design of road culverts for fish passages

Upload: cio-cio

Post on 30-May-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Design of Road Culverts for Fish Passages

    1/111

    Design of Road Culverts for Fish Passage

    2003

  • 8/14/2019 Design of Road Culverts for Fish Passages

    2/111

    Design of Road Culverts for Fish Passage 1

    Design of Road Culverts for Fish Passage

    Preface ..............................................................................................................................................................................................................................................................................4

    Introduction ..............................................................................................................................................................................................................................................................................8

    Chapter 1 Habitat Issues at Road Crossings..............................................................................................................................................................................................9

    Chapter 2 Fish Barriers at Culverts ..................................................................................................................................................................................................................13

    Chapter 3 Culvert Design for Fish Passage ..............................................................................................................................................................................................14

    Chapter 4 No-Slope Design Option..............................................................................................................................................................................................................17

    Chapter 5 Hydraulic Design Option...............................................................................................................................................................................................................19

    Chapter 6 Stream-Simulation Design Option .......................................................................................................................................................................................29

    Chapter 7 Channel Profile.........................................................................................................................................................................................................................................40

    Chapter 8 High-Flow Capacity .............................................................................................................................................................................................................................48

    Chapter 9 Tide Gates and Flood Gates ......................................................................................................................................................................................................49

    Chapter 10 Fishways...........................................................................................................................................................................................................................................................53

    References ...........................................................................................................................................................................................................................................................................54

    Additional Resources.....................................................................................................................................................................................................................................................................55

    Appendix A Glossary...........................................................................................................................................................................................................................................................56

    Appendix B Washington Culvert Regulation..............................................................................................................................................................................................59

    Appendix C Design Flows for Ungauged Streams.................................................................................................................................................................................63

    Appendix D Hydraulics of Baffles ............................................................................................................................................................................................................................72

    Appendix E Design of Roughened Channels.............................................................................................................................................................................................76

    Appendix F Summary Forms for Fish-Passage Design Data .......................................................................................................................................................86

    Appendix G Construction Unit Costs................................................................................................................................................................................................................99

    Appendix H Measuring Channel-Bed Width............................................................................................................................................................................................100

    Appendix I Sample Design Sketches..............................................................................................................................................................................................................103

    Appendix J Washington Department of Fish and Wildlife Contact Information ..............................................................................................110

  • 8/14/2019 Design of Road Culverts for Fish Passages

    3/111

    Design of Road Culverts for Fish Passage 2

    Updates and Feedback

    Design of Road Culverts for Fish Passage is a work in progress. It was first published in 1999, and it has beenupdated several times since then. We welcome comments and ideas that would make the contents more useful.A summary of updates is available online at the Washington Department of Fish and Wildlife web page,www.wa.gov/wdfw/hab/engineer/cm/toc.htm. Comments or ideas for the guideline can be e-mailed to:[email protected]; or mailed to:

    Chief Habitat EngineerWashington Department of Fish and Wildlife600 Capitol Way N.Olympia, WA 98501-1091

  • 8/14/2019 Design of Road Culverts for Fish Passages

    4/111

    Design of Road Culverts for Fish Passage 3

    Acknowledgments

    This guideline was produced with the assistance of many individuals.Many thanks to reviewers who provided insight, advice and suggestions during its preparation.

    Principal Author

    Ken Bates, P.E., Chief Environmental Engineer, Washington Department of Fish and Wildlife

    Contributing Authors

    Bob Barnard, P.E., Washington Department of Fish and WildlifeBruce Heiner, P.E., Washington Department of Fish and WildlifeJ. Patrick Klavas, P.E., Washington Department of Fish and WildlifePatrick D. Powers, P.E., Washington Department of Fish and Wildlife

    Reviewers and Technical Assistance

    Thomas J. Burns, Washington Department of Fish and WildlifeKay Saldi-Caromile, P.E., Washington Department of Fish and WildlifeMike Chamblin, Washington Department of Fish and WildlifePhillip Jensen, P.E., Washington Department of Fish and WildlifeRich Johnson, Washington Department of Fish and WildlifeDonald C. Ponder, P.E., Washington Department of Fish and WildlifePaul Sekulich; Washington Department of Fish and WildlifePadraic Smith, P.E., Washington Department of Fish and WildlifeTony Whiley, P.E., Washington Department of Fish and Wildlife

    Technical Editing

    The Demich Group

    Graphic Design

    Ellis Paguirigan Designs

    Funding Provided By

    Washington Department of Fish and WildlifeWashington State Department of Natural Resources - Jobs for the Environment ProgramWashington State Department of TransportationWashington State Salmon Recovery Funding BoardU.S. Fish and Wildlife Service National Conservation Training Center

  • 8/14/2019 Design of Road Culverts for Fish Passages

    5/111

  • 8/14/2019 Design of Road Culverts for Fish Passages

    6/111

    Design of Road Culverts for Fish Passage 5

    To carry out such a mission, the program is designedto meet the following objectives:

    make the expertise of professional resourcemanagers available to a wide variety oforganizations and citizens who are seekingassistance in habitat protection andrestoration activities;

    streamline local, state and federal regulatoryreview of activities involving aquaticenvironments by providing guidelines basedon best available science;

    provide a scientific basis for any future changesto current local policies or activities associatedwith aquatic resource in the state; and

    maintain ongoing reviews and updatesto the Aquatic Habitat Guidelines to reflectexperience and emerging scienceand technical practice.

    Guiding Principles

    The Aquatic Habitat Guidelines Guiding Principlessummarize current, scientific understanding abouthow ecosystems work, and they reflect currentresource-agency policy and technical approachesto protect ecosystem functions. Documenting thisscientific and technical understanding and policy willenable managers and project proponents to assess theeffectiveness of the Aquatic Habitat Guidelines in theirefforts to protect and restore salmonid habitats as wellas other aquatic and riparian habitats. As scientificunderstanding improves through time, these guidelineswill be updated to reflect the evolution of thought.

    The guiding principles are organized from general

    concepts to topical statements. They weredeveloped by the Aquatic Habitat GuidelinesSteering Committee, whose membership includesthe Washington Department of Fish and Wildlife,Washington State Department of Transportationand the Washington Department Ecology. Someof the principles were taken directly or expandedfrom other planning documents such as the WildSalmonid Policy (Washington Department of Fishand Wildlife, 1997), the Statewide Strategy toRecover Salmon (State of Washington, 1999) andCoastal Salmon Conservation: Working Guidancefor Comprehensive Salmon Restoration Initiativeson the Pacific Coast (National Marine Fisheries Service,

    1996). Links to the websites containing thesedocuments can be found at Links and Referenceson the Washington Department of Fish and Wildlifeswebsite at www.wa.gov/wdfw/hab/ahg.

    Guiding Principles for GeneralEcosystem Function:

    1. Ecological processes create and maintain habitatfunction. These processes include:

    Geomorphic processes theinteraction of water, sediment and wood

    that creates channel and shorelinestructure. Geomorphic processes includebank and bed erosion, channel migrationand evolution, sedimentation, debrisinfluences, erosion, accretion, sedimenttransport and fire.

    Biological processes (e.g., nutrientcycling; species interactions; riparian andupland vegetation dynamics; and species-mediated, habitat-forming processes suchas beaver activity).

    Salmon and other aquatic organisms have evolvedand adapted to use the habitats created by theseprocesses. The long-term survival of naturally

    occurring populations of these species dependson the continuation of these processes.

    2. Ecological processes create and sustain a suite ofecosystem characteristics and functions thatinclude:

    ecosystem complexity, diversityand change;

    ecological connectivity; riparian interactions; floodplain connectivity; species diversity, adaptation

    and survival; water quality and water quantity; and invertebrate production and sustained

    food-web function.

    3. These characteristics and functions have biologicalvalue as well as economic, social, cultural,educational and recreational values.

    4. Because these characteristics and functions varyacross and within watersheds, the use of localwatershed information in planning and design willoften lead to less risk of adverse project impacts.Natural processes that are protected andrestored will minimize risk and providesustainability to ecosystem functions.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    7/111

    Design of Road Culverts for Fish Passage 6

    This principle is paraphrased from the Stateof Washington (1999):

    a. Maintain and restore the freedomof rivers and streams to move andchange, especially during floods.

    b. Allow time for natural regenerativeprocesses to occur and providerecovery of river and stream integrity.

    c. Protect the natural diversity ofspecies and restore the naturaldiversity of habitats within riverchannels and riparian zones.

    d. Support and foster habitat connectivity.e. Tailor actions locally and to the

    whole watershed in the propersequence of time and place. Matchthe system's potential and long-term

    human commitment to stewardshipof the system.

    The principle is also paraphrased from theNational Marine Fisheries Service (1996):

    a. To ensure no net loss of habitatfunctions and to enable naturalprocesses to occur unimpeded,actions should benefit ecologicalfunctions. Actions that adverselyaffect habitat should be avoided.

    b. Maintain habitats required for

    salmonids during all life stages fromembryos and alevins through adults.

    c. Maintain a well-dispersed networkof high-quality refugia to serve ascenters of population expansion.

    d. Maintain connectivity between high-quality habitats to allow forreinvasion and population expansion.

    e. Maintain genetic diversity.

    General Guiding Principles for ProjectPlanning and Implementation:

    1. A holistic approach to project planning employsecologically relevant units of management, suchas watersheds.

    2. Our limited understanding of ecological

    processes and engineered solutions is addressedby using the best available science and erringon the side of caution in project management,design, timing and construction.

    3. A holistic approach to project planningrecognizes and maintains geomorphic processes(e.g., channel migration, channel evolution,hydrologic changes, erosion, sedimentation,accretion and debris influences).

    4. Appropriate uses of riparian, shoreline andfloodplain systems through responsible land-usepractices can maintain natural processes and avoid

    cumulative, adverse effects.

    5. A holistic approach to compensatory mitigationand restoration is desirable; such an approachis based on local watershed conditions,and it strives to maintain or restore historical,ecological functions.

    6. Compensatory mitigation for adverse impactshas risk and uncertainty of success. To minimizesuch risk and uncertainty, adverse impacts are firstavoided and then minimized. Unavoidable, adverseimpacts are addressed by compensating for losses.

    7. Complete compensatory mitigation includesconsideration of the project impacts over time(which usually extends beyond the completionof the project) and across the landscape(which often extends beyond the boundariesof the project).

    8. Appropriate operating and maintenanceprocedures are necessary to ensure that projectobjectives are fulfilled and adverse environmentalimpacts are minimized.

    9. Monitoring and adaptive management are criticalcomponents of restoration, mitigationand management activities.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    8/111

    Design of Road Culverts for Fish Passage 7

    Guiding Principles for Water Crossings:

    1. Culverts result in permanent, direct lossof instream and riparian habitat.

    2. Installation and maintenance of water crossingsthat confine or constrict the channel or floodplainwill break ecological connectivity, alter channel

    processes and change adjacent channel characterand shape by affecting the movement of debris,sediment, channel migration, flood waters,and aquatic and terrestrial organisms.

    3. Water crossings may create an entry pointfor road-runoff pollutants.

    4. Fish passage can be hindered or blockedat water crossings.

    5. Water crossings increase the risk of damage to thedownstream habitat due to water crossing failure.

    6. Cumulative impacts and risks of water crossingscan be avoided or minimized by consolidatingwater crossings; employing full-span bridges,by simulating a natural channel through culverts;or removing water crossings. Access solutionsthat do not require water crossings are preferred.

    It is our nature as human beings to live, workand recreate along and adjacent to waterways,whether freshwater or marine. Our lives and historiesare inextricably linked to water. How we affect thosewaterways has long-term survival consequencesnot only for fish and wildlife, but for humanity.The Aquatic Habitats Guidelines Program is intended

    to help balance mans need to protect lifeand livelihood with the need to protect and restorevaluable habitat for fish, for wildlife and for ourselves.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    9/111

    Design of Road Culverts for Fish Passage 8

    Introduction

    Design of Road Culverts for Fish Passage serves as guidefor property owners and engineers who are designingpermanent road-crossing culverts to facilitate upstreamfish migration. It provides guidance for projectsinvolving new culvert construction as well as retrofittingor replacing existing culverts. The designer will needto have a working knowledge of hydraulic engineering,hydrology and soils/structural engineering to accomplishan appropriate design.

    Formal fish ladders may be required as a retrofitat some culvert sites to provide passage. The designof fish ladders is beyond the scope of this guideline,though there is a brief description of some basicdesign concepts included here. An engineer withexpertise in fish passage should be consultedfor additional assistance for the design of fish ladders.

    Design of Road Culverts for Fish Passage lays out

    the consecutive design steps most likely to be requiredin a culvert project. A form describing the dataneeded for the design and its evaluation is providedin Appendix F, Summary Forms for Fish-Passage DesignData. Explanations and definitions of terms describingchannel, hydrology and data requirements can alsobe found in Appendix F.

    Before using this guideline, great care should betaken to determine whether a culvert is a suitablesolution for providing fish passage at the particularsite in question. Indeed, environmentalcircumstances other than fish passage may makeit impossible to obtain a permit to install a culvert.

    The Washington Department of Fish and Wildlifeprefers construction of a bridge over installationof a culvert in order to minimize risk of impactsto fish and habitat. Wherever a roadway crossesa stream, it creates some level of risk to fishpassage, water quality or specific aquatic or riparianhabitats. Generally, the risks increase the morethe roadway confines and constricts the channeland floodplain. Any and all alternatives shouldbe investigated to minimize the number of siteswhere a roadway crosses a stream, includingdesigning road alignments to avoid crossings,consolidating crossings and using temporarycrossing structures for short-term needs.

    Though this guideline focuses on fish passage, otherhabitat and ecological considerations are also requiredin the siting and design of road-crossing structures suchas culverts. These considerations are essential to theprotection of fish and habitat, and should be addressedfirst in the design of a road crossing. Requirementsaddressing these considerations are outlined in Chapter1, Habitat Issues at Road Crossings. The WashingtonDepartment of Fish and Wildlife's Area Habitat Biologistin the area where your project is located is the finalauthority for Hydraulic Project Approval, so be sureto make contact early on for information on fish passageand other environmental issues that go beyond fishpassage (see Appendix J, Washington Department of Fishand Wildlife Contact Information).

    For information about the inventory of culvertsor the prioritization of culvert barrier remedies, referto the Fish Passage Barrier Assessment and Prioritization

    Manual, published by the Washington Departmentof Fish and Wildlife (1998).

    The design of new or retrofit culverts must bein compliance with Washington Department of Fishand Wildlife fish-passage criteria as defined by WAC220-110-070 (see Appendix B, Washington CulvertRegulation). The information contained in thispublication is the most current guidancefor construction and retrofit of culverts for fishpassage in Washington State. Recommendationsin this publication vary somewhat from WAC 220-110-070 but do not conflict with it. Design of RoadCulverts for Fish Passage is intended to clarify

    the regulation and provide up-to-date guidanceand application of the regulation across a broaderrange of fish-passage projects, including steep culverts.These guidelines can be applied as provided for in WAC220-110-032, Modification of technical provisions.Information gathered, as well as conceptsand guidance developed for this publication willbe incorporated into any future review and updateof WAC 220-110-070.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    10/111

    Design of Road Culverts for Fish Passage 9

    Chapter 1 Habitat Issues at Road Crossings

    The very presence of a culvert has an impact onstream habitat, even when fish are able to migratethrough it successfully. These impacts are oftenassociated with the culvert itself, but they can alsobe associated with the channel modificationsnecessary to install or retrofit a culvert intendedto faci litate fish passage. Upstream and downstreamhydraulic effects of the culvert can have an impact aswell. There are, for example, often habitat lossesassociated with steepening a channel to achieve fishpassage. Whats more, though fish-passage criteriaapply only to fish-bearing streams, other environmentalfactors apply at all crossings. For questions abouthabitat issues, contact the Washington Departmentof Fish and Wildlife's Area Habitat Biologist (seeAppendix J, Washington Department of Fish and WildlifeContact Information).

    Because the impact to stream habitat can be

    significant, the best option for roadway design is toavoid or minimize the number of stream crossingsneeded. However, this is not always feasible, so otheroptions must be considered that will allow the streamto cross the road. Figure 1-1 presents a generalizedapproach to selecting road-crossing options. As youcan see, it explores options other than permanentculverts and addresses habitat issues that may arisebefore considering the formal culvert-design process.

    A generalized approach to selecting road-crossing options.

    Once the culvert option has been selected, anumber of concerns must be taken into accountas design begins. These concerns may dictatethe siting, sizing and design of culverts and/or fishpassage improvements:

    direct habitat loss, water quality, upstream and downstream channel impacts, ecological connectivity, channel maintenance, construction impacts, and risk of culvert failure.

    Direct Habitat Loss

    Salmonid habitat includes all areas of the aquatic

    environment where the fish spawn, grow, feed andmigrate. Culvert installations require some magnitudeof construction activity within the stream channel, andthe culvert itself replaces native streambed materialand diversity with the culvert structure.

    Spawning Habitat

    Each species of salmon and trout require specificspawning conditions related to the water velocity,depth, substrate size, gradient, accessibility and space.All salmonids require cool, clean water in whichto spawn. Most salmonid spawning occurs in pooltailouts and runs. Spawning habitat can be lost or

    degraded by culvert installations in the following ways:

    Culvert placement in a spawning area replacesthe natural gravel used for spawning witha pipe. This is a direct loss of spawning habitat.

    Culvert construction can require significantchannel realignment, eliminating naturalmeanders, bends, spawning riffles andother diversity in the channel that serveas valuabl e habitat.

    Culverts shorten channels, leadingto increased velocities and bed instability thatreduce spawning opportunities and decreaseegg survival.

    Riffles and gravel bars immediately downstreamof the culvert can be scoured if flow velocityis increased through the culvert. Gravelmobilization while eggs are incubating in redds(nests) results in high egg mortality.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    11/111

    Design of Road Culverts for Fish Passage 10

    Any release of sediment into the stream maysmother spawning gravel with silt. In the caseof culverts, sediment releases may be due toconstruction or due to a change in hydraulicscaused by changes to the alignment, sitingor design of the culvert. Such damage canbe avoided or at least minimized by correctlydesigning and implementing an effective

    erosion- and sediment-control plan andby timing the project to avoid critical stagesin salmonid life cycles. Instream work windowsvary among fish species and streams. Contactthe Washington Department of Fish andWildlife's Area Habitat Biologist for informationon work windows (see Appendix J).

    Rearing Habitat

    Juvenile salmonids use almost all segments ofthe stream environment during some stage of theirfreshwater residence. Habitat usage is highly variabledepending upon the species, life stage and time of

    year. Pools with large woody debris are especiallyvaluable habitat. Trees on the streambank alsoprovide important habitat features, serving as coverand a source of insects and large woody material,both of which critical to rearing fish. Culvertconstruction can negatively impact rearing habitatin the following ways:

    There is a direct loss of rearing habitat when itis replaced with a pipe.

    Trees and woody debris at the culvert site mustbe removed to install the culvert, thus eliminatingtheir beneficial effects on channel structure,function, stability and food production.

    Riparian vegetation must be removed fromthe streambank to make way for the culvertinstallation, and it is often removed forthe entire right-of-way width as a regularmaintenance activity.

    Any reduction in stream length is a reductionin usable rearing habitat. Culverts cut offnatural bends, meanders, side channels andbackwater channels, directly e liminating suchhabitat. Most side channels and backwaterchannels experience higher fish usage thanthe main stream channel, especially duringwinter flood flows, so the loss of such habitatcan be especially harmful to fish survival.

    Culvert placement that lowers the natural waterlevel of pools, ponds, backwaters or wetlandswithin or adjacent to the stream can significantlydecrease valuable rearing habitat.

    Loss of Food Production

    Fish, like all other organisms, need food in order to survive, grow and reproduce. Juvenile salmonidsfeed on aquatic invertebrates and terrestrial insectsthat fall into the water. The food chain in the aquaticenvironment begins with the primary producers likealgae and diatoms (periphyton), which require organic

    material and sunlight to fuel the photosynthetic process.The inside of a culvert is dark, and the absenceof sunlight prohibits primary production. Benthicinvertebrates like mayflies, stoneflies and caddis fliesfeed on the primary producers. Invertebrates requiresome of the same conditions as salmonids to thrive,including clean water and stable gravel. Reductionin the number of invertebrates means a reductionin an important food source for salmonids, whichcan reduce salmonid growth rates. Faster growthrates produce larger salmonids a competitiveadvantage that increases their survival rate at sea.

    Removal of riparian vegetation for culvert placement

    reduces organic debris such as leaves, wood, bark,flowers and fruit that enters the stream and fuelsprimary production. Terrestrial insects that drop fromoverhanging vegetation into the water are removedfrom the food base when the vegetation is lost.

    Mitigation of Direct Habitat Losses

    Complete replacement of habitat and channel lengthlost due to culvert installation can be difficult,if not impossible. Mitigation then becomes the nextoption. Mitigation for the impact of lost coverand pools might include adding diversity and habitatfeatures such as woody debris to the channel

    in an appropriate location.

    As mentioned earlier, placement of a culvertin a spawning area results in a direct loss of thathabitat for fish, but invertebrates are also affectedbecause they, too, spawn in gravel beds.Spawning habitat in most Pacific Northwest streamsis not limited by the supply of gravel; it is limitedby the structure and diversity of channel forms thatsort and distribute bed material to create spawningand other habitats. The only effective meansof preserving valuable spawning habitat in most casesis to avoid disturbing it in the first place.

    In streams that are deficient in spawning gravel,a loss of spawning habitat might be mitigated offsite by gravel supplementation. Several techniquesmight be used.

    While it may be tempting to simply place new gravelover an existing streambed inside or outsideof a culvert, it is normally not effective to do soin the short term. The new gravel is, of course,attractive to fish for spawning, but its not stable

  • 8/14/2019 Design of Road Culverts for Fish Passages

    12/111

    Design of Road Culverts for Fish Passage 11

    enough for eggs to survive winter floods. It takesseveral high flows for gravel to be redistributed andsettle into place before it can be valuable habitat.

    Gravel supplementation should instead be donein a way that mimics natural gravel deposits suchas pool tailouts or gravel banks. The downstream endof stable pools and stable riffles can be supplemented

    with a layer of gravel to mimic tailout deposits.Gravel can be placed upstream of streambed controlsthat are installed as part of the fish-passage project.A channel constriction made of mounds of gravel will,in the right circumstances, create a pool and a tailout.Gravel can also be supplied to a bankline to mimica naturally eroding gravel bank. High stream flows willthen efficiently redistribute the gravel to locationswhere it is most likely to remain stable.

    It may seem reasonable to add a layer of gravel insidesteeper culverts to mimic the streambed at eitherend. However, if the gravel layer is too thick, lowwater flows may not be able to rise above the gravel,

    and fish will not be able to swim through.This problem can be especially troublesome whenthere is no input of bedload from upstream to sealthe gravels, such as when there is a wetland or pondimmediately above the culvert or in spring-fedstreams with stable hydrology.

    Water Quality

    To extend the life span of culverts in acidic water,they are sometimes treated with an asphalt coating.It is unknown what affect this may have on fishor invertebrates in the water. Until it can be shown

    that these type of treatments are not a risk to fishhealth they should not be used.

    Quality and quantity of road stormwater runoff mustbe mitigated as deemed appropriate by the localjurisdiction or the Washington State Departmentof Ecology. In addition, all stormwater dischargesinto a stream must be designed to prevent scourduring higher flows.

    Upstream and DownstreamChannel Impacts

    Increased velocity from a culvert can erodedownstream banks, leading to the need for bankprotection. To reduce the likelihood of downstreamerosion, flow velocity at the culvert exit shouldnot exceed the preproject channel velocity by morethan 25 percent.

    Undersized culverts create bed instability upstream.At high flows, the culvert creates a backwater,and bed material is deposited in the channel upstream.With receding flows, the bed and/or banks erodethrough or around the deposition. The result is eithera chronically unstable channel bed or increased bankerosion and the need for bank clearing and protection.The culvert inlet should be designed to limit head loss

    to less than one foot for a 10-year flood. Less headloss may be necessary considering flood impacts.

    The design process described in this guideline helpsminimize these upstream and downstream impacts.Typically, this process determines the size and elevationof culverts such that velocities leaving the culvert willnot be excessive. Sites with banks or beds susceptibleto erosion may require special consideration.

    A culvert placed in a stream with an actively migratingchannel can result in an acceleration of the channelmigration and a substantial maintenance effort to keepthe channel at the culvert location. Channel migration

    is a natural, geomorphic process, but upstreamactivities can accelerate it. Chapter 7, Channel Profilediscusses how to anticipate and address those impacts.

    Ecological Connectivity

    Ecological Connectivity is the capacity of a landscapeto support the movement of organisms, materialsor energy.1 In terms of culvert design, it is the linkageof organisms and processes between upstream anddownstream channel reaches. The health of fishpopulations ultimately relies on the health of theirecosystems, which include migrations and processes

    that depend on that connectivity. Biotic linkages mightinclude upstream and/or downstream movementof mammals and birds, nontargeted fish species,and the upstream flight and downstream driftof insects. Physical processes include the movementand distribution of debris and sediment and the shiftingof channel patterns. Some of these functions maybe blocked by road fills and culverts that are too smallin relation to the stream corridor.

    Debris and bed material should be managedby allowing them to pass unhindered through theculvert. When debris is trapped, fish-passage barriersare created; the debris is not passed to the channel

    downstream, and a backwater is created upstream thatextends the negative effect of the culvert. While thesize of the culvert developed by the design processesdescribed in this guideline will normally be adequateto pass most debris and bed material, there maybe special cases where the culvert size should beincreased to avoid capturing debris. Additionally, theHydraulic Design Option discussed later in this guidelinemay undersize the culvert for debris, so a factorof safety must be applied.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    13/111

    Design of Road Culverts for Fish Passage 12

    Trash racks and multiple, parallel, culvert pipesare generally not acceptable because they trapdebris, create barriers to f ish migration and increasethe risk of culvert failure. In the case of low roadprofiles, raising the road elevation shouldbe considered as an alternative to multiple culverts.

    Debris racks might be a reasonable, temporary

    solution in special cases, if an existing culvert hasa high risk of debris plugging and there is a clearresponsibility and committed schedule for replacingthe culvert. The debris rack for this situation shouldbe mounted high on the culvert, above the ordinaryhigh water mark. The space below it is left openfor typical flows. The rack itself is only functionalat high flows when debris is moving. Openingswithin the bar rack should be no smaller than nineinches. A specific monitoring and maintenance planshould be developed for any debris rack, andconvenient access must be provided for these activities.

    Ecological connectivity issues are difficult to quantify

    and generalize, but they may ultimately be significantto the health of aquatic ecosystems. More developmentof the concept of ecological connectivity in relationto road culverts is expected and encouraged.

    Channel Maintenance

    Other than fish passage, the need for channelmaintenance created by poor siting of road crossingsand culverts is the greatest impact culverts haveon aquatic habitats. Highways are often placedat the fringe of river floodplains and must, therefore,cross the alluvial fans of small streams entering

    the floodplain. As each stream enters the relativelyflat floodplain, a natural deposition zone is created,and the channel is prone to excursions and avulsionsacross its alluvial fan. Culverts placed in theselocations tend to fill with bed material. To keepthe culvert from plugging and the water overtoppingthe road, periodic (in some cases as frequentlyas annually) channel dredging becomes necessary.Bed-material removal is a major cause of channelinstability and loss of spawning and rearing habitatfor some distance upstream and downstream. It alsohas an ecological-connectivity impact by blocking bedmaterial and the aggrading-channel process frommigrating throughout the reach.

    Mitigation for these channel-maintenance impactsincludes installing a bridge or a culvert large enoughthat the aggradation and channel-evolution processescan continue. A bedload sump might be usefulin some situations to localize the dredging neededat existing culverts and even eliminate the upstreamimpacts of dredging. (Information on the designof such sediment traps can be found in the upcoming

    Washington Department of Fish and Wildlifedocument, Stream Habitat Restoration Guidelines.)If relocating the road is possible, it is normallyconsidered a superior alternative.

    Construction Impacts

    Construction impacts might include the releaseof sediment or pollutants, temporary fish-passagebarrier during construction, removal of banklinevegetation, blocking of the flow or stranding of fish.Provisions in WAC 220-110-070 address theseissues by way of construction timing, water-quality

    management, erosion- and sediment-controlplanning, and revegetation. Construction planssubmitted for Hydraulic Project Approval shouldinclude, in addition to plans and specifications,an erosion- and sediment-control plan covering theseitems. The provisions of WAC 220-110-070 maybe modified for specific projects.

    Risk of Culvert Failure

    Structural failure of culverts can cause long-term,extensive and massive damage to habitat. Failurescan be a result of inadequate design, poor construction,

    beaver damming, deterioration of the structure orextreme natural events. Risk of failure can be minimizedby sizing the culvert to accommodate extreme flowevents and debris. This may include appropriate inletand/or outlet armoring and the use of proper backfilland compaction techniques during construction.

    In some cases, fords or alternative road overflow pointsmay be useful. This should be considered along forestroads that are susceptible to debris flows or along roadsthat cross alluvial fans (for guidelines on ford design,contact WDFW for Technical Assistance).

  • 8/14/2019 Design of Road Culverts for Fish Passages

    14/111

    Design of Road Culverts for Fish Passage 13

    Chapter 2 Fish Barriers at Culverts

    The parameters provided in WAC 220-110-070 serveas the technical definition of a fish-passage barrier andthe basis for fish-passage design. Some level of barrieris assumed to be present when the criteria are notachieved. The regulation is included in Appendix B,Washington Culvert Regulation.

    Barriers block the use of the upper watershed,which is often the most productive spawning habitat,considering channel size, substrate and availablerearing habitats. Fish access to upper portionsof the watershed is important; fry produced therethen have access to the entire downstreamwatershed for rearing. Complete barriers block all fishmigration at all flows. Temporal barriers blockmigration some of the time and result in lossof production by the delay they cause (anadromoussalmonids survive only a limited amount of time

    in fresh water, and a delay can limit egg distributionor cause mortality). Partial barriersblock smalleror weaker fish within a species and limit the geneticdiversity that is essential for a robust population.Fish-passage criteria accommodate weaker individualsof target species including, in some cases, juvenile fish.

    There are five common conditions at culverts thatcreate migration barriers:

    excess drop at the culvert outlet, high velocity within the culvert barrel, inadequate depth within the culvert barrel, turbulence within the culvert, and debris and sediment accumulation at the culvert

    inlet or internally.

    The interior surface of a culvert is usually designedto optimize water passage; it does not havethe roughness and complexity needed to slow downthe flow that a streambed does. Instead, the culvertconcentrates and dissipates energy in the formof increased velocity, turbulence or downstreamchannel scour are the most prevalent blockagesat culverts.

    A culvert is a rigid boundary set into a dynamicstream environment. As the natural stream channel

    changes, especially with changes in hydrologydue to land use changes, culverts often are not ableto accommodate those changes. Instead, theybecome barriers to fish passage.

    Fish-passage barriers at culverts can be the resultof improper design or installation, or they maybe the result of subsequent changes to the channel.Fish-passage barriers are very often the resultof degrading channels, leaving the culvert perchedabove the downstream channel. Changes inhydrology due to urbanization are a common causeof channel degradation. Fish-passage barriers are alsocaused by scour-pool development at the culvert outlet.The scour pool may be good habitat in itself but itmoves the backwater control of the downstreamchannel further downstream and creates a drop at theoutlet. The presence of large scour pools at a culvertoutlet and/or midchannel gravel bars upstream of theculvert are often indicators that a velocity barrier for fishexists inside the culvert at high flows.

    All fish-passage structures require some level

    of maintenance. Adult fish typically migrate duringthe high flow seasons and in response to freshets.Timely inspections and maintenance during inclementweather are necessary at all facilities. When culvertsare not adequately inspected and maintained, fish-passagebarriers can form. The maintenance done at a culvertfor the purpose of high-flow capacity is often differentthan what is required for fish passage. For example,debris that is plugging slots in baffles for example maynot affect the flow capacity of a culvert, but it may blockfish from passing through. More than a cursoryinspection of the culvert inlet and outlet is necessaryfor an adequate fish-passage maintenance program.

    Many fish-passage barriers that occur at high streamflows are not apparent during low and normalstream flows. For a complete fish-passage assessment,culverts must be analyzed at both the low and high fish-passage design flows. Definition and selectionof design flows are discussed in this guideline.The Washington Department of Fish and Wildlifehas developed a spreadsheet to determineif a culvert meets the criteria in WAC 220-110-070.The spreadsheet can be found in the Fish PassageBarrier and Surface Water Diversion ScreeningAssessment and Prioritization Manual, publishedby the department and availableat www.wa.gov/wdfw/hab/engineer/fishbarr.htm.

    The manual provides guidance on how to locate,assess and prioritize fish-passage problems (e.g.,culverts, dams, fishways) and problems associatedwith surface-water diversion screens.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    15/111

    Design of Road Culverts for Fish Passage 14

    Chapter 3 Culvert Design For Fish Passage

    Many road crossings in Washington State have beendesigned or retrofitted to provide fish passage.The experience of observing and monitoring such sites,together with research on fish migration behaviors andswimming capabilities, has led to several straightforwarddesign procedures outlined in this guideline. Chapter 1,Habitat Issues at Road Crossings described the first stepin the design process, which involves becoming awareof the potential habitat issues that arise when roadwayscross streams. Chapter 2, Fish Barriers at Culverts,identified some of the concerns to be addressedif culverts are to be used to convey a stream througha roadway crossing. This chapter and the rest of thisguideline describe how to design a culvert to providefish passage. A general flow chart of the culvert-designprocess for fish passage is shown in Figure 3-1.

    A general flow chart of the culvert design process.

    Design of Road Culverts for Fish Passage providesspecific guidance to satisfy state regulationsand to cover additional situations that exceed thosedefined by regulations. The criteria provided here arenot absolute; however, if they cannot be achievedfor a specific project, then other road-crossing meansshould be considered instead. Such options mayinclude installing a temporary culvert, reroutingthe road to eliminate the stream crossing orconstructing a bridge. Variances to some design criteriacan be approved if adequate justification is provided.

    Recent experience in western Washington has shownthat about 25 percent of fish-passage barriersat culverts have required full replacement of the culvert.Some of these replacements have been accomplishedby boring new culverts through high road fills.About five percent have required replacement

    of the culvert with a bridge or abandonment ofthe roadway. These percentages will likely changeas more culvert barriers are fixed in low-gradient areasand projects move upstream to higher-gradient reaches.

    When culverts are the solution of choice, effectivefish passage can often be provided through the properdetermination of culvert slope, size, elevation androughness. Constructing formal structures and allowingthe upstream channel to regrade to a steeper gradientcan also be useful. Fish-passage construction at low-gradient sites can usually be limited to within 100 feetor less of the channel length outside the culvert;construction at steeper sites may extend further

    upstream and downstream from the culvert, or it mayrequire formal fish ladders or full culvert removal.

    The determination of adequate fish passage at aculvert is based on criteria described in WAC 220-110-070. This regulation describes two differentapproaches for ensuring fish passage:

    1. the No-Slope Design Option, and

    2. the Hydraulic Design Option.

    A third option is also acceptable; it is the Stream-Simulation Design Option, in which an artificial stream

    channel is constructed inside the culvert.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    16/111

    Design of Road Culverts for Fish Passage 15

    The No-Slope Design Option results in reasonablysized culverts without requiring much in the wayof calculations. The Hydraulic Design Option requireshydrologic and open-channel hydraulic calculations,but it usually results in smaller culverts being requiredthan the No-Slope Design Option. (Smaller culvertsmay trap more debris; however, so a factor of safetymust be applied.) The Hydraulic Design Option

    is based on velocity, depth and maximum-turbulence requirements for a target speciesand age class. The Stream-Simulation Design Optioninvolves constructing an artificial stream channelinside the culvert, thereby providing passage forany fish that would be migrating through the reach.

    It is difficult in most situations, if not impossible,to comply with velocity criteria for juvenile fish passageusing the Hydraulic Design Option. The No-Slopeand Stream-Simulation Design options, on the otherhand, are assumed to be satisfactory for adult and juvenilepassage; thus, they tend to be used more frequentlyat sites where juvenile fish passage is required.

    Application of the No-Slope Design Option is mosteffective for relatively short culverts at low-gradient sites.

    Road-Crossing Siting

    Fish-passage barriers and the cumulative habitat losscaused by culverts can be reduced in part by properlyciting the culvert and by minimizing the numberof road crossings. Both the siting of culvertsand the land-use planning that creates the needfor the culverts are important.

    Culvert Siting

    The goal in siting a culvert is to make the culvertas short as possible without deviating from thedirection of the upstream and downstream channelcourse by more than 30 degrees. A culvert thatmimics the exact course of a stream may be longenough to become a fish-passage barrier. On theother hand, a culvert made shorter by deviatingthe course of the stream at an extreme angle (greaterthan 30 degrees to the channel) will reduce thesuccess of fish passage by increasing inlet contractionand turbulence at high flows. Increased contractionalso makes the culvert less efficient for flood capacityand sediment transport. In-channel deposition

    and bank scour often occur upstream of culverts withexcess skew. When the culvert is skewed relativeto the downstream channel and the culvert outletis not directed at the channel alignment, there isan increased risk of bank erosion.

    Its also important to anticipate potential naturallateral migration or vertical changes of the channelwhen siting a culvert. The installation of a culvertfixes a section of the channel rigidly in place. If astream is naturally unstable and/or is migrating acrossa floodplain, the rigidity of the culvert may exacerbatethe streams instability, accelerate the streams migrationrate or make the streams migration become more

    pronounced and chaotic. Channels naturally movevertically over time. Instabilities may occur in whichthe channel bed continues to aggrade (rise) or degrade(incise) over long periods of time. A channel may alsofluctuate in elevation in response to floods. Long-termor short-term channel changes must be accommodatedin culvert design. If they cant be accommodated, othersolutions, such as a bridge or an alternative roadalignment, may be more appropriate.

    Land-Use Planning

    Many new stream crossings can be avoided (or atleast the number required can be reduced) through

    proper land-use planning. Even the best of fish-passage design has the potential to become a fish-passage barrier. The way local jurisdictions prepareand implement land-use plans and critical-areasordinances has a direct influence on fish-passage successby distributing land uses and the transportation systemsnecessary to support them. For example, if a countyfails to allocate forest or agricultural land, applyinginstead a very dense pattern of urban, suburban or ruralresidential land uses, one can expect many streamcrossings to be required. This would not be the caseif less dense and intense land uses, such as forestryor agriculture, were coupled with a combinationof compact, urban growth areas and large, rural parcels.

    In addition to the number of road crossings, changesin hydrology and riparian areas due to denseurbanization also affect fish passage. These changescause channel incision and channel simplification thatoften leave culverts perched above the downstreamchannel, forming barriers to fish migration. Otherlikely impacts are sediment and temperature impacts.With these changes, the only adequate habitat leftis confined to areas upstream of the urbanization,making downstream fish-passage barriers even moredamaging to fish production.

    Fish passage is not the only habitat concern created

    by the improper design of fish culverts. These concernsare described in detail in Chapter 1.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    17/111

    Design of Road Culverts for Fish Passage 16

    Bridges

    Where the design process leads away from a culvertas a viable crossing structure, a bridge should beconsidered. This is particularly the case wherethe stream width exceeds 20 feet or stream slope isgreater than about six percent, or when the movementof large debris is frequent. Crossings that are subject

    to debris flows need special consideration. Alternativesin such a situation include fords, temporary bridges,bridges with high clearance and moving the roadto where its crossing is less problematic.

    While general considerations regarding the use ofbridges at crossings are discussed in this guideline, theiractual design is not addressed. An experienced bridgedesign engineer is required for such an undertaking.

    For the purpose of this guideline, a bridge is anycrossing that has separate structural elementsfor the span and its abutments. Unencumbered bythe dimensional limitations of culverts, a bridge can

    be large enough that the structure does not significantlyaffect the flood hydraulic profile. Piers and abutmentscan be drilled or buried deeply enough that thereis very little risk of failure.

    Like culverts, however, bridge designs must alsocomply with regulations; in this case, regulationsaddressing water crossings and the creation of newchannels (WAC 220-110-070 and 220-110-080).And, just as in the case of culverts, bridge designmust begin with considerations for habitat impact.Properly designed bridges are superior to culverts interms of habitat preservation and restoration; however,mitigation measures may still be necessary

    to compensate for impacts from construction, bankarmoring or other habitat losses causedby the presence of the bridge.

    The channel created or restored beneath the bridgemust have a gradient, width, floodplain andconfiguration similar to the existing natural channelupstream or downstream of the crossing. Wherepossible, habitat components normally present in thesechannels should also be included. In high-gradientsituations, the stream-simulation width criteria (seeChapter 6, Stream-Simulation Design Option) maybe used to determine channel width under the bridge.

    Bridge-span calculations should begin witha consideration of required channel width andfloodplain requirements and proceed to side-slopeand abutment allowances to arrive at the correctbridge-span dimensions. The side slopes upto the abutments should be placed at an angle thatleads to natural stability. Large riprap retaining wallsthat encroach on the channel should be avoided.

    WAC 220-110-070 states that abutments, piers, piling,sills, approach fills, etc., shall not constrict the flowso as to cause any appreciable increase (not to exceed0.2 feet) in backwater elevation (calculated at the 100-year flood) or channelwide scour and shall be alignedto cause the least effect on the hydraulics of the watercourse. The purpose of that criteria is to limitthe effect of the bridge on the upstream channel,

    especially in channels with significant gravel bedload.

    When an undersized culvert is removed and replacedwith a bridge, some upstream channel instabilityis likely. This can be due to stored sediment abovethe culvert and/or channel incision below the culvert.The result is excessive drop through the areaof the crossing. The designer should carefully considerthe channel headcut and regrade factors (see thediscussion addressing channel regrade in Chapter 7,Channel Profile). Some sort of grade control, temporaryor permanent, may be necessary to ensure channeland habitat integrity.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    18/111

    Design of Road Culverts for Fish Passage 17

    Chapter 4 No-Slope Design Option

    Description and Application

    Successful fish passage can be expected if the culvertis sufficiently large and is installed flat, allowing

    the natural movement of bedload to form a stable bedinside the culvert. The No-Slope Design Optioncreates just such a scenario. A no-slope culvertis defined by the following characteristics:

    width equal to or greater than the averagechannel bed width at the elevation the culvertmeets the streambed,

    a flat gradient, the downstream invert is countersunk below

    the channel bed by a minimum of 20 percentof the culvert diameter or rise,

    the upstream invert is countersunk belowthe channel bed by a maximum of 40 percent

    of the culvert diameter or rise, the possibility of upstream headcut has beentaken into account, and

    there is adequate flood capacity.The No-Slope Design Option is usually applicablein the following situations:

    new and replacement culvert installations, simple installations, low to moderate natural channel gradient

    or culvert length (generally < 3% slope), and passage is needed for all species.

    The No-Slope Design Option can only be appliedto culvert replacements and new culvert installations.It does not apply to retrofits. No special designexpertise or survey information is required for no-slope culvert designs; and, if velocities are sufficientlylow to allow a bed to deposit in the culvert, it isassumed that a broad range of fish species and sizeswill be able to move through the culvert. In somecases, channel morphological features such as gravelbars and even a thalweg may form inside the culvert.Although culverts installed using the No-Slope DesignOption are typically larger than culverts designed usingthe hydraulic option, the advantage to the culvertowner is the avoidance of additional surveying

    and engineering costs required by other designoptions. Combining the requirements of countersinkingthe outlet and the culvert width for a circular culvert,the diameter must be at least 1.25 times the channelbed width. The primary advantage of this option to theculvert owner is the avoidance of additional surveyingand engineering costs required for other options.

    Information needed for the No-Slope DesignOption includes:

    the average natural channel-bed width, the natural channel slope, the elevation of the natural channel bed

    at the culvert outlet, and the evaluation of potential headcut impacts

    upstream of the culvert.

    The first three of these parameters are described,together with standards for their measurement,in Appendix F, Summary Forms for Fish-Passage DesignData. The most reliable parameter for bed widthin alluvial channels is the distance between channelbankfull elevations. Channel bankfull elevation isthe point where incipient floodplain overbank flowoccurs. For design purposes, use the averageof at least three typical widths, both upstream

    and downstream of the culvert. Measure widthsthat describe normal conditions at straight channelsections between bends and outside the influenceof any culvert or other artificial or unique channelconstrictions. According to WAC 220-110-070,the channel-bed width can also be derived usingthe area below the ordinary high water markas the bed definition. However, ordinary high watermarks are often difficult to ascertain and are,therefore, often disputed. Ordinary high water marksare less related to physical channel processes,so they are less relevant to culvert design thanthe channel bankfull width. Appendix H,MeasuringChannel-Bed Width, provides guidance on selecting

    and measuring channel width for design purposes.

    If a culvert is being replaced, the estimate of futurechannel elevation and slope are critical parametersto the design. If the existing culvert is either perchedor undersized, it will affect the local channel slope,width and elevation. Additionally, a surveyed profileof the channel will be required where it has beenaffected by the existing culvert. The profile is usedto predict the natural channel slope and elevationat the culvert site by interpolating from unaffectedconditions upstream and downstream.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    19/111

    Design of Road Culverts for Fish Passage 18

    A word of caution in using the No-Slope DesignOption: the downstream channel profile may haveto be steepened in situations where it has beenscoured due to an undersized culvert. That steepenedchannel may become buried eventually as the channelaggrades upstream. Assuming the culvert is largeenough to not create a constriction, a sloping channelwill develop inside the culvert even though the culvert

    itself is placed flat. The result of this is the upstreamend of the culvert will have a higher bed and lesscross-section open area than the downstream end.Longer culverts in steeper channels under this optionwill result in less open area at the upstream end.

    A reasonable upper limit of the No-Slope DesignOption is to use it at sites where the productof the channel slope (ft/ft) and the culvert length (ft)does not exceed 20 percent of the culvert diameteror rise. It should be noted that this limitationcan be overcome by understanding and accountingfor the implications of constricting the upstream endof the culvert with the accreted bed or by installing

    a larger culvert. Any culvert shape can be used (round,pipe-arch or elliptical), but it must be countersunka minimum of 20 percent at the downstream endand a maximum of 40 percent at the upstream end(see Figure 4-1). Using a round pipe providessufficient width and additional vertical clearance.

    The culvert must be countersunk a minimum of 20percent at the downstream end and a maximum of 40percent at the upstream end.

    The No-Slope Design Option is, therefore, limitedby slope and length. If a site does not comply with thislimitation, the size of the culvert diameter (D) can be

    increased; the slope (S) can be decreased, or anotherdesign option should be used.

    Channel Profile, Flood Capacityand Other Considerations

    The design of a new or replacement culvert mitigatesfor future design flows as land uses change. Issues ofchannel profile, flood capacity and other considerationsare addressed throughout this guideline.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    20/111

    Design of Road Culverts for Fish Passage 19

    Chapter 5 Hydraulic Design Option

    Description and Application

    The second design option provided in WAC 220-110-070 (see Appendix B, Washington Culvert

    Regulation) is based on the swimming abilitiesof a target fish species and age class. The HydraulicDesign Option can be applied to retrofits of existingculverts as well as to the design of new or replacementculverts. Hydraulic, open-channel flow and hydrologiccomputations, as well as specific site data are requiredfor this option.

    Generally, the Hydraulic Design Option might beapplied in the following situations:

    new, replacement and retrofit culvert installations; low to moderate culvert slope without baffles; moderate culvert slope with baffles (as retrofit);

    and target species have been identified for passage.Engineering design expertise, hydrology and surveyinformation are required for this design option.

    Historically, the Hydraulic Design Option has beenthe standard engineering method for designing fishpassage at culverts. It is no longer the preferredmethod, however. In fact, it is not even allowedin many cases. The option is included here becauseit does apply to temporary retrofits of existing barrierculverts where replacement of the culvert can notoccur in the near future. The method has limitations

    of culvert slopes; other design methods tendto provide less costly and more reliable designsin steep channels, and the Hydraulic Design Optiontargets distinct species of fish. It does not accountfor the ecosystem requirements of nontargetspecies. Additionally, there are significant errorsassociated with estimation of hydrology and fishswimming speeds; however, they can be resolvedby making conservative assumptions in the designprocess. Situations in which the Hydraulic DesignOption is most likely to be acceptable are temporaryretrofit installations.

    The fish-passage design process for the HydraulicDesign Option is reversed from the typicalengineering orientation of culvert design for floodflows. Design considerations begin in the channelbelowthe culvert and proceed in the upstreamdirection through the culvert; the direction of fishpassage. In other words, think like a fish. Culvertsdesigned for fish passage normally result in outlet-control conditions at all fish-passage flows. The inlet-control analysis must then be done to verify adequateculvert capacity for the high structural flow. Fish-passagecriteria will usually control culvert design; flood-passagecriteria are normally less stringent.

    Proper culvert design must simultaneously considerthe hydraulic effects of culvert size, slope, material andelevation to create depths, velocities and a hydraulicprofile suitable for fish swimming abilities. It mustbe understood that there are consequences to every

    assumption; adequate information allows optimumdesign. The following sequence of steps is suggestedfor the Hydraulic Design Option for fish passagethrough culverts:

    1. Length of Culvert: Find the culvert lengthbased on geometry of the road fill.

    2. Fish-Passage Requirements: Determinetarget species, sizes and swimming capabilitiesof fish requiring passage. Species and sizeof fish determine velocity criteria. Allowablemaximum velocity depends upon speciesand length of culvert.

    3. Hydrology: Determine the fish-passagedesign flows at which the fish-passage criteriamust be satisfied.

    4. Velocity and Depth: Find size, shape,roughness and slope of culvert to satisfyvelocity criteria, assuming open channel flowand no bed material. Verify that the flowis subcritical throughout the range of fish-passage flows.

    5. Channel-Backwater Depth: Determinethe backwater elevation at the culvert outlet

    for fish passage at both low and high fish-passage design-flow conditions.

    6. Culvert Elevation: Set the culvertelevation so the low and high flowsfor channel backwater are at least as highas the water surface in the culvert.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    21/111

    Design of Road Culverts for Fish Passage 20

    7. Flood-Flow Capacity: Verify that theflood-flow capacity of the culvert is adequate.

    8. Channel Profile: If necessary, adjustthe upstream and/or downstream channelprofiles to match the culvert elevation.

    Several iterations of Steps 4 through 8 may be required

    to achieve the optimum design. The following sectionsdescribe each of the design steps in more detail.

    Length of Culvert

    The Hydraulic Design Option is based on themaximum water velocity that target fish species areable to swim against as they negotiate the full lengthof the culvert. The longer the culvert, the lower themaximum allowable velocity. Determine the overalllength of the culvert. Include aprons in the length,unless they are countersunk below the invert ofthe culvert. The length can be minimized by adding

    headwalls to each end of the culvert, by narrowingthe road or by steepening the fill embankments.

    Fish-Passage Requirements

    Species and Size of Fish

    The Hydraulic Design Option creates hydraulicconditions through the culvert that accommodate theswimming ability and migration timing of target speciesand sizes of fish (see Figure 5-1). Fish-passage designis based on the weakest species or size of fish

    requiring passage and is intended to accommodatethe weakest individuals within that group. The typesof species that are potentially present and the timeof year when they are present can be obtainedby contacting the Washington Department of Fishand Wildlife Area Habitat Biologist or Regional FishBiologist (see Appendix J , Washington Departmentof Fish and Wildlife Contact Information).

    The passage of adult trout as small as six inches infork length (150 mm) is a design requirement in mostareas of Washington State. It is assumed to bea requirement at each site unless it can be shown that,by distribution of species or habitat, it is not justified.Upstream migration of juvenile salmonids (50- to 120-mm salmon and steelhead) can also be importantat many sites, depending upon the species presentand the habitat distribution within the basin or reach.These fish are small and weak; therefore they requirea very low passage velocity and a low level ofturbulence. Unfortunately, the Hydraulic Design

    Option cannot usually satisfy the limitations of verylow velocity and turbulence. It is, therefore, notgenerally practical to use the Hydraulic Design Optionfor juvenile fish passage. Instead, either the No-SlopeDesign Option or the Stream-Simulation DesignOption may be more appropriate. Juvenile fishpassage may not be necessary in every situation;the biological needs at the site should be clearly

    stipulated by qualified biological experts beforea design is attempted specifically for juvenile fi sh.A culvert specifically designed by the HydraulicDesign Option for six-inch trout is expectedto also provide passage for juvenile salmonids.If the hydraulic characteristics necessary for adulttrout passage are achieved during peak flows, it isassumed that adequate juvenile passage is providedat lesser flows. Hydraulic conditions conduciveto trout passage will result in bed-material depositionand a natural, roughened channel through the culvert,which juvenile fish can successfully use for passage.

    It is believed that juvenile fish can tolerate some delay;

    and, because of their normal migration timing, they willbe subjected to less severe hydraulic conditions thanadult migrants. An exception to the presumptionof stable bed formation for juvenile fish passage mightoccur in situations where a pipe becomes deeplysubmerged and pressurized during an extreme floodevent and bed material is therefore scoured from it.Until new bed material is recruited into the culvert,there may be a barrier to weaker-swimming fish.

    The use of adult trout as a conservative defaultcondition may not apply to fishway design, sincepassage through the fishway does not dependon the accretion of a natural bed, and design issues

    of flow control and energy dissipation are uniquein design of fishways. The design of fishways isnot included in this guideline, though there is a briefoverview of the subject in Chapter 10, Fishways.

    Much of this guideline is focused on the passageof salmonid fishes. However, there are tremendousecological benefits to providing connectivity betweenupstream and downstream reaches for other biotaand physical processes. In addition to salmon andsteelhead, there are at least 15 species of migratingfish in Washington State for which there is little orno information regarding migration timing, migrationmotivation or swimming ability. Ecological healthof both upstream and downstream reaches dependson connectivity of physical processes such as sedimentand debris transport, channel patterns and cycles,and patterns of disturbance and recovery, as wellas biological connectivity. Stationary culverts ata fixed elevation may not be able to communicatethese processes and may, therefore, affect overallecosystem health.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    22/111

    Design of Road Culverts for Fish Passage 21

    Using the Hydraulic Design Option will not likelyprovide for many of these values. They will morelikely be achieved by using the Stream-SimulationDesign Option or by using options other thanculverts, such as full-spanning bridges and roadabandonment or relocation.

    Hydraulic Design Option for fish passage through culverts.

    Species and Size of Fish DetermineVelocity Criteria

    The actual allowable velocity and depth of flowfor adult fish depend upon the target species andlength of culvert as prescribed in WAC 220-110-070.Analysis for both velocity and depth shouldbe performed using a factor of safety. These criteria

    (see Table 5-1) are intended to provide passageconditions for the weakest and smallest individualsof each species.

    As mentioned earlier, the passage requirements forjuvenile salmonids are assumed to be met if the designmeets the needs of adult trout. If the design does nottarget adult trout, then the Hydraulic Design Optionwill not likely provide passage for juvenile salmonids.Even installation of artificial roughness features is noteffective in controlling flow velocities for juvenile fishpassage because of the turbulence they generate.The combination of low velocity and low turbulencerequired for passage of juvenile fish makes

    it impractical to address in design.

    Table 5-1. Fish-passage design criteria for culvert installations.

    Adult Trout>6 in. (150 mm)

    Adult Pink orChum Salmon

    Adult Chinook,Coho, Sockeye or

    Steelhead

    Culvert Length Maximum velocity (fps)

    10 - 60 feet 4.0 5.0 6.0

    60 - 100 feet 4.0 4.0 5.0

    100 - 200 feet 3.0 3.0 4.0

    Greater than 200 feet 2.0 2.0 3.0

    Minimum water depth (ft)

    0.8 0.8 1.0

    Maximum hydraulic drop in fishway (ft)

    0.8 0.8 1.0

  • 8/14/2019 Design of Road Culverts for Fish Passages

    23/111

    Design of Road Culverts for Fish Passage 22

    Based on evaluation of juvenile passage through culvertsconducted by P. D. Powers,2 the recommended designvelocities for fry and fingerlings are 1.1 and 1.3 fpsrespectively. Fry are spring-migrating juveniles generallyless than 60 mm in fork length. Fingerl ings are fall-migrating fish, generally greater than 60 mm in forklength. Powers noted that allowable velocities for thesefish depend upon the type of corrugation of the pipe.

    These velocities are average cross-section velocities andwould apply to any length of culvert. He observed thatthe fish swimming in waters flowing at these velocitiescould continue at that rate for an extended period time.These velocities might be achieved at some low-gradientsites with large culverts or at spring-fed streams with lowpeak flows.

    Increasing the roughness with features like bafflescan create a low enough average velocity to satisfythe needs of juvenile fish, but the turbulence createdto do that becomes a barrier for them at moderateslopes. If juvenile passage is desired, it is recommendedthat a natural channel be built within the culvert.

    The complexity and diversity of natural channelsare better suited to providing passage opportunitiesfor small fish. The natural channel design isthe recommended option in this case; it is describedin the Chapter 6, Stream-Simulation Design Option.

    The Hydraulic Design Option uses the averagevelocity in the cross section of the flow (without bedmaterial) and assumes normal, open, channel flowthroughout the culvert. This is a conservative designbecause it does not account for streambed materialor backwater conditions that will increase the depthand, thus, somewhat reduce the velocity. This canbe treated as a factor of safety for design. In reality,

    flow is seldom at normal depth throughout a culvert,particularly in a culvert that is on a relatively flat slope.Backwater-profile programs can be used to furtherrefine the design. Keep in mind, however, that errorsfrom hydrologic calculations may far outweighdifferences between velocity calculation models.This design method also does not account for theboundary-layer velocities that fish will use in movingthrough a culvert. Boundary-layer velocities cannotbe used because they are difficult to predict; turbulencecan become a barrier, and continuity of a boundarylayer through a culvert is difficult to create.

    Migration Timing

    The Hydraulic Design Option criteria must be satisfied 90percent of the time during the migration season for thetarget species and age class. Since migration timings varyamong species and watersheds, knowledge of the specificmigration timings is necessary for developmentof hydrology. Different species or age classes at

    a site may migrate at different times of the year; multiplehydrologic analyses may be needed to determine thecontrolling hydraulic requirements. Generally, adultsalmon and steelhead migrations occur during the falland winter months. Juvenile salmon migrations occurin the spring as fry and in the fall as fingerlings.

    Hydrology

    Again, the hydraulic-design criteria must be satisfied 90percent of the time during the passage season for thetarget species. The 10-percent exceedance flow for eachtarget species is then considered the high fish-passagedesign flow. Passage criteria must be met for all flows fromzero to the fish-passage design flow. There may be morethan one fish-passage design flow if different life stages orspecies require passage at different times of the year. Untilthe hydrology is analyzed and the culvert hydraulics aredesigned to accommodate these life stages, it is not knownwhich fish-passage design flow will control the design.

    High Fish-Passage Design Flow

    In designing culverts for fish passage, the high-flowhydrology of the stream must be understood to makesure fish can get through the culvert during high flows.

    This requires a hydrologic analysis to determine the highfish-passage design flow. The mean daily flow is theparameter used for fish-passage design-flow analysis.There are four types of hydraulic analysis that areacceptable for determining a range of fish-passage designsthat correctly address flow. The scale and importanceof the project and availability of data will dictate whichlevel is applied to a specific project. They are, in orderof preference:

    1. stream gauging,

    2. continuous-flow simulation model,

    3. local-regression model, and

    4. regional-regression model.

    Another option is to use data obtained from one of theabove methods to calibrate a basin-to-basin correlationbetween recorded flows in a nearby system and spotflows measured in the stream system where design flowsneed to be determined. Extreme care should be usedwhen creating this correlation; the probability of inducederrors increases.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    24/111

    Design of Road Culverts for Fish Passage 23

    Interpretation of historic stream-gauging data fora specific stream is the most preferred type of analysis,but adequate data for specific sites are rare. With afew flow data points, however, a regional flow modelcan easily be verified and calibrated. Calibration datashould be within 25 percent of the fish-passage designflow to be valid. Continuous-flow simulation modelsare acceptable, though they are not normally justified

    solely for a fish-passage design. Single-event modelsare generally not acceptable since the fish-passagedesign flow is based on a flow-recurrence frequencyrather than a peak flow.

    For western Washington an acceptable, regional-regression model is the Powers-Saunders model,3

    which is included in Appendix C, Design Flowsfor Ungauged Streams. It is based specifically onthe hydrology of western Washington streams and,therefore, cannot be used in other regions, nor forsites that do not fit within the range of watershed sizesand climate parameters used in the regression analysis.

    The Powers-Saunders model was built by a multiple-regression analysis on stream flow data from 188streams having drainage basins from less than oneto about 50 square miles and with minimum gaugingrecords of five years. Regression models for predictingfish-passage design flow (10-percent exceedance flow)were developed for three hydrologic provincesin western Washington for winter and spring months.Two regions have models for highland streams (gaugeelevation above 1,000 feet) and lowland sites.

    The models are in the form of the equation below.

    QHP = aAbPcId

    Equation 1

    Where: QHP = high fish-passage design flowin ft3/sec

    A = basin area in square milesP = mean annual precipitation at

    the gauging station in inchesI = rainfall intensity: two-year,

    24-hour precipitationa = regression constantb,c,d = regression exponents

    for basin area, precipitationand rainfall intensity.Mean annual precipitationand rainfall intensity werenot statistically significantin all cases, so exponentsfor some regions are zero.

    The standard statistical errors for the regressionformulae vary from about 26 percent to 75 percent.Sound judgement must be used in applying standarderror to the predicted fish-passage design flow for aspecific site. For eastern Washington E. R. Rowland4

    developed a model that defines a fish-passage designflow per unit drainage area. Geographical InformationSystems were used to evaluate spatial data corresponding

    to the sixth field Hydrologic Unit Code (HUC6), withthe key parameters of mean annual precipitation,mean water stress index and mean elevation.The standard error ranged from 17 percent to 44percent for six different regions. To use the model,the designer must complete five simple steps:

    1. Delineate the watershed for thedesired location.

    2. Find the area of the watershed within eachpredefined HUC6 using the regional maps(termed contributing area).

    3. Read the fish-passage design flow in cfs/ sq micorresponding to each HUC6.

    4. Multiply the contributing area withthe corresponding fish passage design flowin cfs/sq mi for each contributing area.

    5. Sum all the values to obtain the fish-passagedesign flow.

    These approaches produce conservative estimatesin most cases. However, consideration should alsobe given to the specific hydrology of the basin, targetspecies for fish passage and future watershed

    conditions. It is recommended that, as a default,at least one standard deviation be added tothe estimated flows derived from the estimated meanthat was found using these formulas, unless a lowervalue can be justified by current and futurewatershed conditions. Lower values are justifiedfor streams that have a slow response to rainfallevents, such as spring-fed streams and basins with a lotof storage available. Higher estimates for QHP shouldbe applied to steeper and urbanized or urbanizingwatersheds, where land use and basin hydrology maychange during the life of the project, thereby affectingthe maximum and minimum flows.

    Whatever model is used, future watershed conditionsshould be considered when choosing the fish-passagedesign flow. Continuous-flow simulation modelsand calibrated regional models most likely providethe best estimate of future conditions.

    Structural design of the culvert will depend onan accurate analysis of flows higher than the highfish-passage design flow. This is discussed brieflyin Chapter 8, High-Flow Capacity.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    25/111

    Design of Road Culverts for Fish Passage 24

    Low Fish-Passage Design Flow

    The low design flow is calculated to determine theminimum water depth within the culvert. One wayof determining low design flow is to use the two-year,seven-day, low flow as described in WAC 220-110-070. A simpler option is to use the zero-flowcondition as described below.

    Culverts designed using the Hydraulic Design Optionfor trout as the default will generally accumulate bedmaterial, eventually forming a thalweg, at which pointthe depth requirement for the culvert is moot becausethe depth in the rest of the stream will also be tooshallow for fish to travel (zero-flow condition).An exception to this is when a culvert becomespressurized during an extreme flood event, the bedin the culvert scours out. If bed material doesntimmediately recruit to the culvert, the bare-bedcondition may persist for some time, in which casea zero-flow condition becomes a barrier to fishpassage. Culverts designed with natural beds inside

    them need to be monitored and maintained,especially following high-flow events.

    Culverts in Tidal Areas

    The hydrology of culverts in tidal areas is a specialcase. The hydraulic conditions in the culvertand downstream of the culvert change as the tideelevation changes. The fish-passage design flow musttake into account any surface stream flow as wellas any tidal outflow as the tide is ebbing. The totaloutflow is calculated by routing any stored tidal prism(tide water and stream-flow contributions) out

    through the culvert as the tide ebbs. The high fish-passage design flow (10-percent exceedance flow)should be calculated using one-hour incrementsof tidal change, assuming a tidal fluctuation betweenmean lower low water (MLLW) and mean higherhigh water (MHHW).

    Considering the difficulty in achieving the standardfish-passage criteria, new culverts that create a barrierdue to tidal extremes are not generally permitted,and removal is a preferred action for restoration.Where removal is not possible but there is a needto achieve the best possible fish-passage restoration,objectives that are different from the standard fish-

    passage criteria might be acceptable. Defining alternativeobjectives should be done in conjunction with a carefuland thorough review of allowable upstream water levelsand timing. Passage goals have been developedfor specific projects to provide fish passage.

    For example, retrofits have been constructed suchthat the fish-passage hydraulic criteria are exceededno more than four continuous hours at any timeduring the fish-migration season. In such a case,passage is provided most hours of all days thoughmay not be passable 90 percent of all hours.Temporary fish blockages would occur for severalhours at the slack period of the highest tides.

    If there is stream flow at times significant enoughto create a barrier by its velocity, it should be assessedsimultaneously with water-surface differentials createdby tidal fluctuations and any other conditions (i.e. tidegate closure) that create a barrier. The simultaneousevaluation could be done using a Monte Carloprocedure, or other similar analysis.

    Streams on tide flats are sometimes impassable dueto shallow flow at low flow and low tide. If a tide flatimmediately downstream of a culvert is impassableat low tide, the 10-percent exceedance criteriais applied only to the time during which fish can

    get to the culvert.

    A tide chart can be also used to estimate thepercentage of time a culvert is out of compliance.Table 5-2 shows tidal elevations that are exceededat selected frequencies at reference stations in PugetSound and the Washington coast. In general, thefrequency that any tidal elevation (relative to MHHWor MLLW) is exceeded is sufficiently uniform withinthe reference station regions of Washington State,when correction factors are applied. Tidal elevationsfor specific exceedance levels at secondary stationscan be estimated by applying the appropriate tidalcorrection value for each individual station.

    For example, the tide at Aberdeen is lower than 1.8relative to MLLW 10 percent of the time. So a culvertthat is passable at all tides above 1.8 is passable 90percent of the time.

  • 8/14/2019 Design of Road Culverts for Fish Passages

    26/111

    Design of Road Culverts for Fish Passage 25

    Table 5-2. Tide-exceedance chart for selected reference stations in Washington State. Datum is local tidal datum (MLLW= 0.0). MLLW and MHHW are from National Oceanic and Atmospheric Administration (NOAA) data. Percent exceedancevalues are calculated from predicted tidal data from November 1, 1990 to January 31, 1991 for the reference stations.

    Reference TidalStation

    Astoria Aberdeen Pt. Townsend Seattle

    MLLW (NOAA) 0.0 0.0 0.0 0.0

    MHHW (NOAA) 8.42 10.07 8.45 11.35PercentExceedance

    90% 0.9 1.8 0.3 0.8

    80% 2.3 3.4 2.2 3.3

    70% 3.3 4.5 3.9 5.3

    60% 4.0 5.4 5.1 6.8

    50% 4.8 6.5 6.0 7.7

    40% 5.7 7.5 6.8 8.5

    30% 6.5 8.3 7.5 9.4

    20% 7.2 9.1 8.1 10.3

    10% 8.3 10.2 8.7 11.4

    Tidal Elevation Datum

    Determining appropriate high and/or low mean tidalvalues for a specific site can be done with tidalprediction programs, or by accessing the informationat many internet sites including NOAAs at www.co-ops.nos.noaa.gov. It is important to relate the datumused for topographical data at the project site with thetidal datum established for that area. This should bedone by a person experienced