design criteria for work order # c-19034 caltrans road ...lmud 60 kv transmission line relocation...
TRANSCRIPT
DESIGN CRITERIA
For
Work Order # C-19034 CalTrans Road Widening Project
State Route 36 West of Goodrich Creek to Fredonyer Campground
Revision C
Prepared by:
Electrical Consultants, Inc.
3521 Gabel Road Billings, MT 59102
QA/QC Review and Sign-Off:
Task Responsible Individual Date Prepared Transmission Engineer Tony Trudnowski 9/18/19 Reviewed Transmission QA/QC Will Waylander 9/19/19
Issued Project Manager Kent Schacht 9/24/19
COPYRIGHTED Copyright @ 2019 Electrical Consultants, Inc., Billings, MT All Rights Reserved, Unauthorized Reproduction Prohibited
LMUD 60 KV TRANSMISSION LINE RELOCATION
i
Table of Contents
1.0 PROJECT SUMMARY ....................................................................................................... 1-1 Project Overview .......................................................................................................... 1-1 General Design Consideration ...................................................................................... 1-1
Route Information ................................................................................................ 1-1 Survey Information .............................................................................................. 1-2 Right-of-Way (ROW) .......................................................................................... 1-2 Geotechnical Investigation ................................................................................... 1-2 Structures ............................................................................................................. 1-2 Foundations .......................................................................................................... 1-2 Conductors, Shield Wires and OPGW ................................................................. 1-2 Insulators .............................................................................................................. 1-3 Aerial Markers ..................................................................................................... 1-3 Transposition Structures (does not apply to this project) .................................... 1-3 Removal of Existing Facilities ............................................................................. 1-3 Switch Structures (does not apply to this project) ............................................... 1-3 Distribution Underbuild ....................................................................................... 1-3
2.0 ELECTRICAL DESIGN CRITERIA .................................................................................. 2-1 Maximum Ampacity of Standard Conductor ................................................................ 2-1 Overhead Ground Wires ............................................................................................... 2-1 Insulation and Hardware ............................................................................................... 2-1
Insulators .............................................................................................................. 2-1 Insulator Swing .................................................................................................... 2-1 Splicing ................................................................................................................ 2-2 Dampers and Spacers ........................................................................................... 2-2
Lightning Protection and Grounding ............................................................................ 2-2 Lightning Protection ............................................................................................ 2-2 Structure Grounding............................................................................................. 2-2 Bonding ................................................................................................................ 2-2 Splice Enclosures ................................................................................................. 2-2 Touch Potential .................................................................................................... 2-2 Fence Grounding .................................................................................................. 2-3
Transmission Line Impedance ...................................................................................... 2-3 Transmission Phasing ................................................................................................... 2-3
3.0 STRUCTURAL DESIGN CRITERIA ................................................................................. 3-1 Codes and Standards ..................................................................................................... 3-1 Failure Containment ...................................................................................................... 3-1 Weather Cases ............................................................................................................... 3-1 Structure Design ............................................................................................................ 3-1
Loading and Strength Factors .............................................................................. 3-2 Structure Types .................................................................................................... 3-2
Hardware Requirements ................................................................................................ 3-2 Guys and Guy Anchor Requirements ........................................................................... 3-2 Guy Strain Insulators .................................................................................................... 3-2 Insulator String Strength Factors .................................................................................. 3-2
LMUD 60 KV TRANSMISSION LINE RELOCATION
ii
Conductors and Shield Wires........................................................................................ 3-3 Wire Tension Criteria ................................................................................................... 3-3
4.0 CLEARANCE DESIGN CRITERIA ................................................................................... 4-1 General .......................................................................................................................... 4-1 Vertical Clearances ....................................................................................................... 4-1 Vertical Clearance between Wires ................................................................................ 4-1 Horizontal Clearance between Adjacent Circuits ......................................................... 4-1 Vegetation ..................................................................................................................... 4-1 Galloping....................................................................................................................... 4-2 EMF Clearances (not required for L-G voltages less than 98 kV, NESC 232.D.3.c) .. 4-2
5.0 EMBEDMENT AND FOUNDATION DESIGN CRITERIA ............................................. 5-1 Maximum Loading ........................................................................................................ 5-1 General Embedment Design ......................................................................................... 5-1 Concrete Design ............................................................................................................ 5-1 Reinforced Drilled Pier Design ..................................................................................... 5-1 Design Software ............................................................................................................ 5-1 Monopole/Three-Pole Deflection and Rotation Criteria ............................................... 5-1 H-Frame Criteria ........................................................................................................... 5-1
6.0 ENVIRONMENTAL DESIGN CRITERIA ........................................................................ 6-1 APLIC ........................................................................................................................... 6-1
Locations with Larger Birds ................................................................................ 6-1 Vertical Clearances .............................................................................................. 6-1 Tangent Posts ....................................................................................................... 6-1 Braced Posts ......................................................................................................... 6-1 Strain Insulators ................................................................................................... 6-1 Bird Flight Diverters ............................................................................................ 6-1 Bird Discouragers ................................................................................................ 6-2
Storm Water Pollution Prevention Plan (SWPPP)........................................................ 6-2 Fire Regulations ............................................................................................................ 6-2
7.0 ADDITIONAL INFORMATION ....................................................................................... A-1 References .................................................................................................................... A-1
Appendix A Weather Cases
Appendix B Structure Loading and Strength Factors
Appendix C Clearance Table
Appendix D Conductor Sizing
Appendix E Line Rating
Appendix F Impedance Calculations
LMUD 60 KV TRANSMISSION LINE RELOCATION
iii
Appendix G ROW Calculations
Appendix H Insulator Assemblies
LMUD 60 KV TRANSMISSION LINE RELOCATION
1-1
1.0 PROJECT SUMMARY
Project Overview
The CalTrans Road Widening Project 60 kV Transmission Line “Project” is located near Westwood in Lassen County, California in a GO95 Heavy Loading District. The project includes rerouting portions of two single circuit 60 kV lines where necessary in order to add driving lanes to Highway 36. The lines include intermittent underbuilds and taps. The lines will be designed and constructed to meet the minimum requirements as set forth by GO95 and NESC. Specifically, the design will satisfy GO95 Heavy Loading District requirements for Grade A construction and satisfty NECS Medium District requirements for Grade B construction, both codes are required to be satisfied in the state of California. Where one code is greater, the driving code will be chosen and satisfied.
General Design Consideration
Route Information
Lassen Municipal Utility District (LMUD) will be responsible for developing the route with technical input provided by ECI. An attempt will be made to keep the lines within their existing Right-of-Ways (ROWs) where possible. Terrain: The transmission line is routed through heavy forestry with
moderate elevation changes. The specific locations of interest involve crossing a highway, and it is therefore possible that span lengths will not be equal in locations of relocation and that change in tension sections is possible.
Access: The route will primarily be accessible from local roads, where structure access is presumed to be along the right-of-way (ROW).
Structures: There is some existing infrastructure along the route. Infrastructure includes: Highway 36, rural roads, and houses.
Utilities: There are existing distribution and transmission lines along the route.
Public lands: The route is a current ROW and includes stretches through Lassen National Forest.
Roads: Route runs along and crosses Highway 36 in three locations Constraints: Land constraints include environmentally sensitive areas such as
forested areas and wetlands. The route stays within the current ROW as much as possible to avoid these constraints.
LMUD 60 KV TRANSMISSION LINE RELOCATION
1-2
Survey Information
Survey data has been provided. If needed, additional survey will be requested in locations specific to areas of the lines which may need to be relocated. The coordinate system for the lines were defined as State Plane, NAD83, California I, International Feet.
Right-of-Way (ROW)
Wherever relocations are performed, ROW will comply with applicable codes, including: NESC, RUS, local, state, and other national codes. Conductor displacement shall be determined based on structure configuration, weather cases listed in Table 1.2.3, and structure deflection.
Table 1.2.3: ROW Clearances 1 At Rest 9.7 ft.2 NESC Clearance 6 psf. 6.7 ft.3 Extreme Wind 20.736 psf. (90 mph) 1 ft.1
4 GO95 At Rest 6 ft.Notes: 1. Extreme wind from NESC 250C and ASCE 7-05, 50 year Mean Recurrence Interval (MRI)
Geotechnical Investigation (does not apply to this project)
Structures
The Project is to be constructed with wood monopole and H-frame structures. Typical structure heights range from 45 feet to 70 feet above ground-line. Structure geometry is clearly identified on structure detail drawings, drawing series T003.
Foundations
The foundations for the Project are to be direct embed. The single circuit tangent structures or non-containment structures with less than a 2° line angle shall be backfilled with an engineered backfill. For more detailed information regarding the design of the foundations, see Section 5.0 of this document.
Conductors
Conductor for both of the single circuit overhead 60 kV transmission lines is single conductor 477 kcmil 19/0 strand AAC “COSMOS”. There is a stretch (From str. 1-7/7 to str. 1-9/5) of 2.4kV underbuild consisting of single conductor #2 AWG 7/1 strands ACSR “SPARATE” For more detailed information regarding the conductor design, see Section 2.1, and Section 2.2 of this document.
LMUD 60 KV TRANSMISSION LINE RELOCATION
1-3
Insulators
Insulators shall be single post-type assemblies for new monopole tangent structures and suspension bell-string type assemblies H-frame tangent structures. Bell-string type assemblies will also be used for new deadend structures. The lines shall be designed to operate at 60 kV phase-to-phase. For more detailed information pertaining to the insulator design, see Section 2.3 and Section 3.7 of this document.
Aerial Markers
The project is not located in the immediate vicinity of any airports. Structure locations and heights will not be evaluated during detailed design.
Transposition Structures (does not apply to this project)
Removal of Existing Facilities
Removal of existing structures shall be in accordance with the outage plan. All parties affected by any outage and or the removal of the existing line shall coordinate with the Invenergy to ensure proper communication between all parties. The Engineer will provide a list of removal units as material needed to facilitate the outage and any additional hot work which may be required.
Switch Structures (does not apply to this project)
Distribution Underbuild
Distribution underbuild will be designed to accomodate the 2.4kV existing factilities. Locations can be found on the Staking Sheets. Distribution assemblies will be single phase #2 AWG 7/1 kcmil Sparate ACSR with one conductor and one neutral conductor.
LMUD 60 KV TRANSMISSION LINE RELOCATION
2-1
2.0 ELECTRICAL DESIGN CRITERIA
Maximum Ampacity of Standard Conductor
The emergency or maximum operating temperature for line rating and used in part for calculating vertical clearances is 100°C. Normal operating temperature for the line based on a conductor temperature of 75°C.
Overhead Ground Wires (does not apply to this project)
Insulation and Hardware
Insulators
Minimum insulator insulation values are listed in Table 2.3.1 below. A contamination level of Light has been assumed for the required leakage distance. Insulator strength factors are provided in Section 3.8 of this document. Insulator cut sheets have been provided as part of Appendix H.
Table 2.3.1: Insulation Values1
Insulator Assembly
60 kV
LeakageDistance
(in)
60-Hz Dry Flashover
(kV)
60-Hz Wet Flashover
(kV)
Critical Impulse Positive
(kV)
Critical Impulse Negative
(kV)
Vertical Post 63 255 235 385 505
Horizontal Post 63 255 235 385 505
2-bell suspension (2.4 kV)
23 160 100 250 260
5-bell suspension 57.5 400 250 625 650
6-bell suspension (deadend)
69 480 300 750 780
Distribution Vertical Post (2.4kV)
5 45 25 70 85
Notes: 1. Insulation values listed above exceed those required by code, NESC 2017 273.
Insulator Swing
All insulator designs have been analyzed utilizing insulator swing analysis software within PLS-CADD. Allowable insulator swing angle is dependent upon insulator assembly geometry. Structure and insulator geometry has been selected to prevent electrical clearance violations to the structure under required weather conditions. These weather conditions are defined in Table 2.3.2.
LMUD 60 KV TRANSMISSION LINE RELOCATION
2-2
Table 2.3.2: Insulator Swing Cases
Case Number Case Description Required
Clearance to Structure (in.)
Condition 1: No Wind, 60°F, conductor at Creep RS 251 Condition 2: 6 psf. wind, 32°F, conductor at Initial RS 16 Condition 3: 6 psf. wind, 60°F, conductor at Creep RS 16 Condition 4: 90 mph, 60°F, conductor at Creep RS 5
1. The NESC requirement of 25 inches exceeds the GO95 requirement at the same weather case (No wind, 60°F, conductor in Creep condition)
Splicing
All dead end clamps, splices, and connectors will be specified as bolted type hardware or implosive joined. For purposes of design, splices shall be assumed to be full tension unless utilized for the installation of jumper wire. Splices shall not be placed over road spans or within one (1) span of a deadend structure or above crossings. The number of splices shall be per the Contractors stringing plan. The Contractors stringing plan shall be reviewed for pulling-tensioning site and splice locations for the conductor prior to issuing the 70% procurement package.
Dampers and Spacers (does not apply to this project)
Lightning Protection and Grounding
Lightning Protection (does not apply to this project)
Structure Grounding
All transmission structures should be grounded such that the resistance is less than or equal to 25 ohms. If during construction, a significant percentage of structures do not adhere to this resistance requirement, additional action should be taken to improve lightning mitigation performance.
Bonding
Neutral wire type is existing. Bonding wire has been selected to meet the GO 95 and NESC requirement of having a continuous ampacity of not less than one-fifth that of the conductors to which they are attached. All pole line hardware should be bonded.
Splice Enclosures (does not apply to this project)
Touch Potential
Maximum touch potential shall be determined for all objects accessible by the public and by utility crews if an analysis of AC interference for parallel utilities is
LMUD 60 KV TRANSMISSION LINE RELOCATION
2-3
required. IEEE Std. 80 and OSHA Std. 2207 part 1926 sets the guidelines for voltage and current density limits.
Fence Grounding (does not apply)
Transmission Line Impedance (does not apply to this project)
Transmission Phasing
The transmission phasing will be confirmed with phasing at the substations prior to issuing the 90% package for review. A phasing diagram located within the drawing series T006 will be provided for review with the 90% submittal package. There are not transposition structures located in the project.
LMUD 60 KV TRANSMISSION LINE RELOCATION
3-1
3.0 STRUCTURAL DESIGN CRITERIA
Codes and Standards
The structural design for the transmission line has been performed in accordance with the latest accepted revision of the following list of codes and standards:
RUS Bulletin 1724E-200, Design Manual for High Voltage Transmission Lines
National Electrical Safety Code C2-2017 (NESC 2017)
California Public Utilities Commission General Order No. 95 (G095), Rules for
Overhead Electric Line Construction
ASCE Manuals and Reports on Engineering Practice No. 74, Guidelines for Electrical Transmission Line Structural Loading
ACI 336.3, Report on Design and Construction of Dilled Piers
Other recognized standards are used when required to serve as guidelines for the design when they do not conflict with the above listed standards.
Failure Containment
Failure containment structures or deadend structures are defined as structures which are designed to support the full structural loading with either all ahead or all back span wires disconnected. Deadend structures should be considered at major crossings (such as over large roadways or waterways). Deadends should also be considered to limit cascading failures in long line sections. A minimum of one (1) deadend structure shall be placed every 5 miles to limit cascading failure.
Weather Cases
The weather cases in Appendix A shall be included when designing structures and shall be incorporated into the PLS-CADD model.
Structure Design
All structures shall be modeled in PLS-POLE and placed in a PLS-CADD model to check their strength and usage. Modeled structures shall match installed structures in geometry, embedment, attachment points, and strength.
LMUD 60 KV TRANSMISSION LINE RELOCATION
3-2
Loading and Strength Factors
All structures will be designed in accordance with NESC Section 25 loading criteria and NESC Section 26 structure strength criteria and as additionally required per GO95 Section IV. Wind shall be applied in the direction of greatest effect and largest applied stress. Construction cases shall also be considered to account for caught-in-block conductor or failing conductor splices. Deadend structures are designed for all intact load cases as well as controlling deadend loading. The structure loading and strength factors have been provided in Appendix B.
Structure Types
Transmission structures will utilize post and porcelain bells. Structure height and spacing will be clearly identified and provided with the staking sheets and plan and profile drawings, drawing series T005 and T004 respectively. Structures are monopole and H-Frame design. Running angle and deadend structures shall be direct embed.
Hardware Requirements
Hardware shall be designed to comply with NESC Section 26 and GO95 Section IV. All hardware shall be selected to have an ultimate strength greater than or equal to the element it attaches to the pole. Hardware shall also have dimensional compatibility with all attached members and be able to withstand all allowable swing angles.
Guys and Guy Anchor Requirements
Guy wires shall be installed at a tension of 2% of the wire’s ultimate tension and shall be within +/- 6 inches of specified horizontal placement. A strength reduction factor for guy wires is referenced in Appendix B. Anchors must not be rated for an ultimate strength less than that of the guy wire or that of the guy wire assembly where double guys are specified.
Guy Strain Insulators
Guy strain insulators shall be designed with a strength at least equal to the strength of the guy wire in accordance with NESC 279 and GO95 Section IV. A strength reduction factor equal to that of the guy wire shall be applied to the guy strain insulator. The guy strain insulator shall have a minimum rated dry flashover voltage equal to double the line voltage, a minimum rated wet flashover voltage equal to the nominal line voltage between conductors, and be made of fiber-reinforced polymer (NESC 279.A.1.b).
Insulator String Strength Factors
NESC Section 27 dictates the required insulator strength factors. The strength factors shown in Table 3.8 have been applied to their respective insulator configuration.
LMUD 60 KV TRANSMISSION LINE RELOCATION
3-3
Table 3.8: Insulator String Strength Factors Insulator Assembly
Configuration
GO95 Grade “A”1
NESC District Loading2
Extreme Loading Non-Ceramic2
Extreme LoadingPorcelain &
Glass2
Suspension
33% (% of ANSI
standard SML or M&E strength)
50% (% of ANSI
standard SML or M&E strength)
65% (% of ANSI
standard SML or M&E strength)
65% (% of ANSI
standard SML or M&E strength)
Dead-end Assembly
33% (% of ANSI
standard SML or M&E strength)
50% (% of ANSI
standard SML or M&E strength)
65% (% of ANSI
standard SML or M&E strength)
65% (% of ANSI
standard SML or M&E strength)
Line Post3
33% (% of ANSI
standard STL strength)
50% (% of ANSI
standard STL strength)
50% (% of ANSI
standard STL strength)
50% (% of ANSI
standard STL strength)
Pin
33% (% of ANSI
standard cantilever strength)
40% (% of ANSI
standard cantilever strength)
--
40% (% of ANSI
standard cantilever strength)
Notes: 1. From GO95 2018 Rule 44.1 2. From NESC 2017 277. 3. Line Post specified cantilever load for NESC District Loading is 40% (% of ANSI standard SCL strength).
Conductors
The 477 kcmil 19/0 strand AAC “COSMOS” is being used to match the existing line. Table 3.9 contains the physical characteristics of this conductor
Table 3.9: Conductor and Shield Wire Data
Name Size StrandingRated Strength
(lbs.) Diameter
(in) Area (in2)
Unit Weight(lbs./ft.)
COSMOS 477 kcmil 19/0 8360 0.793 0.374 0.4475 SPARATE #2 AWG 7/0 3640 0.325 0.0654 0.1067
Wire Tension Criteria
Conductor design tensions are designed to match existing tension, and area where tensions are increase or changed, sag tables will be provided.
LMUD 60 KV TRANSMISSION LINE RELOCATION
3-4
Table 3.10.1: Wire Stringing Criteria for Conductor
Weather Case Cable Condition % of Ultimate
NESC 250B Medium Initial RS 50 NESC 250C Initial RS 70 NESC 250D Initial RS 70
NESC 261H1C Initial RS 35 NESC 261H1C Creep RS 25
GO95 Loading 43.2 Initial RS 50 20°F Initial RS 20
LMUD 60 KV TRANSMISSION LINE RELOCATION
4-1
4.0 CLEARANCE DESIGN CRITERIA
General
Minimum clearances shall be taken at the closest energized parts of the overhead transmission line. Clearances shall comply with NESC 2017 at maximum line operating condition and with GO95 with a 60°F no wind weather case. See Appendix C for target design clearance tables. Refer to NESC 441 for live line maintenance clearance requirements.
Vertical Clearances
Vertical clearances for ground and objects below the transmission line are checked based on the following conditions:
Final sag at max operating conductor temperature of 212°F (100°C) 32°F, no wind, radial ice thickness from Rule 250B, Final Final unloaded sag, conductor temperature of 120°F Final sag at 60°F with no wind (GO95 requirement of 30’)
Vertical Clearance between Wires
Vertical clearances between wires have been analyzed for the conditions defined in Table 4.3. These conditions and associated wire-to-wire clearances have been analyzed based upon the intact condition of both conductor and shield wires. Wind has not been applied in the calculation of vertical clearance between wires.
Table 4.3: Conditions for Application of Clearance
Criteria Between Conductors Upper Conductor Lower Conductor
212°F, Final 60°F, Final 32°F, radial ice thickness from Rule 250B, Final 32°F, Final
Horizontal Clearance between Adjacent Circuits
If vertical clearance is met, no horizontal clearance will be considered. If vertical clearance is not met, the horizontal wire-to-wire clearance shall be based on GO95 and NESC 235.
Vegetation
Where overhead conductors traverse trees and vegetation, necessary and reasonable clearances are to be measured between line conductors and vegetation under normal conditions. See Appendix C for radial clearance of bare line conductors from tree branches or foliage.
Additional clearances beyond those stated in Appendix C may be deemed appropriate based on various factors such as: operating voltate, length of span, line sag, species type, growth rate and characteristics, local climate, elevation, and fire risk.
LMUD 60 KV TRANSMISSION LINE RELOCATION
4-2
Galloping
Galloping has been considered for the single-loop case for spans less than 600 feet and for the double loop case for spans greater than 600 feet, measured at the quarter span points (RUS Bulletin 1724E-200 6.5.1). The calculated Lissajous loops shall be separated by one-foot.
The loading criteria to determine the swing and sag of the conductors are (respectively):
32°F, radial ice thickness from Rule 250B, 2 psf. wind 32°F, radial ice thickness from Rule 250B, no wind
EMF Clearances (not required for L-G voltages less than 98 kV, NESC 232.D.3.c) (does
not apply to this project)
The vertical clearances to roads shall be increased, as required, due to the electric static effects and in efforts to limit the steady state current to no more than 5 mA per RMS current requirements of NESC 2017 Rule 232.D.3.c. A ground clearance of [40] feet for single circuits is generally required over roads to maintain this limit.
LMUD 60 KV TRANSMISSION LINE RELOCATION
5-1
5.0 EMBEDMENT AND FOUNDATION DESIGN CRITERIA
Maximum Loading
Loads used for the design of embedments and reinforced concrete dilled piers shall be determined using the maximum ground line reactions.
General Embedment Design
Tangent structures with a line angle less than 2° shall be direct embedded and backfilled with an approved engineered backfill. All embedments shall have appropriate properties to support end bearing. Embedments shall be designed considering lateral and axial-compression loading.
Concrete Design (does not apply to this project)
Reinforced Drilled Pier Design (does not apply to this project)
Design Software (does not apply to this project)
Monopole/Three-Pole Deflection and Rotation Criteria (does not apply to this project)
H-Frame Criteria
H-Frame foundations shall be designed in HFAD. Foundation loading shall not exceed the capacity of the soil for the four load cases where these groundline reactions occur:
1) Maximum uplift 2) Maximum moment and corresponding uplift 3) Maximum compression 4) Maximum moment and corresponding compression 5) Maximum compression (settlement)
Where ultimate loading with load factors is considered for all load cases with the exception of case five (5). Settlement shall be limited to two inches (2-in.) under maximum compression loading without load factors. The capacity of the soil shall be appropriately factored by the Geotechnical Contractor, but no further reduction shall be taken.
LMUD 60 KV TRANSMISSION LINE RELOCATION
6-1
6.0 ENVIRONMENTAL DESIGN CRITERIA
All structures in both design and placement shall be compliant with all components of the environmental assessment.
APLIC
APLIC standards are generally met by structures in lines over 138 kV without any modifications with respect to phase to phase and phase to ground configurations. For structures in lines under 138 kV, several items should be taken into consideration to meet APLIC standards and mitigate the danger to raptors and other large bird species.
Locations with Larger Birds
In locales with bird species that have a wing span of over 60 inches, greater horizontal clearances between energized and grounded parts should be considered. These species include Bald Eagles, Golden Eagles, Great Horned Owls, White Pelicans, and Storks. Projects in locations with these species present should be examined on a case by case basis to determine the best approach.
Vertical Clearances
APLIC recommends a vertical separation of 26-48 inches between energized and grounded parts.
Tangent Posts
If the tangent post insulated section is less than 60 inches, the insulators should not be bonded. However, this increases the risk of pole fires and if this risk is unacceptable, then insulator covers, perching deterrents, or longer insulators may be used alternatively.
Braced Posts
Braced post insulators are considered to be adequate perching deterrents for raptors and no additional raptor protection is required.
Strain Insulators
All strain insulators should be bonded. However, when jumper posts are used, there is a risk of perching raptors coming into contact with bonded hardware. To help mitigate this risk, insulator covers, perching deterrents, and insulators with longer insulated sections can be used alternatively.
Bird Flight Diverters
Bird flight diverters should be used in specified areas. They are generally of the PVC type and should be spaced at 15 feet to 30 feet intervals for moderate and high traffic areas, respectively. If two shield wires are used, then bird flight diverters should be staggered between each shield wire.
LMUD 60 KV TRANSMISSION LINE RELOCATION
6-2
Bird Discouragers
Bird discouragers shall be used if needed. Type, placement, and quantity shall be determined on a case by case basis.
Storm Water Pollution Prevention Plan (SWPPP)
A Storm Water Pollution Prevention Plan (SWPPP) should be developed and followed. The SWPPP should include measures for pollutant discharge protection as well as erosion and sediment control.
Fire Regulations
All State, County, National Forest Service, BLM, and any other regulatory administration’s fire safety guidelines and regulations shall be followed.
LMUD 60 KV TRANSMISSION LINE RELOCATION
7-1
7.0 ADDITIONAL INFORMATION
References
The applicable copies of the documents listed are the referenced published versions used in design.
National Electrical Safety Code C2-2017 (NESC 2017)
CPUC General Order 95 (GO95), Rules for Overhead Electric Line Construction
RUS Bulletin 1724E-200, Design Manual for High Voltage Transmission Lines
PLS-CADD Manual, Copyright Power Line Systems, Inc.
MFAD v5.2 Manual, FAD Tools International, LLC
HFAD v5.2 Manual, FAD Tools International, LLC
LMUD 60 KV TRANSMISSION LINE RELOCATION
A-1
APPENDIX A WEATHER CASES
Appendix A ‐ Weather Cases
DescriptionAir Density Factor (Q) (psf/mph^2)
Wind Velocity (mph)
Wind Pressure (psf)
Wire Ice Thickness
(in)
Wire Ice Density (lbs/ft^3)
Wire Ice Load (lbs/ft)
Wire Temp. (deg F)
Ambient Temp. (deg F)
Weather Load Factor
NESC Constant (lbs/ft)
Wire Wind Height Adjust Model
Wire Gust Response Factor
NESC 250B Medium(4psf, 0.25", 15°F, 0.2) 0.00256 39.5 4.0 0.25 57 0 15 1 0.2 None 1
NESC 250C (90 mph) 0.00256 90.0 20.7 0 0 0 60 60 1 0 NESC 2017 NESC 2017
NESC 250D (0.25", 30mph) 0.00256 30.0 2.3 0.25 57 0 15 15 1 0 None 1
NESC 261H1b Medium(15°F) 0.00256 0.0 0.0 0 0 0 15 15 1 0 None 1
NESC 261H1b.2 (60°F) 0.00256 0.0 0.0 0 0 0 60 60 1 0 None 1
NESC Blowout 234.A.2 (6psf, 60°F) 0.00256 48.4 6.0 0 0 0 60 60 1 0 None 1
GO95 Heavy Loading 43.1 0.00256 48.4 6.0 0.5 57 0 0 1 0 None 1
No Wind (SWING 1) 0.00256 0.0 0.0 0 0 0 60 60 1 0 None 1
Moderate Wind (SWING 2) 0.00256 48.4 6.0 0 0 0 32 32 1 0 None 1
Moderate Wind (SWING 3) 0.00256 48.4 6.0 0 0 0 60 60 1 0 None 1
High Wind (SWING 4) 0.00256 90.0 20.7 0 0 0 60 60 1 0 None 1
GALLOPING (SWING) 0.00256 28.0 2.0 0.25 57 0 32 32 1 0 None 1
GALLOPING (SAG) 0.00256 0.0 0.0 0.25 57 0 32 32 1 0 None 1
Extreme Ice (0.25", 30°F) 0.00256 0.0 0.0 0.25 57 0 30 30 1 0 None 1
Construction Loading (2psf, 60°F) 0.00256 28.0 2.0 0 0 0 60 60 1 0 None 1
Construction Loading (2psf, 30°F) 0.00256 28.0 2.0 0 0 0 30 20 1 0 None 1
LMUD 60 KV TRANSMISSION LINE RELOCATION
B-1
APPENDIX B STRUCTURE LOADING AND STRENGTH FACTORS
Appendix B ‐ Structure Loading and Strength Factors
Wire Vert. Load Factor
Wire and Struct.
Wind Load Factor
Wire Tension Load Factor
Struct. Weight Load Factor
Struct. Wind Area
Factor
Strength Factor
Steel Poles Tubular‐ Arms Towers
Strength Factor Wood Poles
Strength Factor
Concrete Poles
Ultimate
Strength Factor Guys
Strength Factor Non‐Tubular Arms
Strength Factor Braces
Strength Factor
Insulators
Strength Factor
Foundation
RULE 250B NESC 250B Medium(4psf, 0.25", 15°F, 0.2) 1.5 2.5 1.65 1.5 1 1 0.65 1 0.9 0.65 0.65 1 1
RULE 250C NESC 250C (90 mph) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 0.8 1
RULE 250D NESC 250D (0.25", 30mph) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 0.8 1
RULE 277 (250B) Post NESC 250B Medium(4psf, 0.25", 15°F, 0.2) 1 1 1 1 1 1 0.65 1 0.9 0.65 0.65 0.4 1
RULE 277 (250C) Post NESC 250C (90 mph) 1 1 1 1 1 1 0.75 1 0.9 0.75 0.75 0.4 1
RULE 277 (250D) Post NESC 250D (0.25", 30mph) 1 1 1 1 1 1 0.75 1 0.9 0.75 0.75 0.4 1
RULE 277 (250B) NESC 250B Medium(4psf, 0.25", 15°F, 0.2) 1 1 1 1 1 1 0.65 1 0.9 0.65 0.65 0.5 1
RULE 277 (250C) NESC 250C (90 mph) 1 1 1 1 1 1 0.75 1 0.9 0.75 0.75 0.5 1
RULE 277 (250D) NESC 250D (0.25", 30mph) 1 1 1 1 1 1 0.75 1 0.9 0.75 0.75 0.5 1
GO95 43.1 ‐ Grade B GO95 Heavy Loading 43.1 1 1 1 1 1 0.8 0.33 0.66 0.5 0.5 0.5 0.5 1
GO95 43.1 ‐ Grade A GO95 Heavy Loading 43.1 1 1 1 1 1 0.8 0.25 0.66 0.5 0.5 0.5 0.33 1
Extreme Ice (Factored) Extreme Ice (0.25", 30°F) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 0.8 1
Extreme Ice (Working) Extreme Ice (0.25", 30°F) 1 1 1 1 1 1 0.75 1 0.9 0.75 0.75 0.8 1
RULE 250B DE Back NESC 250B Medium(4psf, 0.25", 15°F, 0.2) 1.5 2.5 1.65 1.5 1 1 0.65 1 0.9 0.65 0.65 1 1
RULE 250B DE Ahead NESC 250B Medium(4psf, 0.25", 15°F, 0.2) 1.5 2.5 1.65 1.5 1 1 0.65 1 0.9 0.65 0.65 1 1
RULE 250C DE Back NESC 250C (90 mph) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 1 1
RULE 250C DE Ahead NESC 250C (90 mph) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 1 1
RULE 250D DE Back NESC 250D (0.25", 30mph) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 1 1
RULE 250D DE Ahead NESC 250D (0.25", 30mph) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 1 1
Extreme Ice DE Back (Factored) Extreme Ice (0.25", 30°F) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 1 1
Extreme Ice DE Ahead (Factored) Extreme Ice (0.25", 30°F) 1.1 1.1 1.1 1.1 1 1 0.75 1 0.9 0.75 0.75 1 1
Extreme Ice DE Back (Working) Extreme Ice (0.25", 30°F) 1 1 1 1 1 1 0.75 1 0.9 0.75 0.75 1 1
Extreme Ice DE Ahead (Working) Extreme Ice (0.25", 30°F) 1 1 1 1 1 1 0.75 1 0.9 0.75 0.75 1 1
Everyday Deflection Everyday Deflection (60°F) 1 1 1 1 1 1 1 1 1 1 1 1 1 2
Imbalanced Ice (Ahead w/Ice) Extreme Ice (0.25", 30°F) 1 1 1 1 1 1 1 1 1 1 1 1 1
Imbalanced Ice (Back w/Ice) Extreme Ice (0.25", 30°F) 1 1 1 1 1 1 1 1 1 1 1 1 1
Broken Wire NESC 250D (0.25", 30mph) 1 1 1 1 1 1 1 1 1 1 1 1 1
Pole Tip Deflect. Limit %
Description Weather case
Strength FactorsLoad Factors
LMUD 60 KV TRANSMISSION LINE RELOCATION
C-1
APPENDIX C CLEARANCE TABLE
Appendix C ‐ Clearance Table
Feat. Code Feature DescriptionLine From
Feature Top To Bottom
Aerial Obst‐ acle
Point is on Ground
Req Vert Clear 20kV (ft)
Req Horiz Clear 20kV (ft)
Req Vert Clear 60kV (ft)
Req Horiz Clear 60kV (ft)
128 MARSH No No Yes 0 0 25 0
132 STREAM_CL No No Yes 0 0 25 0
143 H_WATER_<20 No No Yes 0 0 27 0
151 PLAYGRND_EDGE No No Yes 0 0 0 0
198 GROUND_SHOT No No Yes 15 0 22 0
200 BUILDING_LINE No No Yes 0 0 0 0
206 ROOF_LINE No Yes No 0 6 12 6
207 ROOF_PEAK Yes No No 0 6 12 6
208 DWELLING_ROOF No Yes No 0 6 12 6
209 DWELLING No No Yes 0 0 0 0
210 STORAGE_TANK Yes No No 0 10 10 10
215 STORAGE_TANK_W_CATWAL Yes No No 0 10 12 10
220 SIGN Yes No No 0 10 10 10
223 STEEL_POST Yes No No 0 10 10 10
224 FLAG_POLE Yes No No 0 10 10 10
225 ANTENNA Yes No No 0 10 10 10
226 TRAFFIC_SIGNAL Yes No No 0 10 10 10
227 SIGNAL_CNTRL_BX No No Yes 0 0 0 0
251 MISC_STR_TOP Yes No No 0 10 10 10
296 TOP_OF_WALL Yes No No 0 10 10 10
297 CHIMNEY/STACK Yes No No 0 10 10 10
320 FENCE_LINE No No Yes 0 0 0 0
327 GUARD_RAIL Yes No No 0 10 10 10
328 FENCE_GATE_CL No No Yes 0 0 0 0
336 BENCH_MARK: Yes No No 0 0 0 0
340 SURVEY_CL No No Yes 0 0 0 0
401 CONC_RD_EDGE No No Yes 0 0 0 0
411 BIT_RD_EDGE No No Yes 0 0 0 0
412 BIT_PARKING No No Yes 0 0 0 0
421 GRAVEL_RD_EDGE No No Yes 0 0 0 0
431 UNMPRVD_RD_EDGE No No Yes 0 0 0 0
440 RR_TRACK_CL No No Yes 0 0 34 0
441 TOP_OF_RAIL Yes No No 0 0 34 0
446 SIDEWALK_FRONT No No Yes 0 0 0 0
447 SIDEWALK_BACK No No Yes 0 0 0 0
451 BRIDGE_EDGE No No Yes 0 0 0 0
455 CONC_CULVERT No No Yes 0 0 0 0
456 CR_MTL_CULVERT No No Yes 0 0 0 0
499 TRAIL No No Yes 0 0 0 0
799 INSUL_ATT_PT No Yes No 0 0 0 0
800 TA_DE No Yes No 0 0 0 0
812 TA_POST_C No Yes No 0 0 0 0
813 TA_STRING_C No Yes No 0 0 0 0
850 DA_DE No Yes No 0 4 6 4
851 DA_TANGENT No Yes No 0 4 6 4
852 DA_ELEV No Yes No 0 4 6 4
853 DA_XING No Yes No 0 8 8 8
862 SPAN GUY XING No Yes No 0 6 6 6
900 TRANS_POLE No No No 0 0 0 0
Appendix C
LMUD 60 KV TRANSMISSION LINE RELOCATION
D-1
APPENDIX D CONDUCTOR SIZING
Does not apply to this project
LMUD 60 KV TRANSMISSION LINE RELOCATION
E-1
APPENDIX E LINE RATING
Does not apply to this project
LMUD 60 KV TRANSMISSION LINE RELOCATION
F-1
APPENDIX F IMPEDANCE CALCULATIONS
Does not apply to this project
LMUD 60 KV TRANSMISSION LINE RELOCATION
F-1
APPENDIX G ROW CALCULATIONS
Does not apply to this project
LMUD 60 KV TRANSMISSION LINE RELOCATION
G-1
APPENDIX H INSULATOR ASSEMBLIES
Input:
Notes:1. Contamination level description, per RUS:
2.
Office: BillingsClient:
25
385
LMUD
Project No. LMUD-013
Objective:
Input
Subject: Insulation Calculations for Post - HPS #P250024S1020Project Name: Horselake to Susanville 60 kVBy: AJT Date: 9/20/2019 Chk. By: WFW Date:
Site Properties
9/24/2019 Rev. A
601.05
235
To calculate transmission insulation recommendations.
The lightning impulse flashover considerations of IEEE 1313 require a study to complete.
IEEE 1313.2-1999: IEEE Guide for the Application of Insulation CoordinationRUS Bulletin 1724E-200: Design Manual for High Voltage Transmission Lines
DescriptionNominal Ph-Ph Line Voltage (kV)
Symbol InputVT
Areas with industries not producing particularly polluting smoke and/or areas with average density of houses quipped with heating plants. Areas with high density of houses and/or rainfall. Areas exposed to winds from the sea but not less than 10 miles form the coast
540025
Light
ReferencesNESC C2-2017: National Electrical Safety Code
Description
--RIc
--
ManufacturerPart NumberStrike Distance (in)Leakage Distance (in)
P250024S102025
505
Insulator TypeInsulator is Bell String?
Line TOV, p.u.Elevation (ft)Footing Resistance (Ω)Lightning Impulse Current (kA)Contamination Level
Insulator Properties
60 Hz Dry Flashover (kV)60 Hz Wet Flashover (kV)Critical Impulse Flashover, Positive (kV)Critical Impulse Flashover, Negative (kV)Insulator Material Polymer
Post
HPS
63255
No
Detailed Calculations:
Results:
Negative Impulse (kV)
Tables 8-1 and 8-2 Recommendations - not provided for this voltage
Date:9/20/2019 Chk. By: WFW
Office: BillingsClient:
Subject: Insulation Calculations for Post - HPS #P250024S1020Project Name:By: TJT Date:
LMUD
Leakage Distance (in)
RUS 1724E-200 Recommendations - 60 kV
60 Hz Low Freq Dry (kV)
60 Hz Low Freq Wet (kV)
Positive Impulse (kV)
Horselake to Susanville 60 kV
Project No. LMUD-013
Rev. A
Contamination Considerations: Leakage Distance
Insulator Properties Summary
---- -- -- --
Table 8-4 Leakage Distance (in): 53.6
44.6
60 Hz Flashover (kV) 160.4
MiscellaneousImpulse Flashover 25kA Strike (kV): 676.4
Insulator PropertySatisfies IEEESatisfies CIGRESatisfies IECSatisfies NESC60 Hz Flashover (kV)
Critical Impulse Flashover (kV)
63
235
385
Leakage Distance (in)
Satisfies IEEE
Result
44.6155.4160.4676.4
Ins. Calc.41.360.8
Switching-Surge Considerations: Phase-to-Ground Flashover
Ic x R + √2 x V/√3 x T =
MethodIEEE
CIGREIEC
Leakage Distance (in)41.360.8
155.4347826Dry Flashover (kV)NESC 273 Requirements
IEEE 1313.2-1999
9/24/2019
Input:
Notes:1. Contamination level description, per RUS:
2.
Insulator TypeInsulator is Bell String?
Line TOV, p.u.Elevation (ft)Footing Resistance (Ω)Lightning Impulse Current (kA)Contamination Level
Insulator Properties
60 Hz Dry Flashover (kV)60 Hz Wet Flashover (kV)Critical Impulse Flashover, Positive (kV)Critical Impulse Flashover, Negative (kV)Insulator Material Polymer
Post
HPS
63255
No
Areas with industries not producing particularly polluting smoke and/or areas with average density of houses quipped with heating plants. Areas with high density of houses and/or rainfall. Areas exposed to winds from the sea but not less than 10 miles form the coast
540025
Light
ReferencesNESC C2-2017: National Electrical Safety Code
Description
--RIc
--
ManufacturerPart NumberStrike Distance (in)Leakage Distance (in)
P250024S223025
505
IEEE 1313.2-1999: IEEE Guide for the Application of Insulation CoordinationRUS Bulletin 1724E-200: Design Manual for High Voltage Transmission Lines
DescriptionNominal Ph-Ph Line Voltage (kV)
Symbol InputVT
Site Properties
9/24/2019 Rev. A
601.05
235
To calculate transmission insulation recommendations.
The lightning impulse flashover considerations of IEEE 1313 require a study to complete.
Subject: Insulation Calculations for Post - HPS #P250024S2230Project Name: Horselake to Susanville 60 kVBy: AJT Date: 9/20/2019 Chk. By: WFW Date:
Office: BillingsClient:
25
385
LMUD
Project No. LMUD-013
Objective:
Input
Detailed Calculations:
Results:
155.4347826Dry Flashover (kV)NESC 273 Requirements
IEEE 1313.2-1999
9/24/2019
Switching-Surge Considerations: Phase-to-Ground Flashover
Ic x R + √2 x V/√3 x T =
MethodIEEE
CIGREIEC
Leakage Distance (in)41.360.8
Satisfies IEEE
Result
44.6155.4160.4676.4
Ins. Calc.41.360.8
60 Hz Flashover (kV)
Critical Impulse Flashover (kV)
63
235
385
Leakage Distance (in)Insulator Property
Satisfies IEEESatisfies CIGRESatisfies IECSatisfies NESC
Insulator Properties Summary
---- -- -- --
Table 8-4 Leakage Distance (in): 53.6
44.6
60 Hz Flashover (kV) 160.4
MiscellaneousImpulse Flashover 25kA Strike (kV): 676.4
By: TJT Date:
LMUD
Leakage Distance (in)
RUS 1724E-200 Recommendations - 60 kV
60 Hz Low Freq Dry (kV)
60 Hz Low Freq Wet (kV)
Positive Impulse (kV)
Horselake to Susanville 60 kV
Project No. LMUD-013
Rev. A
Contamination Considerations: Leakage Distance
Negative Impulse (kV)
Tables 8-1 and 8-2 Recommendations - not provided for this voltage
Date:9/20/2019 Chk. By: WFW
Office: BillingsClient:
Subject: Insulation Calculations for Post - HPS #P250024S2230Project Name:
By A. E. Schwalm at 11:58 am, May 01, 2014
05-01-14
Input:
Notes:1. Contamination level description, per RUS:
2.
Insulator TypeInsulator is Bell String?
Line TOV, p.u.Elevation (ft)Footing Resistance (Ω)Lightning Impulse Current (kA)Contamination Level
Insulator Properties
60 Hz Dry Flashover (kV)60 Hz Wet Flashover (kV)Critical Impulse Flashover, Positive (kV)Critical Impulse Flashover, Negative (kV)Insulator Material Porcelain
Post
Victor
1745
No
Areas with industries not producing particularly polluting smoke and/or areas with average density of houses quipped with heating plants. Areas with high density of houses and/or rainfall. Areas exposed to winds from the sea but not less than 10 miles form the coast
540025
Light
ReferencesNESC C2-2017: National Electrical Safety Code
Description
--RIc
--
ManufacturerPart NumberStrike Distance (in)Leakage Distance (in)
8R5
85
IEEE 1313.2-1999: IEEE Guide for the Application of Insulation CoordinationRUS Bulletin 1724E-200: Design Manual for High Voltage Transmission Lines
DescriptionNominal Ph-Ph Line Voltage (kV)
Symbol InputVT
Site Properties
10/28/2019 Rev. A
2.41.05
25
To calculate transmission insulation recommendations.
The lightning impulse flashover considerations of IEEE 1313 require a study to complete.
Subject: Insulation Calculations for Post - Victor #8RProject Name: LMUD 60 KV Transmission RelocationBy: AJT Date: 10/28/2019 Chk. By: WFW Date:
Office: BillingsClient:
25
70
LMUD
Project No. LMUD-013
Objective:
Input
Detailed Calculations:
Results:
20Dry Flashover (kV)NESC 273 Requirements
IEEE 1313.2-1999
10/28/2019
Switching-Surge Considerations: Phase-to-Ground Flashover
Ic x R + √2 x V/√3 x T =
MethodIEEE
CIGREIEC
Leakage Distance (in)1.72.4
Satisfies IEEE
Result
1.820.06.7
627.1
Ins. Calc.1.72.4
60 Hz Flashover (kV)
Critical Impulse Flashover (kV)
17
25
70
Leakage Distance (in)Insulator Property
Satisfies IEEESatisfies CIGRESatisfies IECSatisfies NESC
Insulator Properties Summary
---- -- -- --
Table 8-4 Leakage Distance (in): 2.1
1.8
60 Hz Flashover (kV) 6.7
MiscellaneousImpulse Flashover 25kA Strike (kV): 627.1
By: TJT Date:
LMUD
Leakage Distance (in)
RUS 1724E-200 Recommendations - 2.4 kV
60 Hz Low Freq Dry (kV)
60 Hz Low Freq Wet (kV)
Positive Impulse (kV)
LMUD 60 KV Transmission Relocation
Project No. LMUD-013
Rev. A
Contamination Considerations: Leakage Distance
Negative Impulse (kV)
Tables 8-1 and 8-2 Recommendations - not provided for this voltage
Date:10/28/2019 Chk. By: WFW
Office: BillingsClient:
Subject: Insulation Calculations for Post - Victor #8RProject Name:
Input:
Notes:1. Contamination level description, per RUS:
2.
Insulator TypeInsulator is Bell String?
Line TOV, p.u.Elevation (ft)Footing Resistance (Ω)Lightning Impulse Current (kA)Contamination Level
Insulator Properties
60 Hz Dry Flashover (kV)60 Hz Wet Flashover (kV)Critical Impulse Flashover, Positive (kV)Critical Impulse Flashover, Negative (kV)Insulator Material Porcelain
Suspension, I-String
LAPP
57.5400
Yes
Areas with industries not producing particularly polluting smoke and/or areas with average density of houses quipped with heating plants. Areas with high density of houses and/or rainfall. Areas exposed to winds from the sea but not less than 10 miles form the coast
540025
Light
ReferencesNESC C2-2017: National Electrical Safety Code
Description
--RIc
--
ManufacturerPart NumberStrike Distance (in)Leakage Distance (in)
8200 -- 5 bells38.75
650
IEEE 1313.2-1999: IEEE Guide for the Application of Insulation CoordinationRUS Bulletin 1724E-200: Design Manual for High Voltage Transmission Lines
DescriptionNominal Ph-Ph Line Voltage (kV)
Symbol InputVT
Site Properties
9/24/2019 Rev. A
601.05
250
To calculate transmission insulation recommendations.
The lightning impulse flashover considerations of IEEE 1313 require a study to complete.
Subject: Insulation Calculations for Suspension, I-String - LAPP #8200 -- 5 bellsProject Name: Horselake to Susanville 60 kVBy: T. Trudnowskik Date: 9/20/2019 Chk. By: WFW Date:
Office: BillingsClient:
25
625
LMUD
Project No. LMUD-013
Objective:
Input
Detailed Calculations:
Results:
155.4347826Dry Flashover (kV)NESC 273 Requirements
IEEE 1313.2-1999
9/24/2019
Switching-Surge Considerations: Phase-to-Ground Flashover
Ic x R + √2 x V/√3 x T =
MethodIEEE
CIGREIEC
Leakage Distance (in)41.360.8
Satisfies IEEE
Result
44.6155.4156.7676.4
Ins. Calc.41.360.8
60 Hz Flashover (kV)
Critical Impulse Flashover (kV)
57.5
250
625
Leakage Distance (in)Insulator Property
Satisfies IEEE
Satisfies IECSatisfies NESC
Insulator Properties Summary
---- -- -- --
Table 8-4 Leakage Distance (in): 53.6
44.6
60 Hz Flashover (kV) 156.7
MiscellaneousImpulse Flashover 25kA Strike (kV): 676.4
By: TJT Date:
LMUD
Leakage Distance (in)
RUS 1724E-200 Recommendations - 60 kV
60 Hz Low Freq Dry (kV)
60 Hz Low Freq Wet (kV)
Positive Impulse (kV)
Horselake to Susanville 60 kV
Project No. LMUD-013
Rev. A
Contamination Considerations: Leakage Distance
Negative Impulse (kV)
Tables 8-1 and 8-2 Recommendations - not provided for this voltage
Date:9/20/2019 Chk. By: WFW
Office: BillingsClient:
Subject: Insulation Calculations for Suspension, I-String - LAPP #8200 -- 5 bellsProject Name:
Input:
Notes:1. Contamination level description, per RUS:
2.
Insulator TypeInsulator is Bell String?
Line TOV, p.u.Elevation (ft)Footing Resistance (Ω)Lightning Impulse Current (kA)Contamination Level
Insulator Properties
60 Hz Dry Flashover (kV)60 Hz Wet Flashover (kV)Critical Impulse Flashover, Positive (kV)Critical Impulse Flashover, Negative (kV)Insulator Material Porcelain
Strain, Deadend
LAPP
23160
Yes
Areas with industries not producing particularly polluting smoke and/or areas with average density of houses quipped with heating plants. Areas with high density of houses and/or rainfall. Areas exposed to winds from the sea but not less than 10 miles form the coast
540025
Light
ReferencesNESC C2-2017: National Electrical Safety Code
Description
--RIc
--
ManufacturerPart NumberStrike Distance (in)Leakage Distance (in)
8200 -- 2 bells15.5
260
IEEE 1313.2-1999: IEEE Guide for the Application of Insulation CoordinationRUS Bulletin 1724E-200: Design Manual for High Voltage Transmission Lines
DescriptionNominal Ph-Ph Line Voltage (kV)
Symbol InputVT
Site Properties
9/24/2019 Rev. A
201.05
100
To calculate transmission insulation recommendations.
The lightning impulse flashover considerations of IEEE 1313 require a study to complete.
Subject: Insulation Calculations for Strain, Deadend - LAPP #8200 -- 2 bellsProject Name: Horselake to Susanville 60 kVBy: AJT Date: 9/20/2019 Chk. By: WFW Date:
Office: BillingsClient:
25
250
LMUD
Project No. LMUD-013
Objective:
Input
Detailed Calculations:
Results:
68.87755102Dry Flashover (kV)NESC 273 Requirements
IEEE 1313.2-1999
9/24/2019
Switching-Surge Considerations: Phase-to-Ground Flashover
Ic x R + √2 x V/√3 x T =
MethodIEEE
CIGREIEC
Leakage Distance (in)13.820.3
Satisfies IEEE
Result
14.968.954.4
642.1
Ins. Calc.13.820.3
60 Hz Flashover (kV)
Critical Impulse Flashover (kV)
23
100
250
Leakage Distance (in)Insulator Property
Satisfies IEEESatisfies CIGRESatisfies IECSatisfies NESC
Insulator Properties Summary
---- -- -- --
Table 8-4 Leakage Distance (in): 17.9
14.9
60 Hz Flashover (kV) 54.4
MiscellaneousImpulse Flashover 25kA Strike (kV): 642.1
By: TJT Date:
LMUD
Leakage Distance (in)
RUS 1724E-200 Recommendations - 20 kV
60 Hz Low Freq Dry (kV)
60 Hz Low Freq Wet (kV)
Positive Impulse (kV)
Horselake to Susanville 60 kV
Project No. LMUD-013
Rev. A
Contamination Considerations: Leakage Distance
Negative Impulse (kV)
Tables 8-1 and 8-2 Recommendations - not provided for this voltage
Date:9/20/2019 Chk. By: WFW
Office: BillingsClient:
Subject: Insulation Calculations for Strain, Deadend - LAPP #8200 -- 2 bellsProject Name: