Presented to: Presented by: Developments at the Yucca Mountain Exploratory Studies Facility Technical Committee on Training in and Demonstration of Waste Disposal Technologies in Underground Research Facilities – Claudia M. Newbury, Senior Policy Advisor Office of License Application and Strategy Office of Repository Development Office of Civilian Radioactive Waste Management U.S. Department of Energy IAEA Headquarters, Vienna Austria December 6 – 10, 2004

Upload: phungdang

Post on 14-Feb-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Developments at the Yucca Mountain Exploratory Studies ... · PDF fileDevelopments at the Yucca Mountain Exploratory Studies Facility ... Cross Drift Construction ... Developments

Presented to:

Presented by:

Developments at the Yucca Mountain Exploratory Studies Facility

Technical Committee on Training in and Demonstration of Waste Disposal Technologies in Underground ResearchFacilities –

Claudia M. Newbury, Senior Policy AdvisorOffice of License Application and StrategyOffice of Repository DevelopmentOffice of Civilian Radioactive Waste ManagementU.S. Department of Energy

IAEA Headquarters, Vienna AustriaDecember 6 – 10, 2004

Page 2: Developments at the Yucca Mountain Exploratory Studies ... · PDF fileDevelopments at the Yucca Mountain Exploratory Studies Facility ... Cross Drift Construction ... Developments

2Claudia_Newbury-WM04-4358.ppt

Exploratory Studies Facility

Page 3: Developments at the Yucca Mountain Exploratory Studies ... · PDF fileDevelopments at the Yucca Mountain Exploratory Studies Facility ... Cross Drift Construction ... Developments

3Claudia_Newbury-WM04-4358.ppt

Safety Upgrades to the ESF

• ESF built as a “temporary” facility more than 10 years ago

• Independent review recommended limited access until appropriate preventative maintenance programs were in place for– Electrical Systems

– Ventilation System

– Communication system

– Rail system

Page 4: Developments at the Yucca Mountain Exploratory Studies ... · PDF fileDevelopments at the Yucca Mountain Exploratory Studies Facility ... Cross Drift Construction ... Developments

4Claudia_Newbury-WM04-4358.ppt

Proposed Surface Facilities

Page 5: Developments at the Yucca Mountain Exploratory Studies ... · PDF fileDevelopments at the Yucca Mountain Exploratory Studies Facility ... Cross Drift Construction ... Developments

5Claudia_Newbury-WM04-4358.ppt

Repository Lay-out

• Panel numbers represent the proposed emplacement sequence

• Sequence:

– Panel 1, Phase 1

Develop initial emplacement drifts

– Panel 1, Phase 2

Complete panel 1 drifts (8 total)

– Panel 2

17 drifts total

• Total emplacement length available is approximately 41 miles (65 km)

• Available contingency of 11 - 13.5 % for the 70,000 MTHM case