design of discontinuous water-using systems with a graphical method 2011
TRANSCRIPT
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 1/12
Chemical Engineering Journal 172 (2011) 799–810
Contents lists available at ScienceDirect
Chemical Engineering Journal
j ournal homepage : www.elsevier .com/ locate /ce j
Design of discontinuous water-using systems with a graphical method
Jin-Kuk Kim∗
Department of Chemical Engineering, Hanyang University, 17, Haengdang-dong, Seongdong-gu, Seoul 133-791, Republic of Korea
a r t i c l e i n f o
Article history:
Received 3 March 2011
Received in revised form 21 June 2011
Accepted 22 June 2011
Keywords:
Water pinch analysis
Water reuse
Water minimisation
Discontinuous water use
a b s t r a c t
A systematic approach using the graphical representation of water use and its system-widemanipulation
is proposed for minimising freshwater and wastewater generation for discontinuous water systems.
Design interactions of time-dependant water reuse and implications of storage tank in the network
design have been fully addressed, and a new targeting and design method has been proposed to provideguidelines for achieving minimum freshwater requirements and to design the configuration of water
re-use networks. Design complexity associated with simultaneous consideration of concentration and
time constraints has been effectively dealt with in the proposed design method, which clearly provides
benefits by reducing water consumptions and maintaining sustainable water usage.
© 2011 Elsevier B.V. All rights reserved.
1. Introduction
Waterisoneofthekeyresourcesinmanufacturingasitiswidely
used as heat transfer media, for example, cooling water and steam,
and mass transfer agents, for example, water for washing, strip-
ping steam. The efficient use of freshwater with less generation
of wastewater to the environment has been regarded one of the
priorities in process industries, in order to minimise costs associ-
ated with water use and its discharge, as well as to ensure much
reduced environmental burden to the society. Minimising water
consumption and, consequently, wastewater generation from pro-
cess industries can be made through various measures, including
process changes, water reuse and water recycling.
The way to use water is dependent on how the process
is designed and operated, and therefore water requirement for
the process can be reduced by adopting appropriate change of
processing mechanism or design. This might be regarded as a
straightforward option to be considered for water reductions, as
process changes for a particular process canbe made in isolationto
other parts of theplant. However, process changes canbe problem-
atic due to practical and engineering constraints, and may requireheavy capital expenditure to accommodate the change.
On the other hand, water reuse and recycling has been widely
considered and implemented in process industries as a practical
method for water conservation. As long as the reused or repro-
duced water does not degrade the quality of product and process
performance, reusing water with/withoutregenerationcan be seen
as a cost-effective and practical approach. However, it is not an
∗ Tel.: +82 2 2220 2331.
E-mail address: [email protected]
easy task to identify the most appropriate manner of water reuse
andrecycling, especially, in industrial practice,where a large num-
ber of water-using operations are involved with complex design
interactions among them.
In order to investigate water-using systems in a holistic way, a
system-wide analysis has been proposed by Wang and Smith [1]
who introduced the graphical definition of water usage in pro-
cess operations and provided a design procedure to manipulate
graphically the profiles of water usage for obtaining minimum
water requirements. This design framework also includes a design
method of water-using networks which achieve the target. One
of the significant benefits from using their method is to screen
all the available system-wide opportunities for water re-use, as
well as to provide conceptual understanding and insights of water
network design problem. Water regeneration and recycling had
been also investigated by Wang and Smith [1], which allows fur-
ther reductions of freshwater consumption at theexpense of water
regeneration cost. This graphical design method had been further
extended to cover the wide range of design problems in water
systems, including treatment systems using distributed treatment
concepts, design with water-using operations and treatment sys-tems together, water reuse for multi-component systems and
network design with process or engineering constraints [2–7].
There are limitations associatedwith graphical design methods.
For example, it is not straightforward to design large-size indus-
trialwatersystems in which multi-component analysisis necessary
and complex design interactions between various water-using and
water-treating units are to be systematically investigated. These
practical and computational issues have been addressed by adopt-
ing mathematical programming and optimisation techniques, with
which practical constraints canbe readily added, as wellas rigorous
economic trade-off can be effectively carried out [8–12].
1385-8947/$ – seefrontmatter © 2011 Elsevier B.V. All rights reserved.
doi:10.1016/j.cej.2011.06.066
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 2/12
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 3/12
J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810 801
in the design. Recent review papers by Gouws et al. [21] has
provided the detailed overview and summary of contribution
made by process integration and system engineering communities
in the area of water system studies in batch and semi-batch
processes.
Although the automated design method has contributed by
providing a decision-support tool for water and wastewater min-
imisation in discontinuous processes, it is still required to fully
gainthe fundamental understanding of time-dependency on water
reuseand its design implicationsfor water network,whichwill help
engineers to implement water reuse in various industrial practices.
Therefore, the development of a graphical design methodology has
been aimed at providing systematic targeting and design tools for
the use and reuse of water when concentration and timing infor-
mation has to be simultaneously considered in a single design
framework. Drawbacks identified from previous studies of Wang
and Smith [13] and Majozi et al. [14] have been addressed as a
new design method proposed in this paper which considers those
issues systematically. This includes that the requirement of stor-
age capacity and its interactions in the water network design is
fully considered; water flowrate for each operation is notfixed, but
varied when targeting and designing of water-using operations are
made; water reuse is considered for the operation as long as the
concentration constraints are met.The paper is organised to explain a new targeting method
first, which is then followed by a novel design procedure for
the water network. Three case studies are illustrated to demon-
strate the effectiveness and robustness of the developed design
method, and the limitation of the developed method has been also
discussed.
2. New designmethod: targeting
The proposed design methodology has two steps: targeting
and network design. The targeting is to represent time-dependant
water-using operations and their water use in a unified and inte-
grated format, to collectively investigate overall characteristics of
time-dependant water use and re-use, and to obtain minimumwater requirement for the water systems.
The newdesignmethodpresentedin thispaper adopts thelimit-
ingwater flowprofile conceptused in Kim andSmith’soptimisation
study [19] f or discontinuous water systems, as shown in Fig. 3.
For continuous water processes, the limiting water conditions are
defined with the rate of mass load to be transferred to the water
stream, and maximum allowable water concentration for inlet and
outlet, while the limiting water flow profile, for time-dependant
water systems, is based on overall mass load to be transferred to
the water stream, which inherently includes timing information by
multiplying time duration with the rate of mass load. It should be
Fig. 3. Limiting water flow profile [19].
noted that any profiles below and at the limiting water flow pro-
file will be considered, which ensures that water flowrate to be
achieved in the design is not fixed, but varied, subject to targeting
and design procedure. Another point to be made is that the limit-
ing water flow profile is separately defined for each time interval
for all the water-using operations, which allows the identification
of reuse potentials within the same time interval as well as across
different time intervals.
In this study, the minimum water requirement or maximum
water re-use has been targeted in two parts, which provides
the boundary of target. A single figure for the target would be
ideal, however, identifying a unique target for minimum water
requirement using graphical representation and its manipulation
is not realistic, because both concentration and timing information
should be simultaneously taken into account. Using mathematical
programming and optimisation techniques is clearly an attractivealternative option for targeting purposes. But, this automated way
had been previously attempted [19] andit is aimed in this study at
creating conceptual understanding of design problems and provid-
ing fundamental knowledge for how time-dependant water reuse
should be considered in the design.
First, the minimum water requirement without considering
time constraints is identified, which is termed as “lower bound
targeting (LBT)”. LBT provides a theoretical minimum water
requirement, and the water flowrate obtained from LBT may not
always be achieved through the network design, due to time-
constraints. However, this LBT procedure provides valuable insight
200
4
400
40.5
100
C[ppm]
M[kg]
20.5
200
P1
8
400
30
100
C[ppm]
M[kg]
2.5
P2
P3 Pinch
Composite curve
Minimum flow
Lower boundtarget: 102.5 t
(a) (b)
Fig. 4. Example 1 – lower bound targeting.
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 4/12
802 J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810
Table 1
Example 1 – limiting water data [13].
Process Limiting
concentration
(ppm)
Limiting
flowrate (t/h)
Time (h)
C in C out T s T f
P1 100 400 100 0.5 1.5
P2 0 200 80 0 0.5
P3 100 200 50 0.5 1.0
of discontinuous water systems as how good the final designis can
be checked against the lower bound target.
The second part of the targeting approach is to consider time
constraints into the investigation of water re-use potential, but the
maximum reuse of water is only considered within the same time
interval, and the reuse possibility from previous time interval to
next through storage tank is not permitted. This procedure pro-
vides another target which canbe further reduced by implementing
water re-use between different time intervals. The identifiedupper
bound target results from conservative application of water re-use
as the multi-period nature of water re-use has not been fully con-
sidered. This upper bound targeting (UBT) method allows users toavoid possible poor design withmore freshwater flowrate required
than target from UBT.
The LBT and UBT will be explained with the example 1, as given
in Table 1, which includes limiting water data and time informa-
tionfor three water-using operations. It is assumed thatfreshwater
is available at the concentration of 0 ppm. The limiting water data
conditions are expressed in terms of limiting water flow profile,
based on limiting concentration and limiting flow. In LBT, the first
step of theprocedure is to draw individual limiting water flowpro-
files in the graph as shown in Fig. 4(a), and the single profile of
composite curve is created by combining three individual profiles
for each concentration interval as shown in Fig. 4(b). The manipu-
lation for creatinga single composite curve from individual profiles
follows the same method developed by Wang and Smith [1]. How-ever, the method in this paper is based on limiting water flow
profiles with which time duration of water-using operation has
been embedded, and, consequently, used for targeting of discon-
tinuous water-usingprocesses. The minimum flowtarget from LBT
is calculated to be 102.5t, which can be obtained from a simple
mass balance for the pinch point.
There are two steps for UBT, as illustrated in Figs. 5 and 6. The
first step of UBT is to divide time intervals based on the limiting
data, and to put individual water-using elements specific to the
particular time interval in the separate concentration and mass
load diagram. In Fig. 5, three time intervals (four boundaries based
on timing information) are first made, and individual operations
are represented in the each time interval, for example, the limiting
water flow profile of P2 is drawn in the first interval [0–0.5h], and
profiles of P3 and P1 are given in the second interval [0.5–1h]. The
water use of P1 is splitto twoparts, according to timing information,
which are put in the second and third time interval, respectively.
The second step of UBT is to analyse water re-use opportuni-
ties in each time interval and to find minimum freshwater flowrate
required for each interval separately. To screen maximum water
re-use potentials, it is required to create the limiting water flow
profiles and to obtain minimum freshwater flow separately by fol-
lowing the same approach used in LBT. The minimum freshwater
needed for each time interval are 40t for the first interval, 43.75 t
for the second interval and 37.5 t for the third interval, which gives
121.25t of freshwater flow as a upper bound target.
Upper bound target from UBT and lower bound target from
LBT provides the range of possible minimum flow which can be
achieved through network design explained in the following sec-
tion. Water reuse is only considered within a single batch orproduction campaign, which means that water re-use from pre-
vious batch to next batch is not allowed.
3. New designmethod: network design
The designof the network of water-using operations is made by
following a few design rules as below:
• Design rule 1: the network design is carried out in sequence from
the first time interval to the following interval, which allows full
utilisation of available water sources from the previous interval
to the next interval.
• Designrule2: reusing as much water from available watersourcesfrom previous time interval as possible is preferred as long as the
intake of freshwater can be reduced. Also, reusing wastewater
source(s) with the lowest concentration, other than freshwater,
is tobe fullyutilisedfirst. Thesewillminimisethe overallintake of
freshwater for the whole network. However, this strategy results
in the introduction of storage tanks for enabling water reuse in
Concentration
P2
40 t
200 ppm
8 kg
Mass load(M)
100 ppm
Mass load(M)
P1P3
Concentration
2.5 kg
200 ppm
400 ppm
25 t 50 t
17.5 kg
Concentration
Mass load(M)
P1
100 ppm
400 ppm
50 t
15 kg
h5.0h0 h5.1h1
Fig. 5. Example 1 – upper bound targeting (I).
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 5/12
J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810 803
Concentration
P2
40 t
200 ppm
8 kg
Mass load(M)
100 ppm
Mass load(M)
Concentration
200 ppm
400 ppm
43.75 t
17.5 kg
Designregion
Concentration
Mass load(M)
P1
100 ppm
400 ppm
50 t
15 kg
0.5 h h5.1h10 h
Compositecurve(P1 + P3)
Designregion
75 t
37.5 t
Upper bound target: 121.25 t (= 40 t + 43.75 t + 37.5 t)
Fig. 6. Example 1 – upper bound targeting (II).
different time intervals. As demonstrated by Kim and Smith [19],
the cost of storage tank is relatively cheap, and it is beneficial to
save further water requirements.• Design rule 3: once the selection of water source(s) to be used in
the particular timeinterval, the maximum re-use between opera-
tions is sought and the corresponding water network is designed
by following water main method developed by Kuo and Smith
[5]. The details of water main method are not explained in this
paper, butcan be found elsewhere, including Smith [22], asithad
been well established and widely applied.• Design rule 4: when more than one re-use possibilities exist, the
matching between water sources and sinks should be made such
that, first, the design to minimise freshwater consumption for
the particular time interval is selected. If there is no differencein freshwater requirements, then, the number of connections
between sources and sinks should be minimised. This strategy
helps to reduce piping cost and design complexities, although
piping cost is heavily dependent on hydraulic design of piping
systems and physical distances between water sources and sinks.
The design procedure for water network design is explained
with example 1. Based on the design rule 1, the design of first time
intervalis carried outfirst, whichthen followed bysecond and third
time interval. Fig. 7 shows the first time interval in which only one
water-using operation is employed. The freshwater flow required
for the first interval is 40t, and correspondingly, wastewater gen-
erated in the end of time interval is 40t with the concentration of
200ppm.For the second time interval, there are two water sources,
namely, 40t of wastewater generatedfrom the previoustime inter-
val at 200ppm (shown as intermediate water (I) in Fig. 8) and
freshwater at 0 ppm. By following design rule 2, wastewater from
intermediate water (I) is re-used, but the addition of freshwater
is required, because maximum inlet concentration allowed in this
time interval is 100 ppm. By mixing two sources of water equally,
100 ppm of water is generated and supplied to this time interval,
and the required freshwater is 37.5 t. From intermediate water (I),
37.5t of wastewater rare used, while 2.5 t of unused water will be
remained to be used for the next available time interval. The net-
work configuration of this time interval is shown in Fig. 8 suchthat
no re-use of water between operations are envisaged, due to the
same inlet maximum concentration allowed, by following design
rule 3. Water consumed in P1 and P3 can be used for the next time
interval as water sources at 200 ppm and 400ppm, respectively.
For the time interval between 1 h and 1.5 h, there are four water
sources available which include one from the first time interval,
two from the second time interval and freshwater (Fig. 9). The
200 ppm water source is selected, rather than 400 ppm the water
source, by following design rule 2, which will minimise the use of
freshwater. As the maximum inlet concentration acceptable for P1
is 100ppm, equal amounts of water from freshwater source and
200 ppm of water sources are combined to supply 50t to P1. There
are two possibilities for taking 25t of 200 ppmwater: one option is
to useintermediate water (II-b) only;the other optionis to useboth
sources of intermediate water (I-a) and (II-b). By following design
rule4, the designforthistimeintervalinclude only onewater re-usefrom intermediate water (II-b) as shown in Fig. 9.
Final water network design is obtained by simply assembling
the design of each time intervals and representing it in a single
network, as shown in Fig. 10. Overall freshwater requirement is
102.5, which achieves the lower bound target through the design,
Fig. 7. Example 1 – design: time interval [0–0.5h].
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 6/12
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 7/12
J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810 805
Table 2
Example 1 – results comparison.
Method Water
consumption (t)
Storage tank (t)
No water reuse 127.5 0
New conceptual design 102.5 62.5
Mathematical optimization [19] 102.5 37.5
while62.5t of storage capacityis necessaryto support water re-usebetween timeintervals. The result is compared withother methods
as shown in Table 2.
When a conventional method based on once-through water
usage is applied, 127.5 t of freshwater is consumed without inter-
mediate storage required. With the new design method, water
consumption is reduced by 19.6% at the expense of storage capac-
ity. Compared to the results obtained from an automated design
method [19], as well as to the design obtained with the aid of WCA
(Water Cascade Analysis) [15], the requirement of storage tanks
that results from the developed design method is bigger than opti-
mal although the required freshwater flowrate is the same.
4. Application of new designmethod
The new design methodology presented in this paper is applied
to a second example. Details of example 2 are given in Table 3,
which had been used in the study of Kim and Smith [16], and it
is assumed that the freshwater source is available at 0 ppm. The
procedure of LBT, gives 185t of minimum freshwater requirement,
while Fig. 11 shows the UBT, resulting in 211.25t of upper bound
target.
The first step of the design is to achieve the target between the
two boundaries obtainedfromUBT andLBT,so thedesignof the first
time interval [0–1h] is carried out. 20t of freshwater is consumed
in P1 andits effluent is availablefor re-use in thenext time interval.
In thenext time interval,the reuse of water from theintermedi-
ate water (I)does not contribute reducing theamount of freshwater
required. This is because water source for the reuse is available at100ppm, andthe maximum inletconcentration to the liming water
flow composite curve is also 100 ppm (Fig. 12). For example, if 20t
at 100ppm is fully reused in this time interval,freshwater required
is 100t and 120t of the water is supplied to this time interval at
16.7ppm. When no water from the intermediate water (I) is re-
used, 100 t of freshwater is still required. Therefore, by followingdesign rule 4, it is decided not to re-use water from the intermedi-
ate water (I). The rest of the designis based on design rule 3, which
identifies water re-use between P2 and P4 within this time inter-
val. Twoadditional water sources at 100 ppmand800 ppm, become
available from the result of water main method.
For the third time interval [3–3.5h] there are many potential
options for water reuse, due to three available water sources that
result from the design of previous two time intervals, as shown in
Fig. 13. One of the possibilities is to mix equal amounts of 35t from
water sources at 100 ppm and freshwater, which is then supplied
at 50ppm. From design rule 4, it is not beneficial to mix freshwa-
ter with the contaminated water in this case, as the same 35t of
freshwater is needed even if only freshwater is supplied. Another
possibility is to utilise water from the intermediate (II-b) source,
which requires more than 35t of freshwater. Therefore, freshwa-
ter is taken as a single water source for time interval [3–3.5h]. The
wastewater from P2 is reused for P3 after mixing with freshwater,
by following design rule 3. It should be noted that consideration
made in the second and third time intervals also contributes to
avoid unnecessary introduction of storage tanks.
Thefinaltimeinterval between 3.5h and5 h introduces themix-
ing between freshwater and intermediate (II-a) (Fig. 14). The four
sub-networks of water systems are nowcombined, as illustrated in
Fig. 15. The overall freshwater required for the final design is 185 t
with 30t of storage capacity, which satisfies the lower bound tar-
get. Table 4 illustrates the benefits of using the developed design
method, which compares with optimal results published by Kim
and Smith [19]. Against a design with no water reuse, considerable
cost saving with the reduction of freshwater demand is achieved.
The design identified from the developed graphical method coin-
cides with the design obtained from mathematical optimisation
when costs of freshwater and storage tanks are considered in theobjective function. When compared the result from the proposed
method in this paper to the network design in which piping cost is
simultaneously considered withfreshwater and storage tank costs,
it gives conceptual insightsthat pipingcostplaysan importantpart
in the water network design and the developed method is limited
to deal with more rigorous economic trade-off. However, Table 4
clearly illustrates the proposed design method is able to provide
significant savings for discontinuous water systems by systemati-
cally implementing water re-use under time constraints, although
optimal or near-optimal solutions may not be achieved.
5. Discussion onnew designmethod
Two examples illustrated in the previous sectionsdemonstrated
the applicability and usefulness of the new design method. How-
ever, there are a few issues to be addressed in terms of the
methodological limitation associated with the targeting concept
and design procedure presented in this paper.
As commented in the previous sections,the developedtargeting
provides the feasible range of possible target freshwater flowrate,
and it has been attempted to achieve as close to the lower bound
target as possible during the design. In examples 1 and 2, the net-
work design is based on the lower bound target flowrate. This may
not be the case for other design problems, which will be explained
with example 3. Table 5 shows the water data of four water-using
operations, of which water concentration and flow condition is
Table 3
Example 2 – limiting water data [19].
Process Limiting c oncentration
(ppm)
Limiting flowrate (t/h) Limiting flow (t) Time (h)
C in C out T s T f
P1 0 100 20 20 0.0 1.0
P2 50 100 100 2001.0 3.0
P4 400 800 10 20
P2 50 100 100 503.0 3.5
P3 50 800 40 20
P3 50 800 40 60 3.5 5.0
P2andP2 are the sameoperation; P3 and P3 arethe same operation.
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 8/12
806 J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810
100
3.5
400
800
35 t
70 t
17.5
50
C[ppm]
M[kg]
Compositecurve
(P2 + P3)
100
Designregion
10
400
800
18
50
C[ppm]
M[kg]
Compositecurve
(P2 + P4)
200 t
100 t
0 h 1 h 3 h
C[ppm]
P120 t
100
2M
[kg]
3.5 h 5 h
P3
800
56.25 t
45
50
C[ppm]
M[kg]
60 t
Upper bound target: 211.25 t (= 20 t + 100 t + 35 t + 56.25 t)
Fig. 11. Example 2 – upper bound targeting.
Table 4
Example 2 – results comparison.
Method No water reuse New graphical
design method
Mathematical optimization [19]a
Optimal
design 1
Optimal
design 2
Water Consumption (t) 230 185 185 190.6
Cost (k£ year−1) 368.0 296.0 296.0 305.0
Storage tank Capacity (t) – 30 30 45
Cost (k£ year−1) – 7.3 7.3 13.6
Piping cost (t) 150.1 170.8 170.8 123.6
Overall cost (k£ year−1) 518.1 (100%) 474.1 (91.5%) 474.1 (91.5%) 442.2 (85.3%)
a Design 1: objective function considersfreshwater and storage tank costs only.
Design 2: objective function considersfreshwater,piping and storage tank costs.
Fig. 12. Example 2 – design: time interval [1–3 h].
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 9/12
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 10/12
808 J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810
Fig. 15. Example 2 – final design.
Step 1: the design of water network is first carried out, assumingthat no water can be reused between different batches as it has
been done in the three previous examples.
Step 2: all the possible water sources which are to be discharged
from the current batch production, but can be reused in the next
batch production, are identified.
Step 3: the water network design for the next batch production is
repeated, but water sources identified from step 2 are included in
thenetworkdesign.Design rulesexplained in Section 3 are applied
to screen all the possible water sources and sinks, and select addi-
tional match which can further reduce freshwater consumption
for the next batch production.
Step 4: steps 2 and 3 are repeated until no improvements have
been achieved.
The design method extended for designing repeated batch pro-
cesses is now explained with example 3. The result of step 1 is
Fig. 17, which is the design for a single batch production and water
reuse is not considered beyond the single batch cycle. From step
2, water sources available for the next batch are identified, whichinclude discharged water of P3 in the first time interval, that of P2
and P3 in the secondtimeinterval, that of P1, P2 and P4 inthe third
time interval and that of P1 in the fourth interval. When additional
water sources are included in the design step 3, wastewater dis-
charged from P3 and P4 is not chosen for the water reuse from the
previous batch to the next batch, as 800ppm of wastewater does
notcontributefor reducingthe freshwater consumption.Water dis-
charged fromP1 or P2can be reused fromthe previous batch to the
next batch by mixingit with freshwater. Water reuse from P1 in the
third time interval [2.5–4.5h] of the previous batch to P3 in the first
time interval [0–1.5h] of the next batch is selected, as this match
reduces design complexities, compared to otherpotential matches.
IfP2inthethirdtimeintervalisselectedforthewaterreuseforP3in
thenext batch, water stream from P3 is split to three streams, lead-ingto a complex splittingjunction.Afterone iterationof steps 2 and
3, no improvement wasobservedand thewater network is finalised
as illustrated in Fig. 18. The final water network obtained for the
repeated batch production consumes 250 t of freshwater, which
Compositecurve
(P1 + P2 + P4)
100
2
400
800
140 t
22
50
C[ppm]
M[kg]
14
0 h 1.5 h 2.5 h 4.5 h 5 h
P3
800
56.25 t
45
50
C[ppm]
M[kg]
60 t
100
Designregion
10
400
800
18
50
C[ppm]
M[kg]
Compositecurve
(P2 + P3)
70 t
140 t
C[ppm]
P1
10 t
100
1M
[kg]
Uper bound target: 276.25 t (= 56.25 t + 70 t + 140 t + 10 t)
Fig. 16. Example 3 – upper bound targeting.
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 11/12
J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810 809
Fig. 17. Example 3 – final design.
corresponds to a lower bound target. This illustrates that thedesign
obtained in Fig. 18 achieves theoretical minimum water require-
ment for the discontinuous water systems by allowing repeated
water reuse between different batch productions.
The methodologypresented in this paper is based on the graph-
ical representation of water usage of water-using operation and
its manipulation for identifying the target and designing the net-
work configuration, and therefore, all the common drawbacks
documented for pinch analysis in the process engineering commu-
nities are also observed. This includes difficulties related to when
the methodology is applied for complex water network problems,
for example, a large number of water-using operations and multi-
contaminant systems, as well as when it is required to address
rigorous economic trade-offs.
However, it should be noted that the proposed method clearly
enables to reduce water consumptions considerably in the discon-
tinuous water systems by giving systematic design guidelines for
engineers, as well as provides methodological advantages by gain-
ing fundamental understanding of time-dependant water use and
reuse. Also, the method explained here helps users to consolidate
their confidence in applying process integration technologies to
discontinuous systems in practice.
Fig. 18. Example 3 – final design forrepeatedbatch processes.
8/12/2019 Design of Discontinuous Water-using Systems With a Graphical Method 2011
http://slidepdf.com/reader/full/design-of-discontinuous-water-using-systems-with-a-graphical-method-2011 12/12
810 J.-K. Kim / Chemical Engineering Journal 172 (2011) 799–810
6. Conclusions
A new systematic targeting and design method for the max-
imising water re-use in the discontinuous water systems has been
developed. First, the time-dependant reusability of water has been
screened by obtaining upper bound target and lower bound target.
Next, the design is carried out to achieve the lower bound target,
by systematically identifying water reuse within and beyond the
particular time interval, and the requirement of storage tank for
reusing water in the different time intervals. Three examples had
been used for illustrating the design methodology developed and
demonstrating the robustness and applicability of the method.
References
[1] Y.P. Wang, R. Smith, Wastewater minimisation, Chem. Eng. Sci. 49 (1994)981–1006.
[2] Y.P. Wang, R. Smith, Design of distributed effluent treatment systems, Chem.Eng. Sci. 49 (1994) 3127–3145.
[3] Y.P.Wang,R. Smith, Wastewater minimisationwith flowrate constraints,Trans.IChemE: Part A 73 (1995) 889–904.
[4] W.J. Kuo, R. Smith,Effluent treatmentsystemdesign, Chem. Eng. Sci. 52 (1997)4273–4290.
[5] W.J.Kuo, R. Smith, Designing for theinteractions between water-useand efflu-ent treatment, Trans.IChemE: Part A 76 (1998) 287–301.
[6] W.J. Kuo, R. Smith, Design of water-using systems involving regeneration,Trans. IChemE: Part B 76 (1998) 94–114.[7] S. Thevendiraraj, J. Klemes, D. Paz, G. Aso, G.J. Cardenas, Water and wastew-
ater minimisation study of a citrus plant, Resour. Conserv. Recycl. 37 (2003)227–250.
[8] S.J. Doyle, R. Smith, Targeting water reuse with multiple constraints, TransIChemE: Part B 75 (1997) 181–189.
[9] B. Galan, I.E. Grossmann, Optimal design of distributed wastewater treatmentnetworks, Ind. Eng. Chem. Res. 37 (1998) 4036–4048.
[10] A. Alva-Algáez, A. Kokossis, R. Smith, An Integrated Design Approach forWastewater Minimisation: Theory and Applications, IChemE Research Event,UK,1998.
[11] G. Huang, C. Chang, H. Ling, C. Chang, A mathematical programming modelforwater usage and treatmentnetwork design, Ind. Eng. Chem. Res. 38 (1999)2666–2679.
[12] M. Gunaratnam, A. Alva-Argaez,A. Kokossis,J. Kim,R. Smith, Automateddesign
of total water systems, Ind. Eng. Chem. Res. 44 (2005) 588–599.[13] Y.P. Wang, R. Smith, Time pinch analysis, Trans. IChemE: Part A 73 (1995)
905–914.[14] T. Majozi, C.J. Brouckaert, C.A. Buckley, A graphical technique for wastew-
ater minimisation in batch processes, J. Environ. Manage. 78 (2006) 317–329.
[15] D.C.Y.Foo,Z.A. Manan, Y.L.Tan, Synthesis of maximum waterrecovery networkforbatch process systems, J. Cleaner Prod. 13 (2005) 1381–1394.
[16] Y. Liu, X. Yuan, Y. Luo, Synthesis of water utilization system using concentra-tion interval analysis method(II) discontinuous process, Chin. J. Chem. Eng. 15(2007) 369–375.
[17] C.L. Chen,J.Y.Lee,A graphicaltechniquefor thedesignof water-usingnetworksin batch processes, Chem. Eng. Sci. 63 (2008) 3740–3754.
[18] M. Almato, A. Espuna, L. Puigjaner, Optimisation of water use in batch processindustries, Comput. Chem. Eng. 23 (1999) 1427–1437.
[19] J. Kim,R. Smith, Automateddesignof discontinuouswater systems,ProcessSaf.Environ. Prot. 82 (B3) (2004) 238–248.
[20] T. Majozi, An effective technique for wastewater minimisation in batch pro-cesses, J. Cleaner Prod. 13 (2005) 1374–1380.
[21] J.F. Gouws,T. Majozi, D.C.Y.Foo,C. Chen,J. Lee, Waterminimization techniquesforbatch processes, Ind. Eng. Chem. Res. 49 (2010) 8877–8893.
[22] R. Smith, Chemical Process Design and Integration,Wiley, Chichester, 2005.