detroit temperature control and...

24
217 217 217 200 200 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56 48 130 120 111 237 237 237 80 119 27 252 174 .59 83 36 118 1 Jeff Ament, Detroit DS Passage Project Manager Kelly Janes, Environmental Resource Specialist Tim Ernster, Detroit Dam Operations and Maintenance Manager North Santiam Watershed Council Meeting 8 February 2018 DETROIT TEMPERATURE CONTROL AND DOWNSTREAM PASSAGE – INFORMATIONAL MEETINGS

Upload: vuongdan

Post on 08-May-2018

218 views

Category:

Documents


3 download

TRANSCRIPT

217217217

200200200

255255255

000

163163163

131132122

2396553

110135120

1129256

62102130

1025648

130120111

237237237

8011927

252174.59

8336118

1

Jeff Ament, Detroit DS Passage Project ManagerKelly Janes, Environmental Resource SpecialistTim Ernster, Detroit Dam Operations and Maintenance Manager

North Santiam Watershed Council Meeting8 February 2018

DETROIT TEMPERATURE CONTROL AND DOWNSTREAM PASSAGE – INFORMATIONAL MEETINGS

2

The purpose of the Detroit DownstreamPassage Project is to:• To provide downstream juvenile fishpassage at Detroit Dam for threatenedUpper Willamette River Chinook salmonand steelhead.• To meet water temperaturerequirements for these threatened fishby providing temperature control forwater released from Detroit Dam.

Lead AgencyU.S. Army Corps of Engineers

Cooperating Federal AgenciesBonneville Power AdministrationNational Marine Fisheries ServiceU.S. Fish and Wildlife ServiceU.S. Forest Service

Cooperating State AgenciesOregon Fish and Wildlife ServiceOregon Water Resources DepartmentOregon Parks and Recreation Department

• These operations are limited to when water is above spillway crest.• Fish are passed over spillway resulting in injury or mortality.

ENGINEERING AND ALTERNATIVES ANALYSIS PROCESS

EDR (Engineering Documentation Report) – 2009-2016 (Complete)–Determine problem–Determine solutions that would solve the problem–Initial Alternatives Analysis and Screening

DDR (Design Documentation Report) – In Progress–Construction Alternatives Analysis

•Develop design, confirm constructability–Environmental Impacts Assessment – NEPA

•public review and comment–Refine/optimize the recommended solution–Detailed Cost Estimate–24 months

P&S (Plans & Specifications) – Future Actions–Develop the design completely–Drawings and Specifications become legal construction contract–24 months (will take place in 2 phases)

Construction–24-36 months (will take place in 2 phases)

Initial Array of Alternatives· Temperature Control Tower with Selective Withdrawal Structure (SWS) – Floating Outlet Combined with Lower Fixed Outlet· Use Existing Equipment – Optimum Operations· Restrict Pool Elevations· Floating (Surface) Withdrawal Structure· Modify Existing Equipment for Lower Flows (Spillway and RO Gates)· Pumps and/or Aerators in Nearfield Forebay· New Outlets in Dam· Heating/Cooling System for Water Release· Pump Water Over Dam· Temperature Control Curtain· Supplement Existing Equipment with Simple SWS· Floating Surface Outlet· Deep Reservoir Drawdown· Prioritization of ROs under Typical Winter Reservoir Elevations

Alternatives Screening Criteria • Would not meet downstream

temperature targets (based on modeling results).

• Would meet temperature targets in cool-wet years but not dry-hot years (based on modeling results).

• Would negatively impact Flood Risk Management.

• Would have very large, long term impacts on recreation, hydropower production, irrigation and water supply needs as well as instream flow requirements.

• Would have negative impacts on water quality.

• Would not be structurally stable in an earthquake.

• Would not meet performance standards.• Not technical feasibility or practical.

mixes

Alternative 1. Extended Low Drawdown• 2 full years with

reservoir levels remaining at 1310’ elevation in order to construct project above water level (i.e. building “in the dry”).

• No hydropower production during construction.

• Lowest safety and implementation risk compared to other alternatives.

Alternative 2. Short Term Low Drawdown• 1 summer season

with reservoir levels at 1310’ to construct project foundation in the dry.

• Construct remainder of project under water (i.e. building “in the wet”).

• Requires no hydropower production during construction (diver safety).

• Increased safety and implementation risk compared with alternatives built entirely in the dry.

Alternative 3. Variable Drawdown with Temporary Cofferdam• Build a watertight enclosure (coffer dam) around the

construction area and pump out the water inside in order to work in the dry below the waterline.

• 2 years with reservoir at reduced elevations, depending on coffer dam capabilities. Start at 1310‘ reservoir elevation to build partial height cofferdam. As construction height grows, coffer dam and reservoir elevations will be raised. Coffer dam would be removed at end of project construction.

• Likely not feasible due to valley geometry and height required.

Alternative 4. Variable Drawdown• 1 summer season

with reservoir levels at 1310’ to construct project foundation in the dry.

• Gradually raise water elevation together with construction height, always building in the dry.

• Increased safety and implementation risk associated with food risk management operations in the winter and building off foating docks.

15

Alternative 5. Build in the Wet• 2+ years with normal

reservoir elevations.• Requires underwater

blasting (potential water quality impacts) and no hydropower production (diver safety).

• Likely more expensive then other alternatives with high safety and implementation risks.

Initial Array of Alternatives• Head-of-Reservoir Collection• Floating Surface Collector, variations include:

-Floating Surface Collector with No Nets-Floating Surface Collector with Partial Depth Nets-Floating Surface Collector with Full Depth Nets and Partial Outlet Coverage- Floating Surface Collector with Full Depth Nets and Full Outlet Coverage

• Selective Withdrawal Structure as Fish Passage Structure

• Selective Withdrawal Structure with Weir Box• Selective Withdrawal Structure with Floating

Screen Structure (need for nets and outlet coverage to be determined)

Alternatives Screening Criteria• Would not meet downstream temperature

targets. • Would require additional fish passage

measures to meet performance standards.

Preferred Alternative Proposes Two PhasesPhase 1: Construct temperature control

Assess efficacy of recently constructed Floating Screen Structures at other sites

Phase 2: Construct Floating Screen Structure

PHASE 1 PHASE 2

FLOATING SCREEN STRUCTURE EXAMPLE

Pelton Round Butte Structure (near Madras, Oregon)• Screens fish from the water going into temperature

control structure• All flow is gravity feed prior to water entering power

house intake or regulating outlets

SELECTIVE WITHDRAWAL SYSTEMEXAMPLE

Cougar Dam Temperature Control Tower

CURRENT STATUS

Developing Design Documentation reports–Temperature Control Tower and Floating Screen Structure

• determining Preliminary Design Details and system interface for all three features with the dam–Assess construction methods and staging areas

Environmental Impacts Analysis per the National Environmental Policy Act (NEPA)–NEPA Scoping & Public Engagement

• Goal: Identify resources of concern (e.g. biological resources, air quality, water quality, water supply, hydropower, recreation, aesthetics, cultural resources, etc.) that could be impacted by the construction, operations, and maintenance of the project.

• Product: Draft a scoping report: summary of the issues to be evaluated in the EIS, a list of who participated in the scoping process, and the views of those participants.

–Drafting Environmental Impact Statement• Characterize existing conditions• Assess the direct, indirect, and cumulative impacts to resources of concern for a reasonable array of alternatives.• Identify preferred alternative, mitigation measures, and impacts that can’t be mitigated.

23rd

23

23

Impacts analysis will include assessment of the following resources:• Water Quality

o Turbidityo Temperatureso Total Dissolved Gaso Dissolved Oxygeno Blue Green Algaeo Contaminants (DDT, hydrocarbons, etc.)

• Flows• Water Supply• Aquatic Community• Ecologically critical resources (wetlands, EFH,

etc.)• Endangered & Threatened Species

o UWR Chinook and steelheado Spotted Owl

• Hydro Power (BPA to assist with analysis)• Cultural Resources• Socioeconomics/Recreation• Traffic• Noise• Visual, scenic, and aesthetic resources

• Air Quality (only short term impacts)

• Geology• Terrestrial Community• Eagles• Migratory Birds• Agricultural Resources

ENVIRONMENTAL RESOURCES