direct revision elj co - emcbc.doe.gov...sdd/dd c seismic/stress analysis e] rank calibration manual...

104
* 1. ECN 119532 ENGINEERING CHANGE NOTICE--------- Page 1 of A.45 Proj. - ECN 2. ECN Category (mark one) 3. Originator's Name, Organization. MSIN. and Telephone No. 4. Date Supplemental 11 A. F. Crane, Effluent Technoloov. R2-20 37-47 2-2791 Direct Revision ElJ Change ECN E S. Project Title/NoiWork Order No. co 6. Bldg./Sys./Fac. No. 7. impact Level Temporary C1 42A/PUJREX, Pl ant Codensate Theatbnent Facil1 i t 202-A/242-A 3 Scovredry 8l S Document Number Affected (include rev. and sheet 9. Related ECN No(s). 1.RltdP o Disceryoid no_)WHC-SO-CO18H-FDC-OO1 REV t 1'4/, 11 a. Modification Work 11 b. Work Package 11 c. Complete Installation Work IId. Complete Restoration (Temp. ECN only) C3 Yes (fill out elk. 11 b) Doc. No. MAi SNo (NA elks. 11ib, [;/,AANI 1 1c, li1d) Cog. Engineer Signature & Date Cog. Engineer Signature & Date 12. Description of Change See attached detailed description of changes. t~ota: Changes have directly affeacted page iurnberinC and, therefore, the Table of Contents. Approved with comments: This- FDC is approved without an approved Hazard Classification (Refer to Safety RCR #LW-1-0). Document number Changed to WHC-SD-CO18H-FDC-001 REV 2 to incorporate the "H"l used in HEC tracking. Preliminary Safety Evaluat 'ion (WHC-SC-WM-PSE-007, released December 27, 1990. suoortin' Document Block 7) address the ,hazard classification of the facility, resolving the above RCR comment L14-1-0. 6L,2, #z'9 ''. -74 ."/ /os C.. 13a. Justification (mark one) 1 3b. Justification Details Criteria Change 0 See attacheC for a detailed justificaticn. Design Improvement C3 Environmental As-Found Facilitate Const. Const. Errori~missionQ Design ErroriOmissionQ 14. Distribution (include name. MSIN, and no. of copies) RELEASE STAMP See Distribution List OFCA EES DATE JUN 03. 191 A-7900-013 (11/88)

Upload: others

Post on 13-Jan-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

* 1. ECN 119532ENGINEERING CHANGE NOTICE---------

Page 1 of A.45 Proj.- ECN

2. ECN Category (mark one) 3. Originator's Name, Organization. MSIN. and Telephone No. 4. DateSupplemental 11 A. F. Crane, Effluent Technoloov. R2-20 37-47 2-2791Direct Revision ElJChange ECN E S. Project Title/NoiWork Order No. co 6. Bldg./Sys./Fac. No. 7. impact LevelTemporary C1 42A/PUJREX, Pl ant Codensate Theatbnent Facil1 i t 202-A/242-A 3

Scovredry 8l S Document Number Affected (include rev. and sheet 9. Related ECN No(s). 1.RltdP oDisceryoid no_)WHC-SO-CO18H-FDC-OO1 REV t 1'4/,

11 a. Modification Work 11 b. Work Package 11 c. Complete Installation Work IId. Complete Restoration (Temp. ECN only)C3 Yes (fill out elk. 11 b) Doc. No. MAi

SNo (NA elks. 11ib, [;/,AANI1 1c, li1d) Cog. Engineer Signature & Date Cog. Engineer Signature & Date

12. Description of Change

See attached detailed description of changes.

t~ota: Changes have directly affeacted page iurnberinC and, therefore, the Table of Contents.

Approved with comments: This- FDC is approved without an approved Hazard Classification

(Refer to Safety RCR #LW-1-0).

Document number Changed to WHC-SD-CO18H-FDC-001 REV 2 to incorporate the "H"l used inHEC tracking.

Preliminary Safety Evaluat 'ion (WHC-SC-WM-PSE-007, released December 27, 1990. suoortin'Document Block 7) address the ,hazard classification of the facility, resolving the aboveRCR comment L14-1-0. 6L,2, #z'9 ''. -74 ."/ /os C..

13a. Justification (mark one) 1 3b. Justification DetailsCriteria Change 0 See attacheC for a detailed justificaticn.Design Improvement C3EnvironmentalAs-Found

Facilitate Const.Const. Errori~missionQDesign ErroriOmissionQ

14. Distribution (include name. MSIN, and no. of copies) RELEASE STAMP

See Distribution List OFCA EES

DATE JUN 03. 191

A-7900-013 (11/88)

Page 2: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

ENGINEERING CHANGE NOTICE Page 2of 'J'5 1- C(uen.fopg1,

(O4f 1195 32 -15. Design Ver if ication 16. Cost Impact -17. Schedule Impact (days)

Required ENGINEERING CONST~OIUCT

SYes Additional E] $ S ______ Additional C3 S ' f r4provement

[2 No Savings 0 S ________ Savings S _________ Delay_____

18. Change impact Review: Indicate the related documents (other than the engineering documents identified on Side 1) that will be affected bythe change described in Block 12. Entertne affected document number in Block 19.SDD/DD C Seismic/Stress Analysis E] rank Calibration ManualFunctionai Design Criteria C Stress/Design Report CHealth Physics ProcedureCOperating Specification Interface Control Drawing Spares Multiple Unit Listing QCriticality Specification C Calibration Procedure CTest Procedures/Specification C3 -Conceptual Design Reciort [3 installation Procedure CComponent index FCEquipment Spec. Cl Maintenance Procedure 0 ASME Coded item C3Const. Spec. C Engineering Procedure C3 Human Factor Consideration MOrocuremner- Soiec. Operating Instruction C Computer SoftwareCVendor Information C Operating Procedure 0 Eiectric Circuit ScheduleCOM Manual 0 Operational Safety Requirement C CRS Procedure C3FSARiSAR C IEFD Drawing CProcess Control Manual/Plan CSafety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0.Radiation Work Permit C Essential Material Specification C3 Purchase Requisition EDEnvironmental impact Statement C Fac. Proc. Samp. Schedule EC CEnvironmental Report C inspection Plan C3 C:Environrrental 0ermit C Inventory Adjustment Request C C

'.9. otther atfected Documents: (NOTE: Documents listed below will not be revised by tnis ECN.) Signatures below indicate that the signingorganization has been notified of other affected documents listed below.

Document Number/Revision Document Number/Revision Document Number/Revision

20. SoprovaisSignature Date Signature Date

OPERATIONS AND ENGINEERING ARCH ITECT-E NGINEER

Coo. Prolect Engineer AF Crane PE____________________ ______

Cog..;P-oect Enigr. Migr DL r! YC!kL J,, Lzg QA____________________ ______

C AP e 1tli -1r I ' / Safety_______ ______ ____

Saf ety I-N I s I ari. Rr9.,,f 1;. ? r^ 3 / , Design _________________________

Security ___________________________ Other ____________________

P-o;.Prog..Dept.,Mgr. DATre?75 - -

Def. React. Div.

Chem. Proc. Div R____________________

Def Wst. Mgmt. Div._________________ DEPARTMENT 9FENERGY

Adv. React. Dev Div.______t'~ .

Proj.Dept.J r9Joble I % iEnviron. Div. JJ Doia2 ADDITIONAL

iRM Dept.______________________ ___________________

Facility Reo. (Ops)-t-Bl+ u.Ji7 AJJ4 /iI4_________________________________

other C14 Dunbar -,zl~

John son-6_______

A-7900-013R (11/8M

Page 3: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC -SD-CO18H-FDC-0O1, Rev. 2 ECN 119532 Page 3.j.. of 5

Description of Change:

Modify the Functional Design Criteria (FDC) for Project C-018H as follows:

ChangeNo. Section Chang~e/Justification (5/16/91)

1) Exec. CHANGE - Remove reference to PUREX for Interim Retention Basins.Sum. JUSTIFICATION - PUREX will not be operational until after Project

C-018H is on line. At that time, PUREX effluent PDD/AD willdirectly feed the C-018H treatment facility.

2) 1.1 CHANGE - Remove reference to PUREX for Interim Retention Basins(Project W-105) and scheduled operating periods.JUSTIFICATION - See Change No. 1. Also, scheduling is not afunctional requi rement.

3) 1.3 CHANGE - Remove reference to scheduled start-up.JUSTIFICATION - Scheduling is not a functional requirement.

4) 1.3 CHANGE - Remove reference to PUREX for Interim Retention Basins,modify basin capacity available, and remove reference to scheduledstart-up.JUSTIFICATION - See Change No. 1, the PUREX PDD/ASD effluentstreams are eliminated, thus the number of interim retentionbasins are reduced by one, and see Change No. 3.

5) 2.0 CHANGE - Remove reference to PUREX and scheduled operatingperiods. Add redundancy, surge tank capacity and recyclecapability to maintain TOE required.JUSTIFICATION - See Change No.'s 1 and 3. The facility designmust have the flexibility to include redundancy, surge tankcapacity and recycle capability to meet the overall TOE systemrequirement. Specifying redundancy, surge capacity, and recyclecapacity is too restrictive. The functional requirement is forthe design to meet the overall treatment system TOE.

6) 2.1 CHANGE - Modify reference list for Appendix D basis.JUSTIFICATION - The reference list reflects the latest guidancefrom Ecology. Changes to the list do not affect the functionalrequirements of the proposed treatment system. KEH and Ebascoevaluated changes and concurred that the process functionalrequirements are not impacted. The KEH and Ebasco evaluations areattached to Change Request HEC-CCB-151.

Page 4: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C018H-FDC-0Oi, Rev. 2 ECN 119532 Page 4 of 5

7) 2.6 CHANGE - Increase retention capacity period to 7.2 hours.JUSTIFICATION - 100% verification will be required to meetDelisting petition conditions. EPA-HQ meeting minutes datedNovember 1, 1990, "When the Hanford Site can prove that thetreatment system is able to treat a worst case feed, there may bea reduction in verification testing.", are attached to ChangeRequest HEC-CCB-151. The 72 hour period assumes that sufficienton-site analytical resources will be available. The cost impactfor increasing from 24 hour (648 Kg) to 72 hour (1,944 Kg)verification capacity is $1,400K (see estimate attached to ChangeRequest HEC-CCB-151).

8) 2.7 CHANGE - Modify operating staff reference.JUSTIFICATION - Changes to the number of operating staff reflect acorrection to Appendix F wherein addition errors were made.

9) 2.8 CHANGE - Call out independent operational capability for each unitprocess, HVAC control through the MCS and process equipmentcontrol through the MCS.JUSTIFICATION - "Independent operational capability" facilitatestrouble shooting, maintenance, and personnel safety. HVAC andprocess equipment control through the MCS is required for a self-functioning system. No cost impact to centralize controlfuncti onal requirements.

10) 3.2 CHANGE -,Remove reference to PUREX for Intirim.Retention Basins.JUSTIFICATION - See Change No. 1.

11) 3.10 CHANGE - Delete specific 4.5 feet instrumentation height call-out.JUSTIFICATION - The human factors analysis will dictate instrumentlayouts.

12) App. B CHANGE - Delete reference to single treatment train, permittingcomplication, and operating schedule.JUSTIFICATION - A value engineering exercise concluded that thestreams to be treated could be mixed within a single process trainand staging tank without further complicating the overallpermitting process and see Change No. 3. The CDR estimateincorporated this single process train.

13) Fig. B-i CHANGE - Modify diagram to single process train.JUSTIFICATION - See Change No. 12.

14) B-i CHANGE - Modify staging tank requirement wording to "shallconsider" and delete second bullet requiring staging of feed fromPUREX and 242-A without mixing.JUSTIFICATION - See Change No.'s 1 and 12. Also, the PUREXfacility will provide piping and staging capacity to the ETF,prior to PUREX becoming operational and sending effluent to theETF.

15) B-2 CHANGE - Delete redundancy requirement.

Page 5: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1, Rev. 2 ECN 119532 Page 5... of 5

JUSTIFICATION - See Change No. 5.

16) B-3 CHANGE - Delete 100% organic destruction & redundancy call-outs.JUSTIFICATION - The 100% destruction requirement was deleted to beconsistent with organic removal treatment targets cited inAppendix D. No cost impact results from this change. Also, seeChange No. 5.

17) B-4 CHANGE -Delete redundancy call-out.JUSTIFICATION - See Change No. 5.

18) B-5 CHANGE - Delete redundancy call-out.JUSTIFICATION - See Change No. 5.

19) B-6 CHANGE.- Delete redundancy call-out.JUSTIFICATION - See Change No. 5.

20) B-7 CHANGE - Delete redundancy call-out.JUSTIFICATION - See Change No. 5.

21) 8-8 CHANGE - Change retention requirement to 72 hours.JUSTIFICATION - See Change No. 7.

22) B-8 CHANGE - Ch 'ange retention requirement to 72 hours.JUSTIFICATION - See Change No. 7.

23) Tbl C-i CHANGE - Modify characterization table.JUSTIFICATION - Revised to be consistent with the stream specificreports.

24) App. D CHANGE - Incorporate NPDES (Appendix E) option.JUSTIFICATION - Appendix D now incorporates one set of treatmenttargets that allows either soil column or N.PDES river discharge.The Project cost estimates are based on soil column discharge. Aseparate alternate cost for a river discharge option will also beincluded.

25) Tbl D-1 CHANGE - Modify treatment target table.JUSTIFICATION - See Change No. 6.

26) App. E CHANGE - River discharge criteria incorporated into Appendix D.JUSTIFICATION - See Change No. 24.

27) App. F CHANGE - Redesignated Appendix F to E. Incorporate requirementsfor typical process instrumentation readout and installation.JUSTIFICATION - See Change No. 11.

28) App. G CHANGE - Redesignated Appendix G to F. Delete reference tooperating schedule dates and modify staffing requirements.JUSTIFICATION - See Change No.'s 3 and 8. Redesignated Appendix Gto F.

Page 6: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

5 FORMATION RELEASE REQUEST URI GINALI I.C-4

Purpose New 10 Number

O Speech or Presentation df ReferenceI"Full Paper Q Technical Report Ei'IDNmer (include revision. volume. etc.)

Summary an0on Thesis or Dissertation F.ijUft -S .- ~g eo Abstract suflix) Q Manualo Visual Aid 1Q Brochure/Flier fpreviously cleared, list ID number.

o Speakers Bureau Q Software/Database A nA rt-f-: m n 7-o F-ILe.o Poster Session 0 Controlled Document Date Release Requiredo videotape Q Other ______

Todl Unclassified Category Impacta $.UC- Level3

Title of Journal Group or Society Sponsoring

Date(s) of Conference or Meeting City/State Will proceedings be published? 0 Yes Q NoIIWill material be handed out? Q Yes Q No

Title of Conference or Meeting

P CHECKLIST FOR SIGNATORIES

neview Required per WIIC.CM-3-4 11es No ReviewerDN!me (nrinted) Signature Datet

Classi fica tion/tUnc lassi tied ControlledNuclear Information 0

Patent -General Counsel 0 ~ C*- 1 ~

Legal - General Counsel R& A)IR ;A.b. <C/1,i i..I (/Z ~ .. .4AU 1 IJ/ILqApplied Technology/Export 0Controlled Informationor International Program

WIIC Program 0 ~ __________

Cornmunications 0J ~ ___________ ?ec~ ~~ ~ iDOE-RL Program. 15 0 I~6,~~ ~

Publications Ser vices C0 ~ _____

Other Program 0 I____________References Available to Intended C /4C~ ~ ~ ~ ~ , ____

Transmit to OOE-1 IQ/Office ofScoettf'c and Technical Information 0J ~ ______________

Information conforms to all applicable requirements. The above information is certified to be correct.

AUthoriltequestor (Printed/Signature) Daste INFORMATION RELEASE ADMINISTRATION APPROVAL STAMP

127'~, All""-I 11 ?/f Stamp is required before release. Release is contingent upon r4lution ofmandatory comments.

Responsible Mar(g '(Printed/Signature) Date

intended Audience

C internal 0 Sponsor .,rExternal ___________________

PtD.7600-062 (04190

Part I

Page 7: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

AaV QJSUPPORTING DOCUMENT 1. Total Pages 9?

2. Tile 3. Number 4. Rev. No.Functional Design Criteria for the242A/PUREX Plant Condensate Treatment F-acility WHC-SO-CO18H-FDC-0O1 2

S. Key Words 6. Author

242A/PUREX, Condensate, Treatment Facility, A. F. CraneAmmonia Scrubber Distillate Treatment, 200 Area NamoL yperPnrit

Signeture

Effluent Technology/87170________________________________________________________ Organizatzoniwharge Coe

7. Abstract

This document provides the Functional Design Criteria for Project C-018H. the 242-AEvaporator and the PUREX Plant Condensate Treatment Facility. This project V.-illprovide collection, treatment, and disposal systems for the 242-A Evaporator processcondensate (PC), and the combined PUREX Plant process condensate (P00)/ammoniascrubber distillate (ASD) stream. The treatment and disposal systems containedwithin the scope of the FDC will meet all applicable regulations, including therequirements of the U.S. Environmental ,Protection Agency, the State of WashingtonDepartment of Ecology, and U.S. Department of Energy.

4 ~Z'ZIPROVED FP________8. Pu OISEA USEo 0w sRE EA U d 10.e w L ioL

the .S. armnt of gy a tscontra . It is e ue yu to zd manaerjs Nm TprPitperf irect. orintegrate under U.S. Dep e f Energy c' ~l~ trNac(tse.rPrnThis d ment is not approved; public release until ed.AuoredMnerSgnue

P A T ATUS - This d me opy. since it is itted in a of Aioie aae' intr

p nt c nc. is ma available confidenc ey sinromScfyDtruonLitEenawo i n contra with~ the U. . epart t of Ener Th ocume is

ot to be pub ed r its contents oth s ssominated 0 -Ifor purpo RELEASE STAMPthor than sp i above before pate royal for such re ase or use h

been secured, n request, from the Department o rgy. PatenAttorney, Richian e rations office. Rich la .WA.

DISCLAIMR- This report was prepared as an account of work sponsored by an R L A Eagency af teUnited States Government. Neither the united States Government LMTnor any agency thereof, nor any of their employees, nor any of their contractors. DISTRIBUTION LMTsubcontractors or their employees, makes any warranty, express or implied, orassumes any legal liability or responsibility for the accuracy, completeness. or any N RALO Ythird party's use or the results of such use of any information, apparatus, m N EN LO4product, or process disclosed, or represents that its use would not infringeprivately owned rights. Reference herein to any specific commercial product.process, or service by trade name, trademark, manufacturer, or otherwise, does SPQfONZ 3O LI MITEDnot necessarily constitute or imply its endorsement, recommendation, orfavoring by the United States Government or any agency thereof or itsContractors or subcontractors. The v~iews and opinions of authors expressedherein do not necessarily state or reflect those of the United States Government EXTER NALor any agency thereof.

9. Impact LevelDAE JU O399

3

Page 8: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

(2) Title

Functional Design Criteria for the 242-A Evaporator and the PUREX Plant Condensate

Treatment Facility

CHANGE CONTROL RECORD

(3) eviion (4)D~riti~ ofChage -Ropacii. dd, nd elee PgesAuthorized f or Release(3)Revsio (4 Dscrptin o Chng - eplce.Add ad Dlet Paes (5) Cogl~fog. Engr. (6) CogjProj. Mgr. Date

2 (7) incorporate ECN 119532 changes ~IJ'to REV 1 (Note: No Rev 0 ever A.F. Crane 'Dt7lycktissued)

A-7320-005 (12,189)

Page 9: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WTHC-SD--C018H-FDC-OO 1., REV 2

* Signature Page from Original Document

Document Title: Functional Design Criteria for the 242-A Evaporator and( the PUREX Plant Condensate Treatment Facility

Prepared by: q6 -46 ____

OT yFTkt7Dt R.L. McCornfack, DataManager -EngineerWaste Management PUREX SystemsAdvanced Technology Unit Engineering

Approved by: X 221 Gate 0 DS~I k iii'{ Da1to

Manager ManagerEngineering and Tank FarmsDevelopment QualityAssurance

W..Brooksher, DaeA. Cahill, O~taMaager anager

Safeguards and S curity fefense Waste Projects

R.F. Oaugherty,'"4 Date R.L. *'Fielder, - DateManager ManagerWaste Management Division Waste Management

(Pr *ec nieering

q%% peer -, -2 ngi70-/ peftr, ae G.4 i~kbDate

Manager ManagerEnvironmental Assurance Evaporator Restart

Program

Manager ManagerPUREX Plant PUREX/U03 Operations

Program

W.. iborgA 0.0 W~odrch,' tat'e-Manager ManagerNuclear Safety Waste Management Engineering

DOE-RL Approval*: (n(q(qR E~ tonDate

DirectorWaste Management Division

( *Appendix Material is considered as information, not for approval.

Page 10: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

Page 11: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

EXECUTIVE SUMMARY

This document provides the Functional Design Criteria (FOC) for

Project C-018H, the 242-A Evaporator and the Plutonium-Uranium Extraction

(PUREX) Plant Condensate Treatment Facility. This project will provide

collection, treatment and disposal systems for the 242-A Evaporator process

condensate (PC), and the combined PUREX Plant process condensate (P00)/ammonia

scrubber distillate (ASO) stream. The treatment and disposal systems

contained within the scope of the FDC will meet all applicable regulations,

including the requirements of the U.S. Environmental Protection Agency

(EPA), the State of Washington Department of Ecology (Ecology), and the

U.S. Department of Energy (DOE).

The facilities provided 'by the Liquid Effluent Retention Facility

(Project W-105) and this project are required for the continued operation of

the 242-A Evaporator. The operation of the 242-A Evaporator is vital to

conducting the Hanford Site environmental restoration mission. It will not be

possible to support the Hanford Federal Facility Agreement and Consent Order

(known as the Tni-Party Agreement*) commitments if the evaporator remains in a

standby condition. In addition, this project will enable Hanford to treat

PUREX Plant POD and ASO effluents to further reduce the radionuclide and

chemical constituents in these streams prior to discharge.

*Ecology, EPA, and DOE, 1989, Hanford Federal Facility Agreement andConsent Order, Washington State Department of Ecology, U.S. EnvironmentalProtection Agency, and the U.S. Department of Energy, Olympia, Washington.

-ii i

Page 12: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

These criteria are coordinated with existing another new facilities

under an overall plan to stop discharges of contaminated liquids into the soil

column on the Hanford site. Specific criteria are presented for the

coordination of this project with the 200 Area Treated Effluent Disposal

System and the 242-A Evaporator Liquid Effluent Retention Facility.

iv

Page 13: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

LIST OF TERMS

AKART all known, available, reasonable technologyALARA as low as reasonably achievableAMU aqueous makeup systemASD ammonia scrubber distillateBDAT Best Demonstrated Available TechnologyCASS Computer-Automated Surveillance SystemDCG derived concentration guidelinesDST double-shell storage tankDOE U.S. Department of EnergyDOE-RL U.S. Department of Energy-Richland OfficeEcology State of Washington Department of EcologyEPA U.S. Environmental Protection AgencyERTC Effluent Retention and Treatment FacilityFOC Functional Design CriteriaFSAD/FSAR Final Safety Analyses Document/Final Safety Analyses ReportHEC Hanford Environmental ComplianceHLAN Hanford Local Area NetworkHVAC Heating, Ventilation, and. Air ConditioningLCCS Laboratory Customer Communications SystemLDR Land Disposal RestrictedMCL maximum contaminant levelMCLG maximum contaminant level goalsMCS Monitor and Control SystemNPDES National Pollution Discharge Elimination SystemPC process condensatePOD PUREX Plant process condensatePMCL Primary Maximum Contaminant LevelsPQL practical quantification levelPSAD Preliminary Safety Analyses DocumentPSAR Preliminary Safety Analyses ReportPSE Preliminary Safety EvaluationPSD Prevention of Significant Deterioration (Permit)PIJREX Plutonium-uranium extractionQA quality assuranceQAPP quality assurance program planRD reverse osmosisSER Site Evaluation ReportTEOF Treated Effluent Disposal FacilityTEDS Treated Effluent Disposal SystemTOE total operating efficiencyUV ultraviolet light-mediate(oxidation)Westinghouse Westinghouse Hanford CompanyHanfordWRAP Waste Recovery and Packaging

v

Page 14: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

vi

Page 15: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-CO18H-FDC-OO1 REV 2

TABLE OF CONTENTS

1.0 INTRODUCTION .. .. ........ ........ ....... ... 11.1 Background .. ...... ........ ........ ...... 11.2 Scope .. ... ........ ........ ....... .... 31.3 Project Interfaces .. ....... ....... .......... 4

2.0 FUNCTIONAL REQUIREMENTS. .. ..... ........ .......... 52.1 Treatment Requirements. .... ....... ........ ... 52.2 Disposal Requirements .. ... ........ ....... .... 72.3 Secondary Wastes .. ....... ....... ........... 72.4 Qffgas Treatment .. ....... ....... ........... 82.5 Chemical Storage and Aqueous Makeup System. ... ......... 82.6 Staging and Verification System. .. ...... ....... ... 92.7 Process and Support Services Facilities. .. ...... ...... 102.8 Monitor and Control Systems .. ... ........ ........ 112.9 Utilities .. .... ....... ........ .......... 132.10 Communications .. ........ ....... ......... 132.11 Fire Protection. .. ....... ....... ......... 132.12 Site Improvements. .. ....... ....... ........ 14

3.0 DESIGN PARAMETERS. ... ........ ....... ........ 153.1 Energy Conservation. .. ...... ........ ........ 153.2 Piping Systems. .... ........ ....... ....... 153.3 Shielding .... . ...... ........ .......... 153.4 Maintenance and Operation .. ... ........ .......... 163.5 Natural Forces .. ......... ... ....... ....... 163.6 Design Life .. ... ........ ........ ........ 163.7 System Reliability .. ......................................163.8 Decontamination and Decommissioning. .. ...... ........ 173.9 Materials of Construction .. ... ........ .......... 173.10 Human Factors. .. ....... ........ .......... 173.11 Security and Safeguards .. .... ........ ........ 173.12 Siting. ..... ....... ........ .......... 183.13 Waste Minimization and Hazardous Material Usage. .. ....... 183.14 Drawing Configuration .. .... ........... ........ 18

4.0 QUALITY ASSURANCE REQUIREMENTS .. .. ........ .......... 19

5.0 SAFETY. .. ...... ....... ........ .......... 215.1 Construction Risks.. ........ .. ..... ......... 215.2 Operating Risks .. .... ....... ........ ...... 215.3 Unacceptable Safety Consequences. .... ........ ..... 22

6.0 CODES AND STANDARDS. ... ........ ....... ....... 23

7.0 REFERENCES. .. ...... ....... ........ ....... 25

Vii

Page 16: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-COi8H-FDC-OO1 REV 2

TABLE OF CONTENTS (con't)

APPENDIX A PROPOSED SITE PLAN .. ...... ........ ....... 31

APPENDIX B PROPOSED TREATMENT SYSTEM .. .. ........ ........ 41

APPENDIX C CHARACTERIZATION DATA. .. ..... ........ ...... 51

APPENDIX D TREATMENT TARGETS. .. ..... ........ ........ 57

APPENDIX E PROCESS AND SUPPORT FACILITY DESIGN CONSIDERATIONS .. ..... 79

APPENDIX F PROPOSED STAFFING PLAN .. ...... ....... ...... 85

LIST OF FIGURES

Figure A-i. Effluent Retention and Treatment Complex, Sites A and B ... 33Figure A-2. Three Potential Soil Column Disposal Sites.. ... ...... 35Figure B-i. Proposed Treatment System. ... ....... ........ 43

LIST OF TABLESTable C-i. C-018 Influent Characterization Data .. ...... ...... 54Table D-i. Treatment Targets. .. ...... ....... ........ 54Table F-i. Estimated Staff Requirements .. ...... ........... 86

viii

Page 17: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

1.0 INTRODUCTION

This document provides the Functional Design Criteria (FOC) forProject C-018H, the 242-A Evaporator and Plutonium-Uranium Extraction (PUREX)Plant Condensate Treatment Facility. The project will provide the facilitiesto treat and dispose of the 242-A Evaporator process condensate (PC), thePlutonium-Uranium Extraction (PUREX) Plant process condensate (PDD), and thePUREX Plant ammonia scrubber distillate (ASD).

1.1 Background

For the past 45 years, the Hanford Site has used the favorable sitecharacteristics of isolation, low precipitation, deep-water table, and soilion exchange properties to discharge large amounts of water containing lowlevels of radionuclides and stable chemicals to the soil column. The policyof the U.S. Department of Energy (DOE) requires that the use of soil columnsto treat and retain suspended or dissolved radionucilides from liquid wastestreams be discontinued at the earliest date practicable in favor ofwastewater treatment and minimization. This policy is implemented throughDOE Orders, which are based on federal and state environmental regulations.

In March 1987, the U.S. Department of Energy-Richland Operations Office(DOE-RL) issued a document entitled Plan and Schedule to Discontinue Disposalof Contaminated Liquids into the Soil Column at the Hanford Site (Plan andSchedule) (OOE-RL 1987). The Plan and Schedule, and its annual updates,contain a strategy for implementing alternative, treatment and disposal systemsfor each of the 33 major waste streams discharged to the soil column. In thisstrategy, the wastestreams were prioritized into Phase I and Phase II. Thealternative treatment and disposal systems for Phase I streams have a higherpriority and are scheduled to be completed by June 1995. The Phase II streamsare to be addressed after the completion of the Phase I projects.

Projects to provide alternative treatment and disposal methods for thePhase I streams have been incorporated into the recently signed "Action Planfor Implementation of the Hanford Federal Facility Agreement and ConsentOrder," an attachment to the Hanford Federal Facility Agreement and ConsentOrder (Tni-Party Agreement) (Ecology et al. 1989).

The Plan and Schedule considered the 242-A Evaporator PC and the PUREXPlant POD and ASO streams to be Phase I streams and provided a schedule forthe implementation of alternative treatment and disposal methods. Funding forimplementation of the evaporator system was to be complete by June 1995 andfor the PUREX Plant system by January 1994. Funding for these alternativesystems were to be provided by two Hanford Environmental Compliance (HEC) lineitem sub-projects.

Page 18: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-Sb-CO18H-FDC-001 REV 2

In April 1989, the 242-A Evaporator was placed in temporary standbybecause of a concern that past Hanford Site waste management and chemicalprocessing activities may have generated listed waste as defined by theResource Conservation and Recovery Act (RCRA) (1976). These potentiallylisted wastes are currently stored in double-shell tanks (DST) and areprocessed subsequently through the 242-A Evaporator to reduce the wastevolume. The processing of the waste in the 242-A Evaporator produces aconcentrated waste, which is returned to the DSTs, and a PC stream, which istransferred to a soil column disposal site. If the DSTs contain a listedwaste, the PC is also a listed waste and must be managed in accordance withRCRA. Additionally, the level of ammonia in the 242-A Evaporator PC is highenough to make this discharge a dangerous waste according to WAC 173-303(Ecology 1989) criteria.

An investigation of past PUREX Plant waste generation practicessuggested a potential for a small amount of listed waste to enter thePUREX Plant PDD, thus potentially making past discharges listed wastes andprecluding future discharges to the existing disposal site. These practiceshave been discontinued, and future PDD is not expected to contain listedwaste. However, because of these potentially listed waste discharges to theexisting disposal site, the PUREX Plant cannot operate until an alternativestorage or disposal site is available.

The facilities provided by the Liquid Effluent Retention Facility(Project W-105) and this project are required for the continued operation ofthe 242-A Evaporator. The operation of the 242-A Evaporator is vital toconducting the Hanford Site environmental restoration mission. It will not bepossible to support the Hanford Federal Facility Agreement and Consent Order(known as the Tni-Party Agreement*) commitments if the evaporator remains in astandby condition. In addition, this project will enable Hanford to treatPUREX Plant PDD and ASD effluents to further reduce the radionuclide andchemical constituents in these streams prior to discharge.

An engineering study has been prepared that contains descriptions ofcurrent plans to provide alternative treatment and disposal systems for the242-A Evaporator PC and the PUREX Plant PDD and ASD streams. The engineeringstudy considered methods to accelerate the implementation schedules for thecurrently planned systems as well as interim systems that would replace oroperate until the currently planned systems are operational (Flyckt andMcCormack 1989).

The engineering study recommended the construction of an interim systemthat would replace the currently planned systems. The preferred system wouldinclude a facility where the 242-A Evaporator PC stream would be stored untiltreatment and disposal systems could be brought online. The Liquid EffluentRetention Basins (Project W-105) is being implemented to provide storage forthis stream.

2

Page 19: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-0O1 REV 2

The project described in this FDC will provide the recommended treatmentand disposal systems for the 242-A Evaporator PC and the combined PUREX PlantPDD/ASD stream. The project systems are scheduled to be operational afterProject W-105 is operational.

1.2 Scope

This project will provide collection, treatment, and disposal systemsfor the combined PUREX Plant POD/ASD stream, and the 242-A Evaporator PC. Thetreatment and disposal systems contained within the scope of this FDC areanticipated to meet all applicable regulations, including the requirements ofthe U.S. Environmental Protection Agency (EPA), the State of WashingtonDepartment of Ecology (Ecology), and the DOE.

Included within the scope of this project are the following systems andfacil ities:

o The PC, PDD, and ASO treatment systems;0 Treated effluent disposal systems;o Secondary waste pretreatment and packaging systems;0 Offgas treatment systems;o Chemical storage and aqueous makeup (AMU) system;o Feed and treated effluent staging and verification tanks;0 Process and support services facilities; ando Monitoring and control systems.

The project will include the necessary utilities, communications, fireprotection and other safety-related items or features to make the projectoperational. In addition, these utilities will be designed to allow thefuture integration of the 200 Area Treated Effluent Disposal System (TEDS).Site improvements will be provided by the project where necessary toconstruct, maintain, or operate the treatment and disposal systems.

Excluded from the scope of this project is the treatment and disposal ofsecondary wastes. Treatment and disposal of these secondary wastes will occurin existing or planned Hanford Site facilities. The use of DSTs for thestorage of secondary wastes will not be considered in the design of theproject.

The preferred site for the treatment systems provided by this project isthe northeast corner of the 200 East Area. Because of the impact of futurenegotiations with the appropriate regulatory entities, it is not possible toidentify a single location for the disposal systems provided by this project.The exact location will be determined during definitive design. Appendix Acontains an illustration of the proposed treatment system site and threepotential disposal system sites.

3

Page 20: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

1.3 Project Interfaces

The operation of the 242-A Evaporator is vital to the Hanford Siteenvironmental restoration program and key to the Hanford site Waste ManagementProgram. These programs will be significantly impacted if the project C-018Hfacilities are not operational. In addition, this project will enable Hanfordto treat two PUREX plant effluents and support the implementation of theoverall plan to stop discharges of contaminated liquids into the soil column.

Design and construction of the Project C-018H systems and facilitieswill be coordinated with the 200 Area TEDS and the Liquid Effluent RetentionFacility.

The Liquid Effluent Retention Facility will provide interim storagebasins for the 242-A Evaporator PC. The project will provide two basins forthe 242-A Evaporator stream and a third basin for back-up capacity in theevent of a primary basin failure. Included in the project are two 6.5-Mgalbasins for the 242-A Evaporator PC and third 6.5-Mgal back-up basin. Thetotal storage capacity in the interim storage basins is 19.5 Mgal. The basinswill store the PC until the inventory is treated and disposed of by thefacilities provided by Project C-018H. Regulatory agreements require that theLiquid Effluent Retention Facility be emptied of Land Disposal Restricted(LOR) wastes and residues by December 1994.

The 200 Area TEDS will provide the collection piping, standby treatment,and disposal systems for 13 effluent streams in the 200 Area. The projectwill interface and, if necessary, increase the treatment capacities providedby Pro ject C-018H. The 200 Area TEDS project is scheduled to be operationalby June 1995.

The design of Project C-018H will be coordinated with the 200 Area TEDSproject. However, these measures will not compromise start-up of ProjectC-018H systems. To reduce overall life cycle costs, the design of these threerelated projects will consider the following measures:

0 Utilize common utilities and operations support where practicable.

0 Provide a design for the process building that can be expanded.The design of the process building may include a temporary,nonload-bearing wall that can be easily removed for expansion.

0 Provide the ability to expand the utilities (e.g., electricalpower, raw and sanitary water, compressed air and sanitary sewer).

0 Provide the ability to expand facilities to handle the incrementalstaffing levels and workloads of the 200 Area TEDS project.

0 Provide capability in the design of the monitoring and controlsystems to allow expansion to incorporate the process controlrequirements of the 200 Area TEDS project.

4

Page 21: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

2.0 FUNCTIONAL REQUIREMENTS

The facilities provided by this project shall use commercially availableequipment and technologies wherever practicable. The design should be basedon treatment technologies currently used by commercial industries for treatingindustrial or process water.

The treatment system will be capable of treating a continuous flow of150 gal/minute. The design should utilize modular units wherever practicable.Appendix B contains a description of a proposed treatment system.

During the first two years of operation, the treatment systems willoperate 7 day/week, 24 hour/day. This operating schedule is needed to treatthe contents of the Liquid Effluent Retention Facility (13 Mgal) while jointlytreating freshly generated 242-A Evaporator PC, PUREX POD, and PUREX ASD. Areduced operating schedule is expected after the contents of the LiquidEffluent Retention Facility have been treated. The design will support atotal operating efficiency (TOE) of 72% during the initial two years oftreatment system operation. The process design shall provide sufficientequipment redundancy, unit process surge tank capacity and unit processrecycle capability to meet and maintain TOE requirements.

2.1 Treatment Requirements

A summary of the characterization data for these effluents is presentedin Appendix C. Additional characterization data are available in WHC-EP-0287,Waste Stream Characterization Report (WHC 1989). The design of the treatmentsystem will assume that chemical additions have been made to the wastes storedin the Liquid Effluent Retention Facility (e.g., algicide) and that the ion-exchange system currently used in the 242-A Evaporator has been bypassed. Thecharacterization data presented in Appendix C have been modified to accountfor the elimination of the 242-A Evaporator ion-exchange system. Thecharacterization data indicate the following:

o The streams are low-level wastes as defined in DOE Order5820.2A (DOE 1988b);

o The 242-A Evaporator PC contains concentrations of ammonia thatare sufficient to be a dangerous waste;

o The PUREX Plant streams are not dangerous waste; and

o The 242-A Evaporator PC is a listed dangerous waste.

The treatment system will be capable of meeting release limits containedin Washington State's Waste Discharge Permit Program, WAC 173-216(Ecology 1986). Washington State policy requires the application of allknown, available, and reasonable technology (AKART) to prevent and control the

5

Page 22: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-0O1 REV 2

discharge of wastes into the waterways throughout the state. During thepermitting process, the appropriate treatment system design will be determinedby the AKART process. The AKART methodology will include a review oftreatment system technologies. Releases from the treatment system will alsobe consistent with as low as reasonably achievable (ALARA) practices containedin DOE Order 6430.1A, WHC-CM-4-9, (WHC 1988c), WHC-CM-4-11 (WHC 1988e), andwith the Best Available Technology (BAT) requirements of DOE Order 5400.5.

The WAC 173-216 permit conditions will be negotiated during the designof the project. Until these criteria are available, the design of the projectwill use the target levels presented in Appendix D. The treatment target forthe radionuclide constituents (excluding tritium) is 0.04 of the derivedconcentration guides.

The treatment targets presented in Appendix D are intended to guide thedesign of the 242-A Evaporator and PUREX Plant Condensate Treatment System andare expected to be conservative (low) estimates of the release limits thatwill be contained in a WAC 173-216, state Waste Discharge Permit Program. Thetargets are not intended to be an indication of the level of treatment that ispossible with the facilities provided by this project. The treatment targetsare not intended to be an indication of the level of treatment that ispossible with the facilities provided by this project. It is possible thatthe BAT selection process of DOE Order 5400.5 or the State of Washington'sAKART process may determine that some of the treatment targets are notachievable.

The treatment targets presented in Appendix D result from an assessmentof (1) the State of Washington's proposed groundwater standards and (2) thebest demonstrated available technology (BDAT) treatment requirements of theRCRA. The treatment targets presented in Appendix D are based on thefollowing:

0 Safe Drinking Water Act3 Primary Maximum Contaminant Levels(PMCL), Secondary Maximum Contaminant Level (SMCL), MaximumContaminant Level Goals (MCLG)

0 Ground water quality criteria as stipulated by WAC 173-200

0 Land disposal restrictions, 40 CFR 268.41 and 40 CFR 268.43

0 One tenth of the purgewater collection criteria values asstipulated in Table 1, "Strategy for Handling and Disposing ofPurgewater at the Hanford Site," (90-ERB-076)

0 Health based limit, as stated in Docket Report on Health-BasedLevels and Solubilities Used in the Evaluation of DelistingPetitions Submitted Under 40 CFR 260.00 and 260.22, written byScience Applications International Corporation, prepared under EPAcontract No. 68-W9-0091 for the EPA, Washington, D.C. (November1989) or the practical quantification limit as listed in 40 CFR264, Appendix IX, whichever is greater.

6

Page 23: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

Not all of the contaminants listed in Appendix 0, Tabl e 0-1, have beenidentified or are anticipated to be in the 242-A Evaporator PC or thePUREX Plant POO and ASD streams.

2.2 Disposal Requirements

The project will provide a design for a state-approved land disposalstructure. The disposal site will be approved by the DOE and the State ofWashington and permitted under WAC 173-216. Should this type of disposalsystem become unacceptable because of technical or permitting system issues,it will become necessary to pursue a river discharge option. Criteria forthis option are presented in Appendix E.

The state-approved land disposal structure will consist of anunderground drain field, liquid-level gauge wells, vent risers with filters,dry wells, and groundwater wells. The design percolation rate will beestablished by site testing and/or evaluation of disposal site soilcharacteristics. The design of the disposal system will, at a minimum,provide the following features:

0 A stabilized finished grade to prevent water ponding

0 Measures to prevent backfill material from silting the voidvol ume

a Security fences according to plant standards

o Transfer piping and pumping stations to effect transfersfrom the treatment system to the disposal site; secondarycontainment systems are not required on the transfer piping

o Redundant composite samplers (designed in compliance with RCRAStandards) on the disposal transfer line

o Stabilization-of all disturbed areas

o Environmental monitoring systems/stations

2.3 Secondary Wastes

Minimization of secondary waste generation will be an objective duringselection of the treatment process. Treatment processes that destroyhazardous materials will be given preference over processes that stabilize orconcentrate those materials for storage.

7

Page 24: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

Design of secondary waste systems will enable storage and disposal ofthese wastes using existing or planned Hanford Site facilities. All secondarywaste forms will be solids with no freestanding liquids. The project willprovide capabilities to treat and package secondary wastes to the extentnecessary to comply with packaging, shipping and storage, and disposalrequirements of the various onsite waste disposal facilities.

The project will provide less than 90-day storage capacity for dangeroussecondary wastes generated in the treatment process. The design of thetreatment system will not consider the use of DSTs for the storage of anysecondary wastes. Life-cycle costs will be considered during design of thesecondary waste systems.

2.4 Offgas Treatment

Offgas treatment, sampling, and monitoring will be commensurate withClean Air Act permit requirements, state and local regulations, andWestinghouse Hanford Company (Westinghouse Hanford) policy as defined in theEnvironmental Complilance Manual, WHC-CM-7-5 (WHC 1988b). The following willdefine permit requirements:

o National Emission Standards for Hazardous Airborne Pollutants(NESHAPS) requirements per 40 CFR 61 (EPA 1988)

o Prevention of Significant Deterioration (PSD) permitper 40 CFR 52

o Requirements generated under the State of WashingtonDepartment of Health per WAC 402-80 and the AirPollution Control Authority of Benton, Franklin, andWalla Walla Counties

2.5 Chemical Storage and Aqueous Makeup System

Chemical load-in, makeup, distribution, and storage capabilities will beprovided as necessary to support Project C-018H. The chemical storage and AMUsystem design will be sufficient to maintain continuous operation of thetreatment system secondary waste packaging and offgas control systems.Storage capacity will be based on optimal life-cycle cost.

The chemical storage and AMU system shall include the followingcomponents:

0 Chemical storage and aqueous makeup tanks

o Equipment and piping to transfer solution from tank trucks to

storage tanks and vice versa

8

Page 25: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

0 Systems to provide sufficient heating of tank truck, tank, andprocess transfer line solutions to preclude solids formation

0 Chemical addition systems, including dry chemical storagecapabilities where necessary

0 Water addition, tank flush, and dilution capabilities

o Tank ventilation systems for personnel protection, environmentalregulatory compliance, and tank pressure control

0 Instrumentation and alarms as specified in Section 2.8

0 Storage and makeup tanks sampling and mixing systems

o Hazardous chemical containment system(s) for the tank truck load-in station, chemical storage tanks, and aqueous makeup tanks

o Safety shower(s) and eyewash station(s)

0 Operating platforms and stairways, as required

0 Permanent and/or portable breathing air systems

The hazardous chemical containment system will ensure that releases ofhazardous chemicals to the environment are controlled in accordance with DOEOrder 6430.1A (DOE 1989a) and Washington (State) Administrative Codes. Designwill minimize containment system volumes and will provide the capability totransfer solutions from the containment area to chemical storage tanks,treatment feed tanks, or temporary storage (i.e., drums or tank truck).

2.6 Staging and Verification System

Storage capacity will be provided for staging feed to the process andfor verifying the effectiveness of treatment. Feed tanks and verificationtanks will comply with WAC 173-303-640 requirements (Ecology 1989). A minimumof one feed tank and three verification tanks will be provided. A samplingsystem will be provided on both the staging and verification tanks. Theverification tanks sampling system will meet RCRA sampling criteria. Analysisof the samples will occur in a non-project facility.

The verification tanks will be used to periodically verify the qualityof the treated effluent whenever one of the following conditions exist:

0 A change in feed to the 242-A Evaporator

0 A change in the treatment system configuration

0 Start-up of the treatment system

9

Page 26: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

Tank storage capacity requirements will be based on a life-cycle costanalysis of tank capacity instead of utilizing sampling-frequency sampleprocessing cost and sample analyses turnaround time. Tank capacity shall besufficient to enable the following:

0 Recycling of the verification tank contents withoutrequiring the shutdown of the PUREX Plant or the 242-AEvaporator;

0 A minimum of 72 hours capacity for sampling and certifiedlaboratory analysis prior to discharge without requiring atreatment system shutdown.

To meet these tank storage capacity requirements, continued use ofthe Project W-105 Liquid Effluent Retention Facility after start-up of thetreatment facility should not be considered for the 242-A Evaporator PCstream. The staging and verification tank systems will include the followingfeatures:

0 Tank flush capabilities and clean out systems

0 Sufficient heating of tanks and transfer lines toprevent freezing of solutions

0 Instrumentation and alarms as specified in Section 2.8

0 Secondary containment systems to prevent releases to theenvi ronment

0 Capability to transfer solutions from the secondary containmentsystems to the treatment process or to temporary storage

2.7 Process and Support Services Facilities

Facilities will be provided to house process equipment and supportservices. Process equipment must be located inside the facility whenevernecessary to protect personnel and the environment. The design of process andsupport services facilities will be based on the requirements of the equipmentand personnel necessary to safely operate and maintain the facility.

Appendix E contains a listing of design features that should beconsidered in the facility. The project will be designed to be operated withan operating staff of less than 81, the proposed staffing levels presented inAppendix F. A design goal shall be to minimize the staff required to operatethe project.

10

Page 27: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-.OO1 REV 2

2.8 Monitor and Control Systems

The project will provide instrumentation to control and monitor theprocess during normal, upset, and accident conditions. Adequateinstrumentation will monitor for hazardous and radioactive materials to ensureenvironmental and personnel safety. Instrumentation will be provided so that,during routine operation, the process will be self-functioning and load-in,makeup, and secondary waste removal activities are not considered routineoperations;- therefore, local operator control for these systems will besufficient. The Monitor and Control System (MCS) shall provide forindependent central and remote control of each unit process including startup,shutdown and optimization.

The MCS will consist of high resolution, state-of-the-art color monitors;dedicated keyboards; and printers, along with data storage and retrievalcapability. The MCS logic development will be based on a Westinghouse Hanfordapproval system. The operation of the MCS will not require any specialknowledge of computer programming or operating systems.

The MCS will be located in a clean area and will provide the followingfunctions:

0 Tank status (staging, verification, and AMU)

0 The HVAC system status and control

0 Conductivity, pH, total beta, and total organic carbon levelof the feed and treated effluent

0 Process equipment status & control

0 Building radiation-monitoring status

0 Leak-detection alarming for secondary containment systems

0 Capability to input laboratory data into database

0 Short-term trending of key parameters

0 Graphics, trend, group, overview, and loop displays along withalarm summaries

0 Capability to provide output to the Hanford Site local areanetwork (HLAN)

0 Pressure and temperature alarms and controls to maintain processsystem safety

Page 28: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-COI8H-FDC-OO1 REV 2

o Position and indication on all actuated valves and on any manualvalves that are critical to providing routing or processinformation (Separate on-off confirms, indication of allpositions of multi-way valves, and 0-100% position indication formodulated valves)

0 Misrouting protection on AMU and on process lines

o On-off confirms for all motor starters, contactors, etc.

0 Current indication for rotating equipment and other applicableequipment

0 Process vessels continuous-level indication and discretehigh-high alarms (where practical, discrete low-low alarmsif a low level would be detrimental to the process orequipment)

The MCS will have the capability to be expanded to include:

0 The requirements of Project W-049H

0 Throughput and material balances

0 Long-term tending for key parameters (e.g., alarms)

Local instruments will be provided for normal operations, trouble-shooting, maintenance, and personnel safety. Local instruments will belocated in a noncorrosive environment, where practicable, or be rated forcorrosive service. At a minimum, the following local instrumentation andalarms will be provided:

o Indication and high-level alarm for staging tanks, verificationtanks, chemical storage, and AMU tanks liqu id levels

0 Indication of critical flows, pH conductivity, totalbeta and total organic level of feed and treatedeffl uent

0 Failure alarms for individual system unit operations

0 High radiation alarms and air monitoring systems necessary forpersonnel safety

Instrumentation, control wiring, signal wiring, etc., installed inprocess area will be water resistant to allow for washdown anddecontamination.

12

Page 29: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-COI8H-FDC-0O1 REV 2

2.9 Utilities

The project will utilize existing water and electrical supplies. Waterand/or steam service required for process applications will be protected frompotential backflows and contamination from the process system. The utilityservices will be designed with spare capacity based on projected requirementsof the 200 Area TEDS project.

The project will provide the required air delivery systems for processand ancillary services. Oil-less air compressors, air dryers and dewpointmonitoring will be provided for the instrument air supply, if instrument airis required.

When required to ensure compliance with existing environmentalregulations and for personnel safety, backup power will be provided. Anun-interruptible power supply will be provided where essential to safeoperations or where continuity of operations or loss of power could requireexcessive effort for recovery and restart.

2.10 Communications

Telephones will be installed in the occupied work areas to permitcommunications within the new facilities and with other area facilities.The number of telephones installed will be determined in the definitivedesign. A private, automatic exchange system will enable supervision,operation, and maintenance communication throughout the administrative andtreatment facilities. Crash alarm phones, evacuation sirens, and othersafety-related communications will be provided in accordance with safetystandards.

A radio base station will be set up in the control room. Provisionsfor future connections to the Computer-Automated Surveillance System (CASS),the HLAN, and a data link to the laboratories via a Laboratory CustomerCommunications System (LCCS) terminal will be provided. No additional voicecommunication equipment is anticipated.

2.11 Fire Protection

Fire protection will be provided as required by DOE Order 6430.1A andDOE-RL Order 5480.7A (DOE 1989a, DOE-RL 1988a). The fire alarm system willbe connected to the Hanford Radio Fire Alarm System. Fire extinguishers willbe installed.

13

Page 30: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-CO18H-FDC-001 REV 2

2.12 Site Improvements

Road access to the process and support services facilities will beprovided. Specifically, road access must be included for chemical load-in,waste removal, supply delivery, maintenance, and equipment replacement.A parking area will be provided for support personnel. The 200 East Areaperimeter fence will be extended to include the project facilities inside200 East Area before operation. Parking areas will be provided. The fenceexpansion will comply with plant standards and include perimeter fencelighting.

New roads or extensions will be designed for economical maintenance andupkeep based on their expected service and use. Existing streets and roadsdisturbed by the installation of the project will be restored to originalcondition. Existing roads will be used to the maximum extent practical.

14

Page 31: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

3.0 DESIGN PARAMETERS

The facilities and systems provided by this project must meet DOEOrder 6430.1A, 0275 ("Industrial Waste Facility") 1323 ("Radioactive WasteFacility"); and WHC-CM-4-9, Radiological Design (WHC 1988c) requirements. Theproject will also comply with the executive directives identified within DOE5440.1C (DOE 1985a), the DOE Order 5480 series, DOE Order 5820.2A (DOE 1988b),DOE Order 6430.1A, DOE Order 5400.1 (DOE 1988c), and DOE Order 5480.5(DOE 1986).

3.1 Energy Conservation

The facilities provided by the project will comply with the energyconservation requirements as defined in DOE Order 6430.1A, 110-12.

3.2 Piping Systems

A piping system will be installed to transport the 242-A EvaporatorPC, PUREX POD, PUREX ASC, and the contents of the Liquid Effluent RetentionFacility to the proposed project site (adjacent to the northeast corner of the200 East Area). The piping system will have the ability to bypass the LiquidEffluent Retention Facility and go directly to the project feed tank. Apiping system will also be installed to transfer the treated effluent to asoil column disposal site.

Piping will comply with RCRA secondary containment and interstitial leakdetection requirements where applicable. All piping will be designed to drainwith minimal line holdup and have the capability to locate and repair transferpipe failures within 1 wk. Gravity flow systems will be used wheneverpracticable. Freeze protection will be provided wherever necessary for pipingsystem protection by adequately burying the pipe underground.

Access to outdoor pipelines will be adjacent to the pipeline right ofway to facilitate surveillance and repair. Graded and graveled roadways willbe provided for right-of-way access. The piping systems will be designed soas not to interrupt the operation of the 242-A Evaporator and the PUREX Plant,unless specifically approved by Westinghouse Hanford.

3.3 Shielding

Personnel radiation exposure will not exceed 1 rem/yr (maximum) to theindividual based on predicted exposure time in normally occupied areas. Therisks of personnel radiation exposure will be minimized through appropriateshielding methods. The amount of shielding will be determined by analysisand will comply with ALARA principles in DOE Order 6430.1A; WHC-CM-4-9,Radiological Design (WHC 1988c); WHC-CM-4-1O, Radiation Protection(WHC 1988f); and WHC-CM-4-11, Alara Program Manual (WHC 1988g). The use oflead for shielding will be minimized.

15

Page 32: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

-3.4 Maintenance and Operation

The project will provide the documentation as well as the initialcomplement of equipment and services required to initiate operation of thefacility. This shall include, but not be limited to, operating andmaintenance procedures, office equipment and furniture, off-road vehicles forpiping surveillance, equipment identification tags, and necessary computersoftware for operations and maintenance activities.

Ease of maintenance will be a design goal. Access will be provided toany component so that it can be replaced or repaired in place with minimalrelocation or removal of other components. Those major components identifiedas requiring frequent maintenance will not be removed or relocated for repairor replacement. In accordance with ALARA guidelines, design of equipment andcomponents will minimize exposure to maintenance personnel.

3.5 Natural Forces

The facility will comply with the earthquake, tornado, snow, volcanicash and wind criteria defined in Hanford Plant Design Standard SDC-4.1,Rev. 11 (DOE-RL 1989e). Roof loads are to comply with SDC 4.1 designrequirements.

3.6 Design Life

The design life for the nonmechanical equipment portion(e.g., structures, tanks, piping) of the facility will be 30 years. Ease ofreplacement will be considered for equipment and systems when a 30-year lifeis not practical.

3.7 System Reliability

The degree of reliability achieved by design will permit the facility tofunction throughout the intended, useful life without creating downtime longerthan 1 wk, assuming critical spare equipment is available. Downtime caused bynormal process operations or equipment failures will not exceed 1 d by design.The facility and processes facilitate easy and cost-effective upgradesnecessitated by regulatory and treatment technology uncertainties.

16

Page 33: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

3.8 Decontamination and Deconmmissioning

Design will incorporate ease of decontamination and decommissioning ofall project systems in accordance with DOE Order 6430.1A and other referencedstandards. Design will minimize the buildup of residual contamination otherthan in the intended process equipment. Systems will be designed for ease ofremoval and disposal at the end of the useful life of the facility. Designwill minimize practices (such as socket weld fittings) that promote buildup ofcontamination in piping or equipment.

3.9 Materials of Construction

All equipment will be constructed of materials selected forcompatibility with the process solutions or fumes to which the equipment isexposed. Special protective coatings will be provided where needed and willcomply with DOE Order 6430.1A, 0900-99. Construction materials will benoncombustible, to the extent practical, and will be selected to minimizeradiation buildup wherever practicable.

3.10 Human Factors

Design will consider human factors for maintenance and operationsactivities, including equipment, valve location and orientation, secondarywaste handling, and building layout. To the extent practical, design willfollow the guidelines and standards of DOE Order 6430.lA,.13OO-12, andWHC-CM-4-9, Radiological Manual (WHC 1988c):

0 Rapid, safe, economical operations and maintenance

0 Anthropometric design for male and female personnel

0 Minimal distraction, discomfort, stress, and fatigue duringoperations and maintenance

The process systems will accommodate physical limitations such ashearing impairment and color blindness,

3.11 Security and Safeguards

The project will be located within the 200 East Area. Design andconstruction activities will comply with requirements of DOE Order 6430.1A,company security procedures, and an approved security plan.

17

Page 34: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

If the facility is constructed outside of the 200 East Area then uponcompletion of construction the perimeter fence will be moved to establish thefacility inside the 200 East Area. Relocation of the 200 East Area perimeterfence and other security-related systems (such as lighting) will be consistentwith initial installation requirements. The facility will not containaccountable quantities of special nuclear material and will include featuresto comply with RCRA security requirements.

3.12 Siting

The treatment system may be sited adjacent to the Project W-105 storagefacility. The soil column disposal site will be in a section of land setaside by a site evaluation report. The proposed locations for thesefacilities are presented in Appendix A. The exact location of the site willbe determined during definitive design.

3.13 Waste Minimization and Hazardous Material Usage

The project design will minimize hazardous and nonhazardous wastegeneration and the use of hazardous materials during construction, operation,and closure. Where materials are used that are hazardous or that will bedesigned as hazardous wastes, a note will be added to the definitive designmedia to identify the material as hazardous wastes. Where lead or similarhazardous materials must be used for shielding or other purposes, the itemwill be encapsulated to prevent radioactive contamination and allow retrieval-in an uncontaminated condition. The item will be permanently marked as tocontents.

3.14 Drawing Configuration

Existing facility drawings directly affected by the project will be as-built by the project. To the greatest extent practical, affected drawingsshould be changed by direct drawing change and used by the project.Fabrication drawings for components that may requirefuture fabrication forreplacement and maintenance will be drawn to Westinghouse Hanford shopstandards.

18

Page 35: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-O01 REV 2

4.0 QUALITY ASSURANCE REQUIREMENTS

Quality assurance (QA) activities for all contractors involved in thedesign, construction, and testing of the proposed facility will be formulatedand executed through the use of a project-specific quality assurance programplan (QAPP). The QAPP shall establish quality assurance program requirements,used to formulate verification, inspection, and testing activities on specialprojects. The quality assurance program requirements will be in accordancewith DOE Order 6430.1A, 0140 "Quality Assurance;" DOE-RL Order 5700.1A,"Quality Assurance (DOE-RL 1983b);" and WHC-CM-4-2, Quality Assurance Manual(WHC, 1989d).

The QA program requirements are based on impact levels and safetyclassifications that are established by management. Safety classification ofsystems, components, and structures will be determined by risk analyses inaccordance with DOE Order 6430.1A, 1300-3. A preliminary list of safety itemswill be included in a preliminary safety evaluation. A preliminary safetyequipment list will be included in a Preliminary Safety Analysis Document(PSAD)/Preliminary Safety Analysis Report (PSAR). A final safety equipmentlist will be included in a Final Safety Analysis Document/Final SafetyAnalysis Report (FSAD/FSAR). All safety classifications will be supported bydocumented analysis.

19

Page 36: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

20

Page 37: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

5.0 SAFETY

5.1 Construction Risks

Risks associated with construction activities are to be considered.In this regard, applicable, referenced DOE Orders and Westinghouse Hanfordmanuals issued for compliance during construction will be considered duringdesign to minimize the risks. A hazards classification-analysis will beperformed for this project. Until this classification is completed, thedesign of the project will be consistent with the criteria for a low hazardnuclear facility. Design will ensure that construction of this project isaccomplished without violating the National Fire Protection Association NFPA101, "Life Safety Code" (NFPA 1988).

5.2 Operating Risks

The facilities provided by this project will provide an environmentallysuitable disposal method for treated industrial or process water. Thesuspended and dissolved materials are of low concentrations. Theconcentration of radionuclides is below the levels requiring secondarycontainment as specified in DOE Order 5820.2A.

The process condensate from the 242-A Evaporator may contain low levelsof source specific dangerous waste. The design and construction of the pipingand treatment systems employed for the 242-A Evaporator PC will comply withthe appropriate RCRA and WAC 173-303 containment and leak detection criteria.

The treatment process will require appropriate design and administrativecontrols to prevent excessive concentration of radionuclides, as well asprevent unacceptable exposure to the operating personnel (as quantified bySection 5.2 guidelines):' The facility will not provide for the long-termstorage or treatment of secondary solid wastes. These solid wastes will betransported to other Hanford Site storage and treatment facilities designed tohandle these and similar Hanford Site wastes.

The treatment systems are anticipated to be commercially availablesystems. The operating procedures and requirements of the treatment systemspresent no great unknowns or risks.

21

Page 38: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-0O1 REV 2

5.3 Unacceptable Safety Consequences

The project design goal will be to prevent an unacceptable safetyconsequence. Unacceptable safety consequences include:

0 Fire or explosion;

0 Criticality event--At least two unlikely, independent, andconcurrent changes (contingencies) in processing and/or operatingconditions must happen before a criticality accident is possible.(a criticality event is anticipated to be an unlikely event);verification will be in accordance with DOE Order 6430.1A, 1300.4;

0 Radioactivity event--Instantaneous releases of radioactivity fromthe facility are in excess of 5,000 times the DerivedConcentration Guidelines limits at the point of discharge averagedover 4-h period as defined in WHC-CM-7-5 Environmental ComplianceManual (WHC 1988b) (a radioactivity event is anticipated to be anunlikely event); verification will be in accordance withDOE Order 6430.1A;

o Exposure of personnel to ionizing radiation in excess of thestandards and guidelines specified in the DOE Order 5480 series;and

0 Exposure of personnel to toxic chemical agents in excess ofceiling threshold limit values (TLV-C) of the American Conferenceof Governmental Hygienists.

New safety documentation to be prepared by the operating and engineeringcontractor will verify the safety design features, operating requirements, andadministrative controls required of the facilities before operation. Theinteractions of systems, components, and structures between Projects C-018,W-049H, and W-105 will be analyzed to ensure required functions survive undernormal, upset, and accident conditions.

22

Page 39: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

6.0 CODES AND STANDARDS

The project will be designed to comply with RCRA containment and leakdetection criteria found in 40 CFR 264 (EPA 1980) and WAC 173-303. Theproject will be designed to handle low-level wastestreams that are below therequirements of secondary containment found in DOE Order 5820.2A. Thecriteria for this discharge system will be based on the DOE Order 6430.1Aand DOE Order 5400.1.

The following outline defines the appropriate codes, standards,regulations, guidelines, and orders that are not defined withinDOE Order 6430.1A.

0 DOE Order 5400.2A, Environmental Compliance Issue Coordination(DOE 1988a).

0 DOE Order-5400.5, Radiation Protection of the Public and theEnvironment, February 8, 1990.

0 DOE Order 5480.5, Safety of Nuclear Facilities (DOE 1986).

0 DOE Order 5440.1C, National Environmental Policy Act (DOE 1985a).

0 DOE Order 5480.3, Safety Requirements for the Packaging ofHazardous Materials, Hazardous Substances, and Hazardous Wastes(DOE 1985b).

0 DOE Order 5820.2A, Radioactive Waste Management.

0 DOE-RL Order 4700.1, Project Management Systems (DOE-RL 1989a).

0 DOE-RL Order 5480.1A, Environment, Safety, and Health Program forDOE-RL Operations (DOE-RL 1989b).

0 DOE-RL Order 5480.48, Environmental Protection, Safety and HealthProtection Standards for DOE-RL Operations (DOE-RL 1989c).

0 DOE-RL Order 6430.1C, Hanford Plant Standards (HPS) Program,March 5, 1990

0 DOE-RL Order 5480.7A, Fire Protection (DOE-RL 1988a).

0 DOE-RL Order 5480.10A, Industrial Hygiene Program (DOE-RL 1988).

o DOE-RL Order 5440.1A, Implementation of the National Environmental

Policy Act at the Richiland Operations Office (DOE-RL 1987).

23

Page 40: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-O01 REV 2

o OOE-RL Order 5480.11A, Requirements for Radiation Protection(DOE-RL 1986).

0 DOE-RL Order 5481.1, Safety Analysis and Review System(DOE-RL 1983).

o DOE-RL Order 5700.1A, Quality Assurance (DOE-RL 1983b).

o WAG 173-201, Water Quality Standards for Waters of the State ofWashington (Ecology 1987).

0 WAC 173-216, Waste Discharge Permit (Ecology 1986).

0 WAC 173-303, Dangerous Waste Regulations (Ecology 1989).

0 WHC-CM-4-2, Quality Assurance Manual (WHC 1988d).

0 WHC-CM-4-3, Industrial Safety Manual (WHC 1988e).

0 WHC-CM-4-9, Radiological Design (WHC 1988c).

0 WHC-CM-4-1O, Radiation Protection (WHC 1988f).

0 WHC-CM-4-11, ALARA Program Manual (WHC 1988g).

0 WHC-CM-4-46, Non-reactor Facility Safety Manual (WHC 1988h).

o WHC-CM-7-5, Environmental Compliance Manual (WHC 1988b).

0 WHC-EP-0063, Hanford Radioactive Solid Waste Packaging Storage andDisposal Requirements (WHC 1988i).

In addition to the above standards, applicable national consensus codesand standards and pertinent state and local codes and standards will be used.The latest edition of all codes and standards will be used.

24

Page 41: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

7.0 REFERENCES

Clean Water Act of 1977, as amended, Public Law 95-217, 92 Stat. 1566,

33 usc 1251.

DOE, 1989a, General Design Criteria, DOE Order 6430.1A, etc.

DOE, 1989b, Hazardous and Radioactive Mixed Waste Program, DOE Order 5400.3,U.S. Department of Energy, Washington, D.C.

DOE, 1988a, Environmental Compliance Issue Coordination, DOE Order 5400.2A,U.S. Department of Energy, Washington, D.C.

DOE, 1988b, Radioactive Waste Management-Guidance Document, DOE Order 5820.2A,U.S. Department of Energy, Washington, D.C.

DOE, 1988c, General Environmental Protection Program, DOE Order 5400.1,U.S. Department of Energy, Washington, D.C.

DOE, 1986, Safety of Nuclear Facilities, DOE Order 5480.5, U.S. Department ofEnergy, Washington, D.C.

DOE, 1985a, National Environmental Policy Act, DOE Order 5440.1C,U.S. Department of Energy, Washington, D.C.

DOE, 1985b, Safety Requirements for the Packaging of Hazardous Materials,Hazardous Substances, and Hazardous Wastes, DOE Order 5480.3,U.S. Department of Energy, Washington, D.C.

DOE-RL, 1989a, Project Management Systems, DOE-RL Order 4700.1, U.S. Departmentof Energy-Richland Operations Office, Richland, Washington.

DOE-RL, 1989b, Environment, Safety, and Health Program for DOE-RL Operations,DOE-RL Order 5480.1A, U.S. Department of Energy-Richland OperationsOffice, Richland, Washington.

DOE-RL, 1989c, Environmental Protection, Safety and Health Protection Standardsfor DOE-RL Operations, DOE-RL Order 5480.48, U.S. Department of Energy-Richland Operations Office, Richland, Washington.

DOE-RL, 1989d, Hanford Plant Standards/Specifications, DOE-RL Order 6430.18, andletter J. H. Antonen, RL to Contractors, "Hanford Plant Standards," July22, 1989, U.S. Department of Energy-Richland Operations Office,Richland, Washington.

25

Page 42: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

DOE-RL, 1989e, Standard Architectural-Civil Design Criteria, "Design Load forStructures," HPS SDC-4.1, Rev. 11 (periodically revised and reissued),U.S. Department of Energy-Richland Operations Office, Richland,Washington.

DOE-RL, 1988 a, Fire Protection, DOE-RL Order 5480.7A, U.S. Department of Energy-Richland Operations Office, Richland, Washington.

DOE-RL, 1988b, Industrial Hygiene Program, DOE-RL Order 5480.10A,U.S. Department of Energy-Richland Operations Office, Richland,Washington.

DOE-RL, 1987, Implementation of the National Environmental Policy Act at theRichl1and Operations Office, DOE-RL Order 5440.1A, U.S. Department ofEnergy-Richland Operations Office, Richland, Washington.

DOE-RL, 1987, Plan and Schedule to Discontinue Disposal of Contaminated Liquidsinto the Soil Column at the Hanford Site, unnumbered U.S. Department ofEnergy-Richland Operations Office, Richland, Washington.

DOE-RL, 1986, Requirements for Radiation Protection, DOE-RL Order 5480.11A, U.S.Department of Energy-Richland Operations Office, Richland, Washington.

DOE-RL, 1983a, Safety Analysis and Review System, DOE-RL Order 5481.1,U.S. Department of Energy-Richland Operations Office, Richland,Washington.

DOE-RL, 1983b, Quality Assurance, DOE-RL Order 5700.1A, U.S. Department ofEnergy-Richland Operations Office, Richland, Washington.'

Ecology, 1989, Dangerous Waste Regulations, Washington Administrative Code 173-303, Washington State Department of Ecology, Olympia, Washington.

Ecology, 1987, Water Quality Standards for Waters of the State of Washington,WAC 173-201, Washington State Department of Ecology, Olympia,Washington.

Ecology, 1986, State Waste Discharge Permit Program, Washington AdministrativeCode, WAC 173-216, Washington State Department of Ecology, Olympia,Washington.

26

Page 43: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2.

Ecology, EPA, and DOE, 1989, Hanford Federal Facility Agreement and ConsentOrder, Washington State Department of Ecology, U.S. EnvironmentalProtection Agency, and U.S. Department of Energy, Olympia, Washington.

EPA, 1988a, Interim Status Standards for Owners and Operator s of Hazardous WasteTreatment, Storage, and Disposal Facilities, Title 40, Part 265, Code ofFederal Regulations, as amended, U.S. Environmental Protection Agency,Washington, D.C.

EPA, 1988b, National Emission Standards for Hazardous Airborne Pollutants, Title40, Code of Federal Regulations, Part 61, as amended, U.S. EnvironmentalProtection Agency, Washington, D.C.

EPA, 19 , Preventing Significant Deterioration Permit, Title 40, Code of-Federal Regulations, Part 52, U.S. Environmental Protection Agency,Washington, D.C.

Flyckt, 0. L., R. L. McCormack, 1989, Storage, Treatment, and DisposalAlternatives for the 242-A Evaporator and PUREX Plant Effluent,WHC-EP-0284, Westinghouse Hanford Company, Richland, Washington.

McKenney, D. E. 1990, Double-Shell Tank Space Analysis of Hanford site OperatingScenarios, WHC-EP-0286 Rev 1, Westinghouse Hanford Company, Richland,Washington.

National Environmental Policy Act of 1969, Public Law 91-190, 83 Stat. 852, 422USC 4321, et seq.

NFPA, 1988, Safety to Life from Building and Structures, Code 101, National Fire.Protection Association.

Resource Conservation and Recovery Act of 1976, as amended, Public Law 94-580,90 Stat. 2795, 42 USC 6901 et seq.

WHC, 1989, Waste Stream Characterization Report, WHC-EP-0287, WestinghouseHanford Company, Richland, Washington.

WHC, 1988a, Annual Status Report of the Plan and Schedule to DiscontinueDisposal of Contaminated Liquids in to the Soil Column at the HanfordSite, WHC-EP-0196-1, Westinghouse Hanford Company, Richland, Washington.

WHC, 1988b, Environmental Compliance Manual, WHC-CM-7-5, Westinghouse HanfordCompany, Richland, Washington.

WHC, 1988c, Radiological Design, WHC-CM-4-9, Westinghouse Hanford Company,Richland, Washington.

27

Page 44: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

WHC, 1988d, Quality Assurance Manual, WHC-CM-4-2, Westinghouse Hanford Company,Richland, Washington.

WHC, 1988e, Industrial Safety Manual, WHC-CM-4-3, Westinghouse Hanford Company,Richl and, Washington.

WHC, 1988f, Radiation Protection, WHC-CM-4-1O, Westinghouse Hanford Company,Richland, Washington.

WHC, 1988g, ALARA Program Manual, WHC-CM-4-11, Westinghouse Hanford Company,Richland, Washington.

WHC, 1988h, Non-reactor Facility Safety Manual, WHC-CM-4-46, WestinghouseHanford Company, Richland, Washington.

WHC, 1988i, Hanford Radioactive Solid Waste Packaging Storage and DisposalRequirements, WHC-EP-0063, Westinghouse Hanford Company, Richland,Washington.

28

Page 45: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

APPENDIX A

PROPOSED SITE PLAN

29

Page 46: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-CO18H--FOC-OO1 REV 2

This page intentionally left blank.

30

Page 47: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-COl8H-FDC-O0l REV 2

APPENDIX A

PROPOSED SITE PLAN

A Site Evaluation Report (SER) will be prepared to evaluate alternativelocations and recommend a preferred site for the Effluent Retention andTreatment Complex (ERTC). The 242-A Evaporator and the PUREX Plant CondensateTreatment Facility are a part of the ERTC. Figure A-i is an illustration ofthe preferred location for the 242-A Evaporator and the PUREX Plant CondensateTreatment facility. The preferred location is shown as "Site A." Figure A-2is an illustration of the three potential soil column disposal sites currentlybeing evaluated.

31

Page 48: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FOC-OOI REV 2

This page intentionally left blank.

32

Page 49: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-COl8H-FDC-001 REV 2

Figure A-i. Effluent Retention and Treatment Complex,Sites A and B.

33

Page 50: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

M7~ RCAJLRI I

334

Page 51: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDCO00l REV 2

Figure A-2. Three Potential Soil Column Disposal Sites.

35

Page 52: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

C a

C4

~9 11LL

*L LLi

4=,--] 3 cc~ __ = !=N C4 C C4 C

0U IV__ _ __ _ _ _

CN /uo4a

0- r- .Z

36

Page 53: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-S-CO18H-FOC-OO1 REV 2

p~7 mm an~-

LI~'

ws r4

3: I tj: I I

U, U.

377

Page 54: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

38

Page 55: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FOC-OO1 REV 2

APPENDIX B

PROPOSED TREATMENT SYSTEM

39

Page 56: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

40

Page 57: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-0O1 REV 2

APPENDIX B

PROPOSED TREATMENT SYSTEM

The proposed treatment system will be capable of treating 150 gal/min.

Because the 242-A Evaporator PC is a listed waste, it is necessary toprepare a U.S. Environmental Protection Agency (EPA)-approved delistingpetition for the wastestream before operation of the treatment system.

The design capacity for the 242-A Evaporator is based on the followingconsiderations:

0 The maximum expected flow rate for the 242-A Evaporator PC is75 gal/mmn. This flow rate assumes that the existing ion-exchangecolumn is bypassed.

0 The 242-A Evaporator will produce 40 Mgal of PC during the firsttwo years of the treatment facility operation.

0 The Liquid Effluent Retention Facility (Project W-105) willcontain 13 Mgal of 242-A Evaporator PC at the time of thetreatment facility start-up. A recent agreement with the EPA andthe coordination with the 200 Area Treated Effluent DisposalSystem (TEDS) require that this inventory be treated and any LandDisposal Restricted (LDR) wastes removed from the basins byDecember 1994.

0 During the first 2 years of operation the treatment system willoperate 7 day/week, 3 shifts per day. The assumed total operatingefficiency (TOE) for this period of time is 72%.

The design capacity for the PUREX Plant train will also be 75 gal/mmn.The expected average flow rate for the combined PDD/ASD stream is 40 gal/mmnwith a maximum 24-hour flow rate of 60 gal/mmn. As a result, some excesscapacity will be provided.

41

Page 58: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

42

Page 59: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

FIGURE B-1. PROPOSED TREATMENT SYSTEM

>0 o Q)

CL hL 5 3

Ln

LLJ

cnto

CO 0 tu75 E U-)

Itij 0 n d) d3Ll- .j u- . 4-

Ln >1 00 M r- %-.u W to co

V) C) 0L)

Lrl

720

fu-6 >a,= 0

5. o ELn Lo a)

cr-

to

43

Page 60: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FOC-OO1 REV 2

This page intentionally left blank.

44

Page 61: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-0O1 REV 2

The proposed treatment system will consist of the following components:

0 Staging tankso Suspended solids removal0 Organic removal0 Ammonium sulfate formation0 Dissolved solids removal0 Dissolved solids polishing0 Final pH adjustment0 Verification tanks0 Secondary waste concentration

B.1 Staging Tanks

The criteria for the staging tanks are presented in Section 2.6 of thisFunctional Design Criteria (FDC). Because the 242-A Evaporator PC is a listedwaste, the staging tanks for this stream will comply with WAC 173-303-6401.The capability to obtain a representative sample of the feed before it entersthe tanks will be provided.

The design shall consider the following to provide sufficient stagingtank capacity to support:

0 The 242-A Evaporator and the PUREX Plant operations if thetreatment system is non-operational for a 48-h period;

o Staging of the feed without shutdown of either facility duringtreatment systems operations; and

0 Staging of feed from the Liquid Effluent Retention Facility(LERF). The feed from the LERF can be mixed with the feed fromthe 242-A Evaporator.

B.2 Suspended Solids Removal -

The suspended solids removal step will remove particles in the 0.5 to2 micron range. The filters will be designed to minimize secondary wastevolumes. The filters could be designed to be air-scoured and backwashablewith one to two filter volumes of backwash. The design should permitbackwashing remotely to eliminate personnel radiation exposure to the maximumextent possible.

'Ecology, 1989, Dangerous Waste Regulations, Washington AdministrativeCode 173-303-640, Washington State Department of Ecology, Olympia, Washington.

45

Page 62: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

The suspended solids removal step shall allow for the treatment facilityto operate at design capacity during periods of filter backwash and filtermaintenance.

8.3 Organic Removal

The preferred organic removal step will consist of an ultraviolet (UV)light mediated-oxidation process (UV oxidation). The system will utilizehydrogen peroxide and/or ozone as the oxidant to promote destruction of theorganic impurities. -This unit is assumed to be capable of destroying theorganic impurities to the treatment requirements as listed in Appendix B ofthis FDC. The validity of this assumption will be tested during the design ofthe treatment system. Activated carbon columns may be considered if theverification testing shows that the UV oxidation system cannot reliably meetthe treatment targets, as described in Appendix D of this FOC.

The design of the UV oxidation step should be based on commerciallyavailable units. The design should minimize modifications to commerciallyavailable units. The design should identify critical components and allow forrapid repl acement.

8.4 Ammonium Sulfate Formation

The ammonium sulfate formation step will consist of an in-lineneutralizer to adjust the pH of the stream to the 4 to 6 range. Thisneutralization will occur in several steps and utilize sulfuric acid. Thedesign should identify critical components and allow for rapid replacement.

8.5 Dissolved Solids Removal

The preferred dissolved solids removal step will consist of a reverseosmosis (RO) unit. The reject for the RO units will be concentrated tomaximum extent possible. It is anticipated that a three-stage RO unit will berequired. Consideration should be given to providing a particulate filterbefore the RO units. This filter will collect any particulates that areformed during the UV oxidation step or the ammonium sulfate formation step.

The design of the dissolved solids removal step should be based oncommercially available RO units. The design should minimize modifications tothe commercially available units. The design should identify criticalcomponents and allow for rapid replacement. For example, the facility shouldbe designed to allow for routine replacement of the RO membranes.

46

Page 63: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD--CO18H-FDC-OO1 REV 2

B.6 Dissolved Solids Polishing

The dissolved solids polishing step will consist of an ion-exchangesystem. This polishing step may be necessary to meet the treatment targetsas described in Appendix E of this FDC. The design of the ion-exchange systemwill incorporate a variety of ion-exchange media. Potential media to be usedin the ion-exchange system include: strong acid/base resins, weak acid/baseresins, mixed-bed resins, zeolites, ion-specific resins, and activated carbon.The final selection of media is dependent upon negotiations with regulatorsand upon the results of the ongoing verification testing.

The design of the ion-exchange system will include the followingfeatures:

0 Mul~ti-vessel design--Consideration should be given to a five-vessel design: cation vessel, anion vessel, mixed-bed vessel,activated carbon, and a spare vessel. The design should allow foreasy modification of the flow path. Because of expected changesin the regulations and in the feed to the treatment system, it maybe necessary to reconfigure the flow path of the ion-exchangesystem.

0 Regeneration of the ion-exchange media.

o Sluicing of the resins into and out of the ion-exchange vessels.

The design of the system will be based on commercially available ion-exchange units. The design should minimize the modifications to commerciallyavailable equipment. The design will identify critical components and allowfor their rapid replacement.

B.7 Final pH Adjustment

The pH of the treated effluent will be adjusted and will consist of anin-line neutralizer to adjust the pH of the stream to the 6 to 8 pH range.This neutralization will occur in several steps. The design should identifycritical components and allow for rapid replacement.

B.8 Verification Tanks

Before release, the treated effluent will be routed to threeverification tanks that will be capable of containing the treated effluentfor a minimum of 72 hours. The verification tanks shall meet the requirementsof WAC 173-303-640.

47

Page 64: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FOC-OO1 REV 2

It is anticipated that these tanks will be used to periodically verifythe quality of the treated effluent whenever one of the following conditionsexist:

0 A change in feed to the 242-A Evaporator

o A change in treatment system configuration

0 During the initial start-up of the treatment system

It is anticipated that several analytical tests required forverification will require a minimum of 72 hours. During these periods ofextensive verification testing, the effluent will be recycled back to thestaging tanks or the system will be placed in a temporary standby condition.

The design of the treatment system will allow for the collection of aflow-proportional sample of the treated effluent. The design of the samplingsystem will be consistent with the requirements of the Resource Conservationand Recovery Act2 (RCRA) and the Clean Water Act.

3

8.9 Secondary Waste Concentration

The preferred process for the secondary waste concentration step is amechanical vapor recompression evaporator. The concentrate from the.evaporator is to be converted into a solid without any freestanding liquid.The criteria for the secondary waste are contained in Section 2.3 of the FOG.A single waste concentrator will be provided for both the 242-A Evaporator andthe PUREX Plant condensate treatment systems.

The design of the secondary waste concentrator will be based oncommercially available units. The design of the system will minimizemodification to commercially available equipment. Redundant concentrationunits will not be provided. However, the design of the system should identify'critical components and allow for ease of replacement and/or repair.

2 Resource Conservation and Recovery Act of 1976, as amended, Public Law94-580 190 Stat. 2795, 42 USC 6901 et seq.

~Clean Water Act of 1977, as amended, Public Law 94-580, 90 Stat. 2795,42 USC,6901 et seq.

48

Page 65: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

APPENDIX C

CHARACTERIZATION DATA

49

Page 66: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-CO18H-FDC-0O1 REV 2

This page intentionally left blank.

50

Page 67: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C0l8H-FDC-O0l REV 2

APPENDIX C

CHARACTERIZATION DATA

The design of the 242-A Evaporator and PUREX Plant condensate treatmentsystem will be based on the characterization data presented in Table B.1.Additional characterization data can be obtained from the Waste StreamCharacterization Report.' Source terms for safety analysis and permittingactivities will be developed separately.

The characterization data for the 242-A Evaporator process condensate(PC) are based on samples collected downstream of the existing ion-exchangecolumn. After the start-up of this project, these ion-exchange columns willbe bypassed. The ion-exchange media currently used in the 242-A Evaporator isvery specific for cesium and strontium. As a result, the cesium and strontiumcharacterization data presented in Table C-1 have been increased by a factorof 10. The only other expected change is a decrease in the concentration ofsilicon. The high silicon levels are likely the result of degregation of theion-exchange media.

'WHC, 1989, Waste Stream Characterization Report, WHC-EP-0287,Westinghouse Hanford Company, Richland, Washington.

51

Page 68: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

52

Page 69: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

P, pn 0 OLe -4 00U. N0

0

UN~ C Ct cc0

0. P N Fl0'1 f mema

u0 o-t NGC- 00LU &M v- Q CD.. 0 iMLf - 0 .4 SUi'0OO

0. r4 -m 0PV r4~ 0* a~ CC 06% 0'r L C

m NL - N'.GO

0. 0n cm O .U Nr 0 I

01

C U 0.0 10

0 O 0 0 oU '00 C-- a O'0 (

D v0 0 - " L

NNr

0 f Nt-1 emt0 0 0(:0 0- O .N 0?( '-t N 0~ ~ (.- -tN 0

C - NU~ - U~ r4

U% 0

0. -N40PC C, cm 2 N -e Com a

WN N0N0 P

z cm 0 0N U

NI 2

aA P, NOo 0U N C n

0 ' 0 ON '0

0.. NR : : C

U toU;c

'00

W. 0 0 0 0 0 U

u m m 0'0m

m 0 Nt '0 - 0000. z (E N -N nL :1 O 00' mTL,0 Nu% j

0 U' NO 0 0 O.ZNN:

u - . N - -C NC c 0 .uWu =z . 0 A( 4

-*53-N

Page 70: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

I 0. 02 C4 w I

,I

N-! No c 0 N 0D 0 0 'ru CWN l rcm N ri UN N

UC, cm w

(U 0u0V 0 .U Ci 0 -0 C . m~

.2p 0 Cl C - la. WN . N l -O4 0. -

0 0Nm

.em

C l -- - .5 t jN '.

u

NM

(UU

LU

>U I~

(U CL >

Pd ~ 00' 1= a I c

Uj (U ca- QUl

U c "t

0 00) 2' M0U0e . . .

0c 0c"00L*P- .- " - -0 >.

UCC mmomr ac n cc 0 ,Qa w m a WUclccw4a; Qz U=

N53-

Page 71: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

St~~ ~ %r .. -0. 0 CD 0 c Im

K, : a 11 -C :!Dt0

u a. 0, m L r oNm n c . "s 001 m- N.

a. aC : C , Cr .1

0'

>U P_ 00 mICO c C* - .OmN 0 . N.o 0 N0 0080 00 em 000=

UN~ 0 Q C!%

st -C

Nr

* l a W w -r PM0 9 040 0 ~m 000

c; - Cm 4-

~~-1 0-

% 14)

";si4- 2 --; 0k;C

8881o0 ON *s.0 SMp., 4141

> -:055- PoGu m '

4- 4 4 -

K 41

co L-oU' 0 0001 1

m >

0 O 0 C, do 1 Gn"4 a- 0 ,F4r-80 I SC5-Sn

41 41 -.

NC 2.V Z = = WC~~ 2 Vi -1 c 41Q 5 4al

CL fm* C0C=JTi ;;.4CDz2

.cP- 8.4- 220.t

0_r -- 0 ;CN; 4A

.~M .. f 0 --

a- a

410 C o 41'- Uacc. a 0 0' 0 0 41 0 24 0o m 0 e

c 40 U' N.3 U- ' 0 dI-~3NO L

r .60= N. cc . u M

X41 .CA N- -J (A- 1 'A' =01 -c"_0 C O-s nc oc 0c~u 006S0..000.0C0 4. 44

41 0 N. 0 0 N~ .- Nm5SOOO 0 0,0 C0o .N"* 4 '44- .wW r_ ' oi 0' (-!U. 0ompn'N I-

53-c

Page 72: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

54

Page 73: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

APPENDIX 0

TREATMENT TARGETS

55

Page 74: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

56

Page 75: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C018H-FDC-O01 REV 2

APPENDIX D

TREATMENT TARGETS

The preferred alternative for the disposal of the treated effluent fromthe 242-A Evaporator and PUREX Plant condensate treatment facility is a soilcolumn disposal system, permitted in compliance with WAC 173-216, WasteDischarge Permit Program. 1 Should this alternative become unacceptablebecause of technical or permitting issues, it will be necessary to pursue ariver disposal option. The design and cost for this option should be includedin the conceptual design report.

The treatment system will be capable of meeting release limits containedin a State of Washington Waste Discharge Permit (WAC 173-216)1 or an NPDESpermit. This are negotiated permits, and requires the application of allknown, available, and reasonable technology (AKART) to satisfy therequirements of the state of Washington or Best Available Technology tosatisfy the Federal requirements. During the permitting process, theappropriate treatment system design will be determined by either the AKART orBAT processes. Both methodologies will include a review of treatment systemtechnologies.

Both WAC 173-216 and NPDES permit conditions will be negotiated duringthe design of the project. Until these criteria become available, the designof the project will use the target levels as presented in Table D-1.

The design of the river disposal option will provide a piping system totransport the treated effluent to the Columbia River. The discharge site willbe located in accordance with the Site Evaluation Report for the 200 AreaEffluent Retention and Treatment Complex (ERTC). The following outlines theminimal requirements of the river discharge system.

o A river outfall or diffuser, if provided, shall comply with theNational Pollution Discharge Elimination System (NPDES) andU.S. Army Corps of Engineers requirements.

0 River piping and diffusers, if provided, shall be secured andanchored to accommodate the 100-year flood.

0 Piping shall be compatible with the anticipated flowcharacteristics and shall be. designed for gravity flow whereverpracticable.

0 Pumps, if used, shall be electric, connected to standby power, andshall be redundant.

0 Piping shall be underground and/or otherwise protected fromfreezing.

'Ecology, 1986, State Waste Discharge Permit Program, WashingtonAdministrative Code, WAC-173-216, Washington State Department of Ecology,Olympia, Washington.

57

Page 76: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-QO1 REV 2

The treatment targets presented in this appendix are intended to beconservative (low) estimates of the release limits that would be contained ineither a WAC-173-216 or NPDES permit. They are not intended to be anindication of the level of treatment that is possible with the facilitiesprovided by this project.

The treatment targets presented in Table D-1 are the most stringent ofthe following:

0 Safe Drinking Water Act 3 Primary Maximum Contaminant Levels(PMCL), Secondary Maximum Contaminant Level (SMCL), MaximumContaminant Level Goals (MCLG)

0 Ground water quality criteria as stipulated by WAC 173-200

o Land disposal restrictions, 40 CFR 268.41 and 40 CFR 268.43

0 One tenth of the purgewater collection criteria values asstipulated in Table 1, "Strategy for Handling and Disposing ofPurgewater at the Hanford Site," (90-ERB-076)

0 Health based limit, as stated in Docket Report on Health-BasedLevels and Solubilities Used in the Evaluation of DelistingPetitions Submitted Under 40 CFR 260.00 and 260.22, written byScience Applications International Corporation, prepared under EPAcontract No. 68-W9-0091 for the EPA, Washington, D.C. (November1989) or the practical quantification limit as listed in 40 CFR264, Appendix IX, whichever is greater.

'Ecology, 1986, State Waste Discharge Permit Program, WashingtonAdministrative Code, WAC-173-216, Washington State Department of Ecology,Olympia, Washington.

2 Resource Conservation and Recovery Act of 1976, as amended, PublicLaw 94-580, 90 Stat. 2795, 42 USC 6901 et seq.

3 Safe Drinking Water Act of 1974, as amended, Public Law 93-523,88 Stat. 1660, 42 USC 300f et seq.

58

Page 77: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-O01 REV 2

Table D-1. Treatment Targets

TREATMENT TARGETS*(with radionucl ides)

March 1, 1991

*Determined from the most restrictive of the constituent values from thetable "Liquid Effluent Current Comparative Limits, October 16, 1990" (WA StateDept. of Ecology) as supplemented by adding constituents and target levelsneeded. for the RCRA delisting petition.

CONST ITU ENT TARGET VALUE____ ____ ___ ____ ___ ____ ____ ___ ____ ___ ____ ___(ppb

1,1,1,2- tetrachl oroethane 5.0

1,1, 1-trichl oroethane 7.0

1,1,2, 2-tetrachl oroethane 0.5

1,1,2-Trichloro-1,2,2-triflouroethane 57.0

1,1,2-trichl oroethane 0.6

1, 1-di chl oroethane 1.0

1, 1-di chl oroethyl ene 7.0

1,2,3, 4-tetrachl orobenzene 50.0-

1,2,3,5- tetrachl orobenzene 50.0

1,2, 3-tn chl orobenzene 50.0

1,2,3-trichloropropane 5.0

1 ,2,4,5-tetrachlorobenzene 10.0

1,2,4-trichlorobenzene 9.0

1, 2-di bromo-3-chl.oropropane 5.0

1, 2-di bromoethane 0.001

1, 2-dichl orobenzene 50.0

1, 2-dichl oroethane 0.5

1, 2-di chl oropropane 0.6

1 ,2-dimethylhydrazine 60.0

1, 2-di phenyl hydrazi ne 0.04

1,3, 5-tn chl orobenzene 50.0

1 ,3-Butadiene 0.3

1 ,3-dichl orobenzene 36.0

1 ,3-dichl oropropene 0.2

59

Page 78: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-C018H-FDC-001 REV 2

CONSTITUENT TARGET VALUE

1 ,3-dinitrobenzene (meta) 10.0

1, 4-di chi orobenzene 4.0

1, 4-dichi oro-2-butene 5.0

1,4 dinitrobenzene 320.0

1, 4-di oxane 7.0

1 ,4-napthaguinone 10.0

1-butanol 5000.0

1-napthyl amine 10.0

2,3,4, 6-tetrachi orophenol 10.0

2,3,7, 8-tetrachi orodi benzo-p-di cxi n 0.0000006

2,4, __ _ _ __ _ _ __ _ _ __ _ _ ___-T_ _ _ __ _ _ 2.0

__ __ __ __ __ __ __ __ __ __ __ __ __ __ __ __ __ __ 50.0

2,4,5tricloropenol16. 0

2,4 -trchloophnol4.0

2,4-0100.0

2, 4-di chi orophenol 44.0

2, 4-dimethyl phenol 5.0

2, 4-di ni trophenol 50.0

2,4-dichiorophenoxy-acetic acid 1000.0

2,4-dinitrotoluene 0.1

2, 4-di arinetol uene 0.002

2,4, 6-trinitrotol uene 1.0

2, 6-di chl orophenol 10.0

2,6-dimethyl phenol 2.0

2,6-dinitrotol uene 0.1

2, 6-tol uenedi ani ne 6000.0

2-chloroethyl vinyl ether 57.0

2-sec-Butyl -4, 6-di ni trophenol 66.0

12-acetyl ami nofi ourene 59.0

50

Page 79: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C018H-FDC-001 REV 2

CONSTITUENT TARGET VALUE____ ___ ___ ___ ___ ___ ___ ____ ___ ___ ___ ___ ___ ___ ___(ppb)

2-hexanone 50.0

2-methoxy-5-nitroanilime 2.0

2-methyl aniline 0.2

2-methylanilime hydrochloride 0.5

2-methyl napahthal ene 10.0

2-acetyl aminofi uorene 10.0

2-chl oronaphthal ene 10.0

2-chl orophenol 44.0

2-napthyl amine 10.0

2-picolime 5.0

3,3 '-dichlorobenzidine 0.2

3,3 '-dimethoxybenzidine 6.0

3,3 '-dimethylbenzidine 0.007

3-chloropropene (see Allyl chloride)___________

3-methyl chol anthrene 5.5

3, 4-dimethyl phenol 4.0

4,4'-methylene-bis-(2-chloroanalime) 500.0

4,4'-methylene-bis- (N,N'-dimethyl)analine 2.0

4,6-dinitro-o-cresol and salts 50.0

4-nitro-l-oxo-quinolime 10.0

4-ami nobi phenyl 10.0

4-bromophenyl phenyl ether 10.0

4-chloro-2-methyl aniline 0.1

4-chloro-2-methyl anilime hydrochloride 0.2

4-nitrophenol 120.0

5-nitro-o-tol uidine 10.0

7, 12-dimethyl benz(a) anthracene 10.0

Acenaphthal ene 10.0

Acenapthene 59.0

61

Page 80: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-0O1 REV 2

CONSTITUENT TARGET VALUE____ ___ ___ ___ ___ ___ ___ ____ ___ ___ ___ ___ ___ ___ ___(ppb)

Acetone 50.0

Acetonitril1e 100.0

Acetophenone 10.0

Acrol ei n 21.0

Acryl ami de 0.02

Acrylic acid 3000.0

Acrylonitrile 0.07

Adi pates r~l (ethylhexyl) adi pate1 500.0

Alachior 2.0

ildrin 0.005

illyl alcohol 200.0

illyl chloride 10.0

Alumi num 50.0

Aluminum, filtered 50.0

Ammoni a 1300.0

ara-di methyl phenethyl amine 10.0

Analine 10.0

Anthracene 10.0

Antimony 3.0

Antimony, filtered 1600.0

Antimony-125 300 pCi/l

Arami te 3.0

Arochlor 1016 0.1

Arochior 1221 0.1

Arochior 1232 0.1

Arochior 1242 0.1

Arochlor 1248 0.1

Arochior 1254 0.1

Arochlor 1260 0.1

62

Page 81: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

COSITETTARGET VALUE(ppb)

Arsenic50.0

Arseictota meals0.05

Arsenic, filtered 48.0

Arsenic acid 790.0

Arsenic oxide 790.0

Azobenzene 0.7

Barium 1000.0

Barium, total metals 1000.0

Barium, filtered 1000.0

Benz (a) anthracene 10.0

Benzal Chloride 280.0

Benzyl Chloride 100.0

Benzene 1.0

Benzidine 0.002

Benzotrichloride 0. 007

Benzo( a) anthracene 10.0

Benzo(g,h, i)perylene 5.5

Benzo (k) fl uoranthene 10.0

Benzo(a)pyrene zero (10.0)

Benzo(b/k)fl uoranthene - 29.0

Benzo(b) fl uoranthene 10.0

Benzo (k) fluoranthene 10.0

Benzyl alcohol 20.0

Benzyl chloride 0.5

Beryllium zero (2.0)

Beryllium, filtered 5.3

Bis(2-chloro-isopropyl )ether 10.0

Bis(2-chloroethoxy) methane 10.0

_is(chloroethyl )ether 0.07

63

Page 82: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C018H-FDC-001 REV 2

CONSTITUENT TARGET VALUE

(ppb)

Bis(2-chloroethyl) ether 7.0

Bis(chloroisopropyl )ether 1000.0

Bis(chloromethyl )ether 0.0002

Bis(2-ethylhexyl) phthalate 6.0

Bromodi chi oromethane 0.3

Bromoforn 2.0

Bromomethane 50.0

Butyl benzyl phthalate 17.0

Cadmiurn 10.0

Cadmium, total metals 10.0

Cadmium, filtered 1.1

Carbazol e 5.0

Carbon disulfide 5.0

Carbon tetrachloride 0.3

Carbon-14 2000 pCi/l

Cesium-137 200 pCi/l

Chloral 70.0

Chl ordane 0.06

Chloride 250000.0

Chl orobenzene 2.0

Chlorobenzene (by ABN) 2.0

Chl orobenzi late 30.0

Chl orodi bromomethane 0.5

Chl oroethane 5.0

Chl oroform 6.0

Cho oromethane 190.0

Chioromethyl methyl ether 0.004

Chlorthalonil 30.0

Chromiurn 50.0

64

Page 83: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-CO18H-FOC-001 REV 2

CONST ITUENT TARGET VALUEI(ppb)

Chromium, total metals 50.0

Chromium (VI) 11.0

Chromium, filtered 11.0

Chrysene 10.0

cis-1 ,2-dichloroethylene 70.0

cis-1 ,3-dichloropropene 36.0

Cabal t-60 100 pCi/l

Coliform bacteria, total 1/100 ml

Color 15 color units

Copper 1000.0

Copper, total metals 1000.0

Copper, filtered 12.0

Corrosivity noncorrosivye

Cresol s 10.0

Cresols, m and p isomers 770.0

Cyanides, amenable 100.0

Cyanide 5.2

Cy an ogen 1000.0

Cyanogen bromide 3000.0

Cyci ohexanone 125.0

DOD 0.1

DOE 0.05

DDT 0.01

DDT+ ODE+ DOD 0.3

.5-BHC 0.1

Dal apon 200.0

Di -n-butyl phthal ate 57.0

Di-n-octal phthal ate 17.0

Oi-n-propyl nitrosamine 10.0

65

Page 84: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-0O1 REV 2

CONSTITUENT TARGET VALUE____ ___ ___ ___ ____ ___ ___ ___ ___ ____ ___ ___ ___ ___(ppb)

liallate 1.0

)ibenz(a,h)acridine 10.0

)ibenz(a, h) anthracene 10.0

)ibenzofuran 10.0

Dibromomethane 110.0

Dibromochi oromethane 1.0

Dichi orodi fiuoromethane 5.0

Dichiorovos 0.3

Dieidrin 0.005

)iethyl phthalate 200.0

Dimethyl phthal ate 47.0

Dimethyl terephthal ate 4000.0

Diguat 20.0

Dimethoate 10.0

Di ni trobenzene 10.0

Dinoseb 1.0

Dioxane 150.0

Dioxin 0.01

Diphenyl amine 10.0

Di phenyl ni trosami ne 400.0

Direct black 38 0.009

Direct blue 6 0.009

Direct brown 95 0.009

Disulfoton 2.0

Endosulfan 1 0.06

Endosulfan 11 29.0

Endosul fan sul fate 29.0

Endothal 1 100.0

Endrin 0.01

66

Page 85: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C018H-FDC-0O1 REV 2

CONSTITUENT TARGET VALUE____ ___ ____ ___ ___ ____ ___ ____ ___ ___ ____ ___ ___(ppb)

Endrin aldehyde 25.0

Epi chi orohydrin 8.0

Ethyl acetate 50.0

Ethyl acrylate 2.0

Ethyl benzene 2.0

Ethyl ether 50.0

Ethyl rethacryl ate 5.0

Ethyl methanesul fonate 10.0

Ethyl ene dibromide 0.001

Ethylene thiourea 2.0

Ethylene oxide 0.1

Famphur 17.0

Fl uoranthene 10.0

Fl uorene 7'.0

Fl uoride 2000.0

Fl ourotri chl oromethane 20.0

Foaming agents 500.0

Folpet 20.0

Formic acid 70000.0

Furazol idone 0.02

Fun um 0.002

Furmecycl ox 3.0

Gl yphosate 700.0

Gross alpha 15 pCi/l

Gross beta particle activity, gross beta activity 50 pCi/l

Gross beta particle activity, tritium 20,000 pCi/l

Gross beta particle activity, strontium 90 8 pCi/lHeptachl or 0.01

Hep tachlor epoxide 0.009

67

Page 86: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-O01 REV 2

CONSTITUENT TARGET VALUE____ ___ ____ ___ ___ ____ ___ ____ ___ ___ ____ ___ ___(ppb)

Hexabromobenzene 70.0

iexachi orobenzene 0.05

lexachl orobutadi ene 5.0

Hexachi orocyci ohexane (al pha) 0.001

lexachiorocyclohexane (technical) 0.05

iexachi orocyci opentadi ene 5.2

Hexachi orodi benzofurans 1.0

Hexachlorodibenzo-p-dioxin, mix 0.00001

Hexachlorodibenzo-furans, All 0.063

iexachl oroethane 7.0

iexachl orophene 10.0

lexachl oropropene 10.0

Hydrazine/Hydrazine Sulphate 0.03

lydrocy anic acid 700.0

Hydrogen sulfide 2.0

i-butyl alcohol 5000.0

Indeno(1 ,2,3-c,d)pyrene 5.5

Iodi ne-129 1 pCi/i

Iodine-132 3 pCi/l

Iodomethane 5.0

Iron 300.0

Iron, total metals 300.0

Iron, filtered 300.0

I sobutanol 1000.0

Isodrin 10.0

Isophorone 10.0

Isosafrol e 10.0

Kepone 1.1

Lead 37.0

68

Page 87: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

CONSTITUENT TARGET VALUE____ ___ ____ ___ ___ ____ ___ ____ ___ ___ ____ ___ ___(ppb)

Lead, total metals 50.0

Lead, filtered 3.2

Lindane 0.06

Lindane, a-BHC 0.14

Lindane, B-BHC 0.14

Lindane, 6-BHC 23.0

indane, v-BHC 0.08

n-phenyl enedi amine 200.0

4aleic anhydride 4000.0

laleic hydrazide 20000.0

langanese 50.0

4anganese, total metals 50.0

langanese, filtered 50.0

ler cury 2.0

lercury, total metals 2.0

lercury, filtered 0.01

lethacryl oni tril1e 5.0

lethanol 250.0

lethapyril1ene 10.0

lethomyl 90.0

4ethoxychlor 0.3

4ethyl bromide 10.0

lethyl chloride 1.0

lethyl chl orocarbonate 40000.0

4ethyl chrysene 3000.0

lethyl ethyl ketone 10.0

4ethyl isobutyl ketone .5.0

4thyl1 methacryl ate 2.0

e thyl methanesul fonate 10.0

69

Page 88: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FOC-001 REV 2

CONSTITUENT - TARGET VALUE(ppb)

Methyl parathion 0.5

ethylene chloride 5.0

irex 0.05

itric oxide 4000.0

Nitroqen dioxide 40000.0

N-nitrosodiphenyl amine 10.0

N-nitroso-di-n-butyl amine 0.006

N-nitrosodiethanol amine 0.01

N-nitrosodiethyl amine 0.0005

N-nitrosodimethyl amine 0. 002

N-nitroso-di-n-propyl amine 0.01

N-nitroso-n-methyl ethyl amine 0.004

N-ni trosomorphol ine 10.0

N-nitrosopi peridi ne 10.0

N-nitrosopyrrol idine 0.04

Napathal ene 7.0

Nickel 100.0

Nickel, filtered 160.0

Nickel-63 50 pCi/l

Nitrate (as nitrogen) 10000.0

Nitrite 3300.0

Ni trobenzene 10.0

Ni trofurazone 0.06

Nitrosopyrrol idine 10.0

Odor 3 threshold odor____ ___ ____ ___ ___ ____ ___ ____ ___ ___ ____ ___ ___ units

0,O,O-triethyl phasphorothioate 10.0

O-toluidine hydrochloride 10.0

o-cresol 200.0

Pxamyl 200.0

70

Page 89: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-CO18H-FDC-001 REV 2

CONSTITUENT TARGET VALUE____ ___ ____ ___ ___ ____ ___ ____ ___ ___ ____ ___ ___(ppb

p-chioroanilime 100.0

P-chi oro-m-cresol 200.0

PAH 0.01

PBB s 0.01

PCBs 0.01

Parathion 0.2

Pcdd's 0.01

Pcdf's 0.01

Pentachi orobenzene 10.0

Pentachl orodi benzo 1.0furans____________

Pentachloro-dibenzo-p- dioxins, all 0.063

Pentachi oro-di benzo-p-furans, all 0.035

.Pentachioroethane 7.0

Pentachi oroni trobenzene 10.0

Pentachioro phenol 13.0

pH 6.5 -8.5

Phenaceti n 10.0

Phenanthrene 7.0

Phenol 39.0

Phenyl enedi amine 10.0

Phenylmercury acetate 3000.0

Phorate 2.0

Phthalates [Di (ethyl hexyl )phthal ate] zero

Phthalic anhydride (as phthalic acid) 540.0

Phthalic acid esters 3.0

Pi cloram 500.0

P1 utoni um-238 1.6 pCi/l

P1 utonium-239, 240 1.2 pCi/l

Pronami de 10.0

71

Page 90: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C018H-FDC-001 REV 2

COSITETTARGET VALUE____ ___ ____ ___ ___ ____ ___ ____ ___ ___ ____ ___ ___(ppb)

Proponiril (Etyl yande)5.0

Propylene _______________oxide_______ 0.01

__ _ _ _ __ _ _ _ __ _ _ _ _ __ _ _ _ __ _ _ _ __ _ _ _ _ 4000.0

__ _ _ _ __ _ _ _ __ _ _ _ __ _ _ _ __ _ _ _ __ _ _ _ _ 10.0

Pyridine 14.0

Para-a!,ct,a-Tetrachl orotol uene 0.004

Quinolime 0.003

Radium-226 & 228 5 pCi/i

Radi um-226 3 pCi/i

Radium 5 pCi/i

Rutheni urn-103 200.0

Rutheni um-106 30 pCi/l

Safrol 10.0

Selenium, total metals 10.0

Selenium, filtered 10.0

Sel enium 10.0

Selenious acid 100.0

Silver 50.0

Silver, total metals 50.0

Silver, filtered 1.0

Simazine 1.0

solids, Total dissolved 50,000.0

Stronti um-89 20 pCi/l

Styrene 1.0

Sulfate 250,000.0

Sul fide 14,000.0

Sym-tri nitrobenzene 10.0

Techneti um-99 900 pCi/i

Tetrachi orodi benzofurans 1.0

72

Page 91: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-C0i8H-FDC-O0I REV 2

CONSTITUENT TARGET VALUE____ ___ ___ ___ ____ ___ ___ ___ ___ ____ ___ ___ ___ ___(ppb)

Tetrachloro-dibenzo-p-dioxins, all1 0.063

Tetrachi oro-di benzo-furans, all 0.063

Tetrachl oroethene 6.0

Tetrachi orophenol s (total) 18.0

Tetrachi oroethyl ene 0.8

Tetraethyl di thi opyrophosphate 20.0

1 etraethyl pyrophosphate 10.0

Thallium 0.5

Thiourea 0.02

Tin, filtered 8000.0

Tol uene 2.0

Toxaphene 0.08

trans-i, 2-di chi oroethane 33.0

trans-1 ,2-di chi oroethyl ene 1.0

trans-i ,3-dichloropropene 36.0

Tri chl oroethyl ene 3.0

Tri chioroethane 200.0

Tri chl orofi uoromethane 50.0

Trichi oromonofi uoromethane 5.0

Trihalomethanes (includes chloroform, bromoforn, 100.0bromodichl oromethane, and dibromochl oromethane)___________

Trimethyl phosphate 2.0

tris-(2,3 dibromopropyl) phosphate 25.0

Uranium 40 pCi/l

Uranium, chemical 59.0

Vanadiurn 42.0

Vanadium, filtered 40.0

Vanadium Pentoxide 70.0

Vinyl acetate 5.0

Vinyl chloride 0.02

73

Page 92: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-001 REV 2

CONSTITUENT TARGET VALUES(ppb)

Xylene 11.0

Zinc 5000.0

Zinc, total metals 5000.0

lic, filtered 110.0

-p-cresol s 770.0

i-di chl orobenzene 36.0

n-nitroanilime 50.0

n-xyl ene 5.0

n-butyl alcohol 5000.0

o, p'-ODD 23.0

o,p'-DOE 31.0

o,p'-DDT 3.9

o-chl oronitrobenzene 3.0

o-cresol 110.0

o-di chi orobenzene 8.0

o-nitroanilime 50.0

0-ni trophenol 28.0

o-phenyl enedi amine 0.005

o-toluidine 0.2

o-xyl ene 5.0

p,p'-DDD 23.0

o,p'-ODE . 31.0

p,p'-DDT 3.9

p-chl oro-m-cresol 5.0

P-chioroanilime 20.0

p-chi oron itrobenzene 5.0

p-di chi orobenzene 8.0

o-dimethyl aminoazobenzene 10.0

p-nitroaniline 28.0

74

Page 93: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

CONSTITUENT TRE AU

p-ni trophenol 1_____0.0_____

p-xylen e 5.0_________

75

Page 94: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD--CO18H-FDC-OO1 REV 2

This page intentionally left blank.

76

Page 95: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

APPENDIX E

PROCESS AND SUPPORT FACILITY

DESIGN CONSIDERATIONS

77

Page 96: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page is intentionally left blank.

78

Page 97: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

AL

WHC-SD-CO18H-FDC-OO1 REV 2

APPENDIX E

PROCESS AND SUPPORT FACILITY DESIGN CONSIDERATIONS

The design of the process and support services facilities shouldconsider the following design features:

0 A process equipment confinement area with excess floor area forincorporation of Project W-049H will be provided. If necessary,shielding will be included in this area.

0 A packaging and shipping area to facilitate the removal ofsecondary waste will be included.

0 Floor drains and sumps will be installed in process areas. Theability to transfer sump solutions to feed tanks or temporarystorage will be provided. Embedded floor drains and wet sumpsshall have testable secondary containment. The design of thesystem should give preference to the use of lined troughs wheredrainage is collected and directed to tanks.

0 Emergency lighting will be provided for personnel egress. Processareas that are occupied will use white light, and the lightingwill be water resistant. Exterior areas and parking lots may belighted by low-pressure sodium if color rendition is not requiredfor safety or operation.

0 Heating, ventilation, and air conditioning (HVAC) systems will beinstalled. The purpose of the HVAC systems will be to controlairborne contamination, provide environmental control forinstrumentation and electrical systems, and maintain human comfortin areas of high personnel occupancy.

0 Equipment and services to flush and decontaminate internalcomponents and exterior surfaces of process systems and theprocess building interior surface will be provided to maintainthem in a relatively clean condition.

0 A maintenance area will include equipment necessary to support themaintenance requirements.

0 Waste accumulation areas to these areas will include coveredenclosures with heating and lighting; spill kit(s); separate areasfor hazardous waste, mixed waste, radioactive waste, clean waste(nonhazardous and radioactive), and used petroleum products inaccordance with requirements of WHC-CM-7-5 (WHC 1989b) andWAC 173-303.

79

Page 98: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

o Safety showers and eyewash stations in compliance withrequirements of DOE Order 6430.1A, will be installed.

0 Permanent and/or portable breathing air systems will be providedwhere required to support maintenance activities or recovery frompostulated accident conditions.

0 Separate change room facilities for men and women will beprovided. Separate areas for street clothes and protectiveclothing will be provided. An area equipped with portal monitorsshall be included.

o Sample preparation and storage area with equipment required tomeet sampling requirements will be provided.

o Separate storage areas for clean and dirty laundry, includinglaundry pick-up and delivery areas, will be provided. Storage ofcontaminated clothing will comply with DOE Order 6430.1A.

0 A break and lunchroom area will be included in the facilities.

0 Shower and restroom facilities will be provided.

0 Personnel survey and decontamination areas will be provided.

0 Office space will be provided for operations, maintenance, andother personnel required to support 5 day/week, 2 shifts per dayoperation of the facilities.

0 A control room area (with "clean" access) for remote processsurveillance and control will be provided.

Jo Process instrumentation readouts typically shall be located 4.5feet .above floor level.

0 Storage and janitor closets for-supplies will be provided.

0 Posts, guards and other types of protection needed to preventdamage to equipment, piping, and structures will be installed.

0 Guard rails or other fall protection around all pits, platformsand surfaces where a fall greater than 4 feet could occur will beinstalled.

80

Page 99: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

o A system of cranes and/or hoists (including monorail systems) andequipment for material handling and transport will be installed asnecessary for operation and maintenance.

0 A network of stairways, walkways, and maintenance platforms foraccess to equipment and instrumentation where routine or frequentmaintenance and surveillance inspections will be required.Elevators will be considered for use when frequent and rapidaccess is needed to higher elevations in the facility or wherebulky or heavy items must be moved. The use of ladders shall beminimized.

o Services doors will be installed to enable movement of equipmentto and from facility.

81

Page 100: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SO-CO18H-FDC-OO1 REV 2

This page intentionally left blank.

82

Page 101: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FOC-OO1 REV 2

APPENDIX F

PROPOSED STAFFING PLAN

83

Page 102: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

APPENDIX F

PROPOSED STAFFING PLAN

This appendix presents the proposed staffing plan for the following

three projects:

o 242-A Evaporator Liquid Effluent Retention Facility, Project W-105;

o 200 Area Treated Effluent Disposal Facility (TEDF), Project W-049H;and

o 242-A Evaporator and PUREX Plant Condensate Treatment Facility,Project C-018H.

The Liquid Effluent Retention Facility (Project W-105) will provideinterim storage basins for the 242-A Evaporator process condensate (PC).

The 200 Area TEDF will provide the collection piping and disposalsystems for 13 effluent streams in the 200 Area. New collection piping willtransport the 200 East and West streams to the W-105 retention basins. Thebasins will have covers and primary liners replaced to ensure a cleanbackground for the streams. The effluents collected in the basins will besampled and analyzed prior to release. If clean, the effluent will bedischarge to a new pond provided by Project W-049H. If the effluent is notreleasable, it will be recycled and treated by the equipment installed byProject C-018H.

Project C-018H will provide a treatment system for the 242-A EvaporatorPC and the combined PUREX Plant POD and ASD streams. Beginning in June 1995,the Project C-018H treatment system will also provide the necessary standbytreatment capacity for the 200 Area TEDF (Project W-049H).

The estimate of staffing requirements is based on the followingassumptions:

0 All three projects will be operated by Westinghouse HanfordCompany Waste Management.

o All three projects will located northeast corner of the 200 EastArea and will be incorporated within the 200 East Area securityfence.

0 During the first two years of operation, Project C-018H willoperate 7 day/week, 3 shifts per day.' Total operating efficiency(TOE) for the treatment system will exceed 70%.

85

Page 103: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FDC-OO1 REV 2

This page is intentionally left blank.

84

Page 104: Direct Revision ElJ co - emcbc.doe.gov...SDD/DD C Seismic/Stress Analysis E] rank Calibration Manual ... Safety Equipment List C Cell Arrangement Drawing C3 Process Flow Chart 0

WHC-SD-CO18H-FOC-OO1 REV 2

0 After the first two years of operation, Project C-018H will operateat an estimated TOE of 50%, 3 shifts per day.

o A single control room will be provided for Projects C-018H andW-049H.

The estimated staffing requirements for the three projects are presentedin Table F-i. The total personnel count accommodated by Project C-018H isbased on the long-term operations requirements. Additional personnel requiredfor the start-up and first 2 years of operation will be accommodated byexisting or temporary facilities.

Table F-i. Estimated Staff Requirements.

Staff requirements Staff Locker space andchange area

Operations 28 27Maintenance 32 32Power operators 7. 6Quality assurance 3 3Janitor 1 1Process engineers 2 2Other 8 17

TOTAL 81 88

NOTE: Male/female ratio will assume 60/40 split.Administrative and clean area assumes accommodations forthe physically handicapped.

86