cryogenic upgrade of the helium central liquefier and ... · • 1998-2006 : average annual lhe...

1
Cryogenic Upgrade of the Helium Central Liquefier and Superconducting Cable & Wire Test Facilities at CERN O Pirotte, A Lees, T Barbe, T Dupont, M Pezzetti (CERN, Accelerator Technology Department, Geneva, Switzerland) Introduction Conclusion Rather than purchase a new cryogenic plant to supply the increased LHe requirement in B165 and B163, a new CDS has been designed and procured to maximize and share the production of the liquefiers in the two adjacent buildings. The CDS of B165 was successfully installed and commissioned during 2019, increasing LHe storage capacity to 20,000 l and enabling the gravity filling of 10,000 l trailer dewar. The installation of CDS for B163 is scheduled to finish early in 2020. B165 – Central Liquifier Supply of 100 l to 500 l LHe mobile dewars to 30 clients CERN wide without dedicated cryogenic infrastructure 1998-2006 : average annual LHe volume of 250,000 l After 2007, increase due to LHe requirement of experiments in Antiproton Decelerator (AD). Peak of 400,000 l in 2010 Increase of TCF50 production capacity to 160 l/h (boosted with LN2), but limitation from LHe storage of 5,000 l LHe Demand from B163 clients The historic LHe requirements of the STC and F1 are known. LHe requirement of F2 is scaled from F1 F1 and F2 will share the WPU, so it is not possible to simultaneously test at 1.9 K in both cryostats. However it is envisaged that the external cryostat of one cryostat could be at 4.5 K while testing is undertaken in the other. C2Po2A-06 [20] Central cryogenic infrastructure of the CERN Meyrin site B163 – SC Wire and Cables Test Facilities Sulzer TCF50 boosted with LN2 : 160 l/h (5.2 g/s) Seven small test cryostats (STC) to test SC wires @ 1.9 K 6000 l LHe dewar supplying FRESCA double test cryostat (F1) to test SC cables (NbTi) @ 1.9 K in a field of max 10 T In project: FRESCA2 (F2) to test new generation of SC cables (Nb3Sn) and HTS cables under field of 13 T B253 – Central Purifier 3 kPa GHe recuperation network Two Linde purifiers 120 m 3 /h @ 120-200 bar Impure and pure GHe HP storage @ 160 bar (1,000 l jumbo cylinders and 50 l batteries) Study of historic deliveries (dependence on operational cycle of each client) with future increase of 20% by AD clients Year Delivered Used by client Max. weekly delivery kg l kg l kg l 2015 39,920 318,288 33,672 268,469 1,842 14,687 2016 39,285 313,220 33,971 270,851 1,561 12,446 2017 49,408 393,932 43,235 344,718 1.552 12,370 * Cool down of either F1 or F2 external cryostat excluded Worst case weekly LHe requirement in B163 * Configuration Load Case Total average requirement (l/week) Weekly flow rate (g/s) Average Peak 1 F1+F2+STC 42,700 8.5 17.4 2 F2+STC 33,700 6.7 15.6 3 STC 12,800 2.60 8.2 Analysis undertaken to combine competing requirements: B163 average weekly requirement combined with B165 future delivery schedule Maximum combined LHe production of B165 and B163 is conservatively 10 g/s (49,950 l / wk) Upgrade of B165 and B163 Main Functional modes of the B165 and B163 CDS No. From To Frequency 1 B165 Liquefier B165 LHe Dewar Continuous 2 B165 LHe Dewar Trailer Dewar 2 per week 3 B165 LHe Dewar B165-Filling Station 30 per week 4 B165 LHe Dewar B163 LHe Dewar 1-3 per week 5 Trailer Dewar B165 LHe Dewar Monthly 6 Trailer Dewar B165 Filling Station Possible 7 B163 Liquefier B163 LHe Dewar Continuous 8 B163 LHe Dewar B163 client Continuous 9 B163 LHe Dewar B165 LHe Dewar Rare 20 m³ LHe Dewar B165-CB F2 SVB Fresca 1 Fresca 2 Gazo Gazo F1 SVB = Cryogenic Valve = Limit of supply = He circuit B163-TL2 B163 TL5 B163 TL4 Atm. = Components = N 2 circuit Atm. EH-VLP PL B163 6 m³ LHe Dewar B163-CB B165-CB 10 m³ Trailer Dewar F2 SVB Fresca 1 Fresca 2 Filling station 7 small test cryostats (STC) LP Gazo LP Gazo LP LP Gazo B163-VB GMP Infra. B165 F1 SVB Key: = Warm Valve B165 TL1 B165-TL3 B165-TL2 B163 TL1 40 m³ Litre LN 2 Dewar Atm. B165-N2VB WPU-F = 1.9 K Pumping He circuit B165-VB LP GMP F1 GMP F2 Atm. Atm. GHe 300K = Existing Valve Gazo B163-JB EH-15kW B163 Upgrade PFD Definition of upgrade Global Process Flow Diagram. Calculated flow rates averaged over 7 days for assume B163 max continual operation of STC + F1 + F2. Harness the full production capacity of the two existing TCF50 to meet the future LHe requirements in B165 and B163 : B165 : 20,000 l LHe dewar to maximize LHe production and allow gravity filling of 10,000 l trailer dewar transportable by road to AD clients B163 : connect FRESCA 2, increase LHe supply by enabling the transfert of surplus LHe from B165, connect 6,000 l dewar directly to liquefier and upgrade WPU FRESCA B253 : replace 50 l batteries by 24 x 3 m 3 jumbo cylinders Cool Down Filling Standby at 4K Operation at 4K Pumping to 1.9K Operation at 1.9K Warm Up 1new Small Cryostats F1 Outer Inner F2 Outer Inner 2 3 4 5 6 7 Wednesday Thursday Friday Saturday Sunday B163 LHe Monday Tuesday B163 – Worst-case weekly test schedule During the last three years, the total average weekly demand was 6,836 l with a peak weekly demand of 14,687 l (2.9 g/s). LHe demand from B165 clients Shortage would occur if configuration 1 (F1+F2+STC) is combined with peak delivery periods in B165 from May to December. Therefore, Load case 1 in B163 should only be operate during low demand periods in B165, from January to April. B165 and B163 CDS – Process flow diagram B163 Compressor B163 CB LHe Dewar 6m³ 1 2 5 3 4 6 7 GMP Infra. GMP F1 GMP F2 F1-SVB F2-SVB F2 F1 B163 JB 15 kW B165 B163-VB TL5 TL4 TL3 TL2 LHe Cold GHe at 1.1 bar Warm GHe New CDS (Cryogenic Distribution System) TL1 WPU WPU WPU WPU WPU B253 Purif WPU FRESCA (B165) F1 / F2 VLP heater B253 Purif Cold GHe at 15 mbar Warm GHe at 15 mbar Combined LHe demand from B165 and B163 B163 B165 B253 40 000 l LN 2 Dewar To B253 Filling Station TCF50 Liquifier 20 000 l LHe Dewar LN 2 VB TL3 to B163 Compressor B165 VB LHe trailer B163 WPU He CDS LN2 CDS He gazometer 4 x 80 m3 GHe Buffer LN 2 trailer 40 000 l LN 2 Dewar LN 2 trailer VLP Heater F1-SVB F2 - SVB F1 F2 JB 15 kW Heater B163 - VB STC - TL CB GMPs 6000 l LHe Dewar Jumbo cylinders Gazometers 20 000 l LHe Dewar B163 Requirement: Possible B165 LHe Deliveries: (10,000 l Trailers) Availability = 1.5 g/s (7,250 L/wk) Availability = 3.3 g/s (16,250 L/wk) 6.7 g/s (33,700 L/wk) 8.5 g/s (42,700 L/wk) Max LHe shortage 10,000 L /wk No LHe Shortage 2.6 g/s (12,800 L/wk) Availability = 7.4 g/s (36,500 L/wk) No LHe Shortage Total LHe production = 10 g/s (49,950 L/wk) Configuration 1: F1+F2+STC Configuration 2: F2+STC Configuration 3: STC only

Upload: others

Post on 13-Feb-2021

7 views

Category:

Documents


3 download

TRANSCRIPT

  • Cryogenic Upgrade of the Helium Central Liquefier and SuperconductingCable & Wire Test Facilities at CERN

    O Pirotte, A Lees, T Barbe, T Dupont, M Pezzetti (CERN, Accelerator Technology Department, Geneva, Switzerland)

    Introduction

    ConclusionRather than purchase a new cryogenic plant to supply the increased LHe requirementin B165 and B163, a new CDS has been designed and procured to maximize and sharethe production of the liquefiers in the two adjacent buildings.The CDS of B165 was successfully installed and commissioned during 2019,increasing LHe storage capacity to 20,000 l and enabling the gravity filling of 10,000 ltrailer dewar. The installation of CDS for B163 is scheduled to finish early in 2020.

    B165 – Central Liquifier• Supply of 100 l to 500 l LHe mobile dewars to 30 clients

    CERN wide without dedicated cryogenic infrastructure• 1998-2006 : average annual LHe volume of 250,000 l• After 2007, increase due to LHe requirement of experiments

    in Antiproton Decelerator (AD). Peak of 400,000 l in 2010• Increase of TCF50 production capacity to 160 l/h (boosted

    with LN2), but limitation from LHe storage of 5,000 l

    LHe Demand from B163 clients• The historic LHe requirements of the STC and F1 are known.

    LHe requirement of F2 is scaled from F1• F1 and F2 will share the WPU, so it is not possible to

    simultaneously test at 1.9 K in both cryostats. However it isenvisaged that the external cryostat of one cryostat could be at4.5 K while testing is undertaken in the other.

    C2Po2A-06 [20]

    Central cryogenic infrastructure of the CERN Meyrin site

    B163 – SC Wire and Cables Test Facilities• Sulzer TCF50 boosted with LN2 : 160 l/h (5.2 g/s)• Seven small test cryostats (STC) to test SC wires @ 1.9 K• 6000 l LHe dewar supplying FRESCA double test cryostat

    (F1) to test SC cables (NbTi) @ 1.9 K in a field of max 10 T• In project: FRESCA2 (F2) to test new generation of SC cables

    (Nb3Sn) and HTS cables under field of 13 T

    B253 – Central Purifier• 3 kPa GHe recuperation network• Two Linde purifiers 120 m3/h @ 120-200 bar• Impure and pure GHe HP storage @ 160 bar (1,000 l jumbo

    cylinders and 50 l batteries)

    Study of historic deliveries (dependence on operational cycleof each client) with future increase of 20% by AD clients

    YearDelivered Used by client Max. weekly delivery

    kg l kg l kg l2015 39,920 318,288 33,672 268,469 1,842 14,687

    2016 39,285 313,220 33,971 270,851 1,561 12,446

    2017 49,408 393,932 43,235 344,718 1.552 12,370

    * Cool down of either F1 or F2 external cryostat excluded

    Worst case weekly LHe requirement in B163*

    Configuration Load Case Total average requirement(l/week)Weekly flow rate (g/s)

    Average Peak1 F1+F2+STC 42,700 8.5 17.42 F2+STC 33,700 6.7 15.63 STC 12,800 2.60 8.2

    Analysis undertaken to combine competing requirements:• B163 average weekly requirement combined with B165

    future delivery schedule• Maximum combined LHe production of B165 and B163 is

    conservatively 10 g/s (49,950 l / wk)

    Upgrade of B165 and B163Main Functional modes of the B165 and B163 CDS

    No. From To Frequency1 B165 Liquefier B165 LHe Dewar Continuous2 B165 LHe Dewar Trailer Dewar 2 per week3 B165 LHe Dewar B165-Filling Station 30 per week4 B165 LHe Dewar B163 LHe Dewar 1-3 per week5 Trailer Dewar B165 LHe Dewar Monthly6 Trailer Dewar B165 Filling Station Possible7 B163 Liquefier B163 LHe Dewar Continuous8 B163 LHe Dewar B163 client Continuous9 B163 LHe Dewar B165 LHe Dewar Rare

    6,000 LitreLHe Dewar

    20 m³ LHeDewar

    B165-CB

    F2SVB

    Fresca 1

    Fresca 2

    Gazo

    Gazo

    F1GMP

    F1SVB

    = Cryogenic Valve

    = Limit of supply= He circuit

    B163-TL2

    B163TL5

    B163TL4

    Atm.

    = Components= N2 circuit

    Atm.

    EH-VLPPL

    B163

    6 m³ LHeDewar

    B163-CB

    B165-CB

    10 m³ TrailerDewar

    F2SVB

    Fresca 1

    Fresca 2

    Fillingstation

    7 small test cryostats(STC)

    LPGazo

    LP Gazo

    LP

    LP

    Gazo

    B163-VBGMPInfra.

    B165

    F1SVB

    Key:

    = Warm Valve

    B165TL1

    B165-TL3B165-TL2

    B163TL1

    40 m³Litre LN2Dewar

    Atm.

    B165-N2VB

    WPU-F

    = 1.9 K Pumping He circuit

    B165-VB

    LP

    GMPF1

    GMPF2

    Atm.

    Atm.

    GHe300K

    = Existing Valve

    Gazo

    B163-JB

    EH-15kW

    B163 Upgrade PFD

    Definition of upgrade

    Global Process Flow Diagram. Calculated flow rates averaged over 7 daysfor assume B163 max continual operation of STC + F1 + F2.

    Harness the full production capacity of the two existing TCF50 tomeet the future LHe requirements in B165 and B163 :• B165 : 20,000 l LHe dewar to maximize LHe production and

    allow gravity filling of 10,000 l trailer dewar transportable byroad to AD clients

    • B163 : connect FRESCA 2, increase LHe supply by enablingthe transfert of surplus LHe from B165, connect 6,000 l dewardirectly to liquefier and upgrade WPU FRESCA

    • B253 : replace 50 l batteries by 24 x 3 m3 jumbo cylindersCool Down Filling Standby at 4K Operation at 4K Pumping to 1.9K Operation at 1.9K Warm Up

    1new

    Sm

    all C

    ryos

    tats

    F1Outer

    Inner

    F2Outer

    Inner

    2

    3

    4

    5

    6

    7

    Wednesday Thursday Friday Saturday SundayB163LHe

    Monday Tuesday

    B163 – Worst-case weekly test schedule

    During the last three years, the total average weekly demandwas 6,836 l with a peak weekly demand of 14,687 l (2.9 g/s).

    LHe demand from B165 clients

    Shortage would occur if configuration 1 (F1+F2+STC) iscombined with peak delivery periods in B165 from May toDecember. Therefore, Load case 1 in B163 should only beoperate during low demand periods in B165, from January toApril.

    B165 and B163 CDS – Process flow diagram

    B163 Compressor

    B163CB

    LHe Dewar6m³

    1

    2

    5

    3

    4

    6

    7

    GMPInfra.

    GMPF1

    GMPF2

    F1-SVB

    F2-SVB

    F2F1

    B163JB15 kW

    B165

    B163-VB

    TL5

    TL4

    TL3 TL2

    LHe

    Cold GHe at 1.1 bar

    Warm GHe

    New CDS(CryogenicDistribution System)

    TL1

    WPU

    WPU

    WPU

    WPU

    WPU

    B253Purif

    WPUFRESCA(B165)

    F1 / F2VLP heater

    B253Purif

    Cold GHe at 15 mbar

    Warm GHe at 15 mbar

    Combined LHe demand from B165 and B163

    B163

    B165

    B253

    40 000 lLN2

    Dewar

    To B253

    FillingStation

    TCF50Liquifier

    20 000 lLHe Dewar

    LN2 VB

    TL3 toB163

    Compressor

    B165VB

    LHe trailer

    B163WPU

    He CDSLN2 CDSHe gazometer

    4 x 80 m3GHe Buffer

    LN2 trailer

    40 000 lLN2

    Dewar

    LN2 trailer

    VLP HeaterF1-SVB

    F2 - SVB F1 F2JB15 kW Heater

    B163 - VB

    STC - TL

    CB

    GMPs

    6000 l LHe Dewar

    Jumbo cylinders

    Gazometers

    20 000 l LHe Dewar

    B163 Requirement:

    Possible B165 LHeDeliveries:(10,000 l Trailers)

    Availability = 1.5 g/s(7,250 L/wk)

    Availability = 3.3 g/s(16,250 L/wk)

    6.7 g/s(33,700 L/wk)

    8.5 g/s(42,700 L/wk)

    Max LHe shortage≈ 10,000 L /wk No LHe Shortage

    2.6 g/s(12,800 L/wk)

    Availability = 7.4 g/s(36,500 L/wk)

    No LHe Shortage

    Total LHe production= 10 g/s (49,950 L/wk)

    Configuration 1:F1+F2+STC

    Configuration 2:F2+STC

    Configuration 3:STC only