This is a presentation of SENTECH about their digital tranmsission and signal carrier programmes and services in South Africa. According to the author, the company will be assisting the DTT Project Office in the establishment and provision of support to citizen support on all matters technical, including but not limited to matters related to signal reception and the general increased technical complexity of the home environment . The document shows the progress of SENTECH’s work so far and describes how digitalisation is being achieved on a province by province basis. For example: a) Gauteng is held in Pretoria, Sunnyside, Welverdiend, Pretoria North, Menlo Park, Helderkruin, Johhanesburg, Heidelberg, Linmeyer, Mondeor, Mulbarton, Bez Valley. c) Free State is held in Kroonstad, Suidrand, Bethlehem, Senekal, Boeskamskop, Dewetsdorp, Ficksburg Town, Ladybrand, Petrus Steyn, Springfontein, Witsieshoek, provincial project status per site Limpopo is held in Tzaneen, Dzamba, Gaba, Malamba, Nylstroom, Sibasa, Tolwe, Tsamavudzi. c) Mpumalanga is held in Davel, Carollina, Dullstroom, Mbuzini, Piet Retief, Volksrust, Hetorspruit, Standerton, Lydenburg, Sabie, d) Kwa Zulu Natal (KZN) is held in Verulam, Donnybrook, Pietermaritzburg, Vryheid, Eshowe, Greytown, Mooirivier, Ubombo, Emapangeni, Estcourt, Greytown Dorp, Howick, Kokstad, Ladysmith, Loskop, Louwsberg, Matatiele, Newcastle, Nongoma, Nqutu, Pongola, Qudeni, e) Eastern Cape is held in Aliwal North, Butterworth, Suurberg, Mount Ayliff, King Williams Town, Queenstown, Umtata, Kirkwood, Kareedouw, Port St Johns. f) North West is held in Schweizer Reneke, Christiana, Provincial Project Status Per Site – WC is held in George, Piketberg, Grabouw, Kleinmond, Knysna, Montagu. g) Northern Cape, there are no site form part of the 80%.

TRANSCRIPT

Page 1: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

This document is offered compliments of BSP Media Group. www.bspmediagroup.com

All rights reserved.

Page 2: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

DIGITAL MIGRATION JOURNEY

PRESENTATION TO THE CTO CONFERENCE

13 February 2012

Page 3: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

DTT MIGRATION MAP: SENTECH’s Location: ACTIVITIES

2

DTT Regulations

BDM Policy

Frequency Plan

Channel Licensing

Radio Stations

TV Channels

Service Information

for EPG

Interactive Content

Playout Coding and Multiplexing

Contribution Linking

Transmitter Network

STB Control System

DVB-T2 Standard Approval

Revise MHEG Profile

EPG User Interface

Revise STB Standard

for DVB-T2

Manufacture STBs

Conformance Testing

Trademark Certification

Wholesale Distribution

STB subsidy

Consumer Messaging

Marketing Channels Retail

FTA Platform

Brand

Installations

On-ground support

Go-Live

Award STB RFP

Platform Management

DoC Direct All Broadcasters FTA Broadcasters

SENTECH USAASA SAPO

STB Manufacturers

ICASA

SABS

CPE Installers Retailers All

Customer Contracts

Acknowledgement: SABC

Page 4: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

DTT MIGRATION MAP: SENTECH’s Location: ACTIVITIES

3

DTT Regulations

BDM Policy

Frequency Plan

Channel Licensing

Radio Stations

TV Channels

Service Information

for EPG

Interactive Content

Playout Coding and Multiplexing

Contribution Linking

Transmitter Network

STB Control System

DVB-T2 Standard Approval

Revise MHEG Profile

EPG User Interface

Revise STB Standard

for DVB-T2

Manufacture STBs

Conformance Testing

Trademark Certification

Wholesale Distribution

CPE subsidy

Consumer Messaging

Marketing Channels Retail

FTA Platform

Brand

Installations

On-ground support

Go-Live

Award STB RFP

Platform Management

Activities that SENTECH is directly responsible for

Activities that SENTECH is directly participating in

Activities that SENTECH is indirectly participating in

Customer Contracts

Page 5: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

SENTECH DTT MIGRATION MAP: Internal Activities: DESCRIPTION

4

Content

Contribution Links

Multiplexing

STB Control

SMS

EPG Applications

Satellite Uplink

Satellite Space

Satellite Reception

PIE Transmitter Combiner &

Feeder Cables

Antenna

Civil Mechanical Electrical

Security Monitoring Operational Readiness

SITE x 183

New Upgrade Optimize New/Upgrade New/Upgrade

New

New

New/Upgrade

New

New New Upgrade/New

Upgrade Upgrade

Upgrade

New

Broadcasters’ responsibility

Page 6: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

SENTECH DTT MIGRATION MAP: Internal Activities: STATUS

5

Contribution Links

Multiplexing

STB Control

Satellite Uplink

Satellite Space

Satellite Reception

PIE Transmitter Combiner &

Feeder Cables

Antenna

Civil Mechanical Electrical

Security Monitoring Operational Readiness

SITE x 183

New Upgrade Optimize New/Upgrade New/Upgrade

New

New

New/Upgrade

New

New New Upgrade/New

Upgrade Upgrade

Upgrade

New

On going and under higher levels of risk management

On going and on track

Page 7: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

DIGITAL TERRESTRIAL TELEVISION (DTT): Provincial Rollout for Financial Year 2012/2013

6

Page 8: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

DIGITAL TERRESTRIAL TELEVISION (DTT): Provincial Rollout for Financial Year 2013/2014

7

Page 9: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

CUSTOMER ENGAGEMENTS: Coverage Example: SABC

8

SABC 3 DTT Mux 1 Population Covered 37 580 832 43 970 922

% of Total Population 75.2 87.9 % Change 17%

Geographic Coverage (km²) 377 770 789 020

% of Total RSA Area 29.7 62.1 % Change 109%

Number of sites 104 183

SABC 2 DTT Mux 1 Population Covered 41 268 816 43 970 922

% of Total Population 82.5 87.9 % Change 7%

Geographic Coverage (km²) 742 390 789 020

% of Total RSA Area 58.4 62.1 % Change 6%

Number of sites 179 183

SABC 1 DTT Mux 1 Population Covered 40 711 270 43 970 922

% of Total Population 81.4 87.9 % Change 8%

Geographic Coverage (km²) 581 940 789 020

% of Total RSA Area 45.8 62.1 % Change 36%

Number of sites 146 183

All SABC channels will be transmitted from the same sites, with varying degrees of increases in both population and geographic coverage.

Analogue TV DTT

We are in discussion with the other two commercial broadcasters in finalizing their coverage areas. We do note however that there are some regulatory

issues that have to be dealt with due to the nature of DTT, the manner of the current allocations on the multiplexors and considerations for maximizing the

utilization of spectrum resources (including geographically) and ensuring the continued viability of the investments that are being made by the company in

the distribution network.

Page 10: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

STATUS UPDATE: Citizen Support: Technical

9

Only 4 million of 12 million TV owning households are used to the complex

home environment that will come with digital terrestrial television;

The remaining 8 million households will need support as they get used to the

increased complexity in the homes;

SENTECH has been asked by the DTT Project Office to assist in the

establishment of a contact center that will provide citizen support on all matters

technical, including but not limited to matters related to signal reception and the

general increased technical complexity of the home environment . The work is

at an initial stage but the center should be in production by the time STBs arrive

into the mass market.

The Home DTT Migration

Content support

Logistic support

Technical support

4 FTA channels

1 power cable

1 remote control

1 indoor signal cable

Picture Quality:

Grades A, B or C

20 FTA channels

2 power cables

2 signal cables

2 remote controls

New outdoor aerial

STB : a new device

Picture Quality:

Grades A or Nothing

Images sourced from the Internet. Copyright belongs to respective owners.

Page 11: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

STATUS UPDATE: Towards the September 2012 Technical Launch

10

The soft launch of terrestrial reception can be at any of the

green places shown above. Simultaneously, the soft launch of satellite reception can be at

any of the white places shown above. The core of the SKA area

already does not have coverage and the demonstration/soft

launch can confirm non-interfering reception of the digital

broadcasting services.

DTH Demonstration: SKA Core

DTT Demonstration

Page 12: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

SENTECH SOC Limited

Page 13: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Gauteng

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 12

Sites 1. Pretoria 2. Sunnyside 3. Welverdiend 4. Pretoria North 5. Menlo Park 6. Helderkruin 7. Johannesburg 8. Heidelberg 9. Linmeyer 10. Mondeor 11. Mulbarton 12.  Bez Valley

Page 14: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 13

1. Kroonstad (83%) 100% Building

92% Electrical

96% Mechanical

58% Transmitter

100% Combiner

0% PIE

0% Commissioning (29/11/12)

PIE Prototype delivered. PIE shipped to site 23/12.

73%

Page 15: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 14

2. Suidrand (82%) 100% Building

44% Electrical

96% Mechanical

58% Transmitter

100% Combiner

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 16: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 15

3. Bethlehem (90%) 100% Building

92% Electrical

58% Transmitter

100% Combiner

0% PIE

100% Antenna Replacement

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 17: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 16

4. Senekal (74%) 100% Building

89% Electrical

58% Transmitter

100% Combiner

0% PIE

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 18: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 17

5. Boesmanskop (74%) 100% Building

89% Electrical

58% Transmitter

100% Combiner

0% PIE

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 19: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 18

6. Dewetsdorp (70%) 75% Civils

100% Electrical

0% Combiner

0% Commissioning (14/12/12)

Site Acquisition Awaiting municipality approval. Continuing work at risk PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 20: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 19

7. Ficksburg Town (16%) 100% Building

0% Electrical

17% Mechanical

50% Transmitter

0% Combiner

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 21: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 20

8. Ladybrand (75%) 100% Building

90% Electrical

9% Transmitter

100% Combiner

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 22: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 21

9. Petrus Steyn (82%) 100% Building

88% Electrical

58% Transmitter

100% Combiner

0% PIE

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 23: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 22

10. Springfontein (66%) 100% Building

50% Electrical

78% Mechanical

17% Transmitter

100% Combiner

0% PIE

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 24: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – Free State

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 23

11. Witsieshoek (66%) 100% Building

87% Electrical

22% Mechanical

17% Transmitter

0% Combiner

0% PIE

0% Commissioning (14/12/12)

Site Acquisition Awaiting municipality approval. Continuing work at risk Power Escalation to Eskom in place. Mitigation plan in place with SBG. Impact – Cost. PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

73%

Page 25: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 24

1. Tzaneen (87%) 100% Electrosys

88% Building

100% HVAC

96% Electrical

9% Transmitter

71% Combiner

0% PIE

0% Commissioning (22/01/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

39%

Page 26: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 25

2. Dzamba (51%) 51% STG

88% Electrical

35% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (13/02/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

39%

Page 27: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 26

3. Gaba (18%) 15% Building

37% STG

15% Electrical

11% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Move old equipment

0% Commissioning (29/03/13)

Site Issues Communication issues with local chief resolved. Lessons learnt to be applied to all future sites. Power Escalation to Eskom in place. Mitigation plan in place with SBG. Impact – Cost. PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

Recovery plan in place for lost time due to site issues Mitigation plan for power issues in hand

39%

Page 28: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 27

4. Malamba (44%) 0% Container

60% STG

92% Electrical

0% Mechanical

20% Transmitter

0% Combiner

0% Commissioning (31/01/13)

39%

Page 29: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 28

5. Nylstroom (77%) 55% STG

99% Electrical

100% Mechanical

100% Transmitter

100% Combiner

100% Commissioning (21/01/13)

39%

Page 30: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 29

6. Sibasa (22%) 42% Building

20% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% Move old equipment

0% PIE

0% Commissioning (27/03/13)

Recovery plan in place for lost time due to site issues Mitigation plan for power issues in hand

Site Issues Communication issues with local chief resolved. Lessons learnt to be applied to all future sites. Power Escalation to Eskom in place. Mitigation plan in place with SBG. Impact – Cost. PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

39%

Page 31: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 30

7. Tolwe (15%) 20% Building

24% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% Move old equipment

0% PIE

0% Commissioning (20/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

39%

Page 32: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Limpopo

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 31

8. Tsamavudzi (11%) 10% Building

21% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% Move old equipment

0% PIE

0% Commissioning (29/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

39%

Page 33: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 32

1. Davel (46%) 73% Building

37% Electrical

0% Mechanical

58% STG

0% Transmitter

0% PIE

100% Combiner

0% Sat Dishes

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

22%

Page 34: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 33

2. Carolina (28%) 10% Building

51% Electrical

11% Mechanical

53% STG

0% Transmitter

0% PIE

0% Combiner

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. STG and Electrical Delay in control panels = delay in electrical works. Catch up in January

22%

Page 35: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 34

3. Dullstroom (35%) 100% Building

11% Electrical

53% STG

0% Transmitter

0% PIE

100% Combiner

0% Commissioning (25/01/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

22%

Page 36: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 35

4. Mbuzini (17%) 11% Building

0% Electrical

53% STG

0% Mechanical

0% Transmitter

0% PIE

0% Combiner

0% Commissioning (29/03/13))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

22%

Page 37: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 36

5. Piet Retief (25%) 22% Building

18% Electrical

53% STG

13% Mechanical

0% Transmitter

0% PIE

0% Combiner

0% Commissioning (08/03/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

22%

Page 38: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 37

6. Volksrust (37%) 99% Building

13% Electrical

53% STG

10% Mechanical

0% Transmitter

0% PIE

0% Combiner

0% Commissioning (28/02/13))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. STG and Electrical Delay in control panels = delay in electrical works. Catch up in January

22%

Page 39: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 38

7. Hetorspruit (23%) 99% Building

13% Electrical

53% STG

10% Mechanical

0% Transmitter

0% PIE

0% Combiner

0% Commissioning (28/02/13))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

22%

Page 40: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 39

8. Standerton (1%) 50% Planning

0% Building

0% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (18/02/13))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

22%

Page 41: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 40

9. Lydenburg (0%) 0% Building

0% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (11/02/13))

22%

Page 42: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site - Mpumalanga

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 41

10. Sabie (0%) 0% Building

0% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (11/02/13))

22%

Page 43: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 42

1. Verulam (12%) 100% Electrical

100% Mechanical

100% Antenna

2% Transmitter

100% Combiner

0% Commissioning (06/12/12))

40%

Page 44: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 43

2. Donnybrook (6%) 5% Building

3% Electrical

0% Mechanical

0% Transmitter

100% Combiner

0% PIE

0% Commissioning (06/02/13))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 45: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 44

3. Pietermaritzburg (99%) 100% CMEE

100% VSAT Terminal

100% Building

100% Electrical

100% Mechanical

100% Transmitter

83% Combiner

96% PIE

0% Commissioning (12/12/12))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 46: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 45

4. Vryheid (23%) 2% Building

2% Electrical

100% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (28602/13))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 47: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 46

5. Eshowe (80%) 100% Building

83% Electrical

100% Mechanical

0% Transmitter

100% Combiner

0% PIE

100% Antenna Replacement

0% Commissioning (14/12/12))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 48: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 47

6. Greytown (34%) 6% Building

2% Electrical

100% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (14/12/12))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 49: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 48

7. Mooirivier (20%) 100% Building

2% Electrical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (25/12/12)))

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 50: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 49

8. Ubombo (48%) 100% Building

42% Electrical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (18/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 51: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 50

9. Empangeni (11%) 100% Building

5% Electrical

25% Mechanical

0% Transmitter

0% Combiner

0% Monitoring

0% Commissioning (18/12/12)

40%

Page 52: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 51

10. Estcourt (56%) 100% Building

21% Electrical

100% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (29/01/13)

40%

Page 53: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 52

11. Greytown Dorp (0%) 0% Transmitter

0% Combiner

0% Commissioning (14/12/12)

40%

Page 54: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 53

12. Howick (41%) 100% Building

5% Electrical

100% Mechanical

0% Transmitter

0% Combiner

0% Monitoring

0% Commissioning (05/02/13)

40%

Page 55: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 54

13. Kokstad (42%) 100% Building

5% Electrical

100% Mechanical

0% Transmitter

0% Combiner

0% Monitoring

0% Commissioning (19/02/13)

40%

Page 56: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 55

14. Ladysmith (8%) 100% Building

5% Electrical

14% Mechanical

0% Transmitter

0% Combiner

0% Monitoring

0% Commissioning (23/01/13)

40%

Page 57: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 56

15. Loskop (11%) 100% Building

6% Electrical

16% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (01/02/13)

40%

Page 58: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 57

16. Louwsberg (24%) 100% Building

4% Electrical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (26/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 59: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 58

17. Matatiele (32%) 100% Building

15% Electrical

25% Mechanical

0% Transmitter

0% Combiner

0% Monitoring

0% Commissioning (21/12/12)

40%

Page 60: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 59

18. Newcastle (63%) 100% Building

86% Electrical

82% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (19/02/13)

40%

Page 61: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 60

19. Nongoma (24%) 78% Building

4% Electrical

18% Mechanical

0% Transmitter

0% Combiner

0% Monitoring

0% Commissioning (28/02/13)

40%

Page 62: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 61

20. Nqutu (15%) 21% Building

15% Electrical

3% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (25/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 63: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 62

21. Pongola (15%) 100% Building

21% Electrical

14% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (19/02/13)

40%

Page 64: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – KZN

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 63

22. Qudeni (15%) 21% Building

3% Electrical

15% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (27/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

40%

Page 65: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 64

1. Aliwal North (7%) 100% Planning

0% Building

0% Electrical

53% STG

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (28/02/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 66: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 65

2. Butterworth (8%) 100% Planning

0% Building

0% Electrical

53% STG

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (28/02/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 67: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 66

3. Suurberg (1%) 100% Planning

0% Building

0% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (20/02/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 68: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 67

4. Mount Ayliff (2%) 2% Building

2% Electrical

2% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (28/02/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 69: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 68

5. King Williams Town (1%) 100% Planning

0% Building

0% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (29/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 70: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 69

6. Queenstown (9%) 100% Planning

0% Building

0% Electrical

20% STG

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Feeder & U-Link

0% Commissioning (29/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 71: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 70

7. Umtata (16%) 0% Planning

22% Building

0% Electrical

53% STG

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (26/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 72: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 71

8. Kirkwood (5%) 82% Planning

0% Site Acquisition

0% Building

0% Electrical

53% STG

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (28/02/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. New Site Evaluation of new site proposal curretnly in progress

6%

Page 73: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 72

9. Kareedouw (1%) 100% Planning

0% Building

0% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (29/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 74: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – EC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 73

10. Port St Johns (0%) 0% Planning

0% Building

0% Electrical

0% Mechanical

0% Transmitter

0% Combiner

0% Commissioning (14/02/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

6%

Page 75: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – North West

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 74

1. Schweizer Reneke (84%) 97% Building

98% Electrical

89% STG

97% Mechanical

100% Transmitter

100% Combiner

0% PIE

0% Commissioning (14/12/12)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12

60%

Page 76: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – North West

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 75

2. Christiana (34%) 13% Building

16% Electrical

89% STG

12% Mechanical

0% Transmitter

100% Combiner

0% PIE

0% Commissioning (07/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

60%

Page 77: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – WC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 76

1. George (40%) 100% Electrosys

100% Building

6% Electrical

86% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Commissioning (18/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

54%

Page 78: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – WC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 77

2. Piketberg (38%) 100% Electrosys

14% Building

31% Electrical

37% Mechanical

0% Transmitter

0% Combiner

0% PIE

0% Feeder & U-Link

0% Commissioning (18/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

54%

Page 79: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – WC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 78

3. Grabouw (79%) 100% Antennas

77% Building

58% Electrical

79% Mechanical

0% Transmitter

91% Combiner

99% Linking

0% Commissioning (18/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

54%

Page 80: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – WC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 79

4. Kleinmond (26%) 86% Building

16% Electrical

36% HVAC

0% Transmitter

91% Combiner

0% Linking

0% Commissioning (28/02/13)

54%

Page 81: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – WC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 80

5. Knysna (16%) 1% Electrical

100% Mechanical

32% STG

0% Transmitter

0% Combiner

0% Linking

0% Commissioning (18/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

54%

Page 82: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – WC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 81

6. Montagu (18%) 86% Building

8% Electrical

31% Mechanical

0% Transmitter

0% Combiner

0% Monitoring

0% Commissioning (29/03/13)

PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.

54%

Page 83: DIGITAL MIGRATION JOURNEY IN SOUTH AFRICA

Provincial Project Status Per Site – NC

SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 82

No sites form part of the 80%

0%