PHASE C
OUTSTANDING WORKS AND DEFECTS LIST NO.1
Dated 13 March 2015
BEFORE PHOTO
AFTER PHOTO
PB TARGET DATE TO COMPLETE
RE / RTO SIGNOFF
REMARKS
1.
Missing Scupper Drain - refer to email dated 26 Jan 2015.
2.
Photos to show plastered wall behind M&E Panels made good & painted.
3
PHASE B1 & B2
OUTSTANDING WORKS AND DEFECTS LIST NO.1
Dated 13 March 2015
BEFORE PHOTO
AFTER PHOTO
PB TARGET DATE TO COMPLETE
RE / RTO SIGNOFF
REMARKS
1.
Missing Scupper Drain - refer to email dated 26 Jan 2015.
2.
Photos to show plastered wall behind M&E Panels made good & painted.
3
PHASE D
OUTSTANDING WORKS AND DEFECTS LIST NO.1
Dated 13 March 2015
BEFORE PHOTO
AFTER PHOTO
PB TARGET DATE TO COMPLETE
RE / RTO SIGNOFF
REMARKS
1.
Missing Scupper Drain - refer to email dated 26 Jan 2015.
2.
Photos to show plastered wall behind M&E Panels made good & painted.
3
PHASE E
OUTSTANDING WORKS AND DEFECTS LIST NO.1
Dated 13 March 2015
BEFORE PHOTO
AFTER PHOTO
PB TARGET DATE TO COMPLETE
RE / RTO SIGNOFF
REMARKS
1.
Missing Scupper Drain - refer to email dated 26 Jan 2015.
2.
Photos to show plastered wall behind M&E Panels made good & painted.
3