BETHLEHEM BAPTIST CHURCH BUILDING PROPOSAL 2019-2023

Upload: others

Post on 23-Apr-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Digital Building Proposal 2019 - Bethlehem Baptist Church

B E T H L E H E M B A P T I S T C H U R C H

BUILDING PROPOSAL

2 0 1 9 - 2 0 2 3

Page 2: Digital Building Proposal 2019 - Bethlehem Baptist Church

WELCOMEIt’s a pleasure to submit to you this booklet outlining future building plans.

We are excited about what God is currently doing in the life of our church, and what He will do in the future. Our ministry to the Tauranga community is one that God continues to trust us with. Growth is a reward for trust. Trust that God has placed in us as a community of people who take Jesus and His mission seriously.

We are moving into a multi-stage building project and it will take prayer and sacrifice. God loves it when His people seek Him about all things. So, as the leadership, we submit these plans to God and to each of you to partner with what we believe will be a very exciting time ahead.

Yours in Christ,

Craig VernallSenior Pastor

We are excited to present this report explaining the alterations that we envision for our church facility.

In 2010, we did a fairly major renovation which created our West Wing and present Auditorium. At that time, we added some needed improvements and upgraded some infrastructure, but stopped short of improving all the amenities that would enhance our facility.

We now feel it necessary and timely to move forward on our prior plans. These plans will be carried out in four stages:

• Stage 1 will expand the Café and expand/upgrade the Office work space.

• Stage 2 will expand our Kid’s Ministry area with a family café, create a new Nurture Room and better space for Kid’s check-in, and expand the Kitchen.

• Stage 3 will include the construction of a new Chapel at the south entrance to our building – a space for prayer, weddings and funerals.

• Stage 4 will include an extension to our current Auditorium.

We will initiate these Stages in order as sufficient funding becomes available for each. Stage 3 and 4 may be reversed in order if needs have changed at that time.

Funding will consist of a combination of: money already in a holding account for future construction, grants from outside entities, and future giving/pledges from our congregation. Our team’s desire is that we will initiate Stage 1 in 2019 or early 2020, and conclude all four Stages within a three to four-year timeframe.

Thank you for your partnership in the Gospel and your commitment to Bethlehem Baptist Church,

Kyle FleischmannExecutive Pastor

BUILDING TEAM REPORT

Page 3: Digital Building Proposal 2019 - Bethlehem Baptist Church

briefBethlehem Baptist Church intends to undertake

alterations of their current building at 90 Bethlehem Road in the following four stages.

stage onecafé space

Each Sunday we have great fellowship in our Café. The Café is also used throughout the week by both in-house ministries (Encore, Serious Coffee, Alpha, etc.) as well as outside groups that hire the space. We have now reached a point at which the Café is often overcrowded – there are not quite enough chairs and tables, and queues for coffee and food fill up quickly. We feel now is a good time to expand the Café space and add a third servery.

We will increase the Café space by utilising the original southern foyer, removing the dividing wall, and replacing the eastern wall with a collapsible wall. We will add another servery station (to increase to 3) to spread out pedestrian flow and line queues. The internal environment aims to be comforting and social, with a variety of contemporary materials, table settings and couches. There will be larger entry/exit points between the foyer and Café to allow for better pedestrian flow between the two spaces.

The new servery station will be like a pod, situated between the Café space and the upgraded Office space. It will have the ability to be entirely shut-down or opened to either side, so that it can serve both situations either simultaneously or one at a time. The servery will contain a coffee machine, sinks, dishwasher, refrigeration equipment, etc.

8125

360

6000

6000

6000

18000

1800090009000

990

6

9

3

4

A C

7

8

B

UP

13.1.11

23.1.11

3.0.10

2

3.0.11 2

NEW ATRIUM

ENLARGE & UPGRADE KITCHEN

UPGRADE SOCIAL SPACE / CAFE

NEW SERVERYCAFE

EXISTINGAUDITORIUM

FOYER

NEW OFFICE + SOCIAL SPACE

NEW DECK & COURT

NEW ADDITIONMAIN ENTRY

NEW CHAPEL

NEW

ROL

LER

+ BE

AM

NEW

SER

VERY

NEW

ROL

LER

+ BE

AMNE

W R

OLLE

R +

BEAM

NEW ROLLER + BEAM NEW ROLLER + BEAM

NEW SERVERY OPENING

NEW SLIDING DOOR

NEW EXIT

NEW COVERED OUTDOOR AREA & DECK

UPGRADE WC BLOCK

NEW RECEPTION

DESK

NEWSLIDING DOOR

NEW SLIDING GATE

NEWSLIDING

GATE

NEW

SLID

ING

DOOR

OFFICE 2

OFFICE 1

OFFICE 3

OFFICE 4

EXISTING MULTI PURPOSE HALL

NEW EXIT

EXIST EXIT

EXTENSION TO EXISTING MEZZANINE BALCONY / SUPPORT - TBC

NEW POST

NEW POST

NEW POST

NEW POST

PATH

PATH

UPGRADE LANDSCAPE AREA

NEW PARKING FOR HEARSE

UNISEX + ACC WC WITH SHOWER

NEW EXIT

NEW COLUMN NEW COLUMN

NEW EXIT

NEW B O H

DROPPED KURB

NEWDECK

1800 HIGH SCREEN WALL

EXIST TREE

NEW ADDITION

NEW DOORNEW WC

REMOVE EXIST DOOR, WINDOWS AND WALL

REMO

VE E

XIST

DO

ORS

AND

WAL

L

NEW DOOR

NEW DOOR

EXIST.STORE

EXIS

T. W

C BL

OCK

EXIST. STAIRS

EXIST. STAIRS

EXIST. CHILDREN AREA

EXIST. STORAGE

EXIST. MOTHERS ROOM

EXIST. STAIRS

INSTALL NEW HEAT PUMP

NEW DOOR

COVERED AREA

EXIST. CAR PARK

EXIST. CAR PARK

RE-LOCATE EXIST. SHADE CANOPY AND PLAY AREA

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NORTH

EXIST. WC BLOCK

NEW DECK

NEW DECK

NEW

SER

VERY

OPE

NING

UPGRADE WC

NEW WC

EXIS

T. S

ERVE

RY O

PENI

NG

EXIST. STORAGE

MAIN DB

EXIST. CURTAINTRACK

OVER EXIS

T.CU

RTAI

NTR

ACK

OVER

EXIST. SOUND BOOTH

NEW DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

FIXED GLASS

STORE UNDER

& BABY CHANGING AREA

NOTE:PRELIM DESIGN TO BE REVIEWED BY FIRE & STRUCTURAL ENGINEER

STORE UNDER

EXIST.PLAY AREA

EXIST.PLAY AREA

LAYOUT TBC

FIXED GLASS

GARDEN

GARD

EN

NEW ROLLER + BEAM

NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

CHILDREN CHECK IN AREA

MOTHER'S ROOM

OFFICE 5

OFFICE 6

OFFICE 7

OFFICE 8

OFFICE 9STAGE 1 - OFFICES

STAGE SCHEDULE

STAGE 2 - NEW ATRIUM, KITCHEN, MOTHER'S ROOM, UPGRADE AND ABLUTIONS

STAGE 3 - CHAPEL

STAGE 4 - FUTURE ADDITION TO AUDITORIUM

This design and drawing is the copyright of First Principles Architects Limited and is not to be reproduced without written permission ©

Project:

Address: Scale:

Drawing:Date:Checked By:Drawn By:

Sheet No: Revision:Project No.+64 7 574 6728, po box 14214,

tauranga MC 3143, new zealand

General notes:1. Do not scale off drawings.2. Contractor shall varify and be responsible for all dimensions on site.3. Architects to be notified of any variation between the site dimensions and those on plans.

@ A1Asindicated

90 Bethlehem Rd, Bethlehem,Tauranga 3110

PROPOSED STAGES

2.1.12

03/20/19

BAP.01

KL Checker

PRELIM DESIGN

BETHLEHEM BAPTIST CHURCH

REVISIONS

1 : 1001

PROPOSED GROUND FLOOR PLANPHASES

Page 4: Digital Building Proposal 2019 - Bethlehem Baptist Church

office space

We have a lot of staff that do a lot of great work. Twenty-six of our 36 staff use our ground floor Office space on a weekly basis. For quite a while now, this space has been inadequate – it’s cramped, it is affected greatly by the extremes of summer and winter, and there is no room for growth. We need a functional office space that allows for efficiency and collaboration so that our staff can serve our community in a greater capacity.

We will increase the Office space by increasing overall square meters and removing internal walls to create more of an open plan working environment. The space will cater for a variety of working situations from singular workstations to large meetings. The working space will be functional and built to today’s standards, making use of passive ventilation open space heating and air conditioning as well as smart eco lighting systems. Variable acoustic environments which allow for versatile meeting spaces, one-on-one catchup’s and single working pods will be key to creating a working space that everyone can use. Individual workstations will be hi/lo desks so that staff can sit or stand while working.

The space will include an enclosed conference room, two private meeting rooms for pastoral care, and several enclosed offices for our pastors and full-time staff. The working space will have direct access to the new servery for self-catering so that disruption of large gatherings in the main Café are avoided. This area will be adaptable so that it can function as part of the office Monday through Friday and additional Café overflow on Sundays. The furniture in this shared Café/Office space will be a combination of soft chairs, couches, and low tables to provide a welcoming social environment.

The reception desk will move near the main entrance and convert to a ‘welcome desk’ on Sundays. Roll up doors will give us the ability to separate the Café and foyer if needed during the week.

8125

360

6000

6000

6000

18000

1800090009000

990

6

9

3

4

A C

7

8

B

UP

13.1.11

23.1.11

3.0.10

2

3.0.11 2

NEW ATRIUM

ENLARGE & UPGRADE KITCHEN

UPGRADE SOCIAL SPACE / CAFE

NEW SERVERYCAFE

EXISTINGAUDITORIUM

FOYER

NEW OFFICE + SOCIAL SPACE

NEW DECK & COURT

NEW ADDITIONMAIN ENTRY

NEW CHAPEL

NEW

ROL

LER

+ BE

AM

NEW

SER

VERY

NEW

ROL

LER

+ BE

AMNE

W R

OLLE

R +

BEAM

NEW ROLLER + BEAM NEW ROLLER + BEAM

NEW SERVERY OPENING

NEW SLIDING DOOR

NEW EXIT

NEW COVERED OUTDOOR AREA & DECK

UPGRADE WC BLOCK

NEW RECEPTION

DESK

NEWSLIDING DOOR

NEW SLIDING GATE

NEWSLIDING

GATE

NEW

SLID

ING

DOOR

OFFICE 2

OFFICE 1

OFFICE 3

OFFICE 4

EXISTING MULTI PURPOSE HALL

NEW EXIT

EXIST EXIT

EXTENSION TO EXISTING MEZZANINE BALCONY / SUPPORT - TBC

NEW POST

NEW POST

NEW POST

NEW POST

PATH

PATH

UPGRADE LANDSCAPE AREA

NEW PARKING FOR HEARSE

UNISEX + ACC WC WITH SHOWER

NEW EXIT

NEW COLUMN NEW COLUMN

NEW EXIT

NEW B O H

DROPPED KURB

NEWDECK

1800 HIGH SCREEN WALL

EXIST TREE

NEW ADDITION

NEW DOORNEW WC

REMOVE EXIST DOOR, WINDOWS AND WALL

REMO

VE E

XIST

DO

ORS

AND

WAL

L

NEW DOOR

NEW DOOR

EXIST.STORE

EXIS

T. W

C BL

OCK

EXIST. STAIRS

EXIST. STAIRS

EXIST. CHILDREN AREA

EXIST. STORAGE

EXIST. MOTHERS ROOM

EXIST. STAIRS

INSTALL NEW HEAT PUMP

NEW DOOR

COVERED AREA

EXIST. CAR PARK

EXIST. CAR PARK

RE-LOCATE EXIST. SHADE CANOPY AND PLAY AREA

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NORTH

EXIST. WC BLOCK

NEW DECK

NEW DECK

NEW

SER

VERY

OPE

NING

UPGRADE WC

NEW WC

EXIS

T. S

ERVE

RY O

PENI

NG

EXIST. STORAGE

MAIN DB

EXIST. CURTAINTRACK

OVER EXIS

T.CU

RTAI

NTR

ACK

OVER

EXIST. SOUND BOOTH

NEW DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

FIXED GLASS

STORE UNDER

& BABY CHANGING AREA

NOTE:PRELIM DESIGN TO BE REVIEWED BY FIRE & STRUCTURAL ENGINEER

STORE UNDER

EXIST.PLAY AREA

EXIST.PLAY AREA

LAYOUT TBC

FIXED GLASS

GARDEN

GARD

EN

NEW ROLLER + BEAM

NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

CHILDREN CHECK IN AREA

MOTHER'S ROOM

OFFICE 5

OFFICE 6

OFFICE 7

OFFICE 8

OFFICE 9STAGE 1 - OFFICES

STAGE SCHEDULE

STAGE 2 - NEW ATRIUM, KITCHEN, MOTHER'S ROOM, UPGRADE AND ABLUTIONS

STAGE 3 - CHAPEL

STAGE 4 - FUTURE ADDITION TO AUDITORIUM

This design and drawing is the copyright of First Principles Architects Limited and is not to be reproduced without written permission ©

Project:

Address: Scale:

Drawing:Date:Checked By:Drawn By:

Sheet No: Revision:Project No.+64 7 574 6728, po box 14214,

tauranga MC 3143, new zealand

General notes:1. Do not scale off drawings.2. Contractor shall varify and be responsible for all dimensions on site.3. Architects to be notified of any variation between the site dimensions and those on plans.

@ A1Asindicated

90 Bethlehem Rd, Bethlehem,Tauranga 3110

PROPOSED STAGES

2.1.12

03/20/19

BAP.01

KL Checker

PRELIM DESIGN

BETHLEHEM BAPTIST CHURCH

REVISIONS

1 : 1001

PROPOSED GROUND FLOOR PLANPHASES

Page 5: Digital Building Proposal 2019 - Bethlehem Baptist Church

stage twokid’s space

Our Kid’s Ministry is thriving, and this Stage will utilise the current courtyard to add a lot of space. The new space will create a robust family-friendly social environment. It will have an atrium, open feel with sections being double-floor height, taking advantage of the northern light through large glazed windows. The theme will be fresh and lively, creating a place where children and parents are free to relax.

It will have its own coffee servery and be furnished with robust outdoor style hard furniture, kid and family friendly. We will create a new area for Kid’s Check-in that is bigger and more efficient, reducing the bottleneck when people enter and exit between services.

This space will have a new Nurture Room for mums, adjoining the main auditorium so they can connect visually with the service and also be close to the family café. This will allow us to re-purpose the current nurture room for additional Kid’s breakout space.

kitchen space

Our current Kitchen is adequate and is utilised heavily, however, with the plans for this Stage we will enlarge the Kitchen a bit and unite it with the main servery in the Café. This will allow for a more efficient flow from preparation in the Kitchen to serving people in the Café. The additional space will also allow more room for food preparation and storage.

As part of this alteration, the men’s and women’s toilets near the Kitchen will be restructured and upgraded as well.

8125

360

6000

6000

6000

18000

1800090009000

990

6

9

3

4

A C

7

8

B

UP

13.1.11

23.1.11

3.0.10

2

3.0.11 2

NEW ATRIUM

ENLARGE & UPGRADE KITCHEN

UPGRADE SOCIAL SPACE / CAFE

NEW SERVERYCAFE

EXISTINGAUDITORIUM

FOYER

NEW OFFICE + SOCIAL SPACE

NEW DECK & COURT

NEW ADDITIONMAIN ENTRY

NEW CHAPEL

NEW

ROL

LER

+ BE

AM

NEW

SER

VERY

NEW

ROL

LER

+ BE

AMNE

W R

OLLE

R +

BEAM

NEW ROLLER + BEAM NEW ROLLER + BEAM

NEW SERVERY OPENING

NEW SLIDING DOOR

NEW EXIT

NEW COVERED OUTDOOR AREA & DECK

UPGRADE WC BLOCK

NEW RECEPTION

DESK

NEWSLIDING DOOR

NEW SLIDING GATE

NEWSLIDING

GATE

NEW

SLID

ING

DOOR

OFFICE 2

OFFICE 1

OFFICE 3

OFFICE 4

EXISTING MULTI PURPOSE HALL

NEW EXIT

EXIST EXIT

EXTENSION TO EXISTING MEZZANINE BALCONY / SUPPORT - TBC

NEW POST

NEW POST

NEW POST

NEW POST

PATH

PATH

UPGRADE LANDSCAPE AREA

NEW PARKING FOR HEARSE

UNISEX + ACC WC WITH SHOWER

NEW EXIT

NEW COLUMN NEW COLUMN

NEW EXIT

NEW B O H

DROPPED KURB

NEWDECK

1800 HIGH SCREEN WALL

EXIST TREE

NEW ADDITION

NEW DOORNEW WC

REMOVE EXIST DOOR, WINDOWS AND WALL

REMO

VE E

XIST

DO

ORS

AND

WAL

L

NEW DOOR

NEW DOOR

EXIST.STORE

EXIS

T. W

C BL

OCK

EXIST. STAIRS

EXIST. STAIRS

EXIST. CHILDREN AREA

EXIST. STORAGE

EXIST. MOTHERS ROOM

EXIST. STAIRS

INSTALL NEW HEAT PUMP

NEW DOOR

COVERED AREA

EXIST. CAR PARK

EXIST. CAR PARK

RE-LOCATE EXIST. SHADE CANOPY AND PLAY AREA

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NORTH

EXIST. WC BLOCK

NEW DECK

NEW DECK

NEW

SER

VERY

OPE

NING

UPGRADE WC

NEW WC

EXIS

T. S

ERVE

RY O

PENI

NG

EXIST. STORAGE

MAIN DB

EXIST. CURTAINTRACK

OVER EXIS

T.CU

RTAI

NTR

ACK

OVER

EXIST. SOUND BOOTH

NEW DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

FIXED GLASS

STORE UNDER

& BABY CHANGING AREA

NOTE:PRELIM DESIGN TO BE REVIEWED BY FIRE & STRUCTURAL ENGINEER

STORE UNDER

EXIST.PLAY AREA

EXIST.PLAY AREA

LAYOUT TBC

FIXED GLASS

GARDEN

GARD

EN

NEW ROLLER + BEAM

NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

CHILDREN CHECK IN AREA

MOTHER'S ROOM

OFFICE 5

OFFICE 6

OFFICE 7

OFFICE 8

OFFICE 9STAGE 1 - OFFICES

STAGE SCHEDULE

STAGE 2 - NEW ATRIUM, KITCHEN, MOTHER'S ROOM, UPGRADE AND ABLUTIONS

STAGE 3 - CHAPEL

STAGE 4 - FUTURE ADDITION TO AUDITORIUM

This design and drawing is the copyright of First Principles Architects Limited and is not to be reproduced without written permission ©

Project:

Address: Scale:

Drawing:Date:Checked By:Drawn By:

Sheet No: Revision:Project No.+64 7 574 6728, po box 14214,

tauranga MC 3143, new zealand

General notes:1. Do not scale off drawings.2. Contractor shall varify and be responsible for all dimensions on site.3. Architects to be notified of any variation between the site dimensions and those on plans.

@ A1Asindicated

90 Bethlehem Rd, Bethlehem,Tauranga 3110

PROPOSED STAGES

2.1.12

03/20/19

BAP.01

KL Checker

PRELIM DESIGN

BETHLEHEM BAPTIST CHURCH

REVISIONS

1 : 1001

PROPOSED GROUND FLOOR PLANPHASES

Page 6: Digital Building Proposal 2019 - Bethlehem Baptist Church

stage threechapel

The Chapel will be connected to the Café on the south side, and be utilised for prayer, weddings, funerals and small events. It will have its own small internal foyer and will seat approximately 90 people. The new structure will utilise the current entry portico for its roof and ceiling – walls will be added and we will keep the trusses and supporting beams of the portico exposed.

It will be contemporary in material selections, however, treating it conservatively with a strong link to traditional chapel interior spaces. Windows shall provide a visual link to the outside landscaping and allow natural light admittance throughout the day. It will be reflective of the Bethlehem community and wider Tauranga/Bay of Plenty region so that it can be a real community asset.

stage fourauditorium

We have prior consent to extend the current Auditorium towards the north property line. With a growing congregation, this will allow enough space to grow into for years to come, not only for our Sunday services but for events that occur throughout the year. Our own ministries in addition to dozens of outside organizations use this space.

This extension will push the stage and side-stage areas back several meters allowing for 6-8 more rows of chairs to be added. It will also increase the side-stage areas for more storage and additional space for people to wait off stage.

8125

360

6000

6000

6000

18000

1800090009000

990

6

9

3

4

A C

7

8

B

UP

13.1.11

23.1.11

3.0.10

2

3.0.11 2

NEW ATRIUM

ENLARGE & UPGRADE KITCHEN

UPGRADE SOCIAL SPACE / CAFE

NEW SERVERYCAFE

EXISTINGAUDITORIUM

FOYER

NEW OFFICE + SOCIAL SPACE

NEW DECK & COURT

NEW ADDITIONMAIN ENTRY

NEW CHAPEL

NEW

ROL

LER

+ BE

AM

NEW

SER

VERY

NEW

ROL

LER

+ BE

AMNE

W R

OLLE

R +

BEAM

NEW ROLLER + BEAM NEW ROLLER + BEAM

NEW SERVERY OPENING

NEW SLIDING DOOR

NEW EXIT

NEW COVERED OUTDOOR AREA & DECK

UPGRADE WC BLOCK

NEW RECEPTION

DESK

NEWSLIDING DOOR

NEW SLIDING GATE

NEWSLIDING

GATE

NEW

SLID

ING

DOOR

OFFICE 2

OFFICE 1

OFFICE 3

OFFICE 4

EXISTING MULTI PURPOSE HALL

NEW EXIT

EXIST EXIT

EXTENSION TO EXISTING MEZZANINE BALCONY / SUPPORT - TBC

NEW POST

NEW POST

NEW POST

NEW POST

PATH

PATH

UPGRADE LANDSCAPE AREA

NEW PARKING FOR HEARSE

UNISEX + ACC WC WITH SHOWER

NEW EXIT

NEW COLUMN NEW COLUMN

NEW EXIT

NEW B O H

DROPPED KURB

NEWDECK

1800 HIGH SCREEN WALL

EXIST TREE

NEW ADDITION

NEW DOORNEW WC

REMOVE EXIST DOOR, WINDOWS AND WALL

REMO

VE E

XIST

DO

ORS

AND

WAL

L

NEW DOOR

NEW DOOR

EXIST.STORE

EXIS

T. W

C BL

OCK

EXIST. STAIRS

EXIST. STAIRS

EXIST. CHILDREN AREA

EXIST. STORAGE

EXIST. MOTHERS ROOM

EXIST. STAIRS

INSTALL NEW HEAT PUMP

NEW DOOR

COVERED AREA

EXIST. CAR PARK

EXIST. CAR PARK

RE-LOCATE EXIST. SHADE CANOPY AND PLAY AREA

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NEW DOOR

NORTH

EXIST. WC BLOCK

NEW DECK

NEW DECK

NEW

SER

VERY

OPE

NING

UPGRADE WC

NEW WC

EXIS

T. S

ERVE

RY O

PENI

NG

EXIST. STORAGE

MAIN DB

EXIST. CURTAINTRACK

OVER EXIS

T.CU

RTAI

NTR

ACK

OVER

EXIST. SOUND BOOTH

NEW DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

FIXED GLASS

STORE UNDER

& BABY CHANGING AREA

NOTE:PRELIM DESIGN TO BE REVIEWED BY FIRE & STRUCTURAL ENGINEER

STORE UNDER

EXIST.PLAY AREA

EXIST.PLAY AREA

LAYOUT TBC

FIXED GLASS

GARDEN

GARD

EN

NEW ROLLER + BEAM

NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR NEW SLIDING DOOR

NEW SLIDING DOOR

NEW SLIDING DOOR

EXIST. STRUCTURE TO BE REVIEWED BY ENGINEER

CHILDREN CHECK IN AREA

MOTHER'S ROOM

OFFICE 5

OFFICE 6

OFFICE 7

OFFICE 8

OFFICE 9STAGE 1 - OFFICES

STAGE SCHEDULE

STAGE 2 - NEW ATRIUM, KITCHEN, MOTHER'S ROOM, UPGRADE AND ABLUTIONS

STAGE 3 - CHAPEL

STAGE 4 - FUTURE ADDITION TO AUDITORIUM

This design and drawing is the copyright of First Principles Architects Limited and is not to be reproduced without written permission ©

Project:

Address: Scale:

Drawing:Date:Checked By:Drawn By:

Sheet No: Revision:Project No.+64 7 574 6728, po box 14214,

tauranga MC 3143, new zealand

General notes:1. Do not scale off drawings.2. Contractor shall varify and be responsible for all dimensions on site.3. Architects to be notified of any variation between the site dimensions and those on plans.

@ A1Asindicated

90 Bethlehem Rd, Bethlehem,Tauranga 3110

PROPOSED STAGES

2.1.12

03/20/19

BAP.01

KL Checker

PRELIM DESIGN

BETHLEHEM BAPTIST CHURCH

REVISIONS

1 : 1001

PROPOSED GROUND FLOOR PLANPHASES

Page 7: Digital Building Proposal 2019 - Bethlehem Baptist Church

budget estimate2 May 2019

Note: These figures are for budget purposes only, and are indicative based on limited information available.

Stage 1: Café and Office Spaces $1,252,819

Stage 2: Kid’s Space and Kitchen $992,261

Stage 3: Chapel $393,761

Stage 4: Auditorium $743,805

TOTAL $3,382,646

funding for projectBuilding Fund Balance $503,000

Estimated Grants $1,500,000

Giving/Pledges $1,380,000

TOTAL $3,383,000 15%

pledgeometertogether with faith we’ll achieve this goal

Page 8: Digital Building Proposal 2019 - Bethlehem Baptist Church

how you can partnerFirst and foremost, be in prayer over this entire project – for the planning, the communication, the finances, the build time, and for the final product.

You can partner through giving – either a one-time financial gift, or by completing a pledge card to make payments over the next 12, 24, 36, or 48 months.

The total amount may seem overwhelming, but if we break up this amount to a weekly amount for each of us it totals just over one large coffee or hot chocolate per week – right around $30 per month. This becomes very achievable if we each sacrifice just a bit.

Another consideration is the benefit from filing your charitable donations and re-donating those amounts. The government gives us 33% back on all donations, so it is the gift that keeps giving. An exercise on a donation of $1000 per year plus the charitable payback equates to $5240 over 4 years – $1240 more than the $4000 out of pocket.

Pledge cards are included with this booklet for you to complete.

For one-time or recurring gifts, give to:BBC Westpac Building Bank Account03-0445-0173975-002Particulars: Your giving number or surnameReference: Building

submit feedback

If you have any questions or comments on this building plan, please feel free to email the building team at: [email protected]. We would love to hear from you.