STANDING COMMITTEE ON CITY FINANCE AND SERVICES DECEMBER 16, 2015 Planning and Development Services Engineering Services DAVIE VILLAGE PUBLIC SPACE IMPROVEMENTS

Upload: others

Post on 27-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

STANDING COMMITTEE ON CITY FINANCE AND SERVICES

DECEMBER 16, 2015

Planning and Development ServicesEngineering Services

DAVIE VILLAGE PUBLIC SPACE

IMPROVEMENTS

Page 2: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of the Davie Village Public Space Improvements, including installation of an Accessible Automated Public Toilet;

THAT staff prepare and implement the Jim Deva Plaza Stewardship Strategy, and report back to Council with a broader stewardship strategy for City-owned plazas, supported by funding from the City’s Innovation Fund;

THAT the Director of Legal Services prepare amendments to various by-laws to regulate activity in Jim Deva Plaza; and,

THAT staff report back to Council with a preliminary business case for an LGBTQ “outdoor museum”.

RECOMMENDATIONPRESENTATION OUTLINESUMMARY OF RECOMMENDATIONS

Page 3: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

3

BACKGROUNDPRESENTATION OUTLINEBACKGROUND

Public open house – Oct. 22nd

Transportation 2040 (2012)

West End Plan (2013)

Heart of Davie Plaza Pilot (2013-14)

Healthy City Strategy (2014)

Council motion re: Jim Deva (Oct. 2014)

Conceptual design & “Jim Deva Plaza” naming approved (July 2015)

Page 4: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

BACKGROUNDPRESENTATION OUTLINEBACKGROUND

Jim Deva

Living Legacy Statement:

“A safe space, inspired by Jim Deva’s lifelong passion for freedom of sexuality, gender diversity, and the fight against censorship. Where LGBTQ people and allies can meet, share ideas freely, dare to dream, and love unapologetically.”

Page 5: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

PROJECT OVERVIEWPRESENTATION OUTLINEBACKGROUND

Project timeline (July to Dec. 2015):

Continued broad consultation with residents, businesses, community groups, West End BIA, City advisory committees & others

Overall more than 1,400 participant contacts

Page 6: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

PROJECT OVERVIEWPRESENTATION OUTLINEWHAT WE HEARD

Support for Jim Deva Plaza design: 76%

Support for transportation changes: 65%

Prioritization for future phases:

1. Mid-block crossing

2. Bute St, north of Davie

3. Decorative overhead feature

Support for plaza design

Page 7: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

PROJECT OVERVIEWPRESENTATION OUTLINEIMPLEMENTATION PLAN

Page 8: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

CONCEPTUAL DESIGNPRESENTATION OUTLINEPHASE ONE – JIM DEVA PLAZA

Jim Deva Plaza – 3D model view

Jim Deva Plaza

Page 9: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

CONCEPTUAL DESIGNPRESENTATION OUTLINEPLAZA DESIGN

Jim Deva Plaza – daytime rendering (looking south)

Page 10: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

10

CONCEPTUAL DESIGNPRESENTATION OUTLINEPLAZA DESIGN

Jim Deva Plaza – evening rendering (looking north)

Page 11: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

CONCEPTUAL DESIGNPRESENTATION OUTLINEPHASE ONE – JIM DEVA PLAZA

Existing Automated Public Toilet

Page 12: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

Key questions to address:- Ownership- Operations- Maintenance- Funding- Roles and

responsibilitiesConsultant to prepare preliminary business case

JIM DEVA’S COMMEMORATIONPRESENTATION OUTLINELGBTQ “OUTDOOR MUSEUM”

Legacy Walk - Chicago

Page 13: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

PLAZA MANAGEMENT STRATEGYPRESENTATION OUTLINEPLAZA STEWARDSHIP STRATEGY

Jim Deva Plaza

Stewardship Strategy

Plaza Design &

Maintenance

Safety and Policing

Special Events and Permits

Moveable Furniture

Other Programming

Elements

Monitoring and Questions

Cleanliness

Restaurant Patios

Access to Storage, Power

and Water

Outreach and Communications

Page 14: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

PLAZA MANAGEMENT STRATEGYPRESENTATION OUTLINEINNOVATION FUND

Innovation Fund Request:

Confirmed contributions from community partners

$58,500

Potential contributions from additional community partners

Up to $41,500

Innovation Fund request

Up to $100,000

Project 2-year TOTAL

Up to $200,000

Funding Allocation:

Jim Deva Plaza Stewardship Strategy test case

$60,000

Develop a broader Stewardship Strategy for City-owned Plazas

$37,000

Contingency $20,000

Other potential test cases

Up to $83,000

Project 2-year TOTAL

Up to $200,000

Page 15: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

To address concerns from public and key stakeholders

Proposed amendments to the Street and Traffic By-law, Health By-law, and Ticket Offences By-law:

- Prevent vehicles from entering plaza

- Prevent overnight loitering

- Minimize exposure to smoking

NEXT STEPSPRESENTATION OUTLINEBY-LAW AMENDMENTS

Page 16: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

If approved, construction begins in early 2016 (goal: open before Pride)

Work with key stakeholders to prepare and implement plaza stewardship strategy, initially as two year trial

Report back by 2018 as part of broader stewardship strategy for City-owned plazas

Retain consultant to develop preliminary business case for LGBTQ outdoor museum

NEXT STEPSPRESENTATION OUTLINENEXT STEPS

Page 17: DAVIE VILLAGE PUBLIC SPACE - Vancouver · 2015-12-17 · THAT Council approve the design for Jim Deva Plaza and a project budget up to $2.3 million for completion of Phase One of

STANDING COMMITTEE ON CITY FINANCE AND SERVICES

DECEMBER 16, 2015

Planning and Development ServicesEngineering Services

DAVIE VILLAGE PUBLIC SPACE

IMPROVEMENTS