diagnostic approach towards structural repairs of damaged buildings
DESCRIPTION
Diagnostic Approach Towards Structural Repairs of Damaged Buildings and case studiesTRANSCRIPT
Diagnostics approach towards
Structural repairsStructural repairs
Typical issues in RCC structures
- Corrosion- Cracking- Spalling of concreteSpalling of concrete- Leakage / seepageBulging of concrete- Bulging of concrete
- Deflection of structural members, etc.,
CRACKS indicate the beginning ofCRACKS indicate the beginning of deterioration in most cases
LEAKAGE
Can be very ugly and dangerous
SPALLINGS G
Result of neglected leakage & cracks for long time
Factors that lead to ProblemsFactors that lead to Problems Built in problems (Internal)
External Causes
Man made causes
Natural calamitiesNatural calamities
Internal CauseInternal Cause
Design issuesDesign issues Improper selection of materials
Wrong waterproofing specifications
Faulty construction methods
E t l CExternal CauseEnvironmental attack
Chlorides
Carbon dioxide
S l h tSulphates
HumidityHumidity
Man made causesChange in use of structures
Over loading
Unplanned modifications /alterationsUnplanned modifications /alterations
Poor maintenance
N t l l itiNatural calamitiesEarthquake q
Flood
Fire
C lCyclones
Typical Causes:Corrosion of rebar- Chemically active soilPollution- Pollution
- Industrial abuse (chemicals)
- High relative humidity- Environmental attack
Chloride & Co2 induced
Cracks due to corrosion …
A major problemj p
Protection reduced
Concrete becomes porous
E f CO &Entry of CO2 &
Chlorides & moisture
Co2 induced corrosion
Chloride induced corrosion
Approach to systematic repairsInspection – most important activity
must be done by a professional- Every structure requires different approach.
E.g. building structure, industrial str, jetty, li t i t k h d cooling towers, intake pump houses, dams,
bridges, etc.,All locations of distress should be noted- All locations of distress should be noted
- Original drawings, if available, should be referredreferred
Approach to systematic repairs
Cause and need identification:-What is main cause?-Why repairs?-What is the life expectancy?-What is the importance of structure?-Is the need only to patch repairs? Or any other
Unless the cause is identified and Unless the cause is identified and removed, repairs can not be
effective & complete.
Approach to repairs must beApproach to repairs must bedifferent for different structures
– River Pump House
– Jetty
– Industrial Building
NEED??- Life extension- Strengthening g g
- Increase in loads- Seismic
i- Restoration to original design values
- Protection
Diagnosis:Diagnosis:(Visual inspection + Diagnosis)
Comparison Structural engineer = Doctor
Pathological tests = NDTPathological tests = NDT
Diagnosis:NDTs are effective tools todetermine the health of concrete
TO ASSESS PERFORMANCE TO ASSESS PERFORMANCE LEVEL DURING SERVICE LEVEL DURING SERVICE LIFELIFE
PARAMETERS TO BE EVALUATEDPARAMETERS TO BE EVALUATEDa) STRENGTH (IN-SITU)b) DURABILITY PERFORMANCE
presence of internal voids/ cracks, materials likely to cause disruption
of concrete (sulphate or alkali reactive aggregates), extent or risk of reinf. aggregates), extent or risk of reinf. corrosion, chloride content, cover thickness, permeability etc.
NDT:Common NDTs areCommon NDTs are
1. Rebound hammer test2. USPV3. Half cell potential meter
Rebar locator4. Rebar locator5. Core test6. Thickness test7. Carbonation test8. Chemical analysis
NDT:Rebound hammertest- To know strength of
concrete / surface hardness
Aah….
- Range: 10 to 70 N / sqmmGuidelines: IS : 13311– Guidelines: IS : 13311 (Part 2) : 1992 & Bs 1881 : Part 202 : 19861986.
NDT:Ultrasonic Pulse Velocity Ultrasonic Pulse Velocity
Test- To know strength of concrete
P t ti R 10 t 5 - Penetration Range: 10mm to 5 m
– Guidelines: IS : 13311 (Part 1) : 1992 & BS 1881 P t 203 1986BS 1881 : Part 203 : 1986.
Ultrasonic Pulse Velocity by Cross probing (Km/Sec) Concrete quality gradingquality grading
1. Above 4.5 Excellent2. 3.5 to 4.5 Good3 3 0 to 3 5 Medium3. 3.0 to 3.5 Medium4. Below 3.0 Doubtful
NDT: Core Test - To know strength
of concrete - Core dia Range:
25 mm to 125 mm-
– Guidelines: Clause 4.8 of BS 1881; 4.8 of BS 1881; Part 120: 1983 for flatness & parallelismparallelism
NDT: Core Test
AFTER DRESSING,CAPING & CURING :THE CORE IS TESTEDIN COMPRESSIONTESTING MACHINE
NDT:Strength analysis- Based on the results of Rebound hammer,
USPV d C t t th i USPV and Core tests, the average compressive strength for concrete shall be considered.
NDT:Chemical analysisChemical analysisChloride Content:
Whenever there is chloride in concrete there is increasedrisk of corrosion of embedded metal. The higher thechloride content, or if subsequently exposed to warm moistconditions, the greater the risk of corrosion.As per IS : 456:2000, the maximum total acid solublehl id t t d K / 3 f t h ld bchloride content expressed as Kg/m3 of concrete should be
0.6 for reinforced concrete
Sulphate Content:Sulphate Content:The excessive amount of water soluble sulphates cancause expansion or disruption of concrete. The total watersoluble sulphate content of the concrete mix, expressed asp , pSO3, should not exceed 4 per cent by mass of cement inthe mix.
NDT:Chemical analysis contd..
pH of concrete sample:pH of concrete sample:The Ph of freshly prepared concrete is around12 and hence it is highly alkaline in nature.Carbonation of concrete by attack fromatmospheric carbon dioxide will result inreduction in alkalinity of the concrete, andincrease the risk of reinforcement corrosion.
NDT:Half cell Potential Meter: for corrosion
Reference Code : ASTM C –876Reference Code : ASTM C –876
Objective :To find out the probability of corrosion of steel inside concrete.
NDT:Half cell Potential Meter: GuidelinesHalf cell Potential Meter: Guidelines
HALF-CELL POTENTIAL(mV) PERCENTAGE CHANCE RELATIVE TO
COPPER/COPPER SULPHATE REFERENCE ELECTRODE
OF ACTIVE CORROSION
< -350 90%
-200 TO –350 50%
> -200 10%
NDT:b iCarbonation Test:
To find out the alkalinity of concrete
If pH is more than 10, concrete p ,turns pink when sprayed with phenolphthalein solution.
Part 2
Repair materials & techniquesCase studies Case studies.
Repairs specifications
- Based on visual inspection- NDT result- NDT result- Need - Life of repair expected Life of repair expected - Selection & evaluation of repair
materials- Budget - Limitations
Repair materials must offer …..
– Compatibility With Old Concrete– Excellent Bonding Properties Excellent Bonding Properties – Low Shrinkage– Good Strength– Dimension Stability– Crack Resistance
I bilit– Impermeability– Ease of Application– DurabilityDurability
All repair scheme must includeAll repair scheme must include
– Holistic job specificationsHolistic job specifications– Compatible materials– Cause identification & eliminationCause identification & elimination– Protective coatings– Corrosion control mechanism, ,
wherever possible – Post NDT
Common repair materials available
Rust removersBonding agents
•Latex, SBR and AcrylicEpo esin based•Epoxy resin based
Injection grouts •Cement•Cement•Low viscous epoxy•PU
Zinc rich epoxy primers for re bar
Common repair materials availableCommon repair materials available
Hand applied polymer mortars•Site modified•Ready to use 2 component•Ready to use single component high build•Ready to use single component, high build
Hand applied epoxy & polyester resin pp p y p ymortars
Fl bl lf ti i t Flowable self compacting micro concrete •Low strength to high strength
Common repair materials availableCommon repair materials available
High strength polyester resin anchor groutsg g p y gUnder water range (cement & epoxy based)Glass and Carbon fibre wrapping systemsProtective coatings• Silane Siloxane based• Solvented acrylic based• Solvented acrylic based• Water based acrylics• Aliphatic PU basedp• Aliphatic epoxy based
Repair techniques
Repairs using injections and Polymer mortarsNormal concrete jacketing Micro concrete jacketingMicro concrete jacketingFibre wrapping – glass, carbon & Aramid Carbon strips – normal, pre-stressedCarbon strips normal, pre stressedSteel plate bonding Anchor stitching E- chem repairs (sacrificial anodes)
Repair Techniques – Polymer Mortar Application
Polymer Modified Mortar is available in two types –• Site MixedSite Mixed• Pre-mixed (Single Part)
PMM i d d i h d li d PMM is very dense and is hand applied
Proper bond coat shall be used for the application Proper bond coat shall be used for the application of PMM
Repair Techniques – Polymer Mortar Application
Repair Techniques – Micro Concrete
Micro concrete is free flow, self compacting, high strength high strength
Available as pre mixed, ready to useAvailable as pre mixed, ready to use
Can be used with addition of aggregates also
Microconcrete is used for the jacketing of Microconcrete is used for the jacketing of Columns & Beams
Repair Techniques – Micro Concrete
Repair Techniques – Micro Concrete
Repair techniques – Injection Grouting
Different types of Injections are available• Cement with non shrink additive Cement with non shrink additive • Epoxy• PU
Type of material to be injected depends on the porosity and the strength requiredporosity and the strength required
Repair techniques – Injection Grouting
Repair techniques – Fibre Wrapping
Diff t t f Fib W i il blDifferent types of Fibre Wrappings are available• E- Glass Fibres• Carbon Fibres • Aramid Fibres
These fibres are available in diff. unit weights• Glass Fibres in 600 & 900 GSM• Carbon Fibres in 230 to 430 GSM
Fibres are used for the strengthening of structural members like Columns & beams
Selection of material depends on the strength requiredApplication of fibres is wet-on-wet lay up or dry-on-dry
lay up.y pFibres are used along with primer & saturant.
Repair techniques – Fibre Wrapping
Repair techniques – Carbon Laminates with PT
Carbon Laminates are available in 1.5 mm thk & 50 mm width.
Laminates are used for the strengthening of beams in Flexure
Laminates are used with or without post tensioningLaminates are used with or without post tensioning
Repair techniques – Carbon Laminates with PT
Repair techniques – Steel Plate Bonding
Steel Plate Bonding is used for the strengthening of Columnsof Columns
Repair techniques – Steel Plate Bonding
Repair techniques – Cathodic Protection
Cathodic Protection is used for the protection of structure from residual corrosionstructure from residual corrosion
Repair techniques – Cathodic Protection
Case StudyCase Study
•Scope Of Work:
»Repairs and Strengthening of Marine Structure.
Areas of Concern:
• Loss of reinforcement by corrosion due to constantLoss of reinforcement by corrosion due to constant contact with saline water.
• Spalling of concreteSpalling of concrete• Delamination of main cover of all main beams • Corrosion of steelCorrosion of steel• Cracks in many members.• Carbonation• Carbonation
Methodology adopted:• Removal of loose materials and cleaning;• Removal of rust
P idi ddi i l i f l• Providing additional reinforcement steel• Application of epoxy based bond coat between old and
new concrete;new concrete;• Protection of reinforcement by providing sacrificial
anode system • Repair of soffit beams and slabs using micro-concrete;• Application of Aliphatic acrylic based anti-carbonation
coatingcoating.
Critical aspects for repairing marine structures:
• Creation of proper access • Ethylene & LPG gas lines on the jetty• No hot work allowed during ship unloading• Special arrangements for people & material
movement Hi h f t• High safety norms
• Man power & material planning D bilit t• Durability parameters
Critical aspects for repairing marine structures:M t i l ifi ti• Material specifications
• Anti carbonation coatings are the key to long lasting repairs • Micro concrete – preferred over ordinary jacketing • Polyester resin for fast repairs to broken edges of fender
blocks • Prevention of further corrosion is the key to such repairs. y p• Trained man power required• Higher cost of mobilization. • One time planning for all manpower & materials• One time planning for all manpower & materials• Aggressive climatic conditions. • Fatigue during work.
Pre Heater BuildingMain Issues ( As per NDT report)- Honey combsHoney combs- Major cavities in concrete
U- Uneven concrete pattern - Leachingg- Spalling of concrete
Pre Heater Building
What report says – summaryC i l l i l i t f l ti• Corrosion level is alarming at few locations.
- 75 % places corrosion is less than 10% probability Concrete strength is average to good- Concrete strength is average to good
- Less cover to the main steel at several locations.Protection level to the main bar is reducing- Protection level to the main bar is reducing
- Carbonation is progressing
FIRE AFFECTED BUILDING
History:
The third floor in the Port Users’ building caught fire in2006 f h f i b d d hMay 2006 . Most of the furniture burned down. But the
concrete members of the building remained intactwithout visible distortion. Due to fire exposurepserviceability of the members was adversely affected.And it became necessary to restore strength to these
bmembers.
Diagnosis:Plaster was removed, inspection of RCC structureswas carried out.Extensive NDT was carried out to see the extend ofdamage.Rebound hammer test-Rebound hammer test
-USPV-Half cell potential meter and-Half cell potential meter and-Core test
Findings:gall beams required strengthening in flexure
& shear zones& shear zonesslab strengthening in flexurecolumns were ok required only groutingcolumns were ok, required only groutingexpansion joint was damagedoverall steel bars were in good conditionoverall steel bars were in good condition,
corrosion was within permissible limits.
Remedial measures adopted:Cementitious Grouting to the beams & slabs, location
decided based on USPV readings
Additional grouting in all visible cracks
Flexural & shear strengthening of beams by bothdirectional glass fiber (2 layers)
Additional 75 mm jacket to beams with Micro concrete
Remedial measures adopted:
Slab strengthening in flexure
Grouting of all columns and floor slab
Expansion joint treatment
Plastering & terrace waterproofing.Post NDT
Cementitious grouting:
- A hole of required size is drilled andcleaned with electric blowercleaned with electric blower
- A nipple is fixed into the hole by usingcementitious putty.
- Grout is prepared using cement andExpansive additive. This mixture is thengrouted in to the holes using lowpressure until refusal.
-
GFRP Wrapping & weld mesh fixing:
- Beam surface is cleaned of anyirregularities Cavities are filledirregularities. Cavities are filledwith Polymer modified mortar.Corners are chamfered.
- Epoxy adhesive is applied over thebeam surface. The GFRP fabric isthen stuck to this surface usingrollers to avoid air from entering.
- After sticking the fiber saturant isapplied on GFRP.
-
Micro-concrete Jacketing:
- Holes of required diameter are drilled intothe beams and shear keys of 10mmthe beams and shear keys of 10mmdiameter are anchored into the same.
- Weld mesh is then tied to the shear keys tocover the whole area of beam to bejacketed. And shuttering is fixed.
- Holes of about 50mm are drilled in the slabjust over the shuttering to facilitatepouringpouring.
- Micro-concrete is then prepared andpoured in to the shuttering.
Fresh Plastering:
- Damaged plaster isremoved completely to bereplaced by good qualityfresh plaster.
Project Highlights:More than 5500 nos grouting pointsMore than 2500 nos of shear connectorsMore than 800 sqm of fiber wrappingAlmost 110 MT of Micro concrete was usedAll the beams & slabs were jacketed through holesmade in slab.The entire job was finished in 3 monthsj
•Scope Of Work:» Repairs and Strengthening of ESRs» Repairs and Strengthening of ESRs
History:History:
-The two ESRs at Ramchandra talkies and one at Ayre road with a total capacity of 5.15 million litres provide water to almost 50% area of the Dombivli (East).
-Structural evaluation of these reservoirs by IIT Powai in 2002-03 revealed that structural rehabilitation was necessary.
Findings during evaluation
• Loss of reinforcement due to corrosion;
• Excessive spalling of concrete leading to accelerated corrosion;
• Crack in many members, mostly at beam column junctions;• Probably weak joints which may be hazardous in case of an
earthquake;earthquake;
• Through cracks in container walls leading to leakages;
• Carbonation on all the surfaces of structures
Methodology adopted:gy p• Removal of loose materials and cleaning;• Grouting of honeycombs and cracks;• Grouting of honeycombs and cracks;• Removal of rust
Pl t f dditi l t l h i d• Placement of additional steel where required;• Application of bond coat between old and
new concrete;• Building the surface of concrete with polymer
modified mortar;
Methodology adopted:gy• Application of GFRP wrap to improve the joint
ductility • Application of UV resistant protective coatings over
exposed surfaces;W i l f G d l l t fi t l l• Wrapping columns from Ground level to first level of tank for peripheral columns;
• Additional re-building of concrete sections using• Additional re-building of concrete sections using Polymer Modified Mortar;
• Increasing the cross sections of affected beams;g ;
Condition of structures at the start of the project
Top slab was broken and re-cast
Shear zone – damage
Wrapping of columns and Joint strengthening using GFRP wrapping
Wrapping of columns and Joint strengthening using GFRP wrapping
Application of protective Coatings.
•Scope Of Work:» Seismic Retrofitting of Industrial Structures» Seismic Retrofitting of Industrial Structures.
Seismic Retrofitting of Industrial Building atSeismic Retrofitting of Industrial Building at Mahad
Diagnosisg• Preliminary analysis of buildings revealed that they
have not been designed for earthquake loads as per the Indian standard available at the time. Hence seismic retrofitting measures were taken.
Scope of work:• Structural strengthening of various members to
enable total structure to withstand possible seismic loads in the regionloads in the region.
Methodology adopted:Methodology adopted:• Footing Expansion
C l J k i• Column Jacketing• Addition of shear walls• Wrapping of beams/ columns with high
strength compositesstrength composites• Structural bracing
Footing Expansion: Weak footings were gexposed and strengthened by increasing their dimensions. Bonding between old and new concrete was ensured
i h husing shear anchors.
• Footing Expansion & Column Jacketing
OriginalOriginal Columns
Jacketing
• Fiber Wrapping
Beam Wrapping for hColumn Wrapping shear
• Addition of shear walls
shear walls
• Non-metallic pre-cured fiber plate
Non-metallic pre-cured fiber plate fixed to beam for flexure
Structural Bracing