Order Activity Activity Code 1 Skid Rig & Prepare Mob 2 Pressure test tubing hanger and 9-5/8― casing hanger seals to 1,000psi, Tree Valves Mob 3 Rig Up slickline PCE and P/T to 5,000psi SLine 4 RIH with drift & pressure /temp log on slick line @ 10,000ft/hr or 3,050m/hr SLine 5 POOH with drift run SLine 6 RIH with plug and set in Nipple profile @ 2,400m mdbrt and P/T to 500psi SLine 7 POOH slickline SLine 8 Place Prong in the tubing near the wellhead Whead 9 Rig Up Radial Torch Cutter on Slickline SLine 10 RIH on slickline with Radial Torch Cutters (RTC) to above the packer and cut @ 2,350m SLine 11 POOH with slickline and RTC SLine 12 Rig Down slickline SLine 13 Circulate with Seawater and test annulus and casing to 1,000psi CirHol 14 Nipple down Xmas tree Whead 15 Nipple Up 13-5/8― riser and BOP. P/T to 1,000psi BOP 16 Recover Upper Completion Tubing and Lay down Tube 17 RIH on 5― DP and set and test Bridge Plug 500 psi above injection pressure @ 2,300m RIH 18 Place 400m of cement plug (combination barrier) and POOH 100m above plug Cement 19 WOC and tag plug WOC 20 POOH POOH Phase One Decomm Well

Upload: jovyan25

Post on 11-Jul-2016

215 views

Category:

Documents


2 download

DESCRIPTION

Decomm steps

TRANSCRIPT

Page 1: Decomm Phse 1

Order Activity

Activity Code

1 Skid Rig & Prepare Mob

2 Pressure test tubing hanger and 9-5/8― casing hanger seals to 1,000psi, Tree Valves Mob

3 Rig Up slickline PCE and P/T to 5,000psi SLine

4 RIH with drift & pressure /temp log on slick line @ 10,000ft/hr or 3,050m/hr SLine

5 POOH with drift run SLine

6 RIH with plug and set in Nipple profile @ 2,400m mdbrt and P/T to 500psi SLine

7 POOH slickline SLine

8 Place Prong in the tubing near the wellhead Whead

9 Rig Up Radial Torch Cutter on Slickline SLine

10 RIH on slickline with Radial Torch Cutters (RTC) to above the packer and cut @ 2,350m SLine

11 POOH with slickline and RTC SLine

12 Rig Down slickline SLine

13 Circulate with Seawater and test annulus and casing to 1,000psi CirHol

14 Nipple down Xmas tree Whead

15 Nipple Up 13-5/8― riser and BOP. P/T to 1,000psi BOP

16 Recover Upper Completion Tubing and Lay down Tube

17 RIH on 5― DP and set and test Bridge Plug 500 psi above injection pressure @ 2,300m RIH

18 Place 400m of cement plug (combination barrier) and POOH 100m above plug Cement

19 WOC and tag plug WOC

20 POOH POOH

Phase One Decomm Well