Secretary, SEAC 1 Annexure A TABLE DECISION ON MINOR MINERAL PROJECTS WITH LEASE AREA LESS THAN 25 HA. ON 17.05.2017 Sl. No SEIAA File No. Name & Address of the proponent District Type of Mineral Name of the project Mining lease period Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist Whet her gener al condit ion apply Maximu m annual producti on capacity (in m 3 ) Recommend ation of SEAC 1. 18101/ 1769- NCM/12 -2016 Smt. Rama Khandual W/o Ranjan Khandual, At- Village Chandhiapall i, Pst Ambapua, Ps Bellaguntha, Dist Ganjam. Ganjam Sand Kokalunda River Sand Bed (13.375 Acres / 5.4128 Ha) At Village- Kokalunda, Tahasil- Bellaguntha, District-Ganjam FY 2015- 16 to 2019 - 20 Nil 1. Furnished filled in Form- I, pre- feasibility report and check list forwarded by Tahasildar. 2. Topo sheet indicating location of the mine has been furnished. 3. EMP submitted. 4. Mining Plan has been approved by Authorized Officer, Dy. Director, Geology, O/o Joint Director, No 2200 The SEAC recommende d to grant EC valid from the date of EC accorded upto the lease period.

Upload: letuyen

Post on 28-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Secretary, SEAC 1

Annexure A

TABLE

DECISION ON MINOR MINERAL PROJECTS WITH LEASE AREA LESS THAN 25 HA. ON 17.05.2017

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

1. 18101/ 1769-NCM/12-2016

Smt. Rama Khandual W/o Ranjan Khandual, At- Village Chandhiapalli, Pst – Ambapua, Ps – Bellaguntha, Dist – Ganjam.

Ganjam Sand Kokalunda River Sand Bed (13.375 Acres / 5.4128 Ha) At Village-Kokalunda, Tahasil-Bellaguntha, District-Ganjam

FY 2015- 16 to 2019 -20

Nil 1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

4. Mining Plan has been approved by –Authorized Officer, Dy. Director, Geology, O/o Joint Director,

No 2200 The SEAC recommended to grant EC valid from the date of EC accorded upto the lease period.

Secretary, SEAC 2

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

Geology (SZ), Berhampur - 10.

5. 4.No forest land involved in lease area

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no

Secretary, SEAC 3

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

court case / litigation pending.

2. 18370/ 1794-NCM/01-2017

Sri Jagannath Sethi, S/o Bachha Sethi, At/Po- Gallery, Tahasil – Ghumusar, Dist – Ganjam.

Ganjam Sand Ambapua Sand Quarry (15.758 Acres/ 6.3775 ha.) Village- Ambapua, Tehsil- Belaguntha, Dist- Ganjam, Odisha

FY 2015- 16 to 2019 - 20

Nil 1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

4. Mining Plan has been approved by the Geologist & Authorised Officer, Bhanjanagar Sub-division, O/o Joint Director Geology,

No 1808 The SEAC decided to consider the proposal after receipt of clarification from the Tahasildar regarding road crossing the river and existence of any bridge over the river.

Secretary, SEAC 4

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

South Zone, Berhampur.

5. No forest land involved in lease area

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation

Secretary, SEAC 5

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

pending.

3. 18866/ 1811-NCM/03-2017

Sri Gagan Mohanty, At – Santhapada, Ps – Talcher, Dist – Angul.

Angul Sand Santhapada-B Sand Quarry (18 Acres or 7.284 Ha) At Village-Santhapada, Tahasil-Talcher, Dist-Angul

FY 2016- 17 to 2020 -21

Nil 1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

4. Mining Plan has been approved by Joint Director, Geology, Zonal Survey, Dhenkanal.

5. No forest land involved in lease area

No 3900 The SEAC decided to take decision on the proposal after a field visit of sub-committee of SEAC to verify cluster approach.

Secretary, SEAC 6

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation pending.

4. 62282/ 1818-NCM/03-2017

Sri Ramesh Kumar Patnaik, At/Po/Ps/Dist - Malkangiri

Malkangiri

Sand Maheswarpur And Kondelguda Sand Quarry over An Area

FY 2015- 16 to 2019 -20

Nil 1. Furnished filled in Form-I, pre-feasibility report and

No 650 The SEAC recommended to grant EC valid from the date of EC

Secretary, SEAC 7

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

of 5.796 Ha. At Village-Maheswarpur and Kondelguda,Tahasil- Kudumulugumma, Dist-Malkangiri

check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

4. Mining Plan has been approved by Joint Director of Geology, Zonal Survey, Koraput.

5. No forest land involved in lease area

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for

accorded upto the lease period.

Secretary, SEAC 8

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation pending

5. 61780/ 1829-NCM/04-2017

Sri Padman Kumar Bisoi, S/o Motising Bisoi, At/Po- Kerla, Ps- Kosagumuda.

Nabarangpur

Sand Boragam Sand Quarry(12.405 Acres Or 5.018 Ha.) At Village-Boragam,Tahasil-Kodinga,Dist-Nabarangpur

FY 2016- 17 to 2020-21

Nil 1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of

No 11939 The SEAC decided to consider the proposal after receipt of the following from the proponent. 1) Full sheet of

Topo map not furnished to ascertain feature

Secretary, SEAC 9

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

the mine has been furnished.

3. EMP submitted.

4. Mining Plan has been approved by Joint Director of Geology, Zonal Survey, Koraput.

5. No forest land involved in lease area

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State

within 10 kms and beyond2. A village road (Tarapur-Tihri kusumi) is crossing lease boundary. It may be clarified whether any bridge exists on river at point where it crossing the river.

Secretary, SEAC 10

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation pending

6. 63875/ 1832-NCM/04-2017

Sri Ashish Yadav, At/Po- Diphupada, Dist – Jharsuguda.

Jharsuguda

Sand Panchpada Sand Bed (E) (15.00 Acres Or 6.07 Ha.) At Village-Panchpada, Tahasil-Jharsuguda, Dist-Jharsuguda

FY 2015- 16 to 2019 -20

Nil 1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

No 3000 The SEAC recommended to grant EC valid from the date of EC accorded upto the lease period.

Secretary, SEAC 11

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

4. Mining Plan has been approved by Dy. Director Geology, Zonal Survey, Sambalpur.

5. No forest land involved in lease area

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within

Secretary, SEAC 12

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

5 km radius of the mine lease area.

7. There is no court case / litigation pending

7. 53339/ 1641-NCM/04-2016

Sri Rakesh Kumar Sahoo, At – Mirapatana, Post/Ps- Kendrapara, Dist - Kendrapada

Kendrapara

Sand Ramachandrapur Luna River Sand Bed over an area of 5.060ha under Garadpur Tahasil, Dist – Kendrapada, Odisha.

FY 2015- 16 to 2019 -20

No other mines within 500 meter from the lease area.

1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

4. Mining Plan approved by the Geologist, Directorate of Geology,

No 5250 The SEAC recommended to grant EC valid from the date of EC accorded upto the lease period.

Secretary, SEAC 13

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

Bhubaneswar

5. No forest land involved in lease area

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation

Secretary, SEAC 14

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

pending.

8. The proposal was placed before the SEAC in its meeting held on 23.03.2017. The SEAC decided to consider the proposal after receipt of clarification from Tahasildar about name of river whether it is Luna or Chitrotpala.

9. The Tahasildar has clarified that the proposal of sand sairat source Ramachandr

Secretary, SEAC 15

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

apur belongs to Chitrotpala River Sand Bed over an area of 5.060 ha. under Garadpur Tahasil.

8. 61120/ 1759-NCM/12-2016

The Tahasildar Jujomura, Dist - Sambalpur.

Sambalpur

Sand Gargadbahal Sand Quarry (13.33 acre/ 5.394 Ha) At Village-Gargadbahal,Tahasil-Jujomura, Dist-Sambalpur

FY 2015- 16 to 2019 -20

No other mines within 500 meter from the lease area.

1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP Submitted.

4. Mining plan approved by Dy. Director Mines, Sambalpur Circle, Sambalpur.

5.No forest land

No 562.5 Appendix-I page-5, 2/2.3 as submitted vide letter no. 1151, dated 18.04.2017 may be clarified. How from a sand quarry annual production of ordinary stone be 2555.25 m3. The Tahasildar, Jujomora may be asked for necessary clarification as mentioned above.

Secretary, SEAC 16

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

involved in lease area

6.There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation pending.

8. The proposal was placed before the SEAC in its

Secretary, SEAC 17

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

meeting held on 31.03.2017 and the SEAC observed the following:

Appendix-I page-5, 2/2.3 may be clarified. How from a sand quarry annual production of ordinary stone be 2555.25 m3.

9. The Tahasildar has not clarified the matter. However, only furnished filled in Appendix-I without changing the page-5, 2/2.3 of Appendix-I i.e. production of ordinary stone be 2555.25 m3.

Secretary, SEAC 18

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

9. 63503/ 1820-NCM/03-2017

Sri Makardhawaj Patel (Auction Holder), At – Kapsila, Post – Rajborasambar, Dist – Bargarh

Bargarh Sand Proposal for Kumunibahali-A Sand Quarry (Ong River Sand Bed) over an area 20.00 acres or 8.09 ha. at village Kumunibahali Tahasil Padampur in the district of Bargarh.

FY 2015- 16 to 2019 -20

Kumunibahali-B – 8.10 ha.

1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

4. Mining plan approved by MD. Q.J.Khan, Geologist/ approving Officer, O/o Joint Director Geology, Sambalpur

5. No forest land involved in lease area

NO 1442.5 The SEAC recommended to grant EC valid from the date of EC accorded upto the lease period with a condition that a safety zone of minimum 200 meter will be maintained on the bridge side of the lease area.

Secretary, SEAC 19

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation pending.

8. The proposal was placed before the SEAC in its

Secretary, SEAC 20

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

meeting held on 27.01.2017 and the SEAC perused the Environment Management Plan submitted by the project proponent. The sustainable sand mining management guideline clearly recommends that no mining zone of minimum 200m is to be maintained on either side of the bridge. The EMP suggests to keep a 30 mt safety zone on either side

Secretary, SEAC 21

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

of the bridge. In view of the above, the proposal was rejected.

9. The proponent has submitted a fresh proposal with revised EIA/EMP report (cluster approach) and modified approved mining plan. In the revised EMP, it has been suggested that a safety zone of more than 200 meter (Kumunibahali-A- 226 meter and kumunibahali

Secretary, SEAC 22

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

-B- 213 meter) will be maintained on both side of the bridge of both the lease area.

10. The proposal was again placed before the SEAC in its meeting held on 24.04.2017 and the SEAC observed the following:

The Deputy Director, Geology, Sambalpur in his approval letter (point 5) dt. 20.6.2015 of the mining plan of Kumunibahal A has mentioned

Secretary, SEAC 23

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

that the mining lease was subjudice. But the proponent in Form-I (sl. No. 24) submits that there is no litigation pending against the project. In view of this contradiction the proponent may clarify the actual position.

11. The concerned Tahasildar has clarified the actual position of the litigation pending against the project.

Secretary, SEAC 24

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

10. 63504/ 1821-NCM/03-2017

Sri Makardhwaj Patel (Auction Holder), At- Kapsila, Post – Rajborasambar, Dist – Bargarh.

Bargarh Sand Proposal for Kumunibahali-B Sand Quarry (Ong River Sand Bed) over an area 20.02 acres or 8.10 ha. at village Kumunibahali, Tahasil Padampur in the district of Bargarh.

FY 2015- 16 to 2019 -20

Kumunibahali-A – 8.09 ha.

1. Furnished filled in Form-I, pre-feasibility report and check list forwarded by Tahasildar.

2. Topo sheet indicating location of the mine has been furnished.

3. EMP submitted.

4. Mining plan approved by MD. Q.J.Khan, Geologist/ approving Officer, O/o Joint Director Geology, Sambalpur.

5. No forest land involved in lease area

NO 1466.5 The SEAC recommended to grant EC valid from the date of EC accorded upto the lease period with a condition that a safety zone of minimum 200 meter will be maintained on the bridge side of the lease area.

Secretary, SEAC 25

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

6. There is no protected areas i.e. National Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve, Protected Monuments, Inter-State boundary and critically polluted area as identified by CPCB etc. located within 5 km radius of the mine lease area.

7. There is no court case / litigation pending.

8. The proposal was placed before the

Secretary, SEAC 26

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

SEAC in its meeting held on 27.01.2017 and the SEAC perused the Environment Management Plan submitted by the project proponent. The sustainable sand mining management guideline clearly recommends that no mining zone of minimum 200m is to be maintained on either side of the bridge. The EMP suggests to

Secretary, SEAC 27

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

keep a 30 mt safety zone on either side of the bridge. In view of the above, the proposal was rejected.

9. The proponent has submitted a fresh proposal with revised EIA/EMP report (cluster approach) and modified approved mining plan. In the revised EMP, it has been suggested that a safety zone of more than 200

Secretary, SEAC 28

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

meter (Kumunibahali-A- 226 meter and Kumunibahali-B- 213 meter) will be maintained on both side of the bridge of both the lease area.

10. The proposal was again placed before the SEAC in its meeting held on 24.04.2017 and the SEAC observed the following:

The Deputy Director, Geology, Sambalpur in his approval letter (point 5) dt. 20.6.2015 of the mining plan of

Secretary, SEAC 29

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

Kumunibahal- B has mentioned that the mining lease was subjudice. But the proponent in Form-I (sl. No. 24) submits that there is no litigation pending against the project. In view of this contradiction the proponent may clarify the actual position The Deputy Director, Geology, Sambalpur in his approval letter (point 5) dt. 20.6.2015 of the mining plan of Kumunibahal A & B has mentioned that both the mining lease were subjudice. But the proponent in Form-I (sl. No. 24) submits

Secretary, SEAC 30

Sl. No

SEIAA File No.

Name & Address of the proponent

District Type of Mineral

Name of the project

Mining lease period

Details of other mines including lease area located within 500 m from the periphery of the proposed mine lease area

Observation of SEAC based on form-I, prefeasibility report, approved mining plan and checklist

Whether

general

condition

apply

Maximum annual production capacity (in m3)

Recommendation of SEAC

that there is no litigation pending against the project. In view of this contradiction the proponent may be clarify the actual position.

11. The concerned Tahasildar has clarified the actual position of the litigation pending against the

project.

Chairman, SEAC