damodar valley corporation - rites · connection with construction of railway infrastructure at...
TRANSCRIPT
1 Signature of the tenderer
under seal of the firm
DAMODAR VALLEY CORPORATION
NOTICE INVITING TENDER NO: 91/OT/DVC-RTPS/Civil & P. Way/PKG-IV/2014 Dated 31.01.2014
Earthwork in formation, Construction of bridges, blanketing , P.Way Linking Works including supply of P. Way fittings & track Ballast in connection with construction of railway infrastructure at BERO Fly over line from Km 2/310 to Km 3/688 & JOC Fly over line from Km 2/052 to Km 3/500 to serve Raghunathpur Thermal Power Station ( RTPS) of DVC at Raghunathpur, Dist - Puralia, West Bengal. ( Pkg - IV).
PART – 2
FINANCIAL BID
CONTENTS
Schedule (Bill) of Quantities
(Percentage rate tender)
Issued to (Name of Tenderer):________________________________________ Address of tenderer:_________________________________________________ Signature of officer issuing the documents___________________ Designation _______________________________ Date of Issue___________________
(A Govt. of India Enterprise)
Regional Project Office, KOLKATA 56 C R Avenue, 2nd floor, Kolkata – 700 012
e.mail : [email protected] Phone No: (033) 22367118/7146/7162/7143(Fax)
2 Signature of the tenderer
under seal of the firm
FINANCIAL BID
Earthwork in formation, Construction of bridges, blanketing , P.Way Linking Works including supply of P.Way fittings & track Ballast in connection with construction of railway infrastructure at BERO Fly over line from Km 2/310 to Km 3/688 & JOC Fly over line from Km 2/052 to Km 3/500 to serve Raghunathpur Thermal Power Station ( RTPS) of DVC at Raghunathpur, Dist - Puralia, West Bengal. ( Pkg - IV).
Part – 2
SCHEDULE (BILL OF QUANTITIES)
POINTS TO BE NOTED WHILE QUOTING RATES Where Tender has been invited on Percentage Rate basis, percentages on the Estimated Cost (whether above or below) are to be quoted for Sch –1 to Sch - 6
3 Signature of the tenderer
under seal of the firm
PART 2 SCHEDULE (BILL) OF QUANTITIES
(PERCENTAGE RATE TENDER) ABSTRACT OF BID
(PERCENTAGE TO BE QUOTED BY THE BIDDER) SCHEDULE-A DESCRIPTION ESTIMATED COST (RUPESS)
1 Earthwork in Railway/Road formation
Rs. 31,25,16,382.00
2 Bridge work. Rs. 14,37,11,031.00
3 Structural steel work at Super Structure
Rs. 62,80,368.00
4 Track Linking works Rs 1,66,83,860.00
5 Supply of P.Way fittings Rs 35,55,086.00
6 Any other unforeseen item Rs 55,55,000.00
Total Estimated cost of Schedule – 1 to Schedule – 6
Rs. 48,83,01,727.00 (Rupees forty eight crores eighty three lakhs one
thousand seven hundred twenty seven only) PERCENTAGE ABOVE (+) OR BELOW (-) ON SCH –1 to SCH -6 AS QUOTED
PERCENTAGE IN FIGURES
* (+) or (-)
PERCENTAGE IN WORDS
* (PLUS) or (MINUS)
Total Quoted cost of Schedules (1) to (6) (Rupees)
Amount in figure (Rupees)
Total Quoted cost of Schedules (1) to (6) ( Rupees)
Amount in word (Rupees)
Rebate if any
Percentage in figure
Percentage in word
Net Quoted Cost of Schedule – 1 to Schedule – 3 ( Rupees)
AMOUNT IN FIGURES (RUPEES)
AMOUNT IN WORDS
(RUPEES)
* Strike out which is not applicable i) SIGNATURE OF AUTHORISED
SIGNATORY OF TENDERER ii) NAME OF SIGNATORY iii) NAME AND SEAL OF TENDERER iv) DATE v) PLACE
4 Signature of the tenderer
under seal of the firm
Schedule (Bill) of Quantities
NAME OF WORK: Earthwork in formation, Construction of bridges, blanketing , P. Way Linking Works including supply of P.Way fittings & track Ballast in connection with construction of railway infrastructure at
BERO Fly over line from Km 2/310 to Km 3/688 & JOC Fly over line from Km 2/052 to Km 3/500 to serve
Raghunathpur Thermal Power Station ( RTPS) of DVC at Raghunathpur, Dist - Puralia, West Bengal. ( Pkg - IV).
Schedule – 1 (Earthwork in railway/Road formation) SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
1 Feeling of trees of girth ( measured at a height of 1m above ground level ) including
lead & stacking of materials within 100m in addition to stumps are grubbed up.
each 50 226.82 11341.00
a) Girth over 30cm and up to 60cm.
2 Earthwork in filling in embankment, guide
bunds, around buried type abutment ,
bridge gap. Trolley refuges, rain bunds if provided , platforms etc. with earth
excavated entirely by the contractor at his own cost as per RDSO's latest guidelines &
specification & special condition of contract including all taxes , royalty, lifts , ascents
descents, crossing of nallah or any other
obstructions . The rates shall include all dressing of bank to final profile ,
demarkation and setting out of profile, site clearance , removing of shrubs roots of
vegetation growth , heavy grass, all
handling /re -handling, taxes , octroi and royalty etc as a complete job.Cut trees shall
be the property of DVC and to be deposited in the DVC/RITES Store.
Cum 1600000 169.40 271040000.00
3 Extra for mechanical compaction of earth
&blanketing material filled in embankment with contractor's roller of suitable capacity,
type and size to achieve specified density as per specification , testing as per IS
codes incl. cost of water, T&P consumable
material and all labour as a complete job. The work is to be executed as per latest
edition of " Guidelines of Earth Work in Railway Projects" issued by RDSO, Lucknow
Cum 1615000 15.55 25113250.00
4 Supplying & spreading of Blanketing
material as per RDSO specification over the embankment as per approved drawing .
The rate shall include cost of material, all lead, lift ascent, descent, testing, supply of
labour , royalty/taxes, octroi as a complete
job. note: Compaction of blanketing will paid by relevant item.
Cum 15000 260.07 3901050.00
5 Signature of the tenderer
under seal of the firm
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
5 Turfing //Planting including all lead and lift ,
and watering as required until properly rooted , with. Note: Initially payment of
only 40% will be made. Balance 60% will be paid only after 3 months of maintenance
period.
Sqm 131115 55.04 7216569.60
a) Turfing with sods,10cm thick and 20 cm square closely laid.
6 Supplying & filling sand in low area/pond as
directed by Engineer - in -Charge including watering, ramming consolidated and
dressing complete.
cum 5000 427.99 2139950.00
Sub total of Schedule – 1 309422160.60
Add: 1% labour welfare cess 3094221.61
Total amount of Schedule – 1 312516382.21
Say Rs. 31,25,16,382.00
Add: 1% labour
welfare cess
3094221.61
Schedule – 2 (Bridge Work)
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
1 Earth work in excavation for foundation and floor of bridges, retaining wall etc, including
setting out, dressing of sides, ramming of
bottom , getting out the excavation material , back filling in layers with
approved material and consolidation of the layer by ramming & watering etc including
all lift, deposal of surplus earth up to a lead
of 300m , all types of shoring and strutting with all labour & material complete as per
drawing & technical specification as directed by Engineer -in - Charge
a) all kind of soils Cum 8768 309.31 2712030.08
b) ordinary/Soft rock Cum 1879 289.60 544158.40
c) Hard rock(blasting prohibited) Cum 1879 616.88 1159117.52
2 Supplying , Spreading and filling coarse
sand(no cohesive materials to be used)of a approved quality including watering and
ramming in foundation, plinth, behind the
abutment , wing wall, retaining wall in layers not exceeding 150mm thick including
its compaction as per direction of Engineer - in - Charge. The rate includes all lead , lift
, ascent, descent, crossing of railway lines
etc. complete with contractor's labour , materials , tools and plant.
Cum 2074 694.89 1441201.86
6 Signature of the tenderer
under seal of the firm
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
3 Providing and laying in position machine
mixed, machine vibrated and and machine
batched design mix mass cement concrete M25 grade ( cast -in - situ)using 20mm
graded crushed stone aggregate and coarse sand of approved quality excluding the
cost of centering , shuttering and finishing complete as per drawing &
technical Specification as directed by
Engineer - in - Charge including the cost of admixture as per IS 9103 up to GL (
Ground level) Payment of reinforcement if required shall be paid as per
relevant item.
Cum 1000 5242.15 5242150.00
4 Cement concrete M-35(controlled) with or without reinforcement as per IS: 456-
2000 with 20mm and down size graded
crushed stone aggregates, coarse sand but excluding the cost of shuttering
including cost of concrete Admixtures (Super- Plasticiser, - Sikament/ Plastiment,
or equivalent as per trial & manufacturer's recommendations) levelling, finishing as per
drawing, mechanical mixing, vibrating by
mechanical or electrical vibrators curing etc., complete with all labour and materials,
including all lead and lift and tools and plants.
Cum 8000 5907.95 47263600.00
The rate includes cost of cement, all
materials, labour charges, etc. with contractor's accessories below & above GL
as directed by the Engineer-in-charge
Supplying and fixing of steel reinforcement are not included in this
item, which will be paid as per relevant item. NOTE: - The above rate
shall be inclusive of submission & getting
approval of design mix & weigh batching
5 Centering and Shuttering including Strutting, propping etc. & removal of form
for:
a) RCC raft foundation Sqm 2425 141.68 343574.00
b) Abutment, pier,wing wall , return wall & through wall, drop wall
Sqm 11432.00 233.97 2674745.04
c) Approach Slab, Deck Slab, Ballast wall etc.
Sqm 1606 233.97 375755.82
6 Supplying reinforcement for RCC work
including straightening, cutting, bending,
placing in position and binding in complete
a) Thermo - Mechanically Treated Bars MT 1100 62250.00 68475000.00
7 Signature of the tenderer
under seal of the firm
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
7 Providing weep holes by making suitable
openings in plain/RCC concrete abutment ,wing wall/return wall with 100mm dia AC
pipe ,extending through the full width of the structural complete
metre 3000 311.89 935670.00
8 Providing & laying pitching with stone
boulder weighing not less than 35kg each with the voids filled with cement , sand
mortar 1:4 on slopes laid over prepared
media including boulder apron laid dry in front of toe of embankment complete as
per drawing & Technical Specification ( Filter media to paid separately under the
relevant item).
cum 680 2328.56 1583420.80
9 Providing and laying of filter media consisting of granular material of
GW,GP,SW groups as per IS:1498-1970 in required profile behind boulder filling of
abutment , wing wall /return wall etc.
above bed level with all labourand material complete job as per drawing and technical
specification of RDSO Guide line.
Cum 3970 1818.19 7218214.30
10 Hand Packed dry boulder filling on the back side of abutment , return wall, wing wall,
drop wall, bridges floor at flow area etc.
including supply , carriage of stone. Cost of all material & labour with all lead & Lift
with boulder size 200mm to 250 mm.
Cum 2600 892.12 2319512.00
Sub total of Schedule – 2 142288149.82
Add: 1% labour welfare cess 1422881.50
Total amount of Schedule – 2 143711031.32
Say Rs. 14,37,11,031.00
8 Signature of the tenderer
under seal of the firm
Schedule - 3 ( Structural Steel work at Super Structure)
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
1 Supplying of all types of structural steel conforming to Fe 410B of IS:2062,
fabrication , assembling, erection /slewing /end launching of steel girder
up to 45.7m span on sub structure incl
provision of trolley refuges , if reqd. Complete as per approved drawing incl.
one coat of Zinc chrome primer to IS -104 & one coat of Zinc chrome Red oxide
to IS 2074and painting as per IRS -B-1 on all members , ( Detailed fabrication
and erection drawing & launching
methology will be prepared and got approved by the contractor from RITES
Ltd). Rate include fabrication of all the types of battens , bracings , ties ,
stiffeners, packing , diaphgrams , shssop
rivets/ welding , T& F bolts drifts, shop welds , templates , Jigs , fixtures back up
supports , accessories , transporting various components from fabrication
shop , to site , including loading, unloading , lift and taxes complete.
Assembling of girders' on - drifts / bolts,
field riveting /welding , assembling of temporary support for side slewing ,
raising of girders to the bed block level, providing sliding arrangements and
slewing the girders in position, lowering
of girder on bearings and bed plates , grouting holes in the bed block for fixing
of HD bolts/ anchor pins of bed plates , all temporary arrangements. The bearing
sets to be provided with girders will be paid separately as per relevent item.
a) Open Web Girder MT 63 77476.31 4881007.53
Payment Schedule
i) Materials at Site -40%
ii) Fabrication at site - 15%
iii) Erection /launching - 20%
iv) Completion incl.painting & finishing -25%
9 Signature of the tenderer
under seal of the firm
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
2 Sand blasting & metalizing the bridge
component with aluminium wire as per IRS BI-2001 including applying one coat
etch primer of IS:5666 & followed by one
coat Zinc Chromate primer of IS:104 & two coats of aluminium paint of IS:2339
( one coat of aluminium paint is to be applied before errection & another coat
of aluminium paint to be applied after errection).During Sand blasting the
surface should be throughly cleaned &
roughened by compressed air with suitable abrasive material.Before
spraying the surface shall be made free from grease,scale, rust, moisture or
other foreign materials. The metal
spraying shall be carried out as per IS:6568. The chemical composition of
aluminium to be sprayed shall be in accordance with BS:1475 material I-
B(99.5%) aluminium otherwise as per IS:739. The surface of the sprayed
coating shall be uniform texture and free
from lumps, coarse areas & loosely adherent particles. The average
thickness of the sprayed aluminium coating shall 150 micron. All paints &
aluminium wire to be tested from
Govt.Approved laboratory with contractor's cost. The DFT of the paint is
to be checked at site with digital electrometer at the cost of the
contractor. The rate include cost of primer,paint,tools & plant and
machineries for metalizing works etc to
complete the work as per direction & satisfaction of Engineer -in - Charge.
sqm 1700 642.87 1092879.00
3 Supplying , fitting and fixing in position
true to line and level cast steel rockerbearing complete as per
IS:7666,IS: 9565,IS:1030,IS:919, IS:3073 and as perbridge code including
all accessories as per drawing and
Technical Specification.
MT 0.98 106332.57 104205.92
4 Supplying , fitting and fixing in position
true to line and level forged steel roller bearing complete as per IS:7666,IS:
9565,IS:1030,IS:919, IS:3073 and as
perbridge code including all accessories as per drawing and Technical
Specification.
MT 1.24 112978.40 140093.22
Sub total of Schedule – 3 6218185.67
Add: 1% labour welfare cess 62181.86
Total amount of Schedule – 3 6280367.52
Say Rs. 62,80,368.00
10 Signature of the tenderer
under seal of the firm
Schedule -4 ( Track Linking Work)
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
1 Supply & delivery of Locally available Machine crushed Ballast of 50 mm
size clean angular, hard and durable track ballast as per specification and
stacking the same on cess of the
formation or toe of the bank or at suitable place as directed by Engineer-in-
Charge at site. The rate includes all cost of lead, lift, royalty, sales tax & other tax
and duties and all incidental charges
complete as applicable. Tools, plants and screens of approved mesh & dimensions
required for inspection and passing at the time of measurement are to be arranged
by the contractor. The rate also includes
leveling of ground, if necessary, where the ballast are to be stacked.Note: 90%
payment shall be released on the net quantity accepted and balance
10% shall be released after spreading.
Cum 6500 1766.11 11479715.00
2 Laying, B.G. straight or curve Track with
following rail section (SWR of 33m to 40m rail pannel ) and concrete sleeper
(M+7) density with standard fittings
ensuring correct specing of sleepers, fixing and tightening of Fish Bolts & Nuts
and maintaining proper guage, alignment, level (both cross &
longitudinal ), expansion gap at rail joints, super elevation as necessary and
with one initial through packing. The
rate should be inclusive of dekinking of rails as required, cutting of rails as
required on straight and curve track for squaring of joints, drilling holes on web
of rail square to rail surface by using
proper template for fish plated joints, champhering of drilled holes, greasing
and oiling of fish plates and fish bolts and nuts and at fishing zone of the rail ends
including supply of grease oil etc.
Sleepers spacing versine,
a) With 60 kg panel rails of 33m to
40m
Track
meter
3000 342.46 1027380.00
11 Signature of the tenderer
under seal of the firm
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
3 Welding of rail joints 60 kg from single
rail to 3-rail panel on 'Cess' or in position SKV process with contractors PORTION
provided from RDSO approved manufacturer, dry moulds including
supplying skilled/artisan staff like welder,
moulder, chipper,lutter, aligner, striker/hammerman & adequate nos. of
semi-skilled and un-skilled labour and supplying petrol, as required for
facilitating welding works on track by
shifting the joint sleepers upto 30 cm on either side, providing suitable gap of
about 23 mm to 25 mm for welding, fixing the petrol tanks & heating the rail
ends by approved contractor's equipment and chipping the exess materials if
required, aligning, levelling etc. complete
including filing after welding on cess.
Each
Joint
561 3094.00 1735734.00
4 Handling, lifting and leading of ballast
from stacks with lead of 50m, which
have been duly measured and spreading ballast on formation,
Track & turnouts to ensure uniform and compact ballast cushion under the
sleepers desired ballast profile. Spreading of ballast should be as per specified line
and level and maintaining approved
profile as provided in the technical specifications. Spreading of ballast on
formation will be done only after supply is completed for a particular stretch as
decided by Engineer in charge and ballast
stacks have been released for spreading.
cum 6600 115.66 763356.00
5 Leading of ballast for every additional
lead of 50 m by contractors diplorry/head lead etc.
cum 4000 46.27 185080.00
6 Through packing of any kind of sleepers
with stone ballast to maintain correct alignment cross and longitudinal level as
required for maintaining track gauge,
versine, superelevation etc. on both straight and curve track laid with
contractor's tools and Plants
a) 1st through packing Track
Meter
3000 49.75 149250.00
b) 2nd through packing Track Meter
3000 41.45 124350.00
c) 3rd through packing Track
Meter
3000 41.45 124350.00
d) 4th through packing Track
Meter
3000 41.45 124350.00
12 Signature of the tenderer
under seal of the firm
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
7 Transportation of PSC sleeper from the Client/RITES Site store to the siteof work
considering lead up to 50m by contractor's transport including loading,
unloading of materials with all lead , lift ,
crossing road/Rly.tracks etc. complete.
MT 1303 113.25 147564.75
8 Additional lead for every subsequent 50m or part thereof over 50m & up to 500m
MT 1303 31.31 40796.93
9 Transportation of PSC sleeper from the Client/RITES Site store to the site of work
considering lead over500m up to 10km
by contractor's transport including loading, unloading of materials with all
lead , lift , crossing road/Rly.tracks etc. complete.
MT 1303 176.34 229771.02
10 Additional lead for every/Subsequent km
or part thereof, over 10km & up to 100km
MT/Km 1303 7.98 207958.80
11 Leading miscellaneous materials such as
iron work, rails, pipes, wooden logsstones over pitching stone size,
RCC/PCC beams/slabs etc. and all sinilar articles(each individual article or bundle
being more than 3.5m long in the longest
direction)by truck, trailor etc. including all loading, unloading and stacking , lead
over 500m and up to 10km.
MT 378 188.62 71298.36
12 Additional lead for every/Subsequent km or part thereof, over 10km & up to
100km
MT/Km 378 9.24 69854.40
13 Distribution of New/SH fittings &
fastenings at site by contractors transport
up to a distance of 2km including handling , loading , unloading of
materials with all lead , lift , crossing road/rly.tracks etc. complete
MT 30 1097.51 32925.30
14 Distribution of small fittings by trolly for every addl. 1 km or part thereof
MT 12 411.57 4938.84
Sub total of Schedule – 4 16518673.40
Add: 1% labour welfare cess 165186.73
Total amount of Schedule - 4 16683860.13
Say Rs. 1,66,83,860.00
13 Signature of the tenderer
under seal of the firm
Schedule -5 (Supply of P. Way Fittings)
SLNo Description of Item Unit Qty Rate (Rs) Amount(Rs)
1 Elastic Rail clips with flat toe (MK.III) to RDSO Drg. No.T-3701 (Alt.3) conforming
to specifications IRS-T-31/1989.
Nos 19034 79.38 1510918.92
2 Elastic rail clips type'J' for use at fish plated joints as per RDSO Drg. No. T-
4158 conforming to IRS Specification.
each 725 80.78 58565.50
3 Supplying of GFN metal liners to RDSO Drg. No.T-3706 (upto date Alteration)
conforming to IRS specification
each 19034 19.50 371163.00
4 Grooved Rubber Sole Plate to RDSO
Drg. No.T-3703 (upto date Alteration) conforming to IRS Specification for 6 mm
thick grooved rubber sole plates (Provisional) 1987 revised 2000
Nos 9517 27.09 257815.53
5 Fish Plates 60 kg to RDSO Drg. No.T-
1898 with upto date alteration conforming to IRS Specification No. T-
1.
Pair 190 2701.59 513302.10
6 Fish Bolts and nuts as per RDSO Drg. No.T-1899 Alt-2 of size 25 mm dia and
140 mm long conforming to IRS Specification No.T-23/67.
each 785 87.75 68883.75
7 Fabrication , Supplying anda fixing in
position Galvanied steel channel sleepers of mild steel of tested quality conforming
to to IS : 2062, on fabricated girders including all fixtures fastenings as per
approved Railway drawings with labour ,
material, tools and plants etc. as a complete job including galvanzing of all
components.
MT 8.188 90283.094 739237.97
Sub total of Schedule - 6 3519886.77
Add: 1% labour welfare cess 35198.87
Total of Schedule - 6 3555085.64
Say Rs. 35,55,086.00
Schedule - 6 ( Any other Unforseen item)
1 Any other unforseen items which are not covered by item of work of Sch A to Sch
E will be operated as per SER unified
standard schedule of rates ( works & Materials), 2010. Basic Cost -
50,00000.00
Ls Ls 10% above
5500000.00
Sub total of Schedule – 6 5500000.00
Add: 1% labour welfare cess 55000.00
Total of Schedule - 6 55,55,000.00
Total of Schedules (1+2+3+4+5 +6) 48,83,01,726.89
Say Rs. 48,83,01,727.00