development_ultra - copy.ppt

22
DEVELOPMENT OF ULTRA MEGA POWER PROJECTS Shyam Wadhera Director (Projects) Power Finance Corporation Ltd. 11 th May, 2006

Upload: ogu

Post on 15-May-2017

234 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Development_Ultra - Copy.ppt

DEVELOPMENT OF ULTRA MEGA POWER PROJECTS

Shyam WadheraDirector (Projects)

Power Finance Corporation Ltd.11th May, 2006

Page 2: Development_Ultra - Copy.ppt

THE CONCEPT: DEVELOPMENT OF LARGE GENERATION PROJECTS THROUGH COMPETITIVE BIDDING Setting up of large projects of 4000 MW at a single location:

ensuring economies of scale

Utilisation of super critical technology: ensuring higher efficiency and lower CO2 emissions

Award of projects to developer through tariff based competitive bidding : ensuring cheaper power

Page 3: Development_Ultra - Copy.ppt

THE APPROACH

Guidelines for determination of tariff through bidding process were issued on 19th January, 2005 under Section 63 of the Electricity Act, 2003. These provide for procurement of power by Distribution Licensees through competitive bidding

Separate SPVs for each project to undertake project development activities including bid process management on behalf of procurers

Page 4: Development_Ultra - Copy.ppt

TECHNICAL FEATURES

Utilisation of higher efficiency super critical technology with unit size of 800 MW

Station capacity of about 4000 MW (5x800 MW)

Flexibility re: unit size to be permitted, subject to meeting thermal efficiency requirements

Page 5: Development_Ultra - Copy.ppt

SITE SELECTION Site selection by CEA taking into consideration availability

of fuel, land and water etc. 5 suitable locations identified based on preliminary scrutiny

by CEA of a number of potential sites available in the country : Two pithead locations based on domestic coal.

Sasan in MP Akaltara in Chhattisgarh

Three coastal locations based on imported coal. Mundra in Gujarat Girye in Maharashtra Tadri in Karnataka

One additional pithead site in Orissa and one coastal site in Andhra Pradesh are also under consideration

Page 6: Development_Ultra - Copy.ppt

LEARNING FROM PAST EXPERIENCE IPP experience in the past highlights critical importance

of availability of Reliable fuel supply Environmental clearances Power purchase agreement with payment security for

achieving financial closure Shell Companies to obtain statutory clearances and to

tie-up inputs

Page 7: Development_Ultra - Copy.ppt

THE SHELL COMPANY CONCEPT

PFC identified as the nodal agency Shell Companies set up as wholly owned subsidiaries of

PFC. Each Company to work independently to reach a stage

where major tie-ups, statutory clearances and linkages are in place.

Selection of developer through tariff based ICB. Shell companies will then be transferred to the successful

bidders for execution of projects.

Page 8: Development_Ultra - Copy.ppt

ROLE OF MINISTRY OF POWER• Ministry of Power to be facilitator• Co-ordination with concerned Ministries/ Agencies and

State Govts. for ensuring: Coal block allotment/ coal linkage Environment/ forest clearances Facilitate acquisition of land Required support from State Govt. & its agencies on various

issues Financial closure by Financial Institutions To facilitate PPA and proper payment security mechanism

with State Govt./ State utilities Monitoring the progress of shell companies w.r.t

predetermined timelines

Page 9: Development_Ultra - Copy.ppt

ROLE OF SHELL COMPANIES Shell Companies to take action for:

Appointment of Consultants to undertake preparation of Project Report

Initiate land acquisition proceedings Obtain coal linkages/ allocation of captive coal blocks for pit-

head projects. Allocation of water by the State Govt. for pit-head locations Approval for use of seawater from Maritime Board/ other

Govt. Agencies for coastal locations Appointment of Consultants for International Competitive

Bidding (ICB), document preparation & evaluation.

Contd..

Page 10: Development_Ultra - Copy.ppt

ROLE OF SHELL COMPANIES ….Contd.

Obtain various approvals and statutory clearances. Tie up for off-take/ sale of power as per provisions of Section

63 of EA 2003. Initiate action for development of the power evacuation

system and undertake system studies considering the addition of capacity from these projects

Page 11: Development_Ultra - Copy.ppt

BIDDING PROCESS For the purpose of selection of a developer, a two stage

selection process has been adopted. The first stage of bidding will involve Request For Qualification

(RFQ) containing qualifying criteria for selection of bidders to participate in the second stage.

The second stage of bidding will invite Request For Proposals (RFP) from the qualified bidders which will further be evaluated by the SPVs with help of appointed consultants.

The RfQ and RfP documents will conform to Competitive Bidding Guidelines of the Govt. of India

Page 12: Development_Ultra - Copy.ppt

TIME SCHEDULE FOR FIRST TWO PROJECTS

Activity Date

Notice for EoI for Sasan/ Mundra 31-1-06/ 1-2-06

Submission of EoI for Sasan/ Mundra 28-Feb-2006

Issue of RFQ Documents for Sasan/ Mundra

31-Mar-2006

Submission of Bids (RFQ) 01-June-2006

Issue of RFP Documents 15-June-2006

Submission of Bids (RFP) 15-Nov-2006

Selection of Developer/ Transfer of SPV 31-Dec-2006

Page 13: Development_Ultra - Copy.ppt

ACTIONS TAKEN BY SHELL COMPANIES Issuance of EOI:

Sasan (MP) 31-Jan-2006Mundra (Gujarat) 01-Feb-2006Girye (Maharashtra) 28-Feb-2006Tadri (Karnataka) 10-Mar-2006

Bidders’ Conference:Sasan & Mundra at New Delhi 21-Feb-2006Girye at Mumbai 17-Apr-2006

Site visit for Bidders Sasan and Mundra sites 22nd to 24th Feb 2006

The Conference attended by about 35 companies including

Overseas Companies and representative of FIs/ Banks.Contd..

Page 14: Development_Ultra - Copy.ppt

ACTIONS TAKEN BY SHELL COMPANIES….contd

Technical Consultants appointed for preparation of Project Reports for 5 projects

Studies started by the consultants for Sasan and Mundra Projects.

Consultant appointed for preparation of bidding documents and to advise regarding bid process management for the tariff based competitive bidding for Sasan and Mundra projects

Page 15: Development_Ultra - Copy.ppt

SCOPE OF TECHNICAL CONSULTANCY

Scope of Work: Topographical Survey Geo Technical Study Area drainage Study EIA Study Socio Economic survey Hydrographic Study (for coastal projects)

Completion Schedule: 15-6-06 for Sasan & Mundra

Page 16: Development_Ultra - Copy.ppt

Scope of Work: To prepare documents for Request for Qualification To assist & advise in carrying out detailed evaluation of RFQ To prepare documents for Request for Proposal (RFP) To participate in all Bidders Conference To Prepare bid evaluation Financial models to carry out analysis of

Bid including sensitivity analysis To assist & advise in detailed evaluation of RFP received To analyse project risks and advise on risk allocation matrix To assist & advise in selection of successful developers and

participate in negotiations.

SCOPE OF BIDDING CONSULTANCY

Page 17: Development_Ultra - Copy.ppt

GOVERNMENT SUPPORT : Support of State Govt:Periodic meetings by Ministry of Power with Senior State Govt. Officials to obtain their support on issues relating to land, water,environment issues

Support of Financial Institutions:Meeting taken by Secretary (Power) with Heads of FinancialInstitutions on 6-01-2006

Support of Industry:Meeting taken by Hon’ble Finance Minister with Industry Leaders on 13-01-2006

Page 18: Development_Ultra - Copy.ppt

GOVERNMENT SUPPORT : ….Contd.

Contd..

Support of Govt. of India:Development of Ultra Mega Power Projects discussed in Meeting of Energy Co-ordination Committee Chaired by Hon’ble Prime Minister on 10-02-2006

Purchase of Power:Meeting taken by Secretary (Power) with Principal Secretaries and Utility Chiefs of purchasing states on 16-02-2006

Transparent Bidding Process:Bidders’ Conference for Sasan and Mundra projects held at New Delhi on 21-02-2006

Broad Qualifying Requirements discussed and consensus evolved

Page 19: Development_Ultra - Copy.ppt

POWER OFF-TAKES.No. State\ Project -> Sasan (MP) Mundra(Gujarat) Girye(Mah.) Karnataka

1 Delhi 500 - - -

2 Uttar Pradesh 500 300 - -

3 Uttaranchal 100 - - -

4 Punjab 600 500 - -

5 Rajasthan 400 400 500 300

6 Haryana 450 400 - -7 Madhya Pradesh 1200 - 500 -

8 Chattisgarh 250 - 500 -

9 Guajarat - 1600 - -10 Maharashtra - 800 2000 100011 Karnataka - - 500 150012 Tamil Nadu - - - 1000

13 Kerala - - - 20014 Andhara Pradesh - - - -

  TOTAL 4000 4000 4000 4000

Page 20: Development_Ultra - Copy.ppt

PAYMENT SECURITY MECHANISM

As condition in PPA Letter of credit (LC) by distribution utilities Escrow on the receivables of distribution utilities Direct supply to HT consumers in the unlikely event of

default as per provisions of the Electricity Act 2003 to be accepted upfront

Page 21: Development_Ultra - Copy.ppt

Meeting with Secretary (Coal) on 01.03.2006 regarding allocation of captive coal blocks

Meeting with Secretary (Environment) on 09.03.2006 to emphasise fast track environmental clearance for the Ultra Mega Power Projects

Presentation given to Dy. Chairman, Planning Commission on 27.03.2006

Meeting with Bidders on 8.4.06 at New Delhi for clarification of RfQ issues

Presentation to Expert Committee (Thermal) of MoEF on 20.04.2006

A presentation to Chairman and Members, CERC on 26.04.06

INVOLVEMENT OF OTHER STAKEHOLDERS

Contd..

Page 22: Development_Ultra - Copy.ppt

…..and the Process Continues

THANK YOU