developing transport performance measures for construction

160
Developing transport performance measures for Construction Logistic Solutions Master Thesis Author: Farah Naz Supervisor: Anna Fredriksson Examiner: Helena Forslund Term: VT19 Subject: Degree Project in Logistics Level: Master (2nd Level) Course code: 5FE04E

Upload: others

Post on 30-Jan-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Developing transport performance measures for Construction

Developing transport

performance measures

for Construction Logistic

Solutions

Master Thesis

Author: Farah Naz

Supervisor: Anna Fredriksson

Examiner: Helena Forslund

Term: VT19

Subject: Degree Project in Logistics

Level: Master (2nd Level)

Course code: 5FE04E

Page 2: Developing transport performance measures for Construction

2 | P a g e

Page 3: Developing transport performance measures for Construction

3 | P a g e

Abstract

Purpose

The purpose of the study is to identify transport related performance measure

within construction logistics in order to evaluate construction logistics

solution. The aim is also to verify identified transport performance measures

by available empirical data from both cases i.e. Case 1 and Case 2.

Methodology

This study is exploratory case study with qualitative research method. The

research approach of this study is both deductive as well as inductive. Data has

been collected from literature review, semi structured interview, focus group

discussion and empirical data.

Research question (RQ)

RQ1 aims at identifying transport related performance measures and then

classifying them according to terminal, checkpoint and their respective

construction sites? The answer to this question lies in Figure 17 and 18.

RQ2 refers to what kind of data is needed to measure identified transport

performance measures. The answer to this question lies in the analysis of RQ2.

RQ3 is related to what empirical data is available at construction logistics end.

The answer to this RQ3 is that mostly the” duration of activities” has been

found within both cases empirical data which seems to be insufficient to

calculate identified performance measures in RQ3.

RQ4 the aim of RQ4 is to find the gap between needed and available data. And

the answer to this RQ can be found in Table 35.

Conclusion

Theoretical and practical case discussion of Case 1and Case 2 has given an in

-depth view regarding the phenomena of construction logistics solutions. This

paper will help in creating awareness among developer and main contractors

regarding the benefit of construction logistics solution.

Key words

Construction Industry, Construction Logistics, Construction Logistics

Solution, Transport Performance Measures

Page 4: Developing transport performance measures for Construction

4 | P a g e

Acknowledgments

First of all, I want to express my profound gratitude to my supervisor, Anna

Fredriksson, for proposing this topic and for her continuous support and

guidance throughout the process of research and authoring this thesis. I am

also grateful to my examiner Helena Forslund for being very helpful and

providing valuable information and suggestions at each seminar. Besides this,

I also want to thank all the opponents in my class for their positive feedback

during the seminars. I also want to appreciate Linnaeus University for giving

me this opportunity to write this thesis. Finally, a quick thank you to my friend

Prasannjeet Singh for his constructive criticism and also for proofreading the

manuscript.

This research could not have been written without the generous assistance of

my friends and family who always encouraged and supported me throughout

my authorial journey. To all of you, I extend my deep appreciation.

Page 5: Developing transport performance measures for Construction

5 | P a g e

Table of contents

1 Introduction 1

1.1 Background 1

1.2 Problem discussion 3

1.3 Purpose of the study and research questions 5

1.4 Conceptual model for research question 1 6

1.5 Originality/Value of paper and Limitations 7

1.6 Thesis outline 8

2 Methodology 10

2.1 Methodology outline 10

2.2 Research purpose 11

2.3 Research design 13

2.4 Research Method 14

2.5 Research approach 15

2.6 Population and Sampling 18

2.7 Research process 20

2.8 Data collection methods 21

2.8.1 Literature review 21

2.8.2 Semi Structured Interviews 23

2.8.3 Focus group 24

2.8.4 Documentation and statistics 26

2.9 Data Analysis 26

2.10 Research Quality 27

2.10.1 Reliability 27

2.10.2 Validity 28

2.11 Ethical considerations 28

3 Contextual background of the study 29

3.1 Basics of construction industry 30

3.1.1 Construction Process 31

3.1.2 Construction Flows 32

3.1.3 Construction site organization 38

3.2 Significance of construction industry 38

3.3 Supply Chain Management in Construction Industry 40

4 Framework for RQ1 42

4.1 Theory 42

4.1.1 Construction logistics 42

4.1.2 Construction logistics solution 44

4.1.3 Construction site and construction site logistics 49

4.1.4 Performance measures and their importance 51

4.2 Frame of reference for semi structured interviews 60

4.3 Empirical findings from semi structured interviews 63

4.3.1 Case 1-Terminal 64

Page 6: Developing transport performance measures for Construction

6 | P a g e

4.3.2 Case 2-Checkpoint 65

4.4 Combining findings from theory and semi structured interviews 67

4.5 Frame of reference for focus group protocol 69

4.6 Empirical finding from focus group discussion 73

4.6.1 Case 1-Terminal 73

4.6.2 Case 2-Checkpoint 75

4.7 Conceptual model of the study 75

4.8 Analysis 77

4.8.1 Explanation of the consolidated table 78

4.8.2 Other Objectives 80

5 Framework for RQ2 83

5.1 Theory 83

5.1.1 Objective: Effective transport planning 83

5.1.2 Objective: Reduction in transportation time 87

5.1.3 Objective: Transport cost minimization 87

5.1.4 Objective: To achieve environmental sustainability 89

5.1.5 Objective: To ensure security 90

5.1.6 Objective: To ensure safety 90

5.2 Frame of reference 91

5.3 Empirical findings from both Case 1 and Case 2 91

5.4 Analysis 92

6 Framework for RQ3 98

6.1 Empirical data from Case 1 Terminal 98

6.1.1 Analysis 99

6.2 Empirical data from Case 2 Checkpoint 108

6.2.1 Analysis 110

7 Framework for RQ4 113

7.1 Analysis 114

8 Overall analysis 115

9 Conclusion 117

9.1 Further study 118

10 Reference list 119

11 Appendix 137

11.1 Semi structured interview guide for RQ1 137

11.2 Protocol for focus group 139

11.3 Interview guide for research question 2 140

11.4 Excerpts of semi structure interview for RQ2 141

11.5 Snapshot of original data by Case 1-Terminal 142

11.6 MATLAB code for the analysis of Case-1 Terminal Data 144

11.7 MATLAB code for the analysis of Case-2 Terminal Data 150

Page 7: Developing transport performance measures for Construction

7 | P a g e

Table of Figures

Figure 1: Conceptual model of research question 1 (Own illustration) ................................... 7

Figure 2: Dependencies among research questions (Own illustration) .................................... 9

Figure 3: Framework for research questions (Own illustration) ............................................ 10

Figure 4: Deductive Inductive approach (Adopted) .............................................................. 17

Figure 5: Abductive research approach (Adopted) ................................................................ 18

Figure 6: Research process of this study (Own illustration) .................................................. 20

Figure 7: Process for shortlisting publications (Own illustration) ......................................... 22

Figure 8: Contextual background of the study (Own illustration) ......................................... 30

Figure 9: Different phases of construction process (Own illustration) .................................. 32

Figure 10: Material flow in construction project (Adopted) .................................................. 35

Figure 11: Information flow in general construction project (Adopted) ................................ 37

Figure 12: Traditional construction supply chain (Adopted) ................................................. 41

Figure 13: Pictorial explanation for RQ1 theory (Own illustration) ...................................... 42

Figure 14: Shipment consolidation at Terminal (Adopted) ................................................... 47

Figure 15: Modelling of Checkpoint (Own illustration) ........................................................ 49

Figure 16: Activities occur at construction site (Own illustration) ........................................ 51

Figure 17: Conceptual model after theory and empiry (Own illustration) ............................. 76

Figure 18: Consolidated conceptual model after analysis (Own illustration) ........................ 82

Figure 19: A sample path of the vehicle (Own illustration) .................................................. 84

Figure 20: Saving in distance by terminal (Adopted) ............................................................ 85

Figure 21: Fast Companies .................................................................................................. 104

Figure 22: Slow Companies................................................................................................. 104

Figure 23: Most inefficient orders ....................................................................................... 105

Figure 24: Most efficient orders .......................................................................................... 105

Figure 25: Number of Deliveries and Time between Deliveries ......................................... 107

Figure 26: Lognet data sheet................................................................................................ 108

Figure 27: Case-2 Empirical Data ....................................................................................... 109

Figure 28: Standard Deviation Graph for Case-2 ................................................................ 111

Page 8: Developing transport performance measures for Construction

8 | P a g e

Table of Tables

Table 1: Methodology selection (Own illustration) ............................................................... 11

Table 2: Various research purposes (Adopted) ...................................................................... 13

Table 3: Deductive and Inductive approach (Adopted) ......................................................... 17

Table 4: Sampling technique (Adopted) ................................................................................ 19

Table 5: Key words used for searching articles (Own illustration)........................................ 22

Table 6: Semi structured interview cases (Own illustration) ................................................. 24

Table 7: Focus group details (Own illustration) .................................................................... 26

Table 8: Physical flows steps (Adopted) ............................................................................... 33

Table 9: Information flow steps in construction project (Adopted) ....................................... 37

Table 10: Four roles of supply chain management in construction (Adopted) ...................... 41

Table 11: Comparison between terminal and checkpoint (Adopted) ..................................... 49

Table 12: Performance measures related to effective transport planning (Adopted) ............. 56

Table 13: Performance measure for time minimization (Adopted) ....................................... 57

Table 14: Performance measures related to cost minimization (Adopted) ............................ 58

Table 15: Performance measures related to environmental sustainability (Adopted) ............ 59

Table 16: Security related performance measures (Adopted) ................................................ 59

Table 17: Safety performance measures (Adopted) ............................................................... 60

Table 18: Operationalization for semi structured interviews (Own illustration) ................... 63

Table 19: Performance measures highlighted by Case 1 during interview (Own illustration)

............................................................................................................................................... 65

Table 20: Performance measures highlighted by Case 2 during interview (Own illustration)

............................................................................................................................................... 67

Table 21: Focus group protocol (Own illustration) ............................................................... 68

Table 22: Operationalization of focus group protocol (Own illustration) ............................. 73

Table 23: Additional performance measures got highlighted during focus group discussion-

Case 1 (Own illustration) ....................................................................................................... 74

Table 24: Additional performance measures got highlighted during focus group discussion-

Case 2 (Own illustration) ....................................................................................................... 75

Table 25: Consolidated performance measures (Own illustration) ........................................ 78

Table 26: Performance measures to be studied under RQ2 (Own illustration)...................... 83

Table 27: Snapshot of Case 1 (Terminal data translated in English) ..................................... 99

Table 28: Processed table for Efficient/Inefficient Activities .............................................. 101

Table 29: Efficient Orders ................................................................................................... 102

Table 30: Inefficient Orders................................................................................................. 102

Table 31: Slow and Fast Companies.................................................................................... 103

Table 32: Time difference between deliveries ..................................................................... 106

Table 33: Delivery frequency .............................................................................................. 107

Table 34: Case-2 Sort By Company .................................................................................... 110

Table 35: Comparison between required and available data ............................................... 115

Page 9: Developing transport performance measures for Construction

1 | P a g e

1 Introduction

This chapter introduces the research area of this study and tries to define the

important constructs briefly. This is then followed by the problem discussion,

purpose of the study and four research questions. After this, the chapter

introduces the conceptual model of the study and originality/value of the paper

along with limitations. The study outline is also mentioned in this chapter end

to follow subsequent chapters of this thesis clearly.

1.1 Background

Construction industry not only plays an important role in economic

development but also in the lives of almost every individual (Sears et al.,

(2015). Razak Bin Ibrahim et al. (2010) define “construction” as a complex

production of physical infrastructure by the co-operation of temporary teams.

According to United Nations International Standard of Industrial

Classification (ISIC) (2008) “construction industry” is defined as an industry

consisting of firms responsible for building structures such as offices,

hospitals, airports, shopping centers, housing, factories etc. as well as civil

engineering such as infrastructure for water supply, irrigation, transportation,

power generation and the likes. As per Rangelova (2015), construction

industry is complex in nature due to the involvement of multiple stakeholders

and wide connections with other areas such as manufacturing, material

handling, energy, finance, labor, equipment etc. Razak Bin Ibrahim et al.

(2010) are of the view that construction industry owns fundamental position

in converting the aspirations and needs of people into reality by executing

various construction development projects.

In accordance with Andersson and Nilsson (2018), the Swedish construction

industry has turnover of 639 billion SEK, which can be linked to an increase

of 71% over the last decade. They further suggest that Sweden is the fastest

urbanizing country across all of Europe. According to Gothenburg Port

Authority (2016), the rate of construction in Gothenburg and other cities in

Sweden is higher than ever. Due to urbanization, there are many urban

construction projects going on in Sweden (Janné, 2018). “Urban construction

projects” are considered as short-term network of teams in a city premises.

These temporary organizations consist of many phases and in each phase many

participants take part resulting in complexity of construction projects (Janné,

2018; Janné and Fredriksson, 2018).

Page 10: Developing transport performance measures for Construction

2 | P a g e

Vrijhoef and Koskela (2000) explain that many supply chain management

initiatives have been taken within construction industry in the end of 1980’s

in order to enhance internal and external efficiency, minimizing waste and to

add value across entire construction supply chain. They further suggest that

the major initiative of Supply Chain Management (SCM) in construction has

been in the field of “logistics” which is defined as flow of materials, tools and

equipment from the point of release to the point of consumption. Fredriksson

(2018) defines “construction logistics” as providing construction site with

resources in the form of materials, machines and personnel in an efficient

manner along with managing resources efficiently on the construction site

itself as well as ensuring efficient recycling and waste management that

enables circular economy and durability. United Nation (ISIC) (2008) defines

“construction site” as a place where construction activities such as building,

repair, additions and alterations, erection of prefabricated structures etc. take

place.

According to Sullivan, Barthorpe and Robbins (2010), Matouzko and

Methanivesana (2012) and Janné (2018) the future of construction logistics

lies in construction logistics solutions. Janné (2018) defines “construction

logistics solution” as logistic solution applicable in construction projects in

order to coordinate material flows, thus resulting in less transport disruptions

and efficient construction. Sullivan et al. (2010) and Janné (2018) say that

dedicated construction logistic solutions are not widely adopted and is

considered as new phenomenon in the construction industry. Janné (2018)

suggests that there are two types of construction logistics solution i.e. terminal

and checkpoint. He further suggests that the main difference between the two

is that “terminal” co-ordinate deliveries to various construction sites thus

reducing the number of deliveries as well as number of times on-site personnel

has to receive and handle materials whereas “check point” focuses on just in

time deliveries as distinguished from following consolidation approach to

deliveries.

According to Ying, Tookey and Seadon (2018) “performance measures” are

widely used to evaluate the performance of any industry. Epstein and Rejc

(2005) suggest that “evaluation” is a systematic determination of merit, worth

and significance of something. They further suggest that it is an assessment to

determine the worth or fitness of any subject. According to Ying et al. (2018),

measurement of logistics is an important step to improve construction industry

performance. Velimirovic, Velimirovic and Stankovic (2011) suggest that

appropriate selection of metrics to be used for measuring is of great

Page 11: Developing transport performance measures for Construction

3 | P a g e

importance. They call these metrics as performance measures. They further

suggest that performance measures provide information about performance in

the past, performance as of now and the likely performance in the future.

Jahangirian et al. (2017) define “performance measure” as a quantifiable

metric that is used to gauge or compare performance in terms of achieving

strategic and operational goals. The terms “performance measures” and

“performance metrics” have been used synonymously in this study.

Minges (2017) suggests that transport management plays crucial role in

assuring construction logistics competitiveness. He further adds that

measurement and quantification of transport flows within construction

logistics is of prime importance for many researchers and practitioners. In

order to measure and quantify transport flows, Sutton and Austin (2015)

highlight the importance of data collection. According to them, “data

collection” is a process of gathering information empirically as well as

theoretically. By “empirically” they mean data collected by observation and

experience. They further suggest that in order to make informed decisions,

provide solutions to the complex problems, analyze new insights etc. it is

essential to play with the data. Surkis and Read (2015) defines “data” as facts

and statistics collected for the purpose of analysis and finding research results.

Jayasinghe, Sano and Nishiuchi (2015) refer “transport flow” as vehicle

movements or flow of vehicles as well as other activities such as loading,

unloading etc.

1.2 Problem discussion Due to fragmented nature and unwillingness to change, the construction

industry is often considered as backward, inefficient and poorly organized

(Janné, 2018). This has also been advocated by Fellow and Liu (2012),

Ekeskär and Rudberg (2016), Berden (2017), Dubois, Hulthén, Sundquist

(2019). Jensen (2017) suggests that construction industry has remained slow

in adopting the proven benefits of logistics and supply chain management.

Sullivan et al. (2010) suggest that every major industry such as manufacturing

(mainly automotive), retailing, shipping, third party logistics etc. is reaping

benefits from employing logistics whereas construction industry is incurring

heavy costs due to poor logistics management. They further suggest that

effective logistics management is critical for the success of current businesses,

primarily the ones that involve huge supplier networks and just in time

deliveries. According to Sullivan et al. (2010) market forces and labor relations

will ultimately have to trigger adoption of logistics by construction industry.

Page 12: Developing transport performance measures for Construction

4 | P a g e

Once this happen, the actors who are not able to adopt will not survive because

of high costs and waste levels and in this way even if they want to sustain, they

would not be able to continue their operations (Sullivan et al., 2010).

As per Ying et al. (2018) and Dubois et al. (2019) construction project involves

numerous transport related activities which account for 39-58% of total supply

chain costs. Sullivan et al. (2010) also suggest that transport is a major

component of supply chain which is responsible for delivering goods and

services to the construction site. Despite the fact that different industries (such

as manufacturing, retailing, shipping, third party logistics etc.) have achieved

out class performances, cost savings, efficiencies and that they have set various

examples of best practices by implementing logistics, a question still arises as

to why the construction industry is not widely adopting logistics and why is

this not becoming a reality? This reflects a research gap within the area of

construction logistics that besides knowing the benefits of implementing

logistics there is a lack of knowledge within the construction industry about

how these reductions, efficiencies, etc. can be achieved. For this, there is a

need for providing detailed advice to decision makers (such as developers,

contractors etc.) on how construction logistics can be controlled and

effectuated. As of now, decision makers do only have a vague idea of how

they can improve transport flows or how should they organize transport or

employ construction logistics, thus achieving maximum efficiency. This

implies that there is a need to really pinpoint and identify main performance

indicators of transport flows in order to control, manage and improve

construction logistics. This can be justified by Edwards Deming quote

mentioned by Lingard, Wakefield, Blismas (2013);

“If you can’t measure it, you can’t improve it”

(Edwards Deming, 1994)

As construction industry is not well organized in terms of data management

there is need to identify what data is available to evaluate performance and

where data is lacking. Lingard et al. (2013) suggest that Deming means that

one cannot know whether one is successful until success is defined and

tracked. They further suggest that with a clearly established measure for

success, one can quantify progress and adjust to achieve the desired outcomes.

This shows that construction industry is still at its initial stages regarding

transport flow and logistics performance measurements and reality is that very

little is known about construction specific logistics (Dubois, et al., 2019).

Page 13: Developing transport performance measures for Construction

5 | P a g e

1.3 Purpose of the study and research questions The purpose of the study is to identify transport related performance measures

within construction logistics and to see which performance measures are

relevant for terminal construction logistics solution, checkpoint construction

logistics solution and their respective construction site. As mentioned above,

terminal and checkpoint are two types of construction logistics solutions and

are also the focus of this study. These performance measures will be developed

while keeping in mind the common transport strategic objectives such as

effective transport planning, minimizing time for transportation, transportation

costs minimization, achieving environmental sustainability, ensuring safety

and security. Besides this, the study will also throw light upon the availability

of empirical data at construction logistics solutions end (i.e. terminal and

checkpoint) and also a reflection on what further data is needed in order to

calculate identified performance measures accurately. The aim of the study is

to create construction logistics awareness among multiple construction

stakeholders mainly developers and contractors who are the main decision-

making bodies in any construction project. The study will also put emphasis

on the need of organizing transport flows within the Swedish construction

industry.

Following research questions (RQs) have been formulated in order to fulfill

the purpose of the study;

Research Question 1

What performance measures can be used for the evaluation of construction

logistic solutions and their respective construction sites with respect to

transport flows?

Rationale behind RQ1: There are very few studies regarding the transport

related performance measures specifically within the context of construction

logistics. The focus of this research question is to identify transport related

performance measures within “construction logistics”. These identified

performance measures will then be used to evaluate the performance of

construction logistics solutions and their respective construction sites in terms

of transportation. Since construction logistic solution is a new phenomenon

within construction logistics so it is important to measure its performance in

terms of transport flows.

Page 14: Developing transport performance measures for Construction

6 | P a g e

Research Question 2

What kind of data is needed to measure identified transport related

performance measures in research question 1?

Rationale behind RQ2: The focus of this research question is to find out the

way how identified transport performance metrics in research question 1

within construction logistics can be measured quantitatively. The need of data

will be determined by identifying factors or variables that will collectively

form performance measures. Developing formulas and calculations will play

an important role in figuring out the data required to measure identified

transport performance metrics. In other words, RQ 2 is a detailed breakdown

of performance measures identified in RQ1 in the form of formulas and

calculations.

Research Question 3

What transport data is empirically available from construction logistic

solutions?

Rationale behind RQ3: The study aims at verifying the performance measures

identified in research question 1 in order to see that whether those

performance measures are applicable for construction logistic solution

evaluation or not. Therefore, the focus of this research question is to check

what data the cases under study are recording and is it available for cross

checking the identified transport related performance measures.

Research Question 4

What is the gap between required and available data to measure identified

transport related performance measures in research question 1?

Rationale behind RQ4: As the construction industry is not adequately

organized, the odds are high that there would be some missing data, in

addition to the fact that the data might not be present in a ready-to-use format.

The rationale behind this research question is to see what empirical data is

missing, what empirical data is further needed in addition to the available data

to calculate the identified performance measures accurately.

1.4 Conceptual model for research question 1

The conceptual model of research question 1, which is main and independent

research question, is shown in Figure 1 below, where two types of construction

Page 15: Developing transport performance measures for Construction

7 | P a g e

logistic solutions have been mentioned (terminal and checkpoint). The

transport flow has been shown with the help of line with arrows at both ends

representing transport going to construction logistics solution and construction

site and further coming back from construction site to construction logistics

solution. The focus of the paper is on measuring transport flows performance

(i.e. mainly vehicle movement, flow of vehicles, loading, unloading, material

handling activities etc.) only under the concept of construction logistics within

construction industry. The purpose of the RQ1 has been shown by mentioning

performance measures boxes on different construction logistics solution and

their respective construction sites. In checkpoint construction logistics

solution, transit (which is a route or a journey from one place to another) comes

before checkpoint whereas in terminal construction logistic solution, transit

starts when vehicle leaves the area around terminal and is referred as journey

between terminal and construction site.

Figure 1: Conceptual model of research question 1 (Own illustration)

1.5 Originality/Value of paper and Limitations The study will help in developing transport related performance measures

within construction logistics as very few studies have discussed transport

performance measures in the context of construction industry. This study will

Terminal

Construction Site

*Performance measures are related to transport flows only Transport Flows

Transport related performance measures to, from and within the construction site

Checkpoint

Performance Measures

Transit Performance

Measures

Transit Performance

Measures

Site Performance Measures

Site Performance Measures

Performance Measures

Construction Site

Construction Logistics Solution

Construction Logistics

Page 16: Developing transport performance measures for Construction

8 | P a g e

provide an overview that which performance measures belong to which

construction logistic solution. This will give further insight regarding

construction logistics solution evaluation (i.e. what performance measures are

similar among terminal, checkpoint and their respective construction site and

what varies). In this way, the study will contribute in improving the

performance of construction logistics solutions by letting developer and main

contractor know where to focus their efforts. The study will provide deeper

understanding to developers and main contractors regarding available versus

required data to quantify transport performance measures. This study will

guide the decision makers (i.e. developer and main contractor) that what

further data they should consider and enter into their database in order to

evaluate performance measure accurately.

Overall, the study will enhance knowledge for all the actors involved in the

construction project such as client/owner, sub-contractor, suppliers, designers

etc. but mainly developers and main contractor. In this way, the thesis will not

only contribute theoretically but practically as well by digging deep into the

data and acting as major step towards further establishment of logistics in the

future construction industry.

As very few studies have mentioned transport related performance measures

within construction logistics so for developing construction transport

performance measures other industries such as manufacturing, retailing, third

party logistics (TPL) have been consulted. Due to fragmented and unstructured

nature of construction industry, it is difficult to find relevant data for

calculating performance measures precisely. In addition to this, the data has

been stored in a very disorganized way thus requires so much time to make it

in a ready to use format. Besides this, the study has been conducted from the

perspective of construction industry so the findings of the study cannot be

generalized to other industries. Due to time constraint, the scope of the study

is limited to transportation performance measures only.

1.6 Thesis outline After introduction, the next chapter (chapter 2) will discuss methodology of

the thesis. This will include research purpose, research design, research

approach, data collection methods, research quality mainly. Then chapter 3

will discuss contextual background of the study. The aim of this chapter is to

develop basic knowledge about construction industry. In addition to this, the

chapter will throw light upon the significance of construction industry. The

role of supply chain management in the construction industry is also

Page 17: Developing transport performance measures for Construction

9 | P a g e

mentioned in this chapter. Following this chapter, all four research questions

formulated in introduction chapter (Chapter 1) will be discussed one by one

each having its own theory, frame of reference (operationalization), empiry

and analysis. Research question 1 will consider all sections i.e. theory, frame

of reference, empiry and analysis whereas research question 2 will use the

same frame of reference (operationalizations) as used by research question 1,

research questions 3 do not require theory and will only incorporate empiry

and analysis whereas research question 4 is all about analysis. The reason for

responding each research question separately is because of dependencies

among research questions. For example, research question 2 is dependent on

the findings of research question 1 which by itself is independent research

question. Likewise, research question 4 is dependent upon the findings of

research question 1, 2 and 3. Like research question 1, research question 3 is

also independent research question. The dependencies among research

questions can be understood by following Figure 2;

It can be seen from above diagram that RQ1 and RQ3 both are independent

research questions whereas RQ2 is dependent upon the findings of RQ1. RQ4

is also dependent upon the findings of RQ2, RQ3 and RQ1. After contextual

background chapter, all four research questions will be studied under their own

chapter and each chapter will have more or less all sections such as theory,

frame of reference (operationalization), empiry, analysis (where applicable).

The thesis structure regarding these research questions can be shown in the

following Figure 3. After this an overall analysis will be made following the

conclusion.

RQ1

RQ2

RQ3

RQ4

Figure 2: Dependencies among research questions (Own illustration)

Page 18: Developing transport performance measures for Construction

10 | P a g e

2 Methodology

This section discusses the methodological considerations that have been

employed in this dissertation. It begins with research purpose, design, method

and approach. After this population and sampling has been done. Then

research process for this study has been explained followed by data collection

methods and data analysis. The methodology chapter will be concluded with

research quality and ethical considerations.

2.1 Methodology outline The methodology outline is given in Table 1 below;

RQ1

Theory

Frame of reference

Empiry

Analysis

RQ2

Theory

Frame of reference

Empiry

Analysis

RQ3

Empiry

Analysis

RQ4

Analysis

Figure 3: Framework for research questions (Own illustration)

Page 19: Developing transport performance measures for Construction

11 | P a g e

Methodology Selected Methodology

Research purpose Exploratory

Research design Case study

Research method Qualitative

Research approach Deductive with traces of induction

Sampling Purposive

Research process Iterative

Data collection methods Literature review, individual and

group interview, focus group,

documents and statistics

Data analysis 4 types of analysis

1.Consolidation and grouping of

performance measures

2. Theory and personal knowledge

and experience

3. Data analysis by using MATLAB

and Excel

4. Based on the findings of RQ1,

RQ2 and RQ3

Research quality External validity, construct validity

and internal and external reliability

Ethical considerations Anonymous and informed

respondents

2.2 Research purpose

According to Yin (2018) research projects can be classified into three research

purposes i.e. exploratory, descriptive and explanatory. Saunders et al. (2016)

suggest that in addition to these three above mentioned research purposes there

are two more research purposes (i.e. evaluative and combined). Yin (2018) and

Saunders et al. (2016) suggest that “exploratory” research provides initial

groundwork for future research. They further suggest that in exploratory

studies the focus is on open questions starting with words such as “how” and

“what”. They further suggest that exploratory study makes researcher to

understand certain phenomena in detail, to seek new insights and to find out

what is happening by asking various questions. Yin (2018) suggests that

exploration can be done with literature research, a focus group discussion or

case studies. He further suggests that data from exploratory study is mostly

qualitative in nature.

“Descriptive” studies according to Saunders et al. (2016) describe people,

Table 1: Methodology selection (Own illustration)

Page 20: Developing transport performance measures for Construction

12 | P a g e

products and situations. They further suggest that descriptive studies are done

when there is need to describe characteristics and functions of an event. The

aim of descriptive study is to obtain complete and accurate information by

careful planning of research process (Saunders et al. 2016). According to them,

the descriptive study answer questions such as “how”, “what”, “when”,

“where” or “who”. As far as, “explanatory” research is concerned, Saunders

et al. (2016) suggest that it focuses on cause and effect relationship between

different variables. They further suggest that the main purpose of explanatory

research is to explain why certain phenomena takes place and how future

occurrences can be predicted. Yin (2018) suggests that explanatory research

answer questions such as “how” or “what”. Besides this, Saunders et al. (2016)

highlights that “evaluative” research focuses on the process of gathering and

analyzing information to provide feedback and improve effectiveness. They

suggest that evaluative research aims at collecting and analyzing information

regarding activities, characteristics and outcomes of a phenomenon. They

further suggest that evaluative research answer questions such as “when”,

“where”, “which” or “who”. Yin (2018) and Saunders et al. (2016) suggest

that one study can have two or more research purposes thus resulting in

“combined studies”.

The research purposes have been shown in Table 2 below;

Page 21: Developing transport performance measures for Construction

13 | P a g e

Research Purposes Prime focus Answering questions

Exploratory Seeks to formulate new

problems for the

discovery of ideas and

thoughts as well as

more precise

investigation into the

subject matter

“how” and “what”

Descriptive Documents the

existence of certain

social conditions at a

given moment or over

time

“how”, “what”,

“when”, “where” or

“who”

Explanatory Emphasize the testing

of theoretically

significant hypothesis

“how” or “what”

Evaluative Seeks explanations of a

program´s success or

failure

“when”, “where”,

“which” or “who”.

Combined Combine above

mentioned research

purposes

Answers combination

of above-mentioned

research questions

As far as the research questions for this study are concerned, this study is

exploratory in nature because the purpose is to investigate the phenomena of

construction logistics solution.

2.3 Research design

According to Saunders et al. (2016) “research design” is a framework that

guides researcher about answering the research questions of the study. Bryman

(2012) suggests that a “research design” is a framework for the collection and

analysis of data. He further suggests that there are five prominent research

designs which are as follows;

- Experimental design (such as quasi experiment)

- Cross-sectional design (most common form is survey research)

- Longitudinal design (such as panel study and cohort study)

- Case study design

- Comparative design

Table 2: Various research purposes (Adopted)

Page 22: Developing transport performance measures for Construction

14 | P a g e

The research design used in this study is “case study design”. According to

Baxter and Jack (2008) and Bryman (2012) case study design aims at studying

complex phenomenon with detailed and intensive analysis. Saunders et al.

(2016) define “case study” as a research design which involves empirical

investigation of special existing phenomenon within its real-life context using

multiple sources of evidence. They further suggest that case study research

design best suits when the purpose of the study is to gain a rich understanding

of the research context and research processes. Saunders et al. (2016) explain

that as case study design answer “what” questions so it is more often used in

studies having exploratory research purpose.

Single versus multiple case study

Yin (2003) distinguishes between the cases based on single versus multiple

case dimension. According to him, a “single case” represents critical case or

an extreme and unique case. He further suggests that single case is selected

when it provides the researcher an opportunity to observe and analyze a

phenomenon rarely studied or observed before. He adds on that when there is

more than one case then the study is referred as multiple case study. He

explains that multiple case study is used when there is need to establish some

connection between the two cases i.e. whether the findings of the first case

also match with the findings in other case so that the results can be generalized.

As Yin (2003) suggests that multiple case study is preferable to a single case

study so in this study multiple case study has been chosen.

Unit of analysis (Holistic versus embedded)

Yin (2003) suggests that the other dimension on which cases can be

distinguished is “unit of analysis”. He suggests that the unit of analysis is

“holistic” when researcher study the case organization as unified whole

whereas if the researcher examines departments, workgroups, sub-units within

the organization rather than treating it as a unified whole then it would be

considered as “embedded” unit of analysis. In this study holistics unit of

analysis is considered because data has been collected only from one unit i.e.

transportation/vehicle flows.

2.4 Research Method

Saunders et al. (2016) suggest that there exist three research methods for

carrying out research (i.e. Qualitative, Quantitative and Mixed). Bryman

(2012) suggests that “quantitative research method” deals with the collection

and analysis of data in numeric form (quantitative data). They suggest that

quantitative method is objective, standardized, structured and emphasize

Page 23: Developing transport performance measures for Construction

15 | P a g e

relatively large scale and representative sets of data. But due to variable control

and other restrictions quantitative method produce trivial findings of little

consequence (Bryman, 2012). It can be said according to Bryman (2012) that

quantitative research methods aim at testing the theory. While throwing light

upon “qualitative research method” Saunders et al. (2016) suggest that it is

more open and responsive to its subject. They suggest that qualitative research

strive to capture experience as close as possible to what participants feel or

live. They further suggest that it involves collection of non-numeric

information referred as qualitative data. They suggest that although qualitative

research method provides deeper understanding but at the same time it is hard,

complicated and more time consuming. It can also be said that qualitative

research methods play an important role in theory generation rather than

testing it (Bryman, 2012). Saunders et al. (2016) suggest that some studies

incorporate both qualitative and quantitative research methods in order to

obtain comprehensive and holistic view by filling the gaps offered by both

methods. They explain that the combination of both research methods i.e.

qualitative and quantitative then result in mixed method research.

As the focus of this study is on words so “qualitative research method” is

being used in this study.

2.5 Research approach

Bryman (2012) suggests that there are two main approaches towards research

i.e. deductive and inductive. He explains that these approaches are classified

based on relationship between theory and research. He further explains that

research approach directs the researcher that when and how theory is to be

collected. Saunders et al. (2016) suggest that a researcher follows deductive

approach when he/she first collects the theory and after finalizing it moves to

the next step of data collection. Bryman (2012) suggests that in case of

deduction, researcher test the developed theory with the help of collected data.

In other words, it can be said that deductive approach begins with theory

development and then theory guides the researcher what data is to be collected

in order to verify the theoretical findings (Yin, 2018). According to Saunders,

et al. (2016) deductive approach is quicker to complete because while

developing theory researcher gets the clear idea of the required data and

afterwards data is collected in one go. They also highlight that it is easy to

predict accurate time schedules in deductive approach. Whereas Saunders et

al. (2016) suggest that in case of inductive approach, researcher develop theory

after collecting data. They further suggest that based on data analysis

Page 24: Developing transport performance measures for Construction

16 | P a g e

theoretical data is collected (i.e. theory follows data analysis). They also

explain that inductive research approach is time consuming because it requires

longer period of data collection and analysis to extract the useful meanings

from the data. The deductive and inductive approach have been explained in

the Table 3 below;

Page 25: Developing transport performance measures for Construction

17 | P a g e

Deductive approach Inductive approach

Moving from theory to data Moving from data to theory

Collection of quantitative data Collection of qualitative data

Highly structured approach More flexible approach and allow

changes in research purpose as the

study progresses

Require representative samples of

larger size in order to generalize

results

Less concerned with the need to

generalize

Low risk strategy (no response risk

mainly)

High risk (chances of no useful data

patterns or theory emergence)

Explanation of causal relationships

between variables

Close understanding of the research

context

Operationalization of concepts to

have clear definitions

Researcher is part of the research

process

This can be shown by below Figure 4;

In addition to this, there is third type of research approach known as “abductive

approach” in which the researcher mixes both research approaches (i.e.

deductive and inductive). Saunders et al. (2016) suggest that abductive

approach overcome the weaknesses of both deductive and inductive

approaches. They explain that the main weakness of inductive approach is that

it is incomplete (i.e. it is hard to get 100% results) and can lead to false

conclusions even with accurate observations whereas the main weakness of

deductive approach lies in its assumption that initial premises are correct but

if one or more premise turn incorrect then whole argument becomes invalid

Theory

Observations/Findings

Observations/Findings

Theory

Deductive approach Inductive approach

Table 3: Deductive and Inductive approach (Adopted)

Figure 4: Deductive Inductive approach (Adopted)

Page 26: Developing transport performance measures for Construction

18 | P a g e

and unsound.

Saunders et al. (2016) suggest that unlike deductive and inductive research

approach, abductive research can explain, develop or change the theoretical

framework before, during or after the research process. They further suggest

that abductive research moves back and forth between inductive and open-end

research settings to more deductive attempts of hypothesis verification.

Abductive research approach has been used in this study because there is less

theory and the aim is to develop more theory with the help of empiry. This is

shown below in Figure 5;

2.6 Population and Sampling Saunders et al. (2016) suggest that it is important to define research population.

According to them, the full set of cases from which a sample is taken is

considered as “population”. They further suggest that it is impossible to collect

data from whole population due to certain constraints such as size,

accessibility, time, cost etc. Due to this fact, they emphasize the need of

targeted population which is population of construction logistic solution in

Sweden for this study. The target population for this study is small. Further

sampling has been done from this small targeted population. They highlight

the importance of sampling by mentioning that sampling saves time, data

collection becomes more manageable due to fewer subjects involved, analysis

gets quicker because of less amount of data and so on.

Bryman (2012) suggests that sampling can be done on the basis of two

techniques i.e. probability or representative sampling and non-probability or

judgmental sampling. He further suggests that when there is equal and known

chance for each case to get selected then this is referred as probability sampling

Figure 5: Abductive research approach (Adopted)

Page 27: Developing transport performance measures for Construction

19 | P a g e

whereas when the chance of case being selected is unknown then this can be

considered as non-probability sampling. Saunders et al. (2016) further

classifies probability and non-probability sampling techniques which are as

follows in Table 4;

Sampling

Probability Sampling techniques Non-Probability sampling

techniques

- Simple random - Quota

- Systematic - Purposive

- Stratified random - Snowball

- Multistage cluster - Convenience

Purposive sampling has been done in order to answer research objectives of

this study. Because cases have been selected with the purpose of studying

construction logistics solution phenomena. Saunders et al. (2016) suggest that

generally case studies use purposive sampling because of small sample size

and need of informative cases.

Selection of cases

As the purpose of the study is to explore construction logistic solution

phenomena within construction logistics, so very few companies are operating

in this field. For this study one company has been chosen from terminal and

one from checkpoint.

Saunders et al. (2016) suggest that cases are selected on the basis of following

criteria such as able to address the research questions raised in a study and case

should be real world phenomena that has some concrete manifestation/should

not be an abstraction.

Case 1-Terminal is a construction logistics solution located in Linköping for

a project called Urban Escape, which is at the heart of Stockholm, Sweden.

Urban Escape is a largest urban development project consisting of houses,

offices, hotels, shops, restaurants, cafes, bars, and meeting places

(Urbanescape, 2019). The case 1 is responsible for making deliveries from

suppliers to the construction site by using a principle of consolidation.

Case 2-Checkpoint is a construction logistics solution located in Linköping

for a project called Ebbepark, which is at the heart of Linköping, Sweden.

Table 4: Sampling technique (Adopted)

Page 28: Developing transport performance measures for Construction

20 | P a g e

Ebbepark is a construction project offering new opportunities and workplaces

such as schools, housing apartments, offices, leisure activities etc. to the

people of Linköping. The case 2 is also responsible for making deliveries from

suppliers to the construction site by using just in time delivery schedule.

2.7 Research process The steps involved in the research process for this study are shown in the

Figure 6 below;

This section will provide the general overview of the steps involved in the

research process, the details of which will be explained later in this chapter in

section 2.8 (data collection methods) and 2.9 (data analysis). In order to get

better understanding of the thesis topic, literature review was conducted as first

step. While doing literature review, it was found that very few articles discuss

transport related performance measures within construction industry. This

raised the need of interviews with selected cases in order to get better hold of

the subject matter and to develop good theory regarding transport performance

measures as far as construction logistics is concerned. Both individual and

group interviews were arranged depending upon the availability of intervieews

within each case. This is the second step in the research process. With the help

of theory and interviews, a protocol for focus group has been developed. The

purpose of focus group is to have an expert opinion regarding the identified

transport performance measures and their relevance. The focus group

discussion has also helped in developing understanding that how transport

related performance measures varies among terminal, checkpoint and

construction site. This can be called as step three in the research process. After

having focus group discussions, the step four and step five is to do analysis for

research question 1 and research question 2 respectively. After analyzing the

first two questions, data from cases were collected as step six in order to

empirically verify the performance measures identified in first two research

questions. After collecting and analyzing data, the answers to research

questions 3 and 4 were given. This is considered as the last steps i.e. step seven

Literature

review

Individual

&

Group

Interviews

Focus

Group

Analysis of

RQ1

Analysis of

RQ2

Data from

cases

Analysis

of

RQ3

Analysis

of

RQ4

Figure 6: Research process of this study (Own illustration)

Page 29: Developing transport performance measures for Construction

21 | P a g e

and eight in the research process.

2.8 Data collection methods The data collection method used in this study are literature review, interviews

both individual and group, focus group and case documents and statistics. The

detailed data collection methods will be discussed one by one below.

2.8.1 Literature review

Literature review is the secondary data used in this study. O´Reilly and

Kiyimba (2015) describe “secondary data” as data collected by someone else

other than the researcher him/herself. According to them, existing available

resources can be considered as secondary data (for example, research reports,

reference books, electronically published articles and so on. In order to answer

research questions 1 and 2 literature review has been conducted. Electronic

means have been used in order to gather secondary data for this study. Figure

7 shows the search technique applied to obtain the list of publications used in

this study. Database such as Google scholar has been used as the primary

search engine because it contains large number of quality sources including

the ones by the most reputable publishers such as Elsevier, ResearchGate,

Emerald insight etc. The other sources used are One Search, Diva and Scorpus.

All journals and research articles used in this study are related to construction

industry and transportation. Peer review articles are given preference. In order

to use valid and trustworthy source, publication institute and citations are

given much importance. Few articles are not available in full text so “Abstract”

has been used in order to understand the findings of those research articles.

HBR articles have also been studied in order to understand latest

advancements in this area. The initial aggregation resulted in approximately

146 publications which are then shortlisted to 90 publications. The process of

shortlisting publication is shown below in Figure 7;

Page 30: Developing transport performance measures for Construction

22 | P a g e

The initial list was manually investigated to select the most recent and relevant

publications. Publications in language different than English or not accessible

were discarded. In order to find relevant articles snowballing technique was

also used. This practice of back tracing remained quite effective and helped in

finding credible literature. Some secondary or tertiary studies such as survey

papers, dissertations, systematic literature reviews were also considered if they

appeared to be relevant. The key words used for searching relevant sources are

shown in the Table 5 below;

List of search key words

-Construction industry -Terminal

-Construction supply chain -Checkpoint

-Construction logistics -Construction Site

-Construction process -Performance measures

-Construction logistics solutions -Transport related performance

measures

-Construction performance

measures

-Calculations for transport

performance measures

Initial List

Other

Sources

One search

Scopus

Ecluding

Non-English

Papers

Excluding

Non-Accessible

Papers

Snowballing

Excluding

Old

Publications

Manual

Selection

Shortlisted

Publications

Google Scholar

Figure 7: Process for shortlisting publications (Own illustration)

Table 5: Key words used for searching articles (Own illustration)

Page 31: Developing transport performance measures for Construction

23 | P a g e

Harvard referencing style has been used throughout the thesis and sources of

the data can be viewed in the reference list.

2.8.2 Semi Structured Interviews

Semi structured interviews are the primary data used in this study. O´Reilly

and Kiyimba (2015) refer “primary data” as data specifically gathered by the

original researcher for his/her research purposes. In order to get good

understanding of transport performance measures within construction

logistics, interviews were conducted in order to get answers for research

question 1 and 2 due to insufficient amount of relevant theory.

According to Bryman (2012), semi structured in depth interviews are widely

used for case study research. In this study, semi structured interviews are

conducted in order to get deep understanding of transport performance

measures being used in construction logistics by selected cases. Saunders et

al. (2016) suggest that semi structured interviews are given preference in

qualitative study because it allows researcher to get rich and detailed answers

along with deep idea of intervieew´s point of view. Bryman (2012) suggests

that in order to have effective semi structured interviews, there is a need to

develop “interview guide”. According to Saunders et al. (2016), interview

guide for semi structured interviews can be formulated based on previous

literature, personal knowledge, field experience and information gathered

from preparatory work. The similar approach has been followed in preparing

interview guide for this study.

Two interviews have been conducted for getting deep understanding regarding

transport performance measures within construction logistics. The interview

conducted with Case 1-Terminal was group interview whereas the Case 2-

Checkpoint interview was individual. Both interviews were conducted face to

face for the period of two hours. According to Bryman (2012), it is good to

conduct face to face interviews because it allows researcher to collect more in-

depth data and comprehensive understanding due to clear body language and

facial expressions. He further suggests that face to face interview gives an

interviewer the opportunity to probe for more explanations regarding

interviewees responses. The interview details are mentioned in Table 6 below;

Page 32: Developing transport performance measures for Construction

24 | P a g e

2.8.3 Focus group

In order to have expert opinion and focused discussion on performance

measures identified via literature review and semi structured interviews, two

focus groups have been conducted i.e. One for the Case 1 and one for Case 2

consisting three to four participants excluding moderator/facilitator each. The

participants of the focus group are selected based on their expert knowledge

in the field. The purpose of the focus group was to see that whether the

identified performance measures are relevant to Case 1 and Case 2 along with

their respective construction sites.

Primary data has been collected by using focus group in order to answer RQ1

and RQ2. While explaining “focus group” Bryman (2012) suggests that it is a

form of group interview aims at focused discussions in which there are several

participants (usually at least 4) in addition to the moderator/facilitator.

According to him, the person who runs the focus group session is usually

called the moderator or facilitator and he or she is expected to guide each

session. The whole discussion revolves around this focus group protocol

which has resulted from literature review and semi structured interviews.

Interviewed cases

Case Industry

area of

interviewed

case

Number of

respondents

Position of

respondent

Date of

the

interview

(ddmyyyy)

Duration

of the

interview

in hours

Type of

interview

Case 1-

Terminal

Construction

logistic

solution

3 Founder of

case

company,

Sales

executive,

Business

unit

manager

14.1.2019 2 Group

interview

Case 2-

Checkpoint

Construction

logistic

solution

1 Logistic

consultant

at case

company

14.1.2019 2 Individual

interview

Table 6: Semi structured interview cases (Own illustration)

Page 33: Developing transport performance measures for Construction

25 | P a g e

The details about the focused group are presented in the following Table 7,

including the case company´s area of business, the position of the focus group

participants, the date and duration of focus group along with number of

participants involved.

Focused group Case Industry area

of case

Number of

participants

Position of

participants

Date of the

focus

group

(ddmyyyy)

Duration of

the focus

group in

hours

Case 1-

Terminal

Construction

logistic

solution

5

Business

unit

manager of

case

company,

founder of

case

company,

PhD

researcher at

Linköping

University,

Master´s

degree

student,

Associate

professor at

Linköping

University

(Moderator)

04.4.2019 2

Case 2

Checkpoint

Construction

logistic

solution

4 Logistics

consultant at

case

company,

PhD

researcher at

Linköping

University,

Master´s

degree

student,

Associate

professor at

15.4.2019 1

Page 34: Developing transport performance measures for Construction

26 | P a g e

Linköping

University

(Moderator)

2.8.4 Documentation and statistics

For research question 3 and 4, the use of primary data such as company

documents and statistics has been collected for both cases. Bryman (2012)

suggests that information through documents and data play very important role

for researchers who are conducting case studies. Cases documents are used to

get the overview and progress of the projects that these cases are involved

with. And the data has been used in order to see that whether the identified

performance measures can be measured with this data or not and if not then

what further data is needed. This also gave insight that how these two cases

are recording data at their end. The data provided by Case 1 consists of order

numbers, company codes, activity codes and their descriptions, date of

activities, time taken in performing activities, internal markings mainly. This

data has been provided for the period of 5 months. The case 2 data consists of

delivery ID, company name, vehicle arrival, vehicle departure, duration,

summary of activities performed, date, projects, unloading site, supplier,

number of vehicles and type of vehicles. This data provided by Case 2 is

through portal named as “Lognet”. The data in the “Lognet” is not exportable.

So, one-week data has been manually entered in Excel in order to answer

research questions 3.

This study incorporates an additional quality of “iterative data collection”. The

use of this data collection process increases the level of flexibility during the

research. Bryman (2012) describes iterative data collection process when a

researcher does a reflection about the theory and collected data. He further

suggests that it happens when the researcher weave back and forth between

data and theory to ensure that correct data is collected for the assumptions.

According to him, when the researcher wants or requires further information

to verify the strength of theory, he/she can go back and get more data.

2.9 Data Analysis Four analysis has been conducted in this study due to the presence of four

research questions. The analysis for first research question is made by

Table 7: Focus group details (Own illustration)

Page 35: Developing transport performance measures for Construction

27 | P a g e

consolidating performance measures. The consolidation has been done in

order to remove duplication and redundancy among identified performance

measures. The other reason for doing consolidation is to have few but

comprehensive performance measures. In this way it will become easy to

monitor performance measures. The selection of performance measures (for

consolidation) has been done based on ease of calculation.

For research question 2, the analysis has been done on the basis of theory and

personal knowledge and experience. Empirical findings remain unable to

provide deep insights into the subject at hand.

For research question 3, the analysis has been done using numerical computing

programs such as Matlab and Excel. Besides this, the findings such as efficient,

inefficient orders and fast and slow companies have been made by using data

provided by Case 1. Standard deviation and mean are calculated in order to

see the variation among data entries in the data provided by Case 2. Graphical

analysis has also been done to show the findings.

The analysis of research question 4 has been done on the basis of findings from

research question 2 and research question 3 mainly. As this research question

is to find a gap between needed and available data. So, reflection has been

made on this research question.

2.10 Research Quality According to Bryman (2012) the most important criteria for research quality

are reliability and validity. He further suggests that these criteria have always

remained a question mark for qualitative studies because of its subjective

nature.

2.10.1 Reliability

Bryman (2012) suggests that there are two types of reliability i.e. external

reliability and internal reliability. Saunders et al. (2016) suggest that external

reliability is concerned with the repeatability of the study results. In other

words, it can be said that what is the possibility to exactly replicate the research

findings. In qualitative research, to maintain external reliability is challenging

because the social environment and the conditions keep on changing. It is very

difficult to produce exact same results when using interviews and focus groups

as data collection method (Bryman, 2012). In this study, external reliability

has been assured by providing interview guide and protocol for focus group in

Appendix 1 and Appendix 2. If needed, all the notes taken during interview

and focus group session can also be provided.

Page 36: Developing transport performance measures for Construction

28 | P a g e

Bryman (2012) further discusses the second type of reliability which is

internal reliability. According to him, internal reliability deals with

consistency while conceptualizing measures. In other words, it can be said that

it deals with a question that whether the measures that are devised for concepts

in the study are consistent or not. Internal reliability in this study has been

assured by making use of different data collection techniques and by

discussing with supervisor that whether the results have been interpreted in a

correct way as they were supposed to be interpreted. In addition to this,

different researchers’ opinion who has similar background knowledge has

been considered several times to ensure consistency in defining the key terms.

2.10.2 Validity

According to Yin (2018) and Saunders et al. (2016) there are three types of

validity i.e. external validity, construct validity and internal validity. Bryman

(2012) suggests that in case of exploratory studies external validity is very

important to ensure whereas internal validity plays a crucial role for

explanatory research. As this study is exploratory study, so not much

consideration has been given to internal validity in this study.

Saunders et al. (2016) suggest that external validity deals with a question

whether the results of the study can be generalized beyond the specific

research context. Although the aim of the study is to develop performance

measures for construction logistics solution so this may lead to the formulation

of performance measures for other construction logistics solutions involving

transportation flows and vehicles such as trucks.

Yin (2018) suggests that construct validity refers to a degree that how well

researcher has measured the constructs that he/she claimed to measure. In this

study, construct validity has been ensured by identifying the right operational

measures for the terms used. The terms under study has been defined in a

measurable way and this has been done through operationalization of all-

important concepts. Besides this, same terminologies and wordings have been

used throughout the study in order to give a clear idea to the reader.

2.11 Ethical considerations According to Bryman (2012), Saunders et al. (2016) and Yin (2018) it is very

important to consider ethics while conducting research and gathering

empirical data. They further suggest that it is important to give respondents

and participants enough information about the significance of the study, how

this study will be conducted, how the answers will be handled and used and

Page 37: Developing transport performance measures for Construction

29 | P a g e

why is there need to conduct this study. In addition to this, it is essential to

take participant’s consent that whether they want to take part and contribute in

the research or not. In addition to this, it is important to ask if it is allowed to

record respondents’ responses or not. It is also necessary to know that

participants want to disclose information about themselves or prefer to remain

anonymous.

The purpose of this study is to create awareness and contribute theoretically

so this study can be used and transferred to other purposes. There are certain

ethical considerations made in this study such as company names have been

kept anonymous. Instead, case 1 terminal and Case 2 checkpoint has been used

in this study. Very less information has been disseminated while describing

the cases. In order to maintain anonymity, the company’s sources are not listed

in the text, appendix and reference list. Names of the participants will not be

mentioned throughout the study. In addition to this, all respondents were sent

interview questions and focus group protocol well before in time so that they

can prepare their responses and think about their responses. No recordings

have been done during the interview and focus group discussions whereas

detailed notes have been taken.

3 Contextual background of the study

In this chapter, the contextual background of the study will be discussed. The

study is being conducted from construction logistics perspective within the

construction industry. This gives rise to the need of understanding the basics

of construction industry (construction process, construction flows i.e. physical

and information flow and construction site organization) and its significance.

It is also important to know the role of supply chain management within

construction industry. The contextual background will set the stage for all

research questions being studied in this thesis.

The pictorial view of contextual background chapter has been shown below in

Figure 8.

Page 38: Developing transport performance measures for Construction

30 | P a g e

3.1 Basics of construction industry Razak Bin Ibrahim, et al. (2010) state that “construction” is the activity of

creating and repairing physical immobile structures and related facilities. They

suggest that schools, houses, hospitals, airports, railways, factories, shopping

malls are some of the examples of construction. Hughes, et al. (2015) advocate

above definition and consider “construction” as economic activity aimed

towards creation, renovation, repair or extension of fixed assets in the form of

buildings, land improvements, roads, bridges, dam etc.

According to Razak Bin Ibrahim, et al. (2010), “construction industry”

comprises of companies involved in the construction of buildings and other

structures, heavy construction, additions, alterations, reconstruction,

installation, maintenance and repairs. They also add that companies

responsible for destruction or flattening of buildings, clearing of building sites

and sale of wreckage also come under the definition of construction industry.

This can be summarized by United Nations (2013) definition of construction

industry that is a sector of national economy that handles land preparation and

development. It involves repair and remodel property too.

Contextual background of the study

Section 3.2

Significance of

construction industry

Section 3.1

Basics of

construction industry

Section 3.1.1

Construction

process

Section 3.1.2

Construction flows

Section 3.1.3

Construction

site organization

Section 3.1.2.1

Physical flow

Section 3.1.2.2

Information flow

Section 3.3

Supply chain management

in construction industry

Figure 8: Contextual background of the study (Own illustration)

Page 39: Developing transport performance measures for Construction

31 | P a g e

Sears, et al. (2015) suggest that construction team involves architects,

engineers, craft workers, specialty contractors, material suppliers, designers,

main contractor, project manager and client/owner mainly. They further

suggest that construction work is done by contractors which differ in size and

skill set. Some contractors are specialized in some tasks of construction project

and are known as specialty contractors whereas there are general contractors

who are responsible for broader construction tasks. General contractors

subcontract specialty contractors for specific tasks and in this way a network

of general and specialty contractors come into existence.

Razak Bin Ibrahim, et al. (2010) suggest that construction companies work in

an uncontrollable environment i.e. outside in the field and is susceptible to

number of various variables and unpredictable factors. Peiffer (2015) suggests

that there are three categories of construction industry i.e. building

construction industry, heavy construction industry, and special trade

construction industry. The focus of this study is mainly on building

construction category.

3.1.1 Construction Process

Sears, et al. (2015) state that “construction projects” are complicated and time

consuming. They suggest that construction project generally gets completed

in the form of several phases such as planning and definition, design,

procurement and construction and project completion. All these phases require

a lot of supervision, monitoring and diverse range of specialized services (such

as electrical, concrete, excavation, piping, roofing etc.).

According to Odeh (2019) construction projects/process starts with a

client/owner who then communicate his/her idea to consultant/project

manager or a designer. Sears, et al. (2015) suggest that client/owner is the one

who initiates the construction process by identifying the need for a new

facility. They further suggest that generally client sets the project boundaries

in terms of budget and other requirements. After “need identification and

sharing” “planning phase” starts in which broad project characteristics are

discussed such as location, performance goals, size, layout, configuration,

equipment, services and so on. Odeh (2019) suggests that after conceptual

planning, the work on preliminary “design phase” starts. Sears, et al. (2015)

suggest that design phase incorporates architecture and engineering design of

whole project such as working drawings and specifications. Odeh (2019)

suggests after client´s approval the design gets finalized. He further adds that

after design selection the “procurement and construction phase” begin.

Page 40: Developing transport performance measures for Construction

32 | P a g e

Sears, et al. (2015) suggest that procurement consists of ordering, execution

and delivering of required materials and equipment and with the help of this

material, equipment, labor, supervision and management construction takes

place. After construction is done the project is delivered to client for

occupation and utilization and all contracts are closed out. (Sears, et al. (2015).

The construction process is shown and summarized in Figure 9 below;

3.1.2 Construction Flows

Sacks (2016) suggests that due to complex and dynamic nature of construction

industry it is difficult to control and manage flows within the construction

projects. Kalsaas and Bolviken (2010) define “flow” as continuous stream of

something”. They also suggest that “flow” is a chain of events (sequence),

continuous movement, moving freely and value addition without interruption.

Sacks (2016) further suggests that flows in the construction industry comprises

of “physical flows” such as flows of materials and equipment’s and

“immaterial flows” such as flow of information, crew, space and external

conditions e.g. weather, authority’s approval and so on. He suggests that the

visible flow in the construction industry is primarily of workers and their

equipment because the final product in this case is immovable (i.e. building).

Alves and Formoso (2005) are of the view that by explicitly and systematically

Figure 9: Different phases of construction process (Own illustration)

Page 41: Developing transport performance measures for Construction

33 | P a g e

planning and controlling construction flows (such as flow of workers,

equipment, materials etc.) process transparency can be enhanced. In addition

to this, there would be reduction in cost, time, wastage and variability (Alves

and Formoso, 2005).

3.1.2.1 Physical Flows

Alves and Formoso (2005) suggest that physical flows consists of both

material and production unit flows. Sacks (2016) suggest that it is difficult to

measure physical flows because the flow perspective was missing in

traditional construction management. Patel and Vyas (2011) suggest that

efficient and effective physical flows are designed in order to ensure

construction material availability at right time and in right quantity. According

to them physical flow begins with on-site material need generation. In order to

fulfill this need material is ordered in the store from different suppliers and for

that indent is generated. According to Merriam-Webster (2019) “indent” is

referred as official order or requisition for goods. Patel and Vyas (2011) further

suggest that after indent generation in store material availability is checked

and in the absence of required material, vendors are selected from the client´s

approved vendor list. The inspection of received material stock is done and

unnecessary stock is returned to vendors. After completing all these steps,

material is issued to concerned department and with the help of right

equipment and transport the material is delivered to the point of use (Patel and

Vyas, 2011). The steps are summarized as follows in Table 8 (Patel and Vyas,

2011);

Steps involved in physical flows

• On-site need for material

• For ordering material in the store, indent is generated

• Checking of in-store material availability

• Vendor selection from client´s approved vendor list

• Inspection of received stock

• Return of unnecessary stock

• Material issued to concerned department

• Material delivered to right place by utilizing right equipment and

transport

Alves and Formoso (2005) suggest that uncertainty in the physical flow can

be reduced by better planning and control at different hierarchical levels in the

construction process. For example, a general site lay out should be developed

Table 8: Physical flows steps (Adopted)

Page 42: Developing transport performance measures for Construction

34 | P a g e

at master plan level (strategic), workflows of repetitive processes should be

prepared at operational level and cleanliness and workplace order should be

managed at tactical level (Alves and Formoso, 2005). Alves and Formoso

(2005) consider qualification and selection of suppliers, selection of transport

equipment’s (cranes, lifts, excavators, etc.) and their location, material storage

area, material consumption rates as important physical flow decisions.

Here it is important to mention type of construction material and their delivery

in order to know the nature of material vehicles carry in construction industry

or what type of material is being transported to the construction site.

Types of construction material

Li et al. (2016) suggest that there are four types of material used in construction

projects namely construction material, packaging material, extracted material

and target building material. They refer “construction material” to those

material which is used to form the target building element. According to

Napier (2016) examples of construction material can be cement, concrete,

wood, glass, steel, aluminum, copper, gravel, stone, rock, plastic, textile etc.

Li et al. (2016) suggest that large amount of construction material gets

consumed in forming target building material and as a result very few

construction materials gets wasted. They consider “packaging material” a

material that cover/package construction material. Tolstoy, Bjorklund and

Carlson (1998) consider mineral wool, plaster board, card board, plastic sheets

as packaging material. According to Pericot (2011) every construction

material is delivered in some type of packaging at construction site. Li et al.

(2016) suggest that packaging material does not play any role in forming target

building element and therefore this end up as construction waste. They define

“extracted material” as soil abstractions in the construction process. Tolstoy et

al. (1998) suggest clay, sand etc. as extracted material. They are of the view

that extracted material become waste if not used in target building elements or

in backfilling. They define last type of material “target building element” as

design elements of a building such as windows, doors, steel beams, bricks,

frames etc. Part or whole of a building element can be considered as wastage

due to change in design or poor construction quality.

Li et al. (2016) show material flow of typical building construction project in

the following Figure 10;

Page 43: Developing transport performance measures for Construction

35 | P a g e

Li, et al. (2016) demonstrate construction site as dotted rectangle. According

to them input to target building is various construction materials such concrete,

cement, glass, wood, rocks and gravel etc. as well as other construction

packaging materials such as plastic sheet, cardboard, wool etc. They further

suggest that the output of construction are different building elements formed

such as frames, doors, windows etc. and construction waste for example

broken tiles, bricks, cables, pipes, insulation material and so on. They add on

that the construction waste mainly include extracted materials involved in the

construction of target building. According to them, the sum of construction

materials, packaging materials and extracted material is equal to the target

building elements and construction waste.

Delivery of construction material at Site

Napier (2016) suggests that with the help of equipment and manual labor

construction material is delivered at desired location into industrial containers

of various types. Materials are picked and sorted with the help of specially

designed equipment and are then loaded into trucks and containers of various

types. According to Olsson (2000) the traditional and most common way is to

deliver construction material at site. In this way materials are sourced by the

contractor and then client does payment after on-site material delivery.

3.1.2.2 Information flow

Golyani and Yan Hon (2010) highlight that in construction industry there is

still existence of inaccurate and untimely information flow. According to

Phelps (2012) information flow incorporates a starting point known as source,

an ending point called as receiver, a path as interaction and driving force said

Figure 10: Material flow in construction project (Adopted)

Page 44: Developing transport performance measures for Construction

36 | P a g e

as mutual relevance. Otjacques, Post, Feltz (2005) suggest that due to large

number of stakeholders involved in construction projects, hundreds of

information flow occurs. Golyani and Yan Hon (2010) suggest that

construction information mainly consists of documents such as design

drawings, specifications, schedules, budget calculations, meeting´s minutes,

invoices, flow charts and so on. According to them, construction information

keeps on changing throughout the construction process due to continuous

improvements in the planning and design phase. They are of the view that as

multiple stakeholders are involved in the construction project so effective and

efficient information sharing plays an important role in better and informed

decision-making regarding construction projects. Otjacques, Post, Feltz (2005)

define “information sharing” as the set of all elements responsible for

providing some knowledge and evidence to concerned individuals. According

to them, information consists of changes, cost control, documents and reports,

risk analysis, programming and so on. They further state that both formal and

informal information sharing has great influence on construction projects

quality, cost and timely completion.

Forcada Matheu (2005) throws light upon information flow steps in general

construction project. He suggests that initially “client´s requirements” are

shared with project manager and designer. After finalization of client´s idea

“strategic brief” is prepared which consists of procedures, project

configuration, consultants and other people to be involved. The next step is to

develop “full brief” based on discussed strategic brief which focuses on cost

estimations and procurement aspects. After this, “production information” is

prepared in order to obtain tender (Forcada Matheu, 2005). Tribelsky and

Sacks (2010) are of the view that at tender stage information should be

complete and clear. According to Kenton (2019) “tender” is structured

invitation to suppliers to submit a bid for supplying products and services

whereas “bid” is an offer to set price. Bid determines the cost and value of

something (Kenton, 2019). Forcada Matheu (2005) suggest that as tender is

released potential contractors and sub-contractors are evaluated. Contractors

are then appointed, and construction starts. According to Ndekugri and

McCaffer (2006) during design and construction there is continuous need of

information to be transferred quickly and reliably between stakeholders. After

completion of construction final inspection and final settlement is done and is

known as “handing over”. Ndekurgi and McCaffer (2006) emphasized the

importance of reliable, standard and efficient flow of information.

Page 45: Developing transport performance measures for Construction

37 | P a g e

The summary of information flow steps in construction project is shown below

in Table 9 (Forcada Matheu, 2005);

Information flow steps in construction project

1- Sharing of client´s requirement with project manager and designer

2- Preparation of strategic brief (includes procedures, project

configuration, decisions regarding people to be involved)

3- Development of full brief (focusing on cost estimations and

procurement aspects)

4- Preparation of production information for obtaining tender

5- Evaluation of contractors and sub-contractors after the release of

tender

6- Appointment of contractors for construction project

7- After handing over of construction project, final inspection and final

settlement is done

Bröchner (2005) has demonstrated information flow in general construction

project below which is adopted by Bishop´s information flow model which he

presented in 1972 in Figure 11;

Table 9: Information flow steps in construction project (Adopted)

Figure 11: Information flow in general construction project (Adopted)

Page 46: Developing transport performance measures for Construction

38 | P a g e

3.1.3 Construction site organization

Merriam-Webster (2019) defines “construction site” as a space of ground

occupied or to be occupied by a building. According to Holland (2014)

construction site organization is critical, thorough and meticulous process

resulting in healthy and safe construction site throughout the building process.

As per Vidovszky (2015) construction sites are prepared by managing traffic,

protecting the public, storing material and managing waste, required paper

work and meeting legal requirements. Holland (2014) suggests that it is

important to keep pedestrians and vehicles separate on construction site. She

further adds on that there are separate entryways and exits for pedestrians and

vehicles. She is of the view that walkways and crossings are well drained in

order to avoid any slips. She considers obstructions, visibility and barriers very

critical for well managed construction site. She states that vehicle movements

on construction site should be minimized such as workers or visitors are not

allowed to park car near construction site, entry to work site should be

controlled and specific area should be allocated for delivery vehicles in order

to avoid unnecessary trips across construction sites.

Vidovszky (2015) suggests that it is critical to enhance visibility on

construction sites as maximum as possible and this can be done by placing

mirrors, reverse alarms, closed circuit television (CCTV) cameras, adequate

lighting and so on. She further suggests that it is of prime importance to define

boundaries of construction site. According to her, material storage and

stacking should be kept aside so that accidents can be avoided. Holland (2014)

suggests that manholes and pits should be covered with lids. According to her

flammable materials should be kept away from storage area to hinder

accidental ignition and contamination. In addition to this, she suggests that

other facilities such as toilet, washing, drying, cooking, eating area, rest area,

soundproof telephonic booth should be allotted to construction workers and

employees. She also states that materials should be kept safe from theft,

vandalism, and careless behavior.

3.2 Significance of construction industry Fira (2015) states that the idea of construction is as old as human history and

therefore evolution of construction and human lifestyle took place hand in

hand. This evolution took place from primitive age cave to a tent, a hut, an

igloo, a log cabin, a castle, a palace, a detached house and today`s modern red

brick town house, concrete apartment building and sustainable wooden

structure. Fira (2015) highlighting the importance of construction suggests that

modern humans spend on average one third of their income on construction in

Page 47: Developing transport performance measures for Construction

39 | P a g e

the form of housing. According to McKinsey& Company (2017) construction

matters because it accounts for 13% gross domestic product (GDP) globally

and it employs 7% of the world´s working population. Carlgren (2017) define

gross domestic product (GDP) as total value of all final goods and services

produced in a country during specific period. He states that increase in GDP

over time reflects country´s economic growth. Fira (2015) further suggests that

urbanization and modern living has spurred construction globally and further

make construction a more crucial sector for any economy.

According to Rose (2015) construction industry despite being one of the oldest

and crucial sectors in human history as well as in economic development

respectively has shown slow adoption of modern techniques and methods in

comparison to other sectors mainly manufacturing, retail, third party logistics

service providers and so on. For example, according to McKinsey& Company

(2017) the “retail industry” has adopted global supply chains, digitized

distribution systems, customer intelligence and transformed the small retail

outlets known as mom-and-pop stores into large scale modern retailers such

as Walmart and Aldi. Likewise, “manufacturing industry” has also

incorporated lean and extensive automation. O´Reilly (2015) adds on that

“third-party logistics” have also gone far in terms of implementing information

systems and supply chain planning. According to him, the entry of specialized

firms in express parcel deliveries such as DHL, FedEx, UPS has revolutionized

the third-party logistics industry. The underlying reasons according to her are

involvement of multiple independent stakeholders, the temporary nature of

work, continuously changing construction network in terms of teams and

involved parties i.e. every construction project is unique (no two jobs would

exactly be the same), conflicting interests of owner and project manager, lack

of knowledge transfer from one project to another due to involvement of

different stakeholders in different projects, non-technical education

background of contractors and other concerned parties and so on.

According to Burke (2018) construction industry needs to be revolutionized in

order to fulfill its role in future economic development. Brasington (2018)

advocates by saying that traditionally construction industry is very

competitive, dependent on public-sector demand, extensively regulated,

vulnerable to economic fluctuations, disorganized, risk averse and slow in

technology adoption but now time has come to consider new solutions in order

to cope with future demands. He further highlights that inefficient project

management and execution, insufficient skill base, inadequate design

processes and lack of research and development investments has made

Page 48: Developing transport performance measures for Construction

40 | P a g e

construction industry fragmented and backward in comparison to other

industries (i.e. manufacturing, retail, third party logistics service provider etc.)

3.3 Supply Chain Management in Construction Industry Lee (2002) suggests that in order to gain competitive advantage supply chain

management (SCM) has become one of the most important aspect. Dubios et

al., (2019) define” supply chain management (SCM)” within construction

industry as the planning and management of all activities along with

coordination and collaboration with channel partners (which can be suppliers,

intermediaries, third party service providers and customers. Andersson and

Nilsson (2018) and Dubios et al., (2019) suggest that supply chain

management plays four major roles in construction from the perspective of

supply chain, the construction site or both. They also suggest that these roles

have been identified by Koskela and Vrijhoef in 2000. These roles are

mentioned below in Table 10 (Andersson and Nilsson, 2018; Dubios et al.,

2019);

Roles of

SCM in

Construction

From which

perspective/focus

To achieve

Beneficial

for

First role Focus on impact

of supply chain

on site activities

- To reduce time

consumption from

activities and cutting

overall costs on site

- To ensure dependable

material and labor flows

to the site to avoid

disruption to the

workflow

Main

contractor

Second role Focus on impact

of supply chain

on itself

-To reduce costs not

only on-site as well as

along whole supply

chain such as logistics,

lead time and inventory

Material

and

component

supplier

Third role Focus on

transferring

activities from

site to early

-To avoid interference

between on-site

activities

Contractors

and

suppliers

Page 49: Developing transport performance measures for Construction

41 | P a g e

stages of supply

chain

-To achieve wider

concurrency between

activities

Fourth role Focus on

integrated

management and

entire supply

chain

-To improve supply

chain and sit production

Clients,

suppliers

or

contractors

Koskela and Vrijhoef (2000) suggest that construction supply chain (CSC)

possess certain characteristics which makes it unique and complex. They add

on that construction supply chain is converging supply chain which means that

it directs all materials to the construction site where structure is built from

incoming materials. They also say that it is temporary supply chain which

comes to end with the completion of construction project. According to them,

construction supply chain is characterized as unstable, fragmented and

complicated. They also highlight that construction supply chain is make-to-

order supply chain because every project creates a new product or prototype.

There is very less repetition because most of the times every project is different

and does not belong from same kind (without considering exceptions).

Koskela and Vrijhoef (2000) depicts traditional construction supply chain

below in Figure 12;

Table 10: Four roles of supply chain management in construction (Adopted)

Figure 12: Traditional construction supply chain (Adopted)

Initiative Tendering Design Procurement

Use Hand OverConstruction

on site

Operation

capacity

Material

production

Parts

manufacture

Fabrication

of elements

Resident PrincipalArchitect &

consultants

Direct

suppliers &

sub-contactors

Indirect

supplier

Main Contactor

Information flow (orders, schedules, forecasts, etc)

Material flow (supplies, production, deliveries, etc)

Page 50: Developing transport performance measures for Construction

42 | P a g e

4 Framework for RQ1

The framework for RQ1 consists of theory, frame of reference, empirical

findings and analysis.

4.1 Theory This chapter will discuss theory for research question 1. As the RQ1 is about

exploring transport related performance measures for construction logistics

solutions and their respective construction sites so this chapter will start by

brief overview of construction logistics which then set the stage for introducing

construction logistics solutions. After that a light will be thrown upon

construction site and site logistic. Then performance measures and their

importance, need of performance measures within construction industry and

link of performance measures with transport objectives will be discussed. In

the end transport related performance measures will be mentioned.

The theoretical framework for RQ1 is shown below pictorially in Figure 13;

4.1.1 Construction logistics

Council of supply chain management professionals (CSCMP) (2016) defines

“logistics” as “part of supply chain management that plans, implements and

controls the efficient, effective forward and reverse flow and storage of goods,

Section 4.1

Theory

Research Question 1

What performance measures can be used for the evaluation

of construction logistic solutions and their respective construction sites

with respect to transport flows?

Section 4.1.1

Construction

Logistics

Section 4.1.2

Construction

logistics solution

Section 4.1.2.1

Terminal

Section 4.1.4

Performance measures

and their importance

Section 4.1.2.2

Checkpoint

Section 4.1.3

Construction site

and construction site

logistics

Section 4.1.4.1

Transport performance measures

Figure 13: Pictorial explanation for RQ1 theory (Own illustration)

Page 51: Developing transport performance measures for Construction

43 | P a g e

services, and related information between the point of origin and the point of

consumption in order to meet customer’s requirement”. Sullivan et al., (2010)

define “logistics” as the process of designing, managing and improving supply

chains which involve purchasing, manufacturing, storing and transport. Appel

(2016) suggests that logistics have evolved over time i.e. from the management

of all activities facilitating movement and coordination of supply and demand

(with respect to time and place) to controlling the physical flow of materials

and goods as well as related information that a firm sends, transfers and

receives.

Ying, Tookey and Roberti (2014) suggest that construction logistics is a vital

part of construction supply chain management (CSCM) and can be defined in

various ways. According to them, “construction logistics” comprises of

planning, organizing, coordinating and controlling of material flows from

point of extraction to the point of incorporation into the finished building.

Janne and Fredriksson (2019) define “construction logistics” as all activities

related to supplying the right material and resources to the right customer and

construction site to meet customer´s requirements.

Tsaxiri (2018) suggests that the main aim of construction logistics is to manage

construction projects in an effective way. She further adds that construction

logistics includes numerous activities such as planning, purchase, control,

coordination, forecast, warehousing, transportation, inventory management

and customer service. Janne and Fredriksson (2019) suggest that construction

logistics encompass planning, supplying and maintaining loading and

unloading zones, on or off-site warehousing and on and off-site materials

handling.

Lundesjö (2015) suggests that no efficiency improvements such as cost

reductions and other certainties can be made in construction industry without

the application of professional logistics. Sullivan et al. (2010) suggest an

estimated 10-20% of all construction costs are transport related. Ying et al.

(2019) are also of the view that construction logistics is an important part of

construction supply chain management as far as project management and costs

are concerned. Sullivan et al. (2010) and Dubois et al. (2019) suggest that there

are four reasons construction industry should employ dedicated approach to

logistics. The first reason according to them is to maximize the productivity

and efficiency at the construction site, second is to maximize the quality of

logistics, third is to reduce environmental impact and fourth one is to maximize

safety and health on site. According to Sullivan et al. (2010) logistics is one of

Page 52: Developing transport performance measures for Construction

44 | P a g e

the most important elements of construction project and has the potential to

affect cost, speed of construction, planning reliability and so on. Andersson

and Nilsson (2018) suggest that as construction logistics incorporates several

processes within construction industry, it is important for parties involved in

construction project to practice supply chain management.

Sundquist, Gadde, Hulthen (2018) suggest that construction logistics can be

divided into two categories i.e. “supply logistics” and “site logistics”.

According to them, “supply logistics” is related to specification, acquisition,

transport and delivery of materials to the construction site whereas “site

logistics” is concerned with on-site physical flow planning and material

handling. Andersson and Nilsson (2018) suggest that there are two ways to

improve construction logistics. The first one is to reduce inventories of

resources and the second is by enhancing coordination between material flow

and information flow. The first one is referred as traditional approach whereas

the latter is considered as modern approach. Fadiya et al. (2015) suggest that

construction supply chain integration can be achieved by linking supply

logistics and site logistics.

4.1.2 Construction logistics solution

According to Andersson and Nilsson (2018) construction industry is facing

logistics challenges such as congestion at site, delayed deliveries, other supply

chain mismanagement and so on. They further add that due to lack of logistics

standardization, unplanned deliveries take place resulting in chaotic situations

both at roads and at construction sites. Considering this, “construction logistic

solution” is considered a mean to achieve logistics efficiency and effectiveness

both at construction site and on roads. The rationale behind this solution is to

overcome congestion, un-planned deliveries with very short notice to drivers

(Andersson and Nilsson, 2018). Ekeksär and Rudberg (2016) and Sundquist,

Gadde, Hulthén (2018) suggest that “construction logistics solution” can range

from just a small change in working practices, implementing planning systems

and information and communication tools, large scale terminal networks

structures or just in time solutions.

According to Le et al. (2019) the idea of construction logistics solution has yet

to gain wide acceptance within the construction industry. They further suggest

that due to involvement of multiple stakeholders in construction projects it

becomes unclear that who will get the ultimate benefit and who will incur costs

for bringing improvements in the construction projects. They suggest that this

makes participants less motivated to bring improvements in the construction

Page 53: Developing transport performance measures for Construction

45 | P a g e

projects. They also highlight that main contractors and sub-contractors in order

to achieve their own economic benefits just focus on increasing the efficiency

of their own tasks and responsibilities and do not bother about whole

construction project efficiency.

Need for construction logistics solution

Russo and Comi (2010) highlight that the increasing transport vehicles in

urban areas is leading to congestion, air pollution, noise and increased logistics

costs. They also suggest that different types of vehicles also enhance safety

risks. They further suggest that this raised the need of having effective logistics

systems in the form of construction logistic solution. They further suggest that

it is vital to consider logistics solutions where loads can be consolidated and

deconsolidated thus improving transport management. Sundquist et al. (2018)

suggest that due to poor management of materials, equipment and tools

construction industry is not performing on its optimum. Sobotka and

Czarnigowska (2005) suggest that logistics performance can be improved by

proper planning of delivery and storage and better organization of materials

handling and resource utilization. Janne and Fredriksson (2019) while

emphasizing the importance of construction logistics solution suggest that it

will fulfill the need of limited space at construction site, reduce environmental

impact, improve accessibility and other noise restrictions.

Civic Handbook (2018) highlights that construction logistics solution should

encompass three main areas i.e. transports, site and planning and organization.

It also suggests that a comprehensive construction logistic solution is the one

which incorporates more activities and more roles. Civic Handbook (2018)

also emphasize that construction logistic solutions are not universal rather they

should be adapted to unique settings and peculiarities. The two-construction

logistics solution “terminal” and “checkpoint” and “site logistics” are

discussed below;

4.1.2.1 Terminal

Yamada, Taniguchi and Noritake (1999) define “logistics terminals” as multi-

company distribution centers as well as complex facilities with multiple

functions that fulfills the requirements of supply chain management using

information and communication technologies (ICT). Russo and Comi (2010)

define “terminal” as a place where long distance transport is converted into

short distance transport and consignments are also sorted and packaged here.

They further suggest that in order to build logistics terminals, their function,

size, location, management as well as legal formalities should be considered.

Page 54: Developing transport performance measures for Construction

46 | P a g e

According to them, “logistics terminals” are connection points between line-

haul and local pick-up/local deliveries. They define “line-haul” as long-

distance transport by large trucks on expressways and local pick-up/delivery

which is short distance transport by small trucks on urban streets. Sullivan et

al. (2010) define “terminals” a storage facility that hold materials or equipment

for a limited time period before delivering them to the point of consumption

on the construction site.

Matouzko (2015) suggests that “terminal” is a distribution facility which

ensures material deliveries to construction site. He further suggests that it is a

temporary warehouse made for material handling and big enough where trucks

can be off-loaded and turned around. Janne and Fredriksson (2019) suggest

that terminal can be put forth by different bodies such as the developer or

municipality. They further suggest that the aim of construction logistics

solution is to coordinate and plan deliveries to multiple construction sites

within an urban area. In other words, it can be said that “shipment

consolidation” is the main aim of terminal (Civic Handbook, 2018).

Matouzko and Methanivesana (2012) suggests that terminals are construction

consolidation centers and are utilized in supplying and distributing materials

to several construction projects. They further suggest it is an effective supply

chain management solution because it ensure safe and efficient material flow

from supplier to the construction site. Matouzko and Methanivesana (2012)

highlight that terminals distribute and supply materials in a right time, to the

right place and in the right quantity.

According to Matouzko and Methanivesana (2012) the idea behind terminals

is to combine multiple part loads into one consolidated shipment. Ekeskär and

Rudberg (2016) suggest that aim of terminal is to establish efficient logistics

systems and to reduce total social and environmental costs of transporting

goods within urban areas. Matouzko and Methanivesana (2012) have depicted

this in Figure 14 below;

Page 55: Developing transport performance measures for Construction

47 | P a g e

According to Sullivan et al. (2010) terminals involve receipt, temporary

storage and distribution of construction material and equipment. They further

suggest that materials and equipment are delivered to terminals by the supplier

which is then stored for shorter period and then delivered to the point of use

by dedicated logistic team. Janne (2018) while explaining the functionality of

terminal suggests that after the placement of order by main contractor,

suppliers deliver material either directly or via terminal. He further suggests

that in case of terminal, materials from different suppliers are received,

controlled, registered and put away for storage. He adds on that materials are

picked on requirement, thereafter, packed and delivered to the construction

site.

Matouzko and Methanivesana (2012) highlight that with the help of using

terminals un-interrupted materials supply can be made to different

construction projects in an overloaded urban area. Lundesjö (2011) and

Sullivan et al. (2010) suggest that the use of terminals can reduce freight traffic

to site by up to 70% by consolidating number of individual deliveries of

material and equipment, provide the possibility of delivering material at night

when roads are not that busy, provide more control and accountability by

offering single point of contact, reduce harmful CO2 emissions by using

appropriate low emission, fuel efficient vehicles, deliver materials in exact

quantities as required by builders, increase time reliability by acting as

production buffer for materials extended lead times, reduce waste by using

reusable delivery cartons and packaging. Janné (2018) suggests that by having

terminals as a coordinating contact point, main contractors can focus on their

operations without being worried about maintain contacts and relationships

with multiple other contractors. Matouzko and Methanivesana (2012) suggest

Single

Consolidated

Shipment

at

Terminal

Shipment no. 1

Shipment no. 2

Shipment no. 3

Shipment no. 4

Shipment no. 5

Construction site 1

Construction site 2

Construction site 3

Construction site 4

Figure 14: Shipment consolidation at Terminal (Adopted)

Page 56: Developing transport performance measures for Construction

48 | P a g e

that terminals result in better supply certainty, reduced number of deliveries to

site, reduced amount of stored materials and reduced waste.

4.1.2.2 Checkpoint

Checkpoint is another type of construction logistics solution with an aim of

providing controlled access to construction site by controlled queues and just

in time deliveries (Civic Handbook, 2018). Matouzko and Methanivesana

(2012) suggest that just in time deliveries refer to deliveries that are made in

time for usage. Landqvist and Rowland (2014) suggest that due to narrow

loading and unloading areas at construction site there is greater demand for

accurate and precise just in time deliveries. Matouzko and Methanivesana

(2012) suggest that just in time deliveries help in completing tasks without any

delay. Tsaxiri (2018) suggests that a checkpoint is established on site in order

to organize the trucks coming from different contractors for all project´s

stages. She further suggests that checkpoint organizes the trucks, sets up the

lanes and the paths on which truck will transfer the material and unload them

safely as per contractor requirements. She identifies that construction projects

where waiting time for the material is greater than just in time deliveries play

an important role in making material reach the site on time.

Janné (2018) suggests that the delivery process in checkpoint starts when

contractor places an order with a supplier. At the same time, contractor makes

delivery bookings in the checkpoint using information and communication

tools (ICT). In this type of system, time slots for deliveries are booked and

specified with information on sort of materials, types of vehicles, goods

volume etc. Once the supplier has shipment ready a delivery announcement is

sent from the supplier to the contractor and the checkpoint operator and the

shipment is delivered to the physical checkpoint. Here the delivery may have

to wait for its allotted time slot before the final delivery to the construction site

is carried out (Janné, 2018).

Matouzko and Methanivesana (2012) highlight that just in time deliveries

within Checkpoint help in reducing on-site material storage, which in turn

reduces the risk of material damage and other safety incidents. Tsaxiri (2018)

suggests that it helps in reducing waiting time for material to reach on site. She

highlights that checkpoint also reduce workers stress by handling material in

a better way. The checkpoint model can be understood by below Figure 15;

Page 57: Developing transport performance measures for Construction

49 | P a g e

4.1.2.3 Comparison between Terminal and Checkpoint

Tsaxiri (2018) suggests a terminal is considered as a good solution where there

are more projects in the area because then multiple construction sites will be

served simultaneously and there would be a smaller number of trucks

involved. She further suggests that transport is more flexible in case of

terminal whereas in checkpoint it is difficult to make changes in the deliveries.

According to Janné (2018) the difference between terminal and checkpoint lies

in the way material deliveries are planned and carried out. The focus of

terminal is mainly on the consolidation of deliveries whereas the checkpoint

focuses on just in time deliveries. Tsaxiri (2018) compares the two solutions

in terms of their usage depending upon different situations and this is shown

in Table 11 below;

Situation Construction logistic solution

High number of vehicle on-site Use terminal

Workers waiting for materials Use checkpoint

Transportation problem and queues

in the gate

Use combination of terminal and

checkpoint

Delays with suppliers Use terminal

Many contractors in tight area Use checkpoint

Environment issue Use terminal (reduce no. of vehicles)

Damaged material and waste Use terminal

4.1.3 Construction site and construction site logistics

United Nation (ISIC) (2008) defines “construction site” as a place where

construction activities takes place. “Construction activities” as per Razak Bin

Ibrahim, et al. (2010) are referred to all types of activities related to erection

Construction

SiteCheck

point

Figure 15: Modelling of Checkpoint (Own illustration)

Table 11: Comparison between terminal and checkpoint (Adopted)

Page 58: Developing transport performance measures for Construction

50 | P a g e

and repair of non-moveable structures and facilities. Olsson (2000) considers

construction sites a strong logistic spot due to number of materials, people,

equipment and vehicle movements and flows. From logistics point of view, he

highlights that usually very little effort has been made to manage and handle

on-site material efficiently and effectively. He found that a lot of construction

activities are culturally accepted and remain unquestioned and site logistics is

one among those culture driven activities. He states that this makes site

logistics difficult to manage and organize.

Matouzko and Methanivesana (2012) identify that construction workers utilize

less than 50% of their total time in productive and value adding activities on

site. The non-value adding tasks on which they spend most of their time are

moving products around the site and unloading trucks. They then emphasized

that on site construction logistics provide skilled workers ample time by

creating safe, clean and effective workplace so that they can focus more on

valuable work. According to Civic Handbook, (2018) the aim of site logistics

is to have fewer on-site transport, fewer unnecessary movements and greater

controlled and coordinated deliveries.

Sikka, Dawood and Marasini (2006) suggest that construction logistics system

consists of three phases i.e. routes and logistics schedules, site layout and site

resource planning. They further explain that “routes and logistic schedule”

focus on external transportation systems and strive towards optimal traffic

network to deliver material at site such as vehicle routes and route travel time.

“Site layout” as per Sikka, Dawood and Marasini (2006) consists of locations

such as off-loading, loading, storage etc. In addition to this, they suggest that

site layout also map how material movement will take place within

construction area. They further add on that construction site resource planning

include integration of work requirements (such as labor, cranes, machinery,

equipment etc.) with external logistics and site layout. According to them,

construction site logistics is very dynamic in nature because variety of

materials and assembly components are transported towards the site and

eventually the site turns into a finished building. The main activities that take

place at construction site are shown below in Figure 16;

Page 59: Developing transport performance measures for Construction

51 | P a g e

4.1.4 Performance measures and their importance

Goshu and Kitaw (2017) suggest that “performance” is a construct around

which organizational competitiveness and excellence revolves because

according to them performance reflects organizational ability to manage

projects and other services. Hove and Banjo (2015) suggest that the term

“performance” due to multi-faceted and subjective nature is not easy to define,

describe and measure. They further suggest that traditionally “performance” is

described as efficiency, effectiveness, improvement, growth, and success.

According to Dubois, et al., (2019) “efficiency” is defined as “how well the

resources expended are utilized whereas “effectiveness” is defined as the

extent to which the established goals are accomplished.

Zetterberg and Minges (2017) define “performance measures” as a metric used

to quantify the efficiency or effectiveness of an action. They further suggest

that performance measures help decision makers and managers to compare

actual versus estimated performance as far as effectiveness, efficiency and

quality is concerned. They add on that if there is a gap between actual versus

desired performance then corrective actions can be taken based on information

gathered by performance measures. Goshu and Kitaw (2017) further suggest

that in order to remain competent in the market, organizations need to know

that how best they are running their activities, how well the resources are being

utilized, how to meet set goals and objectives, how to bring efficiency and

Construction

Site

StorageCrane

Waste Mgmt

Loading

Un-Loading

Delivery

precision

On site

inventory

level

Material

relocation

Figure 16: Activities occur at construction site (Own illustration)

Page 60: Developing transport performance measures for Construction

52 | P a g e

effectiveness in current processes and so on. Cain (2004) suggests that

developing performance measures is the first step towards improvement that

brings benefits for all the involved parties. Takim, Akintoye, Kelly (2014)

suggest that organizations measure both financial and non-financial aspects as

well as compare performance measures with others in the industry in order to

improve results.

Yu, et al., (2007) suggest that performance measures are very important for

the success of almost every organization. Kulatunga, Amaratunga, Haigh

(2007) suggest that performance measures lead to profitability and sustainable

competitive advantage. They further suggest that performance measures act as

a monitoring tool and keep organizations on track in achieving their objective.

Theeranuphattana and Tang John (2008) suggest that in this complex and

continuously changing environment performance measures play critical role

in increasing profits, market penetration and market share. Lukviarman (2004)

suggests that performance measures describe how well work is being done

from cost, time and quality aspects.

Latiffi, et al. (2014) suggest that although it is important to have performance

measures but at the same time this is quite challenging. They further suggest

that it is hard to develop performance measures because obtaining correct

source of information is difficult especially when variables or constructs that

are supposed to be measured are changing constantly. They add on that it also

requires right knowledge of methods to measure performance and experience

of using the right tools. Balm et al. (2014) also advocates that lack of right data

makes it more complicated to developed performance measures. They further

suggest that to measure everything in practice is not that easy. Looy and

Shafagatova (2016) also highlight that it is difficult to replicate performance

measures from one organization to another because of their organization

dependent nature. They further suggest that it is not easy to select appropriate

performance measures because best practices vary from company to company.

Need for construction transport performance measures

Garcia-Arca, Prado-Prado, Fernandez-Gonzalez (2018) suggest that “transport

management” has become a serious concern for construction industry not only

from economic aspect of cost reduction and service improvement but also from

other aspects such as reduction in resource consumption, carbon emission and

traffic congestion. Valenciaport Foundation (VPF) (2014) considers

construction industry as one of the biggest producers as well as consumers of

transport in urban areas. It also highlights that due to fragmented nature of

Page 61: Developing transport performance measures for Construction

53 | P a g e

construction industry and involvement of multiple stakeholder’s transport has

gained critical importance.

Andersson et al., (2019) advocate that due to complex nature of construction

supply chain it is very difficult to predict and simulate the impact of new

solutions on the transport systems. As a result, it becomes difficult to convince

stakeholders for bringing improvements within construction logistics (Goshu

and Kitaw, 2017). Due to this, Wegelius-Lehtonen (2001) emphasizes the need

of transport performance measures in construction industry. Latiffi, et al.,

(2014) highlight that in order to bring improvement and sustainability,

construction industry should recognize the importance of transport

performance measures.

Linking performance measures to strategic objectives

Marr (2015) suggests that in order to develop a performance measure care

should be taken that to which strategic objective the performance measures

relates to. Olsen (2016) suggests that performance measures are developed in

order to achieve certain goals and objectives. She further suggests that

performance measures are quantifiable expressions of pre-determined goals

and objectives. According to her, it is of considerable importance to identify

the right performance measures because they inform decision makers that

whether progress is taking place towards goal achievement or not. Goshu and

Kitaw (2017) define “goals” as desired result or outcome and “objectives” are

defined as a support to specific goals which provide additional details or

strategies on how the goal will be achieved.

Yan, Xu, Han (2015); Yan and Zhang (2015); Harish (2013) suggest that

construction industry faces various transportation challenges during

construction such as simultaneous pick-up and delivery, managing travel time

uncertainty, vehicle routing optimization, high transportation costs, air

pollution, traffic incidents and so on. In order to meet these challenges,

transportation objectives such as to make effective transport planning and

coordination (Yan, Xu, and Han, 2015); (Jia, Deschamps, Dupas, 2016); (Fu,

2017); Sichwardt (2011), Jonsson (2008) reduce transportation time

(Multanen, 2011), minimize transportation costs (Murray, 2018);

(Stringfellow, 2019); (Yin, Tookey, Seadon, 2018), ensure environment

sustainability (Sichwardt, 2011) and to have less safety and security incidents

(Polzin, 2002; Burdick, 2012; Jacob, 2017); (Tamuli, 2016; Botha, 2005) are

formulated. Baird (2017) highlights the difference between “security” and

“safety”. He suggests that security is the protection against deliberate threats

Page 62: Developing transport performance measures for Construction

54 | P a g e

whereas safety is being secure against unintended threats. In order to achieve

these transport objectives, performance metrics are developed (Yin, Tookey,

Seadon, 2018) in the following section.

4.1.4.1 Transport performance measures

In order to develop transport related performance measures for construction

industry, other industries such as manufacturing, retail, third party logistics

(TPL) have been considered because very few studies have been conducted on

performance measures regarding construction transport. In addition to this,

these performance measures are general transport performance measures

without being classified as terminal, checkpoint and construction site because

no credible study has been found in this realm.

4.1.4.1a) Performance measures related to effective transport planning

Sichwardt (2011) suggests that transport should be planned in a way that it

allows suppliers to deliver the material efficiently i.e. to meet material

requirement in the shortest possible time with minimum number of kilometers

driven. Jonsson (2008) suggests that transport planning determines the

structure of transport networks and the flow of traffic. Performance measures

for effective transport planning along their definitions and reference is

mentioned in below Table 12;

Performance

measures

What it entails Reference

Reduced number of

miles driven outside of

pre-determined routes

This measure refers to

number of miles that

vehicle will travel

outside of already

determined route in

order to reach the

destination. Due to

this, vehicle may take

more time to reach the

destination. So, by

measuring this a time

buffer can be estimated

that will eventually

help in effective

transport planning.

Robinson (2019), Ryus

et al., (2013)

Page 63: Developing transport performance measures for Construction

55 | P a g e

Reduce total distance

driven

It refers to the total

distance that vehicle

has travelled. This

measure will give

information regarding

delivery distances and

helps in effective

transport planning.

Kaparias and Bell

(2011), Freight best

practice (2010)

Ensure trucks

availability (trucks

confirmed vs

requested)

This measure refers to

the truck’s availability

in need. Truck

unavailability will lead

to delays which is a

sign of ineffective

transport planning.

This indicator will help

in fleet management.

Brierley (2017), Key

performance indicator

survey (2013)

Reduced no. of

unplanned deliveries

This measure refers to

the presence of

contingency plan

within transport

system. Based on this

measure, the extra time

that gets consumed in

unplanned delivery

will be reduced.

Beetrack (2016),

Faschingbauer (2015)

Optimal no. of

deliveries arrives at

gate per day

This performance

measure leads to

efficient delivery

scheduling which

consequently results in

efficient transport

planning. The input for

this measure will be

effective material

requirement planning.

Thomas (2017), Ogden

and Turner (2015)

Page 64: Developing transport performance measures for Construction

56 | P a g e

Maximize vehicle

utilization

-travel capacity

-weight capacity

Vehicle utilization can

be measured in two

ways i.e. in terms of

travel and in terms of

weight. “Vehicle travel

utilization” will help in

calculating no. of trips

thus playing major role

in effective transport

planning whereas

“vehicle weight

utilization” will

determine the quantity

of material carried.

Malacarne (2018),

Hosseini and Shirani

(2011)

4.1.4.1b) Performance measures related to time minimization

Multanen (2011) suggests that one of the transport objectives is to reduce

delivery times as maximum as possible. He further suggests that like other

industries, construction industry also demand quick and fast material

deliveries. He adds on that due to fragmented nature of construction industry,

it is necessary to save time wherever possible. In order to achieve this

objective, suggested performance measures are as follows in Table 13,

Table 12: Performance measures related to effective transport planning

(Adopted)

Page 65: Developing transport performance measures for Construction

57 | P a g e

Performance measure What it entails Reference

Ensure on time delivery On time delivery is the

date and time of the day

promised by supplier to

make a delivery to its

client. It helps in

optimal utilization of

time.

Marion (2019)

Reduce truck

turnaround time

Truck turnaround time

is a major performance

measure including

loading and unloading

times as well as access

time to construction

facility

Van Der Spoel, Amrit,

Van Hillegersberg

(2015)

Minimize vehicle travel

time

It is defined as total

time that vehicle take in

reaching its destination

Yan, Xu, Han (2015),

Lomax, Schrank,

Lasley, Eisele (2013)

Reduce the time taken

in preparing shipping

documents

This refers to time

taken in preparing

shipping document. It

also indicates the time

difference between

order placed and

making shipping

documents ready

Naoh (2018),

Manaadiar (2017)

Minimize the time

taken in doing shipping

documents corrections

It refers to time taken in

doing corrections in

shipping documents

such as address, price,

quantity, product detail

and so on

Naoh (2018),

Manaadiar (2017)

4.1.4.1c) Performance measures related to cost minimization

Murray (2018) suggests that transportation costs are major portion of overall

logistics costs. Stringfellow (2019) suggests that reducing transportation cost

is top priority of many companies. Following are the performance metrics for

transportation costs in Table 14;

Table 13: Performance measure for time minimization (Adopted)

Page 66: Developing transport performance measures for Construction

58 | P a g e

Performance

measure

What it entails Reference

Reduce no. of trips

per vehicle

This measure refers that how

many trips vehicle must make

to meet the customer demand.

It also determines the no. of

vehicles that one should have.

Florida department

of transport (2014),

Freight best practice

(2010)

Ensure vehicle

fuel efficiency

including idle time

This measure refers to the

distance that a vehicle can

travel by using a particular

amount of fuel.

Waters (2019),

EECA business

(2017)

Reduce no. of

empty miles

Empty miles refer to the

distance travelled while

generating no income. Empty

miles results when truck travel

without load.

Freight best practice

(2010)

Minimizing

maintenance cost

There is critical need to

maintain vehicles in order to

avoid any kind vehicle failure.

It includes cost of cleaning and

costs of good quality tyres etc.

Dönmez and

Zemmouri (2016)

Reduce no. of

damages during

delivery

This measure refers to damages

that occur in transit or at the

time of loading and unloading.

Bodenheimer (2014)

Optimize no. of

vehicles

movement

This measure includes all the

vehicle movements from

delivering material to

removing waste at construction

site

Yin, Tookey,

Seadon (2018)

4.1.4.1d) Performance measures related to environmental sustainability

Sichwardt (2011) suggests that due to global warming and green-house effect

environment protection is common objective of many transport companies. He

further suggests that since CO2 and N2O emissions results from burning

vehicles fossil fuel, so the connection of environment and logistics is very

Table 14: Performance measures related to cost minimization (Adopted)

Page 67: Developing transport performance measures for Construction

59 | P a g e

interesting. Due to globalization and increasing competition, transport

companies are adopting environment friendly processes and green logistics

Sichwardt (2011). Performance measures for this objective are mentioned

below in Table 15;

Performance measure What it entails Reference

Reduction in CO2

emission

This measure refers to

minimize air pollution

due to CO2 emission

via vehicles

Sichwardt (2011)

Minimize no. of

breaches in noise limits

This measure refers to

the number of times the

vehicle has violated the

noise limitations such

as horns, sound of

engines, material

loading and unloading

at night etc.

Sound noise limit

report (2005)

4.1.4.1e) Performance measures related to security assurance

Polzin (2002) suggests that transport security is logistically complex and

remains an important part of security business protocol. He further suggests

that a secure transportation system is critical because transportation facilities

may be target of terrorists intending to harm the economy. These performance

measures are shown in Table 16 below;

Performance

measure

What it entails Reference

Ensure good

quality

packaging of

hazardous

material

This measure refers to quality

criteria for material packaging. It

suggests that material should be

packaged in strong and leak tight

way while delivery

Burdick (2012)

Reduce on

road material

theft

On road material theft affect

productivity and drain profits. On

road material theft should be

avoided.

Berg and Hinze (2005)

Table 15: Performance measures related to environmental sustainability

(Adopted)

Table 16: Security related performance measures (Adopted)

Page 68: Developing transport performance measures for Construction

60 | P a g e

4.1.4.1f) Performance measures related to safety assurance

Tamuli (2016) suggests that vehicle transport safety is very important because

road traffic accidents contribute one third of the total accidents. He further

suggests that road accidents are one of the leading causes of preventable deaths

worldwide. Botha (2005) indicates that transport safety can be measured by

no. of transport incidents. These are mentioned inTable 17 here;

Performance measure What it entails Reference

Reduce no. of transport

incidents

This refers to number

of traffic incidents and

casualties resulting

from crashes per time

period

Tamuli (2016)

Ensure vehicle

insurance

In order to safeguard

vehicles against

accidents, damage and

theft it is important to

insure vehicles.

Jonck (2019)

4.2 Frame of reference for semi structured interviews The operationalization of key terms used in interview guide (attached in

Appendix 1) regarding semi structured interview is as follows in Table 18,

Key term Conceptual definition Operational

definition

Construction

industry

An industry consisting of

firms responsible for

building structures such as

offices, hospitals, airports,

shopping centers, housing,

factories etc. and civil

engineering such as

infrastructure for water

supply, irrigation,

transportation, power

generation and the likes

ISIC (2008)

Construction industry

is a building industry

which constructs

houses, hospitals,

schools, commercial

real estate and so on.

Construction

logistics

Construction logistics is

defined as providing

construction site with

resources in the form of

Construction logistics

is defined as the

planning, execution,

control of

Table 17: Safety performance measures (Adopted)

Page 69: Developing transport performance measures for Construction

61 | P a g e

materials, machines and

personnel in an efficient

manner along with

managing resources

efficiently on the

construction site itself as

well as ensuring efficient

recycling and waste

management that enables

circular economy and

durability Fredriksson

(2018)

procurement,

transport, stationing of

workers, materials and

other resources in

order to complete a

construction project

Construction

logistics solution

Construction logistics

solution” is defined as

logistic solution applicable

in construction projects in

order to coordinate

material flows, thus

resulting in less transport

disruptions and efficient

construction Janne (2018)

Construction logistic

solution is a solution

to coordinate material

flows to ensure

efficient construction

and reduce

disturbances on urban

transport system

Performance

measures

A quantifiable measure

that is used to gauge or

compare performance in

terms of achieving

strategic and operational

goals. Jahangirian, Taylor,

Young, Robinson (2017)

A quantifiable

indicator used to

assess how well an

organization or

business is achieving

its desired objectives

Efficiency How well the resources

expended are utilized.

Dubois, et al., (2019)

Ratio of useful output

to total input or doing

things in a right way.

Effectiveness The extent to which the

established goals are

accomplished. Dubois, et

al., (2019)

How much of a

product or service is

produced in a given

time frame? Doing the

right things.

Transport flows “Transport flow” is

referred as vehicle

movements/ flow of

vehicles (i.e. the number of

vehicles that pass through a

specific point during a

specific interval of time)

and material handling

Transport flows is a

movement of vehicles

such as trucks

Page 70: Developing transport performance measures for Construction

62 | P a g e

activities such as vehicle

unload, dumping, material

carrying, vehicle reloading

etc. Jayasinghe, Sano and

Nishiuchi (2015)

Objectives “Objectives” are defined as

a support to specific goals

which provide additional

details or strategies on how

the goal will be achieved.

Goshu and Kitaw (2017)

Objective is a specific

step that company

takes to a achieve a

desired result

Effective transport

planning

To plan transport in a way

so that material

requirement can be met in

the shortest possible time

with minimum number of

kilometers driven

(Sichwardt, 2011).

To plan transport in a

way that vehicles can

visit maximum

number of touch

points, deliver largest

amounts of material,

minimize delivery

time and reduce

distance travelled etc.

Security Protection against

deliberate threats (Baird,

2017)

Potential harm caused

by others. For

example, if somebody

throws the brick or if

somebody starts a fire.

Safety Being secure against

unintended threats (Baird,

2017)

Protection against

things that happen by

chance/accident. For

example, a brick falls

on a builder head or if

fire starts by accident

etc.

Comprehensiveness It means including or

dealing with all or nearly

all elements or aspects of

something. Cambridge

dictionary (2019)

Comprehensiveness

means complete,

covering almost every

aspect.

Early delivery Early delivery is a delivery

that is made well before

agreed time. Northey

(2018)

Delivery that

happened before time.

Page 71: Developing transport performance measures for Construction

63 | P a g e

On time delivery On time delivery is the date

promised by supplier to

make a delivery to its

client. It helps in optimal

utilization of time.

Marion (2019)

Delivery that happen

exactly on agreed time

Late delivery Late delivery is a delivery

that take place after the

agreed upon time of

delivery. Darvik and

Larsson, (2010)

Delivery that happed

after agreed time

Vehicle utilization

(km)

Vehicle utilization will

help in calculating no. of

trips or kilometer travelled

by vehicle in a specific

period thus playing major

role in effective transport

planning.

Hosseini and Shirani

(2011), Malacarne (2018)

Mileage i.e. how many

kilometers a vehicle

can cover per hour

Vehicle weight

utilization

Vehicle weight utilization

will determine the quantity

of material carried.

Hosseini and Shirani

(2011), Malacarne (2018)

How much volume a

vehicle can carry

Shipping

documents

Shipping documents are

papers that accompany a

shipment listing the date

shipped, the customer, the

method of shipment and

the quantities and

specifications of goods

shipped. Collins English

dictionary (2019).

Documents also

known as pick list

containing

information such as

customer address,

shipment date,

delivered products

code and description,

product quantity,

value and so on.

4.3 Empirical findings from semi structured interviews The main aim of semi structured interviews was to identify transport related

performance measures within construction logistics solutions. These

interviews have highlighted those transport related performance measures

whose measurement is crucial for both logistics solutions. At this point in time,

no classification has been made that which transport performance measures

Table 18: Operationalization for semi structured interviews (Own illustration)

Page 72: Developing transport performance measures for Construction

64 | P a g e

belongs to terminal, checkpoint and construction site. This empirical finding

reflects only transport related performance measures without being classified

into terminal, checkpoint and construction site.

4.3.1 Case 1-Terminal

According to business unit manager (14.1.2019) construction logistic solutions

can bring efficiency to the construction site. As he suggests that the benefits

of logistic solutions are obvious, but it is hard to verify these benefits. He

further adds on that in order to quantify construction logistics benefits, there

is a need to develop transport performance measures. On asking about the

transport performance measures being used by their company, sales executive

(14.1.2019) suggests that due to fragmented nature of construction projects it

is hard to develop good and comprehensive performance measures. In addition

to this, he suggests that the process of performance measure development is

also not so streamlined. Founder of case company (14.1.2019) suggest that it

is important to have few but comprehensive and holistic performance

measures. He is of the opinion that too many performance measures make it

difficult to monitor them thus resulting in no improvement. All the respondents

are of the view that it is important to have well defined performance measures,

and these should be developed from 360-degree perspective. In addition to the

performance measures discussed in theory, business unit manager (14.1.2019)

highlights some other performance measures which are as follows in Table 19;

Page 73: Developing transport performance measures for Construction

65 | P a g e

Performance measures

highlighted by Case 1-terminal

during interview

Explanation

Reduction in average waiting time

at gate and stops etc.

According to business unit manager

(14.1.2019), 50% of the daytime gets

wasted in waiting. So, this is very

important to consider as a

performance measure.

Optimal route planning to and

from construction site

Case founder (14.1.2019) suggests

that it is important to optimally plan

delivery routes. He is of the view

that a lot of time and cost get wasted

if there is ineffective route planning.

Easy access to construction site Case founder (14.1.2019) suggest

that it is essential for construction

logistic solution to give vehicles

easy access to the construction site.

Because otherwise vehicles will not

be able to come to the destination

and unload the required material

which will eventually lead to delay

in construction project.

Assuring estimated time of arrival

(ETA)

Sales executive (14.1.2019) suggest

that it is important to measure

estimated time of arrival because it

will give a clear idea that when a

vehicle is expected to arrive at a

certain place.

They also suggest that it is good to develop performance measures aligning

with the strategic objectives.

4.3.2 Case 2-Checkpoint

Logistics consultant at case company 2 (14.1.2019) advocates Case 1

respondents and have similar views. According to her, following performance

measures are necessary to develop which are as follows in Table 20;

Table 19: Performance measures highlighted by Case 1 during interview (Own

illustration)

Page 74: Developing transport performance measures for Construction

66 | P a g e

Performance measures

highlighted by Case 2-terminal

during interview

Explanation

Reduce cost of delivery Logistics consultant (14.1.2019)

suggests that cost of delivery is very

high. So, it is important to measure

the costs of delivery and reduce the

unnecessary steps to make it less

costly

Reduce cost of moving material According to her, in order to get

discounts generally more material is

ordered as compared to what is

needed which results in cost for

moving material. By measuring this,

wastage can also be reduced along

with the reduction in cost of moving

material

Optimal transport per day Logistics consultant (14.1.2019)

suggests that it is important to

determine what amount of transport

should be there and how this

transport will vary between different

days as well as between different

parts of the day.

No. of booked vs un-booked

deliveries

According to logistics consultants

(14.1.2019) in checkpoint for

delivery and pickup, a booking is

done in order to effectively manage

delivery. So, it is important to

measure no. of booked vs un-booked

deliveries in order to control

inefficiency that takes place due to

un-booked delivery.

Vehicles schedule reliability She suggests that it is important to

have reliable vehicle schedule so that

there should be no delays and no

waiting times.

Minimize delivery distances Logistic consultant (14.1.2019)

suggest that measuring delivery

distance is very important

performance measure because it then

helps in defining proper delivery

routes

Page 75: Developing transport performance measures for Construction

67 | P a g e

Effective loading and unloading

(in terms of time)

She suggests that there should be

efficient loading and unloading and

no time should be wasted while

performing these activities. So, this

is an important performance

measure in order to bring

improvement in transport flows.

Reduce road damage due to

vibrations

According to her, transport vehicles

impact overall environment as well

such as road damage due to vehicle

movements. She suggests that it is

important to meet weight limits and

criteria for vehicles before going on

road. As construction material is

heavy so care should be taken in

deciding how much load a vehicle

should carry.

4.4 Combining findings from theory and semi structured

interviews Empirical findings from semi structured interviews along with theory have

resulted in identifying transport related performance measures which are

applicable to both logistics solution and their respective construction site. This

has helped in developing protocol for focus group discussion which will be

mentioned below in Table 21 and as well as attached in Appendix 2. The aim

of focus group was to identify which performance measure is relevant to what

logistic solution.

Table 20: Performance measures highlighted by Case 2 during interview (Own

illustration)

Page 76: Developing transport performance measures for Construction

68 | P a g e

Objective:

Effective

transport

planning

Objective:

Reduce

transportation

time

Objective:

Transport

cost

minimization

Objective:

To achieve

environmental

sustainability

Objective:

To ensure

security

Objective: To

ensure safety

Reduced no. of

miles driven

outside of pre-

determined

routes

Ensure on time

delivery

Reduce no. of

trips per

vehicle

Reduction in

CO2 emission

Ensure good

quality

packaging

of

hazardous

material

Reduce no. of

transport

incidents

Reduce total

distance driven

Reduce truck

turnaround time

-Loading and

unloading time

- Easy access to

construction site

-Utilization rate

of loading and

unloading

equipment

Ensure

vehicle fuel

efficiency

including idle

time

Minimize no.

of breaches in

noise limits

Reduce on

road

material

theft

Ensure vehicle

insurance

Ensure trucks

availability

(trucks

confirmed vs

requested)

Minimize

vehicle travel

time

Reduce no. of

empty miles

Road damage

due to vehicle

vibrations or

vehicle

overload

Reduced no. of

unplanned

deliveries

Reduce the time

taken in

preparing

shipping

documents

Minimizing

maintenance

cost

Optimal no. of

deliveries

arrives at gate

per day

Minimize the

time taken in

doing shipping

documents

corrections

Reduce no. of

damages

during

delivery

Maximize

vehicle travel

capacity

Reduction in

average waiting

time at gate

Optimize no.

of vehicles

movement

Maximize

vehicle weight

utilization

Vehicles

schedule

reliability

Reduce cost

of delivery

Table 21: Focus group protocol (Own illustration)

Page 77: Developing transport performance measures for Construction

69 | P a g e

4.5 Frame of reference for focus group protocol The operationalization of focus group protocol is mentioned below in Table

22;

Key terms Conceptual definition Operational definition

Reduced no. of

miles driven

outside of pre-

determined

routes

This measure refers to no. of miles

that vehicle will travel outside of

already determined route in order to

reach the destination.

Robinson (2019), Ryus et al.,

(2013)

This measure will ensure the effectiveness/

accuracy of planned routes. Are routes planned

well that vehicles do not face any problem in

following those routes or vehicles have to

follow another route to reach their destination?

The focus of this measure is to see how well

vehicle routes have been designed.

Reduce total

distance driven

It refers to the total distance that

vehicle has travelled. This measure

will give information regarding

delivery distances and helps in

effective transport planning.

Kaparias and Bell (2011), Freight

best practice (2010)

Total distance driven is measured to see how

many miles or kilometers vehicle has to travel.

Measuring this will help in planning deliveries

i.e. how much time will be needed to reach

vehicle to reach destination, what should be the

buffer time for vehicles and so on. This

measure will also help in determining the

optimal speed level that drivers can maintain to

reach to the destination on time.

Ensure trucks

availability

(trucks

confirmed vs

requested)

This measure refers to the truck’s

availability in need. Truck

unavailability will lead to delays

which is a sign of ineffective

transport planning. This indicator

will help in fleet management.

Brierley (2017), Key performance

indicator survey (2013)

The measure aims at measuring no. of vehicles

required for material supply deliveries. It will

help in identifying delays due to vehicles non

availability.

Reduced no. of

unplanned

deliveries

This measure refers to the presence

of contingency plan within

transport system. Based on this

measure, the extra time that gets

consumed in unplanned delivery

will be reduced.

Beetrack (2016), Faschingbauer

(2015)

This measure aims at measuring planning

effectiveness or how well delivery process has

been designed.

Optimal no. of

deliveries

This performance measure leads to

efficient delivery scheduling which

consequently results in efficient

The measure aims at measuring the total

material requirement at construction site on

daily basis. This also indicates that how much

Page 78: Developing transport performance measures for Construction

70 | P a g e

arrives at gate

per day

transport planning. The input for

this measure will be effective

material requirement planning.

Thomas (2017), Ogden and Turner

(2015)

material should be made available at supplier’s

end.

Maximize

vehicle travel

capacity

Vehicle capacity is a measure for

vehicle utilization. Vehicle

utilization will help in calculating

no. of trips thus playing major role

in effective transport planning.

Malacarne (2018), Hosseini and

Shirani (2011)

It refers to the number of times trucks are in

use in a given period.

Maximize

vehicle weight

utilization

Vehicle weight utilization will

determine the quantity of material

carried. Malacarne (2018),

Hosseini and Shirani (2011)

Weight capacity utilization is defined as the

ratio of truck weight plus the material weight

that truck is carrying and total weight capacity

of the truck.

Ensure on time

delivery

On time delivery is the date

promised by supplier to make a

delivery to its client. It helps in

optimal utilization of time.

Marion (2019)

It mainly means “being on time”. On time

delivery (OTD) can be measured by

calculating the amount of shipments delivered

on time to the customer in relation to the total

number of orders shipped. It indicates

organization capability to achieve requested

delivery date (RDD)

Reduce truck

turnaround

time

-Loading and

unloading time

- Easy access to

construction site

Truck turnaround time is a major

performance measure including

loading and unloading times as

well as access time to construction

facility. Van Der Spoel, Amrit, Van

Hillegersberg (2015)

Truck turnaround time is defined as the

average time utilized between a truck’s arrival

at any plant/facility and its departure from the

same. In simple words it is in time and out time

of truck.

Minimize

vehicle travel

time

It is defined as total time that

vehicle take in reaching its

destination. Yan, Xu, Han (2015),

Lomax, Schrank, Lasley, Eisele

(2013)

It refers to reduction in total travel time of the

vehicle.

Reduce the time

taken in

preparing

This refers to time taken in

preparing shipping document. It

also indicates the time difference

between order placed and making

Shipping documents include bill of lading,

commercial invoice, certificate of origin,

insurance certificate, packing list and other

custom clearance documents.

Page 79: Developing transport performance measures for Construction

71 | P a g e

shipping

documents

shipping documents ready. Naoh

(2018), Manaadiar (2017)

Minimize the

time taken in

doing shipping

documents

corrections

It refers to time taken in doing

corrections in shipping documents

such as address, price, quantity,

product detail and so on. Naoh

(2018), Manaadiar (2017)

It reflects the accuracy of shipping

documentation such as address, invoice

number, customer name, right material name,

quantity and price calculations

Reduction in

average waiting

time at gate and

stops

This measure refers to the vehicle

waiting time at gate and stops. 50%

of the daytime get wasted in

average waiting time. Business unit

manager (14.1.2019)

It refers to waiting time that truck has to pass

while being in queue at the entrance gate of

construction site

Vehicles

schedule

reliability

It refers to dependability on vehicle

time of arrival and departure.

Logistic consultant (14.1.2019)

It shows that how reliable or consistent vehicle

schedule is

Reduce no. of

trips per vehicle

This measure refers that how many

trips vehicle must make to meet the

customer demand. It also

determines the no. of vehicles that

one should have. Florida

department of transport (2014),

Freight best practice (2010)

It shows the number of trip that vehicle will

make from supplier to construction site.

Ensure vehicle

fuel efficiency

including idle

time

This measure refers to the distance

that a vehicle can travel by using a

particular amount of fuel. Waters

(2019), EECA business (2017)

It refers how efficiently vehicle fuel is getting

consumed in comparison to its

output/performance.

Reduce no. of

empty miles

Empty miles refer to the distance

travelled while generating no

income. Empty miles results when

truck travel without load. Freight

best practice (2010)

Empty miles refer to empty returns that truck

has to do in some cases.

Minimizing

maintenance

cost

There is critical need to maintain

vehicles in order to avoid any kind

vehicle failure. It includes cost of

cleaning and costs of good quality

tyres etc. Dönmez and Zemmouri

(2016)

The cost incurs in order to maintain vehicle

Page 80: Developing transport performance measures for Construction

72 | P a g e

Reduce no. of

damages during

delivery

This measure refers to damages that

occur in transit or at the time of

loading and unloading.

Bodenheimer (2014)

Damages can happen during transit, loading

and unloading or at site.

Optimize no. of

vehicles

movement

This measure includes all the

vehicle movements from delivering

material to removing waste at

construction site. Yin, Tookey,

Seadon (2018)

Vehicle movements refer to all movement

from delivering material to carrying back the

waste as a return

Reduce cost of

delivery

Cost of delivery is hourly cost of

delivery divided by number of

deliveries made each hour. Logistic

consultant (14.1.2019)

Total delivered cost is the amount of cost that

is incurred by the company from point of

manufacturing a product to its delivery. It

includes all costs such as packing, loading,

unloading, transporting, etc

Reduction in

CO2 emission

This measure refers to minimize air

pollution due to CO2 emission via

vehicles. Sichwardt (2011)

To reduce air pollution

Minimize no. of

breaches in

noise limits

This measure refers to the number

of times the vehicle has violated the

noise limitations such as horns,

sound of engines, material loading

and unloading at night etc. Sound

noise limit report (2005)

To reduce air pollution

Road damage

due to vehicle

vibrations or

vehicle overload

Due to vehicle overload and

resonance, roads get damaged.

Logistic consultant (14.1.2019)

Roads getting torn due to heavy duty vehicles

Ensure good

quality

packaging of

hazardous

material

This measure refers to quality

criteria for material packaging. It

suggests that material should be

packaged in strong and leak tight

way while delivery. Burdick (2012)

Packaging should be leak tight and of good

strength

Reduce on road

material theft

On road material theft affect

productivity and drain profits. On

road material theft should be

avoided. Berg and Hinze (2005)

To reduce on road material thefts

Page 81: Developing transport performance measures for Construction

73 | P a g e

Reduce no. of

transport

incidents

This refers to number of traffic

incidents and casualties resulting

from crashes per time period.

Tamuli (2016),

Botha (2005)

Reduce no. of vehicle accidents

Ensure vehicle

insurance

In order to safeguard vehicles

against accidents, damage and theft

it is important to insure vehicles.

Tamuli (2016),

Botha (2005)

In order to remain safe from any unforeseen

circumstance, it’s good to have vehicle

insurance

4.6 Empirical finding from focus group discussion The aim of focus group was to classify performance measures according to

terminal, checkpoint and construction site. So, the main theme under focus

group discussion was “what performance measures do you consider are the

most relevant”. The purpose was to verify and cross check identified transport

performance measures via theory and semi structured interviews and also to

make changes (add/remove) accordingly.

4.6.1 Case 1-Terminal

According to business unit manager (4.4.2019) the measure “reduced no. of

miles driven outside of pre-determined routes” is relevant to terminal because

terminal follows a milk run approach. He further suggests that it would be easy

to measure by selecting one regular supplier and then taking observations.

Founder, business unit manager (4.4.2019) further suggests that performance

measures such as reduced total distance driven, ensure on time delivery, reduce

truck turn-around time, vehicle schedule reliability, reduced no. of empty

miles, reduced no. of damages, reduction in CO2 emissions, minimizing

maintenance cost, reduced no. of unplanned deliveries, optimal no. of

shipment arrive at gate per day, maximize vehicle weight utilization, reduction

in average waiting time at gate, reduce the time taken in preparing shipping

documents, minimize the no. of errors in shipping documents, minimize

vehicle travel time, no. of vehicle movements, reduce no. of trips per vehicle,

reduce no. of transport incidents, ensure good quality packaging of hazardous

material, reduce on road material theft, road damage due to vibrations,

optimize vehicle movements are all relevant to terminal.

Table 22: Operationalization of focus group protocol (Own illustration)

Page 82: Developing transport performance measures for Construction

74 | P a g e

They further add on that instead of truck availability they also require right

kind of fuel due to objective of achieving environmental sustainability. In

addition to this, they also emphasized the importance of not only vehicle

capacity in terms of kilometers and volume but also in terms of shape of

vehicle. They suggest that it is very important for them to consider shape of

vehicle to fit in the turning area and also they need to care about the height of

vehicles due to entrance into the basements. They add on that in winters they

ensure the use of winter tyres for having more grip in the snow.

Regarding vehicle insurance for safety they suggest that all their vehicles are

already insured. Regarding noise breaches, they suggest that it is good to have

but they have not faced any difficulty with this. Additional performance

measures which got highlighted during focus group are shown in Table 23;

Additional performance measures

got highlighted during focus

group discussion

Explanation

Reduced no. of unauthorized

entries

While talking about security,

business unit manager (4.4.2019)

suggest that reduced no. of

unauthorized entries to construction

site are also important to measure.

Reduced no. of interruptions to

ongoing construction site

Again, referring to security, business

unit manager (4.4.2019) suggest that

there is need to ensure reduced no. of

interruptions to ongoing

construction activities.

Certificate for good eco driving Founder (4.4.2019) suggest that it is

their aim to achieve certificate for

good eco driving in order to ensure

environmental sustainability

objective

Predictability of turnaround time Moderator (4.4.2019) suggest that it

is also important to have good

estimates regarding turnaround

times

Table 23: Additional performance measures got highlighted during focus group

discussion-Case 1 (Own illustration)

Page 83: Developing transport performance measures for Construction

75 | P a g e

4.6.2 Case 2-Checkpoint

Logistic consultant (15.4.2019) suggests that for checkpoint the performance

measure “minimizing distance from checkpoint to unloading zones” is more

relevant rather than performance measure “reducing total distance driven”.

She further suggests that reduction of unplanned deliveries is very relevant for

checkpoint. According to her, optimal no. of shipments arrives per day,

reduction in truck around time, reduced no. of damages, reduction in material

theft, availability of no. of parking spaces for unloading available vehicles is

relevant. She further suggests that optimal no. of vehicle movements and

reducing cost of delivery also plays an important role in checkpoint

performance evaluation.

Other performance measures mentioned in focus group protocol are not very

relevant to checkpoint according to logistic consultant (15.4.2019). This is

because they do not own their own vehicles. Additional performance measures

got highlighted during focus group discussion are mentioned in Table 24;

Additional performance measures

got highlighted during focus

group discussion

Explanation

Ensure unloading available

vehicles

Logistics consultant (15.4.2019)

suggest that it is important to ensure

unloading of available vehicles

Maximum no. of available parking

spaces

Logistics consultant (15.4.2019) is

of view that it is important for

checkpoint to have a greater number

of parking spaces

4.7 Conceptual model of the study Figure 17 below shows conceptual model after theory and empiry. In this

model, all identified transport related performance measures (i.e. via theory,

semi structured interview and focus group have been arranged according to

terminal, checkpoint and their respective construction sites.

Table 24: Additional performance measures got highlighted during focus group

discussion- Case 2 (Own illustration)

Page 84: Developing transport performance measures for Construction

76 | P a g e

Figure 17: Conceptual model after theory and empiry (Own illustration)

3

Con

stru

ctio

n Lo

gist

ic S

olut

ion

6 6

Ter

min

al

Con

stru

ctio

n S

ite

Con

stru

ctio

n S

ite

*Per

form

ance

mea

sure

s ar

e re

late

d to

tran

spor

t flo

ws

only

Tra

nspo

rt F

low

s

Tra

nspo

rt r

elat

ed p

erfo

rman

ce m

easu

res

to, f

rom

and

with

in th

e co

nstr

uctio

n si

te

Per

form

ance

Mea

sure

s

- E

nsur

e on

tim

e

deliv

ery

-Ens

ure

relia

bilit

y

in tr

avel

tim

es

- E

nsur

e rig

ht k

ind

of tr

uck

and

fuel

avai

labi

lity

- O

ptim

al n

o. o

f

ship

men

ts a

rriv

e at

gate

per

day

-Max

imiz

e ve

hicl

e

utili

zatio

n in

km

(

mor

e sh

ape

and

heig

ht)

- M

axim

ize

vehi

cle

wei

ght u

tiliz

atio

n

- Red

uce

time

tak-

en in

pre

parin

g s-

hipp

ing

docu

men

ts

- Min

imiz

e th

e no

.

of s

hipp

ing

docs

erro

r

- Red

uce

C02

emis

sion

- Red

uce

num

ber

of a

ccid

ents

- Red

uce

num

ber

of d

amag

es d

ue

to v

ibra

tions

Che

ckpo

int

Per

form

ance

Mea

sure

s

- M

inim

izin

g di

stan

ce fr

om c

heck

poin

t

to u

nloa

ding

zon

e

- R

educ

e nu

mbe

r of

unp

lann

ed d

eliv

er-

ies

- M

axim

um n

umbe

r of

ava

ilabl

e pa

rkin

g

spac

es

- E

nsur

e un

load

ing

avai

labl

e ve

hicl

es

Tra

nsit

-Red

uced

num

ber

ofm

iles

dr-

iven

out

side

of p

re d

eter

min

-

ed r

oute

s

-Red

uce

tota

l dis

tanc

e dr

iven

-Red

uce

num

ber

of e

mpt

y

mile

s

-Min

imiz

e ve

hicl

e tra

vel t

ime

-Red

uce

num

ber

of d

amag

es

-Ens

ure

vehi

cle

fuel

effic

ienc

y

-Opt

imiz

e nu

mbe

r of v

ehi-

cle

mov

emen

ts

-Red

uce

vehi

cle

mai

nte-

nanc

e co

st

-Ens

ure

good

qua

lity

mat

-

eria

l pac

kage

Tra

nsit

-Red

uce

num

ber o

f dam

ages

-Opt

imiz

e nu

mbe

r of v

ehic

le m

ovem

ents

-Red

uce

cost

of d

eliv

ery

-Red

uctio

n in

mat

eria

l the

ft

Site

-Red

uce

num

ber o

f dam

ages

-Ens

ure

on ti

me

deliv

ery

-Num

ber o

f una

utho

rized

entr

ies

-Num

ber o

f int

erru

ptio

ns

to o

ngoi

ng c

onst

ruct

ion

oper

atio

ns

-Opt

imal

num

ber o

f shi

pmen

ts

arriv

e at

gat

e pe

r day

-Red

uce

time

take

n in

prep

arin

g sh

ippi

ng

docu

men

ts

-Eas

y ac

cess

to th

e co

ns-

truc

tion

site

-Red

uctio

n in

ave

rage

w-

aitin

g tim

e at

the

gate

-Red

uce

truc

k tu

rnar

ound

time

Site

-Opt

imal

num

ber

of d

eliv

erie

s ar

rive

at g

ate

per

day

-Red

uctio

n in

ave

rage

wai

ting

time

at g

ate

-Red

uce

num

ber

of d

amag

es

-Red

uce

truc

karo

und

time

Con

stru

ctio

n lo

gist

ics

Page 85: Developing transport performance measures for Construction

77 | P a g e

4.8 Analysis The purpose of research question 1 was to identify transport related

performance measures for the evaluation of construction logistics solution and

their respective construction site. Business unit manager (14.1.2019)

expressed his opinion during semi structured interview that it is good to have

few but comprehensive performance measures so for this reason there is need

to consolidate performance measures. The other reason for consolidating

performance measure is to remove redundancy and duplication among

identified performance measures. For example, the performance measure

“optimize no. of vehicle movements” aims at measuring the same variables as

another performance measure “reduce cost of delivery”. These both

performance measures aim at reducing logistics cost. The criteria for choosing

performance measures in consolidation process is ease in calculation.

The consolidated table for transport related performance measures within

construction industry is shown below in Table 25;

Objective:

Effective

transport

planning

Objective: To

reduce

transportation

time

Objective:

To minimize

cost

Objective:

To achieve

environmental

sustainability

Objective

: To

ensure

security

Objective:

To ensure

safety

Performance

measures:

Vehicle route

optimization

• Reduce

total

distance

driven (no.

of stops,

distance

between

stops)

• Minimize

vehicle

travel time

(no. of

miles

Performance

measures:

Reduce truck

turnaround time

• loading/un

loading

activities

• vehicle

waiting

time

• access

time to

constructi

on site

• utilization

rate of

loading

Performance

measures:

Minimize no.

of in-transit

damages

Performance

measures:

Minimize road

damage

-Road

vibrations and

overload

Performan

ce

measures:

Ensure

good

quality

packaging

of

hazardous

material

Performance

measures:

Reduce no.

of transport

incidents

Page 86: Developing transport performance measures for Construction

78 | P a g e

traveled

and speed)

and

unloading

equipment

Effective

contingency

planning

• Reduced

no. of un-

planned

deliveries

Minimize

vehicle

maintenance

costs

-cleaning

-oil and filter

change

-tire

replacement

-brake pad

and fluid

replacement

-coolant

replacement

-vehicle

washing

-wear and

tear etc.

Reduce CO2

emission

-Maximize

vehicle

utilization

-Optimize no.

of vehicle

movements

-Vehicle route

optimization

Reduce on

road

material

theft

Ensure

vehicle

insurance

Effective material

requirement

planning

• Optimal

no. of

shipments

arrives at

gate per

day

Maximize

vehicle

utilization

-time

-capacity

Optimize no.

of vehicles

movement

4.8.1 Explanation of the consolidated table

For effective transport planning, three major performance measures have been

identified i.e. vehicle route optimization, effective contingency planning,

Table 25: Consolidated performance measures (Own illustration)

Page 87: Developing transport performance measures for Construction

79 | P a g e

effective material requirement planning. And then identified transport related

performance measures have been clubbed/merged into these major

performance measures which will be discussed in detail below;

4.8.1.1 Effective transport planning

4.8.1.1a) Vehicle route optimization

According to Yan, Xu, Han (2015) vehicles route optimization minimizes total

travelling time as well as reduce uncertainties in pickup and delivery timings.

He further suggests that effective transport planning includes route

determination i.e. to visit maximum number of touch points, to deliver largest

amounts of material, minimize delivery time and distance travelled etc.

Business unit manager (14.1.2019) explained during interview that the biggest

challenge they are facing with terminal construction logistic solution is “how

to route deliveries to and from construction site”. For this purpose, this

consolidated measure has been chosen. Sichwardt (2011) suggests that in case

of distribution via terminal it is good to choose shortest distance for respective

routing. He further suggests that shortest distance will not only save costs but

there would be less CO2 emissions as well. He adds on that vehicle route

optimization can be measured by “Reduced Total Distance Driven” metrics.

Eriksson (2015) suggests that in order to calculate this it is important to have

data on number of stops, distance between stops, time for hauling etc. In

addition to this, “Minimize Travel Time” is also considered as important for

vehicle route optimization Yan, Xu, Han (2015). Lomax et al. (2013) define

“Travel Time” as the door to door sum of all travel times. They further suggest

that factors such as bad weather, unexpected vehicle breakdown, congestion,

driver skill and experience will be considered in this.

4.8.1.1b) Effective contingency plan

Sanchez-Rodrigues, Potter, Naim (2010) suggest that uncertainty in supply

chain act as a hurdle in effective transport management and control. They

further suggest that uncertain situation can occur due to external factors (such

as road closures, accidents, terrorist attacks, etc.,) as well as internal factors

(such as poor planning and demand prediction). Logistic consultant

(15.4.2019) suggests that unplanned deliveries create inefficiency in whole

delivery process within checkpoint construction logistics. She further suggests

that transport planning should be so effective that there should not be any

unplanned deliveries. But she adds on that if due to unforeseen circumstances

any unplanned delivery takes place then the system should be so strong that

without any delay it can respond to unexpected situation without wasting any

Page 88: Developing transport performance measures for Construction

80 | P a g e

time. Anastasia (2017) suggests that it is important to have effective

contingency or business continuity plans because it reflects organization

capability to deliver its products or services even after any disruptive incident.

Faschingbauer (2015) suggest that contingency plan is the best customer

service that transportation company can provide by allowing freight to remain

operational. Beetrack (2016) suggests that there should be flexibility within

the delivery management process and transporters should respond and adjust

schedules as unplanned issues arise. The effectiveness of contingency plan can

be measured by responsiveness of unplanned deliveries metric.

4.8.1.1c) Effective material requirement planning

Sarkar et al. (2013) suggest that material requirement planning (MRP) helps

in calculating the material and components required to construct a building.

They further suggest that it includes three steps i.e. to know what material and

components are in hand, identifying which additional material is needed

followed by raising request for procurement or production. They further

suggest that material requirement planning ensure availability of required

materials in time of need while maintaining adequate inventory levels.

Thomas (2017) highlights that material requirement planning play crucial role

in effective shipment planning i.e. what, where and when the material is

required. He further suggests that effective material planning helps in

calculating “Optimal no. of shipments arrive at gate per day” performance

metric.

4.8.2 Other Objectives

In order to meet the objective of transportation time minimization, a

consolidated measure “reduced turnaround time” will be considered. This is a

very comprehensive measure because it includes loading/unloading activities,

access time to construction site and also utilization rate of loading and

unloading equipment. For meeting objective of cost minimization, the

performance measures such as reduced no. of damages (in-transit), reduced

vehicle maintenance cost, maximum vehicle utilization and optimal no. of

vehicle movements have been considered. These performance measures have

been selected because they are relevant to both construction logistics solutions

and will also give true picture of logistics cost. As far as environmental

sustainability objective is concerned, two performance measures have been

selected i.e. reducing the road damage incurred due to vehicle vibrations and

vehicle overload and reduction in CO2 emission. CO2 emission can be reduced

by maximizing vehicle utilization, optimizing number of vehicle movements,

Page 89: Developing transport performance measures for Construction

81 | P a g e

optimizing vehicle route. Good quality packaging of hazardous material and

reducing material theft are two measures chosen to ensure security. And lastly

reduced no. of transport incidents and having vehicle insurance are necessary

measures for ensuring safety.

The conceptual model with consolidated transport performance measures

classified according to construction logistics solution (i.e. terminal and

checkpoint) and their respective sites are shown below in Figure 18.

Page 90: Developing transport performance measures for Construction

82 | P a g e

Figure 18: Consolidated conceptual model after analysis (Own illustration)

6 6

Term

ina

l

Con

str

uctio

n S

ite

Con

str

uctio

n S

ite

*Perf

orm

ance m

ea

su

res a

re r

ela

ted

to

tra

nsp

ort

flo

ws o

nly

Tra

nspo

rt F

low

s

Tra

nspo

rt r

ela

ted

pe

rfo

rma

nce

me

asure

s t

o,

fro

m a

nd

with

in th

e c

onstr

uction

site

Pe

rfo

rma

nce

Me

asu

res

Vehic

le R

oute

Optim

ization

-

Reduce tota

l dis

tance d

riven

-

Min

imiz

e v

ehic

le tra

vel tim

e

Effective m

ate

rial re

quirem

ent pla

nnin

g

-O

ptim

al num

ber

of ship

ments

arr

ive

a

t gate

per

day

Effective c

ontingency p

lan

-R

educed n

o. of unpla

nned d

eliv

eries

-M

axim

ize v

ehic

le u

tiliz

ation

-E

nsure

vehic

le insura

nce

Che

ckpo

int

Pe

rfo

rman

ce M

ea

su

res

Effective c

ontingency p

lan

-R

educed n

um

ber

of pla

nned d

eliv

er-

ies

Effective m

ate

rial re

quirem

ent pla

nnin

g

-O

ptim

ize n

um

ber

of ship

ments

arr

-

ive a

t gate

per

day

Tra

nsit

-Reduced n

um

ber

of dam

ages in tra

nsit

-Min

imiz

e v

ehic

le m

ain

tenance c

ost

-Optim

ize n

um

ber

of vehic

le m

ovem

ents

-Good q

ualit

y p

ackagin

g o

f hazard

ous m

ate

rial

-Reduced r

oad d

am

age

-Reduced C

O2 e

mis

sio

n

-Reduced n

um

ber

of tr

ansport

incid

ents

Tra

nsit

-Reduced n

um

ber

of dam

ages

-Optim

ize n

um

ber

of vehic

le m

ovem

ents

-Reduce m

ate

rial th

eft

Site

Reduced n

um

ber

of dam

ages a

t site

Effective m

ate

rial re

quirem

ent pla

nnin

g

-O

ptim

al num

ber

of shpm

ents

arr

ive a

t gate

per

day

Reduced n

um

ber

of tr

ansport

incid

ents

Reduce tru

ck turn

aro

und tim

e Site

-Reduced m

ate

rial th

eft

-Reduced n

um

ber

of tr

ansport

incid

ents

-Reduced tru

ck turn

aro

und tim

e

Co

nstr

uctio

n lo

gis

tics

Co

nstr

uctio

n lo

gis

tic s

olu

tio

n

Page 91: Developing transport performance measures for Construction

83 | P a g e

5 Framework for RQ2

The research question 2 is “what kind of data is needed to measure identified

transport related performance measures in research question 1. The purpose of

this research question will be satisfied by providing calculations to the

identified transport performance measures in RQ1. Here the prime focus is to

only show the way for calculating identified performance measures

irrespective of goal assigned to them i.e. maximize or minimize. The

operationalization for this research question will remain the same as used in

research question 1. Because this chapter shows calculations for same

performance measures that have been explained previously in section 4.2 and

4.5.

5.1 Theory This chapter will discuss theoretical formulas for the following identified

performance measures shown in Table 26;

Identified performance measures

from RQ1

Identified performance measures

from RQ1

Objective: Effective transport

planning

-Total distance driven

-Total travel time

-No. of unplanned deliveries

-No. of shipments arrives at gate per

day

Objective: To achieve

environmental sustainability

-Road damage through vibrations

-CO2 emission

Objective: Minimizing

transportation time

-Truck turnaround time

Objective: To ensure security

-Packaging of hazardous material

-On road material theft

Objective: Cost minimization

-No. of in-transit damages

-Vehicle maintenance costs

-Vehicle utilization (time, capacity)

-No. of vehicle movements

Objective: To ensure safety

-No. of transport incidents

-Vehicle insurance

After this empiry will be discussed and then analysis will be made on the basis

of theory and empiry.

5.1.1 Objective: Effective transport planning

The objective “effective transport planning” is majorly divided into vehicle

route optimization, effective contingency planning and effective material

Table 26: Performance measures to be studied under RQ2 (Own illustration)

Page 92: Developing transport performance measures for Construction

84 | P a g e

requirement planning which are further measured by following performance

measures.

5.1.1.1 Total distance driven

According to Network for transport calculations, NTMCalc (2010) the “total

distance driven” can be calculated as follows;

Let us consider a vehicle as shown in Figure 19 that is supposed to unload

goods to n different construction sites, each named 1, 2, 3, … , n, respectively.

The vehicle is assumed to start from a certain Starting Point, and it finishes its

route by coming back to that point.

In the forthcoming discussion, the distance between two sites would be

expressed in the form of:

𝑑(𝑋, 𝑌)

Figure 19: A sample path of the vehicle (Own illustration)

Page 93: Developing transport performance measures for Construction

85 | P a g e

Where, X and Y represent two distinct sites, that could either be a construction

site, or the starting point.

Therefore, the total distance traveled (D) by the vehicle can be represented by

𝐷 = 𝑑(𝑆𝑃, 1) + 𝑑(𝑛, 𝑆𝑃) + ∑ 𝑑(𝑖, 𝑖 + 1)

𝑛−1

𝑖=1

Here, SP denotes the Starting Point.

In order to find the saving in distance by a terminal, the formula suggested by

Sichwardt (2011) can be considered which is as follows;

Sichwardt (2011) explains saving in distance formula with the help of Figure

20 that if each construction site is served by a single vehicle from the terminal,

then the total distance would be 2x15km and 2x12km=54 km. He highlights

that if only one vehicle is used in a single trip the total distance would be 15

km+5 km+12 km= 32 km. So according to Sichwardt (2011) the total distance

saved would be equal to 15km + 12 km -5 km = 22 km

Terminal

Construction

site A

Construction

site B

15 km

5 km

12 km

Figure 20: Saving in distance by terminal (Adopted)

Saving in distance by terminal= Distance (Terminal to Construction Site

A) + Distance (Terminal to Construction Site B) – Distance (Construction

Site A to Construction Site B)

Page 94: Developing transport performance measures for Construction

86 | P a g e

5.1.1.2 Travel Time

According to Lomax et al. (2013), the total travel time can be calculated as

follows;

They further suggest that the “delay” in travel time can be calculated as

follows;

5.1.1.3 No. of unplanned deliveries

According to Sanchez-Rodrigues et al. (2010) the formula for calculating “no.

of unplanned deliveries” is as follows,

5.1.1.4 No. of shipments arrive at gate per day

As per NTMCalc (2010) the “no. of shipments arrives per day” can be

calculated as;

Or it can also be calculated as (NTMCalc, 2010);

Travel Time= Vehicle miles of travel/Travel speed

Delay in travel time= [(Vehicle miles of travel/actual speed) – (Vehicle

miles of travel/free-flow speed)]

No. of unplanned deliveries= No. of unplanned deliveries/ Total no. of

deliveries

No. of shipments arrive per day = Daily material requirement/ total

material requirement (for a project)

No. of shipments arrive per day = Rate of material being used

per day

Page 95: Developing transport performance measures for Construction

87 | P a g e

Thomas (2017) has suggested a formula for calculating “optimal number of

shipments per day” which is as follows;

According to him, “average delivery lead time” is the amount of time taken

by shipment to arrive at final destination”.

Delivery lead time can be calculated as (Thomas, 2017);

For example;

Month Order Amount Delivery time

Jan 80 pieces 7 days

Feb 80 pieces 5 days

Mar 50 pieces 3 days

Average lead time = 15 days/ 3 (no. of orders) = 5 days

5.1.2 Objective: Reduction in transportation time

5.1.2.1 Truck turnaround time

The “truck turnaround time” can be calculated in minutes or hours as

suggested by (Hensel, 2014);

5.1.3 Objective: Transport cost minimization

5.1.3.1 No. of damages (in transit)

As per Sonoco (2017), “number of damages” can be calculated as;

Sonoco (2017) further calculated “cost of damage” as;

Optimal no. of shipments arrives at gate per day = (Average daily

material consumption x delivery lead time) + Safety stock

Delivery lead time =Delivery time in days/ Total no. of orders

Truck Turnaround time= (Vehicle Time out) – (Vehicle Time in)

No. of damages = Total loss and damage/total stock costs

Cost of damage per unit= Total sales + Total profit before cost of

damage + Cost of damaged unit to customer + Cost to replace the unit

Page 96: Developing transport performance measures for Construction

88 | P a g e

5.1.3.2 Vehicle maintenance cost

The formula for calculating “vehicle maintenance cost” suggested by Dönmez

and Zemmouri (2016) is as follows;

5.1.3.3 Vehicle utilization

The formula for calculating “vehicle utilization” by (Malacarne, 2018) is as

follows;

According to Hosseini and Shirani (2011), “vehicle utilization” is calculated

in terms of time and weight which is as follows;

5.1.3.4 Cost incurred by no. of vehicle movements

The cost incurred by number of vehicle movements can be calculated by

transportation cost as per Ying, Tookey and Seadon (2018) because according

to them vehicle movements incorporate transportation from start of delivery

to the point when material is returned. So, “cost of vehicle movements” can

be estimated by “transportation cost” which is mentioned as follows;

Where CO is vehicle operating cost and D is the distance between site and

depot of the ith trip.

Vehicle maintenance cost = Sum of all maintenance cost (oil and filter

change + tire replacement + brake pad and fluid replacement + coolant

replacement + vehicle washing + general wear and tear etc.)

Vehicle utilization= Kilometers per vehicle per period

Or

Vehicle utilization= Operational hours or days per vehicle per period

Vehicle utilization (time)= Utilized time/available time

Vehicle utilization (weight)= Utilized load capacity/Available load

capacity

Total vehicle utilization= capacity utilization x time utilization

Transportation cost = σ COi x Di𝑛𝑖=1

Page 97: Developing transport performance measures for Construction

89 | P a g e

5.1.4 Objective: To achieve environmental sustainability

5.1.4.1 Road damage

According to Bai et al. (2009) the “road damage” can be calculated with a

damage function which measures the decline of road quality to traffic or axle

passes. The general form of damage function is shown below;

Where g= damage index

N= no. of times an axle group of specified weight pass

τ = the no. of axle passes at which the pavement reaches failure

β= damage rate for a given axle

5.1.4.2 CO2 emission

NTMCalc (2012) suggests transport companies should use energy-based

approach to calculate CO2 emission because it is easy and accurate to record

energy and fuel use and also to convert energy or fuel values into CO2

emissions. According to NTMCalc (2012) every liter of fuel consumed results

into a certain amount of CO2 emissions.

The formula used by NTMCalc (2012) to calculate “CO2 emission” is as

follows;

Sichwardt (2011) suggests fuel-based method to calculate CO2 emission which

is as follows;

𝑔 = (𝑁/𝜏 )β

CO2 emissions= fuel consumption x fuel emission conversion factor

[Tonnes CO2-emissions = litres x kg CO2 per liter fuel/1.000]

∑ CO2 emissions = ∑t=1 T (AFCt,n,m x hv x EF)

Where,

AFC = absolute fuel consumption in [1/100km] for the number of trucks (t

= 1, …. T), sort of truck (n= Scania, Volvo), Euro class (m = 0, ….5)

Hv = heating value of fuel expressed in [GJ/L]

EF= emission factor expressed in [kgCO2 /GJ] or [kgCO2 /L]

Page 98: Developing transport performance measures for Construction

90 | P a g e

5.1.5 Objective: To ensure security

5.1.5.1 Quality of hazardous material packaging

Bodenheimer (2014) suggests that “material packaging quality” can be

calculated as;

5.1.5.2 Risk of on road material theft

Polzin (2002) suggest that “risk of material theft” can be calculated as

follows;

5.1.6 Objective: To ensure safety

5.1.6.1 No. of transport incidents

The “number of transport incidents” can be calculated by following formula

according to (Botha, 2005);

5.1.6.2 Vehicle insurance

Coverfox (2019) suggests that the major components in calculating “vehicle

insurance” are insured declared value (IDV), cubic capacity, manufacturing

year, geographical location and no claim bonus (NCB).

Cover fox (2019) highlights that insured declared value (IDV) decreases as the

age of the vehicle increases and as a result insurance premium decreases as the

vehicle gets older. According to Coverfox (2019) “insured declared value” of

vehicle is calculated as;

The formula for calculating “vehicle insurance” is (Coverfox, 2019);

Quality of hazardous material packaging = No. of client´s complaints

Risk of on road material theft= Probability of incident attempt x

vulnerability x damage

No. of transport incidents = Rate of fatalities per vehicle x kilometers

travelled

Page 99: Developing transport performance measures for Construction

91 | P a g e

5.2 Frame of reference The frame of reference for this research question will remain the same as used

for research question 1 because there is no new term introduced in here. This

will only reflect the calculations of already identified transport related

performance measures. The interview guide for this is attached in Appendix 3.

5.3 Empirical findings from both Case 1 and Case 2

According to Business unit manager at Case 1 (14.1.2019) and Logistics

consultant at Case 2 (14.1.2019), there is no proper record of data at their end.

This can be due to the fact that multiple stakeholders are involved in the

construction project and as construction industry is fragmented in nature, so

the sharing of data is not taking place. Logistics consultant suggests

(14.1.2019) that this thesis is their first step towards data collection. Founder

of case company 1 (14.1.2019) also share same view as logistics consultant at

case 2. Upon asking questions that how do you measure performance measures

such as total distance travelled, unplanned deliveries, no. of shipments per day,

estimations regarding material demands vehicle weight utilization, both

respondents explicitly said that they do not measure these performance

measurements. The excerpts of the questions and respondents answer are

attached in Appendix 5.

Regarding turnaround around time, business unit manager (4.4.2019) suggests

that they measure truck turnaround time only with the help of data regarding

loading and unloading time. He further suggests that truck turnaround time

depends upon the time of the day because no. of queues vary in whole day.

Regarding vehicle capacity utilization business unit manager (4.4.2019)

suggests that they do not measure it exactly, but they calculate it in the form

of fill rate, and in loading meters. In addition to this, he highlighted that as

Vehicle insurance premium = Own damage premium- (depreciation + no

claim bonus) + Liability premium

Where,

Own damage premium is measured by insured declared value (IDV) which

is calculated as;

Insured declared value = Age of the vehicle + ex-show room price

Page 100: Developing transport performance measures for Construction

92 | P a g e

they do not get any data from suppliers, so it becomes difficult for them to

foresee the amount of material coming and also amount of trucks outgoing.

5.4 Analysis

The purpose of this research question is to find what data is needed to measure

the identified transport performance measures. From empirical findings this

has become clear that both cases are not maintaining sufficient data to

calculate these performance measures. On the basis of theory, it can be said

that following data is needed;

Reduce Total Distance Driven

• Data Required:

1. The location of touchpoints

2. List of availability of direct routes between various

touchpoints.

• Description: With only the accessibility of the aforementioned data, it

could be easy to calculate the shortest route that should be opted by the

vehicle so that it completes its journey in the shortest possible time via

the classical traveling salesman problem (Lawler, 1985). Note that

other constraints such as geography of the road (uphill/downhill),

speed limits, etc. are not considered in this scenario. Moreover, it is

assumed that the vehicle travels at a constant speed while visiting all

these touch points. Furthermore, it is also presumed that there is no pre-

determined sequence that the truck has to follow for unloading the

materials.

Minimize Vehicle Travel Time

• Data Required

1. The location of touchpoints.

2. List of availability of direct routes between various touch

points.

3. The unloading schedule of various unloading sites.

• Description: As it can be observed, the first two data required to

minimize the travel time is similar to that of the previous performance

measures, i.e. Reduce total distance driven. This is because the time

taken to complete a journey by a vehicle is directly proportional to the

distance traveled. According to 𝑠 = 𝑣 ∗ 𝑡, where s signifies the

distance traveled and v is the velocity of the vehicle. Thus, a shorter

distance will automatically imply that the travel time is reduced.

Page 101: Developing transport performance measures for Construction

93 | P a g e

Additionally, the vehicle travel time can further be reduced if the

unloading schedule of various unloading sites are known, as in this

case, the vehicles can easily reduce the waiting time in these unloading

sites. Note that, in the previous performance measure, the shortest route

is calculated by disregarding the unloading schedule, however, in this

case, this schedule can be considered to further minimize the time.

Thus, a trade-off has to be established where the shortest route is

calculated by the aforementioned traveling salesman problem, and

then comparing it with the respective unloading schedule, and finally

a manual analysis can be done to find out the concluding shortest route.

Reduction in unplanned deliveries

• Data required:

1. List of all the previous unplanned deliveries.

• Description: To reduce the number of unplanned deliveries, a list of

all the previous such incidents is required. Hereupon, these incidents

can be individually analyzed as to what was the primary ground that

led to this unplanned delivery. Following which appropriate actions

can be taken so that these deliveries are minimized in the future.

Optimize the number of shipments arrived at gate per day

• Data required

1. Material required for consumption at a construction site

2. Materials that are going to be delivered by the supplier

3. The time of delivery

• Description: It is important for the construction sites to gather the

information beforehand about the amount of material required between

two consecutive shipment deliveries. This way, the aforesaid details

can be shared with the suppliers so that all the required materials are

timely received. This will also prevent any unplanned deliveries that

will result in an increased number of shipments that arrive per day.

Furthermore, if the construction sites are aware of the list and amount

of materials that are going to be delivered by the supplier, they can plan

their construction activities in such a way that all the materials are

consumed appropriately. However, at the moment the construction

sites are largely unaware of the amount of materials that are going to

be provided by the supplier in their trip (Business unit executive,

14.1.2019). Additionally, the awareness of delivery time will also help

Page 102: Developing transport performance measures for Construction

94 | P a g e

reduce the number of shipments, as tasks such as unloading the

shipment can be organized accordingly.

Reduce truck turnaround time

• Data required

1. The breakdown of time utilized in each activity that constitutes

one instance of loading or unloading.

2. Ease of access to the construction site by the vehicle

3. Utilization rate of loading and unloading equipment

• Description: An instance of loading or unloading activity can

comprise of many sub-activities, such as sorting, packaging, lifting,

filling, etc. These sub-activities can be individually assessed to find out

a particular quantum of activity that may be responsible for delaying

the complete process of loading or unloading. The sub-activities can

then be further analyzed and improved to decrease the total turnaround

times. Moreover, it is important that the vehicle takes minimum

amount of time to enter the construction site. Proper arrangements

should be done by the construction sites this can be minimized.

Similarly, utilization rate of loading and unloading equipment would

reveal how effectively are the set of equipment utilized. This

information can be used to reduce the total utilization time, thus also

plummeting the overall truck turnaround time.

Reduce number of damages

• Data required

1. The breakdown of each activity that constitutes one instance of

loading or unloading.

2. The packaging process

• Description: As discussed with the Business Unit Manager

(14.01.2019), it was found out that the most number of damages occur

while loading and unloading of shipments. Thus, a detailed analysis is

required about each activity that takes place while loading and

unloading so that the damages can be reduced.

Minimize vehicle maintenance cost

• Data required

1. The factors that lead to vehicle damage such as:

▪ Oil and filter exhaustion

Page 103: Developing transport performance measures for Construction

95 | P a g e

▪ Tire damage

▪ Brake pad and fluid damage

▪ Coolant exhaustion

▪ Untidiness of vehicles

▪ General wear and tear

▪ Other miscellaneous damages

2. The location of touchpoints

3. List of availability of direct routes between various

touchpoints.

• Description: The factors mentioned in the first point above are the

primary reasons that lead to the damage of vehicles, which in turn

increases the vehicle maintenance cost. Analyzing these factors so that

the vehicle damages can be reduced will eventually decrease the cost

of vehicle maintenance. Moreover, it can be observed that points 2 and

3 are similar to the ones required to reduce the total distance traveled,

as minimizing the total distance traveled will, in due course lead to the

reduction of maintenance cost, since any type of damage in the vehicle

is directly proportional to the distance traveled by the vehicle. Thus,

lesser the distance traveled, lesser is the vehicle damage, resulting to a

reduced vehicle maintenance cost.

Maximize vehicle utilization capacity

• Data required

1. Volume of the containers of the vehicle

2. Type of material

• Description: As it is known that the weight of any material is

equivalent to the density of the material multiplied by its volume, the

type of material will tell its density, and thus, the maximum amount of

material by weight that could be loaded in the truck could be calculated

by the above formula. Let´s consider that n different types materials

are being transported in a truck. Thus, the total volume of the materials

transported can be calculated as:

𝑣𝑡𝑜𝑡𝑎𝑙 = ∑ (ρ

𝑖

𝑚𝑖)

𝑛

𝑖=1

Where:

• ρ𝑖 signifies the density of ith material, and

Page 104: Developing transport performance measures for Construction

96 | P a g e

• mi signifies the mass of ith material

Thus, above formula will effectively formulate the maximum amount

of materials that can be loaded into a truck before actually loading the

materials, as vtotal should always be less than or equal to the total

volume of the truck. Thus, a systematic plan can be developed to load

the materials.

Optimize number of vehicle movements

• Data required

1. Data required to reduce total number of distance drive.

2. Data required to reduce the time traveled.

3. Data required to optimize the number of shipments arrived per

day.

4. Data required to reduce truck turnaround time.

5. Data required to reduce number of damages.

6. Data required to maximize the vehicle utilization capacity.

• Description: To optimize the number of vehicle movements, it is

imperative that the vehicle travels the least, completes its journey in

the minimum possible time, the number of shipments arrived per day

are optimized, the truck turnaround time is reduced, there are less

damages in the vehicle, and the vehicle is utilized to its maximum

capacity. Thus, all the data to achieve the above performance measures

are needed to accomplish the vehicle movements optimization. In other

words, achieving the above performance measure will automatically

optimize the number of vehicle movements.

Reduce road damage and CO2 emission

• Data required

1. Data required to optimize the vehicle utilization capacity

2. Data required to optimize the vehicle movements

3. Data required regarding fuel efficiency

• Description: In order to reduce road damage and CO2 emission

there is a need to optimize vehicle utilization capacity and vehicle

movements because in this way number of trips and shipments will

be planned exactly according to the need and therefore this will

lead to effective utilization of fuel. There is need to ensure that

efficient and effective utilization of vehicle takes place.

Page 105: Developing transport performance measures for Construction

97 | P a g e

Good quality packaging of hazardous material

• Data required

1. What type of material is being transported

2. How long the material will remain in transit

3. What harm it could generate if got mishandled

• Description

Burdick (2012) define “hazardous material” as substance or material

capable of posing an unreasonable risk to health, safety, environment

and property when transported in commerce. So, it is important to take

care of material packaging while transportation in order to avoid any

security threat.

Reduce on road material theft

• Data required

1. Real time vehicle location

2. What material the vehicle is carrying

• Description

It is important to track vehicles in order to ensure on road material

safety. By knowing what material is being transported extra care

should be taken and if needed security should also be provided.

Reduce number of transport incidents

• Data required

1. Knowledge of incidents that has taken place in the past

2. Based on this any future event can be predicted

• Description

In order to ensure safety, it is important to remain vigilant and

implement safety measures.

Ensure vehicle insurance

• Data required

1. Knowledge regarding premium, age of vehicle, depreciation,

insured declared value, liability premium etc.

• Description

In order to avoid any vehicle loss, it is good to ensure vehicle insurance

Page 106: Developing transport performance measures for Construction

98 | P a g e

6 Framework for RQ3

The purpose of research question 3 is to identify what data is empirically

available from construction logistic solution. No theoretical evidence is being

employed in this research question.

6.1 Empirical data from Case 1 Terminal The data from Case 1 Terminal has been received in excel file for the period

of six months ranging from November 2018 to March 2019. The data was

provided in Swedish language which was later translated into English. A

snapshot of the sample data in its original form is attached in Appendix 4

whereas the snapshot English is shown below in Table 27. Here only 22 rows

are shown but in actual there were 11, 080 rows in the data with various details.

The headers in this data are briefly explained here. “Order number” reflects

the order that is created in Case 1 systems and is handed to the customer to

order activities on and also to be used later for billing purposes. “Company

code” is a code for companies such as Skanska which then have several orders.

“Activity code” is a code for an activity such as activity T132 represents

activity in the warehouse when forklift is used to move material. Likewise,

T105 is transport with a truck. “Activity detail” is the description or summary

of the activity code. “Date” represents the date of activities. “Duration” is the

time it took to perform the activity. The duration is in hours. For example, it

took Case 1 0.25 hours (15 minutes) to label the material to Skanska.

Page 107: Developing transport performance measures for Construction

99 | P a g e

6.1.1 Analysis

As it can be seen from above snapshot, limited parameters have been provided

in this data. After extensively investigating the data, it has been discovered

that a lot of inferences can be made. However, the analysis was limited to

finding a certain amount of essential deductions, that are:

Finding out

1. The list of orders whose constituent activities holistically performed

relatively faster than the global average. (Efficient Orders)

2. The list of orders whose constituent activities holistically performed

relatively slower than the global average. (Inefficient Orders)

3. The list of companies towards which the activities done by the terminal

were quick. (Fast Companies)

4. The list of companies towards which the activities done by the terminal

were slow. (Slow Companies)

OrderNumber CompanyCode ActivityCode ActivityDetails Date Duration

B1501 2727 T131 Fråga 11/21/2018 0.17

B1501 2727 T131 Order 12/5/2018 0.33

B1501 2727 T132 Plock 12/5/2018 1

B1501 2727 T132 avfalls handtering lass 1 12/5/2018 0.5

B1501 2727 T132 avfallshandtering lass 2 12/5/2018 0.9

B1501 2727 T132 lastning avfall 12/6/2018 0.25

B1504 2791 T105 transport inkl chaufför 11/9/2018 3

B1504 2791 T105 transport inkl chaufför 11/13/2018 2

B1504 2791 T105 transport inkl chaufför 11/16/2018 3

B1504 2791 T105 transport inkl chaufför 12/18/2018 3

B1504 2791 T105 transport inkl chaufför 12/19/2018 2.5

B1504 2791 T105 transport inkl chaufför 12/20/2018 2

B1504 2791 T105 transport inkl chaufför 12/20/2018 3

B1504 2791 T105 transport inkl chaufför 1/17/2019 3

B1504 2791 T105 transport inkl chaufför 1/21/2019 2.5

B1504 2791 T105 transport inkl chaufför 2/13/2019 2

B1504 2791 T132 lastning div staket 2/13/2019 0.8

B1504 2791 T132 lagerarbete inkl truck 2/27/2019 0.5

B1504 2791 T105 transport inkl chaufför 2/27/2019 2

B1504 2791 T132 lastning 2/27/2019 0.5

B1725 2450 T131 inleverans 11/6/2018 0.17

Table 27: Snapshot of Case 1 (Terminal data translated in English)

Page 108: Developing transport performance measures for Construction

100 | P a g e

5. Number of deliveries done by the terminal per company.

6. The delivery freequency for a company by the terminal.

All the analysis has been done by using MATLAB R2019a and Excel 2010.

Comprehensive discussion regarding the analysis is described in the following

sections.

6.1.1.1 Efficient and inefficient orders

As mentioned above, since the duration was provided in hours with the data

values smaller than 10 or in fractions for the most part, it was decided to

convert them to minutes by multiplying the column with 60 for readability.

Thereafter by splitting the dataset using the column ActivityDetails, the

average duration for each individual activity was calculated. Thus, the average

duration for a particular activity will be the same over the complete dataset.

This duration was added to the table by appending a new column with the

name AverageTime (Table 28). It can be observed that the average time for the

activity plock remains constant throughout the table. Subsequently, the actual

duration of a particular activity was compared with the global average for that

activity, and the time-difference was then noted down in a separate column

named Efficiency. A positive value indicates that the activity performed faster

than the global average. Likewise, a negative value designates a slower

process. The numeric value tells the amount of time the activity is faster or

slower than the average.

Page 109: Developing transport performance measures for Construction

101 | P a g e

Since an OrderNumber consists of multiple ActivityDetails, the Efficiency of

one OrderNumber was calculated by adding the Efficiency of all the activities

in an order. Finally, if the resultant Efficiency for an order was a positive

number, it was inferred that that particular order performed faster than the

global average (efficient order). Similarly, a negative number deduced a

slower performance (inefficient order).

Although efficient and inefficient orders has been derived, it should be noted

that the orders can still not be compared with each other quantitatively as the

orders do not contain equal number of activities. Thus, an order with 10

activities, each a minute faster than the average will be equal to an order with

just an activity, but 10 minutes faster than the average. Thus, for comparing

different orders, the numeric value was further divided by the total number of

activities in to find efficiency of an order per activity. A snapshot of this table

can be seen at Table 29. It can be inferred intuitively from the table that

OrderNumber CompanyCode ActivityCode ActivityDetails Date Duration AverageTime Efficiency

B1501 2727 T132 plock 12/5/2018 60 27.6206 -32.3794

B1516 2009 T132 plock 12/3/2018 30 27.6206 -2.3794

B1519 2727 T132 plock 11/6/2018 15 27.6206 12.6206

B1519 2727 T132 plock 11/8/2018 30 27.6206 -2.3794

B1519 2727 T132 plock 11/8/2018 30 27.6206 -2.3794

B1519 2727 T132 plock 11/13/2018 15 27.6206 12.6206

B1519 2727 T132 plock 12/3/2018 60 27.6206 -32.3794

B1519 2727 T132 plock 12/4/2018 60 27.6206 -32.3794

B1519 2727 T132 plock 12/6/2018 30 27.6206 -2.3794

B1519 2727 T132 plock 12/12/2018 15 27.6206 12.6206

B1533 2009 T132 plock 12/10/2018 10.2 27.6206 17.4206

B1533 2009 T132 plock 2/15/2019 15 27.6206 12.6206

B1533 2009 T132 plock 3/8/2019 15 27.6206 12.6206

B1533 2009 T132 plock 3/21/2019 10.2 27.6206 17.4206

B1552 2727 T132 plock 11/20/2018 30 27.6206 -2.3794

B1552 2727 T132 plock 2/4/2019 30 27.6206 -2.3794

B1552 2727 T132 plock 2/7/2019 150 27.6206 -122.3794

B1552 2727 T132 plock 2/11/2019 30 27.6206 -2.3794

B1585 2727 T132 plock 11/28/2018 15 27.6206 12.6206

B1585 2727 T132 plock 12/17/2018 30 27.6206 -2.3794

B1585 2727 T132 plock 1/21/2019 30 27.6206 -2.3794

Table 28: Processed table for Efficient/Inefficient Activities

Page 110: Developing transport performance measures for Construction

102 | P a g e

efficiency has a high variance whereas efficiency per activity has a low

variance, and thus, it can be compared.

Order Number Efficiency Efficiency Per Activity

'B1599' 142.2453 35.561325

'B2242' 141.9013 35.475325

'B2164' 194.3151 32.38585

'B2226' 284.8346 31.64828889

'B1977' 187.9621 31.32701667

'B1928' 149.2803 29.85606

A similar structure can be seen for the inefficient orders (Table 30).

Order Number Inefficiency Inefficiency Per Activity

'B2301' -74.048 -10.57828571

'B2291' -462.9924 -10.06505217

'B2318' -19.6325 -9.81625

'B2279' -19.092 -9.546

'B1666' -181.0507 -8.621461905

'B2360' -1365.4038 -8.127403571

'B2223' -90.1356 -7.5113

Finally, all the efficient and inefficient orders have been graphically described

using a bar graph respectively in Figure 24 and Figure 23.

Implication:

The implication of finding efficient and inefficient order is this that the most

efficient order will be compared with the most inefficient order and then it can

be observed that why same activity such as plock is taking place quickly in

efficient order whereas the same activity i.e. plock is taking so much time.

From this, the process of efficient activity can be studied and in this way, short

coming of slow activities can be found out which can be improved further.

6.1.1.2 Slow and fast companies

Continuing the work from Table 28, the entire dataset was first separated by

the company. Furthermore, by the column ActivityDetails, it was realized that

the total unique activities in the complete dataset are 1032. However, not all

Table 29: Efficient Orders

Table 30: Inefficient Orders

Page 111: Developing transport performance measures for Construction

103 | P a g e

the activities are performed by the terminal for all the companies. Furthermore,

it was also observed that the exact same activity takes different to complete in

different instances. Thus, it was decided to list down for all the 1032 unique

activities, the company code for which the terminal performs that activity the

fastest and the slowest.

An excerpt of the final table containing 1032 rows for each unique activity can

be seen in in the Table 31. The first column names the activity, followed by

the second column that lists the name of the company for which the terminal

performed the activity with the longest duration, whereas the third column

enumerates the companies that performed the activity in the quickest possible

time.

Activity performed Slow Quick

3 tel. samtal. ingen info om vart godset ska. 2009 2450

4 samtal med frågan om leveransplats.2 till kunden och 2 till servisti

2822 2009

4 tel. samtal. ingen information om vart godset ska. 2009 2450

admin/order 2009 2450

armeringsnät lastning 2450 2009

Finally, to quantitatively represent the data, the number of time a company

appears in the Slow column as well as the Quick column was calculated. For

instance, in the sample Table 31, a total of 3 activities were performed the

slowest by the terminal for the company 2009, whereas 3 activities were

performed the quickest for the company 2450. The top 3 companies for which

the activities were performed the fastest are listed below.

Company Activity Count

2450 739

2009 266

2545 18

Similarly, the top 3 companies for which the activities were performed the

slowest are listed below.

Company Activity Count

2009 729

2450 68

2547 4

Table 31: Slow and Fast Companies

Page 112: Developing transport performance measures for Construction

104 | P a g e

This data has been pictorially represented in the form of pie-chart

Implication:

The implication of this finding is that why one task being performed by one

company is more effective whereas the same task performed by other company

is ineffective so by digging deep into this the task that is performing slow can

be improved.

Figure 21: Fast Companies

Figure 22: Slow Companies

Page 113: Developing transport performance measures for Construction

105 | P a g e

Figure 24: Most efficient orders Figure 23: Most inefficient orders

Page 114: Developing transport performance measures for Construction

106 | P a g e

6.1.1.3 Number of Deliveries and Frequency

In this section, the total number of deliveries performed by the terminal for a

company was calculated. This was done by analysing the ActivityDetails

column. The Swedish word used in the table for delivering in the goods is

inleverans. Thus, all the ActivityDetails that had the word inleverans were

considered to be a delivery. Thereupon, the number of deliveries per company

was calculated, following which an attempt was made to calculate the time

duration between two consecutive deliveries. Note that since the delivery time

is mentioned in Date, and not DateTime, the companies that had all their

deliveries in a single day were ignored while calculating the average duration

between two consecutive deliveries. Furthermore, those companies were

ignored as well, that had no deliveries, or just one delivery, as to calculate the

time between two deliveries in our case needs at least two deliveries in two

distinct dates. Thus for each company, a data similar to the one in Table 32 is

calculated, where total number of rows represent total number of deliveries,

and the difference between the time of a delivery and the time of immediately

next delivery will denote the time difference between two consecutive

deliveries.

Order Number

Company Code

Activity Code

Activity Details

Date Difference

'B2158' 2009 'T131' 'inleverans' '23-Nov-2018 00:00:00' 4

'B2158' 2009 'T131' 'inleverans' '23-Nov-2018 00:00:00' 0

'B1533' 2009 'T131' 'inleverans' '26-Nov-2018 00:00:00' 3

'B1533' 2009 'T132' 'inleverans' '26-Nov-2018 00:00:00' 0

'B1533' 2009 'T131' 'inleverans' '04-Dec-2018 00:00:00' 8

As it can be observed, the last row in the above table has a time difference of

8, as the time of delivery is 4th December, which is 8 days after 26th November.

Thenceforth, an aggregate table similar to Table 33 is created containing the

Company Name, the number of deliveries and average time between two

consecutive delivery for a company.

Company Name Delivery Count Time Between Deliveries

2009 71 1.871429

2450 359 0.405028

Table 32: Time difference between deliveries

Page 115: Developing transport performance measures for Construction

107 | P a g e

2591 34 3.787879

2709 25 4.291667

2727 226 0.657778

2811 26 4

Finally, the complete data, part of which is represented in Table 33 was

normalized between 0 and 1 separately for number of deliveries and time

between two consecutive deliveries, so that they can be pictorially analyzed.

Subsequently, these were represented in the form of a bar graph that can be

seen in the Figure 25.

Implication:

It can be observed that the companies that have high amount of deliveries have

very less time between two consecutive deliveries, whereas this time

difference is high in case of companies that have less deliveries.

Thus, the number of deliveries is roughly inversely proportional to the average

time between two consecutive deliveries.

Table 33: Delivery frequency

0

0.2

0.4

0.6

0.8

1

24

50

27

27

30

52

28

17

20

09

25

91

30

49

28

22

30

59

28

11

27

09

29

77

28

29

30

14

29

85

29

97

30

26

28

12

30

48

28

87

30

42

Number of Deliveries and Time Between Deliveries for Companies

Deliveries Time Between Deliveries

Figure 25: Number of Deliveries and Time between Deliveries

Page 116: Developing transport performance measures for Construction

108 | P a g e

6.2 Empirical data from Case 2 Checkpoint

Case 2 Checkpoint has given access to their Lognet for empirical data which

is shown below in the Figure 26;

The data entered in Lognet is on weekly basis and the data from this portal

cannot be exported into Excel spreasheet so only one week data was manually

entered in excel to do the analysis which is shown as follows in Figure 27;

Figure 26: Lognet data sheet

Page 117: Developing transport performance measures for Construction

109 | P a g e

Figure 27: Case-2 Empirical Data

Page 118: Developing transport performance measures for Construction

110 | P a g e

As it was not a large amount of data, so the findings are not that much

conclusive, however, many points of interests have been identified.

6.2.1 Analysis

In order to analyze the data, it was first sorted out by company, by project and

by unloading site. Mean and standard deviation is calculated for all. This can

be shown as follows;

6.2.1.1 By company

CompanyName MeanDuration StandardDeviation

Assemblin EL 1.5 0

Assemblin Vent 0.5 0

BM Byggställningar 1 0

Cramo 0.375 0.176776695

Dahl 2 0

ED-Bygg 6 0

STB Ställningsbyggarna Bestorp AB 0.5 0

Schenker 2 0

Strängbetong AB 1.178571429 0.668153105

Torpheimer Tubes 0.25 0

Unspecified Company 9.333333333 4.082482905

YIT 1 0

Åhlin & Ekeroth 5.388888889 3.887301263

In this snapshot, it can be seen that the standard deviation in the time duration

for companies (i.e. Assemblin, Dahl, Schenker) having more than one

entry/observation is zero implying that the total time taken to complete one

activity by that particular company never changes. This can happen because

of two reasons i.e. either they are too perfect or in Lognet activity time has

been entered upon estimation rather than actual time. According to Logistics

Consultant (15.4.2019) the time estimations has been made for mass transports

which keep on coming continuously.

There are two companies (Cramo and Stränbetong AB) whose standard

deviation related to duration to complete activity is in considerable range that

<1 hour (less than 1 hour). In addition to this, there are two other companies

Table 34: Case-2 Sort By Company

Page 119: Developing transport performance measures for Construction

111 | P a g e

(Unspecified and Åhlin & Ekeroth) with a very high standard deviation for the

time duration per activity which reflects that these companies perform

different nature of work which require different time to get completed. If more

data is available then further insights can be extracted. There is also a need to

know that what is the work that happen in one hour and what is the work that

happen in four hours because in Lognet the activity details/summaries are not

that clear.

Graphical representation:

It can be seen from this graph (Figure 28) that many companies have zero

standard deviation which means there is no variation in the duration of their

activities. But it has also been found that some companies have zero deviation

because they only have only one or two entry. For example, Assemblin EL.

But then there are companies such as Dahl which has more than one entry but

even then its standard deviation is zero. According to Logistics consultant

(15.4.2019) the reason for this is that these companies have standard delivery

time i.e. they have an agreement that deliveries should come at the same time

always. So, it shows there is no variation because what is happening today is

mirror image of tomorrow so no inference can be drawn from this.

As the total number of observations recorded for this week are only 49 and the

total no. of companies are 13, 6 companies had only one entry. Thus, not much

could be inferred there. In order to analyze the data and infer anything out of

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

StandardDeviation

Figure 28: Standard Deviation Graph for Case-2

Page 120: Developing transport performance measures for Construction

112 | P a g e

it, there must be some variance in the data. However, it was observed that all

the entries within a company are absolutely identical, barring a few. For

example, for the company Åhlin & Ekeroth for the project Dynamic, the truck

always arrives at 06:30 and departs at 4 pm throughout the week, hence, there

is a lack of variation. The reason for this is that this truck comes under mass

transport, i.e. they keep on driving throughout the day. As it can be seen, the

standard deviation for most of the companies is zero or very less.

This can be seen here;

6.2.1.2 By project

Project Mean Duration Standard Deviation

Calm 10.16666667 2.041241452

Checkpoint Depos

1.840909091 0.527644853

Dynamics 9.5 0

Workshop 1.758333333 2.201570103

When one-week data has been filtered "by project" then it is found that there

are only 4 projects. 3 projects (Calm, Checkpoint, Dynamics) have their

respective and exclusive unloading sites (Calm 1, Chp depo, Dune 1)

respectively. The 4th project i.e. Workshop has a total of 4 unloading sites

which implies that Project workshop is the bigger project as compared to other

projects.

As the 3 smaller projects (Calm, Checkpoint depos, Dynamics) take exactly

same time in completing their work in every instance (all in 11 hrs, 2 hrs, 9.5

hrs) except just two entries. Because of those two entries there is slight

difference in the standard deviation value of these projects. But overall the

same time taken by all activities show signs of approximation in the data

entry.

The bigger project i.e. Workshop can be further investigated once I have more

data. It is also needed to know more details that why some tasks take 1 hour

while others take 9.9 hours to get completed.

Page 121: Developing transport performance measures for Construction

113 | P a g e

6.2.1.3 By unloading site

Unloading site Mean Duration Standard Deviation

Calm 1 10.16666667 2.041241452

Chp depot 1.840909091 0.527644853

Dune 1 9.5 0

Pit 6.75 3.889087297

V1 1.40625 1.209615494

V2 2 2.853569194

V3 1 0

Observing the data set in perspective of unloading sites, it has been realized

that it is also quite similar to what has been observed in "data filtered by

project" as each project has their own exclusive unloading sites. Therefore,

similar conclusions can be inferred here.

Comments about Case 2 data:

It seems that quite a lot of approximation has been done while entering data

into the "Lognet" because a lot of activities over the span of one week start at

the same time and end at same time and also takes exactly the same time. As

there is no variation in the data thus little to no analysis can be done in those

entries.

As there are no unique IDs in this data so it become difficult to find chain of

events (dependencies that which activity occurred first and which after) for

one whole process/order. All events in Case 2 data appeared to be independent

as this point in time.

7 Framework for RQ4

The purpose of research question 4 is to find a gap between required and

available data to measure identified transport related performance measures in

research question 1? This research question does not require any theory and

empiry, so analysis is the main response to this research question.

Page 122: Developing transport performance measures for Construction

114 | P a g e

7.1 Analysis As it could be seen from research question 2 various data is required to

accomplish the performance measures proposed, however these data are

currently unavailable for the analysis. Furthermore, efficient orders, inefficient

orders, fast companies, slow companies were calculated above however to find

out how can these inefficient orders and slow companies be improved,

breakdown of each activity is required so that the sub activities from inefficient

orders and slow companies could be compared with efficient orders and fast

companies respectively. In this the factors leading to inefficiency could be

found out, analysed and thereafter rectified for the overall improvement.

The gap between required and available data can be found out by making

comparison between what data is needed and what data is available from Case

1 and Case 2. This can be done with the help of Table 35 below;

Data required (as

found in RQ2)

Data available from

Case 1

Data available from

Case 2

Location of touch

points

Duration of different

activities such as plock,

inleverans, transport

inkl chaufför, lossning

av slingbil mainly

Duration of activities

different activities such

as truck with gravel

transport, daily

delivery, emptying

container mainly

List of availability of

direct routes between

various touchpoints

Order number Delivery ID

Unloading schedule of

various unloading

sites

Company code Company name

List of previous un-

planned activities

Activity code and

activity details

Arrival and departure

Material required for

consumption at a

construction site

Date Duration

Time of delivery Amount/quantity of

material in tonnage

Summary of activities

Information

regarding what

material is going to be

delivered by a

supplier

Customer marking Date

Page 123: Developing transport performance measures for Construction

115 | P a g e

Breakdown of loading

and unloading

activities in terms of

time

Internal marking Projects

Utilization rate of

loading and unloading

equipment

Signature Unloading site

No. of damages - Supplier

Details regarding

product packaging

- No. of deliveries

Vehicle maintenance

cost

- Vehicle type

Volume of the

containers of the

vehicle

- -

How long the material

will remain in transit

- -

Real time vehicle

location

- -

Knowledge of past

incidents

- -

8 Overall analysis

This chapter will discuss the overall analysis of all four research questions

mentioned in this study.

The purpose of the study is to identify transport related performance measures

in order to evaluate construction logistic solution and then to see what data is

needed to calculate these identified transport performance measures and what

data is empirically available. It has been found that very few researchers have

discussed about transport flows within construction industry. This is due to the

fact that construction logistic solution is not a widely accepted area within

construction logistics.

With the help of theory, semi structured interviews and focus group transport

related performance measures have been identified under respective strategic

objectives. As Marr (2015) suggest that it is important to link performance

measures with the right strategic objectives. For this purpose, six strategic

objectives have been identified after theoretical and empirical research and

Table 35: Comparison between required and available data

Page 124: Developing transport performance measures for Construction

116 | P a g e

these are to plan transport effectively, to minimize transportation time, to

reduce transportation cost, to achieving environmental sustainability, to ensure

security and safety. Then performance measures have been identified under

these strategic objectives. According to business unit manager (14.1.2019)

there should be few but comprehensive performance measures thus making it

easy to track them and bring improvement. Considering this, the identified

performance measures were later consolidated and clubbed together in order

to find few but comprehensive performance measures which can be seen

below;

Identified performance measures

from RQ1

Identified performance measures

from RQ1

Objective: Effective transport

planning

-Total distance driven

-Total travel time

-No. of unplanned deliveries

-No. of shipments arrives at gate per

day

Objective: To achieve

environmental sustainability

-Road damage through vibrations

-CO2 emission

Objective: Minimizing

transportation time

-Truck turnaround time

Objective: To ensure security

-Packaging of hazardous material

-On road material theft

Objective: Cost minimization

-No. of in-transit damages

-Vehicle maintenance costs

-Vehicle utilization (time, capacity)

-No. of vehicle movements

Objective: To ensure safety

-No. of transport incidents

-Vehicle insurance

In addition to this, identified performance measures were also classified with

respect to terminal, checkpoint and their respective construction sites (Figure

17 and 18). After finding these performance measures the next objective was

to find ways of calculating them. In order to do that theory remained major

contributor as according to both case representatives, the case companies are

not measuring these performance measures and the data that they have is not

sufficient to calculate these performance measures. Despite this fact, an effort

has been made to develop some calculations and formulas to calculate

identified performance measures. After devising the formulas empirical data

was collected and analyzed. It has been found out that the empirical data from

both cases rely on duration of activities mainly and not providing any other

good amount of information with the help of which identified performance

measures can be calculated. The analysis such as efficient and in-efficient

Page 125: Developing transport performance measures for Construction

117 | P a g e

orders, fast and slow companies, number of deliveries done by the Case 1-

Terminal per company, the delivery frequency for a company by terminal was

done. On the other hand, analysis on Case 2-Checkpoint empirical data has

been conducted by calculating mean and standard deviation. Extensive data

analysis for Case 2-Checkpoint could not be done due to limited number of

entries i.e. one week. After empirical data analysis, a comparison among

required data, available data at Case 1 and available data at Case 2 is made

in order to identify the gap. As a result, it has been found that empirical data

mainly consists of duration of different activities which does not fulfill the

requirement of data needed to calculate or verify identified transport

performance measures.

9 Conclusion

To conclude this paper, the research questions will be answered. As there are

four research questions in this study so the conclusion will give answers to all

research questions one by one. In the end, further research area will be

discussed.

The first question for this thesis is “what performance measures can be used

for the evaluation of construction logistic solutions and their respective

construction sites with respect to transport flows?” In order to answer this

research question, the use of literature review, semi structured interview and

focused group was made and as a result transport performance measures within

the connect of construction logistics has been identified. In addition to this,

these performance measures have also been classified according to

construction logistic solution (i.e. terminal and checkpoint) and their

respective construction site. This can be found in Figure 17. In order to suggest

few but comprehensive performance measures consolidation and grouping

have been done resulting in major performance measures aiming at achieving

the strategic objectives. This can be found in Figure 18.

The second research question which is “what kind of data is needed to

measure identified transport related performance measures in research

question 1?” For answering this research question, theory has remained

helpful as compared to empirical data because according to business unit

manager at Case 1 (14.1.2019) and logistic consultant at Case 2 (14.1.2019)

insufficient data has been recorded and they are making very less use of data.

With the help of theory and personal knowledge and experience the answer to

this research question has been provided in section 5.4.

Page 126: Developing transport performance measures for Construction

118 | P a g e

The third research question of this study is “what transport data is empirically

available from construction logistic solution?” In order to answer this

question, empirical data was collected from Case 1 and Case 2. It has been

found that within both empirical datasets, mainly the duration of activities has

been provided which does not fulfill the purpose of calculating identified

performance measures in research question. The Case 1 data has been analyzed

by efficient and inefficient orders, by slow and fast companies, by number of

deliveries done by the Case 1 (per company), the delivery frequency for a

company by terminal mainly. Whereas the Case 2 data has been analyzed by

calculating average mean and standard deviation in order to see the variation

in entered data. The implication of this data analysis is that it can provide

enough insights to bring improvement in slow and underperforming processes.

The fourth question in this paper is “what is the gap between required and

available data to measure identified transport related performance measures

in research question 1? In order to answer this research question a comparison

has been made between the findings of RQ2 and RQ3. And a list of gaps has

been identified in the required and available data in Table 35.

9.1 Further study There is permanent need of further research in this area of studies because the

phenomena of construction logistics solution is not widely accepted. Besides

this, in order to verify identified transport performance measures there is need

to collect relevant data. So, a new study related to collection of relevant data

can be conducted further.

Page 127: Developing transport performance measures for Construction

119 | P a g e

10 Reference list

- Alves, T.C.L., Formoso, C.T., 2005. Guidelines for managing physical

flows in construction sites.

- Andersson, O., Nilsson, A., 2018. Planning for construction logistics.

An evaluation and development of a construction logistics plan at

Serneke. Chalmers University, Gothenburg.

- Andersson, D., Dubois, A., Eriksson, V., Hulthen, K., Holma, A., M.,

2019. The transport service traid: a key unit of analysis. Journal of

Business and Industrial Marketing.

- Anastasia., 2017. How to write a business continuity plan. Cleverism.

Available online: https://www.cleverism.com/write-business-

continuity-plan/

- Appel, V., (2016). Shorter project lead times in construction. Master

thesis. Luleå University of Technology.

- Bai, Y., Schrock, S.D., Mulinazzi, T.E., Hou, W., Liu, C., Firman, U.,

2009. Estimating highway pavement damage cost attributed to truck

traffic. The university of Kansas.

- Baird, P., 2017. The relationship between security and safety. Philips

- Balm, S., Browne, M., Leonardi, J., Quak, H., 2014. Developing an

evaluation framework for innovative urban and interurban freight

transport solutions. 8th international conference on city logistics.

Procedia-Social and Behavioral Sciences 125 (2014) 386-397

Page 128: Developing transport performance measures for Construction

120 | P a g e

- Baxter, P., Jack, S., 2008. Qualitative case study methodology: Study

design and implementation for novice researchers. The qualitative

report. Vol. 13, No. 4, pp. 544-559.

- Berden, M., 2017. Report : Analysis of construction logistics

calculation models and factors that obstruct their development.

- Beetrack., 2016. The challenges of delivery. Slideshare

- Berg, R., Hinze, J., 2005. Theft and vandalism on construction sites.

Journal of construction engineering and management

- Bishop, D., 1972. Information flow in the construction industry: a

study and the development of its recommendations. Aslib Proceedings,

Vol. 24 Issue: 2, pp. 79-95. [Accessed on 2 April 2019]

- Botha, G., 2005. Measuring road traffic safety performance.

Proceedings of the 24th Southern African Transport Conference (SATC

2005), ISBN Number: 1-920-01712-7

- Bodenheimer, G., 2014. Mitigating packaging damage in the supply

chain. Packaging digest

- Brasington, L., 2018. Are we overdue a building construction

revolution? Cleantech group.

- Brierley, L., 2017. Key metric for reliability centered fleet

maintenance. Concrete construction.

- Bröchner, J., 2005. Managing information flow in construction supply

chains. Construction innovation 5(2):71-82.

- Bryman, A., 2012. Social research methods. Fourth edition. Oxford

University Press

Page 129: Developing transport performance measures for Construction

121 | P a g e

- Burdick, M., 2012. Hazardous material in transportation. Are your

products regulated and shipped safely?

- Burke, M., 2018. The fourth industrial revolution is about to hit the

construction industry. Here`s how it can thrive. World Economic

Forum

- Cain, C.T., 2004. Performance measurement for construction

profitability. Blackwell publishing U.K.

- Cambridge dictionary (2019). Available online:

https://dictionary.cambridge.org/dictionary/english/comprehensive

- Carlgren, F., 2017. GDP-Gross Domestic Product. Ekonomifakta.

Available online: < https://www.ekonomifakta.se/en/Facts-and-

figures/Economy/Economic-growth/GDP/> [Accessed 31 March

2019]

- Civic Handbook., 2018. Smart construction logistics. Research Gate

Publishing.

- Collins English dictionary, 2019. Available at:

https://www.collinsdictionary.com/dictionary/english

- Coverfox, 2019. Car insurance calculator. Available online:

https://www.coverfox.com/car-insurance/car-insurance-premium-

calculator/

- CSCMP, 2016. Glossary terms prepared by the council of supply chain

management professionals (CSCMP).

- Darvik, L., Larsson, J., 2010. The impact of material delivery

deviations on costs and performance in construction projects. Master´s

thesis in the design and construction project management.

Page 130: Developing transport performance measures for Construction

122 | P a g e

- Deming, E.W., 1994. The new economics for industry, government,

education. Second edition, MIT, Center for advanced educational

services, Cambridge, Massachusetts.

- Dönmez, S., Zemmouri, M., 2016. Analyzing the value of vehicle

maintenance activities. Master of science thesis in the supply chain

management.

- Dubois, A., Hulthén, K., Sundquist, V., 2019. Organising logistics and

transport activities in construction.

- EECA business, 2017. Monitoring and measuring fuel use. Available

online:

https://www.eecabusiness.govt.nz/sectors/transport/monitoring-and-

measuring-fuel-use/

- Ekeskär, A., Rudberg, M., 2016. Third party logistics in construction:

the case of a large hospital project. Construction management and

economics, 2016, Vol.34, No. 3, 174-191.

- Epstein, M. J., Rejc, A., 2005. Evaluating performance in information

technology. Management accounting guideline. Management strategy

measurement.

- Eriksson, O., 2015. Method to calculate distance in LCA including the

empty return travel. Research gate.

- Fadiya, O., Georgakis, P., Chinyio, E., Nwagboso, C., 2015. Decision

making framework for selecting ICT-based construction logistics

systems. Journal of engineering, design and technology. Vol. 13, Issue.

2, pp.260-281.

- Faschingbauer, M., 2015. Contingency planning keeps freight moving.

Inbound logistics.

Page 131: Developing transport performance measures for Construction

123 | P a g e

- Fellow, R., Liu, A., 2012. Managing organizational interfaces in

engineering construction projects: addressing fragmentation and

boundary issues across multiple interfaces. Construction management

and economics, 30(8), 653-671

- Fira, 2015. The brief history and the bright future of construction.

[Video online] Available at:

<https://www.youtube.com/watch?v=P_FAwqRK7nA> [Accessed 31

March 2019]

- Florida department of transportation, 2014. Best practices in evaluating

transit performance. Final report. Freight logistics and passenger

operations, transit office.

- Forcada Matheu, N., 2005. Life cycle document management system

for construction. Ph.D. thesis, polytechnic university of Catalonia,

University of Catalonia, Catalonia, Spain 2005.

- Fredriksson, A., 2018. VREF conference, Gothenburg.

- Freight best practice, 2010. Performance management for efficient

road freight operations. Department for transport.

- Fu, J., 2017. Evaluating and improving the transport efficiency of

logistics operations. Doctoral thesis in Transport Science. KTH Royal

institute of Technology.

- Garcia-Arca, J., Prado-Prado, C., Fernandez-Gonzalez, A.J., 2018.

Integrating KPI´s for improving efficiency in road transport.

International journal of physical distribution and logistics

management, Vol. 48, Issue: 9, pp. 931-951.

- Golyani, A., Yan Hon, H., 2010. Information handling in construction

projects. Department of Civil and Environmental Engineering.

Page 132: Developing transport performance measures for Construction

124 | P a g e

Division of construction management. Chalmers University of

Technology.

- Goshu, Y.Y., Kitaw, D., 2017. Performance measurement and its

challenge: a literature review. International journal of business

performance management, Vol.18, No. 4, 2017.

- Gothenburg port authority, 2016. Construction worth 1000 billion

planned for the Gothenburg region. Port of Gothenburg.

- Harish, M., 2013. Urban transport and traffic management-for

sustainable transport development in Mysore City. International

journal of IT, Engineering and Applied Sciences research (IJIEASR),

Vol. 2, No. 3, March 2013.

- Hensel, B., 2014. Calculating turnaround time. Excel forum

- Holland, L., 2014. Site organization for construction. ESE Direct.

Available online: <https://www.esedirect.co.uk/articles/post/site-

organisation-for-construction.aspx> [Accessed on 3 April 2019]

- Hosseini, S.V.,Shirani, M., 2011. Fill rate in road freight transport.

Department of technology management and economics.

- Hove, G., Banjo, A., 2015. Performance in the construction industry-

A conceptual and Theoretical analysis. Journal of business and

management. Vol. 3, No. 2.

- Hughes, S.W., Tippett, D.D., Thomas, W.K., 2015. Measuring project

success in the construction industry. Pages 31-37.

- Jacob, D., 2017. Quality metrics: Customer complaints benchmark

data. Industrial transformation blog. Available online:

https://blog.lnsresearch.com/quality-metrics-customer-complaints-

benchmark-data

Page 133: Developing transport performance measures for Construction

125 | P a g e

- Jahangirian, M., Taylor, S.J., Young, T., Robinson, S., 2017. Key

performance indicators for successful simulation projects. Journal of

operational research society Vol. 68, Issue 7.

- Janné, M., 2018. Construction Logistics Solutions in Urban Areas.

Linköping University. Thesis, L., 1806.

- Janné, M., Fredriksson, A., 2018. Problems and solutions in urban

construction logistics. Department of science and technology. LiU-

ITN-TEK-A—18/001 –SE

- Janne, M., Fredriksson, A., 2019. Construction logistics governing

guidelines in urban development projects. Construction Innovation.

- Jayasinghe, A., Sano, K. and Nishiuchi, H., 2015. Explaining Traffic

Flow Patterns Using Centrality Measures. International Journal for

Traffic and Transport Engineering, 5(2), pp.134–149.

- Jensen, C.A., 2017. Staged competition as a driver of construction

innovation. Procedia Eng. 196, 872–879.

- Jia, Z-Z., Deschamps, J-C., Dupas, R., 2016. A negotiation protocol to

improve planning coordination in transport-driven supply chains.

Journal of manufacturing systems, Vol. 38, January 2016, Pages 13-

26.

- Jonck, A., JW., (2019). Car insurance and road safety. Available

online: https://www.arrivealive.mobi/car-insurance-and-road-safety

- Jonsson, P., 2008. Logistics and supply chain management, McGraw-

Hill, Berkshire, UK.

- Kalsaas, B.T., Bolviken, T., 2010. The flow of work in construction: a

conceptual discussion. 18th annual conference of the international

group for lean construction. Page number, 52-62.

Page 134: Developing transport performance measures for Construction

126 | P a g e

- Kaparias, I., Bell, M.G.H., 2011. Key performance indicators for

traffic management and intelligent transport systems. 7th framework

program, deliverable no. 3.5, Imperial college London.

- Kenton, W., 2019. Tender. Investopedia. Available online: <

https://www.investopedia.com/terms/t/tender.asp> [Accessed 2 April

2019]

- Key performance indicator survey, (2013). Available online :

http://fleetanswers.com/sites/default/files/KPI_Report_0.pdf

- Kulatunga, U., Amaratunga, D., Haigh, R., 2007. Performance

measurement in the construction research and development.

International journal of productivity and performance management,

56(8), 673-688.

- Landqvist, M., Rowland, A., 2014. Stakeholder requirements affecting

urban freight transportation to and from construction sites in the city.

Department of technology management and economics, Gothenburg,

Sweden.

- Latiffi, A.A., Carrillo, P., Ruikar, K., Anumba, C.J., 2014. The need

for performance measurement in construction strategy development: A

current scenario.

- Lawler, E.L., Karel, J., Kan, A.R., Shmoys, D.B., 1985. The traveling

salesman problem: a guided tour of combinatorial optimization. Vol.

3. Wiley New York

- Le, P.L., Elmughrabi, W., Dao, T.M., Chabaane, A., 2019. Decision

making in construction logistics and supply chain management:

evolution and future directions. 7th international conference on

information systems, logistics and supply chain ILS conference 2018,

July 8-11, Lyon, France.

Page 135: Developing transport performance measures for Construction

127 | P a g e

- Lee, H.L., 2002. Aligning supply chain strategies with product

uncertainties. California management review, 44(3), 105-119.

- Li, Y., Zhang, X., Ding, G., Feng, Z., 2016. Developing a quantitative

construction waste estimation model for building construction projects.

Resources, Conservation and Recycling. Science direct.

- Lingard, H., Wakefield, R., Blismas, N., 2013. “If you can not measure

it, you can not improve it”: Measuring health and safety performance

in the construction industry. 19th CIB World Building Congress:

“Construction and Society”, 5-9 May 2013 Brisbane, Australia.

Queensland University of Technology.

- Looy, A.V., Shafagatova, A., 2016. Business performance

measurement: a structured literature review of indicators, measures

and metrics.

- Lomax, T., Schrank, D., Lasley, P., Eisele, B., 2013. Developing a total

peak period travel time performance measure. An updated concept

papers. Mobility measurement in urban transportation pooled fund

study.

- Lukviarman, N., 2004. Ownership structure and firm performance: The

case of Indonesia. Curtin University of Technology, Australia.

- Lundesjö, G., 2011. Using construction consolidation centers to reduce

construction waste and carbon emissions. Guidance construction

logistics. Wrap

- Lundesjö, G., 2015. Supply chain management and logistics in

construction: Delivering tomorrow’s built environment. London

- Marr, B., 2015. Key performance indicators for dummies. John Wiley

and Sons.

Page 136: Developing transport performance measures for Construction

128 | P a g e

- Marion, G., 2019. Supply chain management-How do I measure on

time delivery?

- Malacarne, E., 2018. How to make sure fleet vehicle utilization hits

100%. Transpoco. Available online:

https://www.transpoco.com/blog/how-to-make-sure-fleet-vehicle-

utilization-hits-100

- Manaadiar, H., 2017. Documentation involved in a sea freight

shipment. Shipping and freight resource.

- Matouzko, Y., 2015. Efficient construction logistics. A case study of

an office block project. KTH architecture and the built environment.

Thesis no. 357

- Matouzko, V., Methanivesana, N., 2012. Improving construction

logistics. A case study of residential building project. KTH

Architecture and the Built Environment.

- McKinsey&Company, 2017. Reinventing Construction: A route to

higher productivity. In collaboration with Mckinsey´s Capital Projects

& Infrastructure Practice. McKinsey Global Institute (MGI).

- Merriam-webster, 2019. Definition of indent. Available online: <

https://www.merriam-webster.com/dictionary/indent> [Accessed on

2nd April 2019]

- Minges, J., 2017. Logistics Performance Measurement System for

Construction Supply Chains. A Case Study at a Large Swedish

Construction Company.

- Multanen, H., 2011. Lower inventory levels and costs due to reduction

of transportation time. To develop a framework to understand the

effects of the transportation time to inventory.

Page 137: Developing transport performance measures for Construction

129 | P a g e

- Murray, M., 2018. Reducing supply chain transportation logistics

costs. The balance small business. Available online:

https://www.thebalancesmb.com/reducing-transportation-costs-

2221049

- Napier, T., 2016. Construction waste management. Whole building

design guide. National institute of building sciences. Available online:

< http://www.wbdg.org/resources/construction-waste-management>.

[Accessed on 2nd April 2019]

- Noah, D., 2018. The export shipping documentation process: An

overview. International trade blog

- Northey, G., 2018. An introduction to early supplier involvement in

the construction industry. GRH

- Ndekugri, I. E., McCaffer, R., 2006. Management information flow in

construction companies. Construction management and economics.

Vol 6, Issue 4, pp. 273-294.

- NTMCalc, 2010. Network for transport measures. Available at:

https://www.transportmeasures.org/wp-content/uploads/2013/11/ft-

model.pdf

- NTMCalc, 2012. Guidelines for measuring and managing CO2

emission from freight transport operations.

- Odeh, I., 2019. Construction vs Manufacturing Industry basics.

Construction project management. Columbia University [online

course] Available online: <

https://www.coursera.org/lecture/construction-project-

management/construction-vs-manufacturing-industry-basics-uzToz>

[Accessed 31 March 2019]

Page 138: Developing transport performance measures for Construction

130 | P a g e

- Ogden, H.J., Turner, R.E., 2015. Customer satisfaction with delivery

scheduling. Taylor and Francis Online.

- Olsen, E., 2016. How to develop key performance indicators. A

whiteboard series by on strategy. Available online

[https://www.youtube.com/watch?v=2tuWjtc2Ifk] Accessed

28.4.2019

- Olsson, F., 2000. Supply chain management in the construction

industry. Lund university.

- O´Reilly, J., 2015. The evolution of Third-Party Logistics. Inbound

logistics. Available online: <

https://www.inboundlogistics.com/cms/article/the-evolution-of-third-

party-logistics/> [Accessed 1 April 2019]

- O´Reilly, M., Kiyimba, N., 2015. Advanced qualitative research. A

guide to using theory. Sage publications

- Otjacques, B., Post, P., Feltz, F., 2005. Management of information

flows during construction projects.

- Patel, V.K., Vyas, C.M., 2011. Construction material management on

project sites. National conference on recent trends in engineering and

technology.

- Peiffer, E., 2015. Defining the construction industry. Available at:

https://www.constructiondive.com/news/10-trends-defining-the-

construction-industry/404564/ [Accessed 22 Feb 2014]

- Pericot, N.G., 2011. Management of waste from packaging of

construction materials in building construction works. The open

construction and building technology journal. Research gate

publication.

Page 139: Developing transport performance measures for Construction

131 | P a g e

- Phelps, A. F., 2012. Managing information flow on complex projects.

A holistic approach to managing information flow in collaborative

design and construction environment.

- Polzin, S.E., 2002. Security considerations in transportation planning:

A white paper. For southeastern transportation center

- Rangelova, F., 2015. Fundamentals of Economics in Sustainable

Construction. [online] Available at:

<https://www.uacg.bg/filebank/att_8856.pdf>.

- Razak Bin Ibrahim, Roy, M.H., Ahmed, Z.U., Imtiaz, G., 2010.

Analyzing the dynamics of the global construction industry: past,

present and future, “Benchmarking: An international journal, Vol. 17,

Issue: 2, pp.232-252

- Robinson, A., 2019.9 KPIs to track for proper freight management.

Cerasis

- Rose, D. S., 2015. Why is there a slow uptake of technology in

construction? Quora, [blog] 3rd March. Available at: <

https://www.quora.com/Why-is-there-a-slow-uptake-of-technology-

in-construction> [Accessed 31 March 2019]

- Russo, F., Comi, A., 2010. A classification of city logistics measures

and connected impacts. The sixth international conference on city

logistics. Procedia social and behavioral sciences 2 (2010) 6355-6365

- Ryus, P., Danaher, A., Walker, M., Nichols, F., Carter, B., Ellis, E.,

Cherrington, L.K., Bruzzone, A., (2013). Transit capacity and quality

of service manual. Third edition.

- Sacks, R., 2016. What constitutes good production flow in

construction? Construction management and economics, 34:9, 641-

656. [Accessed on 2nd April 2019]

Page 140: Developing transport performance measures for Construction

132 | P a g e

- Sanchez-Rodrigues, V., Potter, A., Naim, M.M., 2010. Evaluating the

causes of uncertainty in logistics operations. The international journal

of logistics management, Vol.21 Issue: 1, pp.45-64.

- Sarkar, A., Das, D., Chakraborty, S., Biswas, N., 2013. A simple case

study of material requirement planning. IOSR journal of mechanical

and civil engineering, Volume 9, Issue 5, p.p. 58-64

- Saunders, M., Lewis, P., Thornhill, A., 2016. Research methods for

business students (7th Edition). Harlow: Pearson Education

- Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L., Segner, R.O.,

2015. Construction Project Management. A practical guide to field

construction management. 6th Edition. John Wiley and Sons,

Incorporated. [Accessed 30 March 2019]

- Sichwardt, A., 2011. CO2 allocation in road transportation for Alwex

Transport AB. A comparison of mathematical frameworks.

- Sikka, S., Dawood, N., Marasini, R., 2006. An integration of

construction site logistics and associated vehicle movements towards

a sustainable construction. Joint international conference on computing

and decision making in civil and building engineering.

- Sobotka, A., Czarnigowska, A., 2005. Analysis of supply system

models for planning construction project logistics. Journal of civil

engineering and management, 11 (1), 73-82.

- Sound noise limits, 2005. Sound noise limits. Options for a uniform

noise limiting scheme for EU airports. Solutions for environment,

economy and technology.

- Sonoco., 2017. What´s the real cost of damage when shipping your

product?

Page 141: Developing transport performance measures for Construction

133 | P a g e

- Stringfellow, A., 2019. How to reduce logistics costs: 19 experts reveal

ways organizations can cut their logistics transportation and carry

costs. Available online https://www.camcode.com/asset-tags/how-to-

reduce-logistics-costs/

- Sullivan, G., Barthorpe, S., Robbins, S., 2010. Managing construction

logistics. John Wiley & Sons, Incorporated

- Sundquist, V., Gaadde, LE., Hulthen, K., 2018. Reorganizing

construction logistics for improved performance. Construction

management and economics. Routledge, Taylor and Francis Group.

- Surkis, A., Read, K., 2015. Research data management. Journal of the

medical library association: JMLA, 103(3), 154-156

- Sutton, J., Austin, Z., 2015. Qualitative research: Data collection,

Analysis, and Management. The Canadian journal of hospital

pharmacy, 68(3), 226-231.

- Takim, R., Akintoye, A., Kelly, J., 2014. Performance measurement

systems in construction. School of built and natural environment,

Glasgow Caledonian University.

- Tamuli, R.P., 2016. Road safety measures. Demonstrator, Department

of Forensic Medicine and Toxicology, Tezpur Medical College and

Hospital.

- Theeranuphattana, A., Tang John, C.S., 2008. A conceptual model of

performance measurement for supply chains-alternate consideration.

Journal of manufacturing technology management, 19(1), 125-148.

- Thomas, 2017. Reorder point formula (and safety stock). Inflow.

Available online: https://www.inflowinventory.com/blog/reorder-

point-formula-safety-stock/

Page 142: Developing transport performance measures for Construction

134 | P a g e

- Tolstoy, N., Bjorklund, C., Carlson, P.O., 1998. Material flows

in the construction and heavy engineering sector.

-

- Tribelsky, E., Sacks, R., 2010. Measuring information flow in the

detailed design of construction projects. Research in Engineering

Design Vol 21, Issue 3, pp. 189-206

- Tsaxiri, P., 2018. Problems and solutions in urban construction

logistics. Linköping University.

- United Nations and UN, 2008. International Standard Industrial

Classification of All Economic Activities. United Nations Publication .

- United Nations, (2013). Glossary of statistical terms. Available at:

https://stats.oecd.org/glossary/detail.asp?ID=422

- Valenciaport Foundation., 2017. Business models for construction

logistics optimization and CCC introduction. Sustainable urban

consolidation centers for construction. Version 1.0.

- Van Der Spoel, S., Amrit, C., Van Hillegersberg, J., 2015. A

benchmark for predicting turnaround time for trucks at a container

terminal.

- Velimirovic, D., Velimirovic, M., Stankovic, R., 2011. Role and

importance of key performance indicators measurement. Serbian

journal of management 6 (1) (2011) 63-72

- Vidovszky, I., 2015. Site organization and management. Basics of

construction. BUTE-Faculty of architecture department of

construction technology and management.

- Vrijhoef, R., Koskela, L., 2000. The four roles of supply chain

management in construction. European Journal of Purchasing and

Supply Management 6 (2000) 169-178.

Page 143: Developing transport performance measures for Construction

135 | P a g e

- Yamada, T., Taniguchi, E., Noritake, M., 1999. Optimal location

planning of logistics terminals based on multi-objective programming

method. Transactions on the built environment Vol 41.

- Yan, F., Xu, J., Han, B.T., 2015. Material transportation problems in

construction projects under an uncertain environment. KSCE journal

of civil engineering.

- Yan, Q., Zhang, Q., 2015. The optimization of transportation costs in

logistics enterprises with time-window constraints. Hindawi

publishing corporation, Vol. 2015, Article ID 365367, 10 Pages.

- Yin, R.K., 2003. Case study research designs and methods. Sage

publication

- Yin, R.K., 2018. Case study research and applications: Design and

methods (6th Edition). Cosmos Corporation: Sage

- Ying, F., Tookey, J., Roberti, J., 2014. Addressing effective

construction logistics through the lens of vehicle movements.

Engineering, Construction and Architectural Management, Vol. 21,

Issue, 3, pp. 261-275

- Ying, F., Tookey, J., Seadon, J., 2018. “Measuring the invisible: A key

performance indicator for managing construction logistics

performance”, Benchmarking: An international journal, Vol. 25 Issue:

6, pp.1921-1934.

- Yu, I., Kim, K., Jung, Y., Chin, S., 2007. Comparable performance

measurement system for construction companies. Journal of

management in Engineering, 23(3), 131-139.

- Waters, H., 2019. The top 5 fleet management KPIs. Available online:

https://www.teletracnavman.co.uk/blog/the-top-5-fleet-management-

kpis

Page 144: Developing transport performance measures for Construction

136 | P a g e

- Wegelius-Lehtonen, T., 2001. Performance measurement in

construction logistics. International journal production economics 69

(2001) 107-116.

- Zetterberg, A., Minges, J., 2017. Logistics performance measurement

system for construction supply chains. A case study at a Large Swedish

Construction Company. Chalmers University of Technology

Page 145: Developing transport performance measures for Construction

137 | P a g e

11 Appendix

11.1 Semi structured interview guide for RQ1 The most important statements from semi structured interviews are mentioned

below;

General Information

- What is your position in the company?

- How long have you worked for the company?

- How long have you worked within the construction industry?

Questions related to the topic

- Do you think construction logistics will bring efficiency in the

construction industry?

- Do you agree that construction logistics solution is a new phenomenon

in the construction industry?

- Do you think it is effective to use construction logistics solutions?

- Do you think it is important to measure transport flows in construction

logistics?

- Are you using any transport related performance measures for your

company?

- Do you think transport performance measures should be align with

company objectives such as effective transport planning, transport time

reduction, transport cost minimization, to achieve environmental

sustainability, to ensure security and safety?

- What do you think should be the number of transport related

performance measures such as five, eight, twelve or more?

- Do you believe in the comprehensiveness and quality of performance

measures or it’s the quantity that matters the most?

- Do you consider early delivery as “on time delivery”?

- How do you ensure on time deliveries?

- How do you deal with late deliveries?

- Do you believe that you have enough no. of vehicles to meet daily

demand?

- What factor do you consider more in vehicle capacity i.e. weight a

truck carries or frequency of trips?

- What is the maximum vehicle utilization (in terms of kilometers) that

you have ensured so far?

- What is the maximum vehicle weight utilization that you have ensured

so far?

- Are shipping documents prepared on time?

- How often some error occurs in shipping documents?

- At what point/stage do you experience the most damages?

- How many vehicles do you have for running your operations?

Page 146: Developing transport performance measures for Construction

138 | P a g e

- Do you generally track your shipments/deliveries?

- What transport performance measures do you think are important to

measure?

Page 147: Developing transport performance measures for Construction

139 | P a g e

11.2 Protocol for focus group

The protocol for focus group discussion developed with the help of theory and

semi structured interviews

Objective:

Effective

transport

planning

Objective:

Reduce

transportation

time

Objective:

Transport

cost

minimization

Objective:

To achieve

environmental

sustainability

Objective:

To ensure

security

Objective: To

ensure safety

Reduced no. of

miles driven

outside of pre-

determined

routes

Ensure on time

delivery

Reduce no. of

trips per

vehicle

Reduction in

CO2 emission

Ensure good

quality

packaging

of

hazardous

material

Reduce no. of

transport

incidents

Reduce total

distance driven

Reduce truck

turnaround time

-Loading and

unloading time

- Easy access to

construction site

Ensure

vehicle fuel

efficiency

including idle

time

Minimize no.

of breaches in

noise limits

Reduce on

road

material

theft

Ensure vehicle

insurance

Ensure trucks

availability

(trucks

confirmed vs

requested)

Minimize

vehicle travel

time

Reduce no. of

empty miles

Road damage

due to vehicle

vibrations or

vehicle

overload

Reduced no. of

unplanned

deliveries

Reduce the time

taken in

preparing

shipping

documents

Minimizing

maintenance

cost

Optimal no. of

deliveries

arrives at gate

per day

Minimize the

time taken in

doing shipping

documents

corrections

Reduce no. of

damages

during

delivery

Maximize

vehicle travel

capacity

Reduction in

average waiting

time at gate

Optimize no.

of vehicles

movement

Maximize

vehicle weight

utilization

Vehicles

schedule

reliability

Reduce cost

of delivery

Page 148: Developing transport performance measures for Construction

140 | P a g e

11.3 Interview guide for research question 2 The interview question for RQ2 were shared via email to the concerned contact

persons due to busy schedule of concerned contact persons and due to nature

of the questions;

- Do you record the data of vehicles regularly or not?

- Is the data available in excel sheets (ready to use format) or do we have

to organize the data to turn it into the meaningful format?

- What is average time that you take to deliver material at

site/terminal/checkpoint?

- How long the customer have to let the TPL know of the delivery i.e.

what time they have to book it?

- What is total distance between supplies and destination. Are supplies

far from the destination or are they closer? Is this convenient to supply

material from supplier to destination?

- What is the frequency of un-planned deliveries? How many times this

happen? How you deal with that and do you become successful in

making that delivery happen?

- How do you calculate no. of shipments per day?

- How do you make estimate that what amount of material will be used

in one day?

- How do you measure vehicle capacity?

- What is maximum vehicle capacity utilization that you have ensured

so far?

- How do you calculate vehicle weight utilization?

- How do you calculate vehicle turnaround time?

- At which point do you experience the most damages and how you

cover the cost for damages?

- How much cost you incur on maintaining vehicles?

- Is there any specific target that you have set for CO2 emission?

- How many vehicles do you have for running your operations?

- How do you ensure less safety and security incidents?

Page 149: Developing transport performance measures for Construction

141 | P a g e

11.4 Excerpts of semi structure interview for RQ2

The excerpts of interview for research question 2 are shown here;

Q: What is average time that you take to deliver material at

site/terminal/checkpoint?

JH: We don´t have any measurement regarding lead times from incoming

materials (from the supplier) to delivered on site. Just that the material arrived

before 9 am should be delivered the same day to the project.

Q: What is the frequency of un-planned deliveries? How many times this

happen? How you deal with that and do you become successful in making that

delivery happen?

JH: We don´t have any data of unplanned deliveries, but it happens. Often

when it has happened it´s because something unforeseen has happened in the

project.

Q: How do you make estimate that what amount of material will be used in

one day?

JH: We don´t. See above answers. The materials delivered to the warehouse

before 9 am will be delivered to site the same date. Unfortunately, we don´t

get any data from the suppliers, making it hard to plan number amount of

incoming materials and also amount of outgoing trucks.

Q: What is maximum vehicle capacity utilization in terms of travel that you

have ensured so far?

JH: No exact measurement but about 95% (loading meters)

Q: What is maximum vehicle weight utilization that you have ensured so far?

JH: No exact measurement but close to 100%

Page 150: Developing transport performance measures for Construction

142 | P a g e

11.5 Snapshot of original data by Case 1-Terminal The snapshot of data provided by Case 1 Terminal

Order nr

Företagskod

Artikelkod

Benämning (activities)

Datum Antal (amount)

Kundmärkning(customer marking/number)

Signatur

B1826

2822 T131 Materialförfrågning (material question)

11/1/2018

0.17 1881918302 MOKI

B1725

2450 T131 Inleverans 11/1/2018

0.5 25744 KAIV

B1725

2450 T132 Plock (gathering) 11/1/2018

0.08

MOKI

B2158

2009 T131 Uppmärkning Skanska (marking)

11/1/2018

0.25 114922 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 114875 7SÄT

B2158

2009 T131 Uppmärkning JRETAIL 11/1/2018

0.25 87520 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975929-01 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975932-01 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975936-01 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975931-01 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975937-01 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975935-01 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975943-01 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 5000196005 7SÄT

B2158

2009 T131 Uppmärkning Skanska

11/1/2018

0.25 975991-01 7SÄT

B2158

2009 T131 Uppmärkning Assemblin

11/1/2018

0.25 MB001056 7SÄT

B2158

2009 T131 Uppmärkning Zengun 11/1/2018

0.25 49235-01 7SÄT

B2158

2009 T131 Uppmärkning JRETAIL 11/1/2018

0.25 5165343681 7SÄT

B2158

2009 T105 Transport inkl chaufför

11/1/2018

1.5

8BRU

Page 151: Developing transport performance measures for Construction

143 | P a g e

B1870

2727 T131 Inleverans (delivery) 11/1/2018

0.17 25751 KAIV

B1870

2727 T132 Inleverans 11/1/2018

0.25 25751 KAIV

Page 152: Developing transport performance measures for Construction

144 | P a g e

11.6 MATLAB code for the analysis of Case-1 Terminal Data

In this file, we try to formulate the performance measures based on the

data given.

Data Pre-Processing

ActivityDetails in row 9068 is changed from blank to 'undefined'

ActivityDetails in row 9217 is changed from blank to 'undefined2' Note that

only columns 1 through 6 have been considered here, as other columns were

suggested to be ignored. Moreover, time has been changed from hours to

minutes.

opts = detectImportOptions('Data/Case-1-terminal/case1Data.csv');

% Also specifying the number of columns that we need to be imported.

opts.SelectedVariableNames = [1 2 3 4 5 6];

% Reading the table according to the import options we created above

data = readtable('Data/Case-1-terminal/case1Data.csv',opts);

% Converting time into minutes

data.Duration = data.Duration * 60;

% Converting ActivityDetails to Lower Case

data.ActivityDetails = lower(data.ActivityDetails);

% Sorting the table based on order number

data = sortrows(data, 1);

Refining the Activities

As discussed via eMail, that the activity lossning av slingbil can be combined

together, we are going to consider all the activities that contain the term

"lossning av slingbil" as the same. This decreased unique activities from 2133

to 1036 Doing the same for the term "lastning div ställningar" (down to 1032)

for i = 1:size(data, 1)

if (contains(data.ActivityDetails(i), 'lossning av slingbil'))

data.ActivityDetails(i) = {'lossning av slingbil'};

elseif (contains(data.ActivityDetails(i), 'lastning div ställningar'))

data.ActivityDetails(i) = {'lastning div ställningar'};

end

end

Finding average time for one particular activity.

Here we find all the unique activities and the average time taken to complete

one activity.

Page 153: Developing transport performance measures for Construction

145 | P a g e

activity = table(data.ActivityDetails,data.Duration);

uniqueActivities = sort(string(unique(data.ActivityDetails)));

for i = 1:size(uniqueActivities, 1)

temp = activity(activity.Var1 == uniqueActivities(i), 2);

uniqueActivities(i,2) = mean(temp.Var2);

end

Appending the average time in the main table.

Saving average time of activity in the table

data.ActivityDetails = categorical(data.ActivityDetails);

uniqueActivityNames = uniqueActivities(:,1);

uniqueActivityNames = categorical(uniqueActivityNames);

for i = 1:size(data.ActivityDetails, 1)

temp = uniqueActivities(uniqueActivityNames == data.ActivityDetails(i),

2);

data(i,7) = table(str2double(temp));

end

data.Properties.VariableNames(7) = {'AverageTime'};

data(:,8) = table(data.AverageTime - data.Duration);

data.Properties.VariableNames(8) = {'Efficiency'};

Splitting the main table

Splitting all the orders into separate tables and sorting according to the date

% Finding total unique order numbers

orderNumber = unique(data.OrderNumber);

orderNumber = string(orderNumber);

% Splitting

for i = 1:size(orderNumber, 1)

orderData{1,i} = data(data.OrderNumber==orderNumber(i),:);

orderData{1,i} = sortrows(orderData{1,i}, 5);

orderData{2,i} = orderNumber(i);

orderData{3,i} = mean(orderData{1,i}.Duration);

orderData{4,i} = std(orderData{1,i}.Duration);

orderData{5,i} = orderData{4,i}^2;

end

Now finding out which order number performed better than average

j = 1;

k = 1;

for i = 1:size(orderData,2)

orderData{2,i} = sum(orderData{1,i}.Efficiency);

if orderData{2,i} > 0

Page 154: Developing transport performance measures for Construction

146 | P a g e

efficientActivities (j,:) = [orderData{1,i}.OrderNumber(1)

orderData{2,i}];

j = j+1;

else

inefficientActivities (k,:) = [orderData{1,i}.OrderNumber(1)

orderData{2,i}];

k = k+1;

end

end

Most Efficient and Ineffecient Activities (Overall)

efficientActivities = sortrows(efficientActivities, -2)

inefficientActivities = sortrows(inefficientActivities, 2)

efficientActivities = cell2table(efficientActivities);

efficientActivities.Properties.VariableNames = {'OrderNumber',

'EfficientByMinutes'};

inefficientActivities = cell2table(inefficientActivities);

inefficientActivities.Properties.VariableNames = {'OrderNumber',

'InefficientByMinutes'};

% writetable(efficientActivities,'Data/Case-1-

terminal/efficientActivities.xlsx');

% writetable(inefficientActivities,'Data/Case-1-

terminal/inefficientActivities');

Now splitting the main table based on the Company

Splitting all the orders into separate tables and sorting according to the date

% Finding total unique order numbers

companyCodes = unique(data.CompanyCode);

% Splitting

for i = 1:size(companyCodes, 1)

companyData{1,i} = data(data.CompanyCode==companyCodes(i),:);

companyData{1,i} = sortrows(companyData{1,i}, 5);

companyData{2,i} = companyCodes(i);

companyData{3,i} = mean(companyData{1,i}.Duration);

companyData{4,i} = std(companyData{1,i}.Duration);

companyData{5,i} = companyData{4,i}^2;

end

clear companyNames projects unloadingSites i;

Average activity times in different companies.

Page 155: Developing transport performance measures for Construction

147 | P a g e

companyAnalysis = table(companyCodes);

M = containers.Map(uniqueActivities(:,1),1:size(uniqueActivities, 1));

uniqueActivityCodes = [(1:size(uniqueActivities,1))' uniqueActivities(:,1)];

companyAnalysis(:,2:size(uniqueActivities,1)+1) =

splitvars(table(zeros(size(companyAnalysis,1), size(uniqueActivities,1))));

for i = 1: size(companyData, 2)

companyAnalysis.companyCodes(i) = companyData{2,i};

activity = table(companyData{1,i}.ActivityDetails,

companyData{1,i}.Duration);

uniqueActivities =

sort(string(unique(companyData{1,i}.ActivityDetails)));

for j = 1:size(uniqueActivities, 1)

temp = activity(activity.Var1 == uniqueActivities(j), 2);

uniqueActivities(j,2) = mean(temp.Var2);

end

for k = 1:size(uniqueActivities, 1)

% companyAnalysis(i, k+1) = {uniqueActivities(k,2)};

companyAnalysis(i, M(uniqueActivities(k,1))+1) =

{uniqueActivities(k,2)};

end

clear activity uniqueActivities;

end

tempStr = string(uniqueActivityNames)';

for i = 1:size(tempStr,2)

tempStr(1,i) = strcat(toCamelCase(tempStr{1,i}), num2str(i));

end

companyAnalysis.Properties.VariableNames = ['companyCode', tempStr];

clear tempStr;

% Nowe we have the variable companyAnalysis with company codes per row and

% activities per column. One cell represents the average time taken by the

% company to complete that particular task. A value of 0 represents that

% that company doesn't perform that task.

% Now let's find out which companies perform a particular activity the

% fastest and slowest.

for i = 2:size(companyAnalysis,2)

tempT = table2array(companyAnalysis(table2array(companyAnalysis(:,1)) ~=

0, [1,i]));

Activity(i-1,1) = uniqueActivityCodes(i-1,2);

[~,FastComIdx] = min(tempT(:,2));

[~,SlowComIdx] = max(tempT(:,2));

FastCompany(i-1,1) = tempT(FastComIdx,1);

SlowCompany(i-1,1) = tempT(SlowComIdx,1);

end

SlowFastCompanies = table(Activity, SlowCompany, FastCompany);

SlowFastCompanies((table2array(SlowFastCompanies(:,2)) ==

table2array(SlowFastCompanies(:,3))), :) = [];

Page 156: Developing transport performance measures for Construction

148 | P a g e

clear tempT Activity FastComIdx SlowComIdx FastCompany SlowCompany i j k;

% writetable(SlowFastCompanies,'Data/Case-1-

terminal/SlowFastCompanies.xlsx','Sheet',1,'Range','A1');

Saving other variables to table

byCompany = splitvars(table(companyData(2:end, :)'));

byCompany.Properties.VariableNames = {'CompanyName', 'Mean',

'StandardDeviation', 'Variance'};

% writetable(temp,'Data/Case-1-

terminal/byCompany.xlsx','Sheet',1,'Range','A1');

byOrder = splitvars(table(orderData(2:end, :)'));

byOrder.Properties.VariableNames = {'OrderName', 'Mean', 'StandardDeviation',

'Variance'};

% writetable(temp,'Data/Case-1-

terminal/byOrder.xlsx','Sheet',1,'Range','A1');

PIECHART

SC = SlowFastCompanies.SlowCompany;

FC = SlowFastCompanies.FastCompany;

[f1,f2] = hist(FC, unique(FC));

[s1,s2] = hist(SC, unique(SC));

f1c = categorical (FC);

temp = and(f1c ~= '2009', f1c ~= '2450');

fcOthers = FC;

fcOthers = string(fcOthers);

fcOthers(temp,:) = 'others';

fcOthers = categorical(fcOthers);

hFig1 = figure(1);

pie(fcOthers, [0 1 0]);

s1c = categorical(SC);

temp = and(and(and(s1c ~= '2009', s1c ~= '2450') , s1c ~= '2727'), s1c ~=

'2811');

scOthers = SC;

scOthers = string(scOthers);

scOthers(temp,:) = 'others';

scOthers = categorical(scOthers);

hFig2 = figure(2);

pie(scOthers, [1 0 0 0 0]);

Efficient/Inefficient per activity

Page 157: Developing transport performance measures for Construction

149 | P a g e

%activities per order

ordNum = categorical(data.OrderNumber);

[apo1,apo2] = hist(ordNum, unique(ordNum));

apo1 = string(apo1)';

apo2 = string(apo2)';

apo1(:,2) = apo2;

efficientActivities = sortrows(efficientActivities, 1);

apo1 = sortrows(apo1,2);

for i = 1:size(efficientActivities,1)

idx = apo1(:,2) == efficientActivities.OrderNumber(i);

efficientActivities(i,3) =

{efficientActivities.EfficientByMinutes(i)/str2double(apo1(idx,1))};

end

efficientActivities = sortrows(efficientActivities,-3);

inefficientActivities = sortrows(inefficientActivities,1);

for i = 1:size(inefficientActivities,1)

idx = apo1(:,2) == inefficientActivities.OrderNumber(i);

inefficientActivities(i,3) =

{inefficientActivities.InefficientByMinutes(i)/str2double(apo1(idx,1))};

end

inefficientActivities = sortrows(inefficientActivities,3);

hfig3 = figure(3);

cat1 = categorical(efficientActivities.OrderNumber,

efficientActivities.OrderNumber);

bar(cat1, efficientActivities.Var3);

hfig4 = figure(4);

cat2 = categorical(inefficientActivities.OrderNumber,

inefficientActivities.OrderNumber);

bar(cat2, inefficientActivities.Var3 * -1);

Number of deliveries per company

for i = 1: size(companyData,2)

temp1 =

companyData{1,i}(contains(string(companyData{1,i}.ActivityDetails),

'inleverans'),:);

if (size(temp1,1) == 0 || size(temp1,1) == 1)

byCompany.DeliveryCount(i) = size(temp1,1);

byCompany.AverageTimeBetweenDeliveries(i) = -1;

continue;

end

temp1 = sortrows(temp1, 5);

temp1.Difference(1) = 0;

temp1.Difference(2:end) = datenum(string(table2cell(temp1(2:end,5)))) -

datenum(string(table2cell(temp1(1:end-1,5))));

Page 158: Developing transport performance measures for Construction

150 | P a g e

byCompany.DeliveryCount(i) = size(temp1,1);

byCompany.AverageTimeBetweenDeliveries(i) =

sum(temp1.Difference)/(size(temp1,1)-1);

end

% To be exported to excel to make histogram

companyHistogramData = byCompany(byCompany.AverageTimeBetweenDeliveries >0 ,

[1 5 6]);

%Nr = normalize(A,'range')

companyHistogramData.NrDC =

normalize(companyHistogramData.DeliveryCount,'range');

companyHistogramData.NrAvg =

normalize(companyHistogramData.AverageTimeBetweenDeliveries,'range');

Other Functions

function returnString = toCamelCase (str)

str=lower(str);

idx=regexp([' ' str],'(?<=\s+)\S','start')-1;

str(idx)=upper(str(idx));

str(~ismember(str,['A':'Z' 'a':'z'])) = '';

returnString = str;

returnString = returnString(find(~isspace(returnString)));

end

11.7 MATLAB code for the analysis of Case-2 Terminal Data

KPI Formulation for Case-2-terminal data

In this file, we try to formulate the performance measures based on the data

given.

Data Pre-Processing

ActivityDetails in row 9068 is changed from blank to 'undefined'

ActivityDetails in row 9217 is changed from blank to 'undefined2' Note that

only columns 1 through 6 have been considered here, as other columns were

suggested to be ignored. Moreover, time has been changed from hours to

minutes.

clear;

clc;

opts = detectImportOptions('Data/Case-2-terminal/epData.csv');

% Also specifying the number of columns that we need to be imported.

Page 159: Developing transport performance measures for Construction

151 | P a g e

opts.SelectedVariableNames = [1 3:13];

% Ignore those rows where item value is missing

opts.MissingRule = 'omitrow';

% Reading the table according to the import options we created above

data = readtable('Data/Case-2-terminal/epData.csv',opts);

Splitting the main table based on Unloading Site

Splitting all the orders into separate tables and sorting according to the date

% Finding total unique order numbers

unloadingSites = string(unique(data.UnloadingSite));

% Splitting

for i = 1:size(unloadingSites, 1)

unloadingSitesData{1,i} = data(data.UnloadingSite==unloadingSites(i),:);

unloadingSitesData{1,i} = sortrows(unloadingSitesData{1,i}, 3);

unloadingSitesData{2,i} = unloadingSites(i);

unloadingSitesData{3,i} = mean(unloadingSitesData{1,i}.Duration);

unloadingSitesData{4,i} = std(unloadingSitesData{1,i}.Duration);

unloadingSitesData{5,i} = unloadingSitesData{4,i}^2;

end

Splitting the main table based on Project

Splitting all the orders into separate tables and sorting according to the date

% Finding total unique order numbers

projects = string(unique(data.Project));

% Splitting

for i = 1:size(projects, 1)

projectsData{1,i} = data(data.Project==projects(i),:);

projectsData{1,i} = sortrows(projectsData{1,i}, 3);

projectsData{2,i} = projects(i);

projectsData{3,i} = mean(projectsData{1,i}.Duration);

projectsData{4,i} = std(projectsData{1,i}.Duration);

projectsData{5,i} = projectsData{4,i}^2;

end

Splitting the main table based on Company

Splitting all the orders into separate tables and sorting according to the date

% Finding total unique order numbers

companyNames = string(unique(data.CompanyName));

% Splitting

for i = 1:size(companyNames, 1)

companyData{1,i} = data(data.CompanyName==companyNames(i),:);

companyData{1,i} = sortrows(companyData{1,i}, 3);

Page 160: Developing transport performance measures for Construction

152 | P a g e

companyData{2,i} = companyNames(i);

companyData{3,i} = mean(companyData{1,i}.Duration);

companyData{4,i} = std(companyData{1,i}.Duration);

companyData{5,i} = companyData{4,i}^2;

end

clear companyNames projects unloadingSites i;

Exporting the data

% Export by Company

byCompany = table(companyData(2:4, :)');

byCompany =

splitvars(byCompany,'Var1','NewVariableNames',{'CompanyName','MeanDuration','

StandardDeviation'});

% Export by Project

byProject = table(projectsData(2:4, :)');

byProject =

splitvars(byProject,'Var1','NewVariableNames',{'CompanyName','MeanDuration','

StandardDeviation'});

% Export by Unloading Site

byUnloadingSite = table(unloadingSitesData(2:4, :)');

byUnloadingSite =

splitvars(byUnloadingSite,'Var1','NewVariableNames',{'CompanyName','MeanDurat

ion','StandardDeviation'});

Saving to excel

writetable(byCompany,'Data/Case-2-

terminal/byCompany.xlsx','FileType','spreadsheet'); for i =

1:size(companyData,2) writetable(companyData{1,i},'Data/Case-2-

terminal/byCompany.xlsx','Sheet',1+i,'Range','A1'); end

writetable(byProject,'Data/Case-2-

terminal/byProject.xlsx','FileType','spreadsheet'); for i =

1:size(projectsData,2) writetable(projectsData{1,i},'Data/Case-2-

terminal/byProject.xlsx','Sheet',1+i,'Range','A1'); end

writetable(byUnloadingSite,'Data/Case-2-

terminal/byUnloadingSite.xlsx','FileType','spreadsheet'); for i =

1:size(unloadingSitesData,2)

writetable(unloadingSitesData{1,i},'Data/Case-2-

terminal/byUnloadingSite.xlsx','Sheet',1+i,'Range','A1'); end

clear byCompany byProject byUnloadingSite;