010 8/30/2010 9/7/2010 9/13/2010 9/21/2010 9/27/2010 10/4/2010
10/11/2010 10/18/2010 10/25/2010 11/1/2010 11/8/2010
11/15/2010 11/22/2010 11/29/2010 12/6/2010
12/20/2010 12/28/2010
PW-1 Influent Midpoint
130 140 220 190 160 120 150 230 130 190 220 260 240 260 250 210
280D 250D 220D 250D 240D 230D 210D
190D(190D) 150DJ 190D 250D 180D 180D 170D 160D 120D 180 370 180
160D
<0.50U, < 0.50U'' < 0.50U < 0.50U <0 50U < 0.50U < 0.50U < 0.50U <0 50U < 0.50U < 0.50U < 0.50U < 0.50U < 0 50U <0.50U < 0.50U < 0 50U
<0.50U(<0.50U) <0.50U < 0.50U < 0.50U <0.50U < 0.50U <0.50U 0.5UBJ
<0.50U(<0.50U) <0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U
i0.50U(<0.50U) < 0.50U < 0.50U
* System down for electrics * System down for electrics
150D 270 (260D)
170 150D 270D
< 0.50U < 0.50U < 0.50U
< 0 50U (< 0.50U) < 0.50U
* System carbon change 500D 450D 180D' 240D 400 410 820
< 0.50U < 0.50U < 0.50U < 0.50U
< 0 50U (< 0.50U) < 0.50U < 0.50U
Effluent < 0.50U < 0 50U <0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0 50U < 0.50U < 0.50U <0.50U < 0.50U
0.092J (<0.50U) < 0.50U <0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U
0.5UBJ (0.5UBJ) < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U < 0.50U
< 0.50U (< 0.50U) < 0.50U < 0 50U < 0.50U
repsirs repairs
< 0.50U < 0.50U
< 0.50 (< 0.50) < 0 50U 0.13J
i out
< 0.50U < 0.50U < 0.50U
< 0.50U (< 0.50U) < 0.50U < 0.50U < 0.50U
Influent 94 130 72 110 120 94 90 80 31. 94 73 52 68 77 66 66
70D 76D
I IOD(IIOD) 130D 160D 170D 200D 180D 190DJ 260D 1 (1) 1600 180D 240D 230D 210D 210 89
140(190) 280D 120 280 130D
1 32
64D 53D (55D)
48D 23D 16D 27D 13 84 3.4
0.42 (0.44)
PW-2 Midpoint < 0.50U < 0.50U < 0.50U < 0.50U < 0 50U < 0.50U <0.50U <0.50U < 0.50U <0.50U <0.50U < 0.50U <0.50U < 0 50U
0.25 < 0.50U 0.097J 0.16J
0.088J 063
0.46J (0.45J) 0.64 2.6
0.83 0.74UBJ
0.74 0.074J 0.052JL
0.085J (0.096J) 0 13 0 1
0.091J 0.4
0.65 0.43 0 2
0.37(0.46) , 0.17J
0.1 036 0.26
<0.50U 0.27J
< 0 50U < 0.50U (< 0.50U)
<0.50U <0.50U <0.50U <0.50U <0.50U <0.50U
Effluent < 0.50U < 0.50U < 0 50U <0.50U <0.50U <0.50U <0.50U <0.50U <0.50U <0.50U <0.50U <0.50U <0.50U <0.50U < 0.50U < 0.50U < 0.50U < 0 50U <0.50U
0.063J(<0.50/<0.50U) 0.055J < 0.50U < 0.50U 0.058J 05UBJ 0.059J
< 0.50U < 0.50U {< 0.50UJL)
< 0.50U < 0.50U < 0.50U < 0.50U < 0.50U <0.50U <0.50U
< 0.50U (< 0.50U) <0.50U <0.50U <0.50U < 0.50U < 0.50U < 0 50U < 0 50U
< 0.50U (< 0.50U)
< 0.50U < 0.50U <0.50U <0.50U <0.50U
<0.50U(<0.50U) < 0.50U
Change out performed. Vessel lead/lag configuration change Parenthesis denote s duplicate ssmple D: Diluted Ssmple U: FIsg indicates no detection for the compound J: Ssmple result flagged ss esfimated is below ttie mettiod detection limit B: Analyte was found in the associated method blank as well as the sample All results are in micrograms per liter (tjg/L) Sample results betwreen January 4, 2010 snd Apnl 19, 2010 provided by EA historical analyticsl tables
Page 1 of 1
AR000461
Table 4 Anion Analytical Results
Millsboro, Delaware
Sample ID
Sampling Date
WET CHEMISTRY
Bicarbonate Alkalinity as CaC03
Carbonate Alkalinity as CaC03
Chloride
Nitrate as N
Sulfate
PW-1 A
10/25/10
PW-2A
10/25/10
PW-1 A
12/28/10
PW-2A
12/28/10
Result (mg/L)
11.9
5.0
21.5
6.3
16.3
10.6
5.0
17.1
6.4
13.7
14.8
5.0
18.8
7.0
13.4
12.2
5.0
17.1
6.0
16.3.
Notes:
mg/L: milligrams per liter
Samples collected from influent sampling ports
AR000462
Table 5 Alternabve Discharge Screening Summary Millsboro, Delaware
Discharge Alternative
Reinjection - Use ot 1. Beneficial Reuse Piping
Network
Spray 2. Irngabon/Benefidal
Reuse
2 Surface water discharge to Millsboro Pond •
Overall Protection of Human Health and the Environment
This alternative provides a level of protection similar to that o( Ihe current system operation. Detailed hydraulic modebng suggests that re
injection can be accomplished without compromising the ability of PW-1 and PW-2 to maintain hydraulic control. This alternative will not affect protection of human health and the
environment.
If operated year-round, this alternative could provide a level ot piotection similar to that ot
the current system opeiation. PW-1 and PW-2 treatment systems will provide hydraulic
control which is sbll the primary objective. This alternative will not affect protection of human
health and the environment.
This alternative provides a level o( protection similar to that of the past system operation.
PW-1 and PW-2 treatment systems will provide hydraulic control which is still the primary objective. This alternative will not alfecl protection ot human health and the
environment. However, treatment for nitrates will likely be required before discharging to
surface water.
Effectiveness Evaluation
High: Reinjection allows for the aquifer to be recharged so there is no
loss in aquifer pumping potential.
High: Beneficial reuse will supply irrigation needs for the community. Treated groundwater will be sent directty into beneficial reuse Hne.
Moderate: Surface water discharge to Millsboro Pond will be an effective
discharge location however existing nitrate levels in Millsboro Pond Vrill
require further treatment of groundwater.
Implementability Evaluation
High: Existing beneficial reuse piping avoids installation of new conveyance
piping under existing roadways and makes this the fastest option to implement.
Injection wells and new piping from the beneficial reuse line mininruze
construction. II the current discharge line is not available to facilitate delivery of the treated groundwater to the injection well
locations the addition of new HDPE piping and valves between the treatment systems and the wells VMII be required. Construction
wilt likely require permits and road closures.
Moderate: Infrastructure will not be installed for another 2-3 years. Would need to be supplemented with another
discharge options when beneficial leuse demand is low.
Low: Lack of direct route to Millsboro Pond (or infrastructure piping v*\\ require the
need for construction through main streets. Existing high nitrate concentrations in
Millsboro Pond vrarrant the addition of ion exchange for nitrate treatment.
Estimated Schedule
Fastest Option to Implement: 3-6 Months
6-12Months It existing piping is unavailable for
use.
2-3 Years
1-2 Years
State/Community Concerns
The reintroducfion of treated groundwater back into the
Columbia Aquifer should not be a concern because TCE will have been removed. The treated Columbia formation vrater will be reinjected back
into the Columbia aquifer in a slightly different location in
essentially the same condition it was removed - except for the
treatment of TCE.
Discharge of treated groundwater via spray irrigation (or beneficial reuse should not be a concern. Delaware has a
long history of promoting beneficial reuse ol reclaimed
water.
Discharge of treated groundwater via surface
discharge should not be a concern as the effluent
discharged meets drinking water quality standards.
Relative Cost Evaluation
Moderate: Moderate capital for injection we\k but low 04M
costs to implement and maintain. 5450,000 capital
install. Estimated capital costs for construction of new
discharge piping are -approximately $150,000.
Low: Lowcapitalcosls; low O&M costs.
High: Moderate conveyance line capital costs S600.000; High ion exchange capital
costs $1,100,000; High annual O&M costs
5600,000.
Retained?
Yes: Fastest Option to Implement.
Yes. HoWBvei, significant limitations due to
implementation and inability (or year round end use.
Considered in conjunction with other technologies.
No' Intrastructure piping installation anid additional
design, equipment procurement, and installation will not allow for alternative to
be implemented in a reasonable timeframe.
Conclusion/ Recommendation
Yes, pursue Discharge Alternative 1
No, do nol pursue Discharge Allernalive 2
No, do not pursue Discharge Alternative 3
Notes: O&M - Operations & Maintenance USEPA - United States Environmental Protection Agency
AR000463
„ f - i
- M W / 11-S . M W / , 1 1 - M ' ' M W M 1 ^ 5 ^ ^ /*j£^j
( » . * •
* , * i » I W / 1 5 - S " i t " j B M W / I S - p W P W S
" " ' • ' • i * M W / 1 2 . S V M W M 2 - D
M W / 1 3 . S ^^^^^ . / ^ ^ ^ , ^ 4
i.̂ 'Ofc
W3*.///
- -^ X *:• '̂MWoiMV '^,„J ' / . ' • -̂ .•111 l i j j l l - J l E i > f J - * - J f c r t ^ M ! * • *
f > r y ? ' ^ *
* ^ - ^ ^
^ M W 0 9 S P'MWOSO
; : H D L G P M W 1 K:HDLGP'MW2 , H D L G P M W 3
V HDLGPIVrW4 H D L G P M W 5
- " M W i O S * f M W / 1 0 - O - ! ^ , - ^ „ , . 3 - ..*
I f f •' ' ^
PROJECTION NAU_iyaj_bia!ePline_[JBlaware_FIPS_a/OU AERIAL SOURCE DigitalGlobe (2005),
LEGEND
- ^ Existing Manitotmg WeH
V Monitoring Well (ColumCiia Aqui(er)
'.< Monitoring Well (Bettiany Aquifer)
^ Uonrtonng Wall (Manokin Aquifer}
% Supply Well
SCALE IN F E E T
MILLSBORO, DELEWARE
EXISTING MONITORING WELL LOCATIONS
( ^ ARCADIS FIGURE
1
AR000464