cryogenic upgrade of the helium central liquefier and ... · • 1998-2006 : average annual lhe...
TRANSCRIPT
-
Cryogenic Upgrade of the Helium Central Liquefier and SuperconductingCable & Wire Test Facilities at CERN
O Pirotte, A Lees, T Barbe, T Dupont, M Pezzetti (CERN, Accelerator Technology Department, Geneva, Switzerland)
Introduction
ConclusionRather than purchase a new cryogenic plant to supply the increased LHe requirementin B165 and B163, a new CDS has been designed and procured to maximize and sharethe production of the liquefiers in the two adjacent buildings.The CDS of B165 was successfully installed and commissioned during 2019,increasing LHe storage capacity to 20,000 l and enabling the gravity filling of 10,000 ltrailer dewar. The installation of CDS for B163 is scheduled to finish early in 2020.
B165 – Central Liquifier• Supply of 100 l to 500 l LHe mobile dewars to 30 clients
CERN wide without dedicated cryogenic infrastructure• 1998-2006 : average annual LHe volume of 250,000 l• After 2007, increase due to LHe requirement of experiments
in Antiproton Decelerator (AD). Peak of 400,000 l in 2010• Increase of TCF50 production capacity to 160 l/h (boosted
with LN2), but limitation from LHe storage of 5,000 l
LHe Demand from B163 clients• The historic LHe requirements of the STC and F1 are known.
LHe requirement of F2 is scaled from F1• F1 and F2 will share the WPU, so it is not possible to
simultaneously test at 1.9 K in both cryostats. However it isenvisaged that the external cryostat of one cryostat could be at4.5 K while testing is undertaken in the other.
C2Po2A-06 [20]
Central cryogenic infrastructure of the CERN Meyrin site
B163 – SC Wire and Cables Test Facilities• Sulzer TCF50 boosted with LN2 : 160 l/h (5.2 g/s)• Seven small test cryostats (STC) to test SC wires @ 1.9 K• 6000 l LHe dewar supplying FRESCA double test cryostat
(F1) to test SC cables (NbTi) @ 1.9 K in a field of max 10 T• In project: FRESCA2 (F2) to test new generation of SC cables
(Nb3Sn) and HTS cables under field of 13 T
B253 – Central Purifier• 3 kPa GHe recuperation network• Two Linde purifiers 120 m3/h @ 120-200 bar• Impure and pure GHe HP storage @ 160 bar (1,000 l jumbo
cylinders and 50 l batteries)
Study of historic deliveries (dependence on operational cycleof each client) with future increase of 20% by AD clients
YearDelivered Used by client Max. weekly delivery
kg l kg l kg l2015 39,920 318,288 33,672 268,469 1,842 14,687
2016 39,285 313,220 33,971 270,851 1,561 12,446
2017 49,408 393,932 43,235 344,718 1.552 12,370
* Cool down of either F1 or F2 external cryostat excluded
Worst case weekly LHe requirement in B163*
Configuration Load Case Total average requirement(l/week)Weekly flow rate (g/s)
Average Peak1 F1+F2+STC 42,700 8.5 17.42 F2+STC 33,700 6.7 15.63 STC 12,800 2.60 8.2
Analysis undertaken to combine competing requirements:• B163 average weekly requirement combined with B165
future delivery schedule• Maximum combined LHe production of B165 and B163 is
conservatively 10 g/s (49,950 l / wk)
Upgrade of B165 and B163Main Functional modes of the B165 and B163 CDS
No. From To Frequency1 B165 Liquefier B165 LHe Dewar Continuous2 B165 LHe Dewar Trailer Dewar 2 per week3 B165 LHe Dewar B165-Filling Station 30 per week4 B165 LHe Dewar B163 LHe Dewar 1-3 per week5 Trailer Dewar B165 LHe Dewar Monthly6 Trailer Dewar B165 Filling Station Possible7 B163 Liquefier B163 LHe Dewar Continuous8 B163 LHe Dewar B163 client Continuous9 B163 LHe Dewar B165 LHe Dewar Rare
6,000 LitreLHe Dewar
20 m³ LHeDewar
B165-CB
F2SVB
Fresca 1
Fresca 2
Gazo
Gazo
F1GMP
F1SVB
= Cryogenic Valve
= Limit of supply= He circuit
B163-TL2
B163TL5
B163TL4
Atm.
= Components= N2 circuit
Atm.
EH-VLPPL
B163
6 m³ LHeDewar
B163-CB
B165-CB
10 m³ TrailerDewar
F2SVB
Fresca 1
Fresca 2
Fillingstation
7 small test cryostats(STC)
LPGazo
LP Gazo
LP
LP
Gazo
B163-VBGMPInfra.
B165
F1SVB
Key:
= Warm Valve
B165TL1
B165-TL3B165-TL2
B163TL1
40 m³Litre LN2Dewar
Atm.
B165-N2VB
WPU-F
= 1.9 K Pumping He circuit
B165-VB
LP
GMPF1
GMPF2
Atm.
Atm.
GHe300K
= Existing Valve
Gazo
B163-JB
EH-15kW
B163 Upgrade PFD
Definition of upgrade
Global Process Flow Diagram. Calculated flow rates averaged over 7 daysfor assume B163 max continual operation of STC + F1 + F2.
Harness the full production capacity of the two existing TCF50 tomeet the future LHe requirements in B165 and B163 :• B165 : 20,000 l LHe dewar to maximize LHe production and
allow gravity filling of 10,000 l trailer dewar transportable byroad to AD clients
• B163 : connect FRESCA 2, increase LHe supply by enablingthe transfert of surplus LHe from B165, connect 6,000 l dewardirectly to liquefier and upgrade WPU FRESCA
• B253 : replace 50 l batteries by 24 x 3 m3 jumbo cylindersCool Down Filling Standby at 4K Operation at 4K Pumping to 1.9K Operation at 1.9K Warm Up
1new
Sm
all C
ryos
tats
F1Outer
Inner
F2Outer
Inner
2
3
4
5
6
7
Wednesday Thursday Friday Saturday SundayB163LHe
Monday Tuesday
B163 – Worst-case weekly test schedule
During the last three years, the total average weekly demandwas 6,836 l with a peak weekly demand of 14,687 l (2.9 g/s).
LHe demand from B165 clients
Shortage would occur if configuration 1 (F1+F2+STC) iscombined with peak delivery periods in B165 from May toDecember. Therefore, Load case 1 in B163 should only beoperate during low demand periods in B165, from January toApril.
B165 and B163 CDS – Process flow diagram
B163 Compressor
B163CB
LHe Dewar6m³
1
2
5
3
4
6
7
GMPInfra.
GMPF1
GMPF2
F1-SVB
F2-SVB
F2F1
B163JB15 kW
B165
B163-VB
TL5
TL4
TL3 TL2
LHe
Cold GHe at 1.1 bar
Warm GHe
New CDS(CryogenicDistribution System)
TL1
WPU
WPU
WPU
WPU
WPU
B253Purif
WPUFRESCA(B165)
F1 / F2VLP heater
B253Purif
Cold GHe at 15 mbar
Warm GHe at 15 mbar
Combined LHe demand from B165 and B163
B163
B165
B253
40 000 lLN2
Dewar
To B253
FillingStation
TCF50Liquifier
20 000 lLHe Dewar
LN2 VB
TL3 toB163
Compressor
B165VB
LHe trailer
B163WPU
He CDSLN2 CDSHe gazometer
4 x 80 m3GHe Buffer
LN2 trailer
40 000 lLN2
Dewar
LN2 trailer
VLP HeaterF1-SVB
F2 - SVB F1 F2JB15 kW Heater
B163 - VB
STC - TL
CB
GMPs
6000 l LHe Dewar
Jumbo cylinders
Gazometers
20 000 l LHe Dewar
B163 Requirement:
Possible B165 LHeDeliveries:(10,000 l Trailers)
Availability = 1.5 g/s(7,250 L/wk)
Availability = 3.3 g/s(16,250 L/wk)
6.7 g/s(33,700 L/wk)
8.5 g/s(42,700 L/wk)
Max LHe shortage≈ 10,000 L /wk No LHe Shortage
2.6 g/s(12,800 L/wk)
Availability = 7.4 g/s(36,500 L/wk)
No LHe Shortage
Total LHe production= 10 g/s (49,950 L/wk)
Configuration 1:F1+F2+STC
Configuration 2:F2+STC
Configuration 3:STC only