denver, colorado february 28 - march 2, 2005 … · – request to halliburton ... 200 bar surface,...
TRANSCRIPT
Shell Exploration & Production
07/0
3/20
05Fi
le T
itle
Cop
yrig
ht: S
hell
Exp
lora
tion
& P
rodu
ctio
n Lt
d.
Development / installation of
permanent downhole capillary
injection facilities in gas wells with
sub-surface safety valves
Gas Well De-Liquification Workshop
Denver, Colorado February 28 - March 2, 2005
Eelco Bakker, Dick Klompsma, Hans van Dijk, Gerben Wieldraaijer
Nederlandse Aardolie Maatschappij
(Shell Exploration and Production in The Netherlands)
Shell Exploration & Production
Field exampleHourly 19/12/00 00:00:00
3-12-00 4-12-00 5-12-00 6-12-00 7-12-00 8-12-00 9-12-00 10-12-0011-12-0012-12-0013-12-0014-12-0015-12-0016-12-0017-12-0018-12-00
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0
0.4
18.75
37.5
56.25
75
93.75
112.5
131.25
0
150
pressure
flowrateSudden drop in flow, result of liquids building up and well no longer capable of flowing or flowing intermittently
Shell Exploration & Production
Field example?
Hourly 20-09-02 08:13:56
16-9-02 17-9-02 18-9-02 19-9-02 20-9-02
L15FA1-CCFI01.PV
MILJ.NM3/D L15FA1-CCPC1.PV
BARG L15FA1-CCTI01.PV
DEG.CELC.
0.1
0.2
0.3
0.4
0.5
0
0.6
25
50
75
100
125
0
150
15
30
45
60
75
0
900.00
95.00
35.40
L15FA1-CCFI01.PV
MILJ.NM3/D L15FA1-CCPC1.PV
BARG L15FA1-CCTI01.PV
DEG.CELC.
0.0988.0047.30
17-09-02 09:41:39
Drop in flowrate
Drop in temperature while not flowing
Shell Exploration & Production
Solutions• background
– European legislation requirement for surface- and subsurface safety valves (SSV + SC-SSSV)
– No equipment (SC-SSSV+capillary) readily available within industry
• Conceptual ideas only
– In-house idea Shell patent (TS 9521 EPC)
• Principle: use existing C/L to pump down foam solution + modify SSSV to hang off capillary
• 2-tier follow-up
– In-house development use of existing equipment / components “Foam Insert Sleeve” (FIS concept)
– Request to Halliburton (main supplier completion eqpt.) to modify existing valve (Chemical Injection Safety Valve - CISV)
– Design criteria
» Low cost / standard components / minimal mods existing equipment / cover all tubing sizes 3 ½” 9 5/8” with main focus on 3 ½” and 5 1/2”.
» For both W/L as TR safety valves
Shell Exploration & Production
Foam Insert Sleeve (FIS) concept
Auxiliary equipment
1.Wire-line BOP for sleeve (similar as for SC-SSSV)
2.CT Quad BOP for control valve / hanger 2” ID BOP with slip-type rams for ¼”
Existing SV landing nipple (part of existing completion)
Sleeve with new SV landing nipple profile and by-pass for foam from C/L inlet to control valve/hanger capillary
Control valve (hanger) installed at bottom of sleeve
Capillary string
Shell Exploration & Production
FIS - equipment Standard RQ running / GS pulling tools
Guide sleeve
Insert sleeve
Standard Insert safety valve
SV Control valve + hanger
Shell Exploration & Production
FIS installation sequence
Install insert nipple
Install guide sleeve
RIH 1/4” capillary + space-out
Cut string & connect to Hanger
Install Hanger in Insert Nipple
Start Foam Injection
Pull Guide sleeve
Pull SC-SSSV
WL operation,wire 0.125”
CT operation
Install and test SC-SSSV
Hang-off string in BOP
Shell Exploration & ProductionBegin situation:
1
4
5
6
2
3
7
Install insertnipple
RIH 1/4” capill.+ space-out
Cut string &connect
to hanger
Install hanger in insert nipple
Pull SC-SSSV
Install and testSC-SSSV
Hang-off stringin BOP
1
4
5
6
7
2
3
Shell Exploration & Production
Begin situation: End situation
SC-SSSV installed in sleeve, foam injection + SV operations via ¼”controlline
SC-SSSV installed in tubing SV-LN, operated via ¼”controlline
Shell Exploration & Production
time
Time
(P tbg @ SV depth + P SV full opening – P hydraulic C/L + safety margin)
Shell Exploration & Production
Chemical Injection Safety Valve concept (Halliburton - CISV)
Existing SV
Connection capillary to SV
Auxiliary equipment
1.Full size Modified BOP for modified SV including rams to hold capillary during make-up
• existing for 3 ½”size
Clamp to hold down capillary
Capillary string connected to SV
Shell Exploration & Production
CISV installation sequence
Perform Dummy run
RIH 1/4” Capillary string
Hang-off string in BOP
Cut string & connect SC-SSSV
Install SC-SSSV+coil in LN
Start Foam Injection
Test SC-SSSV
Pull SC-SSSV
WL operation
CT operation
Shell Exploration & Production
CISV – equipment (Halliburton)Connection capillary to safety valve
Capillary clamp construction
Conventional
Flapper valve
By-pass allowing foamer to capillary
Foam Inlet ports
Courtesy Halliburton
Shell Exploration & Production
FIS versus CISV• Key differences
– Halliburton CISV
• SV integrated with chemical injection
• Full size capillary deployment BOP’s required for different valve sizes
• System acts as 1 pressure vessel, SV operating pressure driven by depth / wellhead pressure drives setting of downhole injection valve high operating pressure entire system.
– Pressure range, 200 bar surface, up to 600 bar downhole
– FIS
• Possible to install / pull SC-SSSV independent from capillary injection system
• flexibility in sizes ( 5” - 9 5/8” ) only 1 size capillary deployment BOP required
• 2 operating vessels, operating pressure setting control valve/hanger independent of SV operating pressure lower operating pressures
– Pressure range, 200 bar surface, up to 300 bar downhole
Shell Exploration & Production
QA / QCitem criterion Ensured by
All safety critical equipment installed in the well to meet standard requirements (RQ / XO lockmandrels / 2.75” Halliburton FXE wireline retrievable SV)
In line with API - 14A 1&2
• Materials send to location certified (workshop testing acc procedures)
• function & inflow testing once installed before well taken into production
Critical seals Viton / Chemraz Sh. 90 spec
• tested in NAM lab (autoclave)
Foam selection Stability / compatibility
• tested in NAM lab (autoclave)
No outstanding issues from reviews
• Multidisciplinary HAZID / HAZOP review (WS/ PT/ Ops/ PC / Eng)
Installation /running procedures of capillary & modified safety valve or modified sleeve+ safety valve No outstanding
issues after “dry run”
• All issues closed-out after Zuidbroek testing
Safety Impact of foam systems No significant increase in overall risk levels
• QRA / RAM approach
Shell Exploration & Production
Risks mitigation• Impact foam injection on well related safety
– 3 different steps
• HAZID running & operation of systems
• Qualitative analysis (RAM approach)
• Semi-quantitative analysis
– HAZID running & operation of systems
• Key challenges identified:
– Compatibility foam – seals
– Foam stability
– Compatibility foam solution – hydraulic oil
– Interaction existing ESD-systems
– Impact on (production) surface facilities
– Familiarisation with “new”equipment / services.
Shell Exploration & Production
Risk Assessment Matrix (RAM)
Increasing risk
• Combines scenario consequence with its probability
• Experience is used to determine both classifications
• Focuses on the high impact scenario
• Not a lot of “granularity” for comparison
The level of control should depend on the level or risk !
worst case Likelihood case
Shell Exploration & Production
Quantitative Assessment
• Objective
– Estimate the annual blowout and/or release rates for each of the designs and compare with current background rate
• Industry accepted blowout frequencies (SINTEF, EUB) and failure rate for installed equipment (Wellmaster / Oreda)
• Intervention frequencies based on actual (historical) data
• Results
– No significant differences between without foam / with foam injection
– No impact on location related risk level (effect of exposure included !!)
Shell Exploration & Production
Field installations
COV-55 WAV-18 MKZ-3Tubing 5 1/2" 18#, L-80 Cr-13 3 1/2", 10,2#, CS 7" , 32#, Cr-13Injection valve depth 2850 meter 1760 meter 3880 meterPerforations 2762 - 3161 meter 1756 -1820 meter 3838 - 3934 meterDeviation @ reservoir 20 ° 42 ° 45 °SC-SSSV depth 301 meter 85 meter 103 meterConcept 4.562" FIS 2.75" CISV 5.875" FISCap. Type 1/4" 0.035 " Inc. 625 1/4" 0.035 " Inc. 625 1/4" 0.035 " Inc. 625
Shell Exploration & Production
Learnings– Extensive equipment testing incl. dry runs in test well with capillary paid of
• Equipment behaviour / pressure setting control- and injection valves
• Operational procedures
– Accidentally capillary cutting fishing successful
– Material selection equipment incl. seals critical
• Foamer composition
• Well conditions
– Functioning downhole injection valve critical
• Accurate dosing of chemicals to optimise well lift
• Impact on safety valve operations / behaviour
– Campaign approach
• All systems tested and installed (1*3 ½”, 1 * 5 1/2”, 1* 7”)
– Further investigations for simplifications future installations
Shell Exploration & Production
Contributors & acknowledgements
•
• Shell
– Chris Kuyken
– Hendrik Hindriks
– Dick Klompsma
– Hans van Dijk
– Gerben Wieldraaijer
– Rob Eylander