current status of each countermeasure for … presentations...ice wall ice wall (30 m deep)...
TRANSCRIPT
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 1
Current Status of Each Countermeasure for Contaminated Water
September 8-10th, 2014Yoshitaka HAGIWARA
Fukushima Daiichi Decontamination and DecommissioningEngineering Company, TEPCO
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 2
Contents1. Current groundwater conditions
2. Contaminated water storage
3. Measures against contaminated water
4. Operation of groundwater bypass
5. Construction of seaside impermeable wall
6. Restoration of sub-drains
7. Construction of frozen soil wall
8. Seawater piping trench
9. Water stop of connection between trench and building
10. Facing
11. Radionuclide concentration of water
12. Video about Frozen soil wall
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 3
1. Current groundwater conditions
1号機 2号機 3号機 4号機
地下水
地下水
(c) GeoEye/Japan Space Imaging CorporationCurrent flow of groundwater
Unit 1
Unit 1 Unit 2 Unit 3 Unit 4
groundwater
groundwater
The water level of the contaminated water inside the buildings is kept lower than that of the outer groundwater, which prevents water inside from flowing out. Therefore, contaminated water in the buildings does not mix with the groundwater flowing around the buildings. However, the difference of water level raises the inflow of groundwater into buildings.
The water level of the contaminated water inside the buildings is kept lower than that of the outer groundwater, which prevents water inside from flowing out. Therefore, contaminated water in the buildings does not mix with the groundwater flowing around the buildings. However, the difference of water level raises the inflow of groundwater into buildings.
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 4
2-1. Circulating water and reactor cooling
④Water storage (approx.400m3/day)
TanksTanks
Desalination
Turbinebuilding
Reactor building
Groundwater
Cooling water tank
ALPS(Advanced Liquid
Processing System)
Cs removal
②Groundwater inflow(approx. 400m3/day)
①Reactor cooling water (approx.300m3/day)
Contaminated water
Treated water contaminated water)
③Treatment(approx. 700m3/day)
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 5
Steel horizontal tank
Flange type steel cylindrical tank
Steel square type tank
Welded type steel cylindrical tank
*As of June 17, 2014
【Amount of contaminated water stored in tanks*】
Fresh water: approx. 21,000m3
Waste water generated by evaporative concentration:approx. 9,000m3
Concentrated salt water at RO device:
approx. 367,000m3
Water treated by ALPS: approx. 128,000m3
Total amount of 525,000m3 * is stored in tanks. Current available storage capacity* is 570,000m3. Available storage capacity will be increased up to 800,000m3. (by the end of March 2015 )
Total amount of 525,000m3 * is stored in tanks. Current available storage capacity* is 570,000m3. Available storage capacity will be increased up to 800,000m3. (by the end of March 2015 )
2-2. Contaminated water storage
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 6
20
30
40
50
60
70
2013/8/27
2013/9/24
2013/10/22
2013/11/19
2013/12/17
2014/1/14
2014/2/11
2014/3/11
2014/4/8
2014/5/6
2014/6/3
2014/7/1
2014/7/29
2014/8/26
0
200
400
600
800
1000
1200
1400
1600
1800
2000
建屋内滞留水貯蔵量(①)
廃液供給タンク、SPT(B)(②)
処理水タンク貯蔵量(④)
貯蔵量増加量(①+②+④)
その他移送量除く貯蔵量増加量(①+②+④-※)
浪江降水量*
滞留水貯蔵量
平均の日増加量/浪
万m3
m3/日mm/週
Water in buildings (a)Water in buffer tanks (b)Water in storage tanks (c)Increased volume of stored waterIncreased volume excluding artificial inflowRainfall
olum
e (1
0 th
ouda
nd m
3 )
m3 /d
ay),
rainfa
ll (m
m/w
eek)
2-3. Stored water volumeS
tore
d w
ater
vol
ume
(thou
sand
m3 )
200
300
400
500
600
700
Incr
ease
rate
(m3 /d
ay),
Rai
nfal
l (m
m/w
eek)
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 7
Unit 1 Unit 2 Unit 3 Unit 4
Urgent① Ground improvement/pumping groundwater/ facing
Fundamental a)Seaside impermeable wall
Fundamental c) Sub-drain
Urgent② Removing contaminatedwater from trench
-Stopping flow to the port ① Ground improvement/pumping groundwater/paving at contaminated area<Leakage prevention> <Contaminant isolation>
-Elimination of pollution source ② Removing contaminated water from trench <Contaminant removal>-Suppression of contaminated water increase ③ Pumping up groundwater from hillside(groundwater bypass) <Contaminant isolation>
-Stopping flow to the port ① Ground improvement/pumping groundwater/paving at contaminated area<Leakage prevention> <Contaminant isolation>
-Elimination of pollution source ② Removing contaminated water from trench <Contaminant removal>-Suppression of contaminated water increase ③ Pumping up groundwater from hillside(groundwater bypass) <Contaminant isolation>
- Stopping flow to the ocean a) installing seaside impermeable wall <Leakage prevention>- Suppression of contaminated water increase/ stopping flow to the port b) installing landside frozen soil wall (“Ice wall”)
< Contaminant isolation>- Reducing groundwater flow into reactor facilities etc. c) pumping up groundwater through “Subdrain” <Contaminant isolation>
- Stopping flow to the ocean a) installing seaside impermeable wall <Leakage prevention>- Suppression of contaminated water increase/ stopping flow to the port b) installing landside frozen soil wall (“Ice wall”)
< Contaminant isolation>- Reducing groundwater flow into reactor facilities etc. c) pumping up groundwater through “Subdrain” <Contaminant isolation>
Fundamental measures
Urgent measures
3-1. Measures against contaminated water
(c) GeoEye/Japan Space Imaging CorporationUnauthorized copying and replication of the contents are strictly prohibited. All Rights Reserved. Tokyo Electric Power Company
Fundamental b) Frozen soil wall (“Ice wall”)
Urgent③ Groundwater bypass
After confirmation of pumping up, purification and discharge, due to be closed.
Construction started in June.Due to start freezing in FY2014.
Pumping up, purification and discharge of ground water planned
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 8
3-2. Emergency measures
•Emergency measure(2) Improve ground at the contaminated area with water glass, pave the ground surface with asphalt and pump up groundwater. [Isolation], [Leakage prevention]
•Emergency measure (1)Eliminate highly contaminated water in trenches. [Removal]
•Emergency measure (3)Pump up groundwater from
the mountain side (groundwater bypass)
[Isolation]
• April 9,2014, pumping up ground water at the wells was started.
•Groundwater pump up•(Groundwater bypass)
•Pump-up well•Sub drain
•Water level
•Reactor Building
•Turbine Building
•Pump-up well
•Pump-up
Improve ground and pump up groundwater Pave ground surface with asphalt to curb rainwater
infiltration
Improve ground and pump up groundwater Pave ground surface with asphalt to curb rainwater
infiltration
•Trench
•Groundwater drain pump-up
•Sea level
•Sub drain
•Pump-up
•Isolation of water from the contamination source
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 9
3-3. Fundamental measures•Fundamental Measure(4) Pump up
groundwater by sub-drains. [Isolation]
•Fundamental Measure (6) Install the frozen-soil wall to curb increase contaminated water generated by groundwater flowing into buildings. [Isolation]
•Fundamental Measure (5) Install the ocean-side impermeable walls. [Leakage prevention]
•Pump-up well
•Water level
•Pump-up•Pump-up
•Sub drain
•Groundwater drain pump-up
•Reactor Building
•Turbine Building
•Sub drain
Freezing began in March, 2015. [Supported by METI]
Freezing began in March, 2015. [Supported by METI]
•Isolating water from the contamination source
•Sea level
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 10
4-1. Operation of groundwater bypass
To reduce groundwater inflow into buildings, groundwater is pumped up at the hillside of the buildings and discharged into the ocean after conducting rigorous radioactive analysis.
It is expected that the amount of inflow into the buildings is to be reduced by tens tons of water.
After getting approval from relevant stakeholders, some groundwater have already discharged several times in batches (approx. 28,000m3 by Aug.25).
To reduce groundwater inflow into buildings, groundwater is pumped up at the hillside of the buildings and discharged into the ocean after conducting rigorous radioactive analysis.
It is expected that the amount of inflow into the buildings is to be reduced by tens tons of water.
After getting approval from relevant stakeholders, some groundwater have already discharged several times in batches (approx. 28,000m3 by Aug.25).
Overview of Groundwater bypass system
Cs134 1 Bq/L or less
Cs137 1 Bq/L or less
Gross β 5 Bq/L or less
H3 1,500 Bq/L or less
Operational Targets for Discharge
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 11
4-2. Facilities of groundwater bypass
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 12
4-3. Operation of groundwater bypass
OP9m
OP10m
Well
Well
Well
Well
Well
Pumped up volume
Rainfall
Water level of well
Water level of observation borehole (A,B)
Water level of observation borehole (C)
Rai
nfa
ll (m
m)
Wat
er
leve
l (m
)W
ater
leve
l (m
)W
ater
leve
l (m
)
Commissioning Operation Wat
er
volu
me m
3/da
y
Mar. 1 Apr. 1 May 1 Jun. 1 Jul. 1 Aug. 1
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 13
Seaside impermeable wall is to surround the sea bank of unit 1 through 4 with steel pipe. Currently landfill work between the seat pile and sea bank is underway.
Remaining opening section is planned to be closed after water purification and transfer is confirmed to work stably.
Seaside impermeable wall is to surround the sea bank of unit 1 through 4 with steel pipe. Currently landfill work between the seat pile and sea bank is underway.
Remaining opening section is planned to be closed after water purification and transfer is confirmed to work stably.
Construction the wall
Inside wall
5. Construction of seaside impermeable wall
Groundwater drain
Transfer pipe
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 14
6-1. Pumping up groundwater from groundwater drain and sub-drain systems
Groundwater levelReactor building
Turbine building
Sub-drainGroundwater bypass
Groundwater drainUpper permeable layer
Lower permeable layer
Aquiclude
Aquiclude
Seaside impermeable wall
The well placed on the seaside (groundwater drain) pumps up groundwater flowing to the sea.
Flow of groundwater will also be reduced by the upper-stream well around the buildings (sub-drain).
Since pumping up through sub-drain greatly reduces the amount of groundwater flowing into the reactor facilities, consequently the increasing rate of highly contaminated water stored at the site will be reduced, reducing risks of ocean contamination.
The well placed on the seaside (groundwater drain) pumps up groundwater flowing to the sea.
Flow of groundwater will also be reduced by the upper-stream well around the buildings (sub-drain).
Since pumping up through sub-drain greatly reduces the amount of groundwater flowing into the reactor facilities, consequently the increasing rate of highly contaminated water stored at the site will be reduced, reducing risks of ocean contamination.
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 15
6-2.Effect of pumping up from sub-drain
Pumping
Contaminated water accumulated
in the building
Reactor building
Water level decline
Current After operation of sub-drain
Sub-drain
Inflow of groundwater: small
Contaminated water accumulated in the
building
Reactor building
Sub-drain
Inflow of groundwater: large
Sub-drain pumping will lower groundwater level around the reactor facilities. Especially, as the difference of water levels inside and outside the buildings is 4 – 5 meters at the mountain side, it is estimated to be able to reduce water amount of 200m3/day by the operation of the sub-drain system. Therefore, reducing groundwater inflow will consequently lead to reducing the increasing rate of contaminated water stored at the site.
Sub-drain pumping will lower groundwater level around the reactor facilities. Especially, as the difference of water levels inside and outside the buildings is 4 – 5 meters at the mountain side, it is estimated to be able to reduce water amount of 200m3/day by the operation of the sub-drain system. Therefore, reducing groundwater inflow will consequently lead to reducing the increasing rate of contaminated water stored at the site.
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 16
6-3. Discharge of purified groundwater
Unit 1 Unit 2 Unit 3 Unit 4
Purification
Discharge to port
Pumping-up(Subdrain)
Water collecting
tank
Temporary storage tank
Pumping-up(Groundwater drain)
The purified groundwater will be discharged to inside of port after confirming it meets the water quality standards (management objective) set by groundwater bypass.
Discharge will not be carried out without the understanding of such stakeholders as the relevant ministries and the fishermen.
The purified groundwater will be discharged to inside of port after confirming it meets the water quality standards (management objective) set by groundwater bypass.
Discharge will not be carried out without the understanding of such stakeholders as the relevant ministries and the fishermen.
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 17
7-1. Frozen soil wall The walls surround the buildings with frozen soil and reduce groundwater inflow into them. Test at the site was conducted, and the formation of expected ice wall was confirmed. Freezing pipes are being installed and it is aimed at starting freezing the soil by next March.
The walls surround the buildings with frozen soil and reduce groundwater inflow into them. Test at the site was conducted, and the formation of expected ice wall was confirmed. Freezing pipes are being installed and it is aimed at starting freezing the soil by next March.
Freezing plant
-Total length; 1,500m-Amount of soil to be froze; 70,000m3
Ice wall
Ice wall (30 m deep)permeableimpermeable
Overview and cross-section of ice wall
① ② ③ ④⑤⑥
Japan Space Imaging Inc., (C)DigitalGlobeSmall scale test
test for ground water controlIce wall
Coolant circulation pipes
Wells for freezing pipes
(Frozen soil)
Chunk of frozen soil
Ground-water level T/BR/B
Feasibility study
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 18
7-2. Groundwater flow after installation of frozen soil wall
Seaside impermeable wall
Frozen soil wall (“Ice wall”)
As a fundamental measure, we are constructing the frozen soil wall around Units 1 to 4, as well as pumping groundwater through sub-drain and closing the impermeable wall. The construction started in June, 2014, and freezing is scheduled to start by next March.
The “Frozen soil wall” will prevent groundwater from flowing into the buildings, instead making it flow around the Units 1 to 4 buildings and lead to the sea.
Since flow of underground water around Units 1 to 4 will be greatly reduced if the “Frozen soil wall” operates, the amount of water pumped up by sub-drain will also be greatly reduced.
Amount of water pumped up through groundwater drain will also be reduced since flow of groundwater to the seaside impermeable wall will be greatly reduced after the start of “Frozen soil wall” operation.
As a fundamental measure, we are constructing the frozen soil wall around Units 1 to 4, as well as pumping groundwater through sub-drain and closing the impermeable wall. The construction started in June, 2014, and freezing is scheduled to start by next March.
The “Frozen soil wall” will prevent groundwater from flowing into the buildings, instead making it flow around the Units 1 to 4 buildings and lead to the sea.
Since flow of underground water around Units 1 to 4 will be greatly reduced if the “Frozen soil wall” operates, the amount of water pumped up by sub-drain will also be greatly reduced.
Amount of water pumped up through groundwater drain will also be reduced since flow of groundwater to the seaside impermeable wall will be greatly reduced after the start of “Frozen soil wall” operation.
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 19
8-1. Removing contaminated water from the Seawater Piping Trench
Unit 2 seawater piping trench
Unit 3 seawater piping trench
Shaft A
Shaft B Shaft C
Shaft D
Tunnel B
Tunnel A
Open‐cut duct
Shaft A
Shaft B Shaft C
Shaft D
N
Unit 2 turbine building Unit 3 turbine building
Blocked
Seawater piping trench of Unit 2 and 3 contains highly contaminated water which came from turbine buildings just after the accident.
To prevent from leaking to ocean, this contaminated water will be removed from the trench.
Seawater piping trench of Unit 2 and 3 contains highly contaminated water which came from turbine buildings just after the accident.
To prevent from leaking to ocean, this contaminated water will be removed from the trench.
: Planned freezing areas
Volume of water in Trench (m3)
Unit 2 5,000Unit 3 6,000
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 20
Freezing the connection to the turbine building
Transfer of contaminated water inside the trench
Injection of coolant in the trench and shafts
Unfreezing the connection to the building and injecting coolant
1
2
3
4
O .P .+1 0 m
1
23
3 2
4
配管
立坑
立坑
トンネル
ケーブルトレイ
P
タービ
ン建屋
滞留水水位O .P .約+3 m
O .P .+7 .4 m
:充填範囲
8-2. Removing contaminated water from the Seawater Piping Trench
【Steps involved in the measure for removing contaminated water from seawater piping
trenches】
O.P. +3.8m
O.P. -0.6m
Connection
O.P. -12.0m
O.P. 2.7-3.1m
Seawater piping trench cross section
O.P. +10.0m
Approx. 70m
: Scope of coolant injection
Turbine bu
ilding
Shaft Cable tray
Level of remaining water
Shaft
TunnelDuct
The connections between the turbine building and seawater piping trenches are separated by a wall, but ducts, etc. penetrate the wall and the remaining water is able to travel between the turbine building and seawater piping trenches.
To remove the contaminated water, the feasibility of creating an ice wall is being examined as a means to separate the turbine building from the seawater piping trenches and thereby stop the flow of water.
The connections between the turbine building and seawater piping trenches are separated by a wall, but ducts, etc. penetrate the wall and the remaining water is able to travel between the turbine building and seawater piping trenches.
To remove the contaminated water, the feasibility of creating an ice wall is being examined as a means to separate the turbine building from the seawater piping trenches and thereby stop the flow of water.
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 21
To be surveyed
Tons of Inflow from the connected duct to HTI (High Temperature Incinerator) building was identified and water stop work was completed this March.
Under construction
No inflow:
Water stop completed
9. Water stop of connection between trench and building
Accumulated water
TrenchBuilding wall
Bedding
▽Groundwater level
▽GL
Radionuclide concentration > 103Bq/cm3
Radionuclide concentration > 102Bq/cm3
Radionuclide concentration > 101Bq/cm3
Empty
Unknown
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 22
10. Facing
建屋
降雨
フェーシングImprovement of air dose rate
Lower the groundwater level
①
②
RainfallFacing
buildings
Objectives of facing- To improve air dose rate in the site- To lower the groundwater level, consequently to reduce inflow to buildings
Objectives of facing- To improve air dose rate in the site- To lower the groundwater level, consequently to reduce inflow to buildings
complied with
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 23
5,6号機放水口北側
1
10
100
1000
10000
100000
1000000
10000000
11/3
/20
11/5
/19
11/7
/18
11/9
/16
11/1
1/15
12/1
/14
12/3
/14
12/5
/13
12/7
/12
12/9
/10
12/1
1/9
13/1
/8
13/3
/9
13/5
/8
13/7
/7
13/9
/5
13/1
1/4
14/1
/3
14/3
/4
14/5
/3
14/7
/2
I-131Cs-134Cs-137
(Bq/L)
<Reference> Notified concentrations (Concentration limits for water outside environmental monitoring area)・Cesium 137: 90 Bq/L・Cesium 134: 60 Bq/L
南放水口付近
1
10
100
1000
10000
100000
1000000
10000000
11/3
/20
11/5
/19
11/7
/18
11/9
/16
11/1
1/15
12/1
/14
12/3
/14
12/5
/13
12/7
/12
12/9
/10
12/1
1/9
13/1
/8
13/3
/9
13/5
/8
13/7
/7
13/9
/5
13/1
1/4
14/1
/3
14/3
/4
14/5
/3
14/7
/2
I-131Cs-134Cs-137
(Bq/L)
物揚場前
1
10
100
1000
10000
100000
1000000
10000000
11/3
/20
11/5
/19
11/7
/18
11/9
/16
11/1
1/15
12/1
/14
12/3
/14
12/5
/13
12/7
/12
12/9
/10
12/1
1/9
13/1
/8
13/3
/9
13/5
/8
13/7
/7
13/9
/5
13/1
1/4
14/1
/3
14/3
/4
14/5
/3
14/7
/2
I-131Cs-134Cs-137
(Bq/L)
シルトフェンス設置:4/11~4/14
11-1. Radionuclide concentration of seawater
Installation of silt fence: April 11 to April 14
Vicinity of south side of water outlet
North side of water outlets at Units 5 and 6 Front of cargo unloading wharf
Concentration of radioactive materials has been reduced up to one-100,000th to one-1,000,000th as compared to the time right after the accident.Concentration of radioactive materials has been reduced up to one-100,000th to
one-1,000,000th as compared to the time right after the accident.
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 24
11-2. Radionuclide concentration of groundwater around the buildingRecent measurement results (Bq/L)(As of June 10, 2014)
Gross beta : 36H-3: 31 Cs-134: <0.55Cs-137: 0.97
(Collected on Sep.’13)
Gross beta : <21H-3: 150Cs-134: 0.64Cs-137: 1.3
(Collected on Sep.’13)
Gross beta : <21H-3:200Cs-134:<0.37Cs-137:<0.47(Collected on 9/5)
Gross beta : <21H-3: 80,000Cs-134:<0.54Cs-137:<0.52
(Collected onSep.’13)
Collection points
Upper layer
Lower layerGross beta : 5,000 H-3: 2,500Cs-134:<0.73Cs-137:0.98(Collected on Oct.’13)
Gross beta : <24 H-3:20,000Cs-134:<0.36Cs-137:0.66
(Collected on Sep.’13)
Gross beta : 830H-3: 770Cs-134:<0.47Cs-137:<0.60
(Collected on Sep.’14)
Gross beta : <17 H-3: 1,800Cs-134:<0.38Cs-137:<0.44
(Collected onSep.’13)
Gross beta : <18H-3: <7Cs-134:<0.46Cs-137:<0.59
(Collected on Sep.’13)
Gross beta : <18 H-3:200 Cs-134:<0.38Cs-137:<0.45
(Collected on Sep.’13)
Gross beta : <17H-3: 1,100Cs-134:<0.43Cs-137:<0.58
(Collected on Sep.’13)
Gross beta : 8,500 H-3:12,000Cs-134:<0.67Cs-137:<0.74(Collected on Oct.’13)
1T-4
1T-5
Gross beta : <15 H-3: <110Cs-134: <0.26Cs-137: <0.23
(Collected on Apr.’14)
H25J④
1T-6
Gross beta : 13,000 H-3: 3,300Cs-134:<0.82Cs-137:<0.84
(Collected on Dec.’13)
H25J⑦
Gross beta : <17 H-3: 140Cs-134: <0.3Cs-137: <0.3
(Collected on Jun.’14)
Gross beta : <16 H-3: <110Cs-134: <0.4Cs-137: <0.5
(Collected on May,’14)
No.2-4
June 23June 23
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 25
Video about Frozen Soil Wall
Unauthorized duplication, reprint prohibited Tokyo Electric Power Company 26
For more information
Updated information regarding decommissioning is shared on TEPCO website.http://www.tepco.co.jp/en/decommision/index-e.html