data systems consulting mfg division charley.c/jeff.y/ ganda project plan
TRANSCRIPT
Data Systems ConsultingMFG DivisionCharley.C/Jeff.Y/
Ganda Project Plan
Executive Summary
1. Project scope2. Detail workplan3. Project Team4. TIPTOP ERP connection interface with some
hardware devices5. Clarification about VPS6. EasyFlow, What Digiwin proposal (need to
confirm and discussion for more details)7. BI, What Digiwin proposal (need to confirm
and discussion for more details)8. Finalized the reminding items in the file of
"things to be confirm with Digiwin.docx"
Discussion SummaryTopic Status• Project Scope 73% initial ganda’s requirement met to
Tiptop and 18% need customization
• Work plan Agreed project divided on 2 phase -Phase 1 (6 month) for core business modules-Phase 2 (Phase 1 + 6 mth) for supporting modules.
• Project team~ Digiwin will provide dedicated Project Team (Consultant) • ERP comm. Interface Digiwin proposed some option to Ganda
• VPS~ OK with certain condition• B2B/BI/Easyflow OK, Digiwin accepted• Draft contract Sent to Richard, Alex & Toto for review• Payment term Discuss later on 26 April 2013• After sales service Need to be finalized with CFC
Total 214 of initial Ganda’s requirements
TIPTOP solution match % for Ganda
TIPTOPStandard
Match
158
73%
Need customization
38
18%
Not clear
1Not in scope
6No function
10
9%
Key Principles for Project
Strict Scope Control is required in order to ensure that:1. Initial Ganda’s requirements and TIPTOP modules Standard is
adhered to2. Schedule is met
Therefore:• Allow Changes for statutory or critical business requirements, only
• Any enhancements on the system can only be built AFTER go-live
Management & End users must be aware of this approach and must have the realistic expectations about
what the system will provide
Sales
Purchasing
Inventory
BOM
Distribution
A/P
A/R
G/LConsolidation Financial
reportInter-Company Trading
Fixed Asset
Tax Declaration
Cash/Loan/Investment
BOM
Production
MRP
Cost Accounting
Project Mgt.
Budget Mgt.
Leasing Mgt.
Equip. Mgt.
Quality. Mgt.
System and Parameters System Mgt.
Digiwin Standard Modules suggests in Ganda Group
B2B
Easyflow GP
BI
HRM
Cross-Data transfer
Customization Modules in Ganda Project
Item Estimate Man hours Phase
Manufacturing of Production Daily reports KP+ CFC 500 Phase 1
Vehicle Management ( For Transportation Cost Management)
Base on Ganda 300 Phase 1
HRM report ID 200/ VN 200 Phase 1
Automatic PLC Integration Base on CFC400 Phase 1
Tax reporting to Local Government Free of charge Phase 1
Packing Management (Truck & Belt Scale System)Base on CFC 200 Phase 1
CMMS System(Customization in Equipment Module)
Base on CFC50 Phase 1
Electric Power System Base on CFC100 Phase 2
Telephone Management Base on CFC150 Phase 2
Library Management Base on CFC150 Phase 2
Canteen Meal Management Base on CFC150 Phase 2
GPS Integration 300 Phase 2
TIM(TIPTOP Implement Methodology) &
Project Organization
TIM( TIPTOP Implementation Methodology )
Project Planning Implementing TIPTOP Goes Live Project Closing
< Project Life Cycle >
• Goals• Scope
• Organization• Schedule
• Survey & Diagnosis• Application Training
• S.O.P. Modeling• Gap Analysis & Solution
Design• Data Migration & Input• Simulation & Fine-
tuning• Balance Checked in
• Existing System Stops• On-site Problem-
Solving
• Achievements Check Meeting
• Documentation of Project
• Take-over of TSC• All case profile in
CRM system
Group Company - Project Structure
Chairman
Mr. Tony
Ganda IDN Project Leader
Toto
Chinfon VN Project Leader
Alex
Steering Committe
Mr. RichardMr AlexMr GaryMs MariaMr Toto
Ganda IDN Project LeaderToto – Ganda Group Indonesia
TBD – DIGIWIN PROJECT MANAGER
Accounting & FinanceProcess Owner: Ms Maria
1..........................(Staff) 2...........................
Human ResourcesProcess Owner: Mr Wahyu
1. ...............(Staff)2.................
Sales & DistributionProcess Owner: Ms. Jacqueline
Purchasing & InventoryProcess Owner: Mr Gary
Manufacturing & CMMSProcess Owner: ......
Technical Support
1. Sunu Waskita (leader)2. Appilion
3..Digiwin System Engineer (1 person)
Advance FeaturesB2B, Websales, etc
Business InteligentMgt Report, KPI, etc
Digiwin Consultant
1.Finance & Acc = Consutant 1 (1 person)2.Mfg and Sales & Dist = Consultant 2 (1 person)
3.HRM,= consultant 3 (1 person)4.BI = Consultan 4 (1 person)
5.Easyflow = consultant 5 (1 person)6.System Analysis / Trainer = Consultant 6 ( 2 person)
Note: Not include programmer who should working on Taiwan)
Group Leader 1
1. Vacant
Group Leader 2
1. Vacant
Group Leader 3
1. Vacant
1. ...............(Staff)2.................
1. ...............(Staff)2.................
1. ...............(Staff)2.................
Fleet ManagementProcess Owner: ......
1. ...............(Staff)2.................
Project ManagementProcess Owner: Mr Anang
1. ...............(Staff)2.................
Advance FeaturesPLC/Field instrument integration
Team (Key User)1.. ............ 2. ..........3. ............. 4. ..........
Team (Key User)1.. ............ 2. ..........3. ............. 4. ..........
Team (Key User)1.. ............ 2. ..........3. ............. 4. ..........
Team (Key User)1.. ............ 2. ..........3. ............. 4. ..........
Team (Key User)1.. ............ 2. ..........3. ............. 4. ..........
Team (Key User)1.. ............ 2. ..........3. ............. 4. ..........
Team (Key User)1.. ............ 2. ..........3. ............. 4. ..........
SCOPE:WHI, GG, AASTAR, CG,
NSD, ANP, SAG, MM
SCOPE:GG, AASTAR, CG, NSD,
ANP, SAG, MM
SCOPE:GG, AASTAR, CG, NSD,
ANP, SAG, MM
SCOPE:GG, AASTAR, CG, NSD,
ANP, SAG, MM
SCOPE:CG, SAG, MM
SCOPE:ANP
SCOPE:GG, CG
Support Function
1. Change & Communication : Toto2.Project Supporting: Hary
Chinfon VN Project Leader
T-038 Mr. Alex Hsu TBD – DIGIWIN PROJECT MANAGER
Digiwin Consultant
1.Finance & Acc = Consutant 1 (1 person)2.Mfg and Sales & Dist = Consultant 2 (1 person)
3.HRM,= consultant 3 (1 person)4.BI = Consultan 4 (1 person)
5.Easyflow = consultant 5 (1 person)6.System Analysis / Trainer = Consultant 6 ( 2 person)
Note: Not include programmer who should working on Taiwan)
Finance & Accounting
1.................(Dept. Lead)2..................(Key User)
Team (Key User)
1. GL ............ 2. A/P..........3. A/R............. 4. Cash.......
5. .Costing...... 6.Fixed Asset
G/A Warehouse / Canteen
1.................(Dept. Lead)2.................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
Sales & Distribution
1.................(Dept. Lead)2.................(Key User)
Team (Key User)
1.. HP ............ 2. HN ..........
3. HM .............4. DN .............5. .HPGP.........
Purchasing / Export
1.................(Dept. Lead)2.................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
W/H Spare Parts & Inventory
1.................(Dept. Lead)2.................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
Production / ManufacturingT.K.P & HPGP
1.................(Group leader)2..................(Consultant)
Team (Key User)
1..Quarry2. Raw Mill
3. Kiln .4. Cement Mill
5. CCR6.Packing
7.F/G8.Elec. 9.QC
Maintenance CMMS
1.................(Dept. Lead)2..................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
Logistic & Shipping
1.................(Dept. Lead)2..................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
Finished Goods
1.................(Dept. Lead)2.................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
Project Management
1.................(Dept. Lead)2.................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
HR Management
1.................(Dept. Lead)2..................(Key User)
Team (Key User)
1.. ............ 2. ..........3. ............. 4. ..........
Technical Support
1.V1121 Le Quoc Tuan2.V1422 Nguyen Thu Hong
3..Digiwin System Engineer (1 person)
Support Function
1. Change & Communication : Alex Hsu2.Project Supporting: Richard
Advance FeaturesB2B, Websales, etc
Business InteligentMgt Report, KPI, etc
Group Leader ( Administration )
1. Vacant
Group Leader ( Marketing )
1. Vacant
Group Leader ( Production )
1. Vacant Advance FeaturesPLC/Field instrument integration
Role Responsibility Qualifications Remark
Project Leader
• Deliver the specified project deliverables on time in good quality and in accordance with the budget
• Achieve milestones on time• Report on project progress to the steering committee• Identified of potential bottleneck and initiate to propose the solution• Coordinate & Assign tasks to project members• Keep in touch with Consultant to ensure successfully the project and
for knowledge transfer
• Knowledge of business processes • The ability to work effectively with all levels within Organization• Project Management Expertise• Have good understanding of project scope & constraint. • Time management skills and multi-tasking capabilities • Good on verbal and written communication skills • The ability to make timely decisions • Strong organizational skills • Good leadership and coaching skills
Full time
IT Technical Support
• Providing IT infrastructure for implement ERP System• To setup system requirement for ERP System• Support user to operate this system
• Have Good skill & experience in Databases, networking, and operating system
• Have good understanding on the current IT System• Experience and knowledge in current system environment.
Part time but ready if required
Support Function
• To assist project team on Project administration, training, business process development and prepare new infrastructure (if needed)
• To coordinate change program impacted of ERP impl. system• Project Administration task• Setup and organize documentation control system and records
• Good knowledge of the company’s organizational structure and business processes
• The ability to work effectively with all members of the organization ranging from executive members to front line / users.
Full Time
Group Leader
• Leader on development defined modules• To manage and coordinate project communication, training,
socialization and prepare new infrastructure (if needed)• Working together with consultant to determine business process
flow that needed to ERP system requirement with consultation to process owner.
• Development of business process documentation (incl design standard form and report) with consultation to process owner.
• Conduct testing, data collection, data validate and data migration for new system configuration.
• To drive, coach and facilitate the implementation of new system• Issues resolution• Working together with key user to Identify of end user, training
requirements at their particular site.
• Experience in functional business process, • In-depth knowledge of the company’s business processes & best
practices, • Strong analytical skills and problem solving skills• Strong communication skills and coaching skills• Excellence team player skills, with strong verbal and written
communication skills and coaching skills, • Experience to design and developing System & Procedures.• Experience in delivery training
Full time
Key User • Co-ordinate between Project and End User• Represent End Users• Support project team by share data & information• Validate data & Process• Build knowledge of what new system will do• Assist on end user training• “Owner” of new system• Lead in managing the change in their unit areas
• An in-depth knowledge of the business unit functionality business and requirements in their business process area(s),
• Strong analytical skills. • Active and willing• Able to use own initiative• Good at interpersonal communication
Part Time but ready on demand with advance notification
Project Team Responsibilities
DSC Service Team
Project Manager
Account ConsultantID & VN team
Account ServicesID & VN team
System Engineer
[Consultant Main Tasks]
1. Discuss & confirm System SOP
2. System Education
3. Implement System according to TIM
[System Engineer main tasks]
1. Installation TIPTOP system 2. Assist normal operational maintenance
3. Abnormal recovery
[Service Team main tasks] 1. Assist consultant draw system analysis 2. Coordinate Programming pool & test
3. Customer service
Programmer
[PM qualifications] : 1. Project planning 2. Definition, clearance, & Statement of main project issues
3. Allocate DSC service team resources
4. Main Communicator to client team 5. System progress & risk management
6. monthly report
Device IntegrationFor Ganda Group
Charley Cheng
DigiWin Corporation
2013/04/19
Current
New by Database
Truck Weight Scale
Finger Print
Door Lock
And so on…
Data Collation Software
SQLDatabase
Data Collation Software
Data Collation Software
Data Collation Software
TIPTOP
OracleDatabase
Reports
Statistic
Monitor
Request on demandOr periodically
Feedback dataSave Record
Output
Compute
Query
Device Integration Architecture for TIPTOP (DB solution)
Text File ExchangeTruck Weight
Scale
Finger Print
Door Lock
And so on…
Data Collation Software
Text File Folder
Data Collation Software
Data Collation Software
Data Collation Software
TIPTOP
OracleDatabase
Reports
Statistic
Monitor
Obtain DataPeriodically
Save Records
Output
Compute
Query
Device Integration Architecture for TIPTOP (Text File Solution)
TransferPrograms
Requestby Demand
Sharing FoldersTo ERP
Hardware InfrastructureIndonesia & Vietnam
Hardware Suggestion~ Indonesia
Client UserService Ethernet
Symantec Backup Exec Agent For VM Host / SQL/ Oracle
4Gb or 8Gb Fibre Channel
Giga intranet
Redundant Fiber Channel
Phase 2Backup Guard
Service XP or above
PC
Giga Switch For VMNetwork
- Guard service - VMWare vCenter Server
- Symantec Backup Server
Back up SVR
NAS Appliance( 2TB HDDx6 RAID5)
HP DL380 Gen8 2P12C / 64GB
300GB SAS 10K x28Gb Single HBA x 4
VMWare vSphere 5 ESP
HP DL380 Gen8 2P12C / 64GB
300GB SAS 10K x28Gb Single HBA x 4
VMWare vSphere 5 ESP
VMWare Internal data Transfer
HP DL380 Gen8 2P12C / 64GB
300GB SAS 10K x28Gb Single HBA x 4
VMWare vSphere 5 ESP
IBM DS3500 Storage2G Cache/Per-Controller
HD: 600GB 6Gb SAS 15K*12
IBM DS3500 Storage 2G Cache/Per-Controller
HD: 600GB 6Gb SAS 15K*12
HRM8C/12G (Win+MSSQL)
BI + Auditor8C/12G(Win+MSSQL)
EFGP + ESS8C / 12G(Win+MSSQL)
TIPTOP DB8C / 16G(RHEL+Oracle)
Portal4C/8G(Win+MSSQL)
Crystal Reports4C/8G (Win)
TIPTOP AP8C / 16G(RHEL)
TIPTOP B2B8C / 12G(RHEL)
Hardware all Local purchase QTY
Host for virtual machine
HP DL380 Gen8 : CPU : E5-2620 x 2 、 RAM : 64G 、 HDD : 300G x 2 、 8Gb Dual-Port Fiber Card x 2 、 1Gb Giga Port x 4
3
Storage IBM DS3500 Storage (Dual-Controller) 、 SFP x 8 、 2G Cache/Per-Controller 、 HD: 600GB 6Gb SAS 15K * 12 、 FC Cable x 8
2
Backup Server HP X1430 NAS Appliance G2 WSS NAS(8TB)(Builtin Windows 2012) 1
Guard Server HP ThinClient T610 for P-Cloud (Builtin Windows) 1
Ethernet Switch HP V1910-24G Switch 1
Software partial local purchase QTY
Operation System
RedHat Enterprise Linux for TIPTOP AP 、 TIPTOP DB 、 TIPTOP B2B 2
Windows Server 2008 MOLP for Crystal Report 、 EFGP+ESS 、 Portal 、 BI+Auditor 、 HRMLocal purchase
5
Windows Server CALLocal purchase 100
Database
Oracle DB Standard Ed. For 2-processor for TIPTOP ERP 1
Microsoft SQL Server Standard Ed. MOLP,Device Cal for EFGP+ESS 、 Portal 、 BI+Auditor 、 HRMLocal purchase
4
Microsoft SQL server CALLocal purchase 100
Virtualization VMWare vSphere 5.1 Essential Plus 1
Backup SYMC BACKUP EXEC 2012 V-RAY EDITION WIN 2 TO 6 CORES PER CPU BNDL STD LIC EXPRESS BAND S ESSENTIAL 12 MONTHS 6
SPEC List - Indonesia
Hardware Suggestion~ Vietnam
Client UserService Ethernet
Symantec Backup Exec Agent For VM Host / SQL/ Oracle
4Gb or 8Gb Fibre Channel
Giga intranet
Redundant Fiber Channel
Phase 2Backup Guard
Service XP or above
PC
Giga Switch For VMNetwork
- Guard service - VMWare vCenter Server
- Symantec Backup Server
Back up SVR
NAS Appliance( 2TB HDDx6 RAID5)
HP DL380 Gen8 2P12C / 64GB
300GB SAS 10K x28Gb Single HBA x 4
VMWare vSphere 5 ESP
HP DL380 Gen8 2P12C / 64GB
300GB SAS 10K x28Gb Single HBA x 4
VMWare vSphere 5 ESP
VMWare Internal Data Transfer
HP DL380 Gen8 2P12C / 64GB
300GB SAS 10K x28Gb Single HBA x 4
VMWare vSphere 5 ESP
IBM DS3500 Storage2G Cache/Per-Controller
HD: 600GB 6Gb SAS 15K*12
IBM DS3500 Storage2G Cache/Per-Controller
HD: 600GB 6Gb SAS 15K*12
HRM8C/12G (Win+MSSQL)
HP DL380 Gen8 2P12C / 64GB
300GB SAS 15K x5Raid 5+HSP
VMWare vSphere 5 ES
Existing System
BI + Auditor8C/12G(Win+MSSQL)
EFGP + ESS8C / 12G(Win+MSSQL)
TIPTOP DB8C / 16G(RHEL+Oracle)
Portal4C/8G(Win+MSSQL)
Crystal Reports4C/8G (Win)
TIPTOP AP8C / 16G(RHEL)
TIPTOP B2B8C / 12G(RHEL)
Hardware all Local purchase QTY
Host for Virtual Machine
HP DL380 Gen8 : CPU : E5-2620 x 2 、 RAM : 64G 、 HDD : 300G x 2 、 8Gb Dual-Port Fiber Card x 2 、 1Gb Giga Port x 4
3
Host For Existing System HP DL380 Gen8 : CPU : E5-2620 x 2 、 RAM : 64G 、 HDD : 300G x 5 、 1Gb Giga Port x 4 1
Storage IBM DS3500 Storage (Dual-Controller) 、 SFP x 8 、 2G Cache/Per-Controller 、 HD: 600GB 6Gb SAS 15K * 12 、 FC Cable x 8
2
Backup Server HP X1430 NAS Appliance G2 WSS NAS(8TB)(Builtin windows 2012) 1
Guard Server HP ThinClient T610 for P-Cloud (Builtin Windows) 1
Ethernet Switch HP V1910-24G Switch 1
SPEC List - Vietnam
Software partial local purchase QTY
Operation System
RedHat Enterprise Linux for TIPTOP AP 、 TIPTOP DB 、 TIPTOP B2B 2
Windows Server 2008 MOLP for Crystal Report 、 EFGP+ESS 、 Portal 、 BI+Auditor 、 HRMLocal purchase
5
Windows Server CALLocal purchase 100
Database
Oracle DB Standard Ed. For 2-processor for TIPTOP ERP 1
Microsoft SQL Server Standard Ed. MOLP,Device Cal for EFGP+ESS 、 Portal 、 BI+Auditor 、 HRMLocal purchase
4
Microsoft SQL server CALLocal purchase 100
Virtualization VMWare vSphere 5.1 Essential Plus 1
BackupSYMC BACKUP EXEC 2012 V-RAY EDITION WIN 2 TO 6 CORES PER CPU BNDL STD LIC EXPRESS BAND S ESSENTIAL 12 MONTHS 6
B2B&BI
� Customer can make the sales order / lading bill via web
� Customer can make the cement issue schedule via web
� Customer can know the inventory status via web
� Carrier can know the transport status via web.
• Posting enquiries and sales orders through web-sales (web-sales)
Ganda initial requirement of TIPTOP B2B
TIPTOP B2B
V-Point BIImplementation strategy, improve performance management
Quantization execution strategy, Easy to use, analysis, adjustments
View the target reached, performance indicators management
Ex: Operating margin, current ratio, accounts receivable turnover days,
CCC(Cash conversion cycle), liability ratio, Current ratio, amount of inventory,
turnover per capita, Orders shipping days, revenue growth rate, vaerage customer
price.
26
27
KPI Performance Management
28
Spare Parts-Safety inventory Of Alert Analysis
29
Inventory Trend Analysis
Sales Intelligence with KPI template
Financial Intelligence with KPI template
TIPTOP exception management
Business Object platform
BO Xcelsius Dashboard developer
32
TIPTOP Exception Management
流程追蹤
33
Flow Design Flow Drawing
Flow Progressing
Performance Analysis
Document Tracking
Document Approve
Easyflow~ The Business Process Management
Approval on line
Process Statistic analysis to achieve optimal Process
Performance Loading Cost
~Loading~Process Starts quantityProcess finish quantity
Process trendsTo do list quantityProcess activities
allocation
~Cost~Process dealing cost
AVG Dealing costAVG Dealing cost by
activitiesAVG Dealing cost by activities per User
~Efficiency~AVG process time
AVG process time trend AVG process time by
activities AVG process time per User
35
精進管理
實現投資效益
Pre -Sale
Demand clarifying &
Solution Planning
Valued Sales
Maintenances
Post-enhance
ROI improving
Deploying
Implement
Achieve Project Goal
Demand Satisfying Demand LeadingTotal Services
TIPTOP Service Center/ TIPTOP Programming Center / TIPTOP R&D /
TIPTOP E-Learning/ TIPTOP ERP II e-Service
Total Services Oriented
36
About the after service
Telephone, fax inquiry service; Remote terminal login service; Program debugging service; Elimination of system malfunction arising out of normal usage; and
Program version update: “minor patches” as termed in the industry.
Extra requirement for customization inquiry and SA documents
Technical courses online via video conference(after go-live)
DB diagnosis , system performance advisory
E-service website (in Chinese) for FAQ, Knowledge base for user
E-Learning in (Chinese)
• The System analyst will be fulltime contact window for Ganda after system go-live
• If emergency problem happens, such as system crash, DB crash, power shot down, emergency recovery…etc, the contact window will inform the engineer team to remote to service. AS long as the telecom company network works.
• The All system modules for ERP II just find one contact window.
• 80%questions can be solved within 24 hours, 90% can be solved in 48 hours, and 95% can be solved in 72 hours.
Redundant infrastructure provided in each of Ganda & CFC at local site. And we treat Ganda & CFC as other’s mutual backup & support system . Once the emergency situation happened, Ganda can switch the system via Virtualize Machine in local side. The worst case is JKT machine room is dead, Ganda can switch the system temporary to CFC if the internet is linking and Digiwin can response asap.