development of automotive components
TRANSCRIPT
-
7/28/2019 development of automotive components
1/21
Section 1 - General InformationAll Supplier related transactions are through SAP, Single server environment.
Suppliers are provided with free connectivity through intranet services SRM (Supplier
Relation Management), which is compatible to SAP. Suppliers can view Purchase Order
details, schedules for the delivery of goods, status of their quality acceptance of
supplies, payments. The quarterly feedback on Supplier Rating and Tata motors
standards which are to be followed at their end can also be viewed through SRM.
Periodic supplier meets are conducted to provide a forum for the Suppliers to meet
Senior Officers of the organization, and have formal communication on matters of
mutual interest.
Suppliers are requested to contact the representatives of the following functions for
queries, if any, during the course of supplies.
a) Issues on items under development with Purchase organization
Ancillary Development Department (ADD),
b) Issues regarding POs and schedules on items with Purchase organization
- Auto Materials and concerned Factory Logistic Group (FLG).
c) Issues regarding quality, primary rejection, line rejection, rejection disposal, warranty
complaint, debit due to quality issues, Self Certification-- Quality Assurance
Department.
d) Issues regarding payment -- Finance Department.
Section 2: Quality systems at Tata Motors
2.1 Quality System Requirements
The supplier has to demonstrate the ability to establish, document and implement an
effective quality system that complies with all applicable elements of ISO/TS16949-2002
standards. Apart from this suppliers management has to ensure that supplier quality
policy is understood and maintained, and continuous improvement of the quality system
is followed.
-
7/28/2019 development of automotive components
2/21
2.2 Quality System Development and Audits
Tata Motors may require a formal assessment of the suppliers quality system at
any time. The type of audit done is based on the following requirements .
At the suppliers and/or customers request to provide guidance for
verification of quality system improvements
Supplier does not meet acceptable standards of performance
Potential or Strategic Supplier to Tata Motors.
Manufacturing of new type of item
Periodic quality audit
2.3 Quality Planning
The purpose of having a quality plan is to set direction, action plans and measurements
needed to accomplish stated objectives and plans. To meet the objectives of the
development suppliers us To this end, suppliers shall use some form of systematic
planning and review for new products and product changes. APQP is the minimum
acceptable route for this purpose. Quality development and control activities require
planning to be effective and economical. The quality planning process shall emphasize
problem prevention rather than detection, and support a continual quality improvementphilosophy. This results into increased productivity, efficiency and profits by reducing
waste, scrap, rework and customer complaints when quality planning is properly
performed. Tata Motors requires that its suppliers plan for quality. Supplier may refer to
Tata Motors PPAP process for additional information (Details of PPAP enclosed in
Appendices). The quality planning activity shall be a regularly scheduled, cross-
functional process, involving all departments with goals and objectives supporting the
quality system. Each supplier is responsible for the quality of its own products. The
suppliers failure to provide Tata Motors with quality goods may result in Tata Motors
claims for machining, assembly, sorting and/or administrative costs due to poor quality,
late delivery and other nonconforming conditions.
The quality planning methods and documentation are suggested as per list of PPAP
requirement.
-
7/28/2019 development of automotive components
3/21
2.4 Production Part Approval Process (PPAP)
Suppliers shall fully comply with all requirements of Production Part Approval
Process when doing business with Tata Motors. Before making a shipment to
Tata Motors, the supplier shall meet all of the purchase order requirements and
shall ensure that all parts conform to Tata Motors engineering and quality
specifications. This includes the submission of PPAP for conditions/ situations
listed in Tata Motors PPAP process and as mentioned below, unless it is waived.
.
All Tata Motors suppliers are required to submit a PPAP in case of Major /
Significant process changes.
2.4.1 PPAP Submissions / Retentions and records.
Suppliers are responsible for retaining a complete record of all PPAP
submissions. The records shall show conformance to all dimensional, chemical,
metallurgical, physical, performance and other test specifications. Please refer
PPAP process of Tata Motors.
Suppliers shall have a system to control the updating, distribution, storage and
disposal of engineering drawings, specifications, control plans, FMEAs,
procedures, work instructions, forms, etc.
2.4.2 PPAP Status
The following dispositions will be used: Accept
Reject - The supplier must correct and resubmit the PPAP package. Only
those characteristics affected by the changes to the tooling and/or process
need to be addressed in the resubmission. If the PPAP was rejected
because of missing documentation, the documentation must be included
with the resubmission. The supplier must not ship production quantities
while the status of the PPAP is "Reject" unless a deviation is granted for
all characteristics contributing to the rejection. If the suppliers PPAP is
rejected, the product shall be corrected and PPAP resubmitted for
approval.
Other- This status may be applied to product that has been accepted for
all dimensional and material requirements, but will require subsequent
-
7/28/2019 development of automotive components
4/21
manufacturing evaluation to determine acceptability. When a PPAP
receives this disposition, the supplier is required to submit a small
production lot of product for evaluation. Accept status is granted if no
TATA MOTORS LIMITED
product-related problems are encountered during testing. If problems are
encountered, the status becomes Reject and the supplier must resubmit
based on the feedback they are given.
After PPAP approval has been granted, suppliers are responsible for seeing that
future production continues to meet all customer requirements.
2. 4. 3 Out-of-tolerance Conditions on PPAP Samples
The supplier shall make every reasonable effort to correct any discrepancies
discovered when parts are being evaluated for a PPAP. If, for any reason, the
samples inspected for the PPAP do not conform to all requirements and the
supplier is unable to correct the discrepancy, the supplier must notify the
appropriate Tata Motors contact prior to submitting the PPAP. This will allow for
remediation if needed.
2. 4. 4 Ongoing PPAP Maintenance
The supplier shall carry out audit for product and process at regular intervals
(including complete dimensional, material and performance evaluation) as a part
of internal control and corrective action plan to be implemented wherever
necessary.
2.5 Subcontracted Parts and Services
If a part or service is subcontracted by a primary supplier, the primary supplier
assumes responsibility for the quality of that part or service unless Tata Motors
specifically releases the supplier from that responsibility in writing. Materials
purchased by Tata Motors and consigned to a primary supplier are not
considered subcontracted. The primary supplier is responsible for the quality of
all subcontracted materials, components or services. Parts or services cannot be
subcontracted without prior consent from a Tata Motors representative in writing.
Any materials, components or services purchased by the supplier for use in Tata
Motors products must be adequately inspected and/or tested to assure
conformance to the applicable engineering drawings and specifications. This
-
7/28/2019 development of automotive components
5/21
applies whether the materials/components are Tata Motors designed or are
specified by reference to a particular industry specification or manufacturer's part
number.
Whenever the primary supplier subcontracts a service (e.g., heat treating,
machining, assembly, inspection), it must assure that the results conform to all
applicable specifications. Any characteristics produced or affected by
subcontracted services are to be treated in the same manner as on Tata Motors
designed materials components.
For materials or components that are Tata Motors -specified, but do not have
dimensional, physical, material or aesthetic characteristics specifically indicated
(such as off-the-shelf or catalog items), the supplier must provide the sub
suppliers name and address and the part number and/or name of the
TATA MOTORS LIMITED
subcontracted item with the PPAP documentation. Whenever specified by Tata
Motors, only Tata Motors -approved sources may be used for supplier-procured
subcomponents.
2.6 Special Characteristics
Some Tata Motors products will have features, which are designated as Special
(key, significant, critical, etc.) characteristics on the drawing. When a special
characteristic is shown on a drawing, the supplier shall comply with the
description. It is the suppliers responsibility to understand all special
characteristics on the part drawing, and to notify the division-purchasing
associate when more information is required.
2.7 Material Certifications
The supplier shall ensure that the product supplied to Tata Motors is in
compliance with all material specifications on the product drawing and/or
purchase order. Material certifications containing actual measured results are
required at PPAP and during normal production on an as needed basis, as
designated by Tata Motors.
2.8 Restricted Substances
Tata Motors is concerned for the safety of its employees, customers and society
at large. Suppliers must assure compliance with all governmental and safety
-
7/28/2019 development of automotive components
6/21
requirements on restricted, toxic and hazardous substances used in the
manufacture of products delivered to us. When applicable, Material Safety Data
Sheets are to be sent to the attention of the Environmental Health and Safety
Officer at the Tata Motors prior to the first production shipment and upon request.
Suppliers are required to report any hazardous materials contained in any part of
the product shipped (including coatings, etc) to Tata Motors . (Refer annexure for
restricted substances)
2.9 Statistical and Analytical Techniques
Statistical and analytical techniques may be used by the supplier to measure and
improve process capability, efficiency, and quality of the product. Supplier may
use various types techniques like Design of experiment, X bar & R chart etc.
The supplier must develop a system which documents responsibilities,
involvement, plans and criteria for implementing statistical and analytical
methods. The supplier is responsible for ensuring that tooling, equipment, and
processes used to demonstrate the capability to consistently produce quality
parts with minimum variation. The special characteristics identified on customer
prints will require a minimum of 1.33 CpK. All critical and major dimensions on
the drawing shall demonstrate statistical process control at time of PPAP.
2.10 Internal Supplier Product/Process Audits
The supplier shall have an internal process for the routine audit of product and
process quality. The supplier shall perform internal quality audits scheduled on a
TATA MOTORS LIMITED
regular basis to set a benchmark for continual improvement of their quality
systems and to demonstrate compliance with existing elements of this manual.
The results of the internal audits shall be distributed to the appropriate personnel;
action plans shall be developed, tracked and documented for all areas that are
found to be in noncompliance.
The objectives are to:
Assess the effectiveness of the control plan in assuring conformance to
the requirements.
To evaluate as delivered product quality.
To provide a basis for the improvement of the control plans.
-
7/28/2019 development of automotive components
7/21
To provide additional assurance of product quality.
Assessments of dimensional, functional and/or cosmetic features may be
required to adequately evaluate the part or process to Tata Motors requirements.
2.11 Calibration
The supplier shall establish a calibration system that will track and account for
each gauge and measuring instrument individually. Established calibration
intervals shall be documented, and each instrument shall be traceable to its last
calibration date. Documentation shall include the actual quantitative
measurements taken during the calibration, in order to monitor long term
performance. All gauges used in evaluating process potential shall be in
compliance with Quality System requirements. Copies of the Gauge R&R study
data and results must accompany the process potential study information.
All calibration must be traceable to National Laboratory or an industry recognized
standards/accreditation authority. Outside calibration services must be accredited
to ISO/ IEC17025. These calibration records shall be retained for verification
purposes. Employees involved in using calibration equipment should have
documented training on the instruments they use. Documentation of training
records shall be retained for verification purposes.
2.12 Gauge R&R
The supplier shall conduct Gauge R&R studies upon receipt of new or repaired
measuring equipment. Documented action plans shall be completed for
completion of Gauge R&R studies on existing equipment. After the initial studies,
established intervals for repeat verification, Gauge R&R studies shall be
documented, traceable to the last date of evaluation, and include all significant
study information. These repeat studies are necessary on a regular basis to
assure continued suitability to the application. Gauge R&R studies shall be
conducted under actual operating conditions. Gauge R&R studies shall be
included with each PPAP package.
TATA MOTORS LIMITED
Guide lines for acceptance of Gauge R & R
If GRR as a % of tolerance is 0-20% , it is acceptable for measuringCritical , Major and Minor characteristics
-
7/28/2019 development of automotive components
8/21
If GRR as a % of tolerance is 20-30% , it is acceptable for measuring ,Major and Minor characteristics only.
If GRR as a % of tolerance is greater than 30% , it is not acceptable formeasuring any type of characteristics and measurement system
should be improved
2.13 Notification of and Control of Nonconforming Material
All suspect material shall be properly contained at the suppliers facility. All
suspect nonconforming material shall be quarantined in a segregated area,
designated for that purpose only. An effective system is required for proper
identification and timely disposition of nonconforming material. The supplier is
responsible for maintaining and analyzing data for those non-conformances.
Supplier shall take necessary action to avoid shipment of such material to Tata
Motors. If such material is shipped to Tata Motors, Supplier shall be responsible
for all the liabilities arising due to this. Suspect material (material whose
inspection/test status is not known) and obsolete material shall be treated at par
with Non-conforming material.
2.14 Preventive/Corrective Action and Problem Resolution
The supplier shall establish systems to document and track corrective actions.
Corrective actions could be referred to as Non-conforming Material Reports
(NCMRs), Corrective Action Reports or Defective Material Reports. Results must
be traceable to the initial reason for the corrective action request. The format
used must drive towards root cause analysis and implementation and
effectiveness of permanent action to eliminate the problem and the possibility for
recurrence. Analysis of actions taken and results shall verify the effectiveness of
the solution.
If containment is needed, it shall include:
Method of containment,
How new product is identified, and
Containment plan for product in transit or at Tata Motors.
The permanent corrective action or an action plan shall be issued to the Tata
Motors within 7 working days of notification of the occurrence.
TATA MOTORS LIMITED
-
7/28/2019 development of automotive components
9/21
This shall include:
Root Cause analysis,
Verification of corrective action, and
Dates and Responsibilities for actions not complete.
All corrective action responses are to be closed out in a timely and
expeditious manner, with a maximum target closure date of thirty days.
Corrective action requiring more than 30 days requires written approval
from Tata Motors.
To end this, the suppliers system shall contain a mechanism for escalating
unresolved problems to the suppliers executive management to ensure action is
taken and to enable an understanding of any strategic implications.
The supplier shall develop a method for assessing the responsiveness and
effectiveness of their problem resolution process.
During specific instances Tata Motors supplier may be requested to attend a
Quality meeting. A targeted supplier may be one with a high PPM or one with
chronic repetitiveness of bad quality.
2.15 Traceability
Unless otherwise agreed to, the supplier shall maintain the ability to trace their
product from the lot identification as shipped to Tata Motors, back through theirmanufacturing system to the raw material source.
2.16 Manufacturing Capabilities
Suppliers shall establish systems and procedures, which seek to continually
optimize the efficiency and productivity of its manufacturing capabilities. These
efforts are directed at such activities as minimization of floor space, inventory,
cycle time, manpower, and use of other resources in all aspects of the
manufacturing process. Suppliers shall ensure that cross-functional teams are
established to develop methods to optimize process effectiveness using Kaizen,
mistake proofing, and/or other proven methods. Objective evidence of these
methods must be evidenced during the Preventive and Corrective Action stage of
the process.
2.17 Specific Requirements
In many cases, this manual will not sufficiently describe all of the specific
-
7/28/2019 development of automotive components
10/21
requirements of Tata Motors or particular customer. The Tata Motors specific
requirements shall be identified during the Advanced Product Quality Planning
(APQP) activities. If there are any questions regarding these specific
requirements, the supplier shall contact the respective Purchasing Department of
Tata Motors.
TATA MOTORS LIMITED
Product-specific requirements may include but not be limited to the following:
Special characteristics.
Testing.
Special handling.
Customer-specific requirements may include but not be limited to the following:
Quality management systems.
Process techniques and process controls.
Identification and processing of critical parts and features.
Certification.
2.18 Economic-Considerations of Quality-Related Costs
The suppliers management shall define and document a comprehensive quality
cost management system and facilitate quality improvement efforts that will lead
to operating cost reduction opportunities. Tata Motors believes that when quality
costs can be measured and related to an area where basic quality performance
data exists, the quality improvement process can begin.
An effective quality cost program consists of the following steps:
Establish a quality cost measurement system.
Develop a suitable long-range trend analysis.
Establish annual improvement goals for total quality costs.
Develop short-range trend analysis with individual targets, which
collectively add up to the incremental demands of the annual improvement
goal.
Monitor progress against each short-range target and take appropriate corrective
action when targets are not being achieved.
2.19 Product Safety and Product Liability
The safety aspects of product quality shall be identified with the aim of enhancing
-
7/28/2019 development of automotive components
11/21
product safety and minimizing the potential consequences of product liability. The
company and its employees must be aware of its potential consequences.
2.20 Housekeeping
The supplier shall have a documented system to ensure their facility is clean and
orderly. This verification shall be a part of their internal quality audits. Tata
Motors strongly feels that a supplier with an effective Housekeeping process
allows itself to present well to its customers and employees
2.21 Tooling Management
The supplier shall establish and implement a system for tool control. This
includes items manufactured from stampings, injection molding, template
cutouts, etc. Formal procedures addressing tooling handling, storage,
modification, setup, design, preventive maintenance and calibration shall be
maintained and shall be followed. All tooling purchased, loaned or financed by
TATA MOTORS LIMITED
Tata Motors shall remain the property of Tata Motors. Normal storage,
maintenance, repair and calibration of own and Tata Motors tooling, unless
otherwise negotiated, is the responsibility of the supplier, such as expected tool
life will be achieved and conforming parts are produced.
2.22 Control of Special Process
The supplier must have an approved system in place to validate, revalidate and
to perform special processes such as a) Plating, b)Heat treating, c) Welding, d)
Surface finish / coating / treatment (painting and plating), and others that require
approval certification of the process equipment and procedures. Please refer to
Appendices for the list of current sources approved by Tata Motors for special
processes. Supplier shall take approval for a new sub contractor for special
processes from Tata Motors before starting the development. The requirements
for any qualification of process operations, including associated personnel and
equipment shall be documented.
2.23 Inventory Age Control
The supplier shall have an effective system for age control within their inventory
for items whose acceptability is limited by age of the item. The system must
include a method of identifying the age of such items and provision for the
-
7/28/2019 development of automotive components
12/21
-
7/28/2019 development of automotive components
13/21
in the supply chain. Cost reduction proposals may include ideas, which involve
but are not limited to:
Component Design
Material Type
Packaging Requirements
Logistics
Process Standards
Cycle Time Reduction
Workplace Organization
Value Analysis/Value Engineering
Validation Test Requirements
Certification Methods
3.3 Cost Control and Reduction
The supplier shall have a process that ensures:
All costs are controlled during the life of the products.
All potential cost reduction opportunities are clearly identified.
As part of this process, the supplier shall establish and maintain documented
records of all criteria that may influence the cost of their products. This
information shall primarily be used to manage and control cost, and to ensure theimpact of economic factors and market fluctuations are minimized. This
information shall also be used to highlight opportunities for cost improvement.
The supplier shall compile and maintain a document of continual
improvement/cost reduction ideas for submission to the customer. The continual
improvement ideas shall be frequently reviewed with the appropriate purchasing
agency to maximize the effect of potential cost improvements.
TATA MOTORS LIMITED
3.4 Commercial Agreements
General RequirementThe supplier must comply with Tata Motors standard Purchase Order terms and
conditions. The suppliers must sign the Purchasing Agreement with Tata Motors
and should follow the same during the entire contract period of Purchase Orders.
3.5 Warranty
The supplier shall commit to the terms and conditions of warranty in the
-
7/28/2019 development of automotive components
14/21
Purchase Order / Purchasing Agreement.
3.6 Non-Conforming Materials
Non Conforming Materials affect the quality of final products, and hence the
suppliers shall ensure that these are not getting mixed with their normal supplies
.Non Conforming Material Report (NCMR) may also be referred to as a rejection
report.
Tata Motors may recover an administration fee for each non conforming material.
A late charge will be issued if an initial response is not received within
appropriate time of notification of an NCMR. Suppliers are requested to
communicate the same to QA and Purchasing Agency.
A late charge will be issued if a permanent corrective action or an action plan
showing responsibilities and due dates is not received within 7 working days of
notification of the occurrence. Suppliers are requested to communicate the same
to QA and Purchasing Agency.
Any and all costs related to the NCMR incurred by a Tata Motors facility will also
be charged back to the supplier. These costs may include:
Down time
Sorting
Scrap Supervision
Rework
Premium Freight
TATA MOTORS LIMITED
Section 4 : Delivery4.1 Logistics PlanningGeneral Requirements
The supplier shall ensure that logistics development activities are planned for
and carried out at an appropriate stage in a products development & life cycle.
All logistic planning and development activities shall be carried out according to
the requirements of Tata Motors.
Delivery requirements:
100% On Time delivery is requiredIf a supplier does not meet our 100% target,
the supplier may be requested to provide action plans to address the causes.
-
7/28/2019 development of automotive components
15/21
On-time delivery must contain the complete quantity of parts scheduled and meet
specification.
Any cost incurred due to late delivery will be charged back to the supplier. This
includes:
Late PPAP submissions
Late/missing/incorrect documentation
Any extra cost, associated with a suppliers lack of meeting Tata Motors delivery
and quality requirements will be debited back to the supplier. This cost would
include premium freight, machine downtime, etc.
Suppliers should track all premium freight within their system as a quality
requirement. Tata Motors requires suppliers to be SRM compliant. The supplier
shall identify personnel responsible for the support of product delivery to the Tata
Motors during all hours of operation. This information should be provided to your
Tata Motors contact.
4.2 Design for Logistics
The supplier shall ensure that logistics issues are given due consideration, at an
appropriate stage of product development, to enable the following:
Optimal design to reduce packaging complexity.
Optimal design to improve ease of handling. Optimal design to reduce the likelihood of product damage.
Damage to environment.
Tata Motors encourages use of recyclable cartoon boxes.
4.3 Delivery Process
The supplier shall develop a delivery plan that identifies the most appropriate
process for the delivery of their product to support a daily production requirement
at Tata Motors. In doing so, the supplier should consider the following:
Supply routing for transportation.
Warehousing (size, storage specifications, shelf life).
Any requirement for sequenced delivery product Traceability.
TATA MOTORS LIMITED
Where transportation is provided by Tata Motors (Milk route suppliers), the
supplier must ensure that products, together with an appropriate means of
-
7/28/2019 development of automotive components
16/21
loading, are available at the required times.
Where transportation is the responsibility of the supplier:
The supplier shall have an effective transportation policy. The policy shall
be regularly reviewed for cost effectiveness and success in meeting
customer requirements.
The supplier shall measure transportation performance for identifying
further opportunities for delivery performance improvement.
The supplier should ensure that a deviation form accompanies any
material that is not to specification.
The supplier shall have a process for the measurement and review of
logistics management performance. This review should be conducted at
the executive level of the organization.
4.4 Supply Chain Flexibility
Externally, the supplier shall complete an analysis of the effectiveness of the
planned supply chain and its associated processes for each commodity at the
suppliers manufacturing site. Each supplier shall be responsible for managing
its own supply chain. Internally, the supplier shall identify any constraints that
prevent a free supply of components and assemblies through the manufacturing
process. Areas of inflexibility shall be investigated so that they can be eliminatedor managed. Details of flexibility must be made available to the Tata Motors on
request.
4.5 Labeling Standards
Suppliers shall ensure to attach identification tag on all consignments supplied to
Tata Motors giving complete details. Any deviations from the requested standard
must be provided in writing from the Tata Motors location receiving product.
4.6 Premium Freight
The supplier will be held liable for additional freight cost incurred because ofsuppliers lack of quality and delivery performance. Any premium freight
incidences and their cost must be tracked at the suppliers location as a quality
requirement.
-
7/28/2019 development of automotive components
17/21
Section 5 : Support5.1 Risk Assessment
The supplier must have a process for the identification and management of
potential risks to ensure proper supply of parts and materials to Tata Motors. The
intent of this process is to proactively address contingencies and risk. The
supplier shall inform Tata Motors about the action plan to encounter the
contingencies and risk.
The suppliers Risk Assessment process shall include a periodic assessment and
review of all possible risks. The process shall analyze risks associated with both
facilities and personnel, considering issues such as:
Product, facility or individual skill uniqueness.
Critical process element susceptibility to disruptive damage.
Susceptibility to natural phenomena (i.e. flood and earthquake).
Labor Unrest
Second tier supplier related issues.
Hazardous Material Reporting (i.e. End of Vehicle Life requirements,
Cadmium, Mercury, Hexavalent Chromium).
Change in legislation, which may affect the Suppliers business or QMS.
The output of this assessment shall be used to identify where action is required,
if economically feasible, to remove or reduce the likelihood of these problems
occurring. The assessment shall also include an estimation of potential downtime
in a major catastrophe. The supplier shall inform Tata Motors about occurrence
of such incidence and work-out a joint action plan.
5.2 Continual Improvement
The supplier shall demonstrate the effective deployment of a comprehensive
continual improvement plan across the whole organization. The objective of
continual improvement is to deliver real improvements in customer satisfaction
and business performance, thus maintaining and strengthening the
organizations competitive advantage, and that of the whole supply chain.
The supplier shall ensure that continual improvement activities are focused on
those businesses and manufacturing processes that have the greatest influence
-
7/28/2019 development of automotive components
18/21
-
7/28/2019 development of automotive components
19/21
improvement and work out action plans for improvement in the performance of
the Supplier. The Suppliers shall also be ranked according to their scores in
rating according to the system. While high performing Suppliers shall be given
preferred treatment regarding new developments, those showing no
improvements despite efforts may be considered for deselection.
The Supplier can access the feed back through our network, SRM being
provided to the approved vendors free of any charge. For any queries, the
Supplier is to contact the related Development, Purchasing agency or Quality
Assurance Division.
Rating System Profile :
Following are the details of Tata Motors Supplier Rating System:
The system has been configured in our ERP system, SAP 4.6c.
Suppliers are rated on the overall scale of 1 to 100 in this comprehensive
system. The supplies of the items under development are excluded from the
scope to avoid influence of iterations during development.
The overall score is arrived at by aggregation of the scores on five Main Criteria:
1 Quality
2 Price
3 Delivery4 Design and Development Capability
5 Management Systems
Each of these Main Criteria has the scale of 1 to 100 .
Current weightage to each of these Main Criteria is :
1 Quality 50%
2 Price 20%
3 Delivery 20%
4 Design and Development 5%
5 Management System 5%
TATA MOTORS LIMITED
Tata Motors may revise the weightage of these Main criteria according the
relative importance of the same to Tata Motors from time to time .
-
7/28/2019 development of automotive components
20/21
Each of these Main Criteria has been further drilled down in to constituent sub
criteria elements. While the scores on these sub criteria are mainly arrived at
through transactional details of the supplies made by the Supplier through the
system, officers from the related development / purchasing / quality assurance
divisions allot scores to the Suppliers on others.
Sub Criteria and their weightages and method of scoring are as follows:
Quality :Parameter Vendors with WarrantyImpact (Proprietary)Vendors with no WarrantyImpact (Sheetmetal,machining)Incoming inspection 10 10
Line rejection 25 35Audit - 10Quality systema) Quality certification 10 10b) Audit at vendor 15 15Warranty 30 -PPM* 10 20
PPM PPM score
Below 200 100
201 -500 75
501-1000 50
1001 & Above 1Price :
1Price Level 70% Through system
2Price Behavior 30% Through system based on the
price revisions
Delivery:
Till MRP functionality in SAP goes live , this score shall be updated by
concerned officers .
1 On time Delivery 70%
2 Quantity Reliability 30%
Design and Development Effort: 5% Updated by concerned officers
TATA MOTORS LIMITED
Management System 5% Updated by concerned officers
Currently the frequency of the feed back to the Suppliers through this system is
-
7/28/2019 development of automotive components
21/21
once every quarter.
Sample of the Supplier Rating System:
If Supplier scores as follows:
1 Quality : 90
2 Price: 80
3 Delivery: 80
4 Design and Development: 60
5 Management System 80
Then the overall score is worked out by taking the weighted average as follows :
Overall score ={ Sum of the (Weightage of the Main Criteria * Score for that Main
Criterion) }.
Overall Score in the example ={ ( 0.5*90 ) + ( 0.2*80 ) + (0.2*80 )+ (0.05*60 ) + (
0.05*80 ) } = 83 .