dh in hybrid-a and ild 2014/9/5 yasuhiro sugimoto 1
TRANSCRIPT
![Page 1: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/1.jpg)
DH in Hybrid-A and ILD
2014/9/5
Yasuhiro Sugimoto
1
![Page 2: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/2.jpg)
ILD assembly scheme
• Baseline option– Detector is pre-assembled on
surface up to <200 ton (400 ton for solenoid) pieces
– These pieces are transported to DH and assembled to a complete detector
– Sub-detectors are installed in DH
– Magnetic field measurement is carried out in DH
– We need plenty of space for detector assembly and installation in DH
• Hybrid-A’ option– Detector consisting of 5 rings
is mostly assembled on surface
– Each ring is lowered to DH using 4000 ton gantry crane
– Muon detector, solenoid, and calorimeters are installed on surface
– Magnetic field measurement is carried out on surface after barrel calorimeter installation
– Trackers are installed in DH
2
![Page 3: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/3.jpg)
ILD yoke
3
![Page 4: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/4.jpg)
DH assembly area in Baseline option
• Area 1: Platform– YB0 assembly– Barrel detectors installation/cabling– Endcap calorimeters installation
• Area 2/3: Alcoves– Endcap calorimeters cabling– QD0 support tube assembly– FCAL install/cabling
• Area 4: Tentative platform on beam line side– YE, YB+, YB- (iron yoke and muon
detector) assembly/install/cabling
• Area 5: Loading area side– HCAL rings assembly– Tooling assembly– Storage area
4
Beam line
Access tunnel
AlcoveAlcove
Area1
Area5
Area4
Area3Area2
71m
50m
Utility space (6F)
Loadingarea
![Page 5: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/5.jpg)
DH assembly area in Hybrid-A’ option
• Area 1: Platform– Landing of lowered
detector rings– Barrel trackers
installation/cabling
• Area 2/3: Alcoves– QD0 support tube
assembly– FCAL install/cabling
Beam line
Access tunnel
AlcoveAlcove
Area1 Area3Area2
54m
50m
Loadingarea
5
![Page 6: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/6.jpg)
Requirements for cryogenics
• Baseline option– He compressor in a
compressor cavern located near the center of damping ring
– Cold box on the detector platform or on the utility floor (6F)
• Hybrid-A’ option– He compressor on
surface– He gas pipes through
18m shaft– Cold box on the
detector (YB0)
6
![Page 7: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/7.jpg)
Cranes in DH for ILD
• Baseline option– One 250 ton crane for
yoke assembly– One 80 ton crane for
CAL installation– Another 250 ton crane
(borrowed from SiD) for solenoid installation
– 5 ton cranes in alcoves for end-cap CAL and FCAL installation
• Hybrid-A’ option– One 40 ton crane for tracker
installation– Another 40 ton crane
(borrowed from SiD) for CAL maintenance, if needed
– 5 (or 2.5?) ton cranes in alcoves for FCAL installation
– (If a >80 ton piece has to be taken out from DH, 250 ton crane of assembly hall will be used)
7
![Page 8: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/8.jpg)
DH size• Height
– In Hybrid-A’ option, smaller cranes than baseline option are needed
– Therefore DH height (space above crane rails) could be slightly smaller than Baseline option (by ~2.4m?)
• Length– In Hybrid-A’ option, assembly area at both
ends of DH needed in Baseline option can be reduced
– Loading area at both ends is still necessary for sub-detector installation and detector maintenance
– L=108m seems OK (track of trailer in the loading area has to be seriously studied) 8
DH in Baselineoption
![Page 9: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/9.jpg)
DH size
28m 28m
108m
Trailer(L=16.5m)
Crane accessible area
4.5m
3m
Cable trench
Platform movingjacks2m
3m
6.5m
3m
9
![Page 10: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/10.jpg)
Assembly schedule
• Baseline option– In the new estimate by J-
Power (ALCW2014), DH construction takes much longer time than TDR: 54 months 68 months (62 months if land forming period is subtracted)
– ILD will be ready for commissioning with beam in 9 year from the beginning of land forming (8.5 years from the beginning of excavation)
• Hybrid-A’ option– In the estimate by J-Power at
ALCW2014, DH construction takes 62 months, which is not the critical path
– Assembly hall construction period and detector assembly period on surface are critical
– If assembly hall can be constructed in 2 years, ILD will be ready for commissioning with beam 8.5 year from the beginning of land forming (8 years from the beginning of excavation)
Hybrid-A’ option can make ILD schedule earlier by 0.5 year10
![Page 11: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1](https://reader036.vdocuments.site/reader036/viewer/2022082610/56649dd05503460f94ac6076/html5/thumbnails/11.jpg)
Assembly scheduleBaseline
Hybrid-A’
11