deep · pdf filefall 2008 the magazine of the deep foundations institute ... engineers and...

6
Fall 2008 The Magazine of the Deep Foundations Institute DEEP FOUNDATIONS DFI’s 2008 Outstanding Project Award The Opening of the New South Ferry Subway Station

Upload: duongdan

Post on 11-Mar-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: DEEP · PDF fileFall 2008 The Magazine of the Deep Foundations Institute ... engineers and contractors carved out a new tunnel beneath ... complex temporary excavation support and

Fall 2008 The Magazine of the Deep Foundations InstituteDEEP FOUNDATIONS

DFI’s 2008 Outstanding Project Award The Opening of the New South Ferry Subway Station

Page 2: DEEP · PDF fileFall 2008 The Magazine of the Deep Foundations Institute ... engineers and contractors carved out a new tunnel beneath ... complex temporary excavation support and

8 • DEEP FOUNDATIONS • FAll �008

To make space for the new South Ferry Station in lower Manhat-tan, engineers and contractors carved out a new tunnel beneath

three operating subway tunnels and tangentially to yet another tunnel. Creating the space required the design and construction of complex temporary excavation support and underpinning systems and the design and installation of real-time monitoring systems. Construction for the new station and tunnel was mainly cut-and-

cover in a mixed-face area of soil and rock approximately 2,000 linear ft long, 60 ft wide and up to 70 ft deep. Close coordina-tion between the design/build team and the project owner, the Metropolitan Transportation Authority (MTA), was critical.

With the construction of this $400 million project, the MTA and New York City Transit

(NYCT) are correcting the numerous physical and operational defi-ciencies of the existing station and improving the lives of millions of commuters. Built in 1905, the original South Ferry Station is on the IRT Broadway–Seventh Avenue Line of the New York City Subway and is the southern terminal of the #1 subway service, which forms a loop to return uptown. The station has a sharply curved single platform on the outside of the outer track of a two-track loop. This platform is short and does not allow the rear five cars of a normal 10-car subway train to load or unload. In addition, once the train stops at the station, commuters wait while retract-able floor grates bridge the gap created between the platform and the subway car doors, and then they have only one exit from the station. Spray nozzles keep the tracks lubricated to reduce the train wheels’ friction caused by the tight curve. The sharp curvature of the loop and the inability to use half of the subway car doors slow train operation. With the new ADA-accessible station, 10-car trains will be able to open all doors, and additional entrances, escalators and elevators will greatly reduce travel times.

AUTHORS:David M. Cacoilo, P.E., Partner

Alice Arana, P.E., Associate

Joel L. Volterra, P.E., Associate

Mueser Rutledge Consulting Engineers

DFI �008 Outstanding Project Award WinnerIntricate Excavation for the New South Ferry Subway Station

Excavation in front of historic church

Page 3: DEEP · PDF fileFall 2008 The Magazine of the Deep Foundations Institute ... engineers and contractors carved out a new tunnel beneath ... complex temporary excavation support and

Deep founDations • fall 2008 • �

project participantsThe MTA selected the Design/Build team led by the Joint Venture of Schiavone Construction Company and Granite Construction Northeast, Inc. (formerly Granite Halmar Construction Company). Stantec Consulting Services, Inc. (formerly Vollmer) designed the permanent station structural box. Mueser Rutledge Consulting Engineers (MRCE) provided geotechnical and structural founda-tion engineering for temporary structures needed for the construc-tion of the new box, including underpinning and excavation sup-port systems. In conjunction with Geocomp Consulting, MRCE also provided instrumentation and monitoring of all existing struc-tures within and surrounding the site. Moretrench American Cor-poration provided construction dewatering services, Hayward-Baker installed the minipiles and Skanska installed the secant pile perimeter walls for excavation support.

site ChallengesThe team was confronted with an extremely complex urban site at the southern tip of Manhattan, approximately one-half mile south of the site of the former World Trade Center. Possibly the most histori-cally rich area of Manhattan, it is already heavily built both above and below ground. The space for the new approach tunnel and station had to be created through a maze of existing subway tunnels, sta-tions, utilities and other underground obstructions, as well as nearby historic buildings that required protection during construction.

The site was located in a filled area beyond Manhattan’s original shoreline. The challenges included a high groundwater table, deep organic soils, soft varved deposits and highly variable rock elevations. The contract also imposed strict limitations that impacted the work. In particular, the existing subway lines had to continue to operate during construction, and only weekend shutdown periods were permitted; access to most of the work area at ground level was restricted to a nine-month window because most of the alignment fell within Battery Park, a public park space that overlays nearly the entire site. The contract provisions also required a groundwater cutoff system to prevent settlement of adjacent structures.

The new approach tunnel and station cross beneath three operating subway tunnels, including the existing #1 southbound tunnel, the #4 & #5 tunnel to and from Brooklyn, and both the

uptown and downtown sides of the existing #1 loop station. The new station is situated adjacent to the #1 northbound tunnel, the Brooklyn Battery Tunnel, the Battery Park Underpass and a New York City Department of Transportation vent shaft. Each existing structure had a different type of construction, and each required a unique underpinning solution, including minipiles, underpin-ning piers and bracket piles.

MRCE’s analysis of dewatering impacts demonstrated that the settlement of adjacent structures due to dewatering in the areas surrounding the excavation would be well below limiting thresh-olds. Based on these analyses, the owner relaxed contract-speci-fied groundwater cutoff requirements, which resulted in signifi-cant savings in the design and construction of the excavation sup-port walls.

underpinning The existing tunnels, which required underpinning to permit excavation and construction of the new box beneath, crossed the excavation area at skew angles. MRCE designed the tempo-rary excavation support and underpinning systems in the areas where the new tunnel crosses under existing tunnels. The #1 southbound tunnel and the #4 & #5 tunnel to and from Brooklyn both consist of a two-track concrete box. They were underpinned by a system consisting of minipiles socketed in rock, supporting steel beam frames connected directly to the tracks, tunnel col-umns and walls, and invert slab. The underpinning system used for the existing #1 loop station was similar, with steel wide-flange bracket piles along the perimeter for additional support of the sta-tion platforms, which extended outward beyond the main tunnel.

Looking through the tunnel

The space for the new approach tunnel and

station had to be created through a maze of

existing subway tunnels, stations, utilities

and other underground obstructions, as well

as nearby historic buildings that required

protection during construction.

Page 4: DEEP · PDF fileFall 2008 The Magazine of the Deep Foundations Institute ... engineers and contractors carved out a new tunnel beneath ... complex temporary excavation support and

10 • Deep founDations • fall 2008

The design for the underpinning systems focused on preventing tunnel movement and allowing installation from inside the exist-ing tunnel during weekend 55-hour shutdown periods, known as a Weekend General Order (GO).

The tunnel underpinning system consisted of transverse steel pile caps and longitudinal steel girders placed within the exist-ing tunnel invert slab, and supported on minipiles. The approxi-mately 150 minipiles provided temporary vertical support of the three existing tunnels during excavation beneath them. The design called for locating the minipiles so that they would not interfere with train envelopes after their installation and prior to construc-tion of the steel framing. This framework was connected to the tunnel invert slab and walls and also directly supported the track. The framework was prefabricated outside the tunnel and installed in segments once the pile installation was complete.

During each GO when the trains were not running, the con-tractor removed the existing rails and the concrete fill under the rails within the segment being underpinned, then installed the pile caps and prefabricated frame that tied them together. Finally, they connected the frame to the minipiles and to the tunnel, and re-installed the track. This process allowed train service to resume immediately after the end of each GO.

MRCE also designed the temporary excavation support sys-tems in the area of the existing tunnel crossings. In the area of the #1 northbound and the #4 & #5 tunnels to and from Brooklyn, the excavation extended to depths ranging from 45 to 60 ft. The various types of walls included secant pile walls and soil-mix walls reinforced with steel wide-flange beams, and soldier pile and lag-ging walls. The excavation face directly below the existing tun-nels was supported by concrete underpinning piers. For lateral bracing of the excavation support walls, it was necessary to design an intricate layout of up to four levels of internal struts, due to the complicated geometry of the excavation area and the need to provide lateral support for the existing tunnels. Tieback anchors

were also utilized in the deeper areas of the excavation. The design included a system of temporary walls and bracing to provide effective lateral support during excavation and rock removal to the final subgrade for the new tunnel construction. This system was also sufficiently rigid to minimize set-tlement of adjacent structures.

Real-time Monitoring The contract called for real-time monitor-ing and reporting of settlements, lateral movements and vibrations. The purpose was to evaluate potential effects of the excavation and dewatering on existing transportation structures and adjacent public and private properties, many with historical significance. With Geocomp Consulting, MRCE designed and imple-mented a comprehensive real-time instru-

mentation and construction monitoring program. Monitoring of the existing #1 and #4 & #5 subway lines and the surrounding structures commenced at the start of construction activities, with seismographs to read vibration levels during blasting for rock removal, piezometers to observe groundwater drawdown, and inclinometers and tiltmeters to monitor tilt and lateral deforma-tion of tunnels and support walls. In addition, the system included Automated Motorized Total Stations (AMTS). The AMTS read and recorded vertical and lateral movements from hundreds of reflective prisms, and were mounted along existing tunnel walls, adjacent building facades and selected support wall elements. The AMTS program performed a complete survey of all points up to six times daily and transmitted the data remotely via a real-time web-based monitoring and notification system to MRCE’s office for review by engineers.

Typical section with underpinning

Weekend track replacement in subway tunnel

Page 5: DEEP · PDF fileFall 2008 The Magazine of the Deep Foundations Institute ... engineers and contractors carved out a new tunnel beneath ... complex temporary excavation support and

Deep founDations • fall 2008 • 11

ConclusionsEngineers considered many systems when designing support for the existing tunnels, including soil improvement, ground freezing and tunneling methods. The minipile direct underpinning sys-tem offered the least risk and provided a significant schedule ben-efit. The minipile technology permitted the underpinning to be performed ahead of the access window for Battery Park without major disruption to commuter train service on existing subways.

By prepping the area prior to the GOs and creating modules by prefabricating the underpinning frames, the contractors could install the modules from inside the tunnel within the limited time frame imposed by the GOs. Rigid support walls and an intricate lateral bracing system supported the excavation and existing tun-nels, which was necessary due to the overall geometric complexity of the project site. Finally, monitoring the effects of construction activities on a real-time basis, including monitoring of vibra-

tions due to blasting for rock removal, minimized the prob-ability of train service disrup-tion and damage to adjacent historic structures.

The commuter benefits of this new tunnel and mod-ern station are significant. They include: reduced cus-tomer travel times; increased accessibility with additional entrances and ADA-compli-ance; and easy free transfer between the #1 and the R & W lines at Whitehall Street. All of the physical deficien-cies that beset the original South Ferry Station have been eliminated. These defi-ciencies included the limited passenger volume owing to its single-platform length that could fit only five subway cars at a time, and the ear-

splitting screeching of the trains coming around the sharp curve. The new South Ferry Station provides two platforms on a straight alignment and will be long enough to accommodate full-length 10-car subway trains.

Construction on the project began in 2005 and the new station is expected to open in December 2008. The work involved the use of innovative engineering techniques to overcome the project’s site and scheduling constraints.

The new NYCT South Ferry Station not only serves commut-ers traveling to and from one of the busiest downtown areas of Manhattan, but it is also used by the thousands of tourists from all over the world who visit the city every year on their way to Battery Park and the Statue of Liberty. Through concurrent design and superior coordination, the design/build team met the fast-track design schedule and created a modern station of which New York City can be proud.

1750s-era wall found during construction

#1 tunnel with bracket pile

When the trains were not running, the

contractor removed the existing rails and

the concrete fill under the rails within the

segment being underpinned, then installed

the pile caps and prefabricated frame that

tied them together.

Page 6: DEEP · PDF fileFall 2008 The Magazine of the Deep Foundations Institute ... engineers and contractors carved out a new tunnel beneath ... complex temporary excavation support and

DE

EP

FO

U

NDATIONS INST

ITU

TE

Fall 2007

Deep Foundations Institute326 Lafayette AvenueHawthorne, NJ07506 USA973.423.4030FAX 973.423.4031

PRESORTED STANDARDU.S. POSTAGE PAID

FOLCROFT, PAPERMIT NO. 100

Excavating Under Running Trains for the New South Ferry Subway Station in Manhattan