crystal river nuclear plant @duke energy 1 crystal river ... · crystal river unit 3 - exemptions...

73
@DUKE ENERGY 1 Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428 Docket 50-302 Operating License No. DPR-72 10 CFR 50.12 March 28, 2014 3F0314-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Subject: Reference: Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and Appendix E to Part 50, Revision 1, and Response to Request for Additional Information CR-3 to NRC letter, "Crystal River Unit 3 - License Amendment Request #315, Revision 0, Permanently Defueled Emergency Plan and Emergency Action Level Scheme, and Request for Exemption to Certain Radiological Emergency Response Plan Requirements Defined by 10 CFR 50," dated September 26, 2013. (ADAMS Accession No. ML13274A584) Dear Sir: In accordance with 10 CFR 50.12, Duke Energy Florida, Inc. hereby submits the response to the Nuclear Regulatory Commission (NRC) request for additional information (RAI) received by email on February 20, 2014, regarding the request for exemption to certain Radiological Emergency Response Plan requirements defined by 10 CFR 50, which were contained in the September 26, 2013 submittal (Reference). Enclosure 1 to this letter provides the RAI response. Enclosure 2 to this letter provides the revised request for exemption to certain Radiological Emergency Response Plan Requirements defined by 10 CFR 50.47 and Appendix E to Part 50. This correspondence contains regulatory commitments identified in Enclosure 3. If you have any questions regarding this submittal, please contact Mr. Dan Westcott, Manager, Nuclear Regulatory Affairs, at (352) 563-4796. I declare under penalty of perjury that the foregoing is true and correct. Executed on March 28, 2014. Since , Pr ect Management and Construction JE/sam Enclosures: 1. Response to Request for Additional Information 2. Request for Exemption to Certain Radiological Emergency Response Plan Requirements Defined by 10 CFR 50, Revision 1 3. Regulatory Commitments xc: NRR Project Manager Regional Administrator, Region 1 /1(1

Upload: others

Post on 20-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

@DUKEENERGY 1Crystal River Nuclear Plant

15760 W. Power Line StreetCrystal River, FL 34428

Docket 50-302Operating License No. DPR-72

10 CFR 50.12

March 28, 20143F0314-01

U.S. Nuclear Regulatory CommissionAttn: Document Control DeskWashington, DC 20555-0001

Subject:

Reference:

Crystal River Unit 3 - Exemptions to Radiological Emergency Response PlanRequirements Defined by 10 CFR 50.47 and Appendix E to Part 50, Revision 1, andResponse to Request for Additional Information

CR-3 to NRC letter, "Crystal River Unit 3 - License Amendment Request #315,Revision 0, Permanently Defueled Emergency Plan and Emergency Action LevelScheme, and Request for Exemption to Certain Radiological Emergency ResponsePlan Requirements Defined by 10 CFR 50," dated September 26, 2013. (ADAMSAccession No. ML13274A584)

Dear Sir:

In accordance with 10 CFR 50.12, Duke Energy Florida, Inc. hereby submits the response to theNuclear Regulatory Commission (NRC) request for additional information (RAI) received by email onFebruary 20, 2014, regarding the request for exemption to certain Radiological EmergencyResponse Plan requirements defined by 10 CFR 50, which were contained in the September 26,2013 submittal (Reference). Enclosure 1 to this letter provides the RAI response. Enclosure 2 tothis letter provides the revised request for exemption to certain Radiological Emergency ResponsePlan Requirements defined by 10 CFR 50.47 and Appendix E to Part 50.

This correspondence contains regulatory commitments identified in Enclosure 3.

If you have any questions regarding this submittal, please contact Mr. Dan Westcott, Manager,Nuclear Regulatory Affairs, at (352) 563-4796.

I declare under penalty of perjury that the foregoing is true and correct. Executed on March 28,2014.

Since

,

Pr ect Management and Construction

JE/sam

Enclosures: 1. Response to Request for Additional Information2. Request for Exemption to Certain Radiological Emergency Response Plan

Requirements Defined by 10 CFR 50, Revision 13. Regulatory Commitments

xc: NRR Project ManagerRegional Administrator, Region 1 /1(1

Page 2: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

DUKE ENERGY FLORIDA, INC.

CRYSTAL RIVER UNIT 3

DOCKET NUMBER 50 - 302 / LICENSE NUMBER DPR - 72

EXEMPTIONS TO RADIOLOGICAL EMERGENCY RESPONSEPLAN REQUIREMENTS DEFINED BY 10 CFR 50.47 AND

APPENDIX E TO PART 50, REVISION 1, AND RESPONSE TOREQUEST FOR ADDITIONAL INFORMATION

ENCLOSURE 1

RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION

Page 3: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 1 of 37

RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION

By letter dated September 26, 2013, Duke Energy Florida, Inc. (DEF) requested exemptions from portions of Part 50 of Title 10 of theCode of Federal Regulations (10 CFR 50) for the Crystal River Unit 3 Nuclear Plant (CR-3) Radiological Emergency Response Plan(ADAMS Accession No. ML13274A584). Specifically, DEF requested exemption from certain emergency plan requirements of 10CFR 50.47(b), 10 CFR 50.47(c)(2), and Section IV to Appendix E of 10 CFR 50. The requested exemptions would allow DEF toreduce emergency plan requirements and subsequently revise the CR-3 Radiological Emergency Response Plan consistent with thepermanently defueled condition of the reactor.

On February 20, 2014, via an e-Mail, the Nuclear Regulatory Commission (NRC) provided a request for additional information (RAI)regarding the proposed exemptions to CR-3. The RAI questions and the CR-3 responses are provided below.

In the NRC RAI questions, the specific portions of the requirement within the regulation from which the exemption is being requestedis depicted in emphasized (bold/strikeout) font. In the tables below, the column titled, "Crystal River Request Wording," indicates CR-3's originally requested exemption as contained in Enclosure 2 of Reference 1. The column, titled, "Past Precedent Wording,"indicates exemptions as previously granted by the NRC for the associated regulation.

RAI-001

10 CFR Crystal River Request Wording Past Precedent Wording50.47(b)(1) Primary responsibilities for emergency response Primary responsibilities for emergency response by

by the nuclear facility licensee and by State and the nuclear facility licensee and by State and locall.oal . -ganizations within the Emergency organizations within t-he- EM..geRcY PlanningPlanning Zonce have been assigned, the Zones have been assigned, the emergencyemergency responsibilities of the various responsibilities of the various supportingsupporting organizations have been specifically organizations have been specifically established,established, and each principal response and each principal response organization has staff toorganization has staff to respond and to respond and to augment its initial response on aaugment its initial response on a continuous continuous basis.basis.

Although formal offsite radiological emergency preparedness (REP) plans have typically been exempted for decommissioning sites,State and local organizations continue to be relied upon for firefighting, law enforcement, ambulance and medical services in supportof the licensee's (onsite) emergency plan. Please provide further justification as to why this requirement would not be applicablebased on the context described above.

Page 4: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 2 of 37

Response to RAI-O01

The intent of the originally requested exemption was to continue to rely on State and local organizations for firefighting, lawenforcement, ambulance, and medical services as needed for events at the site, but without an expected need for theseorganizations for offsite radiological emergency response. Details regarding assistance from offsite organizations are provided in thePermanently Defueled Emergency Plan (PDEP), Revision 0 (contained in Enclosure 3 of Reference 1). However, the past precedentwording also meets this intent. Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50.47(b)(1) inReference 1, to read as shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedent wordingshown above.

RAI-002

10 CFR Crystal River Request Wording Past Precedent Wording50.47(b)(7) Infor-mation is m'adailabe to the public Infor.mation is made available to the public en a

on a periodir, hbasis on how they will be priodic• basis on how they Will be notified andnotified and what thelir initial actions ghould :-what their initial actions should be in anbe in an cmcrg8AncY (e.g., listening to -a local-2 emergency (e.g., listening to a local bronadc-astbroadcast st•atio•-n -:and- remaining indoors), stao and. remaining indoor.s), [T]he principalthe principal points Of c-ontac wi90th the news points of contact with the news media for.m.dia for dissemination of inf•rmation dissemination of information during an emergencyduring an emer-gency (including the physical (including the physical location or locations) areIeGat.n- e ,,,'ates, ..are established in established in advance, and procedures foradvance,.and procedures for.coo•.rdinat coordinated dissemination of information to thediss..'-e-minattion- of ifo,-r.m"ation to the publi.c public are established.are established-.II

10 CFR 72.32(a)(16) states, "Arrangements made for providing information to the public." While CR-3 does not currently have anISFSI, the staff used the regulations and guidance for an ISFSI to inform the previous exemptions granted to decommissioninglicensees to maintain consistency as the licensee transitions through the decommissioning process. Please describe howinformation would be disseminated to the public should an event occur at the CR-3 site.

Page 5: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 3 of 37

Response to RAI-002

DEF maintains a corporate communications organization, which includes a media relations group. News media contacts for CR-3will continue to be maintained and upon an event at the CR-3 site, information will be disseminated to the public and briefings withpertinent media organizations will be conducted per corporate communication protocols.

Since there are no longer any pre-planned actions that the public needs to take as a result of an anticipated emergency at CR-3, it isno longer necessary to pre-plan dissemination of emergency information to the public. The intent of the originally requestedexemption was to discontinue specific emergency response organizational requirements for major interactions with news media.However, the past precedent wording also meets this intent. Therefore, DEF is revising the originally requested exemption fromportions of 10 CFR 50.47(b)(7) in Reference 1, to read as shown in Enclosure 2 of this submittal. The revised request is consistentwith the past precedent wording shown above.

RAI-003

10 CFR Crystal River Request Wording Past Precedent Wording50.47(c)(2) Gcnerally, the plume expesurc pathway EPZ Generally, the plume exposure pathway EPZ for

for nuclear power plantS shall conSiSt of an nucicar power plants shall consist of an areaarcpa about 10 miles (16 kin) in radius and the abhout- 110 Milces (16 kin) in radius and t-heingcstion pathway EPZ s-hall so-nSist of an ingestion pathway EPZ shall consist of an area

area-. ab-out- 50 miles (80 kin) in radius. The abou- --t- -50 M --iles (80 kin) in r-adius. The exact sizeexac~t size and configuration of the EM~ and configur-ation o-f t-he EPZs SUrrounding asurrounding a particular nuclear power particular nuclear power reactor shall bereactor shall be deteFrmined i relationto deterrmnend in relatin to local emergencGyloc~al emergency response needs and r-esponse needs and capabilities as they arec~apabilities as they are affected by rsuch affected by such conditio-ns- as de m-ography,coenditions as demography, topography, land topogr-aphy, land characteristics, access routes-,c~haracteristics acsroutes, and and j Urisd ictio-nal boundaries. The size of theIUrisdictienal onais h ieo h EPZs alsG may be determined on a case-by-caseEPZ~s also mnay be determin-edd on a- Case by basis for gas-cooled nuclear reactors and forcase basis for- gas cooled nuclerr reactors reactors with an authorized power level less thanand for reactors with an aulthorized power 250 MW thermal. The plans for the ingestiolevel less than 250 MW thermal. The plans for pathway shall focus on such actions as arethe ingestion pathway sh-all focr-u-s on such appropriate to protect the foodinstoa2c-tio0an s as :are appropriate to protect the food pathway.ringestion patha.....-_____________________

Page 6: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 4 of 37

This requirement as it relates to gas-cooled nuclear reactors and for reactors with an authorized power level less than 250 MWthermal is not applicable to CR-3, and therefore, does not require exemption. Please remove as a requested exemption or providespecific justification for exemption.

Response to RAI-003

DEF agrees that the portion of 10 CFR 50.47(c)(2) that identifies the requirement for determination of the size of the EmergencyPlanning Zones (EPZs) for gas-cooled nuclear reactors and for reactors with an authorized power level less than 250 MW thermal isnot applicable to CR-3 and is revising the originally requested exemption from portions of 10 CFR 50.47(c)(2) in Reference 1, to readas shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedent wording shown above.

RAI-004

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix The final safety analysis report or the site safety

E, III analysis report for an early site permit thatincludes complete and integrated emergencyplans under § 52.17(b)(2)(ii) of this chapter shallcontain the plans for coping with emergencies.The plans shall be an expression of the overallconcept of operation; they shall describe theessential elements of advance planning that havebeen considered and the provisions that havebeen made to cope with emergency situations.The plans shall incorporate information about theemergency response roles of supportingorganizations and offsite ago•ncei. Thatinformation shall be sufficient to provide assuranceof coordination among the supporting groups andwith the licensee. The site safety analysis reportfor an early site permit which proposes majorfeatures must address the relevant provisions of10 CFR 50.47 and 10 CFR part 50, appendix E,within the scope of emergency preparednessmatters addressed in the major features. Theplansp submitt..ed.a FAU,. .e R : 1-u.jde a Annn..;n!:an

Page 7: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 5 of 37

the elements set out in Section IIl for theemnergencY planning ZOneS (EPZs) to an cxtcntsuffmcicnt to demRonStrate that the plansprovide Feasonable assurancc that adequateprotec-tive measure• S •an and InAlfill be taken inthe event of an emergency._'.

This section of the regulations is not applicable to CR-3, as it applies to only license applicants and therefore does not require

exemption. Please remove as a requested exemption or provide specific justification for exemption.

Response to RAI-004

DEF agrees that this requirement is not applicable to CR-3 and is revising the originally requested exemption from portions of 10CFR 50, Appendix E, III in Reference 1, to identify that no exemption is requested.

RAI-005

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix The applicant's emergency plans shall contain, but The applicant's emergency plans shall contain, but

E.IV.1 not be limited to, information needed to not be limited to, information needed todemonstrate compliance with the elements set demonstrate compliance with the elements setforth below, i.e., organization for coping with forth below, i.e., organization for coping withradiological emergencies, assessment actions, radiological emergencies, assessment actions,activation of emergency facilities and equipment, activation of emergency facilities and equipment,training, maintaining emergency preparedness and training, maintaining emergency preparedness andrecovery, and onsite protective actions during recovery, and "nsitc protective artion. duringhostie anctio.. In addition, the emergency hostil. actio. In addition, the emergencyresponse plans submitted by an applicant for a response plans submitted by an applicant for areactor power reactor operating license under this reactor power reactor operating license under thisPart, or for an early site permit (as applicable) or Part, or for an early site permit (as applicable) orcombined license under 10 CFR Part 52, shall combined license under 10 CFR Part 52, shallco.ntain information needed to dc.mOntrate contain information needed to demonstrate.ompliance with the standa,.s described in compliance with the standards described in§6047(b)1 and they will be evaluated against §50.47(b), and they will be evaluated againstthose standards. those standards.

Page 8: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 6 of 37

The standards in §50.47(b) that have not been exempted remain applicable to CR-3. Therefore, the emergency plans still "shallcontain information needed to demonstrate compliance with the standards described in §50.47(b)." Please provide specificjustification for exempting this requirement or delete these words from the exemption request.

Response to RAI-005

DEF agrees that the PDEP still "shall contain information needed to demonstrate compliance with the standards described in§50.47(b)," and is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV. 1 in Reference 1, to readas shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedence wording shown above.

RAI-006

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix Identification, by position and function to be Identification, by position and function to beE.IV.A.4 performed, of persons within the licensee performed, of persons within the licensee

organization who will be responsible for making organization who will be responsible for makingoffeite dosc projcctiens and a de.r.iptiOR o offsie-dose projections and a description of howhow these p.. jcctio, S will be made and, the these projections will be made and the resultsr'eulte t;an.mi.ttd to State and Iocal transmitted to State and local authorities, NRC,authoritie.NRC, and other appropriate and other appropriate governmental entities.governmental entities.

10 CFR 72.32(a)(9) states: "Information to be communicated. A brief description of the types of information on facility status;radioactive releases; and recommended protective actions, if necessary, to be given to offsite response organizations and to theNRC."

While unlikely or not projected to exceed EPA protective action guidelines, a radiological release reaching beyond the site boundaryis still possible (based on elapsed time since cessation of power operations). Please provide specific justification for exempting thisrequirement.

Response to RAI-006

The intent of the originally requested exemption was to discontinue offsite dose assessment and the transmittal of offsite doseprojection results to offsite agencies, but to maintain the responsibility and process for communicating information on facility statusand onsite radioactive releases (from onsite dose projection results) to offsite response organizations and to the NRC if necessary,

Page 9: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 7 of 37

as defined in the PDEP, Revision 0. Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50,Appendix E, IV.A.4 in Reference 1, to read as shown in Enclosure 2 of this submittal. The revised request is consistent with the pastprecedence wording shown above.

RAI-007

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix The means to be used for determining the The means to be used for determining the

E.IM.B.1 magnitude of, and for continually assessing the magnitude of, and for continually assessing theimpact of, the release of radioactive materials impact of, the release of radioactive materialsshall be described, including emergency action shall be described, including emergency actionlevels that are to be used as criteria for levels that are to be used as criteria fordetermining the need for notification and determining the need for notification andparticipation of local and State agencies, the participation of local and State agencies, theCommission, and other Federal agencies, and the Commission, and other Federal agencies, and theemergency action levels that are to be used for emergency action levels that are to be used fordetermining when and what type of protective determining when and what type of protectivemeasures should be considered within and measures should be considered within andoutside the site boundary to protect health and outside the site boundary to protect health andsafety. The emergency action levels shall be safety. The emergency action levels shall bebased on in-plant conditions and instrumentation based on in-plant conditions and instrumentationin addition to onsite and offsite-monitoring. By in addition to onsite and offsite monitoring. ByJune 20, 2012, for nuclear power reactor June 20, 2012, Wor nu.lear powcr reaGcOtlicensees, these action levels must include hostile Iiccnsees, t.hese atolevels mustinlwud-action that may adversely affect the nuclear power hostile action that may adversely affect theplant. The initial emergency action levels shall be nu.,.a. power plant. The initial emergencydiscussed and agreed on by the applicant or action levels shall be discussed and agreed on bylicensee and State and local governmental the applicant or licensee and State and localauthorities, and approved by the NRC. Thereafter, governmental authorities, and approved by theee.rgency ac-tio-n levels shall be reviewed with NRC. Thereafter, emergency action levels shallthe State and local governme.nt•,,l ahorities on be reviewed with the State and local

._an annu-a-l ba-• -. governmental authorities on an annual basis.

In the EP Final Rule, the Commission defined "hostile action" as, in part, an act directed toward a nuclear power plant or itspersonnel. The staff determined that a decommissioning reactor site would not be characterized as a nuclear power plant in view of

Page 10: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 8 of 37

the risk for offsite radiological consequences. Therefore, CR-3 would not be required to include hostile action in the EALs. Pleaseprovide specific justification for maintaining this requirement.

Maintaining the requirement for the offsite response organizations (OROs) to review the EALs on an annual basis will ensure theproper awareness by OROs of applicable emergency classifications and will also ensure that communications with the properauthorities are maintained based on continued requirement for prompt notification of State and local response organizations in theevent of a classified emergency under §50.47(b)(5). As such, the basis for this requirement remains applicable. Please providespecific justification for exempting this requirement.

Response to RAI-O07

After further consideration of the intent of 10 CFR 50, Appendix E, IV.B.1, DEF agrees that the requirement to include hostile actionsin the Emergency Action Levels (EALs) should be included in the exemption in view of the current risk for offsite radiologicalconsequences. Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.B.1 inReference 1, to read as shown in Enclosure 2 of this submittal. This change will require an update to the Permanently Defueled (PD)EAL Bases Manual, Revision 0 (contained in Enclosure 5 of Reference 1), and an update to the PDEP that will be completed with thePDEP RAI response (regulatory commitment).

The intent of the originally requested exemption was to discontinue the review of the EALs with local governmental authorities on anannual basis as a result of the reduced extent of involvement of local county officials in the CR-3 PDEP. However, based upon thisquestion, DEF understands that this annual review supports proper ORO awareness of applicable classifications and ensurescommunications with proper authorities are maintained based upon the State and local response organization notificationrequirements upheld by CR-3. CR-3 proposes to continue to review EALs with the State of Florida and local governmentalauthorities on an annual basis.

The CR-3 Radiological Emergency Response Plan (RERP) currently defines local government to include Citrus County and LevyCounty, as a result of the need for the public to take protective actions and offsite emergency planning by State and localorganizations. Because it is no longer possible for the radiological consequences of a design basis accident or a credible beyonddesign basis accident at CR-3 to result in radioactive releases which exceed the EPA Protective Action Guides at the site boundary,DEF will only include Citrus County government authorities in the review of EALs, since local support organizations may coordinatewith the Citrus County Emergency Operations Center (EOC).

Based upon the reduced scope of EALs for the permanently defueled facility, the scope of the annual review of EALs is expected tobe reduced (informal mailings, etc.), however this will ensure the proper awareness of the applicable emergency classifications.Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.B.1 in Reference 1, to read

Page 11: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 9 of 37

as shown in Enclosure 2 of this submittal. This change will require an update to the PDEP and will be completed with the PDEP RAIresponse (regulatory commitment).

In addition to the past precedent wording included in RAI-007, "and offsite" is struck through the requested exemption to 10 CFR 50,Appendix E, IV.B.1 in Enclosure 2 of this submittal, since offsite monitoring is no longer applicable. This strikethrough was includedin the Table 1, "EXEMPTIONS FOR CONSIDERATION," contained in the NRC draft Interim Staff Guidance (ISG) documentNSIR/DPR-ISG-02, "Emergency Planning Exemption Requests for Decommissioning Nuclear Power Plants," for 10 CFR 50,Appendix E, IV.B.1.

RAI-008

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix The entire spectrum of emergency conditions that The entire spectrum of emergency conditions that

E.IV.C.1 involve the alerting or activating of progressively involve the alerting or activating of progressivelylarger segments of the total emergency larger segments of the total emergencyorganization shall be described. The organization shall be described. Thecommunication steps to be taken to alert or communication steps to be taken to alert oractivate emergency personnel under each class of activate emergency personnel under each class ofemergency shall be described. Emergency action emergency shall be described. Emergency actionlevels (based not only on onsite and offsite levels (based not only on onsite and effe.iteradiation monitoring information but also on radiation monitoring information but also onreadings from a number of sensors that indicate a readings from a number of sensors that indicate apotential emergency, such as the pr...u.. in potential emergency, such as the pressure incontainment and the r .espon .o.nt.ainment and the Fe. po o.... 4

-m..geR.. orcG Cooling System) for ,-c........Ce Cooling System) fornotification of offsite agencies shall be described, notification of offsite agencies shall be described.The existence, but not the details, of a message The existence, but not the details, of a messageauthentication scheme shall be noted for such authentication scheme shall be noted for suchagencies. The emergency classes defined shall agencies. The emergency classes defined shallinclude: (1) notification of unusual events, (2) alert, include: (1) notification of unusual events, (2) alert,(3) site area emergcncry, and (4) genel (3) site arca emergency, and (4) generalemer-geny of 10 CFR Part 50, Appendix E, emeigency of 10 CFR Part 50, Appendix E,IV.C. 1. These classes are further discussed in IV.C. 1. These classes are further discussed inNUREG-0654/FEMA-REP-1. NUREG-0654/FEMA-REP-1.

Page 12: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 10 of 37

CR-3 requested exemption 10 CFR 50.47(b)(9), "Adequate methods, systems and equipment for assessing and monitoring actual orpotential offsite consequences of a radiological emergency condition are in use". Typical EAL schemes for decommissioning sites donot include use of offsite radiation monitoring information as part of EAL scheme. Please provide justification for maintaining therequirement for use of radiation monitoring information.

Response to RAI-008

The intent of the originally requested exemption was to eliminate the requirement to maintain methods, systems and equipment forassessing and monitoring offsite consequences of a radiological emergency condition, as described in the PDEP, Revision 0.Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.C.1 in Reference 1, toread as shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedent wording shown above.

RAI-009

10 CFR 50 Crystal River Request Wording Past Precedence WordingAppendix A licensee shall have the capability to notify A licensee shall have the capability to notifyE.IV.D.3 responsible State and local governmental responsible State and local governmental

agencies within 4-minutes after declaring an agencies within 4.5-minutes after declaring anemergency. Thc liccnse shall demonstrate emergency. The Iccnsec shall demo-n-stratethat the appropriate govcrnmental auithorities that the aprpiate governmental authoritieshave the caabliyt makc a public. alerting have the capability to make a public alertingand naotfiation decison promptly on beiing and- no-tific~ation decision promptly on beinginformed by the licensee of an emnergency inMformed- by the licensee -of an e-mergencyco.ndtieon. Prior to initial oper-ation greater rol;nddition. Prior toe initial operation greater

than ~ _- 5%o ae hral pwrothe frt than 5% of rated thermal power- of the firstreactor at a steach nuclear power reactor reactor at a site, each nuclear power reactorelic-ensee shall1 d-emonst-r-ate that administrative icepnseep shall demonstrate that administrativeand physical1 memans- have bee-pn e-st-ablis-hed- for and physical means have been established forFalerting and providing prompt inRstrucItions to alerting and proeviding prompt instruc-tions tothe public within the plume exposure pathway the public. within the plume exposure pathwayEPZ. The design objective of the prompt EPZ. The design objective of the promptpublic alert a2nd- notific.ation system shall be to public alert and no-tific-ation system shall be tohave the capability to essentially complete the have;P the capability to essentially complete the.initial alerting and initiate notification of the initfial alerting and initiate notification of thepublic within the plume exposure pathway EPZ public. within the plume exposure pathway EPZ

_______within about 15 minutes. The use of this wit-hin ab-out 15 minutes. The use of this

Page 13: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 11 of 37

alerting and no-tific-a-tion capability Will range.rom|l imnmme iatc • pie ing an a fOI4lC~tli fnl T •in•public (within 1 -5 Minutes of thc timc that Stateand local officials arc notified that a situation

n xI nin r n n u ul r in u Ilr a nn i • Pi m n ni i n i n ng m orn

likely events Where there is substantial timeava lab e or he app op iate gove rnm en t

autoriiesto make a judgment whether or notto activate the pub~lic aller-t and notificationsystem. The allerting and noetific-ationecapability shall additionally includeadministrative and physicsal mneansfoabackup method of public. aller-ting andnotification capable of being used in the eventthe primar-y mnethod of allerting and notificationisn unavail bl d r n an e rg cy to ale rt ornotify all Or por-tions of the plume exposureE=PZ population. The bac2kup mnethod shall

have the csapability to allert and notify thpublic within the plume exposure pathwayE PZ, b ut doe s non-t ne ed to M e et the 15 m inu- tedesign objec-tive for the primary prompt publicalert and notification system. WAhen there Is ad-ecisi-on to ac-tivate the allert and no-tificationsystem, the appropriate governmnentalauthorities wIll deter-mine wvhether to activatethe entire alert and notification systes1imult2aneGously Or in a graduated Or stagedmanner. The responsibility for activating such

- 1 n .. l 1 .4 - - A .. 4 : 1. 4 a t s 6. 4 .. k . E

allerting and mnotifica2 tion capability w ill rangefro~m immed-iate allerting and notification ofthpublic. (within 15 minutes of the time that Stateand local2. o-fficials16 are notified that a situationtexists requiring urgent action) to the m•r.elikely events w~hereP thereP issbstantial timeavailable Ifo the appropriate governmentauthorities to make a judgment whether Or notto activate the public alert and- no-tificationsystem. The alerting and_ notificatiocapability shall ad"ditio1nally includeadmian•i0strMative and physical means foDr abackup method of public almerting anno-tific.-ation capable of being used in the eventthe primary method of alerting and notificationis unavaial during an emergency to alert Ornotify all Or portions of the plume exposureEPZ population. The backup method shallh-ave the c-apability to alert and notify thepublic within the plume exposure pathwayEPZ, but does not need to Meet the 15 minutedesign objective for the prmr 3rmpt public,

alet nd notfi atonsystem . W hen there idecision to activate the ealert and notificationsystem, the appropriate governmentalauthon~riti esa will.. de Pter-Fmine.P wMh.etherf to activate

the entire alert and notification systemsFimulta2neoGusly or n a graduated Or stagedm-anner. The responsibility for activating such

t- n Hk~ I -4 - -A - ^ ;6; 4 t* #', ta n ek '~I- - -

reai with the appr-opr-iate governmentalla FU 0 CI

remain %rith the appFOPFiate gGveFnMPnt;lla u t , . h e .• m. e;autheffties-. authefftws-.

10 CFR 72.32(a)(8) states: "Notification and coordination. A commitment to and a brief description of the means to promptly notifyoffsite response organizations and request offsite assistance, including medical assistance for the treatment of contaminated injuredonsite workers when appropriate. A control point must be established. The notification and coordination must be planned so that

Page 14: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 12 of 37

unavailability of some personnel, parts of the facility, and some equipment will not prevent the notification and coordination. Thelicensee shall also commit to notify the NRC operations center immediately after notifications of the appropriate offsite responseorganizations and not later than one hour after the licensee declares an emergency."

The requirement to maintain the capability to notify the local government agencies (response organizations) is still required under§50.47(b)(5) and has been retained for previous exemption requests. Please provide specific justification for exempting requirementto notify local government agencies.

Response to RAI-009

The intent of the originally requested exemption was to maintain the capability to notify offsite response organizations and requestoffsite assistance, including medical assistance for the treatment of contaminated injured onsite workers when appropriate, asdescribed in the PDEP, Revision 0. A control point is established and the responsibilities for notification and coordination areplanned, as described by the PDEP.

In 1999, the NRC exempted Zion Units 1 and 2 from notifying responsible State and local government agencies within 15 minutes ofan emergency with the commitment to maintain notification of the State of Illinois and Wisconsin within 30 minutes (Reference 3). In1998, the NRC exempted Maine Yankee from notifying responsible State and local government agencies within 15 minutes of anemergency and currently Maine Yankee notifies the Maine State Police within one hour of the declaration of an emergency(Reference 4). Both the Zion and Maine Yankee Emergency Plans notify the NRC operations center immediately after notificationsof the appropriate offsite response organizations and not later than one hour after the licensee declares an emergency. The pastprecedent wording of the exemption to Appendix E, IV.D.3 for Zion and Maine Yankee is the same as the past precedent wordingreferenced in RAI 9.

CR-3 will maintain the capability to communicate with the State Watch Office Tallahassee (SWOT) within 60 minutes after anemergency declaration or a change in classification. The SWOT will assume the responsibility to provide notification to Citrus County(acknowledged by agreements between DEF and Citrus County and also the State of Florida). CR-3 will notify the NRC operationscenter immediately after notifications of the appropriate offsite response organizations and not later than one hour after the licenseedeclares an emergency, as described in the PDEP, Revision 0. This notification and coordination practice is consistent withpractices maintained by Zion and Maine Yankee, which were approved by the NRC. This was the intent of the originally requestedexemption, however based upon this RAI, the text strikeout was incorrect. Therefore, DEF is revising the originally requestedexemption from portions of 10 CFR 50, Appendix E, IV.D.3 in Reference 1, to read as shown in Enclosure 2 of this submittal. Therevised request is consistent with the past precedent wording shown above.

Page 15: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 13 of 37

RAI-01 0

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix A licensee ,n.ite technical support center and A licensee onsite technical suppot center and

E.IV.E.8.a(1) an eFme.rgncy operations facility from which an emer;gency operations facility from whicheffective direction can be given and effective effective direction can be given and effectivecontrol can be exercised during an emergency control can be exercised during an emergency

A designated "facility" needs to be maintained to provide a point for command and control. Please provide specific justification for

elimination of term "facility" or provide substitute terminology as part of exemption request.

Response to RAI-010

The intent of the originally requested exemption was to eliminate the requirement to maintain an onsite technical support center andan emergency operations facility, and maintain a designated onsite facility to provide a point for command and control, as describedin the PDEP, Revision 0. Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E,IV.E.8.a(i) in Reference 1, to read as shown in Enclosure 2 of this submittal. The revised request is consistent with the pastprecedent wording shown above.

RAI-011

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix Vlr a nuclear power reactGo llcensee•sE.IV.E.8.b. emergency operations facility r-equired by

paragraph I a of this. section, either a facilitylocated betweean 10 miles and 25 males of thenuclear poer vreacntr site(s), Or a prmaa,'fcili, locted- less than 10 Miles. f•rm thenuclear- power reactor site(s) and a backupfac-ility located be•,-ee•,, ,,n 10 miles and 25 mn*ilesof the nuclVV•Iear poWer reacto• site(s). Anemergency operations fa,.clity may s.,,, morethan one nuclear power rceactOr site. Alicensee desiring to locate an emergencyoperatiIons facility More than 25 miles frnm anura PGIVIIV l -alll r amI~ sha l ll r-qV~ IIPI F I GF,

Page 16: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 14 of 37

Co-mmissio-n approval by submitting anapp~lication for an amendment to- its liccense.For an cmF-gency opeFations facility locatedMore than 25 miles from a nuclear poweVroaG•tr site, .r viio-n munnst h made forlocating NRC and oeffiite responders closer tot-he nuclear. power reactor site so that NRC andoffsitc responderS can interact face to facewith emergency response perSonnel enteringand leaving the nuclear power reactor- site.ProVisionAs for locating NRC and offsitpresponders cloAser to -a nuclear power reactorsit that is mor than 25 miles fromR theemnergency operations facility must include thefollowing

"A licensee desiring to locate an emergency operations facility more than 25 miles from a nuclear power reactor site shall requestprior Commission approval by submitting an application for an amendment to its license. For an emergency operations facility locatedmore than 25 miles from a nuclear power reactor site, provisions must be made for locating NRC and offsite responders closer to thenuclear power reactor site so that NRC and offsite responders can interact face-to-face with emergency response personnel enteringand leaving the nuclear power reactor site. Provisions for locating NRC and offsite responders closer to a nuclear power reactor sitethat is more than 25 miles from the emergency operations facility must include the following:" is not applicable to CR-3 because theEOF is closer than 25 miles from the site. Please remove this wording from the exemption request or justify why the exemption isneeded.

Response to RAI-01I

DEF agrees that this requirement is not applicable to CR-3 and is revising the originally requested exemption from portions of 10CFR 50, Appendix E, IV.E.8.b in Reference 1, to identify that no exemption is requested.

Page 17: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 15 of 37

RAI-012

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix Provisions for communications with Gent 'u"us Provisions for communications with contiguousE.IV.E.9.a Stateic!cal govcrn.m.nts within the plume State/local governments within the plume

exposure pathway EPZ. Such communication exposure pathway EPZ. Such communicationshall be tested monthly shall be tested monthly

Notification of State and the local governments (response organizations) was retained in previous exemptions under §50.47(b)(5)and as discussed in RAI-010 above. Requirement in Appendix E IV.IV.E.9.a continues to be applicable to ensure that adequate linesof communication are maintained in support of these notifications. Please provide specific justification for exempting this requirementas requested.

Response to RAI-012

The intent of the originally requested exemption was to maintain the capability to notify State and local response organizations withadequate lines of communication to coordinate assistance onsite if required, as described in the PDEP, Revision 0. CR-3 willmaintain the capability to communicate with the State Watch Office Tallahassee (SWOT) within 60 minutes after an emergencydeclaration or a change in classification. The SWOT will assume the responsibility to provide notification to the Citrus County EOC(acknowledged by agreements between DEF and Citrus County and also the State of Florida). Additionally, CR-3 will notifyresources for firefighting, law enforcement, ambulance, and medical services through the established lines of communication. Thiswas the intent of the originally requested exemption, however based upon this RAI, the text strikeout was incorrect. Therefore, DEFis revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.E.9.a in Reference 1, to read as shown inEnclosure 2 of this submittal. The revised request is consistent with the past precedent wording shown above.

RAI-013

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix Provision for communications among the nuclear Provision for communications among the nueleaE.IV.E.9.c power reactor control room, the onsite e-hni-a' power reactor. control room, the on..e

suppo~t center, and the emer-gency operations technical r.,ppeot center, and the eMeFgcncyfacility; and among the nuclear facility, the operations facility; and among the nuclearprincipal State and leaal emergency operations facility, the principal State and local emergencycenters, and the field assessment teams. Such operations centers, and the field Assessmentcommunications systems shall be tested annually. teams. Such communications systems shall be

tested annually.

Page 18: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 16 of 37

DEK's Basis for Requested Exemption states in part, "an onsite facility (whether the control room or a facility similar to the technicalsupport center) would continue to be maintained, from which effective control can be exercised during an emergency." While thebasis for requested exemption indicates that one onsite facility will be maintained, the requested exemption wording infers that twoseparate locations: the nuclear power control room AND an onsite nuclear facility will be maintained to support communications toprinciple offsite emergency operations centers. Please clarify or provide further justification for exemption.

Additionally, please provide specific justification for exempting provisions for communications with "local" emergency operations

centers, as required in §50.47(b)(5).

Response to RAI-013

CR-3 will maintain the capability to communicate with the SWOT from the Control Room. The SWOT will assume the responsibilityto provide notification to Citrus County. The communication with State and Citrus County EOCs will ensure the coordination ofassistance onsite if required. Additional offsite organization contact information will be maintained in the Control Room. The onsitefacility located in the Control Complex (adjacent to the Control Room) will be used as a point of assembly for necessary technicalexpertise to assist the Emergency Coordinator in the assessment, mitigation and response to an emergency, as described in thePDEP, Revision 0. The Control Complex contains commercial telephone lines and intra-plant phones (PAX) and augmented staffresponders will bring radios for onsite communication. Augmented staff responding to the Control Complex will have access to up-to-date technical documentation, including drawings, system information and procedures to enable mitigation planning and support of theControl Room staff.

DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.E.9.c in Reference 1, to read as

shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedent wording shown above.

RAI-014

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix Provisions for communications by the licensee Provisions for communications by the licenseeE.IV.E.9.d with NRC Headquarters and the appropriate NRC with NRC Headquarters and the appropriate NRC

Regional Office Operations Center from the Regional Office Operations Center from thenuclear power reactor control room, the onsite nucl.a. pow.. .. a.to. control Froo., the .. n.,etachnical support center, and the .e...gen.- technical ' upport center, and the cme.genc..per-ati"ne facility. Such communications shall opeoatione-facility. Such communications shallbe tested monthly be tested monthly

Page 19: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 17 of 37

DEK's Basis for Requested Exemption states in part, "an onsite facility (whether the control room or a facility similar to the technicalsupport center) would continue to be maintained, from which effective control can be exercised during an emergency". While thebasis for requested exemption indicates that one onsite facility will be maintained. The requested exemption wording infers that twoseparate locations: the nuclear power control room AND an onsite nuclear facility will be maintained to support communications toprinciple offsite emergency operations centers. Please clarify or provide further justification for exemption.

Response to RAI-014

CR-3 will maintain the capability to communicate with the NRC, via the Emergency Notification System (ENS), from the ControlRoom. DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.E.9.d in Reference 1, to readas shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedent wording shown above.

RAI-01 5

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix In addition, a radiologigc •al rOrPinta-ton training In addition, a radiological orientation training

E.IV.F.1 program shall be made available to local program shall be made available to local servicesservices personnel; e.g., local emergency personnel; e.g., local emergency serviceslGivilservices/Civil Defense, local law enforcement Defense, local law enforcement personnel,-leralpersonnel, loc.al .news media peS..S. ne....s media peron. .

10 CFR 50.47(b)(15) states: "Radiological emergency response training is provided to those who may be called on to assist in anemergency."

10 CFR 72.32(a)(10) states: "Training. A brief description of the training the licensee will provide workers on how to respond to anemergency and any special instructions and orientation tours the licensee would offer to fire, police, medical and other emergencypersonnel."

Local services personnel (i.e., firefighting, local law enforcement and ambulance) expected to respond onsite under the licensee'semergency plan will continue to require some basic knowledge about radiation and the facility to facilitate their timely responseconsistent with §50.47(b)(15), which DEF did not request an exemption from. Please provide justification for exempting thisrequirement, specifically how training to prepare these local services personnel to respond to an event at the CR-3 site will beprovided or why training is no longer deemed necessary.

Page 20: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 18 of 37

Response to RAI-015

The intent of the originally requested exemption was to ensure radiological emergency response training is provided to local servicespersonnel (firefighting, local law enforcement, and ambulance) to prepare these local services personnel to respond to an event atthe CR-3 site, as described in the PDEP, Revision 0. This intent is reflected in the PDEP, Revision 0. Therefore, DEF is revising theoriginally requested exemption from portions of 10 CFR 50, Appendix E, IV.F.1 in Reference 1, to read as shown in Enclosure 2 ofthis submittal. The revised request is consistent with the past precedent wording shown above.

RAI-016

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix Each licensee at each site shall conduct a Each licensee at each site shall conduct aE.IV.F.2.b subsequent exercise of its onsite emergency plan subsequent exercise of its onsite emergency plan

every 2 years. Nuclear pwc-r ;cactor licensees every 2 years. Nu-cear powe-r reactor licen•seesshall submit exerci.. cnrios. under § 50.4 hall1 submit ex.rcise sc.naros. un.. er. 50.4a2t least- 60 days before usMna xrise at leas~t 60 days before use in an exercserequired by this paragraph 2.b. The exercise required by this paragraph 2.b. The exercisemFay be inlud-cdl in t.he full par"tipation may be included in the full pa.ticipation

biennial exe~rcise required by paragraph 2.G. of bienniall execs reuied by paragraph 2.G. ofthissertion. In addition, the licensee shall take thaq Aootin In addition, the licensee shall takeactions necessary to ensure that adequate actions necessary to ensure that adequateemergency response capabilities are maintained emergency response capabilities are maintainedduring the interval between biennial exercises by during the interval between biennial exercises byconducting drills, including at least one drill conducting drills, including at least one drillinvolving a combination of some of the principal involving a combination of some of the principalfunctional areas of the licensee's onsite functional areas of the licensee's onsiteemergency response capabilities. The principal emergency response capabilities. The principalfunctional areas of emergency response include functional areas of emergency response includeactivities such as management and coordination activities such as management and coordinationof emergency response, accident assessment, of emergency response, accident assessment,event classification, notification of offsite event classification, notification of offsiteauthorities, assessment of the onsite an.d -fftite authorities, assessment of the onsite-and-effsiteimpact of radiological releases, protective action impact of radiological releases, protective actionrecommendation development, protective action rcoammendation development, protectiFedecision making, plant system repair and action decision making, plant system repair andmitigative action implementation. During these mitigative action implementation. During these

Page 21: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 19 of 37

drills, activation of all of the licensee's emergency drills, activation of all of the licensee's emergencyresponse facilities (T-echn.cal Support Cente response facilities (Technical Support Center(TSC), Ope.ation, Support Center (OSC), and (TSC), Op-rations Suppo.t Crntcr (OSC), andthe Emcr~gcncy Operations Facility (EOF)) the Emergency Operations Facility (EOF))would not be necessary, licensees would have the would not be necessary, licensees would have theopportunity to consider accident management opportunity to consider accident managementstrategies, supervised instruction would be strategies, supervised instruction would bepermitted, operating staff in all participating permitted, operating staff in all participatingfacilities would have the opportunity to resolve facilities would have the opportunity to resolveproblems (success paths) rather than have problems (success paths) rather than havecontrollers intervene, and the drills may focus on controllers intervene, and the drills may focus onthe onsite exercise training objectives, the onsite exercise training objectives.

While previous exemptions granted by the NRC recognized the need to retain the ability to assess the impact of a radiologicalrelease and promptly communicate with offsite government authorities, the technical basis for evaluating exemption requests toremove formal offsite REP plan requirement assumes that release would not exceed EPA protective action guidelines at the siteboundary or that sufficient time would be available for offsite response organizations to implement offsite protective measures on anad hoc basis. As such, please provide specific justification for DEF's retaining ability for "protective action recommendationdevelopment and protective action decision making," including any agreements with State or local government authorities to retainthese capabilities.

Response to RAI-016

CR-3 recognizes that it is no longer possible for a radiological release from a credible accident to exceed Environmental ProtectionAgency (EPA) protective action guidelines at the site boundary and that sufficient time would be available for offsite responseorganizations to implement offsite protective measures on an ad hoc basis. DEF will not plan to retain the ability for "protectiveaction recommendation development and protective action decision making" and this intent is reflected in the PDEP, Revision 0.Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.F.2.b in Reference 1, toread as shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedent wording shown above.

Page 22: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 20 of 37

RAI-017

10 CFR 50 Crystal River Request Wording Past Precedent WordingAppendix Licensees shall enable any State OF -I-.al Licensees shall enable any State or localE.IV.F.2.e gove..mcnt loWtd .ithin the plume . xp.e..e government catcd wiAthi the plume expoure

pathway-EPZ to participate in the licensee's drills pathway-EPZ- to participate in the licensee's drillswhen requested by such State er-loeal when requested by such State or localgovernment, government.

10 CFR 72.32(a)(12) states: "Exercises. (i) Provisions for conducting semiannual communications checks with offsite responseorganizations and biennial onsite exercises to test response to simulated emergencies. Radiological/Health Physics, Medical, andFire drills shall be conducted annually. Semiannual communications checks with offsite response organizations must include thecheck and update of all necessary telephone numbers. The licensee shall invite offsite response organizations to participate inthe biennial exercise.

ii) Participation of offsite response organizations in biennial exercises, although recommended, is not required. Exercisesmust use scenarios not known to most exercise participants. The licensee shall critique each exercise using individuals not havingdirect implementation responsibility for conducting the exercise. Critiques of exercises must evaluate the appropriateness of the plan,emergency procedures, facilities, equipment, training of personnel, and overall effectiveness of the response. Deficiencies found bythe critiques must be corrected."

While formal REP plans may no longer be required pending granting of exemption request, the licensee's emergency plan will stillretain the requirement to promptly notify State and local government authorities and to identify, and provide orientation training to,local service personnel who may be expected to respond to the CR-3 site in the event of an emergency. Please provide additionaljustification for exempting this requirement, specifically addressing how these elements of the licensee's emergency plan would beperiodically tested.

Response to RAI-017

CR-3 will enable the State of Florida or local government to participate in drills when requested by such State or local government.DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.F.2.e in Reference 1, to read asshown in Enclosure 2 of this submittal. The revised request is consistent with the past precedent wording shown above.

Page 23: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 21 of 37

RAI-01 8

10 CFR 50 I Crystal River Reauest Wordinc I Past Precedent WordinaAppendix Remed, ia.,,•l e..erises will be required if the Remedial exercises will be required if theE.IV.F.2.f emergency plan is not satisfactorl•.Y t,,t. d emergency plan is not satisfactorily tested during

durng the biennial exercise, such that NRC, in the biennial exercise, such that NRC, inconsultation with FEMA, cannot (1) find con.ultatn .i..th PUMA, cannot (1) findrc...ag.ohn.ablc -as...ur.anc.e .that adequate protective reasonable assurance that adequate protectivemoasr•-c cran .2nd w"il be taken in the event oe measures can and will be taken in the event of aa radiological, emcr.gcncY Or (2) deter.mine that radiological emergency or (2) determine that thethe Emergency Response Organization (ER•) Emergency Response Organization (ERO) hashas maintained key skills specific. to maintained key skills specific to emergencyemerg...y response. The extent of State and response. The "xte-nt orf Stame and, lc I

locMal particgipatin inR remedial evercises must participation in remedialerceI must bebe sufficient to s~howA tha aprpiaesfficient to show that aporaecretvcorrective measures,~ hvav been takn measu-res haire been taken regarding theregarding the elements of the plan not properly elements of the plan not properlY tMeste in thetested in the prvo exerises. previous exercises.

10 CFR 50.47(b)(14) states: "Periodic exercises are (will be) conducted to evaluate major portions of emergency responsecapabilities, periodic drills are (will be) conducted to develop and maintain key skills, and deficiencies identified as a result ofexercises or drills are (will be) corrected."

Biennial exercises of the licensee's emergency plan continue to be required and are subject to NRC inspection under §50.47(14). Aremedial exercise, if required, ensures that, an exercise does provide reasonable assurance to the NRC that the license can and willtake adequate protective measures in the event of a radiological emergency. Please provide justification for exempting thisrequirement.

Response to RAI-018

CR-3 recognizes the role that a remedial exercise has, if required, is to provide reasonable assurance to the NRC that the licensecan and will take adequate protective measures in the event of a radiological emergency. This was not the intent of the originalexemption, however remedial exercises will be conducted commensurate with the reduced exercise scenario scope when necessary.Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.F.2.f in Reference 1, toread as shown in Enclosure 2 of this submittal. The revised request is consistent with the past precedence wording shown above.This change will require an update to the PDEP and will be completed with the PDEP RAI response (regulatory commitment).

Page 24: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 22 of 37

RAI-019

10 CFR 50 Crystal River Request Wording Past Precedence WordingAppendix The participation of State and local None.E.IV.F.2.h governments. in 2n m.....ergncy ex.... i- not

required to the extent that the applicant hasidetifcdthese goveFrnAment a2g refausing to

partiailpatc furthcr in mcrgcncy plannnactiVities, pur-sunt to § 50.47(r)(1). In suchc~ases, an exerciste shall be hold Ait theapplic~ant or licrensee and such governmentalentitiOes as elect to par-ticipate in the cmergency

_________planning prOccss._____________________

This section of the regulations applies to an "applicant," and therefore, is not applicable to CR-3, and does not require exemption.Please provide justification for further staff consideration as an exemption.

Response to RAI-019

DEF agrees that this requirement is not applicable to CR-3 and is revising the originally requested exemption from portions of 10CFR 50, Appendix E, IV.E.F.2.h in Reference 1, to identify that no exemption is requested.

RAI-020

10 CFR 50 Crystal River Request Wording Past Precedence WordingAppendix By June 20, 2012, for nucl~ear power reactor By June 20, 2012, for nuclear power reactor

E.IV.x licensees, a range of potec..tive , actions to licensees, a range of pro.tec.ive ac.tions toprotect onsite personnel during hostille action protect onsite personnel during hostile actionmust be developed to ensu-re the continued must be developed to ensure the continueability of the li-enseep to safely shut-do-IwFn- the ability of the iene to safely shu-t dowAn the,.e..tF- and perform the functions of the licensee's re.ac.*tor and- perfo-rm the functions Of theemergency plan. I en.see's emergency plan.

Appendix E.IV.l is applicable only to onsite protective actions during hostile actions, which DEF is requesting to be exempted.However, exemption request retains the statement "and perform the functions of the licensee's emergency plan." Please providerational for retaining this statement and provide context for its applicability.

Page 25: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 23 of 37

Response to RAI-020

DEF agrees that the statement "and perform the functions of the licensee's emergency plan" should be included in the exemption.Therefore, DEF is revising the originally requested exemption from portions of 10 CFR 50, Appendix E, IV.1 in Reference 1, to readas shown in Enclosure 2 of this submittal. This change will require an update to the PDEP and will be completed with the PDEP RAIresponse (regulatory commitment).

RAI-021

The Executive Summary in NUREG-1738 states (in part), "the staffs analyses and conclusions apply to decommissioning facilitieswith SFPs [spent fuel pools] that meet the design and operational characteristics assumed in the risk analysis. These characteristicsare identified in the study as industry decommissioning commitments (IDCs) and staff decommissioning assumptions (SDAs).Provisions for confirmation of these characteristics would need to be an integral part of rulemaking." The IDCs and SDAs are listedin tables 4.1-1 and 4.1-2, respectively, of NUREG-1738. Please explain if/how CR-3 meets each of these IDCs and SDAs, or whythey are not considered applicable.

Response to RAI-021

Results of a comparison of the CR-3 spent fuel pool against the IDCs and SDAs listed in tables 4.1-1 and 4.1-2, respectively, ofNUREG-1738, are shown below.

Table 1: Industry Decommissioning Commitments (IDCs) Comparison

IDC IDC Description CR-3 Alignment with IDCNo.

1. Cask drop analyses will be performed or CR-3 practices align with this commitment.single failure-proof cranes will be in usefor handling of heavy loads (i.e., phase II CR-3 has developed procedures for handling heavy loads that comply withof NUREG-0612 will be implemented). NUREG-0612 guidelines. Heavy load drops (other than spent fuel casks) have

been evaluated and safe load paths developed. These safe load paths areadministratively controlled by operations procedures. These controls are inaccordance with CR-3 Final Safety Analysis Report, Section 9.6.4, "Control ofHeavy Loads Program Description." Currently, the CR-3 Auxiliary BuildingOverhead Crane (FHCR-5), which will be used for lifting spent fuel casks, is not asingle failure proof crane. This crane is administratively controlled so that it willnot be used for cask lifts until required upgrades are completed. These upgrades

Page 26: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 24 of 37

IDC IDC Description CR-3 Alignment with IDCNo.

will be completed before the CR-3 Independent Spent Fuel Storage Installation(ISFSI) project is complete. In accordance with License Amendments #239(ADAMS Accession No. ML11321A165) and #241 (ADAMS Accession No.ML12136A392), CR-3 will complete replacement of FHCR-5 with a single failureproof crane prior to moving a spent fuel shipping cask.

2. Procedures and training of personnel will CR-3 practices align with this commitment.be in place to ensure that onsite andoffsite resources can be brought to bear Consistent with CR-3 Radiological Emergency Response Plan (RERP)during an event, requirements, CR-3 has procedures in place to ensure that onsite and offsite

resources are available and appropriate personnel are trained on the access anduse thereof during an event. The Permanently Defueled Emergency Plan(PDEP), Revision 0 (contained in Enclosure 3 of Reference 1), maintains theserequirements with EM-202, "Duties of the Emergency Coordinator." EM-202 is animplementing procedure identified in Appendix A of the RERP. CR-3 alsomaintains agreements with offsite agencies to ensure additional resources areavailable if needed.

3. Procedures will be in place to establish CR-3 practices align with this commitment.communication between onsite andoffsite organizations during severe PDEP implementing procedure, EM-202, will maintain the requirements thatweather and seismic events, establish the appropriate communication between onsite and offsite organizations

during severe weather and following seismic events. CR-3 maintains separateprocedures to provide information to assist in a site response to violent weather.Should severe weather or a seismic event occur that results in a RERP/PDEPentry, EM-202 directs personnel to establish the necessary communications andmake the appropriate notifications. For example, the Emergency Coordinator(Shift Supervisor) would direct notification of the Emergency ResponseOrganization (ERO), the State of Florida who will notify Citrus County, localresponse organizations if necessary, and the NRC.

4. An offsite resource plan will be developed CR-3 practices align with this commitment.

Page 27: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 25 of 37

IDC IDC Description CR-3 Alignment with IDCNo.

which will include access to portable CR-3 maintains an Off-site Support Directory (OSD). The OSD provides thepumps and emergency power to information necessary to access the necessary offsite resources in a timelysupplement onsite resources. The plan manner. Appropriate station personnel are trained to use the OSD to obtainwould principally identify organizations or offsite resources, when needed, to support onsite activities. The OSD listssuppliers where offsite resources could contacts for government agencies, emergency equipment contacts (e.g., for fuel,be obtained in a timely manner. electrical power, makeup water, firefighting equipment, etc.). It also identifies

private agencies that would be capable of transporting resources when needed.

EM-503, "Conduct of the Emergency Mitigation Coordinator." EM-503 requiresthat the Emergency Mitigation Coordinator make the determination on the needfor off-site resources. Once received on-site, the accident assessment procedureaddressing Contingencies for a Loss of SFP Level will be used for installation andoperation of the off-site equipment.

EM-503 is not listed in the current implementing procedure list contained inAppendix A of the PDEP, however will be added to align with this IDC. Thischange will require an update to the PDEP and will be completed with the PDEPRAI response (regulatory commitment).

5. SFP instrumentation will include readouts The CR-3 design aligns with this commitment.and alarms in the Control Room (orwhere personnel are stationed) for SFP SFP temperature: Independent temperature elements monitor SFPs "A" and "B"temperature, water level, and area that provide inputs to the plant computer. Computer points provide highradiation levels, temperature alarms when the monitored pool reaches 1400F.

SFP level: Independent level transmitters monitor SFP "A" and "B" that provideinputs to level indicators on the Main Control Board (MCB) for continuous levelindication. A high level alarm is received when the monitored pool level reacheselevation 159' and a low level alarm is received when pool level reaches elevation1566". Both alarms annunciate in the Main Control Room for the monitored pool.The lowest Control Room level indication is at elevation 154'.

The Cask Loading Area is monitored by a level switch which provides a high level

Page 28: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 26 of 37

No_ IDC Description CR-3 Alignment with IDCNo.

alarm at elevation 159' and a low level alarm at elevation 157'6". Both alarmsannunciate in the Main Control Room.

There are 2 gates located in the SFP which are normally not installed. One gateisolates the "A" SFP from the "B" SFP and one gate isolates the "B" SFP from theCask Area. If the gates are not installed, any one of the three level instrumentswill provide level monitoring for the entire SFP.

Area radiation levels: Two general area radiation monitors are installed tomeasure radiations levels in the fuel storage area. One is located adjacent to thepools at elevation 149' and the second is located on the SF Handling Bridgedirectly above the SFPs. Both monitors provide local indication and alarms inaddition to indication and alarms in the Main Control Room.

6. SFP seals that could cause leakageleading to fuel uncovery in the event ofseal failure shall be self limiting toleakage or otherwise engineered so thatdrainage cannot occur.

The CR-3 design aligns with this commitment.

The CR-3 SFPs have no gates with seals that could lead to fuel uncovery. Thereare 2 gates located in the SFP which are normally not installed. One gateisolates the "A" SFP from the "B" SFP and one gate isolates the "B" SFP from theCask Area. The two gates are identical in construction. The gates are 28'3-3/8"tall and 39" wide. The bottom of the gate is located at elevation 134', wheninstalled, which is approximately 1' above the top of the spent fuel racks.Therefore, failure or leakage of a SFP gate seal would not allow fuel uncovery.

If failure of a seal were assumed, the design of the gates would significantly limitthe amount of leakage allowed. During installation, the gates are lowered downinto a vertical slot which captures the gate horizontally. A W" gap exists on eachside of the gate to allow for installation. In the event of a seal failure, leakagewould be limited to the amount that could flow though the W" gaps. If a differentialwater level existed across a gate, it is likely that the gate would shift horizontallyto one side of the slot due to the differential pressure across the gate and the W"gap would be eliminated. Therefore, it is concluded that the SFP gate design isalso leak limiting.

Page 29: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 27 of 37

No. IDC Description CR-3 Alignment with IDCNo.

It is likely that the gate between SFP "B" and the cask loading area will be used toload spent fuel into casks to support dry fuel storage. The lowest the cask areawater level can be lowered with the permanently installed equipment is elevation138'4". If the SFPs are at the low level alarm set point of 156'6" and the caskarea gate seals fail, approximately 13,500 gallons of water would drain from thefrom the SFPs to the cask area. This would drop the level in the SFPsapproximately 1'3". Since there is approximately 11,100 gallons per foot in theSFPs, it is concluded that the most credible failure scenario involving a SFP gatewould result in a relatively small change in SFP level.

4 I.

7. Procedures or administrative controls toreduce the likelihood of rapid draindownevents will include (1) prohibitions on theuse of pumps that lack adequate siphonprotection or (2) controls for pumpsuction and discharge points. Thefunctionality of anti-siphon devices will beperiodically verified.

Both design features and administrative controls are provided which reduce thelikelihood of rapid draindown events. Normal SFP level is at 158'6", and the lowlevel alarm is at 156'6". The top of the taller fuel storage rack is at 132'11". Thebottom of the SF pump suction connections to the pools are at 154'2". The lowestdrain point with available alignment to installed pumps is at 138'4" in the SF caskloading area connected to the pools via a gate which is normally open. This drainline is equipped with an anti-siphon vent, but is not functionally tested; the onlyvalve in the anti-siphon line is locked open by procedure. The drain is a 3" pipewhich would limit the rate of SFP draindown. If unmitigated draining were tooccur thru this line, the lowest pool level that could be reached would leaveapproximately 5' of pool level over the fuel storage racks. If draining were tooccur, it would be signaled by three level alarms, two area radiation alarms, andlikely an Auxiliary Building sump alarm that all annunciate in the Control Room.

The cask loading area drain, which is normally isolated by a procedurallycontrolled closed valve, can be connected to a pump in the Demineralized Watersystem for water addition. If this drain is used to draw down the cask loadingarea to load in a cask, the water is transferred by SFP-2 to the SFPs. The SpentFuel Cooling system operating procedure contains a limit and precautioninstructing operators to monitor pool levels and affected tank or system levels,when cross connecting to another system, to prevent inadvertent water transferout of the SFPs.

Page 30: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 28 of 37

IDC IDC Description CR-3 Alignment with IDCNo.

8. An onsite restoration plan will be in place CR-3 practices and design align with this commitment.to provide repair of the SFP coolingsystems or to provide access for makeup The Demineralized Water system provides normal makeup to the SFPs. Thewater to the SFP. The plan will provide system can be used to add inventory without accessing the fuel pool floor.for remote alignment of the makeupsource to the SFP without requiring entry An assessment will be performed to determine the feasibility of repairing anyto the refuel floor, emergent SFP cooling system issues. However if repair is not feasible, CR-3 has

two permanent connection points diverse from the SFP deck for makeupcapabilities to the pool. They are located at valves SFV-122 and SFV-129.These valves are physically located on the 143' and 119' elevation of the AuxiliaryBuilding, respectively, and are diverse/separated from the SFP deck (162'elevation plant datum). Each connection (only one is required to achieve therequired flow) requires the removal of a threaded pipe cap and the installation ofan adapter for hook up to a portable independently powered pump. Either valveis approximately 1000 feet from the expected location of the pump used tomitigate this event; hoses are used to connect the pump to the SF valves. Theadapters are stored within an Emergency Operations Box (EOB) which will keepthem protected and readily accessible during the event. The contents of thisstorage box are periodically inventoried by a CR-3 surveillance procedure toensure the availability of the equipment. The installation of the adapter will begoverned by an Accident Assessment procedure addressing Contingencies forLoss of SFP Level, along with the installation of the hose and operation of thepump.

9. Procedures will be in place to control CR-3 practices align with this commitment.SFP operations that have the potential torapidly decrease SFP inventory. These CR-3 has procedures that stipulate fuel handling activities shall not occur withoutadministrative controls may require a licensed Senior Reactor Operator or Certified Fuel Handler providing oversightadditional operations or management of the activities. Procedures further require that heavy loads (> 2750 pounds) thatreview, management physical presence travel over fuel assemblies in the SFP shall not occur without a Shiftfor designated operations or Supervisor/Certified Fuel Handler providing oversight of the activity and anadministrative limitations such as individual qualified in Radiation Protection on site.restrictions on heavy load movements.

Page 31: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 29 of 37

IDC IDC Description CR-3 Alignment with IDCNo.

See IDC 1 for a description of control of heavy loads and the CR-3 requirementfor a single failure proof crane for fuel cask handling operations.

10. Routine testing of the alternative fuel pool CR-3 practices align with this commitment.makeup system components will beperformed and administrative controls for The CR-3 Fire Protection Program establishes the administrative controls overequipment out of service will be the operability of the fire service pumps similar to the controls established in theimplemented to provide added assurance CR-3 Technical Specifications for accident mitigation systems. Surveillancethat the components would be available, Procedures periodically test pump starting and running, output, fuel supply, andif needed. battery condition. Fire hoses for adding water to the pools are also periodically

checked for integrity.

Page 32: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 30 of 37

Table 2: Staff Decommissioning Assumptions (SDAs) Comparison

SDAINo. SDA Description CR-3 Alignment with SDANo.

1 . Licensee's SFP cooling design will be atleast as capable as that assumed in therisk assessment, includinginstrumentation. Licensees will have atleast one motor-driven and one diesel-driven fire pump capable of deliveringinventory to the SFP.

The CR-3 design aligns with this assumption.

The SFP is a safety related, Seismic Class 1 structure that is sufficiently robust tobe protected from severe environmental challenges. It is located within theAuxiliary Building which is a Class I structure (excluding the steel roof supportstructure) protected from external hazards such as missiles and flooding. TheCR-3 engineering procedure for the condition monitoring of structures providesthe inspection and acceptance criteria to assure design function capability ismonitored under the Maintenance Rule.

The SFP cooling system at CR-3 includes all the basic equipment described inFigure 3.1 of NUREG-1738. There are 2 redundant motor driven pumps, 2redundant heat exchangers, an ultimate heat sink, a demineralized water systemtank for makeup water, a filtration system, and isolation valves. The installed SFpumps are powered from Engineering Safeguards (ES) buses and can besupplied power from an onsite diesel generator upon a loss of offsite power.Motor and diesel driven fire pumps are also available to provide makeup water tothe SFPs.

Spent fuel decay heat is transferred to the original systems used to provide SFcooling. These systems include the Nuclear Services Closed Cycle CoolingWater system (SW) and the Nuclear Services and Decay Heat Seawater system(RW). These systems reject heat to the Gulf of Mexico. These systems include anormal duty pump powered from the plant unit buses and safety relatedemergency duty pumps which are powered from ES buses and can also bepowered from the onsite emergency diesel generator.

Any future changes to the SFP cooling configuration will maintain conformancewith the capabilities assumed in the risk assessment.

The response to IDC 5 describes the SFP temperature and level instrumentationand the associated alarms.

Page 33: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 31 of 37

SDA SDA Description CR-3 Alignment with SDANo.

CR-3 has the fire pump configuration described in this SDA, each rated for 2000gpm at 125 psi, capable of delivering inventory to the SFPs.

2. Walk-downsperformed atoperators.

of SFP systems will be The CR-3 operating procedures and processes align with the intent of thisleast once per shift by the assumption.

Procedures will be developed for andemployed by the operators to provideguidance on the capability and availabilityof onsite and offsite inventory makeupsources and time available to initiatethese sources for various loss of coolingor inventory events.

CR-3 procedures require Operations personnel to record SFP level andtemperature in the Control Room and visually observe the pools at least once pershift. Other SF system operating parameters are recorded once per day duringoperator rounds in the Auxiliary Building where the equipment is located.

CR-3 response procedures do not explicitly identify the time available to initiateactions for loss of cooling or loss of inventory events. Operations personnel areaware of SFP conditions based on the daily plant data report that is part of theshift briefing for each on-coming crew. This data continually informs Operationspersonnel of the relative time to respond to SFP events addressed in AbnormalProcedures (AP) for Loss of SFP Cooling or Refueling Canal/SFP LevelLowering. APs are procedures which once entered are executed expeditiouslyuntil the entry condition is resolved using installed systems, or the conditionsescalate to a severity where additional onsite or offsite resources must beemployed. The calculations described in Enclosure 6 of LAR #315 (Reference 1)demonstrate time available to respond to the full spectrum of possible SFPconditions. Due to the 4.5 years since CR-3 last operated, the remaining lowdecay heat of the fuel provides an abundance of time to respond to anticipatedevents addressed in the response procedures.

In the event of a significant loss of inventory that causes SFP area radiationmonitors to alarm, CR-3 would enter one of two Emergency Action Level (EAL)conditions prompting entry in the PDEP. This requires the EmergencyCoordinator (Operations Shift Supervisor) to assess the situation and providenotification to the State of Florida (who will notify Citrus County), local responseorganizations if necessary, and the NRC within one hour, and the ability toaugment the ERO within 4 hours.

Page 34: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 32 of 37

SDA SDA Description CR-3 Alignment with SDANo.

3. Control Room instrumentation that The CR-3 design aligns with this assumption.monitors SFP temperature and waterlevel will directly measure the parameters The response to IDC 5 describes the SFP temperature and level instrumentationinvolved, and the associated alarms.

Level instrumentation will provide alarms CR-3 will adopt the Permanently Defueled (PD) EALs detailed in Nuclear Energyat levels associated with calling in offsite Institute (NEI) 99-01, "Development of Emergency Action Levels for Non-Passiveresources and with declaring a general Reactors," Revision 6. The EAL entry conditions include detection of a SFP lowemergency. level by a high radiation alarm or an elevated temperature condition that may

warrant declaration of an emergency event (Unusual Event).

Regarding the declaration of a general emergency, it should be understood thatconsistent with the PD EAL scheme, station conditions will not have the capacityto reach any threshold requiring the declaration of a General Emergency.

4. Licensee determines that there are no As described in IDC 7, the lowest drain point with available alignment to installeddrain paths in the SFP that could lower pumps could reduce the SFP levels to 20 feet below the normal pool operatingthe pool level (by draining, suction, or level, which is 5 feet above the top of the fuel storage racks.pumping) more than 15 feet below thenormal pool operating level and that Recovery from draining can be accomplished by either onsite or offsite resources.licensee must initiate recovery usingoffsite sources.

5. Load Drop consequence analyses will be The CR-3 design aligns with this assumption.performed for facilities with non singlefailure-proof systems. The analyses and CR-3 has developed procedures for handling heavy loads that comply withany mitigative actions necessary to NUREG-0612 guidelines. Heavy load drops (other than spent fuel casks) havepreclude catastrophic damage to the SFP been evaluated and safe load paths developed. These postulated load drops dothat would lead to a rapid pool draining not result in catastrophic damage to the SFP. All heavy load lifts (other thanwould be sufficient to demonstrate that casks) and safe load paths are administratively controlled by maintenance andthere is high confidence in the facilities operations procedures.ability to withstand a heavy load drop.

See IDC 1 for a description of control of heavy loads and the CR-3 requirement

Page 35: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 1Page 33 of 37

SDA SDA Description CR-3 Alignment with SDANo.

for a single failure proof crane for fuel cask handling operations.

6. Each decommissioning plant willsuccessfully complete the seismicchecklist provided in Appendix 2B to thisstudy. If the checklist cannot besuccessfully completed, thedecommissioning plant will perform aplant specific seismic risk assessment ofthe SFP and demonstrate that SFPseismically induced structural failure andrapid loss of inventory is less than thegeneric bounding estimates provided inthis study (<1 x10 5 per year includingnon-seismic events).

CR-3 has determined that completion of the seismic checklist contained inAppendix 2B of NUREG-1738 is not required. Checklist Item 10 contains thefollowing potential mitigation measures that may be considered in the event thatthe requirements of the seismic screening checklist are not met at a particularplant.

" Delay requesting the licensing waivers (E-Plan, insurance, etc.) until the plantspecific danger of a zirconium fire is no longer a credible concern.

" Design and install structural plant modifications to correct/address theidentified areas of non-compliance with the checklist. (It must beacknowledged that this option may not be practical for significant seismicfailure concerns.)

* Perform plant-specific seismic hazard analyses to demonstrate that theseismic risk associated with a catastrophic failure of the pool is at anacceptable level. (The exact "acceptable" risk level has not been preciselyquantified but is believed to be in the range of 1x10 5 per year.)

To satisfy the first mitigative measure, CR-3 has completed an analysis thatshows that the surface temperature of the cladding in the SFPs will not exceedthe failure temperature for zirconium following a total loss of water from the pools.This is based on spent fuel conditions on or after September 26, 2013. Asdiscussed below for seismic risk, dropped objects, and other IDC/SDAs discussedin this submittal, the probability of a rapid drain down event is very unlikely.Therefore, CR-3 concludes that a zirconium fire is no longer a credible concern.

The second mitigative measure is not being considered by CR-3.

The third mitigative measure is addressed by existing license and design basisfeatures of the SFP. Currently, CR-3 has no plans to complete a plant specific

Page 36: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 34 of 37

SDAINo_ SDA Description CR-3 Alignment with SDANo.

seismic risk assessment to show compliance with the seismic checklist. CR-3 islocated in a seismically inactive zone and considers the catastrophic failure of theSFP due to seismic activity to be very low risk.

The SFP is designed as a Safety Related, Seismic Class I structure using aconservative ground response (0.05g for an Operating Basis Earthquake and0.1g for a Safe Shutdown Earthquake). The conservative nature of the CR-3design basis seismic loads was recently confirmed when CR-3 received the EPRIsponsored ground motion study completed by Lettis Consultants International,Inc. The "Central and Eastern United States Seismic Source Characterization"document shows a ground motion response spectra (GMRS) that is less than thelicensing basis of the CR-3 Safe Shutdown Earthquake ground response.

With no credible zirconium fire and no credible seismic damage to the SFP,CR-3 concludes completion of the seismic checklist is not required. In addition,CR-3 has procedures in place to ensure successful implementation of mitigationmeasures to supply alternate cooling water using portable equipment. As aresult, no radiological releases with offsite consequence are expected following asevere earthquake.

7. Licensees will maintain a program to CR-3 does not have Boraflex in the spent fuel racks. CR-3 proactively replacedprovide surveillance and monitoring of the "B" Spent Fuel Racks that contained Boraflex in 2000 with racks containingBoraflex in high-density spent fuel racks Boral.until such time as spent fuel is no longerstored in these high-density racks.

RAI-022

The first page of Enclosure 2 includes the statement, "shaded text identifies the extent of the proposed exemption with respect to theregulation." However, no shaded text appears in the table, while it appears that strikeouts are actually used to identify proposedexemption text. Please clarify the use of shaded areas or strikeouts.

Page 37: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 35 of 37

Response to RAI-022

The statement on the first page of Enclosure 2 should have specified "strikeout text identifies the extent of the proposed exemptionwith respect to the regulation." DEF has revised this statement to identify "bold strike out text identifies the extent of the proposedexemption with respect to the regulation" and updated the text for the proposed exemptions to bold strike out text, as shown inEnclosure 2 of this submittal. The bold strikeout text is consistent with the format of the past precedence exemptions provided in theRAI (Reference 2) previously granted by the NRC for the associated regulations. The Enclosure 2 also includes revision bars toidentify the sections of regulation wording with strikeout changes and to identify where the basis for exemption text was modifiedfrom the previous Enclosure 2 included in Reference 1.

RAI-023

Part of the justification for relaxing formal offsite REP plan requirements is based on the ability to perform actions to prevent ormitigate the effects of a zirconium fire at CR-3. Section 3.1.5 of Enclosure 1 to DEK's license amendment request #315, states "Thisanalysis determined the time to heat up adiabatically to 900 degrees Celsius to be 19.7 hours. This result meets the acceptancecriteria. Further, because of the length of time it would take for the adiabatic heatup to occur, there is ample time to respond to anypartial drain down event that might cause such an occurrence by restoring cooling or makeup, or providing spray. As a result, thelikelihood that such a scenario would progress to a zirconium fire is not deemed credible.

Please provide additional information related to:

a. What is the availability of trained personnel to perform the required actions?b. How is the referenced equipment maintained and tested?c. Are there procedures developed to perform this task and how are they controlled?d. Will these procedures and equipment be referenced in the emergency plan since the basis for this exemption, in part, is theexistence of these mitigative strategies?

Response to RAI-023

a. Availability of trained personnel to perform the required actions

The on-shift Plant Operators and other plant personnel are appropriately trained on the various actions to provide makeup to theSpent Fuel Pool (SFP) using procedures that have been in place since August 2005 to respond to the spectrum of conditions thatcould result from a large area fire. A minimum of two trained on-shift individuals will be maintained to perform the requiredactions until all fuel is removed from the pools to storage in an ISFSI. This number of trained personnel are sufficient to performthe required actions necessary to mitigate the conditions.

Page 38: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 36 of 37

b. Referenced equipment maintained and tested

Existing plant systems used for SFP makeup are maintained and tested/surveilled during operation using existing plantprocedures. Governance for SFP abnormal inventory events is provided within CR-3's abnormal procedure for RefuelingCanal/SFP Level Lowering. This procedure provides guidance for inventory make-up to the SFPs using permanent plantsystems. An accident assessment guidance procedure contains instructions for multiple methods to provide inventory controlusing normal make-up through the demineralized water (DW) pumps (required flows < 100 gpm) to significantly larger flowvolume pumps, such as the fire service pumps or the portable independently powered pump. During operator rounds, theperformance of the normal duty DW pumps is routinely monitored. With respect to the fire service and portable independentlypowered pump, performance testing by surveillance procedures is performed to validate their functionality on a regular basis.

c. Procedures developed to perform this task and how they are controlled

The CR-3 procedures that govern the operation of the pool are an operating procedure for the spent fuel cooling system,abnormal procedures for Loss of SFP Cooling and Refueling Canal/SFP Level Lowering and an accident assessment procedureaddressing Contingencies for Loss of SFP Level. These procedures are maintained in accordance with the CR-3 10 CFR 50Appendix B document control process.

d. Referencing these procedures and equipment in the emergency plan

These procedures and equipment are not specifically referenced in the PDEP, but are contained in the PDEP implementingprocedure, EM-503, "Conduct of the Emergency Mitigation Coordinator." For the scenario described, EM-503 would instruct theEmergency Mitigation Coordinator to direct implementation of the accident assessment procedure addressing Contingencies for aLoss of SFP Level. As identified in IDC No. 4, EM-503 is not listed in the current implementing procedure list contained inAppendix A of the PDEP, however will be added to align with this IDC.

Page 39: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 13F0314-01 Page 37 of 37

References:

1. CR-3 to NRC letter, "Crystal River Unit 3 - License Amendment Request #315, Revision 0, Permanently Defueled EmergencyPlan and Emergency Action Level Scheme, and Request for Exemption to Certain Radiological Emergency Response PlanRequirements Defined by 10 CFR 50," dated September 26, 2013. (ADAMS Accession No. ML13274A584)

2. NRC to CR-3, e-Mail from C. Gratton (NRC) to D. Westcott (CR-3), "Request for Additional Information: Exemptions to theRadiological Emergency Plan Requirements," dated February 20, 2014.

3. NRC to Zion Nuclear Power Station, Unit Nos. 1 and 2, "Request For Approval of Defueled Station Emergency Plan andExemption from Certain Requirements of 10 CFR 50.47, "Emergency Plans"- Zion Nuclear Power Station, Unit Nos. 1 and 2(TAC NOS MA5253 and MA5254)," dated August 31, 1999. (ADAMS Accession No. 9909070079)

4. NRC to Maine Yankee Atomic Electric Company, "Response to Exemption Request For Portions of Title 10 of the Code ofFederal Regulations Part 50, Appendix E, and Section 50.47 of Title 10 of the Code of Federal Regulations for the Maine YankeeAtomic Power Station (TAC NO. L24661)," dated May 2, 2013. (ADAMS Accession No. ML13112A842

Page 40: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

DUKE ENERGY FLORIDA, INC.

CRYSTAL RIVER UNIT 3

DOCKET NUMBER 50 - 302 / LICENSE NUMBER DPR - 72

EXEMPTIONS TO RADIOLOGICAL EMERGENCY RESPONSEPLAN REQUIREMENTS DEFINED BY 10 CFR 50.47 AND

APPENDIX E TO PART 50, REVISION 1, AND RESPONSE TOREQUEST FOR ADDITIONAL INFORMATION

ENCLOSURE 2

REQUEST FOR EXEMPTION TO CERTAIN RADIOLOGICALEMERGENCY RESPONSE PLAN REQUIREMENTS DEFINED

BY 10 CFR 50, REVISION 1

Page 41: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 1 of 31

REQUEST FOR EXEMPTION TO CERTAIN RADIOLOGICAL EMERGENCY RESPONSE PLAN REQUIREMENTS DEFINED BY 10 CFR 50.REVISION 1

Bold strike out text identifies the extent of the proposed exemption with respect to the regulation. The basis for the exemption explains the scope ofthe exception. The 10 CFR 50.12, "Specific exemptions," provisions with respect to the proposed exemptions are discussed in Section 4.2 ofEnclosure 1.

Reference # Regulation in 10 CFR 50.47 Basis for Exemption

1 10 CFR 50.47(b): The onsite and, exc•pt as provi•dd in Crystal River Unit 3 (CR-3) requests an exemption to the requirementsparagraph (d) of this s. tO.., off.it_ emergency for offsite emergency response plans. Offsite response plans are notresponse plans for nuclear power reactors must meet the necessary because it is no longer possible for the radiologicalfollowing standards: consequences of a design basis accident or a postulated beyond

design basis accident to result in radioactive releases which exceedthe U.S. Environmental Protection Agency's (EPA) Protective ActionGuides (PAGs) at the site boundary.

CR-3 requests exemptions from the regulations to the extent thatthese regulations apply to specific provisions of onsite and offsiteemergency planning that are not applicable to CR-3. Details related tospecific exemption requests are provided below.

2 10 CFR 50.47(b)(1): Primary responsibilities for CR-3 requests an exemption from the regulation requiring theemergency response by the nuclear facility licensee and by assignment of primary responsibilities for emergency response toState and local organizations within the Em.••g.cy State and local organizations within the existing Plume ExposurePlaing Zes have been assigned, the emergency Pathway and Ingestion Exposure Pathway Emergency Planning Zonesresponsibilities of the various supporting organizations (EPZs). Because it is no longer possible for EPA PAGs to behave been specifically established, and each principal exceeded at the site boundary, defined Plume Exposure Pathway andresponse organization has staff to respond and to augment Ingestion Exposure Pathway EPZs are no longer necessary. Lettersits initial response on a continuous basis. of Agreement and conduct of operations with various offsite support

organizations (hospitals, ambulance, fire-fighting and lawenforcement) will be maintained to the extent necessary to supportdefueled conditions. Response may be to the plant or in support oftransport or treatment of contaminated and/or injured individuals. Thenormal station operating staff and Emergency Organization will bereplaced by a Defueled On-Shift Staff and Emergency Organizationwith the capability to respond to declared emergencies on a 24-hourbasis. Minimum on-shift positions will be governed by the CR-3Technical Specifications. Augmented staff will be available to respond

Page 42: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 2 of 31

Reference # Regulation in 10 CFR 50.47 Basis for Exemption

to an emergency.

3 10 CFR 50.47(b)(2): On-shift facility licensee No exemption is requested.responsibilities for emergency response are unambiguouslydefined, adequate staffing to provide initial facility accidentresponse in key functional areas is maintained at all times,timely augmentation of response capabilities is availableand the interfaces among various onsite response activitiesand offsite support and response activities are specified.

4 10 CFR 50.47(b)(3): Arrangements for requesting and CR-3 requests an exemption from the regulation to maintaineffectively using assistance resources have been made, arrangements to accommodate State and local emergency responsearrangement.s to at Stiat and-lol staff , , staff at the Emergency Operations Facility (EOF). Because it is nothe liccnsee's Emerg-..ny Operations Facility have longer possible for EPA PAGs to be exceeded at the site boundary,been-made, and other organizations capable of elimination of the EOF is requested since there will be no need for aaugmenting the planned response have been identified. response by offsite agencies to this facility. The CR-3 emergency plan

will continue to maintain arrangements for requesting and usingassistance resources from offsite support organizations.

5 10 CFR 50.47(b)(4): A standard emergency classification CR-3 requests an exemption from the regulation requiring the onsiteand action level scheme, the bases of which include facility emergency classification and action level scheme information to besystem and effluent parameters, is in use by the nuclear provided in support of initial offsite response measures. CR-3 willfacility licensee, and. Sate- and local response plans cal adopt the Permanently Defueled Emergency Action Levels (EALs)for replancn informin provided by fac.ility detailed in Nuclear Energy Institute (NEI) 99-01, "Development oflicen-•see.. for -detcMination' of minimu.m. initi"al .ff-site Emergency Action Levels for Non-Passive Reactors," Revision 6.rFe.pG.sc mcaurcU . Because it is no longer possible for the radiological consequences of a

design basis accident or a postulated beyond design basis accident atCR-3 to result in radioactive releases which exceed the EPA PAGs atthe site boundary, the need to provide information to State and localresponse organizations for the development of Protective ActionDecisions and offsite emergency planning by State and localorganizations, with currently defined emergency response roles, is nolonger necessary.

6 10 CFR 50.47(b)(5): Procedures have been established for CR-3 requests an exemption from the regulation requiring onsite andnotification, by the licensee, of State and local response State and local offsite emergency plans contain the means to provideorganizations and for notification of emergency personnel early notification and clear instruction to the populace within the Plumeby all organizations; the content of initial and followup Exposure Pathway EPZ. Because it is no longer possible for the

Page 43: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 3 of 31

Reference # Regulation in 10 CFR 50.47 Basis for Exemption

messages to response organizations and-the-publiG has radiological consequences of a design basis accident or a postulatedbeen established; -and m..o.-ans to provide carly beyond design basis accident at CR-3 to result in radioactive releasesn-otific•tion ad c-la- W nat. rUction to the popul.ace within which exceed the EPA PAGs at the site boundary, the need to providethe plume exposurc. pathway Emergency Planning these messages to the public, the need to maintain the Alert andZone have- been establi--h-d. Notification System, the need for the public to take protective actions

and offsite emergency planning by State and local organizations, withcurrently defined emergency response roles, is no longer necessary.

7 10 CFR 50.47(b)(6): Provisions exist for prompt CR-3 requests an exemption from the regulation requiringcommunications among principal response organizations to maintenance of provisions for prompt notification to the public.emergency personnel and tG the public. Because it is no longer possible for the radiological consequences of a

design basis accident or a postulated beyond design basis accident atCR-3 to result in radioactive releases which exceed the EPA PAGs atthe site boundary, the need for prompt notification and supportingsystems, the need for the public to take protective actions and offsiteemergency planning by State and local organizations, with currentlydefined emergency response roles, is no longer necessary.

8 10 CFR 50.47(b)(7): Information is made ava-ilable to CR-3 requests an exemption from the regulation requiring informationthe public On a poridic basis on how they will be be made available to the public on a periodic basis on how they will benot..ificd and what their initial acto.ns sh'uld be in an notified and what their initial actions should be during an emergency.emergecyG (e.g., • li.tenin to a local broadcast station News media contacts for CR-3 will be maintained and upon an eventand r.maini"n indeors), the principal points of contact at the CR-3 site, information would be disseminated to the public andwith the news media for dissemination of information during briefings with pertinent media organizations would be conducted peran emergency (inl•uding the physical" location o corporate communication protocols. Because it is no longer possible-- *ati"ne4-are established in advance, and procedures for for the radiological consequences of a design basis accident or a

coordinated dissemination of information to the public are postulated beyond design basis accident at CR-3 to result inestablished, radioactive releases which exceed the EPA PAGs at the site

boundary, the need to educate the public on what their prompt actionswould be in the event of a radiological emergency is not necessarybecause the need for the public to take protective actions does notexist.

9 10 CFR 50.47(b)(8): Adequate emergency facilities and No exemption is requested.equipment to support the emergency response areprovided and maintained.

10 10 CFR 50.47(b)(9); Adequate methods, systems, and CR-3 requests an exemption from the regulation requiring offsite

Page 44: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 4 of 31

Reference # Regulation in 10 CFR 50.47 Basis for Exemption

equipment for assessing and monitoring actual or potential accident assessment capabilities during an emergency and for theeffsite consequences of a radiological emergency onsite emergency plan to contain established procedures forcondition are in use. coordinating accident assessment capabilities with offsite

organizations. Because it is no longer possible for the radiologicalconsequences of a design basis accident or a postulated beyonddesign basis accident at CR-3 to result in radioactive releases whichexceed the EPA PAGs at the site boundary, there is no need for CR-3to maintain offsite accident assessment capabilities. Since a need formonitoring and assessing no longer exists, CR-3 no longer intends tomaintain the capability to deploy field teams for assessing andmonitoring offsite radiological conditions. The CR-3 PermanentlyDefueled Emergency Plan (PDEP) will continue to maintain onsiteassessment capabilities.

11 10 CFR 50.47(b)(1 0): A raRge of prot-ecttive actions has CR-3 requests an exemption from the regulation requiringbeon devevlpcd for the plume expoeure pathway,. -PZ- development of protective actions for the Plume Exposure Pathwayfor em.gen.y Workers and the public. in d,•vloping and Ingestion Exposure Pathway EPZs. Because it is no longerthis range of actions, consideration has been given to possible for EPA PAGs to be exceeded at the site boundary, the needevac.uation, sheltering, and, as a supplement to these, to provide Protective Action Recommendations (PARs) to State andthe prophylactic use of potassium iodide (KI), as local response organizations for the development of Protective Actionappropriate. E .acuation tim.-e e.tim.ates have be, Decisions, including consideration to evacuation, sheltering, and, as a

delopedby applicants and licensees. License" s supplement to these, the prophylactic use of potassium iodide (KI) isshall update the evacuation time estimates on a no longer necessary. Evacuation of the public and the need toperiodic basis. Guidelines- for the choeie Of protecti;e develop Evacuation Time Estimates (ETEs) is no longer necessary.

acton duin an emergeny cositnt With Federalguidne, arc developed and inplace, and proetectiveac~tions for the ingestion exposre pathway EP-Zappropriate to- t-he loc--ale have been developed.

12 10 CFR 50.47(b)(11): Means for controlling radiological No exemption is requested.exposures, in an emergency, are established foremergency workers. The means for controlling radiologicalexposures shall include exposure guidelines consistentwith EPA Emergency Worker and Lifesaving ActivityProtective Action Guides.

Page 45: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 5 of 31

Reference # Regulation in 10 CFR 50.47 Basis for Exemption

13 10 CFR 50.47(b)(12): Arrangements are made for medical No exemption is requested.services for contaminated injured individuals.

14 10 CFR 50.47(b)(13): General plans for recovery and No exemption is requested.reentry are developed.

15 10 CFR 50.47(b)(14): Periodic exercises are (will be) No exemption is requested.conducted to evaluate major portions of emergencyresponse capabilities, periodic drills are (will be) conductedto develop and maintain key skills, and deficienciesidentified as a result of exercises or drills are (will be)corrected.

16 10 CFR 50.47(b)(15): Radiological emergency response No exemption is requested.training is provided to those who may be called on to assistin an emergency.

17 10 CFR 50.47(b)(16): Responsibilities for plan No exemption is requested.development and review and for distribution of emergencyplans are established, and planners are properly trained.

18 10 CFR 50.47(c)(2): Generally, the plume exposure CR-3 requests an exemption from the regulation requiring definedpathway EPZ for nuclear power plants shall consist of Plume Exposure Pathway and Ingestion Exposure Pathway EPZs.an ar.c..a abo4ut 10 milS (16 kinm) n -adius and the The analysis of the potential radiological impact of an accident for CR-S ngc.StI.. pathway EPZ 'hall c-GonI.sist of an ..... a bout 3 in a permanently defueled condition indicates that any releases50 miles (80 ki) in radiu., Th- exact size and beyond the site boundary are limited to small fractions of the EPAc.onfiguratio. n o^f the EPZs surrounding a particula PAG exposure levels, as detailed in the EPA's "Protective Actionnu..,lear po...er. re^actor shall be dterni,.d in r-.tian Guides and Planning Guidance for Radiological Incidents, Draft forto local , m.rg•nc r. .pons .needs Rnd capabilitics as Interim Use and Public Comment," dated March 2013 (PAG Manual).they are affected by such conditions-as demor•aphy, According to the PAG Manual, "EPZs are not necessary at thosetopography, land chaarateristics, accessn rouites, and facilities where it is not possible for PAGs to be exceeded off-site."jur.isdic.tional b.und.ari• The size of the EPZs also maybe determined on a case-by-case basis for gas coolednuclear reactors and for reactors with an authorized powerlevel less than 250 MW thermal. The plans fCr thei ngestion pathway shall focus on such actions as areappropriate to protect the food ingestion pathway-.

Page 46: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 6 of 31

Reference # Regulation in Appendix E to Part 50 Basis for Exemption

19 10 CFR 50 App E: Ill. The Final Safety Analysis Report; No exemption is requested.Site Safety Analysis ReportThe final safety analysis report or the site safety analysisreport for an early site permit that includes complete andintegrated emergency plans under § 52.17(b)(2)(ii) of thischapter shall contain the plans for coping withemergencies. The plans shall be an expression of theoverall concept of operation; they shall describe theessential elements of advance planning that have beenconsidered and the provisions that have been made tocope with emergency situations. The plans shallincorporate information about the emergency responseroles of supporting organizations and offsite agencies. Thatinformation shall be sufficient to provide assurance ofcoordination among the supporting groups and with thelicensee. The site safety analysis report for an early sitepermit which proposes major features must address therelevant provisions of 10 CFR 50.47 and 10 CFR part 50,appendix E, within the scope of emergency preparednessmatters addressed in the major features. The planssubmitted must include a description of the elements setout in Section IV for the emergency planning zones (EPZs)to an extent sufficient to demonstrate that the plans providereasonable assurance that adequate protective measurescan and will be taken in the event of an emergency.

20 10 CFR 50 App E The scope of the PDEP will not include onsite protective actions during

IV Content of Emergency Plans hostile action. In the Emergency Preparedness (EP) Final Rule

1. The applicant's emergency plans shall contain, but (December 2011), the NRC defined "hostile action" as, in part, an act

not necessarily be limited to, information needed to directed toward a nuclear power plant or its personnel. The NRC

demonstrate compliance with the elements set forth excluded non-power reactors (NPRs) from the definition of "hostile

below, i.e., organization for coping with radiological action." CR-3 should not be required to plan for an offsite impact

emergencies, assessment actions, activation of resulting from "hostile action" because: (1) the facility poses a lower

emergency organization, notification procedures, radiological risk to the public than does a power reactor, and (2) the

emergency facilities and equipment, training, facility has a low likelihood of a credible accident resulting in

I

Page 47: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 7 of 31

maintaining emergency preparedness, recovery, an4 radiological releases requiring offsite protective measures.onsite protective actions during hostile actionI. Inaddition, the emergency response plans submitted byan applicant for a nuclear power reactor operatinglicense under this part, or for an early site permit (asapplicable) or combined license under 10 CFR part 52,shall contain information needed to demonstratecompliance with the standards described in § 50.47(b),and they will be evaluated against those standards.

21 IV. 2 This nuclear power reactor license applicant shall also No exemption is requested. This regulation does not apply to CR-3provide an analysis of the time required to evacuate (intended for nuclear power reactor license applicants).various sectors and distances within the plume exposurepathway EPZ for transient and permanent populations,using the most recent U.S. Census Bureau data as of thedate the applicant submits its application to the NRC.

22 IV. 3 Nuclear power reactOr licn-se_.es shall u-e NRC CR-3 requests an exemption from the regulation requiring the use ofapproved evacuation time estimates (ETE, ) and NRC-approved ETEs and updates to the ETEs in the formulation ofupdates to the ETE6 in the formulation Of ptc•e' tiv' PARs and the requirement to provide ETE updates to State and localaction and shall provide the E..•.- government authorities for use in developing offsite protective actionand ETE updates. to- State and local gove,.menta, strategies. Because it is no longer possible for EPA PAGs to beauthoritie- forF use in developing off.ite PrFotecti, exceeded at the site boundary, EPZs and the associated protective

co,-,n sr,,atege,. actions developed with consideration to ETEs are no longer required.

23 IV. 4 Within 365 days of the later of the date of the CR-3 requests an exemption from the regulation requiring the use ofavailability of th mos•t FRO eet decGnnial cen.us. da:t' NRC-approved ETEs and updates to the ETEs in the formulation offom the- U.S. . Cnsus Bureau Or December 23, 204-1, PARs and the requirement to provide ETE updates to State and localnuclear power reactor ,liensees shall develop an ETE government authorities for use in developing offsite protective actionanalYsi6s usi. thi' deceAnmal d.at. a and wb•m•t "t unde strategies. Because it is no longer possible for EPA PAGs to be§ 60.4 to the NRC. These l-.icensees shall submit th exceeded at the site boundary, EPZs and the associated protectiveETE= analysis to the NRC at least 180 days befor. e using actions developed with consideration to ETEs are no longer required.itGt forFm protective actio ec mmedationst and

providing it to State and lclgvrmental aulthoriticsfor usea in developing offesite protective action• t•v v.., ie . v v w v v v == v . .u . • v . ..

Page 48: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 8 of 31

24 IV 5 Du-rig tho years bet-w;e de.enniall ccnsuscs,i InnuI a power reacto lienee -il esimt tilt-M;!T frj

pcrmancnt residcnt population changes once a ycar,b-ut no later- than 366 days from the datc of thcpr~evious cstimatc, using the mRost Frecent U.S. CcnsusBu-reau annu al resident population estimate andState/local government population data, if availableThese licensecs shall maintain thcsc cstimatcs so thatthcy arc avail-able for- NRC inspection during thc periodbctwecn deccnnial censuscs and shall submit thcscestimates to the NRC with any updated ETE analysis.

CR-3 requests an exemption from the regulation requiring theestimation of EPZ permanent resident population changes once peryear using recent U.S. Census Bureau annual resident populationestimate and State/local government population data. CR-3 alsorequests an exemption to the requirement to maintain estimates forNRC inspection and the requirement to submit estimates and updatedETE analysis. ETEs will no longer be used in the formulation of PARsor to provide ETE updates to State and local government authoritiesfor use in developing offsite protective action strategies. Because it isno longer possible for EPA PAGs to be exceeded at the site boundary,EPZs and the associated protective actions developed withconsideration to ETEs are no longer required.

25 IV A If mt an" time dmirinn the derennhl nerind the FPZ ~----

permanent resident populattion incr-reases such that icýauises- the longest ETE value for the 2 mnile zone OrFmnile zone, including all affected E~mergency ResponsePlanniinn Areast or for the entire 10-miel F=PZ toincrease by 25 percent Or 30 minues, whic.heveless, from the nulear poweFF eacGto licensee'scurrnFtly NRC approved Or updated ETE, the "ienseeshall update the ETE anallysis to reflect the impactothat population ices.The licensee shall submit theupdated ETE analysis to the NR •under § 50.4 no laterthan 365 days after the licnsee's deteormination thatthe criFteriia for updating the ETE have been met and atleast 180 days before using it to form protective ac-t-ionrecommendations and providing itto State and loc-algovernmenltall authorfities f-or use indevelloping offsitennprotectve action sf-trategies

CR-3 requests an exemption from the regulation requiring thecontinuous monitoring of EPZ permanent resident population changesusing recent U.S. Census Bureau annual resident population estimateand State/local government population data and the requirement tosubmit estimates and updated ETE analysis. ETEs will no longer beused in the formulation of PARs or to provide ETE updates to Stateand local government authorities for use in developing offsiteprotective action strategies. Because it is no longer possible for EPAPAGs to be exceeded at the site boundary, EPZs and the associatedprotective actions developed with consideration to ETEs are no longerrequired.

26 IV 7 After an applicant for a combined license under part 52 No exemption is requested. CR-3 is not an applicant for a combinedof this chapter receives its license, the licensee shall license, and therefore, this regulation is not applicable to CR-3.conduct at least one review of any changes in thepopulation of its EPZ at least 365 days prior to itsscheduled fuel load. The licensee shall estimate EPZpermanent resident population changes using the mostrecent U.S. Census Bureau annual resident population

Page 49: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 9 of 31

estimate and State/local government population data, ifavailable. If the EPZ permanent resident populationincreases such that it causes the longest ETE value for the2-mile zone or 5-mile zone, including all affectedEmergency Response Planning Areas, or for the entire 10-mile EPZ, to increase by 25 percent or 30 minutes,whichever is less, from the licensee's currently approvedETE, the licensee shall update the ETE analysis to reflectthe impact of that population increase. The licensee shallsubmit the updated ETE analysis to the NRC for reviewunder § 50.4 of this chapter no later than 365 days beforethe licensee's scheduled fuel load.

27 A OrganizationThe organization for coping with radiological emergenciesshall be described, including definition of authorities,responsibilities, and duties of individuals assigned to thelicensee's emergency organization and the means fornotification of such individuals in the event of anemergency. Specifically, the following shall be included:i

28 A. 1. A description of the normal plant epe~atingorganization.

CR-3 requests an exemption to the term "operating" as it no longerapplies to CR-3. The station will be maintained by a defueled on-shiftstaff.

29 A 2. A description of the onsite emergency response No exemption is requested.organization (ERO) with a detailed discussion of:a. Authorities, responsibilities, and duties of theindividual(s) who will take charge during an emergency;b. Plant staff emergency assignments;c. Authorities, responsibilities, and duties of an onsiteemergency coordinator who shall be in charge of theexchange of information with offsite authorities responsiblefor coordinating and implementing offsite emergencymeasures.

30 A 3. A de,.ript.o., by; position and- f'u'n.ction to hbe CR-3 requests an exemption to the requirement to describepeFf.med, no the li,.en.ee's headquarter. s peronnel headquarters personnel who will be sent to the plant to augment the

h wil .be se.nt to the plant site to a,-•..-e..t the ,te onsite emergency organization. The level of emergency response

Page 50: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 10 of 31

.m..gen.y organization, required by the CR-3 PDEP does not require response byheadquarters personnel. Because it is no longer possible for theradiological consequences of a design basis accident or a postulatedbeyond design basis accident at CR-3 to result in radioactive releaseswhich exceed the EPA PAGs at the site boundary, the need forheadquarters response is no longer necessary.

31 A 4. Identification, by position and function to be performed, CR-3 requests an exemption to the requirement to make offsite doseof persons within the licensee organization who will be projections. The responsibility and process for completing onsite doseresponsible for making-effite dose projections and a projections and the communication of results to State and localdescription of how these projections will be made and the authorities, NRC, and appropriate governmental entities will beresults transmitted to State and local authorities, NRC, and maintained by the PDEP. Offsite emergency response capability is noother appropriate governmental entities. longer appropriate as no design basis accident or postulated beyond

design basis accident can result in radioactive releases which exceedEPA PAGs at the site boundary. The postulated dose to the generalpublic from any credible event would not exceed EPA PAGs.

32 A 5. Id•ntification, by position and function to be CR-3 requests an exemption to the requirement to identify employees,pc."f"med, of other cmployecs of the c.".nscc with other persons or consultants with special qualifications who may bespc.cial, qual.ific.ations for coping with em.ergenc. called upon for assistance. Individuals with special qualifications areconditions that may arise. Other persons with special no longer needed to assist emergency response personnel becausequal-ifications, such as consultants, who are not. no design basis accident or postulated beyond design basis accidentemployees of the ,icc.se .and who m.ay be called upon can result in radioactive releases which exceed EPA PAGs at the sitefor .asi ..tanc. for .em;rgences61 shal a2lo be 5dPntifid, boundary.The speci.alI qualifications of these peFsens shall be

33 A 6. A description of the local offsite services to be No exemption is requested.provided in support of the licensee's emergencyorganization.

34 A 7. By June 23, 2044-, identification of, and a d... iiptiGo CR-3 requests an exemption to the requirement for describingof-the assistance expected from, appropriate State, local, assistance expected from State, local, and Federal agencies withand Federal agencies with responsibilities for coping with responsibilities for coping with emergencies, including hostile action.emergencies, including hostile action at the site. For Since protective actions are no longer needed for the public, thepur-pses of thi. appendix, "hostile action" as defined responding agencies would not have conflicting duties that mayas.. an act dihraected towa.rd. a nu.clea.r .power plant or prevent offsite resources from responding to the site during a hostilepersonnel that icludes the ue of eilent frc;e to action. Offsite emergency response capability is no longer appropriatedet•roy equipment, take hostages, ando. d'ifa.ntimdat as no design basis accident or postulated beyond design basisthe" I...... 6,... p . -.. ... TWA i-- e atta-by '-, accident can result in radioactive releases which exceed EPA PAGs at

Page 51: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 11 of 31

air, land, OF water using guns, expl...i... projctiles, the site boundary. In the EP Final Rule (December 2011), the NRCvehi.k,. , o. other devi.es used to deliverstruc• as. defined "hostile action" as, in part, an act directed toward a nuclearforna power plant or its personnel. The NRC excluded NPRs from the

definition of "hostile action." CR-3 should not be required to plan foran offsite impact resulting from hostile action because: (1) the facilityposes a lower radiological risk to the public than does a power reactor,and (2) the facility has a low likelihood of a credible accident resultingin radiological releases requiring offsite protective measures.

35 A 8. Id-entificration of the State and!or local offic"ias CR-3 requests an exemption to the requirement to identify State or.. sp.nsiblc for planning for, ordering, and controlling local officials responsible for protective actions. Offsite protectiveappropriate protective actions, including evacuations actions are no longer appropriate as no design basis accident orwhen ne...essar.. postulated beyond design basis accident can result in radioactive

releases which exceed EPA PAGs at the site boundary. The need toprovide PARs to State and local response organizations for thedevelopment of Protective Action Decisions and the need to plan for,order and control protective actions, including evacuations, is nolonger necessary.

36 A 9. By De.em.ber 24, 2012, for nuclear powe-r reactr CR-3 requests an exemption to the requirement to complete a detailedlic.ensees, a d.etailedn aanalysi.s demonstrating that on analysis demonstrating that on shift personnel assigned emergencyshift per.sonnel assigned emergency plan plan implementation functions are not assigned responsibilities thatimplementation functions are not assigned would prevent the timely performance of their assigned functions as.responsib iliti that would prevent the timely specified in the emergency plan. In the EP Final Rule (Decemberprfo.rmance of their assigned functions as specified in 2011), the NRC acknowledged that the staffing analysis requirementthe emergency plan. was not necessary for non-power reactor licensees because staffing at

non-power reactors is generally small which is commensurate withoperating the facility in a manner that is protective of the public healthand safety. Because of the slow rate of the event scenariospostulated in the design basis accident and postulated beyond designbasis accident analyses, significant time is available to completeactions necessary to mitigate an emergency without impeding timelyperformance of emergency plan functions.

37 B. Assessment Actions CR-3 requests an exemption to the requirement to use EALs forB. 1. The means to be used for determining the magnitude consideration of protective measures outside the site boundaryof, and for continually assessing the impact of, the release because it is no longer possible for the radiological consequences of aof radioactive materials shall be described, including design basis accident or a postulated beyond design basis accident atemergency action levels that are to be used as criteria for CR-3 to result in radioactive releases which exceed the EPA PAGs atdetermining the need for notification and participation of the site boundary. CR-3 will adopt the Permanently Defueled EALs

Page 52: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 12 of 31

local and State agencies, the Commission, and otherFederal agencies, and the emergency action levels that areto be used for determining when and what type ofprotective measures should be considered within andoutside the site boundary to protect health and safety. Theemergency action levels shall be based on in-plantconditions and instrumentation in addition to onsite andoffaite-monitoring.. By jun 20, 2012, fo. nuclear po..reactor licensees, these a•ctio Ivioov. muvt iudvhostile ac•tin that nay adversely affect the nucl•Mapewe. . pant.-The initial emergency action levels shall bediscussed and agreed on by the applicant or licensee andstate and local governmental authorities, and approved bythe NRC. Thereafter, emergency action levels shall bereviewed with the State and local governmental authoritieson an annual basis.

detailed in NEI 99-01, Revision 6. CR-3 also requests an exemptionfrom the requirement to include "hostile action". In the EP Final Rule(December 2011), the NRC defined "hostile action" as, in part, an actdirected toward a nuclear power plant or its personnel. The NRCexcluded NPRs from the definition of "hostile action." CR-3 should notbe required to plan for an offsite impact resulting from hostile actionbecause: (1) the facility poses a lower radiological risk to the publicthan does a power reactor, and (2) the facility has a low likelihood of acredible accident resulting in radiological releases requiring offsiteprotective measures.

CR-3 proposes to continue to review EALs with the State of Floridaand local governmental authorities on an annual basis. However,based upon the reduced scope of EALs for the permanently defueledfacility, the scope of the annual review of EALs is expected to bereduced (informal mailings, etc.).

38 B.2. A licensee desiring to change its entire emergency No exemption is requested.action level scheme shall submit an application for anamendment to its license and receive NRC approval beforeimplementing the change. Licensees shall follow thechange process in § 50.54(q) for all other emergencyaction level changes.

39 C. Activation of Emergency Organization CR-3 requests an exemption from the requirement to describeC.1. The entire spectrum of emergency conditions that information from containment pressure sensors and the Emergencyinvolve the alerting or activating of progressively larger Core Cooling System (ECCS) System for notification of offsitesegments of the total emergency organization shall be agencies. Because it is no longer possible for the radiologicaldescribed. The communication steps to be taken to alert or consequences of a design basis accident or a postulated beyondactivate emergency personnel under each class of design basis accident to result in radioactive releases which exceedemergency shall be described. Emergency action levels the EPA PAGs at the site boundary, the Permanently Defueled EALs,(based not only on onsite an.d,•ffaite-radiation monitoring detailed in NEI 99-01, Revision 6, will be adopted. This schemeinformation but also on readings from a number of sensors eliminates the Site Area Emergency and General Emergency eventthat indicate a potential emergency, such as the pressUre classifications. Additionally, the need to base EALs on containmentIn c..nt.-ainment and the r.epons. of the Em..genc. pressure and the response of the ECCS is no longer appropriate forCMre Cooling System) for notification of offsite agencies notification of offsite agencies.shall be described. The existence, but not the details, of amessage authentication scheme shall be noted for such

Page 53: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 13 of 31

agencies. The emergency classes defined shall include: (1)Notification of unusual events, (2) alert, (f3)site•a•eae..er.ency, and (4) general emergency. These classesare further discussed in NUREG-0654/FEMA-REP-1.

40 C.2. By June 20, 2012, nuclear power reactor licensees CR-3 requests an exemption from the regulation requiring it maintainshall establish and maintain the capability to assess, the capability to assess, classify and declare an emergency conditionclassify, and declare an emergency condition within. 16 within 15 minutes after the availability of indications to plant operatorsm.nu.e^ after the availability of indications to plant that an EAL has been exceeded and promptly declare the emergency.operators that an emergency action level has been CR-3 will maintain the capability to assess, classify, and declare anexceeded and shall promptly declare the emergency emergency condition. In the permanently defueled condition, thecondition as soon as possible following identification of the rapidly developing scenarios associated with events initiated duringappropriate emergency classification level. Licensees shall reactor power operations are no longer credible. The consequencesnot construe these criteria as a grace period to attempt to resulting from the only remaining events (e.g., fuel handling accident)restore plant conditions to avoid declaring an emergency develop over a significantly longer period. As such, the 15 minuteaction due to an emergency action level that has been requirement to classify and declare an emergency is unnecessarilyexceeded. Licensees shall not construe these criteria as restrictive. The elimination of the time permitted to identify an event ispreventing implementation of response actions deemed by acceptable since there is no need for State or local responsethe licensee to be necessary to P.rtect pub•ic h'alth .nd organizations to implement any protective actions. The 10 CFRsafety provided that any delay in d..l.a'atio"n doe not 50.72(a)(3) requirement to complete an Emergency Notificationdeny the Stat-e and- l-c-al a'- thoities the opper-"unity to System notification of the declaration of an Emergency Class withiniamplement .. ea.e.e nece.sa.y to p.otect the public one hour after the time the licensee declares one of the Emergencyhealth and safety. Classes is not impacted by this exemption. Because it is no longer

possible for the radiological consequences of a design basis accidentor a postulated beyond design basis accident at CR-3 to result inradioactive releases which exceed the EPA PAGs at the siteboundary, and public protective actions are no longer necessary, theneed to identify an emergency within 15 minutes and to promptlyprovide information to the State and local response organizations forthe protection of the public health and safety is no longer necessary.

41 D. Notification Procedures CR-3 requests an exemption from the regulation requiring emergency

D.1. Administrative and physical means for notifying local, plans contain the means to provide early notification to local, State andState, and Federal officials and agencies and agreements Federal officials and agencies for the prompt notification of the publicreached with these officials and agencies fet-he prompt and for public evacuation or other protective measures. Because it islef.e-.Ifon of the public and for Puli,'cA e.ac..Uati or. no longer possible for the radiological consequences of a design basis

other protective.- mea...,ures, should they become accident or a postulated beyond design basis accident at CR-3 to.eesary, shall be described. This description shall result in radioactive releases which exceed the EPA PAGs at the site

Page 54: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 14 of 31

include identification of the appropriate officials, by title boundary, the need to provide these messages to the public, the needand-agenry, of the State and local government agencies to maintain the Alert and Notification System, and the need towithn the r0PZs. implement protective action strategies are no longer necessary. CR-3

requests an exemption from the regulation requiring the description ofState and local government officials within the EPZs. Because it is nolonger possible for EPA PAGs to be exceeded at the site boundary,the description of EPZs is no longer necessary.

42 D.2. Pro.visions shall, bhc. de.Scr.,ibed for yea.rly CR-3 requests an exemption from the regulation to provide informationdis.se•,•inati-on to the publics wit-hin the plume . xpOSU. e to the public on a periodic basis for how they will be notified, what theirpathway EPZ of basic em.er.gency planning i"nformation, initial actions should be during an emergency, and for the onsiter.uch ag tho methods and times required for publ•ic emergency plan to contain established procedures for the coordinatedno^.tifi-atti.n and the pr.otec.tive act.ions planned ifdissemination of information to the public. Because it is no longerac.c.adent occurs, g -nF.al io ationast the nature possible for the radiological consequences of a design basis accidentand- effectsb of radiation, and a listing , of local, broadca-t or a postulated beyond design basis accident at CR-3 to result instati-o-ns that- will -b used for dissemination of radioactive releases which exceed the EPA PAGs at the siteinformation duing an emergen•y. Sign; Or other boundary, the need for the public to take protective actions and themeas.ur. shall also be used- to disse mnatin t any need to educate the public on what their prompt actions would be intran.ient population within the plume exposure the event of a radiological emergency is no longer necessary.pathway EPZ appropriate inform atin that would behelpful if an ac.cident occur-s.

43 D.3. A licensee shall have the capability to notify CR-3 requests an exemption from the regulation requiring theresponsible State and local governmental agencies within capability to notify responsible State and local governmental agencies46 minutes after declaring an emergency. The ficensee within 15 minutes after declaring an emergency. Because it is nos.hall demonstrate that the appro.pri-'ate govermental' longer possible for the radiological consequences of a design basisaut-ho-r-iies-^ have the capability to make a publi... al.erting accident or a postulated beyond design basis accident at CR-3 toand notification decirsin promptly on being informed result in radioactive releases which exceed the EPA PAGs at the siteby the li.ensee of an emergency cO.d.iti. A. Prir t boundary, the need for the public to take protective actions in theinitial. operation greater than 5 percent Of rated thermal event of a radiological emergency is not necessary. CR-3 proposes topoweroF . vh_ thMe firs .t-reato at a site, eac.h n.clear powe complete emergency notification through the State Watch OfficereactGo licensee shall demonstrate that adm-inir.st;rtative Tallahassee (SWOT) within 60 minutes after an emergencyand physi•cal, means have been establis.hed for^alle-ting declaration or a change in classification. This timeframe is consistentand providing prompt ito the public withi with the 10 CFR 50.72 notification to the NRC and is appropriatethe plume exposure pathway EPZ. The design because there is no need for State or local response organizations toobjective of the p.. mpt publich al.e- t and- no-t-ific•a-tion,., implement any protective actions. The SWOT will assume thesste. 6h-ll be We haee the cap-bI t', to e st responsibility to provide notification to Citrus County. An exemption to

Page 55: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 15 of 31

complete thc initial allerting and initiate notification ofthc public within the plume exposure pathway E-PZwiA4thin about 15 minutes. Thc usc of this alerting and

maintain a backup alerting and notification capability is being takenbecause this is an offsite emergency planning requirement. Offsiteemergency response capability is no longer appropriate as no designbasis accident or postulated beyond design basis accident can resultin radioactive releases which exceed EPA's protective action guides atthe site boundary.

. 4; nA 4h.. ... n M... .. .... r .. .. . . .4 .

minutes of thc time that State and local officialls areno-tifficd that a smiatuatin eists rcquir~ing urgent actonto thc•more likely events where tlhere is substantl"timne -avail-ablle for the appropriate governmentallauithorities to make a judgment whether or not toac~tivate the public allert and- noiiaion system. Thealer-ting and notification capability shall additionallyinclude admininstrative and physicall means forabackup methed of pub!i alerting and notificatiGnc~apable of being used inthe event the primairy methodof al.e.ting and- notific.ation is u ailable during anemergencly to aleIrt Or notify all Or Po.rIo of the plumeexposure pathway EPZ popullation. The backup methodshall have the capability to alert and notify the publicwithin the plume exposur-e pathway EPZ, but does notneed to- Meet the 15 mninute design objective for the

primay propt public. alert and notification system.WA.hen thee-i a d-eciAsioen to ac-tivatte the alert and-no-tific-ation system, the appropriate governmentalauthorities will determi. e•whpether to activate the entie•alert and notification system simultaneously OrFngraduated Or staged manner. T~he responsiibiliity forac~tivating such a public ale1rt and iinotification systems-hall remain with the appr-opriate governmentalallthOmoes.

44 D.4. If FE.MA •as. apprved a nuclear power reactor CR-3 requests an exemption from the regulation requiring onsite andsite-'s, --art and notification design report, including the State and local offsite emergency plans contain the means to providebackup aler•t and notification capability, as of early notification and clear instruction to the populace within the PlumeDecember 23, 2011, then the backup alert and Exposure Pathway EPZ. Because it is no longer possible for thene-tific-,-atio.n capability requirements in Sect-io.'n n .D3 radiological consequences of a design basis accident or a postulatedmust be implemented by De•emhber 24, 2012. if the alert beyond design basis accident at CR-3 to result in radioactive releases

._,,,_ and notification design repor.t does not include a which exceed the EPA PAGs at the site boundary, the need for the

Page 56: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 16 of 31

backup alelt and notification capability OF needs public to take protective actions in the event of a radiologicalrcis..n.in-, ensure adequate backup aler, t and emergency is not necessary. Therefore, the need to provide thesenotification capability, then a r.vision of the alcrt and messages to the public, the need to maintain the Alert and Notificationnotification design report must he submitted to FEMA System and backup capability is no longer necessary.for reMviw by -no 24, 2-013, and the FEMAapproGvdbackup allert and notification meanst must hci mplemented Waithin 3-6-5- days after FEMA approlval.

Howevcr, the total time period to implement a FEM Aapproved backup allert and no-tific-at-ion Means must notexceed Juno 22, 2015.

45 E. Emergency Facilities and Equipment No exemption is requested.Adequate provisions shall be made and described foremergency facilities and equipment, including:E. 1. Equipment at the site for personnel monitoring;

46 E.2. Equipment for determining the magnitude of and for No exemption is requested.continuously assessing the impact of the release ofradioactive materials to the environment;

47 E.3. Facilities and supplies at the site for decontamination No exemption is requested.of onsite individuals;

48 E.4. Facilities and medical supplies at the site for No exemption is requested.appropriate emergency first aid treatment;

49 E.5. Arrangements for medical service providers qualified No exemption is requested.to handle radiological emergencies onsite;

50 E.6. Arrangements for transportation of contaminated No exemption is requested.injured individuals from the site to specifically identifiedtreatment facilities outside the site boundary;

51 E.7. Arrangements for treatment of individuals injured in No exemption is requested.support of licensed activities on the site at treatmentfacilities outside the site boundary;

52 E.8.a. (i) A licensee -nsite technicaln suppr't center and CR-3 requests an exemption from the regulation that requiresan em.ergency operation facility from which effective arrangements are maintained to accommodate State and localdirection can be given and effective control can be emergency response staff at the EOF. Because it is no longer

I

Page 57: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 17 of 31

exercised during an emergency possible for EPA PAGs to be exceeded at the site boundary, the EOFwill no longer exist and there will be no need for a response by offsiteagencies or company employees to the EOF. CR-3 also requests anexemption from the requirement to maintain a Technical SupportCenter (TSC). An onsite facility will continue to be maintained, fromwhich effective direction can be given and effective control may beexercised during an emergency. The CR-3 PDEP will continue tomaintain arrangements for requesting assistance and using resourcesfrom appropriate offsite support organizations.

53 E.8.a (ii) For nu.lea. power r... tor li-.• "a"n", a CR-3 requests an exemption from the requirements for the onsiteli,.ns.. .n-ite .p..ational , uppo.t . . ntr;,, Operational Support Center (OSC). In the permanently defueled

condition, the rapidly developing scenarios associated with eventsinitiated during reactor power operation are no longer credible. Assuch, an onsite OSC is no longer needed.

An onsite facility will continue to be maintained, from which controlroom support, emergency mitigation, radiation monitoring, andeffective control may be exercised during an emergency.

54 E.8.b. For a nuclear power reactor licensee's emergency No exemption is requested.operations facility required by paragraph 8.a of this section,either a facility located between 10 miles and 25 miles ofthe nuclear power reactor site(s), or a primary facilitylocated less than 10 miles from the nuclear power reactorsite(s) and a backup facility located between 10 miles and25 miles of the nuclear power reactor site(s). Anemergency operations facility may serve more than onenuclear power reactor site. A licensee desiring to locate anemergency operations facility more than 25 miles from anuclear power reactor site shall request prior Commissionapproval by submitting an application for an amendment toits license. For an emergency operations facility locatedmore than 25 miles from a nuclear power reactor site,provisions must be made for locating NRC and offsiteresponders closer to the nuclear power reactor site so thatNRC and offsite responders can interact face-to-face withemergency response personnel entering and leaving the

Page 58: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 18 of 31

nuclear power reactor site. Provisions for locating NRC andoffsite responders closer to a nuclear power reactor sitethat is more than 25 miles from the emergency operationsfacility must include the following:

55 E.8.b. (1) Space for members of an NRC site team and No exemption is requested. Refer to the 10 CFR Appendix E, IV.Federal, State, and local responders E.8.b., basis for exemption description, which identifies the elimination

of the EOF.

56 E.8.b. (2) Additional space for conducting briefings with No exemption is requested. Refer to the 10 CFR Appendix E, IV.emergency response personnel; E.8.b., basis for exemption description, which identifies the elimination

of the EOF.

57 E.8.b.(3) Communication with other licensee and offsite No exemption is requested. Refer to the 10 CFR Appendix E, IV.emergency response facilities; E.8.b., basis for exemption description, which identifies the elimination

of the EOF.

58 E.8.b.(4) Access to plant data and radiological information; No exemption is requested. Refer to the 10 CFR Appendix E, IV.and E.8.b., basis for exemption description, which identifies the elimination

of the EOF.

59 E.8.b.(5) Access to copying equipment and office supplies; No exemption is requested. Refer to the 10 CFR Appendix E, IV.E.8.b., basis for exemption description, which identifies the eliminationof the EOF.

60 E.8.c. By jU.n 20, 2012, f-•.- nu•. l. a powc. . .. ctO. CR-3 requests an exemption from the requirements for the EOF.

Page 59: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 19 of 31

licensec's cmc.g.n.y operations facility required by Because it is no longer possible for EPA PAGs to be exceeded at theparagraph 8.a of thi -section, a facility having the site boundary, offsite emergency response plans are no longerfollowing capabilities, necessary and there will be no response by offsite agencies to an EOF(1) The capability fo -obtaining and displaying plant and JIC. An EOF and JIC will no longer be maintained. The CR-3data- and radiological information for each reacor at a PDEP will continue to maintain arrangements for requestingnuc.lear power rcactOr s-ite and for .ac.h nucIla. power assistance and using resources from offsite support organizations.reactor site that the fcacliaty serves;

61 E.8.c (2) The capability to analyze plant technical CR-3 requests an exemption from the requirement to brief offsiteinfo,,a-rmation,. and provide techni-cal briefings on e.. nt response organizations on event conditions at CR-3. Because it is no.onditions and prognosis W tic.n-see andl o.ffmit longer possible for EPA PAGs to be exceeded at the site boundary,response organizations for .ac.h ractor at a wncl.ar offsite emergency response plans are no longer necessary and therepower reactor soit and f .eac.h nucle,..ar power reactor , will be no response by offsite agencies to an EOF and JIC. An EOFsite that the facility s. ..es; and and JIC will no longer be maintained. The CR-3 PDEP will continue to

maintain arrangements for requesting assistance and using resourcesfrom offsite support organizations.

62 E.8.c (3) The capability to support response to events This requirement does not apply to the CR-3 EOF.occurring simultaneously at more than one nuclear powerreactor site if the emergency operations facility servesmore than one site; and

63 E.8.d. For nuclear power reactor li.ensees, an CR-3 will maintain an alternative facility for augmentation of the EROalternative facility (Or facilities) that would hb capable of: communicating with the control room and plant Security,acceaAssihbi en if the site fis under threat Of Or performing notifications to the SWOT, enabling emergency repair andexper•icing hostile action, to function as a staging damage control teams to begin planning actions to mitigate thearea for augmentation of emergency response staf consequences of an event, and supporting a rapid response as soonand- .ollec-,tively having the folowing charc•ter6iti-•'s as the site is deemed accessible, in the event that the site is notthe capability forGcoMm•un... ican with the emergency accessible. CR-3 requests an exemption from the requirement tooperations facility, control room., and plant secury,; maintain communications with the EOF. The scope of an emergencythe capability to pefoFrm offsitc notifications; and the response will be appropriate for the defueled plant status (not be thecapability f: r e .. r. .ig assessment activities, same as actions necessary for "hostile actions" at operating powerincluding damage control. team planning and plants). In the EP Final Rule (December 2011), the NRC definedpreparation, for use when onsite emergency facilities "hostile action" as, in part, an act directed toward a nuclear powerc.annot be safely access d dur.iRn hostile actio. The plant or its personnel. The NRC excluded NPRs from the definition ofr.equirements in this paragraph 8.d must be "hostile action." CR-3 should not be required to plan for an offsitei mplemented. no later. than _Decembern^. F 23, 2014, with the impact resulting from hostile action because: (1) the facility poses aexception of the capability f.r staging emergency lower radiological risk to the public than does a power reactor, and (2)......response organization personnel at the alternativ"e the facility has a low likelihood of a credible accident resulting in

Page 60: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 20 of 31

fa.ility (OF facilities) and the capability for radiological releases requiring offsite protective measures.communiM-AMcation Wit-h the cmcrgency opcrationsfaGility, contro•lrom, and plant security, whih mustbe implemented no l2atr. than Juno 20, 2012.

64 E.8.e. A lic-ensee shall not be subject to th• CR-3 requests an exemption from the requirements established for anrequirements Of pr•agraph 8.1 Of thi. seGtion for an EOF. Because it is no longer possible for EPA PAGs to be exceededexisting emergency operations facility appro.ved as, of at the site boundary, the EOF will no longer exist and there will be norDece..mbher 23, 2011; need for a response by offsite agencies to the EOF. The CR-3 PDEP

will continue to maintain arrangements for requesting assistance andusing resources from offsite support organizations.

65 E.9. At least one onsite and one offsite communications CR-3 requests an exemption from the regulation requiringsystem; each system shall have a backup power source. communications with contiguous State and local governments withinAll communication plans shall have arrangements for the Plume Exposure Pathway EPZ. Because it is no longer possibleemergencies, including titles and alternates for those in for the radiological consequences of a design basis accident or acharge at both ends of the communication links and the postulated beyond design basis accident at CR-3 to result inprimary and backup means of communication. Where radioactive releases which exceed the EPA PAGs at the siteconsistent with the function of the governmental agency, boundary, the need to provide prompt notification to the localthese arrangements will include: governments to implement protective actions is no longer necessary.

CR-3 will maintain the capability to communicate with the SWOT.

E.9.a. Provision for communications with contiguous SWOT will assume the responsibility to provide notification to Citrus

State/local governments within the plume . xp..ur.e County. CR-3 will maintain communications with the SWOT and the

pathway-EPZ-, Such communications shall be tested NRC. The onsite response facilities will be combined into a single

monthly. facility.

66 E.9.b. Provision for communications with Federal No exemption is requested.emergency response organizations. Such communicationssystems shall be tested annually.

67 E.9.c. Provision for communications among the maGIoa CR-3 requests an exemption from the requirement for communicationspower reactor contrl room, the onsitoe t.ec;.hnical• among the control room, the TSC, and the EOF; and communicationsupport center, and the emergency . pe.ations fac-ility;" with field assessment teams for assessing and monitoring offsiteand.•among-.h, nuclear facility, the principal State and radiological conditions. Because it is no longer possible for thelocal emergency operations centers, ad- the-field radiological consequences of a design basis accident or a postulatedassessment teams. Such communications systems shall beyond design basis accident at CR-3 to result in radioactive releasesbe tested annually. which exceed the EPA PAGs at the site boundary, the need to provide

prompt notification to the local governments to implement protectiveactions is no longer necessary. CR-3 will maintain the capability to

Page 61: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 21 of 31

communicate with the SWOT from the control room. The SWOT willassume the responsibility to provide notification to Citrus County.Since a need for monitoring and assessing no longer exists, CR-3 nolonger intends to maintain the capability to deploy field teams forassessing and monitoring offsite radiological conditions. The CR-3PDEP will continue to maintain communication between onsiteassessment teams and the onsite response facility.

68 E.9.d. Provisions for communications by the licensee with CR-3 requests an exemption from the requirement for communicationsNRC Headquarters and the appropriate NRC Regional between the NRC and the TSC and EOF. CR-3 will maintainOffice Operations Center from the nu.G•a; pew-; ;cactor communications with the NRC from the Control Room..o..ro. room, th. on.ite technical -upport center, andthe .m..genc op.r.atione facility. Such communicationsshall be tested monthly.

69 F. Training No exemption is requested.F. 1. The program to provide for: (a) The training ofemployees and exercising, by periodic drills, of emergencyplans to ensure that employees of the licensee are familiarwith their specific emergency response duties, and (b) Theparticipation in the training and drills by other personswhose assistance may be needed in the event of aradiological emergency shall be described. This shallinclude a description of specialized initial training andperiodic retraining programs to be provided to each of thefollowing categories of emergency personnel

70 F.1. i. Directors and/or coordinators of the plant emergency No exemption is requested.organization;

71 F.1. ii. Personnel responsible for accident assessment, No exemption is requested.including control room shift personnel;

72 F.1. iii Radiological monitoring teams; No exemption is requested.

73 F.1. iv. Fire control teams (fire brigades); No exemption is requested.

74 F. 1. v. Repair and damage control teams; No exemption is requested.

Page 62: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 22 of 31

75 F.1. vi. First aid and rescue teams; No exemption is requested.

76 F.1. vii. Medical support personnel; No exemption is requested.

77 F.1. viii. Lic~ensee's headqua"t.es support personnel; CR-3 requests an exemption from the requirement to provide trainingto headquarters personnel because the level of emergency responserequired by the CR-3 PDEP does not require response byheadquarters personnel. Because it is no longer possible for theradiological consequences of a design basis accident or a postulatedbeyond design basis accident at CR-3 to result in radioactive releaseswhich exceed the EPA PAGs at the site boundary, the need forheadquarters response is no longer necessary.

78 F.1. ix. Security personnel. No exemption is requested.

79 F.1 In addition, a radiological orientation training program CR-3 requests an exemption from the requirement to maintain ashall be made available to local services personnel; e.g., radiological orientation training program for Civil Defense and locallocal emergency services/CivWl-• Den-e, local law news media persons. Training will be provided to prepare localenforcement personnel, local, ne.s media per-sons. services (firefighting, local law enforcement, and ambulance)

personnel for their response to an event at the CR-3 site. Because itis no longer possible for the radiological consequences of a designbasis accident or a postulated beyond design basis accident at CR-3to result in radioactive releases which exceed the EPA PAGs at thesite boundary, the need to educate the public on what their promptactions would be in the event of a radiological emergency is no longernecessary.

80 F.2. The plan shall describe provisions for the conduct of CR-3 requests an exemption from the requirement to conduct fullemergency preparedness exercises as follows: participation biennial exercises. CR-3 will continue to test theExercises shall test the adequacy of timing and content of adequacy of timing and content of implementing procedures andimplementing procedures and methods, test emergency methods, test emergency equipment and communications networks,equipment and communications networks, test the puns and ensure that ERO personnel are familiar with their duties, throughalert and notificatiin• •ystem, and ensure that emergency periodic exercise, drill and training activities. CR-3 also requests anorganization personnel are familiar with their duties. exemption from the requirement to test the public notification network

as part of emergency preparedness exercises. Because it is no longerpossible for the radiological consequences of a design basis accidentor a postulated beyond design basis accident at CR-3 to result inradioactive releases which exceed the EPA PAGs at the siteboundary, the need to provide emergency messages to the public and

Page 63: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 23 of 31

the need to maintain the Alert and Notification System are no longernecessary.

81 F.2.a. A full paticipation .. e... .. . ... is as mucn

of theIImenlee State, andl ! Iotl IV n~gni plans asiV isHllroSonably achievable wit-hout Amandator; public

partici6pation shall be conducted for Pach aitc at which

a powor reacatoar is locr-ated. N uclear power reactor

Micnsccs shall submit cxercise sccnarios undcr § 50.4

att Waist 6-0- daysc bofore use on a full par-ticiipation

exercise rcguired by this paragraph 2a

CR-3 requests an exemption from the requirement to conduct fullparticipation biennial exercises. CR-3 will continue to include theState of Florida, the Citrus County Sheriffs Office, and local supportorganizations in the periodic drills and exercises to assess its ability toperform responsibilities related to an emergency at CR-3 to the extentdefined by the CR-3 PDEP and State emergency plans. Because it isno longer possible for the radiological consequences of a design basisaccident or a postulated beyond design basis accident at CR-3 toresult in radioactive releases which exceed the EPA PAGs at the siteboundary, the need for State and local response organizations toparticipate in drills and exercises is no longer necessary. CR-3 alsorequests an exemption from the requirement to submit the exercisescenario at least 60 days in advance since relief is being requestedfrom the requirement to perform a full participation exercise.

82 F.2.a(i) For an operating license issued under this part, thisexercise must be conducted within two years before theissuance of the first operating license for full power (oneauthorizing operation above 5 percent of rated power) ofthe first reactor and shall include participation by eachState and local government within the plume exposurepathway EPZ and each state within the ingestion exposurepathway EPZ. If the full participation exercise is conductedmore than 1 year prior to issuance of an operating licenseefor full power, an exercise which tests the licensee's onsiteemergency plans must be conducted within one yearbefore issuance of an operating license for full power. Thisexercise need not have State or local governmentparticipation.

No exemption is requested.

83 F 2.a.(ii) For a combined license issued under part 52 of No exemption is requested.this chapter, this exercise must be conducted within twoyears of the scheduled date for initial loading of fuel. If thefirst full participation exercise is conducted more than oneyear before the scheduled date for initial loading of fuel, anexercise which tests the licensee's onsite emergency plans

Page 64: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 24 of 31

must be conducted within one year before the scheduleddate for initial loading of fuel. This exercise need not haveState or local government participation. If FEMA identifiesone or more deficiencies in the state of offsite emergencypreparedness as the result of the first full participationexercise, or if the Commission finds that the state ofemergency preparedness does not provide reasonableassurance that adequate protective measures can and willbe taken in the event of a radiological emergency, theprovisions of § 50.54(gg) apply.

84 F 2.a (iii) For a combined license issued under part 52 ofthis chapter, if the applicant currently has an operatingreactor at the site, an exercise, either full or partialparticipation, shall be conducted for each subsequentreactor constructed on the site. This exercise may beincorporated in the exercise requirements of SectionsIV.F.2.b. and c. in this appendix. If FEMA identifies one ormore deficiencies in the state of offsite emergencypreparedness as the result of this exercise for the newreactor, or if the Commission finds that the state ofemergency preparedness does not provide reasonableassurance that adequate protective measures can and willbe taken in the event of a radiological emergency, theprovisions of § 50.54(gg) apply.

No exemption is requested.

85 F 2.b. Each licensee at each site shall conduct asubsequent exercise of its onsite emergency plan every 2years. Nu--cae; pow'cr ;cact; Ic.ns.ccs shall submit

Auxurc.~ii ~n~rin~ unnnr o nu.~ ~IT iuii~i nu n~:~ n~Toruiier-in e an na a uvr i~ niitrtF MIA ati least r n GO days - - - - -

....q " an .. .. Fed -b.-y... t.h is n'"'.....,. .b. The""'-"ooo.' oxor c-'- mn 'vb oinc- in, . th e nt. full p, ,a ticip

tio k~ a n . , I p r ~ e .. n IA k n m ft~r .'.r f k Ir ^ ^ f 2 a* .i . . . . I ~

• .. v

CR-3 requests an exemption from the requirement to conduct fullparticipation biennial exercises. Because it is no longer possible forthe radiological consequences of a design basis accident or apostulated beyond design basis accident at CR-3 to result inradioactive releases which exceed the EPA PAGs at the siteboundary, the need for State and local response organizations toparticipate in drills and exercises is no longer necessary. CR-3 willcontinue to include the State of Florida, the Citrus County SheriffsOffice, and local support organizations for firefighting, ambulance andmedical services for events at the CR-3 site in the periodic drills andexercises to assess its ability to perform responsibilities related to anemergency at CR-3 to the extent defined by the CR-3 PIDEP and State

ser.toon. In addition, the licensee shall take actionsnecessary to ensure that adequate emergency responsecapabilities are maintained during the interval betweenbiennial exercises by conducting drills, including-at leastone drill involving a combination of some of the principalfunctional areas of the licensee's onsite emergency

Page 65: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 25 of 31

response capabilities. The principal functional areas ofemergency response include activities such asmanagement and coordination of emergency response,accident assessment, event classification, notification ofoffsite authorities, assessment of the onsite and-effsiteimpact of radiological releases, pr.ot"tive actin---.Frccmmcnlnedation development, pFettmtive actiondeci.-ion .. a.n, ,plant system repair and mitigativeaction implementation. During these drills, activation of allof the licensee's emergency response facilities (Terhn.Gal....... t C.nti. . ITSC. . on . .tinn5S *.. .. r.t Cren.. .

emergency plans.

CR-3 also requests an exemption from the requirement to submit theexercise scenario at least 60 days in advance since relief is beingrequested from the requirement to perform a full participation exercise.The public will no longer have any response actions in the event of anemergency at CR-3. The need to coordinate with State and localresponse organizations for the development of Protective ActionDecisions is no longer necessary. Activation of the EOF, TSC, andOSC is no longer necessary. The onsite response facilities will becombined into a single facility.I v•v

JVbj, ana Mec L-mergencY 0peraIIons 1-aGNITi tLJIJ))would not be necessary, licensees would have theopportunity to consider accident management strategies,supervised instruction would be permitted, operating staff inall participating facilities would have the opportunity toresolve problems (success paths) rather than havecontrollers intervene, and the drills may focus on the onsiteexercise training objectives.

86 F 2.c. Offsito plane for each 6ite shall be exercisodbiennially with full par-ticipation by each offeitoaulthority having a role u-nd-er the rmadiiologic~al rcSpOnscplan. Where the offtitc aulthority has a rolc undcr aradiologic~all rc~ponse plan for more than one 6itc-,itshall fully particiipate in one exorcise every F.wo yearsand shall, at least, partially par-ticipate in other offIteUplanl Cexe~ILU inl tisI periuu. 11 two UIIIurWIL licensees

each have licensed facilities located either on the same siteor on adjacent, contiguous sites, and share most of theelements defining co-located licensees, then each licenseeshall:

CR-3 requests an exemption from the requirement to conduct fullparticipation biennial exercises. Periodic exercises and drills will becompleted to demonstrate ERO proficiency and evaluate performance.Training will be provided to ERO personnel. CR-3 will continue toinclude the State of Florida, the Citrus County Sheriffs Office, andlocal support organizations in the periodic drills and exercises toassess its ability to perform responsibilities related to an emergency atCR-3 to the extent defined by the CR-3 PDEP and State emergencyplans.

Because it is no longer possible for the radiological consequences of adesign basis accident or a postulated beyond design basis accident atCR-3 to result in radioactive releases which exceed the EPA PAGs atthe site boundary, the need for State and local response organizationsto fully participate in drills and exercises is no longer necessary.

87 F 2.c.(1) Conduct an exercise biennially of its onsite No exemption is requested. This regulation does not apply to CR-3.emergency plan;

Page 66: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 26 of 31

88 F 2.c.(2) Participate quadrennially in an offsite biennial full No exemption is requested. This regulation does not apply to CR-3.or partial participation exercise;

89 F 2.c.(3) Conduct emergency preparedness activities and No exemption is requested. This regulation does not apply to CR-3.interactions in the years between its participation in theoffsite full or partial participation exercise with offsiteauthorities, to test and maintain interface among theaffected State and local authorities and the licensee. Co-located licensees shall also participate in emergencypreparedness activities and interaction with offsiteauthorities for the period between exercises;

90 F 2.c.(4) Conduct a hostile action exercise of its onsite No exemption is requested. This regulation does not apply to CR-3.emergency plan in each exercise cycle; and

91 F 2.c.(5) Participate in an offsite biennial full or partial No exemption is requested. This regulation does not apply to CR-3.participation hostile action exercise in alternating exercisecycles.

92 F 2.d. Each State With responsibili;. fo. nuclear power CR-3 requests an exemption to conduct the ingestion pathwayr.a Po .r. megency prep ..aredns , should fully exercise and the State participation in this exercise. Because it is nopartic..ipate in the ingestion pathway por.tion o longer possible for the radiological consequences of a design basisexercises at least once every exerci. e cycle. in States accident or a postulated beyond design basis accident at CR-3 toWith m... than one nuclear power reactor plum. result in radioactive releases which exceed the EPA PAGs at the siteexp..uro pathway EPZ, Mho State sho.uld, roato thi' boundary, the need to conduct an ingestion pathway exercise is noparti.ipation from site et Wite. Each State with longer necessary. CR-3 also requests an exemption from the... p.nsibility fr nuc'lear powe• r.actO. emer.gency requirement to require "hostile action" drills and exercises. In the EPpreparednes hould fully participate in a ho..t.ile Final Rule (December 2011), the NRC defined "hostile action" as, inaction ex...i.e at least once every cycle and should part, an act directed toward a nuclear power plant or its personnel.fully participate on one hostile action exerci. e by The NRC excluded NPRs from the definition of "hostile action." CR-3December 31, 201 5. Stat.s IN with more than one nuc.lear should not be required to plan for an offsite impact resulting frompower reactor plume expo.ure pathway EPZ 6hould hostile action because: (1) the facility poses a lower radiological risk torotate this participation from siwte to s.e. the public than does a power reactor, and (2) the facility has a low

likelihood of a credible accident resulting in radiological releasesrequiring offsite protective measures.

93 F 2.e. Licensees shall enable any State or local CR-3 requests an exemption from this regulation that requiresgovernment located within the plume expsur.e pathway participation of offsite response organizations within the plumeE-P-Z- to participate in the licensee's drills when requested by exposure pathway EPZ in drills. CR-3 will enable any State or local

Page 67: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 27 of 31

such State or local government. government to participate in drills when requested by State of Floridaor local government. Because it is no longer possible for theradiological consequences of a design basis accident or a postulatedbeyond design basis accident at CR-3 to result in radioactive releaseswhich exceed the EPA PAGs at the site boundary, the need to provideinformation to State and local response organizations for thedevelopment of Protective Action Decisions and offsite emergencyplanning by State and local organizations is no longer necessary.

94 F 2.f. Remedial exercises will be required if the emergencyplan is not satisfactorily tested during the biennial exercise,such that NRC, in cc.'tat.-n .ith FEMA, cannot(1) find reasonable assurance that adequate protectivemeasures can and will be taken in the event of aradiological emergency or

(2) determine that the Emergency Response Organization(ERO) has maintained key skills specific to emergencyresnonse. The evxtent of S÷-,^ -,nd loc a.l n-art-ic--'-tion, in

CR-3 requests an exemption from the requirement for the NRC toconsult FEMA if the emergency plan is not satisfactorily tested duringthe biennial exercise. Remedial exercises will be conductedcommensurate with the reduced exercise scenario scope whennecessary. Because it is no longer possible for the radiologicalconsequences of a design basis accident or a postulated beyonddesign basis accident at CR-3 to result in radioactive releases whichexceed the EPA PAGs at the site boundary, the need for State andlocal response organizations to participate in drills and exercises in thesame manner as full participation exercise is no longer necessary.

remedial exercises must be sufficient to show that

approprioate crrec~etiive meacuree have been takentU---------------------------

•A.•I

Fnte orein u Me e- erien ftepae.IP~e1 05-

95 F 2.g. All exercises, drills, and training that provide No exemption is requested.performance opportunities to develop, maintain, ordemonstrate key skills must provide for formal critiques inorder to identify weak or deficient areas that needcorrection. Any weaknesses or deficiencies that areidentified in a critique of exercises, drills, or training mustbe corrected.

96 F 2.h. The participation of State and local governments in No exemption is requested.an emergency exercise is not required to the extent that theapplicant has identified those governments as refusing toparticipate further in emergency planning activities,pursuant to § 50.47(c)(1). In such cases, an exercise shallbe held with the applicant or licensee and suchgovernmental entities as elect to participate in the

Page 68: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 28 of 31

emergency planning process.4-

97 F 2"i. Licensees shall use drill and exercise scenarios thatprovide reasonable assurance that anticipatory responseswill not result from preconditioning of participants. Such

wecnariGo fGo nuI.,car pGo.er rc-pactolice nscee n mtMInlude -a %Wide peptrUM Of radioloegicall rcllases devents, including hostile action.

Exercise and drill scenarios as appropriate mustemphasize coordination among onsite and offsite responseorganizations.

CR-3 requests an exemption from the requirement to conduct fullparticipation biennial exercises. Periodic drills and exercises will becompleted to demonstrate ERO proficiency and evaluate performance.Because it is no longer possible for the radiological consequences of adesign basis accident or a postulated beyond design basis accident atCR-3 to result in radioactive releases which exceed the EPA PAGs atthe site boundary, the need for State and local response organizationsto participate in drills and exercises is no longer necessary. CR-3 willcontinue to include the State of Florida, the Citrus County SheriffsOffice, and local support organizations in the periodic drills andexercises to assess its ability to perform responsibilities related to anemergency at CR-3 to the extent defined by the CR-3 PDEP and Stateemergency plans. CR-3 also requests an exemption from therequirement to include "hostile action" drills and exercises.

In the EP Final Rule (December 2011), the NRC defined "hostileaction" as, in part, an act directed toward a nuclear power plant or itspersonnel. The NRC excluded NPRs from the definition of "hostileaction." CR-3 should not be required to plan for an offsite impactresulting from hostile action because: (1) the facility poses a lowerradiological risk to the public than does a power reactor, and (2) thefacility has a low likelihood of a credible accident resulting inradiological releases requiring offsite protective measures.

i i

98 F 2.i. Th-e exer.cisee ea. A DIducted under naraaranfl ~ at

this s-.ti.n by nuclear po.r. cac.to. riGen-ece mu. tproVide the oppo~tunity for. the FRO to dimoinftrateprofic.icncy in the key ekile cceeR to mlmnthe prwincipall functionall are-av o-f emerigency responieidentified i-n paragraph 2.b of thie ecotion. Eachcxcrcie ,uSt provide the yPPoUwitY for the ERO todemr-onatirate key skills c pecific to emnergency resepnseduties in the control room, TSC, OSC, EOF, and joint

infomaton enter. Additionally, in each eight calendaryearoxecia cycle, nuclear poWer reactor. l6aicnceeceh~~II G ta Gnttent a! sre~narin durn xrin

CR-3 requests an exemption from the requirement to conduct fullparticipation biennial exercises. Periodic drills and exercises will becompleted to demonstrate ERO proficiency in key skills necessary toimplement the principal functional areas of emergency response asapplicable for the permanently defueled plant status. Critiques willfollow each drill or exercise activity. The CR-3 PDEP discussesexercise and drill types and frequencies of occurrence. Scenarios willbe developed to test all major elements of the PDEP within an eight(8) year period. These elements include management andcoordination of emergency response, accident assessment, andsystem repair and corrective action. CR-3 will continue to include theState of Florida, the Citrus County Sheriffs Office, and local supportorganizations in the periodic drills and exercises to assess its ability toI_______ ----..-- Paa-P 2o hs eU RE FV0

Page 69: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 29 of 31

the opportunitY for the ERG to dcmon~tratc proficiencYinR the key skill: neec:ary to rcspond to the folloWingScenario lelmente:!

hostilc :iction dierccted at the plant site, no radiologcarolease Or an unplanned mini-mal r-adOiGologcal Feleaseth2t- doec-6 not require public protcctivc actione,-an

inital caceiicatOnf or rapid escalation to a Site A reaEm~ergcncY o-r GePne-ral Emergency, implementation oetrategies, procedures, and guidance developed under

6 0.54(hh)(2), and integrat-ion of offeite recouree% Vithonito reponsec. The licencee shall maintain a recor~d

of exercices rcondhuc-ted- duFrig each eight year exercrictec~ycle that document: the con~tent Of ecnro ~dtoeomFply with the requirement: of thi: paragraph. Eachlicencee shall coend-ucnt a host-ile act-io 4xricfor

nea ofite ci8te no later than D~ecember 31, 2015. Thefirest eight yea ex rccycle forF a site vAIl begin in thecalendar year in which the firet hostile action exeFcisea: con.ducated. Foar- a sit-e licensed under Part 562, the firsteight year exercise cycle begine in the c-alendar. year otthe inta exrie eurd by Section 'If F 2.

perform responsibilities related to an emergency at CR-3 to the extentdefined by the CR-3 PDEP and State emergency plans. Because it isno longer possible for the radiological consequences of a design basisaccident or a postulated beyond design basis accident at CR-3 toresult in radioactive releases which exceed the EPA PAGs at the siteboundary, the need for State and local response organizations toparticipate in drills and exercises is no longer necessary. CR-3 alsorequests an exemption to require "hostile action" drills and exercises.

In the EP Final Rule (December 2011), the NRC defined "hostileaction" as, in part, an act directed toward a nuclear power plant or itspersonnel. The NRC excluded NPRs from the definition of "hostileaction." CR-3 should not be required to plan for an offsite impactresulting from hostile action because: (1) the facility poses a lowerradiological risk to the public than does a power reactor, and (2) thefacility has a low likelihood of a credible accident resulting inradiological releases requiring offsite protective measures.

99 G. Maintaining Emergency Preparedness No exemption is requested.Provisions to be employed to ensure that the emergencyplan, its implementing procedures, and emergencyequipment and supplies are maintained up to date shall bedescribed.

100 H. Recovery No exemption is requested.Criteria to be used to determine when, following anaccident, reentry of the facility would be appropriate orwhen operation could be resumed shall be described.

101 I. Onsite Protective Actions During Hostile Action CR-3 requests an exemption from the requirement to establishBy June 20, 2012, for nuclear power Feactor li.en.-"e.. protective actions to protect onsite personnel during hostile action toa range of protective action:, to protect onit- ensure reactor shut down. In the EP Final Rule (December 2011), theI......e,,i-'.. hosi -*-' .---" mu.s b--e ..- '-.-- .-- NRC defined "hostile action" as, in part, an act directed toward a

I

Page 70: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 2Page 30 of 31

e..U.. the ... tnu.. ab-;lity of the lir" n... to saf""" nuclear power plant or its personnel. The NRC excluded NPRs for anshut down the F...t. and pe.f.. m the +, fctions of the offsite impact resulting from hostile action because: (1) the facility!i.en...'. em'.genc'. pla,. poses a lower radiological risk to the public than does a power reactor,

and (2) the facility has a low likelihood of a credible accident resultingin radiological releases requiring offsite protective measures.

102 10CFR 50 App E No exemption is requested.V. Implementing ProceduresNo less than 180 days before the scheduled issuance of anoperating license for a nuclear power reactoror a license to possess nuclear material, or the scheduleddate for initial loading of fuel for a combined license underpart 52 of this chapter, the applicant's or licensee's detailedimplementing procedures for its emergency plan shall besubmitted to the Commission as specified in § 50.4.Licensees who are authorized to operate a nuclear powerfacility shall submit any changes to the emergency plan orprocedures to the Commission, as specified in § 50.4,within 30 days of such changes.

103 10CFR 50 App E The regulation that identifies the requirement to maintain the

VI. Emergency Response Data System Emergency Response Data System (ERDS) is not applicable to

1. The Emergency Response Data System (ERDS) is a nuclear power facilities that are permanently shutdown.

direct near real-time electronic data link between thelicensee's onsite computer system and the NRC Based upon the permanently defueled status of CR-3, this system isOperations Center that provides for the automated no longer necessary to transmit safety system parameter data. Notransmission of a limited data set of selected parameters. exemption is requested since this change in ERDS data requirement isThe ERDS supplements the existing voice transmission identified in 10 CFR 50 Appendix E, VI. 2.over the Emergency Notification System (ENS) byproviding the NRC Operations Center with timely andaccurate updates of a limited set of parameters from thelicensee's installed onsite computer system in the event ofan emergency. When selected plant data are not availableon the licensee's onsite computer system, retrofitting ofdata points is not required. The licensee shall test theERDS periodically to verify system availability andoperability. The frequency of ERDS testing will be quarterlyunless otherwise set by NRC based on demonstrated

Page 71: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission Enclosure 23F0314-01 Page 31 of 31

system performance.

2. Except for Big Rock Point and all nuclear power facilitiesthat are shut down permanently or indefinitely, onsitehardware shall be provided at each unit by the licensee tointerface with the NRC receiving system. Software, whichwill be made available by the NRC, will assemble the datato be transmitted and transmit data from each unit via anoutput port on the appropriate data system.

Page 72: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

DUKE ENERGY FLORIDA, INC.

CRYSTAL RIVER UNIT 3

DOCKET NUMBER 50-302 / LICENSE NUMBER DPR-72

EXEMPTIONS TO RADIOLOGICAL EMERGENCY RESPONSEPLAN REQUIREMENTS DEFINED BY 10 CFR 50.47 AND

APPENDIX E TO PART 50, REVISION 1, AND RESPONSE TOREQUEST FOR ADDITIONAL INFORMATION

ENCLOSURE 3

REGULATORY COMMITMENTS

Page 73: Crystal River Nuclear Plant @DUKE ENERGY 1 Crystal River ... · Crystal River Unit 3 - Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and

U. S. Nuclear Regulatory Commission3F0314-01

Enclosure 3Page 1 of 1

REGULATORY COMMITMENTS

The following table identifies the actions committed to by Duke Energy Florida, Inc. in thisdocument. Any other statements in this submittal are provided for information purposes and arenot considered to be regulatory commitments. Please notify the Crystal River Unit 3 (CR-3)Manager, Nuclear Regulatory Affairs of any questions regarding this document or anyassociated regulatory commitments.

Regulatory Commitments Due Date/Event

CR-3 will incorporate the requirement to complete the reviewof Emergency Action Levels (EALs) with the State of Floridaand local governmental authorities on an annual basis in arevision to the Permanently Defueled Emergency Plan(PDEP) in the response to the PDEP RAI.

CR-3 will incorporate the requirement to conduct remedialexercises commensurate with the reduced exercise scenarioscope, when necessary, in a revision to the PDEP in the September 25, 2014response to the PDEP RAI.

CR-3 will remove "hostile action" from the PDEP and the September 25, 2014Permanently Defueled (PD) (EAL) Bases Manual in a revisionto the PDEP in the response to the PDEP RAI.

CR-3 will add EM-503, "Conduct of the Mitigation September 25, 2014Coordinator," to the PDEP implementing procedure list in theresponse to the PDEP RAI.