current complete streets projects · 2014. 11. 18. · cedar springs complete streets project...

31
Cedar Springs Complete Streets Project Meeting Purpose Receive community feedback on two conceptual design options for the Cedar Springs Complete Street Project

Upload: others

Post on 26-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • Cedar Springs Complete Streets Project Meeting Purpose

    Receive community feedback on two conceptual design options for the Cedar Springs Complete Street Project

  • Meeting Agenda

    Presentation (20 minutes)

    Project background and schedule

    Summary of preferences from previous workshop

    Overview of conceptual design options

    Break Out Session (1 hour)

    Review/Discuss conceptual design options

    Reporting Out (30 minutes)

  • Cedar Springs Project Background

    2012 bond program funding

    Budget: $1,304,100

    Project Limits: Oak Lawn to Douglas

    4 blocks - approx. 2,100 feet

    ROW Width: 60 feet (approx.)

  • Interdisciplinary Project Team

    Planning & Neighborhood Vitality

    Strategic Planning

    City Design Studio

    Transportation Planning

    Public Works

    Streets Services

    Storm Water Management (iSWM)

    DART

  • Project Schedule

    Mar 24, 2014 - Public workshop #1: Preliminary design priorities

    Nov 18, 2014 - Public workshop #2: Conceptual design options

    Next Steps Select preferred option Thoroughfare Plan amendment (if necessary) Engineering design

    Summer 2015 - Public workshop #3: Preliminary engineering design

    Next Steps Final engineering Construction contract award Construction

  • Community Priorities Key Themes From First Public Workshop

    Pedestrian improvements throughout the corridor

    Traffic calming

    Gateway treatments at Oak Lawn & Douglas

    Minimize loss of on-street parking

  • Conceptual Design Stage

    • Focus on overall street design concept and general location of priority design elements/features

    • No specific styles, fixtures or materials selected

    • Rough cost estimates to represent allocation of resources to primary design elements

  • Two Conceptual Design Options 4-Lane Option 3-Lane Option

    Improvements spread between Oak Lawn & Douglas

    Improvements focused between Knight and Reagan

    • Gateway enhancements @ Oak Lawn & Douglas

    • Only Continental crosswalks @ Oak Lawn & Douglas

    • Spot repair of existing sidewalks, ADA ramps, redundant curb cut closures

    • Continuous sidewalk widening, curb reconstruction, ADA ramps, redundant curb cut closures

    • Limited landscaping, seating, mini plazas where space allows

    • Continuous landscape enhancement, mini plazas

    • Continental crosswalks at intersections • Continuous road resurfacing, restriping & Continental crosswalks at intersections

    • Decorative paving and bump-outs @ Knight, Throckmorton & Reagan

    • Decorative paving and bump-outs @ Throckmorton & Reagan

    • Pedestrian lighting • Limited pedestrian lighting

    • Library mini plaza • Library mini plaza

  • 4-Lane Option Plan Douglas to Throckmorton

    Kn

    igh

    t

    Th

    rock

    mo

    rto

    n

  • 4-Lane Option Cross Section Knight To Throckmorton

    Public Right-Of-Way (60’ approx.)

    Lighting and

    landscape buffer

    4’

    Maintain/repair

    existing sidewalk

    4’

    NE Side SW Side

  • 4 Lane Option Plan Throckmorton to Oak Lawn

  • Pedestrian realm to be expanded by about 5’ on both sides of street

    4-Lane Option Cross Section Throckmorton To Reagan

    Angled parking

    Maintain existing sidewalk widths

    8’ 7’

    Angled parking

    Public Right-Of-Way (60’ approx.)

    NE Side SW Side

  • Signalizing Intersections

    Requested locations: Knight and Reagan

    Considerations: Signals at staggered intersections are inherently

    inefficient – could cause drivers to try to beat the light

    Warrant study necessary

    Cost of installation per intersection - $200,000

    Not recommended by staff Maintain existing rectangular rapid flashing signals for

    pedestrian safety

  • Hawk Signals

    Requested location: Reagan

    Considerations:

    Hawk signals are designed for mid-block situations

    They can pose safety concerns if installed at intersections

    Not recommended by staff

    Recommend existing rectangular rapid flashing signals and flashing buttons along crosswalk

  • 3-Lane Option Plan Knight to Throckmorton

  • 3-Lane Option Cross Section Knight To Throckmorton

    5’

    Tree

    &

    Light

    Public Right-Of-Way (60’ approx.)

    5’

    Tree

    &

    Light

    NE Side SW Side

  • 3-Lane Option Plan Throckmorton to Reagan

  • 3-Lane Option Cross Section Throckmorton To Reagan

    Extra buffer for

    parking maneuvers

    Angled parking

    8’ 8’

    Maintain existing

    sidewalk width

    Widened sidewalk,

    enhanced landscaping,

    lighting

    Trees

    &

    lights

    5’

    Public Right-Of-Way (60’ approx.)

    NE Side SW Side

  • 4-Lane Option Cost Breakdown Budget ~$1.3 million

    Gateway treatments @ Oak Lawn, Douglas,

    $253,000 , 19%

    Decorative paving and bumpouts, $286,000 ,

    22%

    Continental crosswalks, $61,000 , 5%

    Sidewalk repair, ADA ramps, curb cut

    closures, $291,000 , 22%

    Landscaping, $66,000 , 5%

    Furnishings, $44,000 , 3%

    Pedestrian lighting & conduit, $165,000 ,

    13%

    Library plaza, $34,000 , 3%

    Drainage & irrigation infrastructure, $110,000

    , 8%

  • 3-Lane Option Cost Breakdown Budget ~1.3 million

    Decorative paving and bumpouts, $198,000 , 15%

    Asphalt repaving, lane restriping,

    Continental crosswalks,

    $105,000 , 8%

    Sidewalk widening, ADA Ramps, curb

    cut closures, $456,000 , 35%

    Landscaping, $104,000 , 8%

    Pedestrian lighting & conduit,

    $83,000 , 6%

    Library plaza, $34,000 , 3%

    Drainage & irrigation infrastructure,

    $138,000 , 10%

    Traffic signal replacement,

    $200,000 , 15%

  • Thoroughfare Plan Amendment

    Necessary for conversion from 4 Lanes to 3 Lanes

    Two Public Hearings required with property owner notification City Plan Commission

    City Council

  • Maintenance

    City will seek to partner with private stakeholders on maintenance of some design elements: Soft landscape

    Benches, trash receptacles

    Gateway markers

    Pedestrian way-finding

    Pedestrian lights

  • Continental crosswalks

    Design Element Examples

  • Decorative Pavement

    Design Element Examples

    Note: This is an example only. No style, material or detailed design choices have been made.

  • Vegetated bulb-outs with native landscaping

    Wider sidewalks

    Benches

    Design Element Examples

    Note: This is an example only. No style, material or detailed design choices have been made.

  • Pedestrian lighting with banners

    Design Element Examples

    Note: This is an example only. No style, material or detailed design choices have been made.

  • Gateway Marker

    Design Element Examples

    Note: This is an example only. No style, material or detailed design choices have been made.

  • Mini Plaza Seating

    Design Element Examples

    Note: This is an example only. No style, material or detailed design choices have been made.

  • Pedestrian Way-finding

    Design Element Examples

    Note: This is an example only. No style, material or detailed design choices have been made.

  • Break Out Work Session

    Discuss conceptual design options

    Identify preferred conceptual design option

    Prioritize desired improvements

    Report out

  • Visit Our Blog Site

    www.dallascompletestreets.wordpress.com