dipole review, 20-21 january 2011 1 dipole design review: outlines of talks gijs de rijk, francois...
DESCRIPTION
Dipole review, January 2011 Draft agenda (day 1) Introduction 9h00I-1) EuCARD-HFM and its context. (GdR) 15’+5’ II) Technical part 9h20II-1) Overview of the dipole (J-M Rifflet) 15’+10’ 9h45II-2) Conductor choice, properties and procurement strategy (L. Oberli) 20’+10’ 10h15Coffee break 15’ 10h30II-3) Conceptual design (A. Milanese) 30’+10’ 11h10II-4) Engineering design (P. Manil) 30’+10’ 11h50II-5) Quench protection (P. Fazilleau) 15’+10’ 12h15Lunch break 1h45’ 14h00II-6) SMC as preparatory project (J-C. Perez) 20’+10' 14h30II-7) Fabrication process study (M. Durante) 30’+10’ 15h10II-8) Winding and tooling tests and insulation choice (F. Rondeaux) 20’+10’ Coffee break 15’ 15h55II-9) Cooling, heat transfer and cool-down issues (S. Pietrowicz ) 20’+10’ 16h25II-10) Insert interfacing (M. Devaux) 10' + 10’ III) Scheduling and project management 16h55III-1) Magnet design and construction schedule (GdR) 20' + 10' 3TRANSCRIPT
![Page 1: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/1.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
1
Dipole design review: outlines of talks
Gijs de Rijk, Francois Kircher and Jean-Michel Rifflet
![Page 2: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/2.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11Dipole design review
• Date: 20-21 January 2011• Place: CEA
• Reviewers:– Giorgio Ambrosio (FNAL)– Lucio Rossi (CERN)– Shlomo Caspi (LBNL)– Akira Yamamoto & Tatsu Nakamoto (KEK)– Yuki Iwasa (MIT)– Pasquale Fabbricatore (INFN Genova)
2
![Page 3: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/3.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11Draft agenda (day 1)
• Introduction 9h00 I-1) EuCARD-HFM and its context. (GdR) 15’+5’
• II) Technical part 9h20 II-1) Overview of the dipole (J-M Rifflet) 15’+10’ 9h45 II-2) Conductor choice, properties and procurement strategy (L. Oberli) 20’+10’10h15 Coffee break 15’10h30 II-3) Conceptual design (A. Milanese) 30’+10’11h10 II-4) Engineering design (P. Manil) 30’+10’11h50 II-5) Quench protection (P. Fazilleau) 15’+10’12h15 Lunch break 1h45’14h00 II-6) SMC as preparatory project (J-C. Perez) 20’+10'14h30 II-7) Fabrication process study (M. Durante) 30’+10’15h10 II-8) Winding and tooling tests and insulation choice (F. Rondeaux) 20’+10’ Coffee break 15’15h55 II-9) Cooling, heat transfer and cool-down issues (S. Pietrowicz ) 20’+10’16h25 II-10) Insert interfacing (M. Devaux) 10' + 10’
•III) Scheduling and project management16h55 III-1) Magnet design and construction schedule (GdR) 20' + 10'
3
![Page 4: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/4.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11I-1) EuCARD-HFM and its context. (GdR) 15’+5’
• EuCARD 11 WPs• NED heritage• HFM: 6 tasks• Task 3 dipole, the need for a Fresca (existant 10 T + HF) cable test
facility, prospecting for future accelerator magnets and HFM technologies
• Task 3 EuCard (only) specification for the dipole• Task 3, budget situation and explication of budget links• Work division between the partners
4
![Page 5: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/5.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
5
II-1) Overview of the dipole (J-M Rifflet) 15’+5’
• The specification (boundaries)• Size considerations: coil, yoke (scaling laws)• Conductor choice
– NED heritage– 1 mm strand in 40 strand cable choice– Maximize current to minimize L (reference to Luc, Philippe)
• History of the design• Basic block coil (Picture 2D baseline)• Shell bladder and key, basic reasons for this
![Page 6: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/6.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
6
II-2) Conductor choice, properties and procurement strategy (L. Oberli) 20’+10’
• 1 mm strand (detailed explanation)– Compromise between 1.25 mm and 0.8 mm– Cable size: 40 strands, reasons
• Available providers, history of strand development• Procurement strategy• Cable design parameters and cabling tests• Prototype strands: first results• Prototype cable: first results ( sample length )• Comparison with models Jc used for the design (plot)
![Page 7: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/7.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
7
II-3) Conceptual design (A. Milanese) 30’+10’
• Magnetic design (parameters, plots)– 2D (some optimisation reasons, mid plane etc)– 3D (max field etc)
• Mechanical design• - Présentation générale de la structure mécanique• - Design mécanique global 2D • o dimensioning of components • o quelques courbes de suivi de certains indicateurs, • Option without tube (20 Febr.)• Life cycle construction and powering• Modèle de calcul mécanique 3D• Global structure
![Page 8: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/8.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
8
II-4) Engineering design (P. Manil) 30’+10’
• Géométrie de la bobine : – Bending test – Saut de couche – Etude géométrique – Longueur de câble
• Présentation de la structure– Points critiques : support des têtes, bladders…
• Detailed engineering– Usinabilité / choix des matériaux : tube, tolérances, surfaces
complexes…
![Page 9: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/9.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
9
II-5) Quench protection (P. Fazilleau) 15’+10’
• Only a feasibility study not yet design decisions• Quench development, current decay, T max, T av, V max• Circuit parameters : dump resistor• Quench heaters : needed ?, test usage• Quench behaviour at 1 T, 5 T, 10 T and 13 T• Gradients T during quench (for later mechanical modeling)• Parameter space
![Page 10: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/10.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
10
II-6) SMC as preparatory project (J-C. Perez) 20’+10'
• Aim of the SMC series• SMC description• SMC program (table with magnets / coils, dates, 7 coils )• SMC1 test results• Lessons learned up to now• SMC3 progress• Future work (SMC4 40st) and aims
![Page 11: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/11.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
11
II-7) Fabrication process study (M. Durante) 30' + 10’
Question: which tooling is needed and what are the critical issues ? • Insulating• Winding• Mould mounting• Reaction• Preparation for impregnation
– Island manipulations– Splicing– Instrumentation sheets– Ground insulation
• Moulding• Mounting the structure• Coil pack mounting• Bladder and key operations
![Page 12: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/12.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
12
II-8) Winding and tooling tests and insulation choice (F. Rondeaux) 20' + 10’
• First winding feasibility test April 2010• Winding tests foreseen• Reaction mould design and tests• Insulation schemes available• Insulation scheme choice process• Moulding material and tests
![Page 13: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/13.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
13
II-9) Cooling, heat transfer and cool-down issues (S. Pietrowicz ) 20' + 10’
• Temperature and heat model of the magnet• Steady state heat deposition at 4.2 K• Steady state heat deposition at 1.9 K• Cooldown scenario• Stresses in the magnet during cooldown
![Page 14: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/14.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
14
II-10) Insert interfacing (M. Devaux) 10' + 5’
• Insert layout• Insert mounting• Field with insert• Quench of insert• Quench of dipole• Risk scenarios
![Page 15: Dipole review, 20-21 January 2011 1 Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet](https://reader036.vdocuments.site/reader036/viewer/2022082510/5a4d1b4e7f8b9ab0599a6643/html5/thumbnails/15.jpg)
Dipo
le re
view
, 20-
21 Ja
nuar
y 20
11
15
III-1) Magnet design and construction schedule (GdR) 20' + 10’
• Task breakdown• Design and construction flowchart with decision points• Design and construction schedule (incl SMC4)• Potential bottlenecks