design-stage assumptions for good off-design performance ... · design of an air-cooled binary...
TRANSCRIPT
-
PROCEEDINGS OF ECOS 2018 - THE 31TH INTERNATIONAL CONFERENCE ON
EFFICIENCY, COST, OPTIMIZATION, SIMULATION AND ENVIRONMENTAL IMPACT OF ENERGY SYSTEMS
JUNE 17-22, 2018, GUIMARÃES, PORTUGAL
Design-stage assumptions for good off-design performance of a binary geothermal power plant
Sarah Van Erdeweghea,e
, Johan Van Baelb,e
, Ben Laenenc and William D’haeseleer
d,e
a University of Leuven (KU Leuven), Applied Mechanics and Energy Conversion Section,
Celestijnenlaan 300 – Box 2421, B-3001 Leuven, Belgium, [email protected] (CA) b Flemish Institute for Technological Research (VITO),
Boeretang 200, B-2400 Mol, Belgium, [email protected] c Flemish Institute for Technological Research (VITO),
Boeretang 200, B-2400 Mol, Belgium, [email protected] d University of Leuven (KU Leuven), Applied Mechanics and Energy Conversion Section,
Celestijnenlaan 300 – Box 2421, B-3001 Leuven, Belgium, [email protected] e EnergyVille, Thor Park, Poort Genk 8310, B-3600 Genk, Belgium
Abstract:
In the literature, several studies exist on the design of a binary geothermal power plant. However, most of them do not (properly) account for its off-design operation. Even for a baseload geothermal power plant, frequent off-design operation occurs due to the changing environment conditions. Therefore, in this work, we propose a two-step optimization methodology which allows optimizing the design of an air-cooled binary geothermal power plant as well as the operating conditions during a typical year. In the first step, the design of the shell-and-tube heat exchangers and the air-cooled condenser are optimized towards maximal Net Present Value (NPV). The NPV is chosen as the optimization objective since it accounts for the size of the components, the economic parameters and the time value of money. However, assumptions have to be made regarding the economic parameters, such as the electricity price, and the environment conditions. In the second step, we optimize the operating conditions (temperatures and flow rates) of the binary power plant during a typical year towards maximal net electrical power output. Here, we take into account the Belgian hourly weather data and electricity prices for 2016. If we calculate the NPV in a post-processing step, accounting for the real hourly electricity prices and weather conditions, the value is different from the value in step 1. The real NPV is the highest for an ORC which was designed for the average electricity price (of 36.57 EUR2016/MWh). The electricity prices are not a priory known, but for a design assumption close to the average electricity price (30-60 EUR2016/MWh), the NPV is not more than 10% lower than the optimal value. The influence of the environment temperature assumption on the real NPV is small (
-
off-design ORC performance for source temperatures of 130-180°C and ambient conditions of 0-
30°C. They neither have included an economic analysis. Usman et al. [9] have compared the off-
design behavior of air-cooled and water-cooled ORCs based on monthly-averaged data for the
environment conditions. They have considered two sets of geothermal source conditions (set 1:
130°C and 9.16kg/s, set 2: 145°C and 6.57kg/s) and they did include an economic analysis;
however, they have used monthly-averaged data which are not that accurate.
Calise et al. [10] have made a combined design and off-design analysis. They have first optimized
the heat exchanger design (tube length, tube number and shell diameter) of a solar-fueled ORC
starting from an initial plant design, towards minimal yearly plant cost. Furthermore, they have
investigated the off-design performance of this power plant for source temperatures (thermal oil) of
155-185°C and flow rates of 18-24kg/s. They have assumed constant cooling water inlet
temperatures.
In this work we present a two-step optimization methodology which allows optimizing the (heat
exchanger and condenser) design of a binary geothermal plant, and the optimization of the net
electrical power output during off-design (real operation) as given in Table 1. There are some
differences with the mentioned literature. We focus on an air-cooled condenser since then no
cooling water is needed, and on shell-and-tube heat exchangers because of the high (thermal)
powers and operating pressures. For the off-design optimization we use hourly data for the
electricity price observed in a real market environment and for the environment conditions. From
our model results it follows that it is important to take the hourly variability into account, rather
than using daily- or monthly-averaged data. Besides, we investigate the thermoeconomics (net
present value – NPV) of the geothermal power plant since the decision to build a power plant is
generally based on economics, not on thermodynamics.
Table 1: Objective, variables and parameter values for steps 1 and 2 of the optimization framework.
objective variables note on some parameter values
Step 1: design NPV ORC design & op. cond. Tenv = Tenvav 2016, pel = pel
av 2016
Step 2: off-design electrical power operating conditions hourly data for Tenv, pel
Changing the parameter assumptions for 𝑇𝑒𝑛𝑣 and 𝑝𝑒𝑙 in the design stage (step 1) and making the design and off-design optimization calculations, we can get some insights in the influence of these
parameter assumptions on the real NPV of the project. So the feedback between steps 2 and 1
allows us to make proper assumptions for 𝑇𝑒𝑛𝑣 and 𝑝𝑒𝑙 in the design stage for a good performance and high revenues during the plant lifetime. Furthermore, a big advantage of our two-step
optimization methodology is that the same models for the design and off-design optimizations are
used, but another optimization objective is imposed (NPV versus net electrical power) and the
constraints are slightly different.
2. Model
2.1. ORC set-up
Fig. 1 shows a standard ORC, and the most important states are indicated. However also
recuperated ORCs have been considered; but only the standard ORC is shown for clarity reasons. In
a recuperated ORC, an extra heat exchanger – also called recuperator – is added to use the outlet
superheated vapor of the turbine (state 4) for heating the fluid at the pump outlet (state 2). We
consider 1 pass / 1 pass TEMA E shell&tube heat exchangers with a 30° tube layout and the brine
flowing through the tubes. The wall thickness is 2.5mm and the thermal conductivity is 18W/mK
[11]. Other design parameters will be optimized. Besides, we consider an A-frame air-cooled
condenser (ACC) with flat tubes of 19mm x 200mm and a fin thickness of 0.25mm [1], [12]. The
fin spacing Sfin, fin height Hfin and the number of tubes ntube will be optimized.
-
2.2. Thermoeconomic model
Detailed thermodynamic models are used for the
heat exchangers and the air-cooled condenser.
The shell-and-tube heat-exchangers geometry is
modeled following the TEMA standards [13]–
[15]. We consider an economizer, an evaporator
and a superheater, but assume the same geometry
for the three parts – the three parts together are
called EES in Fig. 1. This eases the heat-
exchanger fabrication and allows us to make off-
design calculations without big numerical issues.
The Bell-Delaware method is used for the shell
side heat transfer and pressure drop modeling
[14], [15]. The working fluid flows through the
shell. For the one phase ideal heat transfer and
pressure drop calculations, we use the correlations
of Shah et al. in [15] and for the two-phase heat
transfer modeling, the correlations as given by
Hewitt in [14]. The brine flows through the tubes
and the correlation of Bhatti and Shah [16] and
the correlation of Petukhov and Popov [17] are
used for the friction factor and heat transfer
coefficient calculations, respectively. The same
modeling approach for the heat exchangers is
followed as in Walraven et al. [11]. For more
info, the reader is referred to [11].
An A-frame air-cooled condenser is considered and the model equations from Yang [1], [12] are
implemented for the air-side heat transfer and friction factor calculations. The working fluid heat
transfer coefficient and friction factor in single phase (desuperheater) are calculated using the
calculations of Gnielinski [18] and Petukhov and Popov [17], respectively. For the two-phase heat
transfer in the condensing part, the CISE correlation [19], the Chisholm correlation [20] and the
correlation of Shah [21] are used for the void fraction, pressure drop and heat transfer coefficient
calculations. The same modeling approach for the air-cooled condenser is followed as in Walraven
et al. [1]. For more info, the reader is referred to [1], [12].
The turbine efficiency is calculated using the widely used correlation of Macchi and Perdichizzi
[22]. A curve-fit has been derived by Walraven et al. in [1]. The off-design turbine performance is
calculated using the Stodola Ellipse Law [23] and the according off-design efficiency is calculated
using the Keeley correlation [24].
All ORC component costs are calculated following the same procedure as in our previous ECOS
contribution [25]. The bare equipment cost for the heat exchangers is corrected for high
temperatures (𝑓𝑇 = 1.6), high pressures (𝑓𝑝 = 1.5) and the need for stainless steel (𝑓𝑀 = 1.6) [26]. An installation factor of 0.6 is considered based on [27]. The chemical engineering index is used to
convert the costs to 2016-values and a euro-to-dollar conversion of 1.2$/EUR is assumed.
2.3. Model parameters
The brine conditions are based on the expected conditions of the Balmatt geothermal site (Mol
Belgium) [28]. The brine temperature, pressure and flow rate are 𝑇𝑏 = 130°𝐶, 𝑝𝑏 = 40𝑏𝑎𝑟 and �̇�𝑏 = 150𝑘𝑔/𝑠. The average environment temperature and pressure for 2016 are 𝑇𝑒𝑛𝑣
𝑎𝑣 2016 =10.85°𝐶 and 𝑝𝑒𝑛𝑣
𝑎𝑣 2016 = 1.01678𝑏𝑎𝑟. Some assumptions are made for the component efficiencies of the pump, motor, generator and fan: 𝜂𝑝 = 80%, 𝜂𝑚 = 98%, 𝜂𝑔 = 98% and 𝜂𝑓 = 60% [1]. The
Fig. 1: Schematic presentation of the standard
ORC, with indication of the most important
states.
-
fan efficiency includes both the mechanical and electrical efficiencies. The economic parameter
assumptions for the discount rate, the yearly electricity-price increase, the plant lifetime and the
plant availability are 𝑑𝑟 = 5%, 𝑑𝑒𝑙 = 1.25%/year, 𝐿 = 30years and 𝑁 = 98%, respectively. The average electricity price for 2016 is 𝑝𝑒𝑙
𝑎𝑣 2016 = 36.57𝐸𝑈𝑅/𝑀𝑊ℎ. Furthermore, the well pumps power consumption is 500kW and the well drilling costs are 15MEUR [29].
2.4. Working fluid
Isobutane (R600a) is chosen as the working fluid because of its low environmental impact [30],
good ORC performance for the considered brine conditions and the low cost of hydrocarbons [31].
The thermodynamic and environmental properties of Isobutane are summarized in Table 2.
Table 2: Thermodynamic and environmental properties of Isobutane (R600a) [30].
MW, g/mole 𝑇𝑐𝑟𝑖𝑡, °𝐶 𝑝𝑐𝑟𝑖𝑡, 𝑀𝑃𝑎 ODP GWP Isobutane (R600a) 58.12 134.66 3.63 0 20
3. Optimization methodology We have developed a two-step optimization methodology. In the first step we calculate the optimal
design of the shell-and-tube heat exchangers and the air-cooled condenser for assumed parameter
values (also assuming a fixed electricity price and fixed environment conditions). In the second step
we calculate the performance of an installed ORC in off-design operation. In this work, we focus on
the ORC off-design operation caused by changing environment conditions and we study the effect
on the net present value (NPV). The real NPV value depends on the electrical power output – which
depends on the (changing) environment conditions – on the one hand and on the fluctuating
electricity prices throughout the year, on the other hand.
3.1. Design optimization
Fig. 2 shows the flowchart of the design-optimization methodology. The input parameters and the
working fluid have been discussed in Section 2.3 and 2.4.
Fig. 2: Flowchart of the design optimization program.
The NPV is taken as the optimization objective since it takes into account the performance, the
component costs, the economics and the time value of money:
NPV = −Iwells − IORC + ∑ [Ẇnetpel(1+del)
iN 8760
106 − 0.025IORC
(1+dr)i]Li=1 [EUR2016] (1)
The operation and maintenance costs are estimated as 2.5% of the total ORC cost [32]. The
variables of the optimization problem and their bounds are shown in Table 3. The ORC cost IORC
-
and the net electrical power output Ẇnet depend on the values of the variables. The well costs Iwells and the economic parameters do not depend on the variables. The bounds on the variables related to
heat exchangers (shell diameter Dshell, tube diameter Dtube, tube pitch ptube, baffle cut Bc and length
between baffles Lbc) are based on the TEMA standards [13], the variable bounds related to the ACC
are based on the validity of the correlations of Yang [12]. Tt, Tevap and Tcond are the turbine inlet
temperature, the evaporator temperature and the condenser temperature, respectively; vair is the air
flow velocity. The operational constraints are chosen to ensure a proper ORC operation ( minimum
ΔTpinch=1°C) and the structural bound for the length of the ACC LACC is based on the report of
Zammit [33]. No constraint has been considered for the brine injection temperature Tb,inj.
Table 3: Variable bounds and operational & structural constraints of the optimization problem.
variables of the optimization process additional constraints
variable lower bound upper bound constraint lower bound upper bound
Tcond, °C Tenv min (Tb, Tupper) Dtube/Dshell, - 0 0.1
Tevap, °C Tenv min (Tb, Tupper) Tt – Tevap, °C 1 Tupper – Tenv
Tt, °C Tenv + 10 min (Tcrit, Tupper) Tevap – Tcond, °C 10 2 (Tupper – Tenv)
ε, - 0.01 0.9 Tb,inj °C 25 Tb
�̇�𝑤𝑓/�̇�𝑏, - 0.01 5 ΔTpinch, °C 1 100
Dshell, m 0.3 2 LACC, m 0 15
Dtube, mm 5 50
ptube/Dtube, - 1.2 2.5
Bc/Dshell, - 0.25 0.45
Lbc, m 0.3 5
Sfin, mm 1.14 3.04
Hfin, mm 14.25 23.75
vair, m/s 1.5 10
ntube, - 500 10000
The direct result of the design optimization problem are the heat exchanger design, the ACC design
and the optimal operation conditions corresponding to the highest NPV for the given parameter
values. From these results, other performance indicators like the net electrical power output, the
brine injection temperature, the size of the heat exchangers, the turbine and self-consumption power
and the component costs can be calculated.
The models have been implemented in Python [34], using the CasADi [35] optimization framework
and the IpOpt [36] non-linear solver. Fluid properties are calculated from the REFPROP 8.0
database [37].
3.2. Power optimization during off-design operation
Whereas the goal in the previous section was the optimal ORC design for given brine, environment
and economic conditions, here the goal is to optimize the revenues from an installed ORC. Due to
the changing environment conditions, the net electrical power output is different from the nominal
power. Combined with the fluctuating electricity prices this leads to changing revenues during the
plant operation. For the installed ORC we want to maximize the revenues, hence we want to
maximize the NPV over the plant lifetime. Therefore, the operating conditions (Tt, Tevap, Tcond,
�̇�𝑤𝑓/�̇�𝑏 and vair) are changed to maximize the electrical power output. Since now the total cost IORC of the installed ORC is fixed, the optimization objective (1) reduces to maximizing the net
electrical power output Ẇnet: max 𝑁𝑃𝑉 → max Ẇnet (2) The same optimization model is used as for the design optimization problem, however the variables
are reduced to the operational variables only and some extra constraints are imposed. The design
and size of the heat exchangers and ACC are fixed, and the turbine operation has to satisfy
Stodola’s Ellipse law in off-design [23].
-
Table 4 summarizes the variables and constraints of the off-design optimization problem1. The
direct results are the optimized operational variables and the value of the net electrical power output
for given brine, environment and economic parameters. We focus on the effect of the environment
conditions and electricity prices so only these values might be different from the values which were
used in the design optimization procedure (Section 3.1).
Table 4: Variable bounds and constraints of the off-design optimization problem.
variables of the optimization process additional constraints
variable lower bound upper bound constraint lower bound upper bound
Tcond, °C Tenv min (Tb, Tupper) Tt – Tevap, °C 1 Tupper – Tenv
Tevap, °C Tenv min (Tb, Tupper) Tevap – Tcond, °C 10 2 (Tupper – Tenv)
Tt, °C Tenv + 10 min (Tcrit, Tupper) Tb,inj °C 25 Tb
�̇�𝑤𝑓/�̇�𝑏, - 0.01 5 ΔTpinch, °C 0.75 100
ε, - 0.01 0.9 ΔPStodola, Pa -5 5
vair, m/s 1.5 10 LACC, m LACC,design LACC,design
AHEx, m² AHEx,design AHEx,design
Arecup, m² Arecup,design Arecup,design
4. Results for standard ORC
4.1. ORC design
In this step, we report on the results for the optimization of the design of the heat exchanger and the
air-cooled condenser. We consider the parameter values of Section 2.3 and Isobutane as a working
fluid. If we follow the flowchart of Fig. 2, we get the following ORC design:
1. Evaporator design: Dshell = 0.70m, Dtube = 5.98mm, pt = 1.2Dtube, Bc = 0.25DShell and Lbc = 2.35m;
2. ACC design: Sfin = 3.04mm, Hfin = 23.75mm and ntube = 714.57;
3. Operating conditions: Tt = 101.54°C, Tevap = 100.54°C, Tcond = 41.75°C, �̇�𝑤𝑓 = 0.54�̇�𝑏 and vair = 7.33m/s.
The design value for the isentropic turbine efficiency is 88.94%. The exergetic plant efficiency is
19.85%, whereas the cycle efficiency is 11.14%2. These values are rather low because the incentive
for building a well-performing and expensive ORC is low at low electricity prices (𝑝𝑒𝑙 =36.57𝐸𝑈𝑅/𝑀𝑊ℎ was considered). The net electrical power output is 2.46MW and the brine injection temperature is 82.09°C. The optimal ΔTpinch = 2.11°C, the heat transfer area of the
evaporator is AHEx = 1192.64m² and the length of the condenser is LACC = 15m. The total ORC cost
is 8.16MEUR from which 70% is allocated to the condenser and the total project cost including
well costs is 23.16MEUR. The specific costs are 9416 EUR2016/kWinstalled including well costs and
3318EUR2016/kWinstalled without well costs. The prospected 𝑁𝑃𝑉 = −12.09MEUR for the assumed parameter values of 𝑇𝑒𝑛𝑣 = 𝑇𝑒𝑛𝑣
𝑎𝑣 2016 = 10.85°𝐶 and 𝑝𝑒𝑙 = 𝑝𝑒𝑙𝑎𝑣 2016 = 36.57𝐸𝑈𝑅/𝑀𝑊ℎ. Note that
the project is economically unfeasible without any kind of feed-in tariff.
4.2. Hourly electricity prices and environment conditions for 2016
The real NPV is different from the estimated one in the design step due to changing environment
conditions and fluctuating electricity prices throughout the year. Fig. 3 shows hourly data for the
environment temperature [38] and the electricity price [39]. We consider data for Mol (Belgium) in
1 The ΔTpinch lower bound has been changed
with respect to the design stage (Table 3) to allow proper convergence.
2 Exergetic plant efficiency: ratio of the net electrical power output (incl. well pumps power and self-consumption by
ORC pump and fan) and the exergy content of the brine at the production state.
Energetic cycle efficiency: ratio of the mechanical turbine power minus the mechanical ORC pump power, and the heat
addition in the evaporator.
-
2016. The average environment temperature is 𝑇𝑒𝑛𝑣𝑎𝑣 2016 = 10.85°𝐶 and the average wholesale
electricity price is 𝑝𝑒𝑙𝑎𝑣 2016 = 36.57𝐸𝑈𝑅/𝑀𝑊ℎ.
Fig. 3: Hourly profiles for the environment temperature [38] and the electricity price [39] for Mol
in 2016. The dashed dotted lines indicate the average values.
4.3. Off-design operation
During operation, the goal is to maximize the net electrical power output at every moment in time
for the designed ORC. In contrast to the design optimization step (first step of the optimization
procedure – Section 4.1) where we used a constant value for the electricity price and for the
environment conditions, in this section we take into account real hourly weather data and electricity
prices. However, we want to reduce the number of data points to speed up the optimization
procedure without losing too much accuracy. Since the net electrical power output of an installed
ORC depends on the environment temperature, our data reduction is based on the monotonic
duration curve of the environment temperature. The original monotonic temperature duration curve
is shown on the left-hand side of Fig. 4 and results from the hourly data which were given in Fig. 3.
We reduce the number of data points to 100 by considering the temperatures at [0.5, 1.5, …, 99.5%]
of the original temperature duration curve. Thereby we reduce the peaks – which has a very small
impact on the overall result – and we still have satisfying accuracy. The resulting environment
temperatures which we use in the simulations are given on the right-hand side of Fig. 4.
Fig. 4: Left: Original temperature duration curve of the environment temperature (red dashes:
spline approximation) with 8784 data points, derived from the hourly environment temperature
data given in Fig. 3. Right: used temperature duration curve consisting of 100 data points.
For the real environment temperature during all 8784 operating hours, we check what the closest
value of Tenv on the reduced temperature duration curve is at that time. We average the electricity
prices for moments with that environment temperature and hence become the averaged electricity
price corresponding to every data point. The averaged electricity prices are given on the left-hand
𝑇𝑒𝑛𝑣𝑚𝑎𝑥 = 33.19°𝐶
𝑇𝑒𝑛𝑣𝑚𝑖𝑛 = −8.13°𝐶
𝑇𝑒𝑛𝑣𝑚𝑎𝑥 = 33.19°𝐶
𝑇𝑒𝑛𝑣𝑚𝑖𝑛 = −8.13°𝐶
𝑇𝑒𝑛𝑣𝑚𝑎𝑥 = 29.07°𝐶
𝑇𝑒𝑛𝑣𝑚𝑖𝑛 = −4.28°𝐶
-
side of Fig. 5 and the price is generally higher at low values of the environment temperatures, which
can be expected. The net electrical power output only depends on the environment temperature, so
for every value of the reduced temperature duration curve (right-hand side of Fig. 4) we optimize
the operating conditions towards maximal net electrical power output. The resulting net electrical
power output for every data point is shown on the right-hand side of Fig. 5.
Fig. 5: Left: Average electricity price for all data points of the reduced temperature duration curve
(right-hand side of Fig. 4). Right: Optimized electrical power output for every data point on the
reduced temperature duration curve (right-hand side of Fig. 4).
The real NPV is calculated as follows:
NPV = −Iwells − IORC + ∑ [∑ [Ẇnet,jpel,j𝑠𝑗]
100𝑗=1 (1+del)
iN 8760
106 − 0.025IORC
(1+dr)i]Li=1 [EUR2016] (3)
sj is the share of the year that a certain value of the environment temperature, out of the 100
considered data points (right-hand side of Fig. 4), occurs. pel,j is the corresponding averaged
electricity price (left-hand side of Fig. 5). We assume the same profiles for the environment
conditions and for the electricity price in every year of the plant lifetime. The real 𝑁𝑃𝑉 =−11.74MEUR, which is different from the estimated NPV in the design stage. This is due to the changing net electrical power output corresponding to changing environment temperatures
(opposite correlation) on the one hand, and the fluctuating electricity prices on the other hand. The
off-design results are better than the design results. Note that we used here 30 times the same annual
profiles for the environment temperature and electricity price.
Note on the accuracy: The electrical power output Ẇnet depends on the environment temperature Tenv. By reducing the number of points to 100, we do not account for the highest and the lowest value of the environment temperature (see Fig. 4). Within one interval on the reduced temperature
duration curve (right-hand panel of Fig. 4), the difference in net electrical power output is smaller
than 1.5%, and the higher and lower values compensate each other. However, the largest errors
occur at the lowest and the highest values of 𝑇𝑒𝑛𝑣. Instead of the correct minimum and maximum values 𝑇𝑒𝑛𝑣
𝑚𝑖𝑛 = −8.13°𝐶 and 𝑇𝑒𝑛𝑣𝑚𝑎𝑥 = 33.19°𝐶, we use the values 𝑇𝑒𝑛𝑣
𝑚𝑖𝑛 = −4.28°𝐶 and 𝑇𝑒𝑛𝑣𝑚𝑎𝑥 =
29.07°𝐶. The corresponding electrical power outputs are Ẇnet = 3.53𝑀𝑊 instead of Ẇnet =3.81𝑀𝑊 for 𝑇𝑒𝑛𝑣
𝑚𝑖𝑛, and Ẇnet = 1.40𝑀𝑊 instead of Ẇnet = 1.19𝑀𝑊 for 𝑇𝑒𝑛𝑣𝑚𝑎𝑥. So, the real electrical
power output at the lowest environment temperature is ∆Ẇnet = 3.81 − 3.53 = 0.28𝑀𝑊 (or 7.93%) higher than the value we consider in our simulations, and for the highest environmental
temperature the real electrical power output is ∆Ẇnet = 1.40 − 1.19 = 0.21𝑀𝑊 (or 15%) lower than the value we consider. 𝑇𝑒𝑛𝑣
𝑚𝑖𝑛 = −8.13°𝐶 occurs during an hour with a corresponding electricity price of 𝑝𝑒𝑙 = 65.61𝐸𝑈𝑅/𝑀𝑊ℎ and the corresponding electricity price at 𝑇𝑒𝑛𝑣
𝑚𝑎𝑥 = 33.19°𝐶 is 𝑝𝑒𝑙 = 34.55𝐸𝑈𝑅/𝑀𝑊ℎ (see Fig. 3). The real income is ∆Ẇnet𝑝𝑒𝑙=18.37EUR higher for the hour with the lowest environment temperature and 7.26EUR lower for the hour with the highest
environment temperature than what we consider in our simulations (by considering only the values
of the right-hand side panel of Fig. 4). So, our results are a bit conservative.
-
5. Discussion: Parameter assumptions in the design stage
5.1. Electricity price assumption The revenues of the power plant depend on the electricity prices. For higher electricity prices, a
better and more expensive ORC can be installed which leads to a higher net electrical power output
and a higher NPV. This is illustrated in Fig. 6. The figure on the left-hand side corresponds to the
design stage where a certain constant value for the electricity price is assumed. The ORC is
designed for this electricity price assumption. If the electricity price would be constant throughout
the year, the NPV of the left-hand side figure would be the real NPV. We can see that the
geothermal power plant becomes feasible (NVP=0) for electricity prices around 65EUR/MWh.
However, the real electricity prices were given in Fig. 3.
The right-hand side figure shows the real NPV, accounting for off-design, for an installed ORC
with the assumed constant electricity price in the design stage on the x-axis. The highest NPV is
reached for an ORC design based on the assumption of 𝑝𝑒𝑙 = 𝑝𝑒𝑙𝑎𝑣 2016 = 36.57𝐸𝑈𝑅/𝑀𝑊ℎ, the
average price for electricity over the year. However, in the design stage the average electricity price
is not known. But we see that in the close environment around 𝑝𝑒𝑙𝑎𝑣 2016 – say for 𝑝𝑒𝑙 = 30 −
60𝐸𝑈𝑅/𝑀𝑊ℎ (indicated by the dotted box) – the real NPV is almost equally high. However, for an electricity price assumption which was too high/too low, the real NPV might be significantly lower.
Furthermore, from the right-hand side figure of Fig. 6 follows that the NPV for the recuperated
ORC (orange line) and the standard ORC (blue line) are almost equal: 𝑁𝑃𝑉𝑟𝑒𝑐𝑢𝑝𝑒𝑟𝑎𝑡𝑜𝑟 =−11.52 𝑀𝐸𝑈𝑅 and 𝑁𝑃𝑉𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 = −11.74𝑀𝐸𝑈𝑅. In general, a cheaper cooling system can be installed in the recuperated cycle due to the internal heat recuperation. The total ORC cost is
slightly higher for the recuperated ORC – partly due to the extra heat exchanger – but also the net
electrical power output is higher than for the standard ORC.
Fig. 6: Left: NPV if 𝑝𝑒𝑙would be constant throughout the year (assumption in the design stage). The blue and orange lines indicate the standard and recuperated ORC, respectively, the dashed green
line is the difference in NPV between the recuperated and the standard ORC and the dashed-dotted
black line is the line for ΔNPV=0. Right: Real NPV accounting for off-design (Fig. 3) as a function
of the electricity price assumed in the design stage of the ORC. 𝑇𝑒𝑛𝑣 = 𝑇𝑒𝑛𝑣𝑎𝑣 2016 = 10.85°𝐶.
5.2. Environment temperature assumption
The ORC revenues also depend on the environment temperature. For a higher environment
temperature, the net electrical power output is lower, which is shown on the left-hand side of Fig. 7.
The left-hand side panel shows the NPV for various environment temperatures according to
different design points, but for each design assuming that the real environment temperature remains
constant over the year.
The right-hand side panel takes off-design into account and shows the real NPV, accounting for the
changing environment conditions. The NPV is presented as a function of the environment
-
temperature for which the ORC was designed. The real NPV is maximal for a temperature
assumption in the design stage of 𝑇𝑒𝑛𝑣 = 14°𝐶 and is 𝑁𝑃𝑉𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 = −11.70𝑀𝐸𝑈𝑅 for the
standard cycle and 𝑁𝑃𝑉𝑟𝑒𝑐𝑢𝑝𝑒𝑟𝑎𝑡𝑜𝑟 = −11.47𝑀𝐸𝑈𝑅 for the recuperated ORC. We see that the optimal design temperature 𝑇𝑒𝑛𝑣 = 14°𝐶 is different from the average environment temperature 𝑇𝑒𝑛𝑣
𝑎𝑣 2016 = 10.85°𝐶. If we design the ORC for a higher environment temperature, we benefit from the higher electrical power output which can be reached at moments of lower environment
temperatures. However, the real NPV only weakly depends on the environment temperature
assumption in the design stage.
Fig. 7: Left: NPV if 𝑇𝑒𝑛𝑣 would be constant throughout the year (assumption in the design stage). Right: Real NPV accounting for off-design (Fig. 3) as a function of the environment temperature
assumed in the design stage of the ORC. 𝑝𝑒𝑙 = 𝑝𝑒𝑙𝑎𝑣 2016 = 36.57𝐸𝑈𝑅/𝑀𝑊ℎ. The blue and orange
lines indicate the standard and recuperated ORC, respectively, the dashed green line is the
difference in NPV between the recuperated and the standard ORC.
6. Conclusions In this work, we have presented a two-step optimization methodology for calculating the optimal
(heat exchanger and air-cooled condenser) design of a binary geothermal ORC, on the one hand,
and for calculating the optimal operating conditions to reach maximal electrical power output of an
installed ORC during off-design, on the other hand. We use the same models for the design and off-
design optimization calculations. However, a different objective (NPV versus net electrical power)
is imposed and the constraints are slightly different. We have calculated the optimal design for a
binary geothermal plant based on the geological conditions of the Balmatt site (Mol, Belgium). In a
second step we have analyzed the performance of the designed power plant during real operation.
Therefore, we consider hourly data for the environment conditions and electricity prices for Mol
(Belgium) in 2016. In real operation, the plant mostly operates in off-design conditions due to
changing environment temperatures and the electrical power output is maximized at every moment.
From the results follows that the electricity price assumption in the ORC design stage might have a
big impact on the real revenues of the power plant. However, for an electricity price assumption in
the design stage of the project close enough to the (future) real average price, the real NPV will be
close to its maximum possible value. The environment temperature assumption in the design stage
of the ORC has a small impact on the real operation and revenues of the ORC. In general, the
recuperated ORC has slightly higher NPV than the basic cycle, but the difference is small (~2%).
Acknowledgments This project receives the support of the European Union, the European Regional Development
Fund ERDF, Flanders Innovation & Entrepreneurship and the Province of Limburg.
-
References [1] D. Walraven, B. Laenen, and W. D’haeseleer, “Economic system optimization of air-cooled
organic Rankine cycles powered by low-temperature geothermal heat sources,” Energy, vol.
80, pp. 104–113, 2015.
[2] K. Braimakis and S. Karellas, “Integrated thermoeconomic optimization of standard and
regenerative ORC for different heat source types and capacities,” Energy, vol. 121, pp. 570–
598, 2017.
[3] C. Zhang, C. Liu, S. Wang, X. Xu, and Q. Li, “Thermo-economic comparison of subcritical
organic Rankine cycle based on different heat exchanger configurations,” Energy, vol. 123,
pp. 728–741, Mar. 2017.
[4] J. Bao and L. Zhao, “A review of working fluid and expander selections for organic Rankine
cycle,” Renew. Sustain. Energy Rev., vol. 24, pp. 325–342, 2013.
[5] D. Fiaschi, G. Manfrida, E. Rogai, and L. Talluri, “Exergoeconomic analysis and comparison
between ORC and Kalina cycles to exploit low and medium-high temperature heat from two
different geothermal sites,” Energy Convers. Manag., vol. 154, pp. 503–516, Dec. 2017.
[6] D. Hu, S. Li, Y. Zheng, J. Wang, and Y. Dai, “Preliminary design and off-design
performance analysis of an Organic Rankine Cycle for geothermal sources,” Energy
Convers. Manag., vol. 96, pp. 175–187, May 2015.
[7] D. Hu, Y. Zheng, Y. Wu, S. Li, and Y. Dai, “Off-design performance comparison of an
organic Rankine cycle under different control strategies,” Appl. Energy, vol. 156, pp. 268–
279, Oct. 2015.
[8] G. Manente, A. Toffolo, A. Lazzaretto, and M. Paci, “An Organic Rankine Cycle off-design
model for the search of the optimal control strategy,” Energy, vol. 58, pp. 97–106, Sep. 2013.
[9] M. Usman, M. Imran, Y. Yang, D. H. Lee, and B.-S. Park, “Thermo-economic comparison of
air-cooled and cooling tower based Organic Rankine Cycle (ORC) with R245fa and
R1233zde as candidate working fluids for different geographical climate conditions,”
Energy, vol. 123, pp. 353–366, Mar. 2017.
[10] F. Calise, C. Capuozzo, A. Carotenuto, and L. Vanoli, “Thermoeconomic analysis and off-
design performance of an organic Rankine cycle powered by medium-temperature heat
sources,” Sol. Energy, vol. 103, pp. 595–609, May 2014.
[11] D. Walraven, B. Laenen, and W. D’haeseleer, “Optimum configuration of shell-and-tube
heat exchangers for the use in low-temperature organic Rankine cycles,” Energy Convers.
Manag., vol. 83, pp. 177–187, 2014.
[12] L. Yang, H. Tan, X. Du, and Y. Yang, “Thermal-flow characteristics of the new wave-finned
flat tube bundles in air-cooled condensers,”Int. J. Therm. Sci.,vol. 53,pp.166–174, Mar. 2012.
[13] TEMA, “Standards of the tubular exchanger manufacturers association,” Eight edition, 1999.
[Online]. Available: http://www.funke.de/pdf/zertifikate/tema.pdf. [Accessed: 31-Aug-2017].
[14] G. F. Hewitt, Hemisphere Handbook of Heat Exchanger Design. New York: Hemisphere
Publishing Corporation, 1990.
[15] R. K. Shah and D. P. Sekulic, Fundamentals of Heat Exchanger Design. John Wiley and
Sons, Inc., 2003.
[16] M. S. Bhatti and R. K. Shah, “Turbulent and transition convective heat transfer in ducts,” in
Handbook of Single-Phase Convective Heat Transfer, S. Kakaç, R. K. Shah, and W. Aung,
Eds. New York: Wiley, 1987.
[17] B. S. Petukhov and V. N. Popov, “Theoretical calculation of heat exchange and frictional
resistance in turbulent flow in tubes of an incompressible fluid with variable physical
properties,” in High Temperature 1, 1963, pp. 69–83.
[18] G. Gnielinski, “New equation for heat and mass transfer in turbulent pipe and channel flow,”
-
Int. Chem. Eng., vol. 16, pp. 359–368, 1976.
[19] A. Premoli, D. DiFrancesco, and A. Prina, “A dimensionless correlation for the
determination of the density of two-phase mictures,” Termotec., vol. 25, no. 1, pp. 17–26,
1971.
[20] D. Chisholm, “Pressure gradients due to friction during flow of evaporating two-phase
mixtures in smooth tubes and channels,” Int. J. Heat Mass Transf., vol. 16, no. 2, pp. 347–
358, 1973.
[21] M. Shah, “An improved and extended general correlation for heat transfer during
condensation in plain tubes,” HVAC&R Res., vol. 15, no. 5, pp. 889–913, 2009.
[22] E. Macchi and A. Perdichizzi, “Efficiency predictions for axial-flow turbines operating with
nonconventional fluids,” J. Eng. Power, vol. 103, no. 4, pp. 718–724, 1981.
[23] D. H. Cooke, “On Prediction of Off-Design Multistage Turbine Pressures by Stodola’s
Ellipse,” J. Eng. Gas Turbines Power, 1985.
[24] K. R. Keeley, “A theoretical investigation of the part-load characteristics of LP steam turbine
stages,” Memo. RD/L/ES0817/M88, Cent. Electr. Gener. Board, 1988.
[25] S. Van Erdeweghe, Van Bael, Johan, B. Laenen, and W. D’haeseleer, “Feasibility study of a
low-temperature geothermal power plant for multiple economic scenarios,” in 30th
International Conference on Efficiency, Cost, Optimization, Simulation and Environmental
Impact of Energy Systems (ECOS), 2017.
[26] R. Smith, Chemical Process Design and Integration. John Wiley and Sons, Inc., 2005.
[27] A. Bejan, G. Tsatsaronis, and M. Moran, Thermal Design and Optimization. New York:
Wiley, 1996.
[28] S. Bos and B. Laenen, “Development of the first deep geothermal doublet in the Campine
Basin of Belgium,” Eur. Geol., vol. 43, pp. 16–20, 2017.
[29] ITG, “Informationsportal Tiefe Geothermie,” Projekte Tiefe Geothermie, 2017. [Online].
Available: www.tiefegeothermie.de/projekte. [Accessed: 10-May-2017].
[30] J. M. Calm and G. C. Hourahan, “Physical, Safety and Environmental Data for Current and
Alternative Refrigerants,” in International Congress of Refrigeration, 2011.
[31] E. Macchi and M. Astolfi, Organic Rankine Cycle (ORC) Power Systems - Technologies and
Applications. Elsevier, 2017.
[32] IEA, “Technology Roadmap - Geothermal Heat and Power,” 2011. [Online]. Available:
https://www.iea.org/newsroomandevents/pressreleases/2011/june/how-to-achieve-at-least-a-
tenfold-increase-in-supply-of-geothermal-power-and-hea.html. [Accessed: 10-May-2017].
[33] K. Zammit, “Air-cooled condenser Design Specification and Operation Guidelines,”
California, 2005.
[34] G. van Rossum, “Python Tutorial, Technical Report CS-R9526,” Amsterdam, 2.7.10, 1995.
[35] J. Andersson, J. Åkessona, F. Casella, and M. Diehl, “Integration of CasADi and
JModelica.org,” Proc. 8th Int. Model. Conf., pp. 218–231, 2011.
[36] A. Wächter and L. T. Biegler, “On the implementation of an interior-point filter line-search
algorithm for large-scale nonlinear programming,” Math. Program., vol. 106, no. 1, pp. 25–
57, Mar. 2006.
[37] E. W. Lemmon, M. L. Huber, and M. O. McLinden, “REFPROP - Reference Fluid
Thermodynamic and Transport Properties. NIST Standard Reference Database 23.” 2007.
[38] The Dark Sky Company, “Dark Sky API,” Forecast Request, 2012. [Online]. Available:
www.darksky.net. [Accessed: 31-Aug-2017].
[39] ENTSOE, “Central collection and publication of electricity generation, transportation and
consumption data and information for the pan-European market,” 2016. [Online]. Available:
https://transparency.entsoe.eu/. [Accessed: 15-Dec-2016].