dependent inventory: material requirements planning ba 339 mellie pullman
TRANSCRIPT
Dependent Inventory: Material Requirements Planning
BA 339
Mellie Pullman
Page 2
Role of the MPS(Master Production Schedule)
• Master production schedule:– Specifies the number & when to produce
each end item (the anticipated build schedule)
– The MPS is the result of the production The MPS is the result of the production planning processplanning process
Page 3
Link between Total Monthly Group Plan and MPS
Month: January February MarchOutput: 200 300 400
Push Mowers 25 25 25 25Self-propelled 35 40Riding 12 13
January (weeks) 1 2 3 4
Total
Mowers
MPS
Page 4
So Far ...
We have only considered Master scheduling
But we haven’t ordered the parts or materials!
Page 5
We’ve scheduled 500 chairs to be ready five weeks from now . . .
. . . Now what?
Page 6
Back supports (3)
Side rails (2)
Front legs (2)
Cross bars (2)
Seat
Material Needed for a Chair
Page 7
Chair Structure Tree(aka “Bill of Materials”)
Chair
LegAssembly
Seat Back Assembly
Legs (2) Crossbar
Siderails (2)
Crossbar
BackSupports
(3)
Page 8
ChairAssembly
(1 week)
Week 5Week 4
If final assembly takes one week, then we must startassembly at the beginningof Week 4 . . .
Lead-Time I
Page 9
ChairAssembly
BackAssembly
LegAssembly
(1 week)
(1 week)
(1 week)
Seats (2 weeks)
Week 5Week 4Week 3Week 2Whichmeans thatthe majorsubassembliesand seats must bedone by thebeginningof Week 4 ...
Lead-Time II
Page 10
ChairAssembly
BackAssembly
LegAssembly
(1 week)
(1 week)
(1 week)
Back Support (2 weeks)
Legs (2 weeks)
Side Rails (2 weeks)
Cross Bar (2 weeks)
Cross Bar (2 weeks)
Seats (2 weeks)
Week 5Week 4Week 3Week 2Week 1
Lead-Time III
Page 11
Lead-Time Key Points
• To have finished chairs at the beginning of Week 5, we must begin production and order materials in Week 1.
• “Exploding” the bill of materials tells us when to order things.
• Not much we can do to adjust output of chairs for the next 4 weeks. Why?
Page 12
Material Requirements Planning (MRP)
Requires:
1. Bill-of-Materials (BOM)
2. Inventory record
3. Master schedule
to determine what should be ordered when, and how much to order.
Page 13
MRPDependent Demand
The demand for one item is related The demand for one item is related to the demand for another itemto the demand for another item
Given a quantity for the end item, Given a quantity for the end item, the demand for all parts and the demand for all parts and components can be calculatedcomponents can be calculated
In general, used whenever a In general, used whenever a schedule can be established for an schedule can be established for an itemitem
MRP is the common techniqueMRP is the common technique
Page 14
Bills of Material
List of components, ingredients, List of components, ingredients, and materials needed to make and materials needed to make product product
Provides product structureProvides product structure Items above given level are called Items above given level are called
parentsparents
Items below given level are called Items below given level are called childrenchildren
Page 15
BOM Example
BB(2)(2) Std. 12” Speaker kitStd. 12” Speaker kit CC(3)(3)
Std. 12” Speaker kit w/ Std. 12” Speaker kit w/ amp-boosteramp-booster11
EE(2)(2)EE(2)(2) FF(2)(2)
Packing box and Packing box and installation kit of wire, installation kit of wire,
bolts, and screwsbolts, and screws
Std. 12” Speaker Std. 12” Speaker booster assemblybooster assembly
22
DD(2)(2)
12” Speaker12” Speaker
DD(2)(2)
12” Speaker12” Speaker
GG(1)(1)
Amp-boosterAmp-booster
33
Product structure for “Awesome” Product structure for “Awesome” ((AA))
AA
LevelLevel
00
Page 16
BOM Example: 50 A needed
BB(2)(2) Std. 12” Speaker kitStd. 12” Speaker kit CC(3)(3)
Std. 12” Speaker kit w/ Std. 12” Speaker kit w/ amp-boosteramp-booster11
EE(2)(2)EE(2)(2) FF(2)(2)
Packing box and Packing box and installation kit of wire, installation kit of wire,
bolts, and screwsbolts, and screws
Std. 12” Speaker Std. 12” Speaker booster assemblybooster assembly
22
DD(2)(2)
12” Speaker12” Speaker
DD(2)(2)
12” Speaker12” Speaker
GG(1)(1)
Amp-boosterAmp-booster
33
Product structure for “Awesome” Product structure for “Awesome” ((AA))
AA
LevelLevel
00
Part B: 2 x number of As = (2)(50) = 100Part C: 3 x number of As = (3)(50) = 150Part D: 2 x number of Bs
+ 2 x number of Fs = (2)(100) + (2)(300) = 800Part E: 2 x number of Bs
+ 2 x number of Cs = (2)(100) + (2)(150) = 500Part F: 2 x number of Cs = (2)(150) = 300Part G: 1 x number of Fs = (1)(300) = 300
Page 17
Accurate Records
Accurate inventory records are Accurate inventory records are absolutely required for MRP (or absolutely required for MRP (or any dependent demand system) to any dependent demand system) to operate correctlyoperate correctly
Generally MRP systems require Generally MRP systems require 99% accuracy99% accuracy
Outstanding purchase orders must Outstanding purchase orders must accurately reflect quantities and accurately reflect quantities and schedule receipts schedule receipts
Additional MRP Scheduling Terminology
• Gross Requirements: needed during each period.
• Scheduled Receipts: Existing orders that arrive at beginning of period.
• On-hand or available balance:
– Book: Inventory balance at end of each period.
• Net requirements: What is need to meet requirements and safety stock.
• Planned order receipt: planned orders that should arrive at beginning of planned period.
• Planned order release: Addresses lead time.
Page 19
End items are also known as “Level 0” items
The MRP Process Starts with the MPS
Chairs Lead Time = 1 week
1 2 3 4 5 6 7MPS Due Date 0 0 0 0 500 400 400Start Assembly 0 0 0 500 400 400 0
Week
Page 20
Where do the gross requirements come from?Do you understand the MRP logic?
The “Parent / Child” Relationship
ChairsLT = 1 week
1 2 3 4 5 6 7MPS Due Date 0 0 0 0 500 400 400Start Assembly 0 0 0 500 400 400 0
SeatLT = 2 weeksMinimum Order = 1 1 2 3 4 5 6 7Gross Requirements 0 0 0 500 400 400 0Scheduled ReceiptsProjected On Hand 0 0 0 0 0 0 0 0Net Requirements 500 400 400Planned Receipts 500 400 400Planned Order 500 400 400
Week
Week
Page 21
Going Deeper…
ChairsLT = 1 week
1 2 3 4 5 6 7MPS Due Date 0 0 0 0 500 400 400Start Assembly 0 0 0 500 400 400 0
SeatLT = 2 weeksMinimum Order = 1 1 2 3 4 5 6 7Gross Requirements 0 0 0 500 400 400 0Scheduled ReceiptsProjected On Hand 0 0 0 0 0 0 0 0Net Requirements 500 400 400Planned Receipts 500 400 400Planned Order 500 400 400
Leg AssemblyLT = 1 weekMinimum Order = 1000 1 2 3 4 5 6 7Gross Requirements 0 0 0 500 400 400 0Scheduled ReceiptsProjected On Hand 25 25 25 25 525 125 725 725Net Requirements 475 275Planned Receipts 1000 1000Planned Order 1000 1000
Back AssemblyLT = 1 weekMinimum Order = 250 1 2 3 4 5 6 7Gross Requirements 0 0 0 500 400 400 0Scheduled Receipts 250Projected On Hand 0 0 250 250 0 100 200 200Net Requirements 250 400 300Planned Receipts 250 500 500Planned Order 250 500 500
Week
Week
Week
Week
Page 22
Do You Understand ...
• Why it is important to have an accurate BOM and accurate inventory information?
• Where gross requirements come from?
• The difference between planned and scheduled receipts?
Page 23
Recall ...
Look at the “lumpiness” of demand for legs
Leg AssemblyLT = 1 weekMinimum Order = 1000 1 2 3 4 5 6 7Gross Requirements 0 0 0 500 400 400 0Scheduled ReceiptsProjected On Hand 25 25 25 25 525 125 725 725Net Requirements 475 275Planned Receipts 1000 1000Planned Order 1000 1000
LegsLT = 2 weeksMinimum Order = 1 1 2 3 4 5 6 7Gross Requirements 0 0 2000 0 2000 0 0Scheduled ReceiptsProjected On Hand 0 0 0 0 0 0 0 0Net Requirements 2000 2000Planned Receipts 2000 2000Planned Order 2000 2000
Week
Week
Page 24
If we order “lot-for-lot”
Much smoother demand for legs, lower average inventory
Leg AssemblyLT = 1 weekMinimum Order = 1 1 2 3 4 5 6 7Gross Requirements 0 0 0 500 400 400 0Scheduled ReceiptsProjected On Hand 25 25 25 25 0 0 0 0Net Requirements 475 400 400Planned Receipts 475 400 400Planned Order 475 400 400
LegsLT = 2 weeksMinimum Order = 1 1 2 3 4 5 6 7Gross Requirements 0 0 950 800 800 0 0Scheduled ReceiptsProjected On Hand 0 0 0 0 0 0 0 0Net Requirements 950 800 800Planned Receipts 950 800 800Planned Order 950 800 800
Week
Week
Page 25
Elements of JIT as a Philosophy
Setup TimeReduction
Small LotSizes
JIT Deliveryfrom Suppliers
Suppliers'Quality Level
KANBANSystem
RepetitiveMPS
DailyScheduleDiscipline
"Pull"Production
System
Product DesignSimplicity
Equipment &Facility Layout
Multi-functionWorkers
Small GroupProblemSolving
EmployeeTraining
PreventiveMaintenance
JIT
Page 26
• A “pull” production system• A physical (normally visual) control
system• Normally composed of cards and
containers (production card and withdrawal card), but can be any type of signal
• Number of containers
Kanban System
C
DTn
The Kanban System
• The Kanban system uses simple cards or signals to strictly control production
• The basic idea is that no station is permitted to produce more than is immediately required by the succeeding station
• This simple idea prevents the buildup of inventory
• No computer is required!
17-17-2727
Page 28
Kanban System
Page 29
Reducing Setup Times and Lot Sizes
• Reducing setup times:– increases available capacity– increases flexibility– reduces inventory
• Reduce setup times and run times simultaneously to reduce lot sizes and throughput times
• Single-digit Setup Times
• Small lots require short setups!
Page 30
Suppliers
• Very close relationship with suppliers
• Frequent deliveries demanded from suppliers
• Sole-sourcing
• Integrated supplier programs
• Deliveries to production line
• No inspection—high quality
Page 31
Comparison of MRP and JIT
• Pull versus Push production systems• Situations for comparing MRP and JIT:
– Pure repetitive manufacturing situation; JIT works best
– A batch process; JIT works well with cellular manufacturing
– A job shop; MRPII with some elements of JIT• MRP assumes the present system is correct and
seeks to make the best of that system.• JIT seeks to change the system to make it better.
The Traditional Push System
• In traditional manufacturing, an item is released for production at a specified time, with an associated due date generated by MRP.
• The item moves through a sequence of operations
• When one operation is finished, the item is “pushed” to the next operation
• Finally, the product is pushed to inventory, to meet the demand forecast
17-17-3232
The Pull System• The pull system focuses on the output of
the system rather than the input.• Finished products are “pulled” from the
final operation in response to firm customer orders.
• This leads to a chain reaction, with each station pulling material from its preceding station.
• JIT uses the “Kanban” system to control the flow of material with very little work-in-process inventory.
17-17-3333