design and implementation of lense2 - jisc€¦ · design and implementation of lense2 nws36,...

31
Design and Implementation of LeNSE2 NWS36, University of Strathclyde 8 th -10 th April 2008 Mike Byrne LeNSE CEO

Upload: others

Post on 23-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Design and Implementation of LeNSE2

NWS36,University of Strathclyde8th -10th

April 2008

Mike ByrneLeNSE CEO

Page 2: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 2

Topics

Background to procurement•

Limitations of LeNSE1

LeNSE2 procurement objectives•

Technical design issues & options

LeNSE2 implementation•

Key attributes of the LeNSE2 solution

Summary•

(If time: example of other potential solutions)

Page 3: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 3

Background to Procurement

LeNSE1:•

Was a 6 year ‘fully managed’

24x7 IP service contract with SSE

Telecom (SSET) which expired in September 2007.•

LeNSE did not own the core ‘P’

routers or the edge ‘PE’

routers.

LeNSE had no access to SSET’s

underlying transmission circuits.•

Core network was based on a Ring topology with 4 C-PoPs.

LeNSE member HEIs wanted no part in LeNSE2 service delivery, hence we had to continue using supplier C-PoP locations.

Therefore, for LeNSE2 we needed:•

A major reprocurement, rather than incremental upgrade.

A budget of circa £5M+ over 5 years to fund the procurement.

Page 4: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 4

LeNSE1 Network (2001-2007)

Page 5: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 5

Limitations of LeNSE1

Cisco GSR12000 ‘P’

core routers were becoming old and software upgrades problematical.

Cisco 7200 ‘PE’

edge routers did not exhibit carrier class performance with the original NSE-1 processors (NPE-G1s were better!).

The design had too many edge IP routers (2 per HEI).•

Bandwidth limitations on inter-core links (2x622Mbps SDH) were becoming restrictive.

MPLS was enabled by SSET but presented problems deploying IPv4 multicast and IPv6.

IP Resilience limited by Ring topology.

Page 6: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 6

LeNSE2 Procurement Objectives

OJEU Competitive Dialogue procurement process for-

A solution technically compliant with SJ5.

-

A new contract service model compliant with the JPA.•

Increased core infrastructure reliability & resilience

-

Five 9s reliability for transmission network and IP routers.-

Better C-PoP environments.

Simplified IP routing architecture-

Reduction of number of core and edge IP routers.

-

‘Dual homed star’

rather than IP ring topology?•

Reduction of Single Points of Failure

-

Resilience links for all core FE aggregation routers. -

Optional secondary links for member HEIs.

Page 7: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 7

Design issues (1)

IP Design –

Ring versus Dual Homed Star?•

Suppliers fell equally into both camps.

We concluded that the dual homed star architecture was technically superior as it offered greater resilience to circuit/interface failures, but is dependent on affordable transmission circuits/channels, especially for an RN the size of LeNSE.

Implementation needs High Availability (HA) router platforms and we concluded that protected DC power was highly desirable for all core routers.

Page 8: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 8

Ring Dual Homed Star

10

10

10 10 1010

10

10

1010

1

1010

11 1 1

111111

1

ADVANTAGES

of Dual Homed Star Network:• Cheaper 1GbE Interfaces on most routers.•

Improved resilience –

A circuit or interface failure only takes down one connection to one customer’s router. SJ5 RNEP failures do not cause loss of service. Very fast convergence (sub 500msec).• Routers only need to route their own 1GbE of traffic, and not the entire RN traffic (as in Ring case). •

More gradual incremental upgrade path –

Additional GbE

circuits can be added to serve specific individual sites –

the entire Ring doesn’t need upgrading.

MAIN DISADVANTAGE

of Dual Homed Star Network:•

Requires more transmission channels, but these can be cost effectively provided if access to DWDM wavelengths (dark fibre or leased).

Core ‘P’

RouterSite ‘PE’

Router10 Gbit/s

circuit1 Gbit/s

circuit10Gbit/s interface1Gbit/s interface

Key

10

1

Page 9: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 9

Design issues (2)

Optical Plant Requirements?•

Physical rings across our region add resilience.

LeNSE did not mandate use of G.655 (40Gbps) fibre; G.652 (10Gbps) was sufficient by using multiple 2.5Gbps or 10Gbps circuits on different wavelengths.

The key was access to multiple DWDM wavelengths.•

Also, it was advantageous if the supplier C-PoPs and fibre infrastructure already existed (lower risk to delivery timescale and reduced cost to the supplier).

Greatest challenge: Cost effective & timely access to extra wavelengths/circuits for future JANET Lightpath

channels

(pre-configured dynamic capacity adds £millions to cost).

Page 10: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 10

Design issues (3)

Transmission Equipment Options?•

We investigated a range of popular transmission products from the Ciena

4200 (SJ5) to the LuxN Gigabit (Neos).

All our potential suppliers used different products –

so hard to find preference but…a) Who is going to monitor, manage, maintain & develop the equipment?

Not us, hence product choice was best left to the suppliers.b) What level of product feature set and configuration flexibility is actually needed?

We concluded a design based entirely on point-to-point GbE

circuits would not require many changes and did not

require sophisticated transmission products. Product and transmission path reliability were more important to us.

Page 11: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 11

Design issues (4)

PoP design•

Separate East and West facing transmission circuits in difference transmission chassis for added resilience.

Where possible, East and West facing chassis should be housed in separate PoP racks on separate power feeds.

Use DC power.

Signal path versus Physical path•

Most suppliers have physical fibre rings, so dual homed star designs have to carry multiple circuits along ring segments.

Ring designs carry signal path through intermediate transmission nodes, hence more components in signal path.

Page 12: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 12

Signal Paths in Rings (Geo/Synetrix example)

M6

24 λ

24 λ

8 λ8 λ

8 λ8 λ

Band 3

F-10A F-10A

LeNSE PoP

1 λ

OTU2

1 λ

OTU2

Any other wavelengths, i.e. those that are not in Bands 1, 2 or 3

8 λ8 λ

Band 2

7604 RouterGBE Links

Ciena 4200 chassis

M6

24 λ

24 λ

8 λ8 λ

8 λ8 λ

Band 3

F-10A F-10A

LeNSE PoP

1 λ

OTU2

1 λ

OTU2

Any other wavelengths, i.e. those that are not in Bands 1, 2 or 3

8 λ8 λ

Band 2

7604 RouterGBE Links

Ciena 4200 chassis

M6

24 λ 24 λ8 λ8 λ8 λ8 λ

Band 3

F-10A F-10A

RNEP 1

1 λ

OTU2

1 λ

OTU2

Any other wavelengths, i.e. those that are not in Bands 1, 2 or 3

8 λ8 λ

Band 2

M6

12410 RouterGBE Links

M6

24 λ 24 λ8 λ8 λ8 λ8 λ

Band 3

F-10A F-10A

RNEP 2

1 λ

OTU2

1 λ

OTU2

Any other wavelengths, i.e. those that are not in Bands 1, 2 or 3

8 λ8 λ

Band 2

M6

12410 RouterGBE Links

M6

24 λ

24 λ

8 λ8 λ

8 λ8 λ

Band 3

F-10A F-10A

LeNSE PoP

1 λ

OTU2

1 λ

OTU2

Any other wavelengths, i.e. those that are not in Bands 1, 2 or 3

8 λ8 λ

Band 2

7604 RouterGBE Links

Ciena 4200 chassis

M6

24 λ

24 λ

8 λ8 λ

8 λ8 λ

Band 3

F-10A F-10A

LeNSE PoP

1 λ

OTU2

1 λ

OTU2

Any other wavelengths, i.e. those that are not in Bands 1, 2 or 3

8 λ8 λ

Band 2

7604 RouterGBE Links

Ciena 4200 chassis

10G from SJ5Working path 1G to HEI

10G from SJ5Bkup

path

1G to HEI

Page 13: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 13

Transmission reliability block diagram for production IP traffic

BkPlane M6 F10A

Pwr

Pwr

BkPlane F10A F10A

Pwr

Pwr

BkPlane M6 F10A

Pwr

Pwr

Fibre

BkPlane M6 F10A

Pwr

Pwr

BkPlane F10A F10A

Pwr

Pwr

BkPlane F10A F10A

Pwr

Pwr

FibreBkPlane M6 F10A

Pwr

Pwr

AMP AMP

AMP AMP

RNEP 1

RNEP 2

HEI

Geo/Synetrix model for calculating path reliability:Aggregate individual component MTBFs

to estimate overall

MTBF for each circuit

Page 14: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 14

LeNSE2 Contract Awards

Contract awards placed in December 2006:Neos Networks

for:

Lot 1 –

transmission network/servicesLot 5 –

additional bandwidth or circuits

Alcatel-Lucent

for:Lot 2 –

supply of new IP routers

Lot 3 –

systems integration/migration servicesLot 4 –

24x7 network monitoring service, 24x7 HEI/FEI

Help Desk service, spares management service and 24x7x4 equipment maintenance services

Page 15: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 15

LeNSE2 Implementation

LeNSE procured a managed transmission service from Neos:

Dedicated managed wavelengths across the Neos regional DWDM core (actually 30 Gbps

worth).

Dedicated LuxN Gigamux

DWDM transmission equipment in serving PoPs, configured in pairs of East and West facing chassis for added resilience.

All connected via fibre pairs dedicated to LeNSE.•

JANET Lightpath

solution: Initial capacity for up to 8

wavelengths via SJ5 RNEP1 (Southampton).

Page 16: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 16

Neos fibre network

Page 17: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 17

LeNSE2 Transmission network

Page 18: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 18

Connection details

Page 19: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 19

SJ5 JANET Lightpaths

Page 20: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 20

LeNSE2 IP network design (“dual homed star”)

Page 21: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 21

Juniper M120 Core ‘P’

HA Router

cFPCFPC

PIC

Page 22: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 22

M120 –

Rear View

Control Board (CB)

Routing Engine (RE)

FEBs

PEMs

Page 23: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 23

Juniper M10i edge ‘PE’

HA router

Production proven high performance technology•

Leverages Internet Processor II•

Ethernet modules have IQ2 PICs•

Runs JUNOS software (same as T640 etc)

IPv6 –

Juniper provides hardware IPv6 support on all platforms

Multicast –

Juniper’s multicast performance is unparalleled and available on all platforms, including multicast over L3 VPNs

Fully redundant configuration available•

Redundant forwarding engine board•

Redundant cooling•

Redundant power•

Redundant routing engine•

Graceful RE Switchover supports RE failover with zero packet loss

In Service Software upgrades

Ideal for:Fully redundant edge services solution for lower density PoPs

Page 24: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 24

M10i Components

Redundant AC or DCPower Supplies

Redundant Forwarding Engine Boards (FEB)

Redundant Routing Engine Boards (REB)• PCMCIA expandable memory • 2 serial aux ports• Ethernet craft interface

5U high 18”

deep

Side to sidecooling

8 slots for hot-

swappable PICs

Page 25: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 25

Key Attributes of Solution (1)

1)

Best technical design & implementation•

Dual fibre rings around region (diverse fibre routing).•

Effectively 30Gbps+ core network.•

Primary & secondary uncontended

GbE

access circuits.•

Only design to treat all LeNSE HEIs equitably, but can also easily satisfy individual HEI bandwidth upgrades (e.g. 2x1GbE or 10GbE).

2) High reliability and resilience to all HEIs•

Five 9s reliability for transmission system and router components.•

Minimum number of core and edge routers, now owned by LeNSE.•

“Dual homed star”

IP network design which maintains the IP service despite a core fibre break, intermediate node or RNEP failure (better than ring).

Sub-500msec convergence after link/interface failure.•

In service software upgrades.

Page 26: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 26

Key Attributes of Solution (2)

3) Control and flexibility in line with JPA requirements•

Managed wavelengths, very scaleable on individual link basis.•

PoP transmission equipment and fibre pairs dedicated to LeNSE.•

Ability to add JANET Lightpaths

between C-PoPs and HEIs.•

Fully compatible with SJ5 at the IP level (same Juniper router family).

4) Reduced risk of project implementation failure•

C-PoPs, fibre and transmission systems were largely in place.•

Existing fibre into all HEIs (hence minimal disruption for sites).

5) High SLA targets in contract•

99.98% (protected links).•

99.96% (unprotected links).

Page 27: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 27

LeNSE2 Project Summary

Did we meet our procurement objectives?•

Yes –

and within budget!

Are we satisfied with the technical solution?•

Very.

Actual network performance?•

Excellent! No core/HEI link failures (in 6 months), sub-500msec IP resilience tests to SJ5 (all protocols –

no noticeable packet loss).

Page 28: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 28

Other Potential Solutions

Optical transmission: a range of potential solutions were tendered:•

Generally either shared with other customers

Some bespoke solutions•

An example of a bespoke solution follows……

Page 29: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 29

“Geo accepts no responsibility as to the interpretation or use made of the provided diagrammatic slides of possible network topologies”

SouthamptonUniversity ofSouthampton

Portsmouth

University of Portsmouth

BrightonUniversity of

Sussex

GuildfordUniversity of

Surrey

Bournemouth

University ofBournemouth

RNEP 1

RNEP 2

WinchesterUniversity ofWinchester

SouthamptonSolent

University

BrightonUniversity of

Brighton

ChichesterUniversity of Chichester

KeySwitch / Router

GbE

Circuit on DWDM

Carrier Circuits

Circuits serving site

GbE

Circuits Transported AroundRing In 10G Bearer Wavelength For Efficiency

Geo/Synetrix Tx

ExampleFarnham

UCCA

Page 30: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 30

A sub-multiplexed 10Gbps wavelength (8 x GbE

circuits) forming a ring linking the sites would give significant immediately available bandwidth to support JANET Lightpath

requirements.

•Circuits can be simply and easily manually patched to provide uncontended

/ unswitchedpoint-to-point GbE

channels.

•Depending on the flexibility of the DWDM multiplexing card, some

of these circuits could beused to transport other service types (e.g. SDH).

8

1

10G λ8

1

8

1

8

1

Southampton

8

1

8

1

Portsmouth

10G

λ8

1

8

1

Brighton

10G

λ

8

1

8

1

Winchester Guildford

10G λ

10G λ

From JANET Lightpath

Sourcee.g. Research

Centre

To SJ5Interconnect

To SJ5Interconnect

GbECircuit

#1

Manually patchedManually Patched

Geo/Synetrix JANET Lightpaths

Example

Page 31: Design and Implementation of LeNSE2 - Jisc€¦ · Design and Implementation of LeNSE2 NWS36, University of Strathclyde. 8. th -10. th. April 2008. Mike Byrne. LeNSE CEO

Networkshop 36 University of Strathclyde, April 2008 31

Questions?