    THE PEOPLES COMMITTEE

    OF BINH DINH PROVINCE

    ----------

    Ref: 637/QD-UBND

    THE SOCIALIST REPUBLIC OF VIET NAM

    Independence Freedom Happiness

    Quy Nhon, 27 Aug 2009

    DECISIONOn the approval of the Province Solid Waste Master Plan (PSWMP) for the urban

    areas and the industrial zones in Binh Dinh area up to 2020

    _______________________

    THE CHAIRMAN OF THE PROVINCIAL PEOPLES COMMITTEE

    Considering the Law on Organization of the Peoples Council and the Peoples

    Committee dated 26 Nov 2003;

    Considering the Resolution Nr.10/2009/NQ-HDND dated 15 Jul 2009 of the 10

    th

    Provincial Peoples Council at the 15 th session adopting the content of the PSWMP for

    the urban areas and the industrial zones in Binh Dinh area up to 2020;

    Considering the Decree Nr.59/2007/ND-CP dated 7 Apr 2007 of the Government

    on the solid waste management;

    Considering the proposal of the Department of Construction at the Proposal Letter

    Nr.57/TTr-SXD dated 14 Aug 2009 on the PSWMP for the urban areas and the industrial

    zones in Binh Dinh area up to 2020;

    DECIDES

    Article 1. To approve the PSWMP for the urban areas and the industrial zones in

    Binh Dinh area up to 2020, with the following main contents:

    1. Plan title: PSWMP for the urban areas and the industrial zones in Binh Dinh area

    2. View of point and objective of the plan:

    a. View of point:

    - The PSWMP must conform to the Solid Waste Management Strategy for

    the urban area and the industrial zones in Viet Nam up to 2020, which was

    approved by the Government, and the Provincial Social-Economic DevelopmentMaster Plan up to 2020. It must also conform to the sector plans (urban, industry,

    health) approved by the Provincial Peoples Committee.

    - Approach the current solid waste management methods of the advanced

    countries in the world, and suit the conditions of Viet Nam. Apply selectively up-

    to-date processing technologies that suit the economic conditions, technological

    level of our country and our province. Minimize the solid waste amount to be

    buried in order to minimize the environmental impact and investment cost as well

    as increase the land use effect.

    - Arrange reasonably the locations for the solid waste treatment plants in theprovincial area so that each waste treatment plant will serve one area with the

    fitting radius (not according to the administrative units). Give the priority to the

    1

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    2/15

    treatment plants for hazardous solid waste, in urban areas and in centralized

    industrial zones. Planning and building solid waste treatment plants must assure

    the sanitation, must not affect the health, livelihood and living activities of the

    population.

    b. Objective: General objective:

    Formulate the solid waste management general strategy in Binh Dinh area up to

    2015, and the orientation up to 2020, in order to ensure the sustainable development of

    Binh Dinh province during the development of the Central Focus Economic Zone.

    Specific objective:

    - Referring to the Resolution of the Provincial Party General Meeting Nr.17:

    100% of the urban domestic solid waste, hazardous industrial solid waste, health

    solid waste are collected and treated in according to the environmental standards,following the schedule:

    + Up to 2015: 100% of the domestic solid waste from Quy Nhon city and 70% of

    the domestic solid waste from other urban areas are collected and treated; 100% of the

    solid waste from the industrial zones is separated, collected and treated by applicable

    methods.

    + Up to 2020: 100% of the domestic solid waste from Quy Nhon city, 80% of the

    domestic solid waste from other urban areas are collected and treated; 100% of the

    domestic solid waste from the urban areas is separated at the source.

    - Improve the State management effect on solid waste management, increasethe service quality of collection, transporting and treating solid waste, and improve

    the living environment quality to meet the increasing demand of the society.

    3. Scale and objects of the plan:

    - Plan scale: Binh Dinh area with 602,600 ha and about 1,536 million of

    population.

    - Plan objects:

    + Domestic solid waste from urban areas and from rural residential zones

    + Industrial solid waste from industrial zones, small industrial zones andmanufactories

    + Health solid waste

    4. Content of the PSWMP up to 2020:

    a. The current situation of solid waste management:

    Domestic solid waste:

    The current urban domestic solid waste amount from the provincial area is about

    306.6 ton/day.

    - The separation of solid waste has not been done at the source. The separation at

    the landfills is spontaneous.

    2

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    3/15

    - The collection and transport of solid waste: In Quy Nhon city, the average

    collection rate is 85%. In the districts, the collection is 15-30% and usually carried

    out at the towns and some town-adjacent communes.

    - The treatment of solid waste: The treatment technology is mainly burying. In Binh

    Dinh province, there are 9 landfills, in which there is only one hygienic landfill inLong My. The other landfills in districts are temporary, unhygienic. They do not

    have the wastewater treatment system, enclosure walls. They are small, from 0.5

    to 1 ha. Therefore, they cannot meet the demand of solid waste treatment in the

    future.

    Industrial solid waste:

    - The industrial solid waste in Binh Dinh province has not been collected

    systematically, so there are no statistic figures on the industrial solid waste

    amount.

    - The separation of the industrial solid waste has not been done thoroughly, themanufactories usually only separate the solid waste that gives them some

    economic value. The solid waste that has no economic value, inclusive of

    hazardous solid waste, is collected and mixed with domestic solid waste.

    - The collection and transport of industrial solid waste is in charge of the

    manufactories.

    - The treatment of industrial solid waste: The industrial solid waste that can be

    recycled is sold to the waste purchasing agencies or recycling agencies. The

    hazardous industrial solid waste has not been separated and treated systematically

    as stipulated.

    Health solid waste:

    - Health solid waste includes 2 components: hazardous solid waste and non-

    hazardous solid waste.

    - Currently, the total hospital beds in the entire province are about more than 2,500.

    The total health solid waste from hospitals in Binh Dinh province is estimated

    more than 700 ton/year, in which hazardous solid waste is about more than 100

    ton/year.

    - All the hospitals in Binh Dinh province separate solid waste at the source and treatthe hazardous solid waste relatively well by incinerators. However, some other

    health agencies has not separated solid waste at the source, health solid waste is

    collected and mixed with domestic solid waste and then transported to the

    landfills, or buried at unsuitable places that can cause environment pollution.

    b. Forecast of the solid waste amount up to 2020:

    The total solid waste amount in the entire province is expected to be 8,073

    ton/day, in which:

    - Domestic solid waste: 1,176 ton/day

    - Industrial solid waste: 6,724 ton/day

    - Health solid waste: 8.5 ton/day

    3

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    4/15

    (The building waste in urban areas is not the object of this plan)

    c. Planning the system of solid waste separation collection transport:

    Domestic solid waste:

    - Separation at the source: Solid waste needs to be separated at the source(households, organizations ) into 3 categories: organic waste, recyclable waste

    and non-recyclable waste.

    - Collection process:

    + In urban areas (towns, cities): Separate solid waste at the source for all

    households having domestic solid waste. Manually collect solid waste to

    intermediate points daily. Mechanically transport solid waste to centralized

    separation and treatment areas.

    + In rural residential zones: Manually collect solid waste to intermediate points

    daily or every two days. Mechanically transport solid waste to landfills within20km.

    Industrial solid waste:

    - Separation: Industrial solid waste must be separated at manufactories,

    industrial zones or small industrial zones; separated into recyclable, reusable,

    fertilized, buried and hazardous solid waste. The separation of solid waste at the

    centralized separation area of the industrial zones aims to gather a large solid

    waste amount of many industrial manufactories.

    - Collection, transport: For the industrial zones / small industrial zones: The

    collection and transport must conform to the solid waste management regulationof the industrial zones / small industrial zones. For the manufactories that do not

    belong to the industrial zones / small industrial zones: The separation, collection

    and transport is self-managed through contracting with an agency who is licensed

    to collect and transport solid waste.

    Health solid waste:

    - Health solid waste includes: domestic health solid waste and hazardous

    health solid waste from hospitals, and health solid waste from other health

    agencies.

    - Health solid waste from all health agencies is separated at the source, after

    separation, they will be collected and transported to the dumping ground of

    hospitals or the treatment plant. The detailed process is as follows:

    + After being separated at the source, domestic health solid waste from health

    agencies is collected and transported to the landfills and is treated together with

    urban domestic solid waste.

    + Hazardous health solid waste: For big hospitals, it is required to build their own

    incinerations to treat hazardous health solid waste. For individual health agencies,

    hazardous health solid waste is collected by specialized means and transported toincinerations at centralized treatment plants.

    4

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    5/15

    - Manage health solid waste according to the Health Solid Waste

    Management Regulation issued enclosing to the Decision Nr.43/2007/QD-BYT of

    the Ministry of Health.

    d. Planning solid waste treatment system up to 2020:

    - In every district, city and town, there is 1 hygienic and standard solid wastetreatment plant. The operation radius of each solid waste treatment plant is about

    20km. Each treatment plant can receive and treat domestic solid waste from urban

    areas and rural residential zones of other administrative areas but within its

    operation radius.

    - Domestic solid waste from urban areas and rural residential zones, non-

    hazardous industrial solid waste and non-hazardous health solid waste are treated

    in the district administrative areas (apart from Tuy Phuoc district, which can use

    Long My landfill).

    Planning solid waste treatment plants up to 2020:

    - 1 conjugate treatment plant at Cat Nhon commune of Phu Cat district, 70 ha

    (approved by the Prime Minister in the Decision Nr.1440/QD-TTg dated 6 Oct

    2008, which approves the construction plan of the solid waste treatment plants for

    3 focus economic zones South, Central and North up to 2020).

    - 14 treatment plants in districts and city of Binh Dinh province.

    - 11 incinerations of hazardous health solid waste, used for district health

    agencies, placed in solid waste treatment plants. Place 4 incinerations of hazardous

    health solid waste at big hospitals: Provincial Polyclinic, Tuberculosis and Lung

    hospital, Bong Son Polyclinic and Phu Phong Polyclinic.

    - The location of treatment plants must assure the current building criteria on

    solid waste, in which, it need to assure the criteria on geology and hydrography. It

    must be far away from big rivers, clean water supply sources, residential zones

    and assure the ecological environment.

    Orientation of solid waste treatment technology:

    Apply up-to-date processing technologies that suit the conditions of Viet Nam,

    minimize the solid waste amount to be buried. The applicable technologies are: Recycle,

    Reuse Process Burn Hygienically bury.- Intensify recycling, reusing solid waste, especially industrial solid waste.

    - For organic solid waste, compost them for the agriculture through the up-

    to-date and comprehensive technological line.

    - For the hazardous industrial solid waste and health solid waste, burn them

    by up-to-date incinerations.

    - Bury the inert substances, which can not be recycled or reused, the ashes

    and cinder that are left after the burning of hazardous solid waste. The landfill

    cells must be hygienic according to Viet Nam standard.

    5. Solution:

    a. Management Operation mechanism:

    5

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    6/15

    - The State manages through policies and guidelines. Encourage and mobilize all

    fund sources from the community and the society in the solid waste management;

    give investment incentives in order to promote the privatization in solid waste

    management at the steps of collection, transport and process.

    - The community is the subject conducting the management of solid waste.- The enterprises (organizations), which manage the solid waste, implement their

    tasks with the high responsibility to the community, under the supervision of the

    community and the inspection of the State.

    b. Task assignment:

    - The Peoples Committee of Binh Dinh province: direct the state management in all

    the activities relating to the solid waste management in the provincial area; assign,

    decentralize the localities and advising agencies to execute, monitor and handle.

    - The Department of Construction, relating departments and the Peoples

    Committees of districts/city have the functions of advising and executing

    according to the direction of the PPC and the task assignment of this plan.

    c. The implementation schedule:

    - The period up to 2015:

    + Focus on the training, capacity building and awareness raising; strengthen the

    awareness of the officers and the people on the solid waste treatment in theunlimited administrative areas; initially separate the solid waste at the source in

    large urban zones, industrial zones, small industrial zones, manufacturers and

    health enterprises; improve the policy frame.+ Focus on the investment and construction of new solid waste treatment plants

    for the districts of Hoai Nhon, Phu My, Phu Cat (at Cat Nhon commune), An

    Nhon and Tay Son; focus on the rehabilitation of the Long My solid waste

    treatment plant, using every fund source of domestic or abroad.

    + Strengthen the socialization of the solid waste management; increase the

    capacity of solid waste collection and transport; invest in the health solid waste

    management system.

    - The period from 2015 to 2020: Increase the capacity of solid waste collection and

    transport (transition projects); build centralized solid waste treatment plants for thedistricts that have not had any treatment plant; rehabilitate the existing treatment

    plants and build the recycling, reusing and treatment lines for hazardous solid

    waste; socialize the solid waste management (transition projects); conduct the

    separation at the source at the high level.

    d. Cost estimation:

    - The total investment is estimated about 1,610 billion VND, in which, about 862

    billion VND for the period up to 2015, about 748 billion VND for the period from

    2016 to 2020.

    - Fund source: government budget (244 billion), loan from ODA organizations andother foreign organizations (588 billion), grant (248 billion), socialization fund

    from private enterprises and other fund sources (532 billion).

    6

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    7/15

    Article 2. To assign the Department of Construction to bear the main

    responsibility and get the coordination of other departments and Peoples Committees of

    districts/city to instruct and implement all the contents of the Plan enclosed to this

    Decision; and make the periodical reports on the situation, especially on the difficulties

    and problems, sending to the PPC for timely direction and solution.

    Article 3. The Chief of PPC Secretariat, the Directors of the Department of

    Planning and Investment, Construction, National Resources and Environment, Finance,

    Industry and Commerce, Science and Technology, Health, the Chief of Nhon Hoi

    Economic Zone Management Unit, the Chairpersons of district/city Peoples

    Committees, and the heads of relating agencies are responsible for executing this

    Decision since the signing date./.

    Recipients:

    - As referred to in the Article 3;

    - Ministry of Construction;- Provincial Standing Committee of the Party;

    - Provincial Standing Committee of the PeoplesCouncil;

    - Chairman and Vice Chairpersons of PPC;- Provincial Police Department;

    - Department of Justice;

    - Quy Nhon Urban Environment Ltd. Company;- Binh Dinh newspaper and TV station;

    - Provincial center of official gazette;

    - Secretariat leaders;

    - Admin, K14 and K4 filed.

    ON BEHALF OF PPC

    CHAIRMAN

    signed and stamped

    Nguyen Van Thien

    7

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    8/15

    ANNEX 1

    ESTIMATED AMOUNT OF SOLID WASTE UP TO 2015 AND 2020

    (Enclosing to the Decision Nr.637/QD-UBND dated 27 August 2009 of the Provincial Peoples Committee)

    Domesticsolid

    waste

    Buildingsolid

    waste

    Industrialsolid

    waste

    Healthsolid

    waste

    Sewer

    mudTotal

    Domesticsolid

    waste

    Buildingsolid

    waste

    Industrialsolid

    waste

    Healthsolid

    waste

    Sewer

    mudTotal

    1 Quy Nhon 508 40.6 1107.6 5.64 30.48 1,692 676 54.1 1590.1 6.23 40.56 2,367

    2 An Nhon 93.95 7.5 54 0.22 5.64 161 118.5 9.5 77.6 0.24 7.11 213

    3 Tuy Phuoc 21.5 1.7 9.8 0.15 1.29 34 30.2 2.4 14 0.17 1.81 49

    4 Phu Cat 56.625 4.5 118.6 0.18 3.4 183 88.05 7 4545.3 0.2 5.28 4,646

    5 Tay Son 44.75 3.6 253.1 0.44 2.69 305 69.5 5.6 363.3 0.48 4.17 443

    6 Van Canh 10.3 0.8 3.2 0.07 0.62 15 13 1 4.5 0.07 0.78 19

    7 Hoai Nhon 80 6.4 30.4 0.61 4.8 122 103 8.2 43.6 0.67 6.18 162

    8 Hoai An 15.875 1.3 4.2 0.08 0.95 22 18.95 1.5 6 0.09 1.14 28

    9 Phu My 28.3 2.3 50 0.17 1.7 82 37.4 3 71.7 0.18 2.24 11510 An Lao 8.55 0.7 3.1 0.07 0.51 13 12.3 1 4.4 0.07 0.74 19

    11 Vinh Thanh 6.95 0.6 2.8 0.07 0.42 11 8.7 0.7 4 0.07 0.52 14

    Total 875 70 1,637 8 53 2,642 1,176 94 6,725 8.5 71 8,073

    Nr Dis trict

    The year of 2015 The year of 2020

    1

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    9/15

    ANNEX 2

    THE LIST OF THE PROVINCE SOLID WASTE MASTER PLAN (PSWMP) FOR THE URBAN AREAS AND THEINDUSTRIAL ZONES IN BINH DINH AREA UP TO 2020

    (Enclosing to the Decision Nr.637/QD-UBND dated 27 August 2009 of the Provincial Peoples Committee)

    Nr District/City Treatment plantPlan scale

    (ha)Treatment technology Service scale Note

    1 Phu Cat Cat Nhon solid

    waste treatmentplant (SWTP)

    70 - Bury domestic solid waste

    - Bury non-hazardous industrialsolid waste

    - Burn and bury hazardous solidwaste;

    - Recycle inorganic solid waste;

    - Treat health solid waste(burn).

    -Treat domestic solid waste and non-hazardous

    industrial solid waste for Phu Cat district, Hoa Hoi

    industrial zone, Cat Trinh industrial zone, smallindustrial zones of Phu Cat district and Nhon Hoi

    economic zone;

    - Burn and bury hazardous industrial solid waste forthe whole province;

    - Recycle inorganic solid waste for the whole

    province

    Build a new

    plant

    2 Phu Cat Phu Cat 2 SWTP

    (to the north of Ba

    mountain)

    10 - Burn domestic solid waste - The north and northeast of Phu Cat district. Build a newplant

    3 Quy Nhon city

    and Tuy Phuoc

    district

    Long My SWTP 30 - Burn domestic solid waste;

    - Burn non-hazardous industrialsolid waste;

    - Process organic fertilizer;

    - Treat health solid waste

    (burn).

    - Burn domestic solid waste and non-hazardousindustrial solid waste for Tuy Phuoc district and Quy

    Nhon city;

    - Process organic solid waste into organic fertilizer

    for Quy Nhon city, Tuy Phuoc district and Van Canh

    district

    Extend and

    upgrade the

    existing

    plant, which

    is 6ha

    4 Quy Nhon city Phuoc My SWTP 4 - Process and recycle stonepowder

    - Solid waste of stone powder at Phu Tai and LongMy industrial zones

    Existingproject

    5 An Nhon

    provincialtown

    Nhon Tho SWTP 20 - Burn urban domestic solid

    waste;

    - Burn non-hazardous industrialsolid waste;

    - Treat health solid waste

    (burn).

    - An Nhon provincial town Build a newplant

    6 Bong Son

    provincial

    Hoai Duc SWTP 20 - Burn urban domestic solid

    waste;- Bong Son provincial town Build a new

    plant

    2

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    10/15

    town - Burn non-hazardous industrialsolid waste;

    - Treat health solid waste

    (burn).

    7 Hoai Nhon Hoai Nhon 2

    SWTP (Hoai Son)

    10 - Burn urban domestic solid

    waste;

    - Burn non-hazardous industrialsolid waste;

    - Treat health solid waste(burn).

    - Hoai Nhon district (after the establishment of Bong

    Son provincial town)

    Build a new

    plant

    8 Phu My My Phong SWTP 16 - Burn urban domestic solid

    waste;- Burn non-hazardous industrialsolid waste;- Process organic fertilizer;

    - Treat health solid waste(burn).

    - Burn domestic solid waste for Phu My district;

    - Burn non-hazardous industrial solid waste for PhuMy district;

    - Process organic solid waste into organic fertilizerfor the districts of Phu Cat, Phu My, Hoai Nhon, Hoai

    An, An Nhon and Tay Son

    Build a new

    plant

    9 Phu My Phu My 2 SWTP 10 - Burn urban domestic solid

    waste;

    - The west of Phu My district Build a new

    plant

    10 An Lao An Trung SWTP 5 - Burn urban domestic solid

    waste;

    - Burn non-hazardous industrialsolid waste;

    - Treat health solid waste

    (burn).

    - An Lao district Build a new

    plant

    11 Vinh Thanh Vinh Quang

    SWTP

    5 - Burn urban domestic solid

    waste;

    - Burn non-hazardous industrial

    solid waste;- Treat health solid waste(burn).

    - Vinh Thanh district Build a new

    plant

    12 Van Canh Hiep Hoa SWTP

    (Am ravine)

    4 - Burn urban domestic solid

    waste;

    - Burn non-hazardous industrialsolid waste;- Treat health solid waste

    (burn).

    - Van Canh district Build a new

    plant

    13 Tay Son Tay Xuan SWTP 16 - Burn urban domestic solid - Burn domestic solid waste for Tay Son district; Build a new

    3

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    11/15

    waste;

    - Burn non-hazardous industrialsolid waste;

    - Treat health solid waste(burn).

    - Burn non-hazardous industrial solid waste for TaySon district, Binh Nghi industrial zone and small

    industrial zones of Tay Son district;

    plant

    14 Tay Son SWTP at the

    North of Tay Son

    district

    - - Burn urban domestic solid

    waste;

    - For the north of Tay Son and adjacent areas Build a new

    plant

    15 Hoai An An Thanh SWTP 5 - Burn urban domestic solid

    waste;

    - Burn non-hazardous industrial

    solid waste;- Treat health solid waste

    (burn).

    - Hoai An district Build a new

    plant

    Total 225 -

    4

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    12/15

    ANNEX 3

    PLAN OF THE HEALTH SOLID WASTE INCINERATORS

    IN BINH DINH PROVINCE

    (Enclosing to the Decision Nr.637/QD-UBND dated 27 August 2009of the Provincial Peoples Committee)

    Nr District/CityAmount of health

    solid waste (kg/day)

    Incinerator capacity

    (kg/time)

    Frequency

    (time/week)

    1 Quy Nhon 846.1 700 7 (2 times/day)

    2 An Nhon 32.5 50 5

    3 Bong Son provincial town 60 100 3

    4 Hoai Nhon 17.2 50 35 Phu Cat 27.5 50 3

    6 Tay Son 65.7 100 5

    7 Van Canh 10 30 4

    8 Hoai An 12.5 30 4

    9 Phu My 25 50 3

    10 An Lao 10 30 4

    11 Vinh Thanh 10 30 4

    1,152.8

    1 Quy Nhon 934.2 700 7 (2 times/day)2 An Nhon 35.9 50 5

    3 Bong Son provincial town 67.5 100 4

    4 Hoai Nhon 19.3 50 3

    5 Phu Cat 30.3 50 3

    6 Tay Son 72.6 100 5

    7 Van Canh 11 30 4

    8 Hoai An 13.8 30 4

    9 Phu My 27.6 50 3

    10 An Lao 11 30 4

    11 Vinh Thanh 11 30 4

    1,272.8

    The period up to 2015

    The period up to 2020

    Total

    Total

    5

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    13/15

    ANNEX 4

    TASK ASSIGNMENT ON THE IMPLEMENTATION

    OF THE PROVINCE SOLID WASTE MASTER PLAN FOR THE URBAN

    AREAS AND THE INDUSTRIAL ZONES IN BINH DINH AREA UP TO 2020

    (Enclosing to the Decision Nr.637/QD-UBND dated 27 August 2009of the Provincial Peoples Committee)

    Agency Functions, duties

    Department of

    Construction

    - Be the advisor of the PPC in directing the implementation of the

    PSWMP for the urban areas and the industrial zones in the

    province up to 2020, be the leader in the coordination with other

    departments to draw up an implementation plan up to 2020.

    - Assess the construction plan of solid waste treatment plants,

    monitor and supervise the construction as planned.

    - Coordinate with the districts and the Department of Planning and

    Investment to make the list of investment projects according to the

    priority order to arrange the fund sources (government budget,

    ODA fund and other fund sources according to the socialization

    policy).

    - Bear the main responsibility in the coordination with other

    departments to draw up the Provincial Solid Waste Management

    Regulation (in the districts, city, industrial zones, and health

    enterprises) and then submit it to the PPC for approval as a

    basement of state management.

    - Bear the responsibility in the coordination with the Department of Natural Resources and Environment to instruct the district/city

    Peoples Committees on the technical standards and conditions of

    location selection and solid waste intermediate point construction

    at rural residential zones.

    Department of

    Planning and

    Investment

    - Bear the main responsibility in the coordination with the relating

    departments to draw up investment incentive policies for the

    organizations that take part in the solid waste collection, transport

    and treatment in the province, and then submit it to the PPC for

    approval.

    - Bear the main responsibility in the coordination with the relatingdepartments to submit the Tender Regulation or Order Regulation

    of solid waste collection, transport and treatment service in the

    province to the PPC for approval and issuing.

    - Arrange the government budget for the solid waste management

    plans approved by the PPC.

    Department of

    Natural Resources

    and Environment

    - Be in charge of the state management on environment matters at

    the intermediate points, solid waste treatment plants in the

    province.

    - Bear the main responsibility in the coordination with the

    Department of Industry and Commerce, Binh Dinh EconomicZone Management Unit and the district/city PCs to periodically

    inspect and supervise the solid waste management situation at the

    6

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    14/15

    industrial zones, small industrial zones and enterprises in the

    province.

    - Bear the main responsibility in the coordination with the

    Department of Health to periodically inspect and supervise the

    solid waste management situation at the health agencies in the

    province.

    - Preside over the program of solid waste separation at the source.

    - Bear the main responsibility in the coordination with other

    departments to appraise the compositions and properties of solid

    waste imported to Binh Dinh.

    - Make annual reports on solid waste management, including

    domestic solid waste, industrial solid waste, health solid waste and

    hazardous solid waste in the province, and then send them to the

    Provincial Peoples Council and Provincial Peoples Committee.

    - Coordinate with the Department of Natural Resources and

    Environment to instruct the district/city Peoples Committees onthe technical standards and conditions of location selection and

    solid waste intermediate point construction at rural residential

    zones.

    Department of

    Finance

    - Appraise and submit the tariff of solid waste collection, transport

    and treatment service in the province to the PPC for approval.

    - Bear the main responsibility in the coordination with other

    departments to draw up tax and finance incentive policies for the

    organizations that take part in the socialization of solid waste

    management.

    Department ofIndustry and

    Commerce

    - Be in charge of the state management on industrial solid waste,monitor and supervise regularly the compositions of industrial

    solid waste, the amount of solid waste at industrial zones, trade

    villages and enterprises, and the implementation of solid waste

    management regulations in the province.

    - Give the instructions on the collection, transport and treatment of

    hazardous solid waste originated from industrial production.

    Binh Dinh Economic

    Zone Management

    Unit and district/city

    PCs

    - Direct and organize the solid waste management within their

    scales of control.

    - Coordinate with environment inspectors and environment police

    officers to inspect and penalize any breach of environmentalprotection regulations in term of solid waste at industrial zones.

    Department of Health - Be in charge of the state management on health solid waste in the

    province.

    - Regularly supervise the collection and treatment of hazardous

    solid waste originated from health activities in the province.

    Department of

    Science and

    Technology

    - Appraise the technologies and equipments of solid waste treatment

    and recycling in the province.

    - Appraise the treatment technologies of hazardous solid waste in

    the province.

    - Coordinate with the Department of Natural Resources and

    Environment to assess the compositions and properties of solid

    7

  • 8/6/2019 Decision 637 of Binh Dinh PPC

    15/15

    waste imported to Binh Dinh from abroad.

    PCs of city, districts

    (provincial towns)

    - Organize and implement the task of state management on

    environment and sanitation matters inclusive of solid waste in their

    areas.

    - Coordinate with the relating departments to draw up investment

    plans of solid waste treatment plants in their areas, implement the

    PSWMP as approved.

    - Set up the tariff of solid waste collection and treatment service in

    their areas, request the DoF to assess it, and then submit it to the

    PPC for approval.

    - Be in charge of planning solid waste intermediate points for rural

    residential zones in their areas.

    Urban Environmental

    Company /

    Cooperatives / Solid

    waste collection teams

    - Collect, transport and treat solid waste according to the signed

    contracts.

    - Coordinate with the DoNRE to implement pilot activities and promote the solid waste separation program at the source (at

    households, organizations, offices, schools, trading service

    enterprises )

    Environment Police - Check and penalize administratively any breach of environmental

    law; conduct investigation to any breach of environmental law;

    verify environment criteria

    - Take the initiative in engaging reconnaissance missions to any

    environmental trouble spot.

    - Coordinate with the natural resources and environment branch,

    through the combination of common administrative penalization

    methods and security professional methods, to delve into the

    penalization of breach on solid waste management and illegal solid

    waste import.

    - Have the authority to suspend an enterprise if any breach on

    environment is detected. If the enterprise does not make good his

    breach, he will be prosecuted to the law.