day-01_1025 engineer's roles and risks - adrias tan

43
Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Senior Legal Counsel, Hyundai Engg & Construction Co Ltd

Upload: adrias-tan

Post on 14-Apr-2017

287 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Adrias TanMSc BSc(Hons) LLB(Hons) FCIArb FSIArb

Senior Legal Counsel, Hyundai Engg & Construction Co Ltd

Page 2: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb

Adrias TanMSc BSc(Hons) LLB(Hons) FCIArb FSIArb

Senior Legal Counsel, Hyundai Engineering & Construction Co LtdFellow, Chartered Institute of ArbitratorsFellow, Singapore Institute of ArbitratorsFellow, Singapore Institute of Builders

Member, Society of Construction Law, UKMember, Society of Construction Law, SingaporeAssociate Member, Singapore Academy of Law

Associate Lecturer, Royal Melbourne Institute of Technology (SIM Singapore)Panel of Arbitrators, SIArb

2

Page 3: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Communication of Risks to the Employer/Contractor

Importance of Aligning Engineer’s Contractual Obligations under His Agreement with the Employer, with the Provisions of the Head Contract

Limits of Engineer’s Authority

Execution of Engineer’s Work within Required Parameters of Time, Cost and Quality

Required Extent of Inspections during Construction

Particular Conditions, Misuse and Core Clauses

Questions & Answers

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 3

Page 4: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Introduction

Acting solely as the agent of the Employer; any default by the Engineer deemed as a default by the Employer (duty of care contractual nexus)

Employer not liable for acts and omissions of the Engineer; disputes finally determined by the Engineer subject to Dispute Adjudication Board’s review and dispute resolution process like arbitration

Any perceived conflicts of interest vis-à-vis independent role to act impartially, professional duty to make fair determination of certain matters, including certification, claims for cost and time; approval of submissions, review of value engineering proposals, etc.

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 4

Page 5: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Introduction

Conflated and Intertwined Roles of the Engineer Employer’s Representative

Designer issuing construction drawings, design revisions, design development, resolve design discrepancies

Site Supervisor on Quality Assurance and Quality Control of Permanent Works and Defects

Project Manager on Progress, Co-Ordination

Contracts Administration in issuing Site Instructions, Variations; Assessing, Evaluating and Determining Claims for Cost and Time; and Adjudicating Disputes

Adjudicator to Determine Disputes and Claims

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 5

Page 6: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Introduction

Perceived Conflicts: Engineer is also Designer of the Permanent Works, issues

contract and construction drawings; originator and author of own design deficiencies, lack of critical information, late issuance of requests for information

Regularising of design revisions as valid variations arising from Engineer’s own design deficiencies and not arising from Change in Employer’s Requirements

Delay, impediment or acts of prevention caused by the Engineer on the Site, affecting regular site progress, approval process, etc

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 6

Page 7: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Communication of Risks to the Employer/Contractor

Because of the Engineer’s wearing so many hats and subsuming multiple roles in a Project, he is often indispensable, to the extent that for some reasons he is absent, sick or on home leave, engaged in multiple management or technical meetings, site works can practically screech to a halt as nobody would venture to approve, consent, determine, inspect or reject on his behalf!

Risks of delay in communication of instructions from the Employer to the Contractor in terms of Changes in Employer’s Requirements

Appointment of Engineer’s Assistants with delegated but limited powers to act for and on behalf of the Engineer

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 7

Page 8: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Communication of Risks to the Employer/Contractor

Engineer’s Determination, administered on behalf of the Employer

Engineer’s role as mediator or conciliator and adjudicator in resolving disputes which invariably originates from his own office, eg., lack of information, discrepancies, validity of instructions constituting as variations, etc

Upholding maxim “nemo judex in causa sua” – one cannot adjudge his own cause

Each role in itself is an expertise and profession with institutionalised training and accreditation, presumably the Engineer is duly trained and qualified to subsume the roles and discharge such duties with impartiality, independence, fairness

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 8

Page 9: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Communication of Risks to the Employer/Contractor

Each role as mediator or conciliator and adjudicator is to be discharged as an independent and neutral party without undue influence from third parties. Can the Engineer perform this role without bias and influence

Impartial: “not favouring one party or side more than another, unprejudiced, unbiased, fair, just, equitable”

Engineer’s duty to consult with each party in an endeavour to reach agreement prior to a Determination regarding any dispute, claims or entitlement. Whether each party is deemed to include representatives of the Employers themselves, or the Engineer is acting as the Employer’s Agent or deemed to act for the Employer?

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 9

Page 10: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Communication of Risks to the Employer/Contractor

Scenario:

Contractor discovers errors, ambiguities, inconsistencies, inadequacies or other defects found in the drawings or Contract Documents, arising from design deficiencies and duly notifies the Engineer for clarification and instruction

Engineer finally resolves the design deficiencies, issues an instruction and the Contractor complies accordingly

Contractor duly submits Clause 20.1 Claims for Cost and Time due to the variation and additional works incurred

Duty of Engineer to seek approval from Employer before approving such cost and time claims

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb

Page 11: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb

Engineer’s Roles and Risks Communication of Risks to the Employer/Contractor

Stringent contractual procedures and protocol, with condition precedent to timeframe for notification of time and cost implications arising from any of the Contract Conditions

Stringent contractual procedures and protocol with regards to submission of fully detailed substantiation with supporting particulars of the basis of the claim and EOT or additional payment claimed, with time line, interim claims and final claims

Engineer exercising no discretion for minor lapses

11

Page 12: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Aligning Engineer’s Contractual Obligations under His

Agreement with the Employer, with provisions of Head Contract

Privity of Contract. The Employer engages the Engineer under a separate and independent Agreement to manage the Project for and on behalf of the Employer

The Engineer who issues an Instruction or makes a Determination on behalf of the Employer represents that he has the authority to act for and on behalf of the Employer

The absence of such Agreement between the Engineer and the Employer, with the express provisions of the Head Contract, is prima facie evidence that the Engineer has been impliedly authorised to represent the Employer

Hely Hutchinson v Brayhead [1968] 1 QB 549

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 12

Page 13: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Aligning Engineer’s Contractual Obligations under His

Agreement with the Employer, with provisions of Head Contract

Under the Agreement, Engineer is typically engaged as a Technical Expert, with functions including giving decision, opinion or consent, approve or disapprove, determine, evaluate or otherwise taking action which may affect the rights and obligations of the Employer or the Contractor

Only the Engineer has a legal relationship with the Employer. Contractor has no such contractual relationship with the Engineer, and as such the Engineer does not owe a duty of care to the Contractor

Spandeck Engg v Defence Science & Technology Agency [2007] SGCA 37

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 13

Page 14: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Aligning Engineer’s Contractual Obligations under His

Agreement with the Employer, with provisions of Head Contract The Engineer is seldom required, or need to show proof, to be a

qualified or accredited mediator, conciliator, adjudicator or arbiter to discharge his professional duties in resolving disputes. Indeed, many such positions are filled with personnel who are only trained in engineering field, very ‘streetwise’, or at best Qualified Engineer, or even as a Quantity Surveyor

The Engineer is under duty to undertake the role of impartial arbitrager between the Employer and Contractor, to exercise his discretion impartially, and having regard to the circumstances

Even if Engineer’s neglect is proven, compensation for economic loss is too remote to succeedRSP Architects v Ocean Front [1985] 3 SLR(R) 653

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 14

Page 15: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Aligning Engineer’s Contractual Obligations under His

Agreement with the Employer, with provisions of Head Contract

Under Clause 3.1, the Employer’s Specific Approval must be obtained before the Engineer is permitted to take action or exercise such Specific Authority on certain matters, e.g.:

a) Subletting the Works

b) Approving of Variation Claims or VE Proposals

c) Granting Extension of Time

d) Expending Prime Cost and Provisional Sums

e) Suspension of Works

f) Adjudicating Disputes

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 15

Page 16: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Aligning Engineer’s Contractual Obligations under His

Agreement with the Employer, with provisions of Head Contract

The Engineer usually under directive to ensure that the Contractor gets only its entitlements in strict compliance with the Contract provisions, procedures and protocol

Sometimes, unwritten rule stipulates that Engineers are precluded from seeking Employer’s approval for funds to compensate the Contractor for variations and additional works arising from the Engineer’s own design deficiencies, resulting in the Engineer resorting to interpreting the Contract with onerous requirements to disentitle the claims

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 16

Page 17: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 17

Page 18: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

The Engineer shall have no authority to amend the Contract

The Engineer has no authority to relieve either Party of any duties, obligations or responsibilities under the Contract

Examples:

Mandating extra contractual procedures or protocol not otherwise encapsulated in the Main Contract Documents or Particular Conditions

Administering the Contract with implied meaning and arbitrary interpretation of the contract terms, implied in fact rather than implied in law, so as to give effect to the Engineer’s stance

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 18

Page 19: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

The Engineer shall have no authority to amend the Contract

The Engineer has no authority to relieve either Party of any duties, obligations or responsibilities under the Contract Challenge of the Engineer’s Determination

Contractor’s legal rights to void or set aside the Contract due to fundamental breach arising from Engineer’s failure to perform his duties under the Contract, or exercising his powers ultra vires in amending or deviating the Contract, or relieving the Contractor of his duties, obligations or responsibilities under the Contract

Whether contractual recourse available to seek Engineer’s Determination, DAB or arbitration to resolve these issues

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 19

Page 20: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Limits of Engineer’s Authority

Clause 20.1

Engineer’s Roles and Risks

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 20

Page 21: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Disputable interpretation of the clause:

“If the Contractor considers himself to be entitled to any EOT or any additional payment, under any Clause of these Conditions … the Contractor shall give notice to the Engineer”

Does this clause refer to costs which are related only to Loss and Expense costs in relation to any relevant event giving rise to the claim, including EOT related costs?

Loss & Expense Claims – Cost implications due to any form of disruption, prolongation, suspension, abortive works, re-engineering, re-submission of documents

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 21

Page 22: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Disputable interpretation of the clause:

“If the Contractor considers himself to be entitled to any EOT or any additional payment, under any Clause of these Conditions … the Contractor shall give notice to the Engineer”

Does this clause refer to any Clause of these Conditions which expressly stipulates that if the Contractor suffers delay and incurs Cost … the Contractor shall give notice to the Contractor subject to this Clause 20.1

In other words, any other Clause without this stipulation is not subject to the protocol of Clause 20.1

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 22

Page 23: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Examples where Clause 20.1 is expressly stipulated that the Contractor must comply in the event of a claim:

Clause 1.9 – delayed drawings or instructions

Clause 2.1 – right of access, possession of site

Clause 4.7 – setting out

Clause 4.12 – unforeseeable physical conditions

Clause 4.24 – fossils

Clause 7.4 & 9.2 – testing

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 23

Page 24: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

More examples where Clause 20.1 is expressly stipulated:

Clause 8.4 – Extension of Time for Completion

Clause 8.5 – delay caused by Authorities

Clause 8.9 – consequences of suspension of work

Clause 10.3 – interference with tests on completion

Clause 13.7 – changes in legislation

Clause 16.1 – suspension of work

Clause 17.4 – consequences of Employer’s Risks

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 24

Page 25: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Rationale why Clause 20.1 is expressly stipulated:

objective to enable Contractor to notify Employer as soon as possible when the situation of a claim arises, to enable Employer to do something to avert unintended consequences

scheme is where potential disputes can be resolved during the course of the project rather than until the works are complete

contract clause clearly states that the party with a claim will lose the right to bring that claim if it fails to comply with the required timescale

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 25

Page 26: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Rationale why Clause 20.1 is expressly stipulated:

Bremer Handelgesellschaft v Vanden Avenne [1978] 2 LR 113, House of Lords held that a notice provision should be construed as a condition precedent, thus would be binding if:

i. it states the precise time within which the notice is to be served

ii. it makes plain by express language that unless the notice is served within that time the party making the claim will lose its rights under the clause

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 26

Page 27: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Rationale why Clause 20.1 is expressly stipulated:

Multiplex Construction v Honeywell Control Systems [2007] EWHC 447 (TCC), Mr Justice Jackson held that:

“Contractual terms requiring a contractor to give prompt notice of delay serve a valuable purpose; such notice enables matters to be investigated while they are still current. Furthermore, such notice sometimes gives the employer the opportunity to withdraw instructions when the financial consequences become apparent.”

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 27

Page 28: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Examples where Clause 20.1 is not expressly stipulated in relation to a variation cost claim:

Clause 3.3 – Instructions of the Engineer

Clause 13 – Variations and Adjustments

In the above scenario, the Engineer will typically proceed to evaluate the claims and re-measurement in accordance with Clause 12 [Measurement and Evaluation]

Poser: Is the Engineer empowered to declare that the above submissions are also subject to Clause 20.1?

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 28

Page 29: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Rationale why Clause 20.1 is not expressly stipulated in relation to a variation cost claim:

Both parties are well aware of the variation, the Engineer issuing the variation, and the Contractor receiving the variation

there is no necessity to bring to the knowledge or awareness of the other party of the existence of such an entitlement, which technically is not even a claim per se

Therefore, such variations are intentionally tracked on a completely different contractual protocol

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 29

Page 30: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

When Clause 20.1 is triggered in relation to a variation cost claim

Likely scenario is when and if the Contractor suffers disruption, prolongation or delay as a result of the variation instructed pursuant to Clauses 3.3 and 13, that he may proceed in accordance with Clauses 8.4 and 20.1 to notify the Engineer of the potential or real cost and time implications

in this case the cost implications refer to the loss and expense claims arising from the variation and not the costs of the physical permanent works arising from the variations per se

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 30

Page 31: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

When Clause 20.1 is triggered in relation to a variation cost claim

Clause 8.4 – variations and additional works giving rise to an extension of time implication

Cost implications related to extension of time, such as preliminaries including insurances, extended site resources

Loss & Expense Claims – Cost implications related to the variations, such as disruption, prolongation, suspension, abortive works, re-engineering, re-submission of documents

NB: costs of additional works not submitted under Clause 20.1

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 31

Page 32: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Disputable interpretation of the clause:

“The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance”

Who is the judge or arbiter of when should the Contractor have become aware, or should have become aware of the event or circumstance?

If the Engineer rules that the Contractor should have become aware earlier than what the Contractor claimed, and rejects the claim, is the Engineer acting ultra vires?

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 32

Page 33: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Clause 20.1

Disputable interpretation of the clause:

“The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance”

Is the Engineer empowered to declare that the date that the 28 days comes into effect is the date of the event itself, i.e., the date of issuance of the Engineer’s Instruction with design revisions, variations and additional works

Is the Contractor allowed sufficient and reasonable time to examine the drawings before this 28-days timeline is triggered?

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 33

Page 34: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

The Engineer unilateral powers and authority in interpreting the General Conditions and Particular Conditions of the FIDIC Form of Contract in a biased manner

What happens when such interpretation is ruled onerous under the contra proferentum rule, or totally misrepresenting the purposive intent and true meaning of the clauses, causing the Contractor to suffer undue losses

Does Contract become voidable when any party to the Contract is misled by undue influence, misrepresentation or fraud of any part of the Contract, resulting in a substantive deviation from the Contract

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 34

Page 35: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Effects of Misinterpretation of the Contract Terms

Rescission and Deceit Erroneous or false statement of the interpretation of the

contract, especially when the Engineer claims specialist knowledge as statements of fact

Remedy of rescission and damages; tort of deceit; damages for fraudulent misrepresentation of contract terms would include all loss flowing directly from the entry into contract, regardless whether or not such loss was foreseeable, including all consequential loss

Smith New Court Securities v Citibank [1996] 3 WLR 1051

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 35

Page 36: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Limits of Engineer’s Authority

Effects of Misinterpretation of the Contract Terms

Voidance of Contract Misstatement of facts, fraudulent misinterpretation of contract

terms persistently held as facts to administer the contract erroneously, to preclude contractual rights of claims

Heilbut, Symons v Buckleton [1912] UKHL 2

Statutory Remedy Misrepresentation Act, Cap 390, 1994 Rev Ed

Misrepresentation has become a term of contract

Damages in lieu of rescission, or voidance of contract

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 36

Page 37: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Particular Conditions, Misuse and Core Clauses

Particular Conditions should only be employed to regulate the project and the country specifics, to suit local and project peculiarities; such as prescriptions for contractual procedures and protocols in compliance with the general conditions

They should not be used to re-allocate the risks, such as changing some fundamental terms of the General Conditions

One favourite clause being the subject of Particular Conditions is Clause 20.1 where the Contractor is to give a notice of claim within the original period of 28 days, being reduced to as short as 14 days, failing which the Contractor is not entitled to additional payment or time extension

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 37

Page 38: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Particular Conditions, Misuse and Core Clauses

No clear rules on fully detailed claims with supporting particulars of the basis of claims and of EOT and additional payment claimed

As a result, Contractor’s submissions are subjected to repeated rejections for re-submissions due to Engineer’s purported reasons for lack of certain information or details, or imposing the onerous rule of strict proof

Parties should agree on these requirements through carefully drafted procedures enshrined in the Particular Conditions; eg., EOT Assessment based on Planned/Impacted/Actual Critical Path Network, framework for Loss & Expense Claims, Direct and Indirect Costs, etc

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 38

Page 39: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Interactive Voting System – Multiple Choice Questions

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb

Do you agree that the Engineer, in wearing so many hats and subsuming multiple roles in a Project, can invariably be in direct conflict of interests between the Employer and the Contractor, thus affecting his independent, unbiased and reasonable manner in discharging his duties?

(1) YES(2) NO

39

Page 40: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks Interactive Voting System – Multiple Choice Questions

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb

What do you like to see as a major revision in the FIDIC Suite of Contracts?

(1) Appointment of Engineer to be an External Independent Party, eg a Project Management Consultant

(2) The Engineer should be a Qualified Accredited Mediator, Conciliator and Arbitrator

(3) Re-define Guidelines for Particular Conditions

40

Page 41: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Engineer’s Roles and Risks References, Bibliography and Acknowledgements

1. EIC/FIDIC Questionnaire: The Use of the FIDIC Red Book, Will Hughes, University of Reading, UK, Oct 1996

2. The Engineer under FIDIC’s Conditions of Contract for Construction, Issaka Ndekugri, Nigel Smith, Will Hughes, School of Engineering and the Built Environment, University of Leeds, UK, Sept 2007

3. FIDIC Conditions of Contract as a Model for an International Construction Contract, Dr Jur Tunay Kőksal, International Journal of Humanities and Social Science, Vol. 1 No. 8: July 2011

4. The FIDIC Contracts Guide, Peter L Booen, FIDIC, 2000

5. Obrascon Huarte Lain SA v Her Majesty Attorney General for Gilbratar [2014] EWHC 1028

6. Making Claims for Time and Money, Nicholas Gould, Fenwick Elliot

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 41

Page 42: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

Adrias TanMSc BSc(Hons) LLB(Hons) FCIArb FSIArb

Adrias has more than two decades of practical working experience in the construction industry, working currently as in-house legal counsel for an MNC Company. Adrias is professionally trained in litigation, arbitration, adjudication, mediation and dispute resolution, and is an accredited arbitrator. He has handled several institutional and ad-hoc arbitral proceedings, as well as having tutored in SIArb, and conducted numerous workshops and seminars on diverse construction, contractual and legal issues including various Standard Forms of Contracts. He also lectures at the Royal Melbourne Institute of Technology, at the Singapore Institute of Management Campus teaching law subjects.Email: [email protected]

https://sg.linkedin.com/pub/adrias-tan/35/340/5ab

© 2015 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb 42

Page 43: Day-01_1025 Engineer's Roles and Risks - Adrias Tan

43