csc track-finder plans for commissioning at bat.904 and point 5 darin acosta university of florida

8
CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

Upload: william-garrison

Post on 17-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5

Darin Acosta

University of Florida

Page 2: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

2 Feb. 2005 Commissioning Meeting 2Darin Acosta, University of Florida

CSC Track-Finder Crate

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

SR /

SP

CC

B

SB

S 6

20 C

ontr

olle

r

Sector Processor

Clock & Control Board

Muon Sorter

From MPC (chamber 4)

From MPC (chamber 3)

From MPC (chamber 2)

From MPC (chamber 1B)

From MPC (chamber 1A)

To DAQ

MS

Interfaces: 180 optical links from 60 EMU peripheral crates (3 fibers/crate) 72 SCSI cables to/from DTTF crates

Single crate system, in production now

Page 3: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

2 Feb. 2005 Commissioning Meeting 3Darin Acosta, University of Florida

Status of Track-Finder Second-generation Sector Processor prototype has

been fully tested, along with a prototype CCB (TTC interface) and Muon Sorter

SP production launched with two pre-production samples

Board manufacture complete and inspected Will be thoroughly tested once successfully assembled

Production & single board tests complete by May ’05 Additional 2 months of testing in U.S. for full Track-

Finder crate tests with Muon Sorter Ready for tests at CERN with full production system by

Aug. ’05 But, the existing 3 prototypes are available for testing

at CERN now Prototype is nearly identical to final design

Page 4: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

2 Feb. 2005 Commissioning Meeting 4Darin Acosta, University of Florida

DT/CSC Integration Tests Two tests have taken place in last 15 months Tested data communication from each Track-Finder to

the other through separate transition cards and cables More sophisticated tests will need to take place in the

future (Bat.904) to test our synchronization procedure, combined Track-Finding, and software integration

Page 5: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

2 Feb. 2005 Commissioning Meeting 5Darin Acosta, University of Florida

CSC TF Used as Trigger at Beam Tests

ME1/1ME1/2ME2/2ME3/2

RPC

Full chain of trigger electronics from detector to TF tested

Page 6: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

2 Feb. 2005 Commissioning Meeting 6Darin Acosta, University of Florida

Scale of Electronic Test at Beam Tests

PC0: ME2/2

PC1: ME1/1 + ME1/2

SP1 SP2CCB MS

Have tested up to 3 peripheral crates (~3 EMU disks) with up to 2 SP’s (260° sectors)

(But with only 4 chambers…)

Page 7: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

2 Feb. 2005 Commissioning Meeting 7Darin Acosta, University of Florida

Track-Finder at CMS Magnet Test CSC system will participate in the CMS magnet

test with a 60° slice of one endcap 36 chambers from

3 stations trigger and readout

cosmic ray hits

CSC TF will provide a cosmic trigger (or can be triggered)

Experience at beam tests very useful Plan smaller slice tests even before magnet

test (March)

ME1 (18 CSC’s)ME2 (9 CSC’s)

ME3 (9 CSCs)

Page 8: CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida

2 Feb. 2005 Commissioning Meeting 8Darin Acosta, University of Florida

Answers to remaining questions Resources required in 904:

Rack space, power, network access, lab bench space for repairs and PC, locked storage for one crate of cards

Interaction with other Sub-Systems, until the end of 2005

EMU (peripheral crates) DT TF GMT and GT DAQ

Contact person Acosta for now, but replaced very soon by CERN-based

postdoc Summary:

Essentially ready for system tests at 904 and SX5 now