day 1 - revision

19
Day 1 Revision

Upload: jeffrey-cheah

Post on 13-Apr-2017

199 views

Category:

Leadership & Management


0 download

TRANSCRIPT

Page 1: Day 1 - Revision

Day 1 Revision

Page 2: Day 1 - Revision

2

Page 3: Day 1 - Revision

1. Integration Management

Page 4: Day 1 - Revision

4Project Management PlanThe Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents the actions necessary to define, prepare, integrate and coordinate the various planning activities. The PMP defines how the project is executed, monitored and controlled, and closed. It is progressively elaborated by updates throughout the course of the project. The PMP is also a communication vehicle for ensuring key stakeholders share an understanding of the project. The PMP is NOT a project schedule. A project schedule lists planned dates for performing tasks and activities to meet milestones identified in the project plan.

Page 5: Day 1 - Revision

2. Scope Management

Page 6: Day 1 - Revision

6Scope Management PlanScope management plan is a component that describes how the scope will be defined, developed, monitored, controlled and verified. The development of the scope management plan and detailing of the project scope begin with the analysis of information contained in the project charter, project management plan, organizational process assets and relevant enterprise environmental factors. This plan helps to reduce the risk of project scope creep.

Page 7: Day 1 - Revision

3. Time Management

Page 8: Day 1 - Revision

8Develop ScheduleTo develop your project schedule, you'll need to do three things first... Define Activity Sequence Activity Estimate Activity Durations

1. Define ActivityThe first step to developing your schedule is to define the specific activities that need to be performed in order to complete the project.

2. Sequence ActivityOnce your activity list is ready, the next step is to determine the order each of the activities needs to be completed in.

3. Estimate Activity DurationsThe third step is to estimate how long each activity will take to complete. This needs to take into account the type, amount, and availability of people, material, equipment and supplies that are needed to perform each activity.

Page 9: Day 1 - Revision

9Activity Dependency

Page 10: Day 1 - Revision

10Critical Path MethodCritical path schedules... Help you identify the activities that must be completed on time in order to complete the whole project on time. Show you which activities can be delayed and for how long without impacting the overall project schedule. Calculate the minimum amount of time it will take to complete the project. Tell you the earliest and latest dates each activity can start on in order to maintain the schedule.

The CPM has four key elements... Critical Path Analysis Float Determination Early Start & Early Finish Calculation Late Start & Late Finish Calculation

Page 11: Day 1 - Revision

11Critical Path Method

Page 12: Day 1 - Revision

12Early Start & Early Finish CalculationThe Critical Path Method includes a technique called the Forward Pass which is used to determine the earliest date an activity can start and the earliest date it can finish. These dates are valid as long as all prior activities in that path started on their earliest start date and didn't slip.Starting with the critical path, the Early Start (ES) of the first activity is one. The Early Finish (EF) of an activity is its ES plus its duration minus one. Using our earlier example, Activity 2 is the first activity on the critical path: ES = 1, EF = 1 + 5 -1 = 5.

You then move to the next activity in the path, in this case Activity 3. Its ES is the previous activity's EF + 1. Activity 3 ES = 5 + 1 = 6. Its EF is calculated the same as before: EF = 6 + 7 - 1 = 12.If an activity has more than one predecessor, to calculate its ES you will use the activity with the latest EF.

Page 13: Day 1 - Revision

13Late Start & Late Finish CalculationThe Backward Pass is a Critical Path Method to determine the latest date an activity can start and the latest date it can finish before it delays the project.You'll start from the last activity in the path. The Late Finish (LF) for the last activity in every path is the same as the last activity's EF in the critical path. Late Start (LS) = LF - duration + 1.In our example, Activity 4 is the last activity on the critical path. LF = EF = 14. To calculate the LS, subtract its duration from its LF and add one. LS = 14 - 2 + 1 = 13.You then move on to the next Activity in the critical path which is Activity 3. Its LF is equal to Activity 4 LS - 1. Activity 3 LF = 13-1 = 12. It's LS is calculated the same as before by subtracting its duration from the LF and adding one. Activity 3 LS = 12 - 7 + 1 = 6.

Page 14: Day 1 - Revision

4. Cost Management

Page 15: Day 1 - Revision

15Earn Value Management (EVM)

Term Full Name Meaning

PV Planned Value Estimated value of the work planned to be done

EV Earned Value Estimated value of the work actually accomplished

AC Actual Costs Actual Costs Incurred

BAC Budget At Completion Amount budgeted for total project EAC Estimate At Completion Currently expected total for projectETC Estimate To Complete How much More to finish VAC Variance At Completion How much over/under we expect to be

Page 16: Day 1 - Revision

16EVM Formula

Name Formula Meaning

Cost Variance CV=EV-AC -ve=over budget, +ve=under budget

Schedule Variance SV=EV-PV -ve=behind schedule, +ve=ahead schedule

Actual Cost AC Actual Costs Incurred

Cost Performance Index (CPI) CPI=EV/AC We are getting _ cents out of every $ spentSchedule Performance Index SPI=EV/PV We are progressing at _% of the rate originally plannedEstimate At Completion EAC=BAC/CPI As of now, how much do we expect the total project to costEstimate To Complete ETC=EAC-AC How much more to finish Variance At Completion BAC-EAC How much over/under we expect to be

Page 17: Day 1 - Revision

17ExampleLet’s imagine our project is to build a wall around a garden. Assuming 4 equal sides, a budget of $200 per side and a schedule of 1 side per day. We should be finished in 4 days for a total of $800. If, after Day 3, our progress is as follows:

Page 18: Day 1 - Revision

18CalculationName Formula Day 3 Value

PV - Planned Value Estimated value of the work planned to be done

Should have done 3 x $200 = $600 or Percentage Complete 75%

SV=EV-PV Estimated value of the work actually accomplished

Actually done 2.5 sides $200+$200+$100 = $500 orActual Percentage Complete 62.5%

AC - Actual Costs Actual Costs Incurred $200+$220+$140=$560

Cost Performance Index Over / Under Budget factor CPI = EV / AC $500 / $560 = 0.89

Schedule Performance Index Ahead / Behind Schedule factor SPI = EV / PV

$500 / $600 = 0.83 0r62.5%/75%% = 0.83

BAC - Budget At Completion Amount budgeted for total project $800EAC - Estimate At Completion ETC=EAC-AC Currently expected total for project EAC=BAC /

CPI

ETC - Estimate To Complete How much more to finish? ETC = EAC - AC $899 - $560 = $339

VAC - Variance At Completion

How much over/under we expect to be VAC = BAC – EAC $800 - $899 = -$99

Page 19: Day 1 - Revision

19Without Goals and Plans to Reach Them,You are Like a Ship that has Set Sail with No Destination