design status of the iter up launcher · three sm designs under development: 1) balanced...
TRANSCRIPT
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
M.A. Henderson1, R. Chavan1,R. Bertizzolo1, A. Bruschi2, D. Campbell3, E. Ciattaglia3,S. Cirant2, A. Collazos1,
I. Danilov4, F. Dolizy1, J. Duron1, D. Farina2, R. Heidinger4, W. Kasparek5,K. Kleefeldt4, H. Kumric5, J.-D. Landis1, A. Moro2, P. Platania2, B. Plaum5,E. Poli6, G. Ramponi2, G. Saibene3, F. Sanchez1, O. Sauter1, A. Serikov4,
H. Shidara1, C. Sozzi2, P. Spaeh4, D. Straus4, V.S. Udintsev1, H. Zohm6, C. Zucca1
1 CRPP, EURATOM – Confédération Suisse, EPFL, CH-1015 Lausanne Switzerland2 Istituto di Fisica del Plasma, EURATOM- ENEA- CNR, 20125 Milano, Italy
3 EFDA Close Support Unit, Boltzmannstrasse 2, D-85748 Garching, Germany 4 Forschungszentrum Karlsruhe, EURATOM-FZK, D-76021 Karlsruhe, Germany
5 IPF-Stuttgart, Max Planck-Institute für Plasmaphysik, D-85748 Stuttgart, Germany6 IPP-Garching, Max Planck-Institute für Plasmaphysik, D-85748 Garching, Germany
Thanks to:T. Bigelow6, J. Doane7, H. Grunloh7, N. Kobayashi8,
D. Rasmussen6, K. Sakamoto9, K. Takahashi96 ITER-US, Oak Ridge TN, USA
7 General Atomics, San Diego CA, USA8 ITER, Cadarache, France
9 JAEA, Naka, Japan
Design Status of the ITER UP Launcher
1
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Outline
EC system functionality
UL mm-wave design
UL steering mechanism
UL interfaces
Conclusion
2
Aim of this presentation: Provide you with a general overview of progress in the UL mm-wave design aspects
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Role of Upper Launcher (<2006)
Steering range:Access q=3/2 and 2 surfacesfor scenarios 2, 3a and 50.64≤ρψ≤0.93
3
q=3/2 q=2
NTM stabilisation
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Role of Upper Launcher (<2006)
Steering range:Access q=3/2 and 2 surfacesfor scenarios 2, 3a and 50.64≤ρψ≤0.93
3
q=3/2 q=2
NTM stabilisation
Achieved jCD/jBS for the 3 scenarios
Focusing:jCD/jBS >1.2(achieved 1.8< jCD/jBS < 3.6)Note: not all PEC will be available all the time!
Scenario 2 Scenario 3a Scenario 5
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Revision of the UL Functionality
UL: 4 ports with 1 application
EL: 1 port with multiple applications
No EL design can achieveall desired functions
4
Several Short Comings have been identified in the ECH system
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Revision of the UL Functionality
UL: 4 ports with 1 application
EL: 1 port with multiple applications
No EL design can achieveall desired functions
4
Several Short Comings have been identified in the ECH system
1
2
1 <100% full passabsorption 2 Partial access
of 20MW inside ρ<0.3
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Revision of the UL Functionality
UL: 4 ports with 1 application
EL: 1 port with multiple applications
No EL design can achieveall desired functions
4
Several Short Comings have been identified in the ECH system
1
2
1 <100% full passabsorption 2 Partial access
of 20MW inside ρ<0.3
UL-FS (2005)3 ports (8 beams/port)
(In 2004: 4 ports for UL)
(2005) ITER: keep 4th port, aim for
lower engineering constraintsimprove physics performanceand collaborate with JAEA
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Enhanced Performance (EP) Launcher
5
Spread out steering rangesAccess in to ρ=0.4 (sawteeth)1 2 Limit steering range, use QO design +
cnt-ECCD mirror, add poloidal tiltcnt-ECCD + QO mirror Poloidal tiltJAEA
co
cocnt
OR
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Enhanced Performance (EP) Launcher
5
Spread out steering rangesAccess in to ρ=0.4 (sawteeth)1 2 Limit steering range, use QO design +
cnt-ECCD mirror, add poloidal tilt
Result: UL controls sawteeth (more efficiently)EL accesses ρ<0.15 with 20MW co and cnt-ECCD availablePure ECH (decouples heating and CD)
ITER (2006): Continue in this direction,minimize engineering constraints and maximize functionality
cnt-ECCD + QO mirror Poloidal tiltJAEA
co
cocnt
OR
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
UL Optical Design
6
Top
view
Side
vie
w
plasma
entrance
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
UL Optical Design
6
Top
view
Side
vie
w
8 beams/port
HE11 waveguide
isolationvalve windowmitre
bends
freespace
propagationsteeringmirrors
focusingmirrorsplasma
entrance
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Planned Design Improvements
7
1. CNR: Optimisation of mirror size and beam clearance+ minimize beam deformation and stray radiation
2. CRPP: Optimisation of beam focusing+ replace mitre bends with free space mirrors (reduces cost and complexity)
3. IPF: Use HE11 to TEM00 converters+ minimize stray radiation
4. Relocate isolation valves and window?
1
24
3
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Simplifying Launcher Entrance
8
Present Design Extremely Congested:Isolation of window from torus pressureActuator bellows forms 1st tritium barrierCongests closure plate, limiting accessComplicates access for valve maintenanceRequires non-standard valve design
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Simplifying Launcher Entrance
8
Present Design Extremely Congested:Isolation of window from torus pressureActuator bellows forms 1st tritium barrierCongests closure plate, limiting accessComplicates access for valve maintenanceRequires non-standard valve design
Alternative valve location:Displace Valve (and window?) from port plugLauncher maintenance independent of valveIncreases available space at closure plateSimplifies valve (and window?) accessSimplifies waveguide-closure plate interface
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Low power
Low and high power RF tests
9
1. Test optical integrity of focusing mirror(s)2. Quantify mirror and shield block aperture affects
High power1. Test complete mock-up launcher2. Planned for ~2010 (pending source availability)
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Steering MechanismPneumatic system:Frictionless and backlash free
Accurate rotational control≤0.1º or ~2 to 4mm(<3.5% degradation in jCD)
flexure pivot replaces bearings
Bellows ‘piston’ replaces push-pull rods
10
Flexure pivot concept
Pneumatic actuator conceptPbellows=nominal Pbellows~13barPbellows~2bar
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Three SM designs under development:
1) Balanced configuration- lower forces on FP
2) 1st prototype design- test machinability- test actuator concept- Initiate industrial collaboration
3) Cantilevered configuration- simpler support- optimizes actuator space- increase beam clearance @ FWP
(a) Steering Mechanism design
11
(2003 design)
(2007 design)
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Forces on flexure pivot doubledSimplifies fixation to BSMSimplifies RH aspectsMirror expands freelyOptimizes use of BSM spaceMore space for beam passage through FWP
Cantilevered Steering Mechanism
12
XY
Z
EM Moment
0.175m 0.175m
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Bellows (cyclic fatigue)Most susceptible to cyclic fatigue
ITER lifetime: ~23’000 cycles
Present design: ~150’000 cycles(based on EJMA with SS bellows)
Investigating Alloy718 and NiCo
Analyzing thermal treatment effects(ITER database points out uncertainty)
Critical component: Bellows
13
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Thermal Treatment of Alloy 718 BellowsWorking with BOA AG for understanding thermal treatment effects
14
Solution annealing
Additional heat treatment
ITER prescribed heat treatment
Each sample undergoes equivalent stress cycling
ITER treatment achieves 560’000 cycles without failure
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Induced currents during VDEVDE results in strong torques on mirrorFFP ~ 1.4 to 3kN
Present design supports accepts FFP > 6kN(at worst rotation and maximum torque)
Critical Issues: Induced EM currents
15
XY
Z
EM Moment
0.175m0.175m
All FE modeling in ANSYSThermal-mechanical
EM induced currents
Rigidity
(models inputed from CATIA)
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
T-line - Launcher Interface
16
Compatible with Tritium barriersMaximize maintenance accessMaximize access at launcher entranceSimplify procedure for launcher removalCompensate for ±30mm torus displacementCompatible with T-line calibration
CRPP/EFDA proposal
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
T-line - Launcher Interface
16
Compatible with Tritium barriersMaximize maintenance accessMaximize access at launcher entranceSimplify procedure for launcher removalCompensate for ±30mm torus displacementCompatible with T-line calibration
CRPP/EFDA proposal ITER-US, GA T-line layout for UL
Wall of tokamak buildingDoor of bioshield
Port cellUL port plug
D. Rasmussen et al, this conference.
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Common Issues active or under consideration: mitre bend tests waveguide tests HIPping tests mirror encoder free space mirror loading isolation valve waveguide cooling bellows analysis fail-safe concepts auxiliary systems
EL - UL Common Issues
17
JAEA
JAEA
JAEA
IAEA ITER ECH: 6.06.2007M.A. Henderson ITER Upper Launcher
/ 18
Conclusion
18
UL has an adequate margin of safety for NTM stabilization
Physics roles of UL and EL can be redefined for a more balanced partitioning of physics objectives- relaxes some of the engineering constraints- increases capabilities of the EC system
UL design is continuing to progress toward- a more simplified/reliable design- further optimized optical design
Collaboration with local industry has begun in preparation for fabrication
Testing has begun on critical components/subsystems
Active collaboration with other ITER parties- resolving interface issues- sharing design and analysis- moving toward a common component philospohy