david c. oehl, p.e. president maven power september 2006
TRANSCRIPT
INTERCONNECT CHALLENGES IN THE DEVELOPING WORLD’S DISTRIBUTED GENERATION INFANCY
David C. Oehl, P.E. President
MAVEN POWER
September 2006
2
TABLE OF CONTENTS
OVERVIEW ................................................................................................................................................................3 PROJECT BACKGROUND ......................................................................................................................................4 POWER PLANT OPERATION ................................................................................................................................6 CHALLENGES ...........................................................................................................................................................7 GRID INSTABILITY ........................................................................................................................... 7
LOAD SHEDDING & LOAD FOLLOWING ............................................................................................... 9
RECLOSER ISSUES.......................................................................................................................... 10
UTILITY/REGULATORY BODY ISSUES ................................................................................................ 11
CONCLUSION ..........................................................................................................................................................13
LIST OF TABLES TABLE 1. SG2 REVERSE POWER CONDITION FAULT RECORDER DATA .........................................................................8
LIST OF FIGURES FIGURE 1. 2.5MW ON-SITE POWER PLANT....................................................................................................................5 FIGURE 2. ON-SITE GENERATION SINGLE LINE DIAGRAM .............................................................................................6 FIGURE 3. ATS CONTROL, METERING & PROTECTION SYSTEMS...................................................................................7 FIGURE 4. TYPICAL OBSERVED REVERSE POWER CONDITION.......................................................................................9 FIGURE 5. RECLOSER & REVERSE POWER TIMING.......................................................................................................13
3
Overview Significant challenges await the on-site or distributed power producer wanting to interconnect to
a developing-world’s national or regional government electric utility having little or no
experience with the technical or operational considerations associated with interconnections.
Due to recent economic growth and limitations on generation or transmission capacity, these
utilities are now compelled to allow self-generation, albeit without extensive interconnect
agreements or specifications applicable to distributed generation.
This manuscript profiles a case study of one of the first distributed generation applications in a
given developing country—an onsite power plant in Colombia. In this case, the regional utility
had little experience introducing an independent generator to the grid. There was not a formal
interconnect agreement for on-site power applications. This manuscript details the technical and
operational challenges encountered and how they were overcome to ensure the safety and
availability of the grid, the on-site generation, and the end user’s plant. The type of equipment
used, operations sequences, relay protection schemes, and recloser issues are discussed. Controls
used for plant load shedding, load following, utility power import control, and breaker operation
are also discussed on an operational-level to allow the reader to follow the methods used.
The development of fast-track, personalized agreements were explored that allowed for the best
tradeoff between safety, availability, and power quality. To reach satisfaction on both sides of
the agreement, equipment additions and modifications were investigated. However, due to the
minimal responsibilities required of the grid operator, greatly expedited solutions were proposed.
It is becoming ever more apparent that distributed generation is not solely reserved for developed
countries with overheated economies. This manuscript describes some of the processes and
techniques that have successfully been used to address the growing trend towards distributed
generation in developing nations.
4
Project Background
Maven Power was contracted to provide power generation equipment and engineering services
for a 2.5 MWe on-site, distributed generation power plant in Barranquilla, Colombia. With
electrical power selling at around 11-13 cents/kWh and the price of natural gas at competitive
levels, the spark gap (cost of fuel vs. cost of open market electricity) created an attractive
scenario for on-site power. The plant was centered around two 1.33MWe natural gas fired
reciprocating engines (see Figure 1). Maven Power was responsible for the electrical power
equipment, balance of plant, and the design/integration engineering. Maven provided multiple
15kV switchgear sections, an ATS (automatic transfer switch) transfer trip control system,
protection, metering, electrical coordination, power control, SCADA, and startup &
commissioning services.
The power plant electrical configuration consisted of the two gas engines and their respective
generator circuit breakers (G-1, G-2), a step up transformer to 13.2kV (T-1), generator feeder
breaker (SG1), utility feeder breaker (SG2), and the ATS control which performed all
sequencing, monitoring, and power transfer between sources. The single line diagram given in
Figure 2 shows the setup.
5
Figure 1. 2.5MW On-site Power Plant
The plant was to be operated at base load, in parallel with the local utility (Electricaribe). On-
site generation was at 480V, 60Hz and grid interconnection was done at 13.2kV. The end user
had a relatively stable load og 2.5 - 3.0 MWe, such that the two gas engines could be operated at
rated capacity with the additional power being imported from the utility. Power export from this
facility was not permitted. The end user’s facility was located in the industrial area of the city
and connected to a general-use feeder. Downstream of the feeder, the end user’s facility and
some 70 other industrial customers were supplied through an OCR (overcurrent recloser) at
13.2kV.
6
Figure 2. On-Site Generation Single Line Diagram
Power Plant Operation
The normal operating mode for the power plant was in grid parallel with the facility’s load being
supplied by both the on-site generators and power imported from Electricaribe. In the event of
the loss of either source, the ATS control system would manage the transfer to the available
source. The control system managed the operation of the 15kV generator feed switchgear (SG1)
and the utility feed switchgear (SG2). The ATS performed an automatic transfer, which was
accomplished using a semi-closed transition scheme. Under normal conditions, 400kW was
supplied by the utility and 2000 kW by the generators. Upon loss of the normal (utility) source,
the ATS was designed to activate a load-shedding scheme, trip the utility breaker and perform a
7
closed transition to the generator supply. Just prior to the transition, the generators are toggled
from base load (constant kW control) to load sharing mode (isochronous control). The purpose
of the load-shedding scheme was to reduce the total plant load and allow the generators to carry
the remaining load in an islanded operation. Upon restoration of the utility, the ATS performed
an open transition to the utility, such that the utility carries the total plant load until the
generators are re-synchronized. Once synchronized, the generators are brought on-line and set
back to base load mode. The system then resumes normal operation. A detailed arrangement of
the control system utilized is given below in Figure 3.
Figure 3. ATS Control, Metering & Protection Systems.
Challenges Multiple challenges presented themselves throughout the course of this project. They included
issues associated with grid instability, load shedding, load following, indeterminate recloser
operation, and utility/regulatory body disputes.
Grid Instability Upon completion of the power plant commissioning, within a few weeks it was observed that the
local power grid, operated by Electricaribe, was significantly more unstable than anticipated or
initially designed for based on the provided data. Power quality had degraded significantly since
the time period represented by the data provided. The instability manifested itself in most cases
8
as voltage sag, which was defined as a voltage level dropping more than 5% below nominal for
more than 5 cycles. In many cases, the sags could be quite severe, with voltage levels dropping
15-20% of nominal for several cycles.
The lower intensity sags were caused by general disturbances grid-wide. This grid covered
multiple regions of the country and served several major cities. The more severe sags were
caused by the starting of large induction motors from one of the other consumers on the same
feeder as the end user in this study. During one of these events, as the voltage dropped, the
current and reactive power from all generating sources increased.
In many cases, the voltage sags resulted in a reverse power condition as monitored at the utility
feeder entrance severe enough to trip the SG2 breaker (32R) and take the end user’s facility and
on-site generation off-line. Due to the high frequency of the voltage sag events (up to 6 times
daily), the end user was negatively impacted due to the obvious effects on lost production and
reduced revenue. An ABB DPU2000R protective relay had been installed in both SG1 and SG2
switchgear sections. Fault recorder data given in Table 1 demonstrates typical duration and
current levels observed during a reverse power condition. Nominal phase current at rated load
was approximately 130A.
SG2 Fault Recorder Data for Reverse Power (32R) Events Record
No. Date Time Duration
(cycles) Current
(A) 1 21-Jan-06 5:34:07 AM 6.24 22 3 21-Jan-06 7:58:32 AM 3.46 40 5 21-Jan-06 10:12:55 AM 5.46 300 7 22-Jan-06 7:47:34 AM 6.21 45 12 22-Jan-06 9:23:37 PM 2.96 20 14 23-Jan-06 12:51:51 PM 6.21 45 16 24-Jan-06 4:34:39 AM 2.46 30 18 24-Jan-06 8:21:52 AM 2.96 15
Average 4.50 cycles Max 6.24 cycles
Table 1. SG2 Reverse Power Condition Fault Recorder Data
It can be seen that the average voltage sag condition did not have a long duration—typically less
than 5 cycles.
9
A typical reverse power condition vector diagram and waveform trace is shown in Figure 4. The
condition is most apparent by the phase angle given between the phase voltage and phase
current. In this example, Vc is referenced at the zero angle. The reverse power torque angle
setting in the protective relay was 150˚ with a sector width of 180˚. Clearly the line phase
current Ic is nearly at the maximum reverse power angle and both the 32R and 67P functions
were triggered (green bars near the bottom center of the screen capture).
It is important to note that during each reverse power condition, no matter how limited, the SG2
breaker had to be tripped offline. This was required since there were no means available to
distinguish whether the condition had been caused by a temporary, minor voltage sag or a
complete loss of grid voltage due to an external fault.
Figure 4. Typical Observed Reverse Power Condition
Load Shedding & Load Following
A load shedding system was investigated such that, upon loss of the utility or other (32R)
tripping of the SG2 breaker, the end user’s facility could remain online—powered by the onsite
10
generators. However, loads available for shedding, two 500hp motor-driven compressors, were
so large that shedding them would have interrupted the facility operation entirely. It was not
feasible to trip the compressors offline. Shedding of smaller loads, while possible, was not
sufficient to reduce the load below the base load rating of the generators. This would have
caused the generators to trip offline due to an overload condition. It was concluded that an
effective load shedding scheme could not be implemented under the given conditions.
A load following scheme, however, was implemented that was designed to minimize the effect
of the grid’s voltage sags on the end user’s plant. It was observed that if a constant minimum
amount of import power was maintained (approximately 150kW) during parallel operation, the
instabilities on the grid had less effect on the on-site power generation, and reverse power
tripping was reduced. During the voltage sags, less real and reactive power was pulled out to the
grid from the on-site generators. The ATS control continuously metered utility import power as
well as the on-site generation power. Since the generators were normally deployed in a base
load, or kW control mode, they could not self-regulate based on the changing plant load at the
facility. The kW variation, or swing as it is often termed, was carried by the utility. However,
during times of low facility load, such as typically occurred on weekends, the amount of
imported load could fall well below the 150kW threshold required to minimize 32R tripping
during voltage sags. The load following control monitored both generator and utility load.
During times of low load, a signal was sent from the ATS site controller to the generator controls
in order to lower the kW control setpoint on the individual units. This allowed for a constant
import level of 150kW, and reduced reverse power tripping for all but the more severe voltage
sag conditions. In effect, during low plant load conditions, the generators became the variable,
or swing source.
Recloser Issues
Further complicating matters, the utility source coming into the customer’s plant was fed from an
overcurrent recloser (OCR). Due to the novelty of on-site and distributed generation in this part
of the country, the local utility was not prepared to effectively address recloser operation as
required in an on-site or distributed generation scenario. The recloser was configured and
designed around a single source of generation and was set to clear the feeder (trip) in the event of
11
a fault and to automatically re-close 500mS later. This was cause for great concern as the
recloser would operate regardless of the presence of another generation source on its downstream
line, without any attempt to synchronize the two existing sources. This could result in serious
equipment damage, or injury and death to support personnel. The inability to lockout the
recloser after it tripped to prevent a reclose operation into the live, onsite generation, posed the
largest challenge to the ability to provide uninterrupted power to the end user. Since it was
impossible to distinguish a 32R reverse power condition as being caused by the OCR tripping
offline or a simple grid voltage sag, the on-site generation plant had to be tripped offline in every
instance of detected reverse power—causing the end user’s facility to undergo an open transition
to the utility source and resulting in a momentary interruption. While not of great inconvenience
to the facility, the high frequency of voltage sags and full load SG2 trips did cause significant
concern for the health and integrity of the generators and their accompanying switchgear.
Utility/Regulatory Body Issues
Two solutions to the problem were proposed by Maven Power to the local utility representatives.
The first was an operational procedure. As part of the original scope of work, Maven Power
performed the integration of a SCADA (Supervisory Control and Data Acquisition) system
which provided for remote monitoring and control of the on-site power generation by the local
utility. Power parameters such as kW, kVAR, kVA, Hz, and power factor were provided
allowing Electricaribe the ability to monitor the remote generation facility. Also included in the
SCADA system was the ability to remotely trip the SG2 utility feeder breaker and to provide
feedback information on the breaker position. The proposed solution required Electricaribe to
transmit a trip signal to SG2 any time a fault occurred on the OCR feeder, and to not allow the
OCR to re-close until the breaker position indication was that of an open SG2 breaker
(successful SG2 trip command). This procedure was designed to prevent both an islanded
condition as well as a re-close into a live buss. This solution was problematic in that the remote
trip signal was transmitted using fiber optic cable over a distance of several miles. While the
communications protocol and the media were robust, the customer’s transmitting and receiving
RTU equipment was prone to interference and temporary communications interruptions occurred
on a frequent basis. In the event communications were down at any point during the recloser
12
period (500mS), the inability of the utility to block the recloser operation would place the system
in great peril.
The second solution was to implement a synch check (25) or undervoltage (27) monitoring
system at the utility’s substation where the OCR was located. This system would monitor the
line and load side of the OCR for a voltage source. Following an OCR trip, and in the absence of
a source on the load side, a re-close operation would be permitted. If both line and load sources
were present (islanded condition on the load side), a re-close operation would be prevented. For
multiple phase monitoring, these solutions required the installation of a minimum of two (2)
15kV PTs in the case of the undervoltage monitoring, and four (4) PTs in the case of a
synchronization check.
Both proposed solutions were initially rejected. The first solution was rejected outright with the
utility asserting that with the communication system’s unreliability, this could result in lengthy
time periods in order to verify the successful tripping of the SG2 which isolated the plant. This
would have an adverse impact on the other numerous power consumers connected to the
common general use feeder. The second proposal was countered with a variation on how the
reverse power relaying was to be performed. The original reverse power function used was 32R,
or an instantaneous reverse power. This had the effect of tripping the SG2 breaker without
regard to the intensity or duration of the reverse power condition. Electricaribe suggested that
the 67P function be used instead—directional-phase time-overcurrent. Maven Power had indeed
analyzed the appropriateness of this function early in the design phase of the project. This
function could be set to allow a given intensity and duration of reverse power to flow before
tripping the SG2 breaker. The basic principle is that the 67P curve settings (pickup & time dial)
are such that some reverse current is permitted which allows SG2 to remain online and both
sources in parallel during the voltage sag transients observed on the grid, but only for a duration
less than that of the OCR’s re-close time setting. If the observed reverse power condition were
caused by a recloser trip instead of a voltage sag, this would ensure SG2 tripped offline before
the re-close operation occurred. A sample of the timing scheme is given in Figure 5:
13
Typical Time Dynamics for Voltage Sags, Reverse Power and Recloser Functions at SG2 (Barranquilla)
-150%
-100%
-50%
0%
50%
100%
150%
-42 m
S
-21 m
S
0 mS
21 m
S
42 m
S
63 m
S
83 m
S
104
mS
125
mS
146
mS
167
mS
188
mS
208
mS
229
mS
250
mS
271
mS
292
mS
313
mS
333
mS
354
mS
375
mS
396
mS
417
mS
438
mS
458
mS
479
mS
500
mS
521
mS
542
mS
563
mS
583
mS
604
mS
625
mS
646
mS
667
mS
688
mS
Vphase
Protection "Buffer Zone" for Synch Check (25) or Undervoltage (27) Functions
67P Trip Command from SG2Protective Relay (Time Delay = 200mS)
Reclose Time forOCR (79)-Electricaribe500mS.
(Voltage sag)
Start of Event (67P Pickup)
Figure 5. Recloser & Reverse Power Timing.
Maven rejected the idea of the sole use of the 67P function without a 25 or 27 function on the
OCR. For such a critical application, it was not deemed prudent to rely solely on a timing
scheme and the integrity of one OCR control which was beyond Maven’s operational or
technical control.
At present, negotiations are ongoing to implement the synch check or undervoltage monitoring
systems in the utility’s recloser.
Conclusion On-site power and distributed generation must balance the needs of the end user, the power
generator, and the local grid. In a market new to distributed generation, regulatory bodies and
utilities may not be prepared or empowered to expeditiously make system modifications to
accommodate new power plants. Available tools such as protective relaying, system