d. ene, d. ridikas, b. rapp, j.c david, d. doré cea-saclay...
TRANSCRIPT
HIAT'09, 8-12.06.2009-Venezia 0
D. Ene, D. Ridikas, B. Rapp, J.C David, D. DoréCEA-Saclay, IRFU/SPHN, F-91191 Gif-sur-Yvette, France
for EURISOL Task#5 Safety & Radioprotection:
GANIL, France, FZJ, Germany, LMU, Germany, CERN, EUCEA, France, NIPNE, Romania, FI, Lithuania, Univ. Warsaw, Poland
HIAT'09, 8-12.06.2009-Venezia 1
Radiation safety issues
⇒ the strategy used for the design of RNB facilities
EURISOL-DS project (illustration) –early stageProblems addressed:
Legislation framework sets-up safety requirements protection of the environment, public and staff
Radioactive sources identification and estimation deciding the radiation safety features
Safety design objectives:(Protection of workers, public & environment)
HIAT'09, 8-12.06.2009-Venezia 2
1.1. Operation phaseOperation phase :
Protection against radiationsProtection against radiations => optimum shielding configurationoptimum shielding configuration
Containment of radioactive materialsContainment of radioactive materials=> risk analysis > risk analysis > equipments are adequate to minimize risk of radioactive material dispersion.
Compatibility with the environmentCompatibility with the environment=> impact of the radioactive releasesimpact of the radioactive releases
Radiological studies: Characterization of the prompt radiation field for normal and accident conditionsSafety studies: Classification of the events & Risk assessment Environmental studies: Characterization of the specific site & impact assessment
2.2. Post Post --operational phaseoperational phase:
Protection against radiationsProtection against radiations => measures to limit the exposure & working proceduresmeasures to limit the exposure & working proceduresduring maintenance and interventions machine will be dismantled and decommissionedwaste transportation/disposal
Compatibility with the environmentCompatibility with the environment=> impact of the radioactive releasesimpact of the radioactive releases>decommissioning & waste transportation/disposal
Radiological studies: assessment of the residual radiation field => specifications on the exposure of the personnel Environmental studies: Characterization of the specific site & impact assessment
HIAT'09, 8-12.06.2009-Venezia 3
HIAT'09, 8-12.06.2009-Venezia 4
• Direct: high energy spallation100 kW
- Converter: neutron fission 4MW
Al2O3, SiC, UCx, Pb, etc
p, 1GeV
Direct method
p, 1GeV Hg
UCx
UCx
Converter method (~1015 fiss/s)
Production yield (atoms s-1 mA-1)
40 50 60 70 80 90 100
Neutron number (N)
25 30 35 40 45 50 55 60 65
Ato
mic
num
ber
(Z)
6 7 8 9 10 11 12 13 14
Production yield (atoms s-1 mA-1)
40 50 60 70 80 90 100
Neutron number (N)
25 30 35 40 45 50 55 60 65
Ato
mic
num
ber
(Z)
235U + n( ~ 100 keV)
238U + p( 1GeV)
Direct target: R=1.8cm, L=40cm
Fission target(30kW)(Rext=1.75cm, Rint=0.4cm,H=20cm)
Production yield (atoms s-1)
0 20 40 60 80 100 120 140
Neutron number (N)
0
20
40
60
80
100
Ato
mic
num
ber
(Z)
6 7 8 9 10 11 12 13 14
Production yield (atoms s-1)
0 20 40 60 80 100 120 140
Neutron number (N)
0
20
40
60
80
100
Ato
mic
num
ber
(Z)
HIAT'09, 8-12.06.2009-Venezia 5
H*(10)[μSv h-1]
Total_H*(10)[mSv y-1]
Public areas:inside fence
0.11
1
Controlled areas 10 20 / 2000 hFull beam loss: Total_H*(10) ≤ 50 μSv
JUSTIFICATION
LIMITATION
OPTIMISATION
Design limits for occupied areas/ ICRP 60
+ limited intervention time & remote handling>2
Remote handling essential>20
Planification and optimisation of all work>0.1
Maintenance constraintsH*(10) [mSv h-1]CERN guidelines:
HIAT'09, 8-12.06.2009-Venezia 6
Design guidelines & previous experience => Basic estimates
Few exemples:Equipement primary Energy Intensity
(pps)Losses(pps)
Specificsources
Linac p 1GeV (1-4)*6*1015 6*1012/E[MeV] m-1
(6*107 - 6*108 )m-1
(6*107 - 6*108 )m-1
~4*1012
( stripper zone)
-Few hot spots -Neutron
backscatter
Linac#1(L=209m)
132Sn (0.6 – 150) MeVu-1
6*1012 No spotsspecification
Linac#2(L=156m)
132Sn (0.6 – 150) MeVu-1
6*1012 - 2.5*1012 No spotsspecification
HIAT'09, 8-12.06.2009-Venezia 7
• Prompt radiationPHITS, FLUKA, MCNPX-HI
Mixed Φ & Conversion factors->H*(10)
10-2
10-1
1
10
10 2
10 3
10 4
10 5
10 6
10 7
10 8
10 9
10 10
10 11
10 12
1 10 102
103
40 ° (×10 7)
100 ° (×10 4)115 ° (×10 3)
145 ° (×10)
0 ° (×1010)
10 ° (×10 9)
25 ° (×10 8)
55 ° (×10 6)
85 ° (×10 5)
130 ° (×10 2)
160 °
Energie (MeV)
d2 σ/dΩd
E (m
barn
/MeV
/sr)
Fe(p,xn)X à Ep = 1600 MeV
Données
Cascade Bertini
Cascade Cugnon
PHITS
0°
30°
50°
80°
110°
Ar(95MeV/u)+Cu neutrons
PHITS
p(1.6 GeV) + Fe neutrons
(MCNPX)
100 200 300 400 500 60010-7
10-6
10-5
10-4
10-3
10-2
10-1
100
101
d=60 cm (x10-3)
d=40 cm (x10-2)
d=20 cm (x10-1)
Neu
tron
flux,
n/M
eV/s
r/ion
E, MeV
experiment MCNPX
d=0 cm
Neutron penetration in concrete shieldMCNPX
Benchmarks related to prompt radiation
HIAT'09, 8-12.06.2009-Venezia 8
• Residual radiation:
1GeV p+Pb
10-1
1
10
10 2
25 50 75 100 125 150 175 200A
Cro
ss S
ecti
on
(m
b)
Production of Residual Nuclei
Benchmarks related to induced activityNeutron flux in ith cellGeometry
and materialsdescription
DCHAIN-SP-2001/CINDER
PHITS/MCNPX
Residues in ith cell
Irradiation Scheme
H*(10)MCNPX
Activation products&
Photon sources
5000h irradiation at 4MW40 years & duty factor 0.7
HIAT'09, 8-12.06.2009-Venezia 9
Hg converter and secondary fission targets
MAFF-like configuration =>
NEUTRON STREAMINGNEUTRON STREAMING
Monte Carlo & generic studies -> choices of materials & shielding effect
First version of design =>
BULK SHIELDINGBULK SHIELDING
Biasing methods
HIAT'09, 8-12.06.2009-Venezia 10
• Prompt radiation: BULK SHIELDING
+Attenuation formula
Iron 100 cm140180220260300
conc
rete
• 1 m of iron• For θ= 0, 90, 180°
9.0, 8.0 & 6 m of concrete
FLUKA (CERN)
HIAT'09, 8-12.06.2009-Venezia 11
• Prompt radiation: NEUTRON STREAMING FLUKA (CERN)
Ion extraction
tubes
Spallation target
600
cm
Fission targets
12 3
concrete
Fission target handling room
6 m
con
cret
e
RIBlines
Laserportholes
~9 m
Z=0
Fission target handling room
HIAT'09, 8-12.06.2009-Venezia 12
10-2
10-1
100
101
102
103
104
105
0 100 200 300 400
H*(
10)
(μS
v h-1
)
Concrete depth (cm)
I = 6.25*109 ion s-1 | 10-4 m-1 loss over 10 m concentrated at one point
150MeV/u | Normal operation: continuous loss of 10-5 - 10-4 m-1
---------- 225 cm ---------
------------------- 340 cm -----------------
limit controlled areas
limit public areas
10-2
10-1
100
101
102
103
104
105
106
107
108
0 100 200 300 400 500H
*(10
) (μ
Sv
h-1)
Concrete depth (cm)
150MeV/u | Full beam loss: I = 6.25*1012 ion s-1
------ 225 cm ------
-------------- 340 cm -------------
10 mSv h-1*tcut(=1s)
0.1 mSv h-1*tcut (=1 s)
2.78 μSv
27.8 nSv
A shield designed for a continous beam loss of 10-4 m-1 (point loss of 6.25*109 ion s-1 ) during the routine operation is also adequate for an accident loss of the full beam at a localised point, providing that the linac cutoff time is less than
1s.
z (cm)-600 -400 -200 0 200 400 600
x (c
m)
-400
-300
-200
-100
0
100
200
300
400
500
n/c
m^2
1
10
210
310
410
510
610
710
810
910
1010
(150 MeV/u) 132Sn + Cu | Neutron fluence given by a total beam loss of 1 second
PHITS132Sn
θ
Method(CEA)
HIAT'09, 8-12.06.2009-Venezia 13
E[MeV/u]
Η1
[Sv m2 ion-1]λ1
[g cm-2]
H2
[Sv m2 ion-1λ2
[g cm-2]
150 2.00E-10 38.78 7.98E-11 62.00
115 1.13E-10 23.50 6.14E-11 57.32
76 6.18E-11 21.36 1.27E-11 53.20
45.5 1.69E-11 12.19 1.55E-11 40.52
21.3 - - 2.00E-12 33.57
⎥⎦⎤
⎢⎣⎡−+⎥⎦
⎤⎢⎣⎡−=
22
)(2
12
)(1 expexp)/,(*λλ
λ dr
EHdr
EHdEH ppp
10-1
100
101
102
103
104
105
106
0 50 100 150 200 250 300 350 400
H*(
10)
(μS
v h-1
)
Concrete depth (cm)
21 MeV45 MeV76 MeV
115 MeV150 MeV
Stripper zone
21MeV/u 150MeV/u
10-10
10-9
10-8
10-5 10-4 10-3 10-2 10-1 100 101 102
E d
Φ/d
E (
n cm
-2s-1
ion-1
)
Energy (MeV)
20 cm40 cm60 cm80 cm100 cm
10-8
10-7
10-6
10-5 10-4 10-3 10-2 10-1 100 101 102E
dΦ
/dE
(n
cm-2
s-1 io
n-1)
Energy (MeV)
Spectral fluences at various depths in concrete for 150MeV/u
20 cm40 cm60 cm80 cm100 cm
* Agosteo S, Nakamura T , at al. NIM/B 217, 2004
!!
neutrons
HIAT'09, 8-12.06.2009-Venezia 14
U-238 : 400 MeV/uHe-3 : 777 MeV/uproton : 1 GeV
Beam on stopping Cu targetRonningen & Remec, 2005
Beam direction
10-1
100
101
102
103
104
0 50 100 150 200 250 300
H*(
10)
(μS
v h-1
)
Concrete depth (cm)
I = 6*109 ion s-1 | 10-4 m-1 loss over 10 m concentrated at one point
6He2+ at 250 MeV/u
132Sn50+
neutronsphotons
Photon H*(10) < 3% Total H*(10)
3 m of concrete:Neutron H*(10) for 6He (250MeV/u)
Neutron H*(10) for 132Sn (150MeV/u) ~ 5
Safety operation domain:energy range and beam intensities.
!!
Other species & secondaries
HIAT'09, 8-12.06.2009-Venezia 15
• Underground target position• Front-end retracts vertically • Hot-cell for target exchange• Separator in 3rd level• Neighboring hot-cell accessible during run
Effe
ctiv
e do
se r
ate
E (S
v/h)
Soil activation!
Effective dose rate maps
Conceptual design of 100kW target station (CERN)
HIAT'09, 8-12.06.2009-Venezia 16
0.585MeV/u
RFQ150 MeV/u
beam
du
mp
L(1) L(2)
Experimentrooms
21.3 MeV/u
Experimentrooms
44 m 102 m
2.8
W
<= 10-4 m-1 =>10-4 m-1 => 7.92
W
6 W
4 W
2.4
W
Stripper
1.68
kW
Uncontrolled beam loss of
10-4 m-1
0.585MeV/u
RFQ L(1) L(2)
Experimentrooms
21.3 MeV/u 150 MeV/u
Experimentrooms
44 m 165 m2.8
W
<= 10-4 m-1 =>10-4 m-1 => 19.8
W
15 W
10 W
6 W
beam
du
mp
Shielding of Postaccelerator (CEA)
Energy[MeV]
21.3 45.5 76 115 150
Length [m] 44 40 40 40 45
Thickness (cm)
70 130 175 210 225
Vstaff (m3) 338.05* 4732.7 for a tunnel surface of 3 m x 4m
Thickness (cm)
140 195 245 320 380Public
Vpublic (m3) 536.6* 7512.4 for a tunnel surface of 3m x 4m
Staff
1501157645.5Stripper21.3Energy[MeV]
173321311044Length (m)
20018015011016070Thickness (cm)Staff
325295230185235140Thickness (cm)
Public
205.8* 2881.2 for a tunnel surface of 3 m x 4 mVstaff (m3)
Vpublic (m3) 343.4* 4120.2 for a tunnel surface of 3 m x 4 m
HIAT'09, 8-12.06.2009-Venezia 17
z (cm)-200 -100 0 100 200 300 400
x (c
m)
-300
-200
-100
0
100
200
300 -1Sv
hμ
1
10
210
310
410
510
610
710
810
910
1010
) ->DUMP & SHIELD | Neutron H*(10)12, 6.25*10-1Sn (150MeV u132
SHIELD [cm]material
Η1
[Sv m2 ]λ1
[g cm-2]H2
[Sv m2]λ2
[g cm-2] Staff
60.36 364
steel - - 5.000E+04 112.14 254 320
Public
concrete 1.747E+03 23.7 1.338E+02 480
concrete
concrete / steel
soil
void
beam
Bea m 5o
Iron shieldCopper + 10% water
Graphite (1.84g/cm3)
100 cm40 cm
8 cm 16 cm
132 Sn 25+
Beam power = 19.8 kW (150 MeV/u)
Beam size σ = 2 mm
Beam Dump cavity: thickness of lateral wall (CEA)
HIAT'09, 8-12.06.2009-Venezia 18
Dose in distance of 1m after 1 day decay time:1014 fission/sec235U ion source
~ 10 kCi ‘open’ source
Beam tube3.108 μSv/hnon-volatile activity
ions
slit aperture ofpre-separator(m=95, 140: 97%)~ 5.106 μSv/h
slit aperture ofhigh-resolution separator~ 104 μSv/h
~2%non volatile
~68%
Dispersion of radioactivity: from MAFFEURISOL 10 higher!P. Thirolf et al.
(LMU)
exhauststorage tanks
outer beam tube~ 300 μSv/h
~30%
~ 0.02%
atoms/gases
regeneration
decay on thecryopump
slits/targets of beam line~ 3.103 μSv/h
large small
Capability of Capability of CryotrapCryotrap3 cryotraps prototypes tested:Retention capability (vs. pressure behind cryotrap)‘carry over’: fraction of leaking gas load transported across cryotrap
Cryotrap workswithin (simulated) expectations 99.98% of volatileradioactivity canbe localized!
HIAT'09, 8-12.06.2009-Venezia 19
EURISOL-DS RISK REGISTER
Equipment Operational phase and Risk RP [mSv/h] and intervention
Risk assessment before mitigation Mitigation of Risk Risk assessment after
mitigation
Owner Name and location Acronym -Number Action type desccription of failure Description of associated risk Dose rate Job
duration Probability Impact Score Comments - Needed actions Probability Impact Score
•The methodology used
•The file format
derived from the CERN-AB risk register elaborated by P. Bonnal (05/05/2003)
HIAT'09, 8-12.06.2009-Venezia 20
EURISOL-DS RISK REGISTER
Equipment Operational phase and Risk RP [mSv/h] and intervention Risk assessment before mitigation Mitigation of Risk
Risk assessment
after mitigationOwner Name and location Acronym -
Number Action type desccription of failure Description of associated risk Dose rate Job
durationProbabi
lity Impact Score Comments - Needed actions Probability Impact Score
Loss of Hg flow, flow blockage and cavitation
2 2 4 Instrumentation to control Hg flowrates 2 1 2
Explosion by Hg boiling 1 5 5 Containement of Hg (safety hull) 1 1 1
Overheating of the window 3 3 9 Instrumentation to control Window
temperature 3 1 3
T2 CGS target vessel ??? Operation Rupture of the vanes
Partial melting of the window 1 5 5 Containement of Hg (safety hull) 1 1 1
Main risks for the Hg converter
EURISOL-DS RISK REGISTER
Equipment Operational phase and RiskRP [mSv/h]
and intervention
Risk assessment before mitigation Mitigation of Risk Risk assessment
after mitigation
Owner Name and location Acronym -Number Action type desccription of failure Description of associated risk Dose rate Job
duration Probability Impact Score Comments - Needed actions Probability Impact Score
T4 UC target/running
RU-T-06 operation firing target
stop of operation, target is lost, removal of target and replace with a new one, clean the pit region. The pit and beam line are highly contaminated.
1PBq 2000 2 5 10
avoid oxygen contamination, redondancy of safety valves. Neutral atmosphere during removal may be foreseen 1 5 5
Main risks for the Fission target
HIAT'09, 8-12.06.2009-Venezia 21
10-1
100
101
102
103
104
105
10-810-710-610-510-410-310-210-1 100 101 102 103
Tot
al a
ctiv
ity (
GB
q)
Decay time (years)
min hour day yearmnth
235U20% 235U
3% 235UUnatUdep
Th
1 year after irradiation 10 years after irradiation
ISABEL-ABLA
CEM2k INCL4-ABLA
ISABEL-ABLA
CEM2k INCL4-ABLA
Total activity
Half life 9.8102 2.8 103 4.1 102 6.1 102 1.6 103 2.0 102
195Au 186.1 d 2.8 101 2.4101 2.6 101 2.1 10-4 1.8 10-4 2.0 10-4
148Gd 74.6 y 2.110-1 7.4 10-1 1.1 10-1 2.0 10-1 6.8 10-1 9.7 10-2
3H 12.32 y 1.9 102 2.3 103 3.9 101 1.1 102 1.4 103 2.3 101
172Hf 1.87 y 1.8 102 2.3 102 1.7 102 6.5 10-1 8.3 10-1 6.1 10-1
194Hg 444 y 3.0 1.2 101 2.6 3.0 1.2 101 2.5
UCx
Hg
10-1
100
101
102
103
104
10-8 10-7 10-6 10-5 10-4 10-3 10-2 10-1 100 101 102
Sp
eci
fic a
ctiv
ity (
GB
q c
m-3
)
Decay time (years)
min hour day yearmnth
Total145Sm
α emmiters210Po
Direct target | CEM2kUCx( L=40cm, R=1.8cm)
MMW target
Hg235U:
7% halogens
10% rare gases
1% actinides
HIAT'09, 8-12.06.2009-Venezia 22
Z (cm)-1000 -500 0 500 1000
R (c
m)
-1000
-500
0
500
1000
-610
-410
-210
1
210
410
610
810
1010
1210 -1 B
q g
-610
-410
-210
1
210
410
610
810
1010
1210
1 MBq/g < A < 1GBq/g
1 kBq/g < A < 1MBq/g
1 Bq/g < A < 1kBq/g
A < 1Bq/g
40 years irradiation at 2.28 MW
105
106
107
108
109
1010
1011
10-6 10-5 10-4 10-3 10-2 10-1 100 101 102 103
Speci
fic a
ctiv
ity (
Bq g
-1)
Decay time (years)
min hour day yearmnth
Total56Mn
60Co170Tm
55Fe51Cr
63Ni59Ni
102
103
104
105
106
107
108
10-6 10-5 10-4 10-3 10-2 10-1 100 101 102 103
Specific
activity (
Bq g
-1)
Decay time (years)
min hour day yearmnth
Total3H
45Ca37Ar
41Ca55Fe
28Al104Rh
39Ar
Activity map at 100days
Stainless steel Concrete
Activities
10-4
10-3
10-2
10-1
100
101
102
103
104
105
10-1 100 101 102 103
Tot
al A
ctiv
ity (
TB
q)
Decay time (y)
LL-ILW steelLL-ILW concreteSL-ILW concrete
EW concrete
100
101
102
103
104
105
10-1 100 101 102 103
Mas
s (t
)
Decay time (y)
LL-ILW steelLL-ILW concreteSL-ILW concreteEW concrete
Mases
Waste categories
HIAT'09, 8-12.06.2009-Venezia 23
Activation of Cu structure (150 MeV/u)
10-1
100
101
102
103
104
105
106
107
104 105 106 107 108
Sp
eci
fic a
ctiv
ity (
Bq
cm
-3)
Decay time (s)
1 d1 w
1 m
1 y10 y
1 h
Total64Cu (T1/2 =12.7h)61Cu (T1/2 = 3.34h)62Cu (T1/2 = 9.74m)65Ni (T1/2 = 2.52h)
51Cr (T1/2 = 27.7d)59Fe (T1/2 = 44.5d)60Co (T1/2 = 5.27y)
3H (T1/2 = 12.3y)63Ni (T1/2 = 100.1y)
100
102
104
106
108
1010
1012
100 101 102 103 104 105 106
Tota
l act
ivity
(Bq)
Decay time (s)
Point full beam implant (6.2*1012 ions) of 132Sn
1s 30s1min
1h 1d 1w
1m
Total132Sn (T1/2=39.7s)
132Sb (T1/2=2.79min)132Te (T1/2=3.2d)
132I (T1/2=2.3h)
10-4
10-3
10-2
10-1
104 105 106 107 108
Spe
cific
act
ivity
(B
q cm
-3)
Decay time (s)
1 h
1 d 1 w1 m
1 y10 y
Total 7Be
3H41Ar
38Cl39Cl
11C37Ar
10-3
10-2
10-1
100
101
104 105 106 107 108
Spe
cific
act
ivity
(B
q cm
-3)
Decay time (s)
1 h1 d
1 w1 m
1 y 10 y
Inner concrete wall -(0-20)cm | Loss of 6.2*109 ion s-1 of 150MeV/u Dominant radioactive nuclides
Total37Ar
3H24Na
31Si45Ca
56Mn55Fe
32P238U
Activation of concrete (150 MeV/u)
Air activation (150 MeV/u)Total activity due to implantation
Contribution of the wall is
not significant
Air activation using PHITS (evaluated cross sections)
14,15O,13N |41Ar 0.35Bq cm-3
Activity vs Discharge limit
Inhalation dose received by workers intervening in tunnel
1011 Bq 132Sn implantation132I accumulation after 1h
HIAT'09, 8-12.06.2009-Venezia 24
21MeV/u
150MeV/u
10-2
10-1
100
101
102
103
100 101 102 103
H*(
10)
(μS
v h-1
)
Decay time (h)
21MeV/u | H*(10) inside the tunnel
1 h1 d
1 w
1 m
6 m
10
Cu activationFull beam implantTotal
10-1
100
101
102
103
104
100 101 102 103
H*(
10)
(μS
v h-1
)
Decay time (h)
150MeV/u | H*(10) inside the tunnel
1 h
1 d1 w
1 m
6 m
Cu activation Full beam implantTotal
104
105
106
107
104 105 106 107 108
Act
ivity
(B
q)
Decay time (s)
21MeV/u | Total activity inside tunnel
1 h1 d
1 w
1 m
1 y
10 yCu activationFull beam implantConcrete wall
105
106
107
108
109
104 105 106 107 108
Act
ivity
(B
q)
Decay time (s)
150MeV/u | Total activity inside tunnel
1 h1 d
1 w1 m
1 y
10 y
Cu activationFull beam implantConcrete wall
Points -> contact
Lines -> 1m distance Total activity
H*(10)
Residual field:-high energy zone
copper structure copper structure activationactivation
-low energy zone
ion ion implantationimplantation
In the high energy zonecontinuous accessibilityafter ~ week cooling timeoroccupancy factor of minimum 570 hours/year=> 20 mSv y-1
Maintenance operations to be planed
HIAT'09, 8-12.06.2009-Venezia 25
Isotope T1/2 Soil Groundwater3H 12.33y 3.149*10-5 3.299*10-6
7Be 53.12d 3.662*10-6 3.662*10-7
22Na 2.6y 7.782*10-6 7.784*10-7
24Na 14.96h 7.551*10-6 7.583*10-7
32P 14.26d 1.047*10-8 9.584*10-9
35S 87.32d 2.262*10-23 4.938*10-9
45Ca 162.61d 8.111*10-6 7.800*10-7
46Sc 83.79d 6.833*10-7 2.540*10-21
54Mn 312.3d 2.217*10-7 3.674*10-13
55Fe 2.73y 2.679*10-6 4.912*10-12
65Zn 244.26d 3.867*10-8 5.880*10-12
Specific activity [Bq cm-3] in first 100 cm of soil/groundwatersurrounding the concrete wall after 40 y of continous irradiation
1.301*104 Bq < 105 Bq --LIMIT*
*IAEA TECDOC-1000, 1998,Clearance of materials resulting from the use of radionuclides in medicine, industry and research.
5.265*104 Bq < 1012 Bq --LIMIT*
Transport of radioactive species into the ground does not represent a hazard for
the population
POSTACCELERATOR
HIAT'09, 8-12.06.2009-Venezia 26
A schematic layout for liquid Hg-target disposal strategy
Extrapolation from laboratory scale to “industrial” scale still to be done!
Disposal of liquid Hg (FZJ)
Chemical stabilization of Hg as an inorganic compound, e.g. HgS,HgSe, HgO, Hg2Cl2,
HgCl2
HIAT'09, 8-12.06.2009-Venezia 27
Further steps:
• Derived Intervention Levels (DIL)• Exposure from underground water contamination• Development of a resident GIS platform• Cadastral Impact Analysis (GIS based)• …
Methodology validated, recommended & accepted by safety authoritiesTools, data & knowledge to be used in
Environmental and health Impact Assessment DESKTOP ASSISTANT
Point Source Exposure Acute Exposure to Environmental Releases
Prolonged Exposure toEnvironmental Releases
E-BOOK
DATA Libraries
Nuclear Facilities Derived Release Limit
The Map Manager
Combination of knowledge on Accelerator & Research Reactor based nuclear installationscreation of dedicated toolkit for EURISOL DS
Toolkit operational both for normal operation and accidental situations!
Site dependent analysis to be performed!
NIPNE
HIAT'09, 8-12.06.2009-Venezia 28
Safety integration from the start hints innovative and flexible solutions in maters of safety
EURISOL has similarities with high-power spallation n-sources & small research reactors
Very specific features:
Use of pyrophoric actinide carbide targets;
Presence of alpha-emitters;
Distribution over extended buildings of intense RIBs and sources of all chemical nature
Dedicated technical standards to be applied under utmost reliable safety rules and procedures.
HIAT'09, 8-12.06.2009-Venezia 29
BackBack--upup
HIAT'09, 8-12.06.2009-Venezia 30
Target positions:Target positions:
Geometry : Geometry : Last design variant (L. Last design variant (L. TecchioTecchio): 30kW load heat ): 30kW load heat Volume = 181cmVolume = 181cm33 ((RRextext=1.75cm, =1.75cm, RRintint=0.4cm,H=20cm=0.4cm,H=20cm))Material:Material:Targets: graphite + U, density=1.88 g cmTargets: graphite + U, density=1.88 g cm--33, , (mass U=15g | (mass U=15g | masemase rate: U/C=1/20 , rate: U/C=1/20 , MKLNMKLN))Moderator: HModerator: H22O, Fe (O, Fe (232232Th)Th)Reflector: Reflector: BeOBeO, Fe (, Fe (232232Th)Th)PhysicsPhysics parametersparameters::
Source: p; E=1GeV,Gauss (Source: p; E=1GeV,Gauss (σσ = 1.5cm)= 1.5cm)Model:CEM2kModel:CEM2kT=239KT=239K
Moderator
Reflector
Mercury target
Iron shielding
Concrete
Proton beam
Fission target
z = 0 T#5 T#1 T#3z = 15 T#6 T#2 T#4x=> -15 0 15y=> -12.9 10 -12.9
Reflector
Iron
Fission target
Concrete xy
zy Results normalised at 1mA
HIAT'09, 8-12.06.2009-Venezia 31
Neutron Flux – distribution over the targets
1013
1014
Target#5 Target#1 Target#3
Φ (
n cm
-2s-1
)
235U20%U5
3%U5Unat
Udep232Th
--------------z = 0 cm--------------
1013
1014
Target#6 Target#2 Target#4
Φ (
n cm
-2s-1
)
-------------z = 15 cm-------------
--------------z = 0 cm--------------
Configuration Average
z=0cm Average z=15cm
235U 5.1380E+13 5.6604E+1320% 235U 5.0084E+13 5.5219E+133% 235U 4.9764E+13 5.4867E+13
Unat 4.9707E+13 5.4811E+13Udep 4.9700E+13 5.4794E+13
232Th 5.2496E+13 5.8150E+13
10-6
10-5
10-4
10-3
10-910-810-710-610-510-410-310-210-1 100 101 102 103E
dΦ/d
E (
n cm
-2s-1
)
Energy (MeV)
100% 235U
20% 235U
3% 235UUnat
Udep232Th [Fe/Fe]
Neutron flux (n cm-2 s-1)
Neutron Flux – energy distribution (T#1)
HIAT'09, 8-12.06.2009-Venezia 32
Fission Rates –energy distribution (T#1)
10-12
10-11
10-10
10-9
10-8
10-7
10-6
10-5
10-4
10-910-810-710-610-510-410-310-210-1100 101 102 103
Fis
sion
rat
e (f
iss
prot
on-1
)
Energy (MeV)
100% 235U20% 235U3% 235U
UnatUdep
232Th
1011
1012
1013
1014
Target#5 Target#1 Target#3
Fis
sion
rat
e (f
iss
s-1)
235U20%U5
3%U5Unat
Udep232Th
--------------z = 0 cm--------------
1011
1012
1013
1014
Target#6 Target#2 Target#4
Fis
sion
rat
e (f
iss
s-1)
-------------z = 15 cm-------------
--------------z = 0 cm--------------
Configuration 235U* (fiss/s)
238U (fiss/s)
Total (fiss/s)
235U [%]
235U 5.7689E+14 5.7689E+14 100 20% 235U 1.3823E+14 1.2021E+12 1.3943E+14 99.143% 235U 2.1712E+13 1.3931E+12 2.3106E+13 93.97
Unat 5.2449E+12 1.4172E+12 6.6621E+12 78.73Udep 1.4591E+12 1.4223E+12 2.8814E+12 50.64
232Th 5.2366E+11 5.2366E+11 * 232Th for Th case
Fission Rates – distribution over the targets
Fission Rates – total
HIAT'09, 8-12.06.2009-Venezia 33
C(235U) vs D(UC3*)
Neutrons vs 1GeV protons
Neutron fission rate: fission | spallation
10-9
10-8
10-7
10-6
10-5
10-4
10-3
10-910-810-710-610-510-410-310-210-1 100 101 102 103
Fis
sion
rat
e (f
iss
prot
on-1
)
Energy (MeV)
235U
238U
235U |Converter method
UC3 |Direct method
Neutron flux: fission | spallation
10-6
10-5
10-4
10-3
10-2
10-910-810-710-610-510-410-310-210-1 100 101 102 103
EdΦ
/dE
(n
cm-2
pro
ton-1
)
Energy (MeV)
235U |Converter method:T#1
T#2
T#3
T#4
T#6
T#5
10-6
10-5
10-4
10-3
10-2
10-910-810-710-610-510-410-310-210-1 100 101 102 103
EdΦ
/dE
(n
cm-2
pro
ton-1
)
Energy (MeV)
235U |Converter method:
UC3 |Direct method
Configuration Φavg(n cm-2 s-1) z=0cm
Φavg(n cm-2 s-1) z=15cm
Φtotal (n cm-2 s-1)
Converter (235U) 5.1380E+13 5.6604E+13 Direct (UC3) 2.473E+13
Configuration 235U
(fiss/s) 238U
(fiss/s) Total (fiss/s)
Converter (235U) 5.7689E+14 5.7689E+14 Direct (UC3) 1.591E+11 4.0415E+13 4.0574E+13
* Direct target: R=1.8cm, L=40cm
HIAT'09, 8-12.06.2009-Venezia 34
Yields – Kr: fission | spallation
75 80 85 90 95 100 0
20
40
60
80
100
Mass Number (A)
ratio
105106107108109
10101011101210131014
75 80 85 90 95 100
Pro
duct
ion
yiel
d (a
t. s-1
| at
. s-1
mA
-1)
Mass Number (A)
ratio
235U |Converter methodUC3 |Direct method Kr
115 120 125 130 135 140 145 150 0
20
40
60
80
100
Mass Number (A)
ratio
105106107108109
10101011101210131014
115 120 125 130 135 140 145 150
Pro
duct
ion
yiel
d (a
t. s-1
| at
. s-1
mA
-1)
Mass Number (A)
ratio
235U |Converter methodUC3 |Direct method Xe
105 110 115 120 125 130 135 140 0
20
40
60
80
100
Mass Number (A)
ratio
105106107108109
10101011101210131014
105 110 115 120 125 130 135 140
Pro
duct
ion
yiel
d (a
t. s-1
| at
. s-1
mA
-1)
Mass Number (A)
ratio
235U |Converter methodUC3 |Direct method Sn
65 70 75 80 85 0
20
40
60
80
100
Mass Number (A)
ratio
105106107108109
10101011101210131014
65 70 75 80 85
Pro
duct
ion
yiel
d (a
t. s-1
| at
. s-1
mA
-1)
Mass Number (A)
ratio
235U |Converter methodUC3 |Direct method Ga
Yields – Xe: fission | spallationYields – Sn: fission | spallation
Yields – Ga: fission | spallation
Neutrons vs 1GeV protons
HIAT'09, 8-12.06.2009-Venezia 35
Major Risks:• breaking of target container• target firing
Consequences:Dissemination of radioactivity in the environment
1015 fission fragments/sec per target(~ 5 x 104 Ci)
1st container
2nd container
1st container2nd container
Main risks for the Fission target
Luigi Tecchio – Task 4
HIAT'09, 8-12.06.2009-Venezia 36
large small
Capability of Capability of CryotrapCryotrap3 cryotraps prototypes tested: retention capability (vs. pressure behind cryotrap)‘carry over’: fraction of leaking gas load transported across cryotrap
2 trap types operated at different temperatures:
Cryotrap works within (simulated) expectations 99.98% of volatile radioactivity can be localized!
(LMU)
10-10 10-9 10-8 10-7 10-6 10-5 10-4 10-310-6
10-5
10-4
10-3
10-2
10-1
100
GP N 18KSP N 30KSP N 8KGP N 28KGP N 21K
Car
ry o
ver p
R/p
M
PCryo [hPa]
design goal