Order Activity
Activity Code
1 Skid Rig & Prepare Mob
2 Pressure test tubing hanger and 9-5/8― casing hanger seals to 1,000psi, Tree Valves Mob
3 Rig Up slickline PCE and P/T to 5,000psi SLine
4 RIH with drift & pressure /temp log on slick line @ 10,000ft/hr or 3,050m/hr SLine
5 POOH with drift run SLine
6 RIH with plug and set in Nipple profile @ 2,400m mdbrt and P/T to 500psi SLine
7 POOH slickline SLine
8 Place Prong in the tubing near the wellhead Whead
9 Rig Up Radial Torch Cutter on Slickline SLine
10 RIH on slickline with Radial Torch Cutters (RTC) to above the packer and cut @ 2,350m SLine
11 POOH with slickline and RTC SLine
12 Rig Down slickline SLine
13 Circulate with Seawater and test annulus and casing to 1,000psi CirHol
14 Nipple down Xmas tree Whead
15 Nipple Up 13-5/8― riser and BOP. P/T to 1,000psi BOP
16 Recover Upper Completion Tubing and Lay down Tube
17 RIH on 5― DP and set and test Bridge Plug 500 psi above injection pressure @ 2,300m RIH
18 Place 400m of cement plug (combination barrier) and POOH 100m above plug Cement
19 WOC and tag plug WOC
20 POOH POOH
Phase One Decomm Well