  • 7/28/2019 DCB Power ATP Document

    1/20

    ATP Document Page 1DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    POWER SWAP PHASE 10

    Power ATP Swap Document

    TP48200A with DCB

    Site ID: ________________________

    Location: ________________________

    Date & Time: ________________________

  • 7/28/2019 DCB Power ATP Document

    2/20

    ATP Document Page 2DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    ACB Power Solution ATP Snags Classification

    ATPDate

    Snag DetailsSnag Classification

    (Major/Minor)WorkmanshipFactor(WM) *

    ProductFactor (PrF)

    PlanningFactor (PF)

    Note: *WF: Means Snags reported due to Workmanship /Human Factor.(Technical Expertise , Skills lacking. Poor

    Workmanship etc)

    PRF: Means Snags reported due to Product Factor/Issues (Product & Design issues/flaws, High fault rate etc)

    PF: Means Snags reported due to planning factor/Issues (Poor planning and Management etc).

  • 7/28/2019 DCB Power ATP Document

    3/20

    ATP Document Page 3DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    Contents:

    S # No. Test Items Tests StatusT01 Installation of Power System Pass Fail

    T01-01 Installation of TP48200A Power Cabinet 5

    T01-02 Installation of Mixed Power cabinet DCB600 5

    T02 Commissioning of Power System

    T02-01 Commissioning of TP48200A Power Cabinet8

    T02-02 Commissioning Mixed Power System (DCB600AH) 4

    T03 AC / DC / Grounding & Alarm Cables

    T03-01Installation of AC Power Cable, DC Cables andGrounding Cables/SPD

    5

    T04 Site Tagging and Labels 3

    T05Charging and Discharging of BatteriesMixed Power System (DCB600AH)

    T05-01

    Battery Test Items 5

    Test Item: I Appearance, Wiring, Installation13

    Test Item: II Capacity Test1

    T05-02 Battery Test 1

    T06 Documentation Required 1

    T07 Annexure A 1

  • 7/28/2019 DCB Power ATP Document

    4/20

    ATP Document Page 4DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    T01 Installation of Power System

    T01-01 Installation of TP48200A Power Cabinet.

    Objective

    Verify that the installation of the Power System with PMU, PSUs complies with the engineering specifications.

    Result:

    PassFailNot RunZapped

    Comment & Remarks

    Prerequisites

    The Power system TP48200A installation as per site approved design.

    The power modules are installed in Rectifier Cabinet.

    Cabinet Security and Locking mechanism for TP48200A.

    Procedure Expected result Result

    1. Installing the TP48200A

    Power system Cabinet.

    1.1:The Power system is installed securely on the

    concrete PAD or mounting racks/ iron beams as

    per site layout.

    PassFail Not RunZapped

    1.2: No damage has been done to equipment while

    installation and door opening of installed power

    system can be > 900

    PassFail Not RunZapped

    1.3: All the packing materials are removed from the

    equipment area after equipment installation. PassFail Not RunZapped

    2. Installation of Expansionbolts for Power system

    TP48200A.

    2.1: The mounting holes for the cabinet must becarried out by drilling on concrete PAD.

    PassFail Not RunZapped

    2.2: The 4 expansion bolts (M12 x 60) are installed

    and tightened by using appropriate socket wrench. PassFail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    5/20

    ATP Document Page 5DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    2.3: The extra holes for cable entry are properly

    sealed and covered by fire resistant mud

    insulation.

    PassFail Not RunZapped

    3. Check the PSU

    Installation inside power

    cabinet TP48200A.

    3.1: The rated output current of each PSU is

    50Amps, and minimum installed quantity of PSUs

    must be 4 and all should be in working condition.

    PassFail Not RunZapped

    3.2: The empty slots of remaining PSUs are

    covered with dummy covers / slots. PassFail Not RunZapped

    4. Check the TP48200A

    cabinet locks / security

    mechanism and holes for

    cable entry.

    4.1: The Entrance door and locks of TP48200A are

    installed and operate properly, door closer is

    operational

    PassFail Not RunZapped

    4.2: The TP48200A Cabinet Security Locks and

    mechanism as per approved design.PassFail Not RunZapped

    4.3: The TP48200A Cabinet Door sealing is

    adequate and proper as per approved design. PassFail Not RunZapped

    Huawei Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    PTML Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

  • 7/28/2019 DCB Power ATP Document

    6/20

    ATP Document Page 6DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    T01-02 Installation of IBBS Cabinet DCB-600.

    Objective

    Verify that the installation of the IBBS cabinet DCB-600 complies with the engineering specifications.

    Result:

    PassFailNot RunZapped

    Comment & Remark

    Prerequisites

    The DCB-600 cabinet installation as per site layout.

    DCB batteries installed for 600AH system.

    inter-connection Battery strings.

    Procedure Expected result Result

    1. Installing the IBBS Battery

    Cabinet DCB-600.

    1.1: The DCB-600 battery cabinetis installed

    securely on the concrete PAD or mounting

    racks/ iron beams as per site layout.

    Pass Fail Not RunZapped

    1.2: No damage has been done to equipment

    while installation and door opening of installed

    IBBS cabinet can be > 900

    Pass Fail Not RunZapped

    1.3: All the packing materials are removed from

    the equipment area after equipment

    installation.

    Pass

    Fail

    Not Run

    Zapped

    2. Installation of the Expansion

    bolts of IBBS Battery

    cabinet DCB-600.

    2.1: The mounting holes for the cabinet must

    be carried out by drilling on concrete PAD.Pass Fail Not RunZapped

    2.2: The 4 expansion bolts (M12 x 60) are

    installed and tightened by using appropriate

    socket wrench.

    Pass Fail Not RunZapped

    3. Installation of DCB battery

    in IBBS Battery cabinetDCB-600.

    3.1 Check one DCB Banks are installed with

    24 battery cells and the total battery bankcapacity is up to 600AH.

    Pass Fail Not RunZapped

    3.2 The interconnection strips for each battery

    string cell to cell terminal must be tightenedPass Fail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    7/20

    ATP Document Page 7DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    Huawei Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    PTML Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    T02 Commissioning of Power System

    T02-01 Commissioning of TP48200A Power Cabinet.

    Objective

    Verify that the commissioning of the Power System connected with PMU, PSUs complies with the engineering

    specifications.

    Result:

    PassFailNot RunZapped

    Comment & Remark:

    Prerequisites

    The Power system TP48200A commissioning.

    The power modules are in working condition.

    The AC / DC and signaling cables are routed and properly connected with DCB-600.

    The Alarm connections are extended as per approved from customer and verified from NOC.

    Procedure Expected result Result

    1. Check the TP48200A

    specifications and check

    AC, DC and signal cable

    connections of TP48200A

    Power system Cabinet.

    1.1: The Power system installed is as per

    BOQ. No component in Rectifier cabinet is

    loose or damaged.

    Pass Fail Not RunZapped

    1.2: The AC power cable installed to power up

    the rectifier is power cable 4*16mm^2, (Cores:

    Red, Yellow, Green, Black) connected with

    ACDB to rectifier main breaker.

    Pass Fail Not RunZapped

    1.3: The Rating of DC cable from Rectifier to

    Battery enclosure (Wire,450/750V,

    35mm^2,Blue & Black,135A)

    Pass Fail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    8/20

    ATP Document Page 8DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    1.4: The power cables (AC/DC) are connected

    correctly, all the cable routing is proper. And all

    Alarms cables are connected.Pass Fail Not RunZapped

    2. Check PMU commissioning

    with system power

    parameters.

    2.1: The PMU has been installed and in

    working condition and PMU Display shall be

    properly visible and each parameter appearing

    on PMU shall be viewable. Blurring &

    disappearance of parameters shall fall PMU

    into faulty State.

    Pass Fail Not RunZapped

    2.2: Set all provided parameters in PMU such

    as DC float volts, boost volts, charging current;

    etc shall be appearing on PMU display.

    Date & Time Set

    Battery Capacity 600AH

    Charge Current Limit 0.1C

    Float Voltage 53.5 Volts

    Boost Voltage 56.5 Volts

    Low battery Voltage 46 Volts

    LLVD Voltage 44 Volts

    BLVD Voltage 43 Volts

    Pass Fail Not RunZapped

    3. Check the alarm LEDs on

    PMU

    4.1: On event of alarm respective LED shall lit

    on to give alarm indication.Pass Fail Not RunZapped

    4.2: No alarm is present on the Rectifier

    indicator PMU. Both battery & load power

    ratings visible on PMU are according with the

    specifications.

    Pass Fail Not RunZapped

    4. Check Extended Alarm

    connections to CPMU to

    BTS alarm Card.

    5.1: All alarms provided by customer are

    extended from TP48200A to BTS EMUA Card.Pass Fail Not RunZapped

    5.2: The EAS alarms of TP48200A cabinet are

    patched and reported at NOC.

    For Rectifier Cabinet:

    1. Mains Failure Alarm Pass Fail Not RunZapped

    2. Rectifier Major AlarmPass Fail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    9/20

    ATP Document Page 9DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    3. Rectifier Minor Alarm Pass Fail Not RunZapped

    4. Low Battery Voltage Pass Fail Not RunZapped

    5. Heat Exchanger (Fan) Alarm Pass Fail Not RunZapped

    For Battery Cabinet:

    1. Door Open AlarmPass Fail Not RunZapped

    2.DC Aircon fault Alarm Pass Fail Not RunZapped

    5. Check the status of the heat

    exchanger connections and

    working.

    6.1: The internal fans of heat exchanger are

    working and air circulation inside power cabinet

    is adequate.

    Pass Fail Not RunZapped

    6. Check the status of the

    indicators on the PMU.

    7.1 The Power-On LED is in ON state while

    rectifier working,Pass Fail Not RunZapped

    7.2: Alarm status indicators in case of any

    abnormal state or if any alarm appears on

    PMU screen,

    Pass Fail Not RunZapped

    7. Check the status of the

    indicators on the PSU.

    Power input indicator (top): ON

    Protection indicator (middle): OFF

    Fault indicator (bottom): OFF

    Pass Fail Not RunZapped

    Huawei Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    PTML Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

  • 7/28/2019 DCB Power ATP Document

    10/20

    ATP Document Page 10DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    T02-02 Commissioning Mixed Power System (DCB-600)

    Objective:

    To verify various IBBS parts installed in DCB-600 cabinet (i.e. DCB Battery, Air Condition, etc) , and to check

    DCBs can be normally charged and discharged after the mains power supply is switched on/off.

    Result:

    PassFailNot RunZapped

    Comment & Remark:

    Prerequisites

    The IBBS Cabinet is well installed with complete accessories (DCB Battery, DC/GND cables, etc).

    The IBBS DCB-600 cabinet is interconnected with TP48200A

    Procedure Expected result Result

    1. Check DC cables for DCB

    Batteries and check

    interconnection of battery

    cables between cells to

    cell.

    1.1: The cell to cell connectors for each DCB

    cell is connected and tightenedPass FailNot RunZapped

    1.2: Check the ve cable is connected

    through DC breaker in power system and all

    connections are tightened by screw wrench.Pass FailNot RunZapped

    2. Check DC Air-condition

    connections and working.

    2.1: The Air-condition is in working condition

    and power cable for powering Air-condition is

    connected with rectifier output

    Pass FailNot RunZapped

    2.2: The temperature inside IBBS cabinet is

    normal and no leakage of cool air observed

    outside IBBS cabinet.

    Pass FailNot RunZapped

    2.3: The compressor and internal fan units of

    Air-condition are in working condition.Pass FailNot RunZapped

    2.4: The Alarm cables of Air-condition are

    terminated to EMUA boardPass FailNot RunZapped

  • 7/28/2019 DCB Power ATP Document

    11/20

    ATP Document Page 11DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    3. Check signal cables b/w

    DSS

    3.1: The signal cable of cabinet DSS (Door

    Status Switch) of IBBS system is connected

    and Alarm is verified from NOC.

    Pass FailNot RunZapped

    Huawei Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    PTML Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

  • 7/28/2019 DCB Power ATP Document

    12/20

    ATP Document Page 12DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    T03 AC / DC / GNDG and Alarm Cables

    T03-01 Installation of AC Power Cable, DC Cables and Grounding Cables/SPD

    Objective

    Verify that the AC power cable, DC Cables and PGND cables &SPD are correctly processed and installed.

    Result:

    PassFailNot RunZapped

    Comment & Remark

    Prerequisites

    All internal cables (AC / DC / Alarm) are installed.

    Procedure Expected result Result

    1. Check the specifications andinstallation of AC power

    cable.

    1.1: The main AC power cable installed topower up the rectifier is Wire 4*16mm

    2

    (Cores: Red, Yellow, Green, Black)connected with ACDB to rectifier mainbreaker.

    Pass Fail Not RunZapped

    1.2: The AC Power cable must be routedseparately from other cables and both endconnections of cable are tightened with Lugs.

    Pass Fail Not RunZapped

    1.3: The AC power cable is routed and tiedinside the power cabinet and no loose

    connection from both ends.

    Pass Fail Not RunZapped

    1.4: No joint lies in the middle of the ACpower cable.

    Pass Fail Not RunZapped

    1.5: The OT terminals of the AC power cablesare wrapped up with insulating tapes/ heatshrinks.

    Pass Fail Not RunZapped

    2. Check specification andinstallation of DC Power

    cable.

    2.1: The Rating of DC cable from Rectifier to

    Battery enclosure (Wire,450/750V,

    35mm^2,Blue & Black,135A)

    Pass Fail Not RunZapped

    2.2: The positive and negative DC power

    cables are connected with IBBS cabinet andTP48200A power system cabinet.

    Pass Fail Not RunZapped

    2.3: No joint lies in the middle of the DCpower cable.

    Pass Fail Not RunZapped

    2.4: The OT terminals of the DC power cablesare wrapped up with insulating tapes/heatshrinks.

    Pass Fail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    13/20

    ATP Document Page 13DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    3. Check the specification andinstallation of GND cables.

    3.1: The rating of grounding cable (Wire, 450

    / 750V, 25mm^2, yellow green, 110A.)Pass Fail Not RunZapped

    3.2: Lugs at both ends of the power cables

    and PGND cables are soldered or securely

    crimped. Flat washers and spring washers

    are securely and closely mounted on wiring

    terminals.

    Pass Fail Not RunZapped

    4.Connection of Groundingcable to main site DC Earth

    plate.

    4.1: Grounding Cable for Cabinet shall be

    properly terminated to DC Earthing Bus bar.

    End to End connectivity of grounding cable to

    Bus bar to Earthing pit shall be verified.

    Pass Fail Not RunZapped

    4.2: The lugs at both ends of the power

    cables and PGND cables are soldered or

    securely crimped.

    Pass Fail Not RunZapped

    4.3: The bare wires and lug handles at the

    wiring terminals are tightly wrapped up with

    insulating tapes or heat-shrinkable tubes.

    Pass Fail Not RunZapped

    4.4: Flat washers and spring washers are

    securely and closely mounted on wiring

    terminals.

    Pass Fail Not RunZapped

    5. Check the Surge Protectionunits connections and

    specifications..

    5.1: The Surge Protection Devices installed inRectifier Cabinet (TP48200A) shall be inhealthy state.

    Pass Fail Not RunZapped

    5.2: The SPD rating installed in Built-in powersystem of TP48200A Cabinet shall be as per

    design.

    Pass Fail Not RunZapped

    5.3: Check Color of on front of SPD shall beGREEN, In case of RED/BLACK, it isdeclared to be faulty.

    Pass Fail Not RunZapped

    Huawei Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    PTML Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

  • 7/28/2019 DCB Power ATP Document

    14/20

    ATP Document Page 14DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    T04 Site Tagging and Labels.

    Objective:

    Verify that the Tagging and Labels of each new installed part /spare are proper.

    Result:

    PassFailNot RunZapped

    Comment & Remark

    Prerequisites

    Check Tagging and Labels of each item for newly installed system / cabinet / cables etc.

    Procedure Expected result Result

    1. Labels / Taggingspecifications.

    1.1: The labeling and tags of every iteminside both power & battery cabinet must bepasted as per delivered in systemaccessories package.

    Pass Fail Not RunZapped

    1.2: The Tags should be bold visible andpasted in printed form, Pass Fail Not RunZapped

    1.3: The insulation of tags must be of goodquality and can sustain in the environmentalconditions.

    Pass Fail Not RunZapped

    1.4: Hard Plastic type tags pasted at theoutdoor routing of every cable if it is routedinside duct / GI flexible pipe.

    Pass Fail Not RunZapped

    2. Labels / Tagging of Cables(AC / DC / communication /

    Alarm etc)

    2.1: The Tags must be pasted at the bothends of each cable (AC/DC/Alarm/Signal)inside both cabinets TP48200A and IBBSDCB-600 cabinet.

    Pass Fail Not RunZapped

    3. Labels of DCB Batteries and

    Alarm cables

    - All installed DCB batteries are tagged withits battery cell number for each cell. Pass Fail Not RunZapped

    - All alarm cables for every extended alarmmust be pasted with proper taggingseparately inside BTS and power system.

    Pass Fail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    15/20

    ATP Document Page 15DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    Huawei Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    PTML Representative

    Name:_____________________

    Signature:__________________

    Date:______________________

    T05 TEST PROCEDURES

    T05-01 Testing of Extended Alarms of TP48200A Rectifier from NOC

    Num of Test Case EAS Alarm Test # 1Name of test Case Mains FailurePreset Conditions Alarm Testing at Wapda & D.G. Power shutdownTest Procedures 1) Check float voltages on CPMU screen.

    2) Turn Off the Mains power supply from ACDB

    3) Check MF Alarm signal observed at CPMU LED indicator.

    4) Call to NOC for MF Alarm verification

    5) Restore Wapda or D.G supply and check float voltages again.

    Expected Results Mains Failure alarm reported to NOC.Test Results Pass / Fail

    Num of Test Case EAS Alarm Test # 2Name of test Case Rectifier Major AlarmPreset Conditions Alarm testing at any Major fault occurs in rectifierTest Procedures 1) Check float voltages on CPMU screen and Alarm LED is OFF.

    2) Unplug & remove any 2 modules (PSUs) from the rectifier.

    3) Check alarm indication observed on CPMU

    4) Call to NOC for Major Alarm verification

    5) Connect the PSUs again with rectifier and check Alarm indication OFF.

    Expected Results Rectifier Major alarm reported to NOC.Test Results Pass / Fail

    Num of Test Case EAS Alarm Test # 3Name of test Case Rectifier Minor AlarmPreset Conditions Alarm testing at any Minor fault occurs in rectifier

  • 7/28/2019 DCB Power ATP Document

    16/20

    ATP Document Page 16DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    Test Procedures 1) Check float voltages on CPMU screen and Alarm LED is OFF.2) Unplug & remove one SPD unit from the rectifier.

    3) Check alarm indication observed on CPMU

    4) Call to NOC for Minor Alarm verification

    5) Connect the SPD unit again with rectifier and check Alarm indication OFF.

    Expected Results Rectifier Minor alarm reported to NOC.Test Results Pass / Fail

    Num of Test Case EAS Alarm Test # 4Name of test Case Low Battery Volt AlarmPreset Conditions Alarm testing if DCB battery bank voltages are Low.Test Procedures 1) Adjust low battery voltage value to 48V from CPMU

    2) Adjust float voltage value to 47.5V

    3) Check low battery voltage indication on CPMU

    4) Confirm alarm from NOC

    5) Adjust low battery voltage value back to 46V from CPMU and float voltage to

    53.5V

    6) confirm alarm disappears on CPMU and NOC

    Expected Results Low Battery alarm reported to NOC.Test Results Pass / Fail

    Num of Test Case EAS Alarm Test # 5Name of test Case Heal Exchange FaultPreset Conditions Alarm testing if Temperature inside HPS48300 cabinet increased.Test Procedures 1) Open the door of rectifier cabinet and turn its fan off.

    2) Call to NOC for Low Heat Exchg.alarm verification.

    3) Again restore power supply of Heat Exchange Unit.

    Expected Results Low Battery alarm reported to NOC.Test Results Pass / Fail

    T05-02 Testing of Extended Alarms of DCB 600AH Battery Cabinet from NOC

    Num of Test Case EAS Alarm Test # 1Name of test Case DC AirCon Fault AlarmPreset Conditions Alarm testing if DC Aircon of Battery Cabinet not working.Test Procedures 1) Check DC Aircon of BB Cabinet is in working condition.

    2) Turn Off the breaker of DC AirCon form Rectifier unit.

    3) Check AirCon fault Alarm signal at EMUA card against dedicated port #.

    4) Call to NOC for AirCon Fault Alarm verification.

  • 7/28/2019 DCB Power ATP Document

    17/20

    ATP Document Page 17DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    5) Again Turn-On the breaker of DC Aircon and check Alarm indication OFF.

    Expected Results AirCon Fault Alarm reported to NOC.Test Results Pass / Fail

    Num of Test Case EAS Alarm Test # 2Name of test Case Door Switch AlarmPreset Conditions Alarm testing for Door of Battery CabinetTest Procedures 1) Check DC Aircon of BB Cabinet is in working condition.

    2) Open the Door of Battery cabinet.

    3) Check DSS Alarm signal at EMUA card against dedicated port #.

    4) Call to NOC for DSS Alarm verification.

    5) Again close the door of battery cabinet and check Alarm indication OFF.

    Expected Results DSS Alarm reported to NOC.Test Results Pass / Fail

    T05 Charging and Discharging

    T05-01 Charging and Discharging of DCB Batteries

    Objective:

    Verify that the Batteries can be normally charged and discharged after the mains power supply.

    Result:

    PassFailNot RunZappedComment & Remark:

    Prerequisites

    The DCB batteries are well installed.

    The mains power supply for the Rectifier TP48200A is working normally.

    The BTS is working normally.

    Procedure Expected result Result

    1. Health check of battery

    banks

    1.1: PTML standard battery health check

    template (attached) is attached with ATP

    documents for battery testing.

    Pass Fail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    18/20

    ATP Document Page 18DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    2. Voltage measurement of

    batteries

    2.1: Take the complete cell to cell voltage

    readings before commencing battery test.

    Pass Fail Not RunZapped

    3. Battery heath check 3.1: Shutdown the AC Input supply of Rectifier

    to take batteries on load

    Pass Fail Not RunZapped

    3.2: Check the batteries feeding power to load

    after disconnection of AC power.

    Pass Fail Not RunZapped

    3.3: Take the complete bank & cell voltage

    readings after every 30 minutes.

    Pass Fail Not RunZapped

    3.4: Check that tested battery backup for

    cabinet is as per designed backup.

    Pass Fail Not RunZapped

    3.5: Is tested battery backup is up to/greater

    than designed backup.

    Pass Fail Not RunZapped

  • 7/28/2019 DCB Power ATP Document

    19/20

    ATP Document Page 19DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    T05-02 Battery Test:

    BATTERY BANK TEST CHECKLIST

    ank No: of Cell Float / Discharge Cell Voltages

    1

    Time (mins) :: Before Test 30 mins 60 mins 90 mins 120 mins 150 mins 180 mins Restore VoCell 1

    Cell 2

    Cell 3

    Cell 4

    Cell 5

    Cell 6

    Cell 7

    Cell 8

    Cell 9

    Cell 10

    Cell 11

    Cell 12

    Cell 13

    Cell 14

    Cell 15

    Cell 16

    Cell 17

    Cell 18

    Cell 19

    Cell 20

    Cell 21

    Cell 22

    Cell 23

    Cell 24

    Output Voltage

    Output Current

    Ambient Temp:

    Observations: REMARKS ( GOOD / AVBAD )

    Last Discharge O/P Voltage Discharge Time(Hrs)

  • 7/28/2019 DCB Power ATP Document

    20/20

    ATP Document Page 20DCB Power SolutionUfone/Technical/ANO/DOC/04/00

    T06 Documentation Required:

    Objective:

    All Site related documentation and BOQ provided.

    Result:

    PassFailNot RunZapped

    1. Equipment BOQ Available Not Available

    2. Equipment Layout Available Not Available

    3. DCB Battery Configuration / Connection layout Available Not Available

    4. Power Parameters Available Not Available

    T07 Annexure A:

    Spare Type Supplier Type Marker Qty (as per BOQ)

    AC Cable

    ZRA-VV-0.6/1KV 4x16mm^2&100

    ZRA-VV-0.6/1KV 4x16mm^2

    DC Cable(Blue/Black)

    60227IEC02(RV) 35mm^2

    60227IEC02(RV) 35mm^2&02

    60227IEC02(RV) 35mm^2&01

    Ground Cable

    60227IEC02(RV) 25mm^2&02

    60227IEC02(RV) 25mm^2

    60227IEC02(RV) 25mm^2&01

    SPDLevel-B Surge Protection 60KA,8/20s,220V /225V-N - HUAWEI

    1 Unit