Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts Road, Plymouth, MA 02360 508-747-7900 extension 117 [email protected]

Upload: margarita-batchler

Post on 14-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Design and Implementation of Title 5 Systems and Small Package Treatment Plants

Presented by:

John B. McAllister, P.E.

Norfolk Ram Group, LLC

One Roberts Road, Plymouth, MA 02360

508-747-7900 extension 117

[email protected]

Page 2: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Wastewater HappensHow We Deal with it is very

important!

Page 3: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Health Impacts Associated with Wastewater

• Can carry/cause Disease• Nitrates harmful effects on infants• Drinking water contamination • Coastal Impacts

• Plant Growth• Algae Blooms• Fish Kills• Shellfish Bed Closures

Page 4: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Residential Areas without a Centralized Wastewater System

Regulated by 310 CMR 15.00 Title 5

On-Site Subsurface Disposal Systems

Page 5: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Inspections Required for Sale of Home Periodic for Large Systems and

Condominiums Must Inspect

TankDistribution BoxLeaching System (if accessible)

Failure – Conditions Validity of Inspection

Residential Areas without a Centralized Wastewater System

Page 6: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Title 5 System Design Planning Soil Evaluation Percolation Test

Page 7: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Title 5 System Design Planning

Design Plans

Page 8: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Title 5 System Implementation

Trenches

Page 9: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Title 5 System Implementation

Galleys

Page 10: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Title 5 System Implementation

Plastic Chambers

Page 11: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Title 5 System ImplementationInnovative/ Alternative

Technology• Nitrogen Sensitive Areas• High Groundwater• Site Constraints

Page 12: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Title 5 System Implementation

Operations & Maintenance• Pumping Bi-Annually• Removing Garbage Grinders• Avoid Dumping Bleach, Paint, and Solvents into System

• I/A Systems have specific maintenance considerations• Some BOH’s require O&M documentation and/or testing for I/A

Systems

Page 13: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Large Systems – Greater Than 10,000 gpd

Regulated by DEP – Groundwater Discharge Permit• Nutrient Loading Approach• Effluent Discharge Standards

• Water Reuse Standards• 30/30/10 Standard

Page 14: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Large Systems – Greater Than 10,000 gpd

Rotating Biological Contactor – RBC Treatment Plant• Residential Apartment Complexes• Commercial Buildings

Page 15: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Large Systems – Greater Than 10,000 gpd

RBC Treatment Plant• Residential Apartment Complexes• Commercial Buildings

Page 16: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Large Systems – Greater Than 10,000 gpd

RBC Treatment Plant

Control Panel• Pumps• Filters• Blowers

All Automated

Page 17: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Large Systems – Greater Than 10,000 gpd

Membrane Treatment Plant• Different Sized Membranes• Microfiltration- Ultrafiltration

Page 18: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Large Systems – Greater Than 10,000 gpdSBR Treatment Plant

• The Classic Treatment Plant• Most Municipal Facilities

Page 19: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Treatment Options and Effluent Characteristics

Typical Nitrogen Treatment Characteristics

Type of SystemTitle 5 System

I/A Technology System

Advanced Wastewater Treatment Facility

Water Re-use Standards

Nitrogen Load (mg/l) 35 20 10 5

Page 20: Design and Implementation of Title 5 Systems and Small Package Treatment Plants Presented by: John B. McAllister, P.E. Norfolk Ram Group, LLC One Roberts

Design and Implementation of Title 5 Systems and Small Package Treatment Plants

[email protected]

QUESTIONS?