  • 8/13/2019 Design Authority for New Civil Reactor Build

    1/6

    Health and Safety

    Executive

    Design AuthorityFor

    New Civil Reactor Build

    Bob Jennings

    ND 6D

  • 8/13/2019 Design Authority for New Civil Reactor Build

    2/6

    Health and Safety

    Executive

    Definition of Design Authority?

    A part of the Licensees organisation with aduty to maintain the knowledge of the designintegrity of its nuclear facility throughoutwhole lifecycle of the facility.

    While maintaining the integrity of the safety case

    is an important element in the DAs role it isbroader than this covering detailed engineeringsubstantiation and supporting design

    documentation.

  • 8/13/2019 Design Authority for New Civil Reactor Build

    3/6

    Health and Safety

    Executive

    DA Roles INSAG 19 (not para 30)

    For example: Establish a detailed understanding of why the design

    is as it is.

    Develop an understanding of the experimental andresearch knowledge on which the design is based.

    Capture and retain design inputs such as basicfunctional requirements, performance requirements,safety goals and safety principles, applicable codes,standards and regulatory requirements, designconditions, loads such as seismic loads, interface

    requirements, etc.

  • 8/13/2019 Design Authority for New Civil Reactor Build

    4/6

    Health and Safety

    Executive

    DA Roles INSAG 19 (2)

    Develop a detailed knowledge of the designcalculations which demonstrate the adequacy of thedesign and the ability to reproduce the designcalculations if needed.

    Acquire an understanding of the inspections, analysis,testing, computer code validation and acceptancecriteria used by participating design organizations toverify that the design output meets the designrequirements.

    Understand the assumptions made in all the stepsabove, including assumptions related to operatingmodes or procedures, expected life history such aschanges in fluence, expected transients, etc.

    Review the implications of operating experience on thedesign.

  • 8/13/2019 Design Authority for New Civil Reactor Build

    5/6

    Health and Safety

    Executive

    DA- Employees and Contractors

    It is not expected that the Licensee will have tocover all technical areas in great depth with its

    own staff. Use of support contractors for very detailed

    areas of the facilitys design integrity is allowed.

    The Licensee however must have in-houseknowledge of all major technical areas at IC and

    practitioner level.

  • 8/13/2019 Design Authority for New Civil Reactor Build

    6/6

    Health and Safety

    Executive

    Links to Licence Conditions

    LC12 DULY AUTHORISED AND OTHER SUITABLYQUALIFIED AND EXPERIENCED PERSONS.

    LC14 SAFETY DOCUMENTATION.

    LC15 PERIODIC REVIEW. LC22 MODIFICATION OR EXPERIMENT ON

    EXISTING PLANT

    LC23 OPERATING RULES. LC28 EXAMINATION, INSPECTION, MAINTENANCE

    AND TESTING.