dh in hybrid-a and ild 2014/9/5 yasuhiro sugimoto 1

11
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

Upload: scot-heath

Post on 24-Dec-2015

223 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

DH in Hybrid-A and ILD

2014/9/5

Yasuhiro Sugimoto

1

Page 2: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

ILD assembly scheme

• Baseline option– Detector is pre-assembled on

surface up to <200 ton (400 ton for solenoid) pieces

– These pieces are transported to DH and assembled to a complete detector

– Sub-detectors are installed in DH

– Magnetic field measurement is carried out in DH

– We need plenty of space for detector assembly and installation in DH

• Hybrid-A’ option– Detector consisting of 5 rings

is mostly assembled on surface

– Each ring is lowered to DH using 4000 ton gantry crane

– Muon detector, solenoid, and calorimeters are installed on surface

– Magnetic field measurement is carried out on surface after barrel calorimeter installation

– Trackers are installed in DH

2

Page 3: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

ILD yoke

3

Page 4: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

DH assembly area in Baseline option

• Area 1: Platform– YB0 assembly– Barrel detectors installation/cabling– Endcap calorimeters installation

• Area 2/3: Alcoves– Endcap calorimeters cabling– QD0 support tube assembly– FCAL install/cabling

• Area 4: Tentative platform on beam line side– YE, YB+, YB- (iron yoke and muon

detector) assembly/install/cabling

• Area 5: Loading area side– HCAL rings assembly– Tooling assembly– Storage area

4

Beam line

Access tunnel

AlcoveAlcove

Area1

Area5

Area4

Area3Area2

71m

50m

Utility space (6F)

Loadingarea

Page 5: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

DH assembly area in Hybrid-A’ option

• Area 1: Platform– Landing of lowered

detector rings– Barrel trackers

installation/cabling

• Area 2/3: Alcoves– QD0 support tube

assembly– FCAL install/cabling

Beam line

Access tunnel

AlcoveAlcove

Area1 Area3Area2

54m

50m

Loadingarea

5

Page 6: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

Requirements for cryogenics

• Baseline option– He compressor in a

compressor cavern located near the center of damping ring

– Cold box on the detector platform or on the utility floor (6F)

• Hybrid-A’ option– He compressor on

surface– He gas pipes through

18m shaft– Cold box on the

detector (YB0)

6

Page 7: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

Cranes in DH for ILD

• Baseline option– One 250 ton crane for

yoke assembly– One 80 ton crane for

CAL installation– Another 250 ton crane

(borrowed from SiD) for solenoid installation

– 5 ton cranes in alcoves for end-cap CAL and FCAL installation

• Hybrid-A’ option– One 40 ton crane for tracker

installation– Another 40 ton crane

(borrowed from SiD) for CAL maintenance, if needed

– 5 (or 2.5?) ton cranes in alcoves for FCAL installation

– (If a >80 ton piece has to be taken out from DH, 250 ton crane of assembly hall will be used)

7

Page 8: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

DH size• Height

– In Hybrid-A’ option, smaller cranes than baseline option are needed

– Therefore DH height (space above crane rails) could be slightly smaller than Baseline option (by ~2.4m?)

• Length– In Hybrid-A’ option, assembly area at both

ends of DH needed in Baseline option can be reduced

– Loading area at both ends is still necessary for sub-detector installation and detector maintenance

– L=108m seems OK (track of trailer in the loading area has to be seriously studied) 8

DH in Baselineoption

Page 9: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

DH size

28m 28m

108m

Trailer(L=16.5m)

Crane accessible area

4.5m

3m

Cable trench

Platform movingjacks2m

3m

6.5m

3m

9

Page 10: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

Assembly schedule

• Baseline option– In the new estimate by J-

Power (ALCW2014), DH construction takes much longer time than TDR: 54 months 68 months (62 months if land forming period is subtracted)

– ILD will be ready for commissioning with beam in 9 year from the beginning of land forming (8.5 years from the beginning of excavation)

• Hybrid-A’ option– In the estimate by J-Power at

ALCW2014, DH construction takes 62 months, which is not the critical path

– Assembly hall construction period and detector assembly period on surface are critical

– If assembly hall can be constructed in 2 years, ILD will be ready for commissioning with beam 8.5 year from the beginning of land forming (8 years from the beginning of excavation)

Hybrid-A’ option can make ILD schedule earlier by 0.5 year10

Page 11: DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1

Assembly scheduleBaseline

Hybrid-A’

11