Department of Public Health Facilities Plan-update Report to the Health Commission January 15, 2013
JANUARY 2013
Prepared by Mark A. Primeau, AIA, Capital Integration Advisor to the Health Department
Potrero Hill Health Center Renovation Gala Celebration
Department of Public Health Facilities Plan-update January 2013
The initial Facilities Plan was presented to the Health Commission on May 17, 2011.
This Facilities plan is updated (2013) and contains new emerging capital needs.
The purpose of this Facility Plan is to provide a road map and strategy for continued support, funding, and improvements to the Department of Public Health capital infrastructure.
The Plan chronicles past & recent capital improvement projects and contains project schedules for all ongoing Major Projects that are funded, exceeding $1 million. Please refer to Appendix B-Major Project Schedules contained in the plan.
Supports the City’s 10 yr Capital Plan to maintain City buildings in a state of good repair to support the efficient and effective delivery of services. *
*This Purpose statement is from the City’s Capital Plan
2
Department of Public Health Facilities Plan-update
January 2013
The Facilities Plan is divided into four parts:
Part 1: Highlights of the Facilities Planning Retreat-September 2012
Part 2: Capital infrastructure background & overview
Capital assets overview
Past & recent accomplishments
Capital funding & Birth of the City’s 10 year Capital Plan
Part 3: Current major projects
Current on going major projects over $1 million-see Appendix B in the Facilities Plan project schedules
Project descriptions
Capital requests-FY12-13 through FY 14-15
Part 4: Emerging needs & future next steps
Emerging capital needs
Capital project list for future requests
Future General Obligation Bond-November 2015
Lessons Learned & Strategies for the future
3
Part 1: CAPITAL PLANNING RETREAT:
o Held on September 10, 2012
o Over 40 participants-including Health Director & Deputies, CEO’s
from SFGH/LHH, CFO & Financial Directors, Facility/Operations
staff department wide attended
o Purpose of the Retreat was to:
o Collectively develop a road map for space planning
decisions
o Establish a framework for determining funding needs for
future major capital projects
Key Planning Drivers
To guide decision-making during the planning retreat, key drivers
were identified as noted below:
1. Consolidation : To increase operational efficiencies by
relocating departments currently scattered throughout the
campus and from off-site into locations that increase efficiencies
and reduce costs
2. Decompression: To relieve overcrowding of programs
3. Retrofit: To plan for the orderly retrofit of buildings identified in
previous assessments as requiring seismic upgrades.
Part 1: CAPITAL PLANNING RETREAT:
o Participants gained an understanding of the department’s space
needs
o Learned about future major capital projects required to achieve
seismic safety and meet objectives for relocation strategies
o Participated in the decision making regarding specific relocation
strategies for the Department at:
• SFGH CAMPUS
• LAGUNA HONDA CAMPUS
• DPH HEADQUARTERS-101 GROVE STREET
• STD CLINIC
• 1380 HOWARD STREET
o Learned about plans for major UC Projects on the SFGH CAMPUS
o Collectively develop a road map for space planning decisions & a
framework for determining future capital funding needs
Part 1: RETREAT OUTCOMES:
1. SFGH Campus: new hospital, existing hospital, older
brick buildings
2. STD/TB: relocation & consolidation strategies
3. UC: Planned Capital Projects: Impact on SFGH Campus
4. 101 Grove Street / Tom Waddell Clinic -seismic upgrade &
Lab relocation
5. 1380 Howard Street-swing space & relocation strategies
6. Laguna Honda Hospital Campus: re-use of remaining wing
buildings
Part 1: Six MAJOR SPACE NEEDS / RELOCATION
STRATEGIES WERE EXAMINED:
.
¼”
Behavioral Health
and Rehabilitation
B80
B90
B2
(Service
Building)
B
3
B4
B1
B100
B5
(Existing
Hospital)
B25 (New
Hospital)
B1
0
B2
0 B3
0
B4
0
B
9
Parkin
g
Garage
B/C Lot –
Proposed location
for UC Research
Building
SFGH CAMPUS MAP
MOVE 1:
A: ACUTE CARE SERVICES MOVE FROM EXISTING HOSPITAL BLDG. 5 TO NEW HOSPITAL BLDG.
25
B: MORGUE MOVES FROM BUILDING 3 TO NEW HOSPITAL BUILDING 25
MOVE 2:
A: RETROFIT EXISTING HOSPITAL BUILDING 5
MOVE 3:
A: ANATOMIC PATHOLOGY MOVES FROM BUILDING 3 TO BUILDING 5
B: PUBLIC HEALTH LAB MOVES TO BUILDING 3
C: OUTPATIENT SERVICES MOVE FROM BUILDINGS 80/90 TO BUILDING 5
D: STD CLINIC MOVES TO BUILDING 5
E: RETROFIT BUILDING 80 /90
MOVE 4:
A: BUILDING 40 TO BE USED AS CONSTRUCTION STAGING AREA
B: CONSTRUCT NEW UCSF RESEARCH BUILDING
MOVE 5:
A: UCSF DEPARTMENTS IN BUILDINGS 1, 10/20, AND 30/40 MOVE TO NEW UCSF RESEARCH BLDG.
B: RETROFIT BUILDINGS 1, 10/20, AND 30/40
SFGH CAMPUS SEQUENCING MOVES
Morgu
e
MOVE 1
RELOCATION B
LEGEND
Department Moving
Buildings are impacted
1”
MOVE 1:
A: ACUTE CARE SERVICES
MOVE FROM EXISTING
HOSPITAL BUILDING 5 TO
NEW HOSPITAL BUILDING 25
B: MORGUE MOVES FROM
BUILDING 3 TO NEW
HOSPITAL BUILDING 25
ACE
Admin – Nursing
Admitting
Cardiology / Cath Lab
Central Sterile
Processing
Clinical Lab – Blood
Bank
Diagnostic Imaging
Emergency Department
ICU / CCU
Med / Surg
Med / Surg - Forensic
Med / Surg - Step
Down
Med / Surg - Trauma
NICU
Obstetrics – Post
Partum / LDRP
Patient Intake /
Recovery
Pediatrics
Surgery / Operating
Rooms
MOVE 1
RELOCATION A
Diagram A-showing the sequenced relocations after completion of the new Acute Care Facility (Bldg. 25):
168,000 square feet of acute care services move from existing Main Hospital to New Facility
Morgue moves from Bldg. 3 into the new Acute Care Facility
Once the above moves are made-the existing Main Hospital is ready for renovation
Diagram A
1/4”
1/8”
LEGEND
Buildings are impacted
Proposed Building
Department Moving
MOVE 5:
A: UCSF DEPARTMENTS IN
BUILDINGS 1, 10/20, AND
30/40 MOVE TO NEW UCSF
RESEARCH BUILDING
B: RETROFIT BUILDINGS 1,
10/20, AND 30/40
Diagram C-showing the sequenced relocations to a proposed new UC Research Facility to be located on the
B/C surface parking lot adjacent to the existing Main Hospital.
UCSF Departments in Buildings 1,10/20,30/40, and 100 move into UCSF Research Facility
The Research facility is still be developed and programmed out-approximately 160,000 square
feet in size
The Research Facility be must completed and operational by 10/2019
Diagram C
1”
OVERVIEW OF SFDPH RELOCATION AND
SEISMIC RETROFIT MASTER PLAN
Diagram D depicts the phased relocation of occupants from 101 Grove Street to 1380 Howard
Street and the Public Health Lab to SFGH Building 3 to allow for the seismic upgrade work at
101 Grove Street.
This plan assumes that the occupants of 1380 Howard can be relocated to space at Laguna
Honda Hospital in Wards D,E,K,L,M, O. Once the construction work is complete, staff will
reoccupy 101 Grove Street-and the lease at 1380 Howard can be terminated. The lease
currently costs the Department $1.5 million annually.
Diagram D
.
North Building
South Building
Pavilio
n
Administratio
n Building H
Wards
B A
C D E K M
G F
L O
LHH CAMPUS MAP
Part 1: NEXT STEPS FROM THE RETREAT:
o Based on the roadmap developed in the planning retreat –prepare an implementation schedule of
planned projects at:
• SFGH CAMPUS
• LAGUNA HONDA CAMPUS (re-use of wings).
• DPH HEADQUARTERS-101 GROVE STREET SEISMIC UPGRADE (using 1380 Howard St. as swing
space).
o Based on the roadmap/schedule prepare updated cost estimates for:
• SFGH Buildings: 5, 80/90, 10,20,30,40
• 101 Grove St
• LHH reuse tenant improvements
o Submit updated funding needs to Capital Planning to inform City’s 10 yr Capital Plan.
o Include updated funding needs in the revised DPH Facilities Master Plan.
Department of Public Health Facilities Plan-update January 2013- Part 2: Capital infrastructure background & overview
DPH operates and maintains over 42 facilities that provide direct public health services to city
residents.
The 42 facilities account for over 2.4 million square feet of space.
DPH leases another 18 sites, totaling 222,672 square feet.
DPH ranks #2, with 2.4 million square feet, just behind the Department of Real Estate which serves as the City’s landlord
Of the 42 facilities, DPH operates two large medical campuses
which together account for 24 facilities, and constitute 65% of the department’s overall facility capacity.
City Departments Department of Real Estate 5,393,738 Department of Public Health 2,404,578 Department of Recreation & Parks 1,880,039 Sheriff 829,674
War Memorial 792,700
15
Departments with Most Square Footage
(Top 5)
ADM
5,393,738
DPH
2,692,383
REC
1,907,539
WAR
792,700
SHF
716,600
15
Department of Public Health Facilities Plan-update
January 2013- Part 2: Capital infrastructure background & overview
An Unprecedented wave of over $1.7 billion of capital improvements to the Department’s facilities has occurred in the last 10 years (including on-going work).
During this time, over 60% (1.5 million square feet) of the Department’s facilities/sites were in some phase of design and/or construction.
Of the $1.7 billion, over $ 1 billion is underway in either design, or in construction. The majority of this work is at SFGH Medical center where the new acute Care Hospital is under construction, nearing 50% completion on target for final occupancy in late 2015.
Several major capital improvement programs make up the majority of a $1.7 billion capital investment over the last 10 years Laguna Honda Rebuild- $585 million, the 500,000 square feet of new construction and 150,000
square feet of remodeling.
Primary Care Modernization Program-9 Health Clinics, $17 million, increased exam rooms by 48%
SOAR –, $10 million, San Francisco Office of AIDS Renovation Project-95% complete
SFGH Rebuild-$887.4 million, new 448,000 square feet Acute Care Hospital, -50% complete
Golden Gate Avenue Tenderloin Clinic,-$3 million, 11,000 sq. ft., adds 19 exam rooms-complete-2012
16
Department of Public Health Facilities Plan-update
January 2013- Part 2
Results of the Primary Care/ Behavioral Health Modernization Program include: Renovation of nine clinics -$17 million, The total number of exam rooms at
clinics have increased by 48% adding 16 rooms for a new total of 55 system- wide. New and reconfigured space in the clinics will increase potential medical visit capacity by 30% (2008) to 34,100 visits per year
Elevator improvements at 4 clinics increased program & ADA access to services to the second floor
Potrero Hill Renovation –complete 2012
Sunset Renovation Project –complete 2012
220 Golden Gate Avenue-Tenderloin Clinic-11,000 sq. ft & 19 Exam rms
Results of the SFGH Rebuild Acute Care Hospital: 50 % complete while maintaining overall budget-$887.4 million
Results of the SOAR Renovation Project: 95 % complete while maintaining overall budget-$10 million
On target for final completion –January 2013, one year ahead of original schedule
17
Department of Public Health Facilities Plan-update
JANUARY 2013- Part 2: Past Capital Funding
Table 3 of the report-Overview of Capital investments over the
last seven years
GF
Appropriation
s to DPH
MOD-DPH
Projects
Other Non-
GF
Total % of
Total (All
Sources)
FY 06-07 18,401,000 2,479,365 0 20,880,365 16%
FY 07-08 17,824,500 2,793,361 0 20,617,861 17%
FY 08-09 11,629,348 3,032,500 83,938,851 98,600,699 54%
FY 09-10 2,303,941 1,533,868 24,282,700 28,120,509 12%
FY 10-11 3,980,000 3,500,000 0 7,480,000 6%
FY 11-12
6,195,000 2,951,824 10,852,907 19,999,731 24%
FY 12-13
8,540,000 7,033,200 0 15,573,200 16%
Total 68,873,789 23,324,118 119,074,458 211,272,365 22%
Adjusted
Total
63,285,481 18,140,837 119,074,458 200,500,775 21%
Department of Public Health Facilities Plan-update
JANUARY 2013- Part 2: Past Capital Funding
Table 3 shows the level of funding from the General Fund over the last 7 years. In FY 06/07 thru FY 12/13 substantial funding was provided for pre-planning on the SFGH Rebuild.
This funding ensured the project would complete its CEQA findings into a certified EIR approved by the Board of Supervisors in July 2008, as required before the project could be place on the ballot in November 2008.
The Table also indicated non General Fund-COP-Certificates of Participation that helped fund FFE for the Laguna Honda Rebuild in FY 80/09 & FY 09/10.
*Also note the bottom row-labeled Adjusted Total: This adjusted total reflects mid year cuts that occurred during FY 08/09 thru FY 10/11.
19
Department of Public Health Facilities Plan-update
JANUARY 2013-Part 2: City’s 10 year Capital Plan
How the Plan came into existence
In August 2005, concerns from City leaders, citizens, Mayor Newson and the Board of Supervisors culminated in developing Administrative Code sections 3.20 and 3.21 requiring the City to annually develop and adopt a ten-year constrained capital expenditure plan for city-owned facilities and infrastructure.
Capital Plan timelines
By March 1 of each odd-numbered year, the City Administrator shall submit to the Mayor and Board of Supervisors a ten-year capital expenditure plan.
By May 1 of the same year, the Mayor and Board of Supervisors shall annually review, update, amend, and adopt by resolution the ten-year capital expenditure plan.
20
Department of Public Health Facilities Plan-update
January 2013- Part 3 Current Major Projects-15 Projects
Major projects are defined as those that either have full or partial funding-over $1 million, and have enough scope definition to prepare a project baseline schedule. In most cases, these projects are in advanced phases of design and/or construction.
PRIMARY CARE, BEHAVIORAL HEALTH SERVICES – (4 Projects) Sunset Mental-base project complete-additional work being done
Southeast Health Center Behavioral Health Services Integration Project
SOAR Renovation Project
Maxine Hall Elevator & Health Services Improvements Project
LAGUNA HONDA CAMPUS - (2 Projects) Laguna Honda Remodel Project-Wards A, B, C, H
Site Improvements
SFGH CAMPUS - ( 9 Projects) Rebuild, Emergency Generator
Fema Equipment Bracing
Bldg. 80/90 Elevators, Bldg.5 Elevators
Bldg. 5 ADA-2 projects
SFGH Campus Signage
ADA improvements –Public restrooms & exterior ramps
21
2012-2013 Capital Request for DPH The FY 2012-13 capital budget totals $15.5 million in for maintenance, capital renewal and
accessibility improvements at health clinics and hospitals.
Overall Capital Projected Need $ 36,439,000
Capital Budget Proposed Funding $15,573,200 -this is 58% less than the projected capital funding need
FY 12-13 Capital Budget
by Service Category Column 1 Column 2 Column 3 Column 4
GF Sources Only Pie Chart A Pie Chart B Pie Chart C Pie Chart D
GF REQUEST Scenario 1 Scenario 2 Scenario 3
Capital Plan* Mid-level Low-level
Economic Development $ 1,700,000 $ 1,000,000 $ 500,000 $ 500,000
General Government $ 10,914,478 $ 4,927,093 $ 4,095,393 $ 3,630,242
Public Health $ 18,169,746 $ 11,344,000 $ 9,643,000 $ 8,540,000
Human Services $ 11,377,591 $ 10,539,155 $ 9,009,544 $ 8,920,097
Infrastructure & Streets $ 22,351,793 $ 13,268,294 $ 11,293,866 $ 9,297,472
Public Safety $ 37,044,251 $ 10,735,782 $ 8,643,709 $ 7,214,635
Recreation, Culture &
Education $ 29,249,364 $ 11,109,883 $ 9,534,633 $ 7,823,327
Pay-as-you-go Total $ 130,807,223 $ 62,924,207 $ 52,720,144 $ 43,425,773
22
2012-2013 Capital Budget for DPH
Facility Requested Funding CPC Approved Budget
SFGH FM NA $1,100,000
LHH FM NA $950,000
101 Grove St FM NA $50,000
Behavioral Health FM NA $110,000
Primary Care FM NA $300,000
SFGH Bldg. 5 Elevator Replacement $2,000,000 $2,000,000
Southeast HC Consolidation Project $2,500,000 $2,500,000
Seismic Studies: 101 Grove St, Bldg. 5
& SFGH Campus Buildings
$1,000,000 $1,000,000
Laguna Honda Hospital Boiler Retrofit $280,000 $280,000
Curry Rear Wall Repair $250,000 $250,000
Mayor’s Office on Disability funding $7,033,200 $7,033,200
TOTALS $25,020,946 * $15,573,200
The approved FY 2012-13 capital budget totals $15.5 million in for maintenance, capital renewal and accessibility
improvements at health clinics and hospitals. This budget represents 62% less than the projected need for FY2012-13.
* This number includes other smaller requests listed in detail on page 18 of the Facilities Plan 23
Department of Public Health Facilities Plan-update
January 2013-Part 4 : Emerging capital needs & future next steps
Even though the Department, through various funding sources, has invested over
$1.7 billion in its capital infrastructure, it is projected that another approximately $1
billion remains to be implemented (when escalated into the future to mid-point-of-
construction).
The Department is aggressively planning on and advocating for a bond measure on
the November 2015 Ballot, amount estimated to be $435 million, to include the
following: Existing Main Hospital-Bldg. 5- $190 million
Bldg.'s 80/90-SFGH Campus- $60 million + $13 million for Cooling Towers
101 Grove Street, DPH Headquarters-$150 million
Southeast Health Center- Behavioral Health Services Consolidation -$22 million
In February 2012, DPH & UC initiated a task force to foster collaboration of planned
capital improvements between the agencies on the SFGH Campus. UC is planning
for a new research facility on campus along with interim seismic measures at various
buildings on campus.
In 2012, the Department initiated a study into the possible re-use of the older LHH
wings to accommodate DPH programs in leased space throughout the City.
24
January 2013- Part 4 : Future Bond Measure
25
Last year, the Department was successful in getting a place holder for some of the seismic
upgrading work into the City’s 10 year Capital Plan for 101 Grove Street, including a new
extension to Van Ness Avenue, and funding for the Existing Main Hospital in a General
Obligation Bond currently planned for 2016, in the amount of $510 million.
However, after reviewing preliminary seismic reports, behavioral health services integration
plans, and the priorities for back filing the existing main hospital at SFGH, the planned
Bond program was re-configured to include the following projects:
Existing Main Hospital (Building 5): $190 million1
Building: 80/90: $60 million1
Critical renewal infrastructure-SFGH-cooling towers/roof: $13 million
101 Grove Street: $150 million1
Southeast Health Center/Behavioral Health Services Integration Project: $22 million2
Total: $435 million
1 Estimated project costs are rough order of magnitude. Additional seismic studies and more detailed cost
estimates will be prepared in 2013. 2 The Southeast HC project’s total cost is $25 million. The project has $3 million in MHSA funding.
Department of Public Health Facilities Plan-update
January 2013- Part 4 : Emerging capital needs & future next steps
CAPITAL ACTIVITIES FOR 2013-PRIMARY CARE/BEHAVIORAL
HEALTH SERVICES/ADMINISTRATION 1. Request funding for Clinic Patient Enhancement Program-this work would make improvements
/enhancements to several primary care clinics in advance of 2014 Healthcare Reform
2. Request funding for expansion potential at specific primary care clinic sites
3. Request additional funding to make patient care improvements to the 2nd floor at Maxine Hall
4. Initiate review and study of Tom Waddell Urgent Care services
5. Work with the Controller’s Office of Public Finance to identify alternate funding strategies for
the Southeast Health Center Project
6. Continue to review technical requirements & refine cost estimates for projects included in the
future bond measure
26
Department of Public Health Facilities Plan-update
January 2013- Part 4 : Emerging capital needs & future next steps
CAPITAL ACTIVITIES FOR 2013-SFGH CAMPUS 1. Continue technical studies & refine cost estimates for project on campus included in the future
bond measure
2. Review programming requirements for Bldg. 5
3. Continue collaboration with UCSF on interim seismic measures and planning for the new
Research Facility and planning for expanded parking on campus
4. Request funding for In-patient pharmacy expansion
27
Department of Public Health Facilities Plan-update
January 2013- Part 4 : Emerging capital needs & future next steps
CAPITAL ACTIVITIES FOR 2013-Laguna Honda Campus 1. Complete studies for and initiate improvements to the re-use of Wards: D,E,K,L,M,O
2. Complete RFP process and initiate procurement for the Dialysis Project
3. Request funding for a Master Plan
4. Continue exterior waterproofing & window replacement program
28
Department of Public Health Facilities Plan-update
January 2013- Part 4 : Emerging capital needs & future next steps
Lessons Learned & Strategies for the future Several key strategies that have emerged as valuable lessons to be applied to
future capital projects. They include:
Early and continued advocacy with past capital funding partners-.i.e. Mayor’s
Office on Disability, Mayor’s Office of Community Development, and Public Utility
Commission.
Establish client- based project teams including operational staff input early in the
project initiation
Acquire pre-bond funding for planning ,and environmental activities for large
major projects
Maximize opportunities to relocate staff from leased space into City-owned
properties
Include Information technology Staff –DPH/DT in programming meetings early
on in the project budgeting process
Utilize alternate delivery projects methods on projects where the process will
benefit the project either through project savings or in schedule enhancements
29