department of defense acquisition yvette rodriguez email : ytorres@usc
DESCRIPTION
Department of Defense Acquisition Yvette Rodriguez Email : [email protected]. Yvette Rodriguez Biography. Personal East Los Angeles Resident for 41 years DAU Instructor in El Segundo Education University of Southern California - Doctoral Student, BSEE 1996 - PowerPoint PPT PresentationTRANSCRIPT
Yvette Rodriguez Biography
• Personal• East Los Angeles Resident for 41 years• DAU Instructor in El Segundo
• Education• University of Southern California - Doctoral Student, BSEE 1996• Naval Postgraduate School - MSSE 2003
• Teaching • University of Southern California Teaching Assistant
• SAE 541, SAE 549, SAE 574• Defense Acquisition University
• Systems Engineering Instructor
• Engineering• Port Hueneme Division Naval Surface Warfare Center
• Combat Systems Installation Engineering Lead
USN Shipboard Installations
• May 1996, USS ASHLAND - test platform for the Ship's Self Defense System (SSDS).
• Performed 17 SSDS, Battle Force Tactical Trainer, AN/SPQ-9B Radar Installations, Testing, and Sea Trials • Landing Ship Dock Class Hulls 41 – 52 • Landing Platform Dock Class Hull 17• Carrier Vessel Nuclear Class Hulls 68, 69, 73, 74
What is DoD Acquisition
https://ilc.dau.milVersion 5.4 15June2010
Operations & Support
• Decision points: 6• Phases: 5• Milestone documents: 40+
IOCBA
Engineering & ManufacturingDevelopment
Production & Deployment
Pre-Systems Acquisition Systems Acquisition
Operations & Support
C
Sustainment
Technology Opportunities & Resources
MaterielSolutionAnalysis
TechnologyDevelopment
Post CDRAssessment
FRPDecisionReview
FOC
Materiel DevelopmentDecision
User Needs
CDR
Life CycleSustainment
Disposal
LRIP Full-Rate Prod & Deployment
Integrated System Design
System Capability & Manufacturing ProcessDemonstration
Defense Acquisition Management System 2008
• The Materiel Development Decision precedes entry into any phase of the acquisition framework• Entrance criteria met before entering phases• Evolutionary Acquisition or Single Step to Full Capability
PDR PDR
Post PDRAssessment
New in bold blue italics
or
5
Materiel Solution Analysis
Analyze/Assess Concepts Versus
Defined User Needs &Environmental Constraints
Decompose Concept Functional Definition into Component Concepts &Assessment Objectives
Decompose Concept Functional Definition into Component Concepts &Assessment Objectives
Develop Component Concepts, i.e., Enabling/Critical
Technologies, Constraints, & Cost/Risk Drivers
Develop Component Concepts, i.e., Enabling/Critical
Technologies, Constraints, & Cost/Risk Drivers
INPUTS OUTPUTS
Assess/AnalyzeConcept & Verify System Concept
Performance
Assess/AnalyzeConcept & Verify System Concept’s
Performance
Assess/AnalyzeSystem Concept
Versus FunctionalCapabilities
Assess/AnalyzeSystem Concept
Versus FunctionalCapabilities
Assess/AnalyzeEnabling/Critical
Components VersusCapabilities
Assess/AnalyzeEnabling/Critical
Components VersusCapabilities
Interpret User Needs,Analyze Operational
Capabilities &Environmental Constraints
Interpret User Needs,Analyze Operational
Capabilities &Environmental Constraints
Develop Concept Performance (& Constraints)
Definition & VerificationObjectives
Develop Concept Performance (& Constraints)
Definition & VerificationObjectives
Decompose ConceptPerformance into
Functional Definition &Verification Objectives
Decompose ConceptPerformance into
Functional Definition &Verification Objectives
ITRITR ASR
• ICD• AoA Plan• Exit Criteria• Alternative Maintenance & Logistics Concepts
• Draft System Requirements• T&E Strategy•SEP• System Safety Analysis• Support and Maintenance
Concepts and Technologies• Inputs to:
- draft CDD - AoA -TDS- Cost/Manpower Est.
Technology Development
OUTPUTS
Demo /Validate System& Tech Maturity Versus Defined User Needs &
Environmental Constraints
Interpret User Needs, Refine SystemPerformance Specs &
Environmental Constraints
Interpret User Needs, Refine SystemPerformance Specs &
Environmental Constraints
Develop System Functional Specs & Verification Plan toEvolve System Functional
Baseline
Develop System Functional Specs & Verification Plan toEvolve System Functional
Baseline
Demo/ModelIntegrated System Versus
Performance Spec
Demo/ModelIntegrated System Versus
Performance Spec
Interpret User Needs.Analyze Operational
Capabilities and Environmental Constraints
Interpret User Needs.Analyze Operational
Capabilities and Environmental Constraints
Develop System Perf(& Constraints) Spec andEnabling/Critical Tech &
Prototypes Verification Plan
Develop System Perf(& Constraints) Spec andEnabling/Critical Tech &
Prototypes Verification Plan
Develop FunctionalDefinitions for Enabling/
Critical Tech/Prototypes &Associated Verification Plan
Develop FunctionalDefinitions for Enabling/
Critical Tech/Prototypes &Associated Verification Plan
Demo Enabling/Critical Technology
ComponentsVersus Plan
Demo Enabling/Critical Technology
ComponentsVersus Plan
Evolve FunctionalPerformance Specs into CI Functional (Design to)
Specs and CI Verification Plan
Evolve FunctionalPerformance Specs into CI Functional (Design to)
Specs and CI Verification Plan
Decompose FunctionalDefinitions into Critical
Component Definition &Technologies Verification Plan
Decompose FunctionalDefinitions into Critical
Component Definition &Technologies Verification Plan
Demo System &Prototype
FunctionalityVersus Plan
Demo System &Prototype
FunctionalityVersus Plan
INPUTS
Design/Develop System Concepts,i.e., Enabling/Critical Technologies,
Update Constraints, and Cost/Risk Drivers
SRR
PDRPDR
• ICD and Draft CDD• Approved Materiel Solution• Exit Criteria • Support and Maintenance
Concepts and Technologies•AoA •TDS• T&E Strategy• System Safety Analysis
• System Allocated Baseline•PDR Report •TEMP •SEP •PESHE •PPP •TRA• NEPA Compliance Schedule• Risk Assessment• Validated Sys Support & MaintObjectives & Requirements
• Inputs to: -IBR -ISP -STA -CDD- Acq Strategy- Affordability Assessment- Cost/Manpower Est.
SFR
• Initial Product Baseline• Test Reports•TEMP• Elements of Product Support• Risk Assessment•SEP •TRA • PESHE• Life Cycle Sustainment Plan• System Safety Analysis• Inputs to: -CPD -STA -ISP
- Cost/Manpower Est.
Engineering and Manufacturing Development
FCA
OUTPUTS
Combined DT&E/OT&E/LFT&EDemonstrate System to
Specified User Needs andEnvironmental Constraints
SVR PRR
Fabricate, Assemble,Code to “ Build-to”
Documentation
Fabricate, Assemble,Code to “ Build-to”
Documentation
INPUTS
Integrated DT&E, LFT&E & EOAs Verify Performance
Compliance to Specs
Integrated DT&E, LFT&E & EOAs Verify Performance
Compliance to SpecsTRR
Individual CIVerification
DT&E
Individual CIVerification
DT&E
System DT&E, LFT&E & OAs,Verify System Functionalityand Constraints Compliance
to Specs
System DT&E, LFT&E & OAs,Verify System Functionalityand Constraints Compliance
to Specs
Evolve CI FunctionalSpecs into Product
(Build to) Documentationand Inspection Plan
Evolve CI FunctionalSpecs into Product
(Build to) Documentationand Inspection Plan
Evolve CI FunctionalSpecs into Product
(Build to) Documentationand Inspection Plan
Interpret User Needs, Refine System
Performance Specs andEnvironmental Constraints
Interpret User Needs, Refine System
Performance Specs andEnvironmental Constraints
Develop SystemFunctional Specs and
System Verification Plan
Evolve FunctionalPerformance Specs into CI Functional (Design to)
Specs and CI Verification Plan
CDRCDR
• Sys Performance Spec• Acquisition Strategy• Exit Criteria•APB •CDD •SEP •PPP •TEMP•PESHE•STA• NEPA Compliance Schedule• Risk Assessment• Validated Sys Support & MaintObjectives & Requirements
• Product Support Strategy
SFRSFR
PDR
CDR
Production and Deployment
LFTEReport to Congress
BLRIPReport to Congress
Production Qualification Testing
OTRROTRR AOTRAOTR
Independent IOT&E
Full- Up System Level LFT&E
J- 6 System Validation
JITC Interoperability Certification Testing
Analyze DeficienciesTo Determine Corrective
Actions
OUTPUTS
Modify Configuration(Hardware/Software/Specs)
To Correct Deficiencies
INPUTS
Verify and ValidateProduction
Configuration
• Production Baseline• Test Reports•TEMP •PESHE •SEP • System Safety Analysis • Input to:
- Cost/Manpower Est.
PCA
• Test Results • Exit Criteria•APB •CPD •SEP •TEMP• Product Support Package•PESHE• System Safety Analysis
Operations and Support
Implement andField
• Process Change – Hardware/Support• Materiel Change
OUTPUTS• Data for In - Service Review• Input to CDD for next increment• Modifications/upgrades to fielded
systems•SEP• System Safety Analysis
In-ServiceReview
DevelopCorrective
Action
Integrate and TestCorrective Action
Assess Risk of Improved SystemAssess Risk of
Improved System
INPUTS• Service Use Data• User Feedback• Failure Reports• Discrepancy Reports•SEP •PESHE• System Safety Analysis
Monitor and CollectAll ServiceUse Data
Analyze Data toDetermine
Root Cause
DetermineSystem Risk/
Hazard Severity
Weapon Systems Acquisition Reform Act of 2009
• WSARA Content –Three Major
Categories
• Organizational/Personnel Changes
• Acquisition Policy & Process Changes
• Congressional Reporting Requirements
Sec. 102. Directors of DT&E and Systems Engineering
• Director, Systems Engineering (SE) (Mr. Stephen Welby)• Deputy Assistant Secretary of Defense for Systems• Appointed by SECDEF• Develops policies and guidance for SE
• Director, DT&E (Mr. Edward R. Greer)• Deputy Assistant Secretary of Defense, Developmental Test
and Evaluation• Appointed by SECDEF• Develops policies and guidance for DT&E
• Requires joint coordination, joint DT&E/SE guidance, and joint annual report to Congress
• Requires CAE’s with MDAPs to appropriately resource DT&E and SE organizations, and report to the Directors within 180 days that they have done so
Who’s Who in Acquisition
• Assistant Secretary of Defense for Research & Engineering for Department of Defense, Zachary J. Lemnios
• Deputy Assistant Secretary of Defense for Systems, Mr. Stephen Welby
• Deputy Assistant Secretary of Defense, Developmental Test and Evaluation, Mr. Edward R. Greer
• Assistant Secretary of Defense for Acquisition , Katrina McFarland• Defense Acquisition
University President
Risk Management Guide
• New Risk Management Guide
• Released August 2006
• Redefines Risk Management Process
• Provides detailed guidance on key activities, e.g.,
• Risk Identification• Identification of Root
Causes• Risk Analysis• Mitigation Planning• Tracking• Planning
RISK
MANAGEMENT
GUIDE FOR
DOD ACQUISITION
Sixth Edition
(Version 1.0)
August, 2006
Department of Defense
https://acc.dau.mil/CommunityBrowser.aspx?id=17757
Systems Engineering Plan
SYSTEMS ENGINEERING PLAN (SEP) OUTLINE Version 1.0, 04/20/2011
Systems Engineering References
Department of Defense (DoD) Systems Engineering (SE) References
Non-specific DoD SE References
Department of Defense Directive 5000.01, The Defense Acquisition System
INCOSE Systems Engineering Handbook, A Guide for System Life Cycle Processes and Activities
Department of Defense Instruction 5000.02, Operation of the Defense Acquisition System
International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC) 15288, Systems and Software Engineering – System Life Cycle Processes
OUSD(AT&L) Directive-Type Memorandum (DTM) 09-027, Implementation of the Weapon Systems Acquisition Reform Act of 2009
ISO/IEC 12207, Systems and Software Engineering – Software Life Cycle Processes
ASA(ALT) Memorandum, Army Systems Engineering Policy ISO/IEC 26702, Application and Management of the Systems Engineering Process
US Army RDECOM Systems Engineering Policy IEEE 1220-2005, IEEE Standard for Application and Management of the Systems Engineering Process, Institute of Electrical and Electronics Engineers, 09Sept2005
Air Force Instruction 63-1201, Life Cycle Systems Engineering ANSI/GEIA EIA-632, Processes for Engineering a System, 01 Sept 2003
Navy Systems Engineering Guide Defense Acquisition University (DAU) Guidebook, Chapter 4 Systems Engineering
DAU Systems Engineering Fundamentals MIL-STD-499B